You are on page 1of 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/3638724

Benefits of a low frequency, low voltage railway electrification system

Conference Paper · January 1996


DOI: 10.1109/RRCON.1996.507977 · Source: IEEE Xplore

CITATIONS READS
10 3,377

1 author:

Bharat Bhargava
Sunlight Power Consultants
32 PUBLICATIONS   747 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Please check the website - advancedpstinc.com View project

Power System Oscillations, Synchrophasors View project

All content following this page was uploaded by Bharat Bhargava on 29 April 2016.

The user has requested enhancement of the downloaded file.


Benefits of a Low Frequency, Low Voltage Railway Electrification System
Bharat Bhargava
Southern California Edison Company
Rosemead, California 91770

ABSTRACT environmental pressures will continue and will force railway


electrification on the heavily traveled freight routes. In view
The benefits of a low frequency (15-20 HZ) railway of this, this may be an opportune time to select an
electrification system are presented in this paper. The low appropriate railway electrification system which could
frequency railway electrification system has been used in provide superior performance at an economical price.
European countries for almost a century. The railway
electrification load is one of the worst kinds of load to be fed RAILWAY INDUSTRY IN USA AND EUROPE
by an electrical utility. It requires over sized substation
facilities and results in power quality deterioration. With the Railway usage in the U.S. differs greatly from the
modern day power electronics technology available for railway industry in Europe and on other continents. They are
frequency conversion and the high power quality demanded primarily used for freight in the U.S. The freight trains in the
by the utility power customers, the low frequency systems U.S. are much larger and carry a much higher load as
will provide an affordable and desirable railway compared to those in Europe and in other parts of the World.
electrification system. Since the railways are generally used for freight movement
in the U.S., they do not have to move as fast as in other
INTRODUCTION European countries where the railway usage is for personal
travel. The freight trains in the U.S. often carry double
The low frequency electrified railway system has been stacks, which require much higher electrical clearances. The
in operation for over a century in Sweden, Germany and railways are operated by private companies and two or more
other European countries. With the modern day power companies operate in the same general area carrying freight
electronics technology available for frequency conversion, from major ports to the main consumption areas in the
and the high power quality demanded by the utility power country. For local transportation and the commute from
customers, the low frequency system is likely to make the work to home, the desired mode of transportation has been
railway electrification system more affordable and desirable. the automobile. Because of the low cost, faster service and
This paper will detail specifically how low frequency longer distances involved in the United States, air travel has
railway electrification may provide economic and superior been the primary people mover.
performance over the present railway electrification system On the other hand, in Europe and even in most of the
in America. rest of the World, the railways are the primary people
The United States has the highest mileage of railway mover. Railway travel is not only used in the inner cities, but
tracks in the World, but is the least electrified when also for the daily commute to work in the city from the
compared to other industrialized countries. Only one percent outskirts of the city. The railway trains move the people as
of the 244,000 miles of railway track is electrified in the well as the freight. Air travel is used rarely and for longer
U.S. The reasons for the low level of electrification have distances only. European countries provide railway
been the abundance of cheap diesel oil and the high cost of transportation at an affordable price. The train speeds have
railway electrification. However, because of environmental steadily increased to reduce travel time, and TGV trains
constraints, several major U.S. cities are considering railway travelling as fast as 330 MPH are in operation in France.
electrification. In view of these marked differences in public attitude,
railways have flourished steadily in Europe and other major
parts of the World, whereas they have been used to a limited
extent in the United States and mostly for freight
transportation. Amtrak was set up by the U.S. Government
to encourage railway travel.

FUTURE FOR RAILWAY ELECTRIFICATION :

