Professional Documents
Culture Documents
Define and
structure
project
activities
based on
the
deliverables
agreed to
deliver.
Effective project management requires decisions that focus on both “what” and on
“who.” After making “what” decisions about deliverables and project timelines, the
last step before starting the project is to is to create a linear responsibility chart --
also called a responsibility matrix -- that identifies who is responsible for core
project activities, actions and decisions.
Creating estimation and costing for project is an extremely crucial part of any project management.Various things are
taken in consideration while calculating budget for project like labor costs, necessary equipment acquisition, material
costs, etc.
In corporate budgeting, a top-down approach involves the senior management team developing a
high-level budget for the entire organization. Once these budgets are created, amounts are allocated
to individual departments, and those departments must then take those numbers and build their own
corresponding budgets within the confines of the executive-level-created budget.
Advantages: With top-down budgeting, only the executive team is involved and thus lower management
does not have to take time to prepare the budget. This can represent significant time-savings for those
who are more involved in the day-to-day rather than the overall strategy for the organization.
Disadvantages: With the top-down approach, those creating the budget may not be involved with the
day-to-day and as a result may not be aware of some of the specific expenses required. This may result
in problems for departments looking for resources that just don’t fit into the top-down budget.
Gantt chart is defined as the bar chart. PERT chart is similar to a network diagram
Gantt chart was developed by Henry L. Gantt. PERT chart was developed by the United States navy.
Gantt chart is often used for Small Projects PERT chart can be used for large and complex Projects
3. Create a Network Diagram: A critical path analysis chart, or network diagram, depicts the order of activities.
5. Use the Critical Path Algorithm: The algorithm has two parts; a forward pass and a backwards pass.
6. Forward Pass: Use the network diagram and the duration of each activity to determine their earliest start (ES) and earliest finish (EF). The ES of an activity is equal to the EF of its
predecessor, and its EF is determined by the formula EF = ES + t (t is the activity duration). The EF of the last activity identifies the expected time required to complete the entire
project.
7. Backward Pass: Begins by assigning the last activity’s earliest finish as its latest finish. Then the formula to find the LS is LS = LF – t (t is the activity duration). For the previous
activities, the LF is the smallest of the start times for the activity that immediately follows.
8. Identify the Float of Each Activity: The float is the length of time an activity can be delayed without increasing the total project completion time. Since the critical path has no float,
the float formula reveals the critical path: Float = LS – ES
9. Identify the Critical Path: The activities with 0 float make up the critical path.
10. Revise During Execution: Continue to update the critical path network diagram as you go through the execution phase.
These steps determine what tasks are critical and which can float, meaning they can be delayed without negatively impacting the project by making it longer. Now you have the
information you need to plan the schedule more accurately and have more of a guarantee you’ll meet your project deadline.
You also need to consider other constraints that might change the project schedule. The more you can account for these issues, the more accurate your critical path method will
be. If time is added to the project because of these constraints, that is called a critical path drag, which is how much longer a project will take because of the task and constraint.