Also, several major cities and their Metropolitan areas are The extensive railway route length in the United States
either building or expanding their Metro rail system and will require large amounts of capital investment for railway
building electrified railway traction systems. These electrification maintenance and operation. Because of the
large amounts of new capital and the low investment return, this system is 60 HZ. This is the most commonly used
there is reluctance to electrify the railways on the part of the railway electrification alternative.
railway companies. Therefore, the electrification has still not There are some exclusive freight trains electrified in the
been done except for heavily traveled routes. Reducing the U.S. as well, particularly the Black Mesa-Lake Powell
cost of railway electrification will generate incentives for the railroad, which carries coal for the Navajo steam plant[2].
railway companies and will help in expediting railway The freight train for the Black Mesa-Lake Powell is a unique
electrification. system built in the wilderness. Considerable economy in the
The U.S. railways are under pressure due to the substations has been achieved by building the line on 50 KV
environment to electrify some routes which are either catenary voltage and using series compensation. The entire
heavily traveled corridors or carry large quantities of freight. railway line, which is about 80 miles long, is fed from a
Since most of the tracks in America are already built and in single substation. Since this railway line is in the wilderness
service, most of the civil work is already in place. and the railway line is for coal haulage, the economy has
Electrification of these routes will require extensive civil been achieved by partially compromising the reliability.
modifications, like lowering the railway tracks or raising the There are some railway electrification systems in the
overhead bridges, etc., which is in itself very expensive. The eastern U.S. operating at low voltage and low frequency.
completed civil engineering work limits the choice of The New Jersey Coastline between Rahway and Matawan-
voltages as the higher voltage operating systems may require Longbranch operates at 12 KV, 25 HZ. The low frequency
extensive civil work modifications and turn out to be more used is 25 HZ. The frequency conversion is done using
expensive. Innovative methods of reducing the operational rotary converters and cyclo-converters[3]. Although this is a
voltages, which will eventually reduce civil work costs, are low frequency system, it appears that the full benefits of the
required. lower frequency have not been exploited by this railway
Railway electrification costs in the U.S. can be reduced electrification.
and railway electrification/utility system performance can be As indicated above, the trains in the U.S. are mostly
improved by suitable selection of the railway electrification used for freight. Passenger traffic is comparatively much
system. Modern day power electronics technology smaller and mostly confined to very heavily traveled routes.
developments such as the high power thyristors and the Gate Some of these heavily traveled routes are San Diego-Los
Turn Off thyristors (GTO) can make it economically Angeles, Washington-New York, and New Haven-
attractive to select systems with frequencies other than the Connecticut, etc. The train travel is usually limited to
utility system frequency. As a result of these developments distances less than 150 to 200 miles. The larger distances
in power electronics, the principle of frequency conversion such as San Francisco-LA, LA-Phoenix or LA-Las Vegas,
is being used extensively not only to improve the operational etc. which are in the range of 250-500 miles are mostly
efficiency of the induction motor application, but will traveled by airplane.
provide superior speed control. The same principles can be
applied to railway electrification system improvements and Railway Electrification Substations:
cost reduction.
The best fit for a U. S. railway electrification system The railway electrification substations in U.S. typically feed
could be to select a low frequency, low voltage system. The 20 miles of route length, 10 miles on each side of the railway
low frequency (like 15 HZ or 20 HZ), of the traction power electrification substation. The railway tracks are generally
system will enable the U.S. to increase the distance between double tracks and each substation feeds about 40 miles of
the system by increasing the distance between two Single Track Mile (STM). Thus the distance between each
successive substations. Also, lowering the frequency would substation is about 20 miles. The distance between each
provide a margin to lower the voltage from the 25 KV substation is usually limited because of the voltage drop in
catenary voltage most commonly used to 15 KV - 16.5 KV, the catenary[4,5]. The railway electrification load is a single
which could enable reducing the clearance requirements thus phase load on the secondary side of the transformer which
reducing the civil modification costs. feeds the catenary. This results in a highly unbalanced load
on the electrical system. The catenary can be serviced from
RAILWAY ELECTRIFICATION SYSTEMS IN USA either a 25 KV or 50 KV voltage catenary to ground. The
auto transformer system is supplied with a voltage level of
Electrification System (Voltage, Frequency): +/- 25 KV when large loads have to be fed as in the case of
northeast corridor electrification[5,6]. The primary side of
The railway electrification system in America has the substation transformer can be connected phase to ground
generally been electrified for commuter rails. There are or between two phases. From the utility standpoint, it is
some widely traveled routes such as the Amtrak northeast desirable to connect the primary of the transformer between
corridor railway between Boston, Massachusetts and New two phases as the railway load is fed from two phases and
Haven, Connecticut which were electrified recently. The the loading on a single phase and unbalanced load is
electrification system is supplied by a single phase auto reduced. A typical layout for a railway substation is shown
transformer +/- 25 KV catenary voltage[1]. The frequency in in Figure 1. The two adjacent substations are thus fed from
two different sets of phases. Substation A in Figure 1 may be substations and thus the cost of railway electrification. The
fed from phases AB, Substation B from BC and Substation methods include going to higher voltage (50 KV), and using
C from phases CA. The catenaries between the substations harmonic filtering and series compensation at the middle of
are separated by Phase Breaks, which is a portion of the the line to reduce the voltage drop further[2]. Other methods
catenary with no power from either substation. used to supply large loads are the auto-transformer feeder
method, etc.[6].

Sub. A Sub. B Sub. C Power Requirements and Other Needs of Railway


Phase A Electrification :
Phase B
Phase C
The freight trains in America are run by four to six
diesel locomotives. With each diesel locomotive providing
power of about 4.0 MW, the total train load can be between
18-24 MW. This load level is considerably higher than the
commuter loads in the U.S. or the freight and commuter
trains in other countries. With up to four trains within the
substation jurisdiction, the substation peak load can be
Figure 1. Power Distribution System for Three Adjacent estimated to be between 60-100 MVA.
Railway Electrification Substations The train load depends on a multitude of factors, such as
the train load, train headway, train speed, load hauled, the
The train relies on its inertia to move through this phase track profile, etc. The railway electrification load is
break distance. When a train travels from Substation A to B generally determined using Train Simulation Programs.
and passes through the phase break, the train load on the The programs can give a reasonably accurate load
system will be switched from Substation phases AB prediction. Generally when a system is designed, it must be
(Substation A) to BC (Substation B) and when it travels designed keeping in mind the future development or the
from Substation B to C the load will be switched from ultimate needs the railway electrification system has to
phases BC (Substation B) to phases CA (Substation C). The serve.
sudden change in the train load or the load on the substation The freight trains with loads above 18 to 24 MW could
as the train moves out of the substation jurisdiction, will require substations at shorter distances or higher voltage or
cause voltage flicker and is usually observable even at a very auto transformer service because of higher loads and power
low percentage change. The perceptibility of this flicker is requirements. The possible alternative arrangement to reduce
dependent on the voltage change and its frequency. If the the catenary voltage drop to maintain the distance separation
change becomes too frequent or large then it will cause is to increase catenary service voltage with an auto
annoyance to the people who may be supplied power from transformer arrangement to +/- 25 KV. This system runs a
this common substation bus. The irritability is dependent on parallel feeder circuit to maintain about 50 KV service
the frequency of occurrence and the percentage of voltage voltage between the positive and the negative feeder circuit
change and is generally analyzed using a voltage flicker but the railway catenary voltage to ground is at 25 KV. This
curve. A frequently traveled route may result in annoyed system is being used in the Boston-New Haven northeast
utility customers and result in more frequent complaints. corridor railway line.
Several studies conducted recently have shown that a 50
Number of Substations and other Major Railway KV phase to ground system for railway electrification could
Electrification Costs: be less expensive, but would require extensive civil work
modifications. The civil work would therefore increase the
The number of substations built to supply a railway cost of overall electrification considerably.
electrification system has a direct impact on the cost of the
railway electrification project. The other factors which will
influence the cost are the size of the substation and the
voltage level required to feed the railway electrification load.
The number of substations could be reduced if a substation Design Basis for the Railway Electrification Loads :
can provide power for greater track length. As indicated
above, this track length served from a substation is usually When designing a railway electrification system, the
limited by the catenary voltage drop. Higher conductor size, system is generally designed to operate with full efficiency
if used, would reduce losses, increase current capacity, but even with the loss of a substation. Thus in Figure 1, the
would not significantly reduce the inductive voltage drop system must be able to withstand the loss of Substation B
and thus not solve the voltage drop problem. without any impact on train efficiency. Substations A and C
Innovative methods as in the case of the Black Mesa- should be able to feed the power when the trains are in the
Lake Powell line have been used to reduce the number of respective area. This basically puts a demand of almost 150
percent of the nominal substation load on each of the negative phase sequence currents which flow into the utility
substations as each substation should be able to withstand generators and result in heating the generator rotors. The
the loss of the adjacent substation. As such, Substation A unbalance limit of a generator is dependent on the I2 T
should be able to carry the load of Substation A and half of withstand capability of the generators. Typically at
Substation B for the loss of Substation B, Substation B unbalanced voltage, the generators have to provide power
should be able to carry Substation B and half of Substation and negative sequence currents which heat the generator
A for the loss of Substation A, and Substation C should be rotors and may result in tripping the generators. For utility
able to carry the load of Substation C and half of Substation customers, unbalanced voltage causes negative phase
B, for the loss of Substation B, etc. These loads thus become sequence currents to flow into the motors and causes the
the basis for the design of the system and for determining the motors to be heated up. This reduces the motors’ capacity
voltage unbalance, harmonics, voltage flicker, etc. and the motors have to be derated[9].
Electrical utilities in the U.S. try to limit the unbalance
POWER QUALITY CONSIDERATIONS FOR to about 2 percent maximum. There is also an inherent
RAILWAY ELECTRIFICATION LOADS: system unbalance present in the utility system because of
other sources. Typically these sources are the single phase
The railway electrification load is one of the worst kinds loads being fed from the distribution system, or the un-
of load for an electrical utility to supply. The only load transposed high voltage transmission lines, etc. Typically an
which gives more challenge to the utility is arc furnace load. electrical utility can see up to 0.5 - 0.8 percent unbalance
The railway electrification load is highly intermittent, inherently present in the system. Electrical utilities make
irregular, low load factor and poor power factor. The railway efforts to balance these single phase loads on the distribution
electrification load creates system voltage and current system, but it is extremely difficult to reduce the unbalance
unbalance, generates harmonics and results in voltage because of the random nature of the load.
flicker. Because of the above characteristics, the railway Allowing for 1 percent ambient unbalance from other
electrification load generally requires oversized substation sources, the voltage unbalance from the railway
facilities. It stresses the electrical utility equipment more and electrification load will have to be limited to 1 percent.
also causes interference with other customer loads and often Some utilities may allow higher ambient voltage unbalance.
complaints from the other utility customers, etc. The railway Also some utilities have reported consumer complaints when
electrification load is fed on single or two phases of the 2 percent imbalance was used [7,9]. While designing
electrical utility system. This load has always been a substations and the electrification system for railway
challenge to utility engineers and results in increased electrification, it is always desirable to measure the ambient
electrification cost to the railways. Some recently electrified voltage unbalance over a period of a couple of days. Also
railroads and the utilities are using extremely tight power the unbalance should be compared with the short circuit duty
quality standards to maintain acceptable power quality to available to actually calculate the load in the MW causing
other customers. They have also installed expensive Static this ambient voltage unbalance.
Load Balancing devices to reduce voltage unbalance and The typical load fed from a railway electrification
flicker problems [8]. Some of the common power quality substation was estimated to be about 60 - 100 MVA. This
characteristics of the loads are discussed below: would allow about four trains within the substation beat.
Assuming that a 100 MVA load has to be fed from two
Voltage Unbalance: phases of a substation in Figure 1, and also assuming that the
ambient unbalance is 1 percent, then the short circuit duty
The most restrictive criteria among voltage unbalance, must be more than 10,000 MVA to limit the voltage drop to
voltage flicker or harmonics is the voltage and current less than 1 percent imbalance.
unbalance. Voltage unbalance in an electrical utility system
is caused by unbalanced load or the un-transposed
transmission system. Railway electrification load is an
unbalanced load as it is fed from one or two phases only.
Voltage unbalance is dependent on the unbalanced load and Voltage Flicker:
the power system source strength or the available short
circuit duty at the substation. The short circuit duty is The voltage flicker caused by the railway electrification
dependent on the transmission system and the number of load is also dependent on the system source strength or the
generators connected in the system. Current unbalance is short circuit duty. If the source has a high short circuit duty
dependent on the load itself. At light load conditions, the (say 10,000 MVA), then a 25 MVA train load moving out of
number of generators is lower and so the short circuit duty is the substation will cause approximately 0.25 percent voltage
lower. The lesser number of generators results in each of change in the voltage. For a single phase load, the short
those generators sharing more unbalance current. Voltage circuit duty for one phase (in this case 3333 MVA) and the
and current imbalance impacts both the utility and its flicker would be 0.75 percent. If the power is fed from two
customers. For the utility, the unbalance results in the primary phases, then the load is divided from two phases and
the flicker will be about half or about 0.375 percent. In order to limit the unbalance to 1 percent and allowing
Although unbalance is hard to uncover, the flicker is readily for the ambient unbalance of 1 percent, the minimum short
perceivable and can be detected easily by the customers. circuit duty required to meet a 60 to 100 MVA unbalanced
load would be 6,000 to 10,000 MVA. This type of short
Harmonics from Railway Electrification Load: circuit duty is only feasible on 230 KV substations with a
strong network. Also, this short circuit duty would be
Most railway locomotives used today are thyristor required to limit the voltage flicker to 1 percent or below.
controlled power electronics based. This type of load Although the higher flicker levels can be tolerated, a high
generates high levels of harmonics. Harmonic currents from train frequency could result in customer complaints.
modern day locomotives have been shown to be as high as
25 percent. The voltage THD is as high as 6 percent.[6] The Substation Capacity and Primary Voltage:
harmonics can, however, be controlled by appropriate
filtering whether on board or at the substation. The The primary side substation voltage is a major concern.
allowable harmonic levels generally depend on the utility Basically this will establish the voltage level from which the
but IEEE-519[10] defines some guidelines. The standard just railway electrification load will be fed by the utility and will
gives a guideline and each utility must establish its own have a major impact on the project cost. Both the substation
standards. The allowable harmonics are dependent on cost and the transmission costs will increase with substation
system characteristics. Systems with extensive shunt capacity and the voltage level. A power level of 120 MVA
capacitors have to be specially analyzed to avoid resonances can easily be fed by a 69 KV or a 115 KV substation. The
with the utility or the customers capacitor installations. The typical three phase short circuit duties on a 69 KV or a 115
French and English grid operators have specified much KV substation range from 1500 MVA to 5000 MVA. Thus
lower harmonic limits for the Channel Tunnel[8]. the single phase load that could be fed from these
Although the levels given in IEEE-519 may not be a substations would be 15 MVA to 50 MVA only. Higher
major problem, the harmonics could interfere with design basis loads require that the short circuit duty of the
sophisticated control systems and other loads. The voltage system be enough so that the voltage flicker, unbalance and
harmonics are also dependent on the short circuit duty at the harmonics standards are satisfied. These are dependent on
substation. the system strength at the substation. The only solution is to
push for a higher voltage system.
Power Factor: A 230 KV or higher voltage substation would be
The railway traction load power factor can range required to serve single phase loads with more than 60 MVA
between 0.5 to 0.8. Although power factor correction is power. Most of the substations built in France to supply
possible, the rapidly changing railway load and the power power to TGV high speed trains which feed power to
factor still present a challenge for power factor correction. substations with 40-60 MVA capacity are built with primary
Power factor cannot be corrected as rapidly as the load is voltages of 275 KV or 400 KV. A 230 KV voltage
changing and thus rapidly changing power factor and the substation if built to provide 60-100 MVA power will be
load will still result in fast changes in vars from the system under utilized and costly. In the U.S., these substation
and thus result in some flicker or voltage changes. voltages are typically used to provide 500-800 MVA power.

Load Factor: Power Quality Problem Solutions in European


Countries:
The railway electrification load factor is dependent on
the train frequency and usage. The typical load factor for a Because of the above power quality and system
substation is about 15-25 percent depending on the train problems, some European countries have totally isolated the
frequency. Compared to the other utility loads, this is a poor railway electrification systems from other industrial and
load factor and the energy sales are much lower compared to residential loads. This of course increases their investment in
the peak load demand. This type of load thus results in power generation and transmission but eliminates other
excessively high investment costs for the utility. problems and enables them to design the electrification
system best suited for railway electrification. To solve the
SUBSTATION SHORT CIRCUIT DUTY, PRIMARY problems mentioned above they have designed single phase
VOLTAGE AND CAPACITY REQUIREMENTS: railway electrification systems which provide several
benefits in the utilization of the catenary system, keep the
Short Circuit Duty Requirements: power quality to the other customers clean, and eliminate the
current unbalance problems, etc. The railways in Germany
The voltage unbalance, flicker and harmonics are all generate their own power, transmit and transform it.
dependent on the short circuit duty level at the substation. A Generating electricity and transforming it at low frequency
high duty substation has more capability and can feed higher increases the size of the generating and transforming
unbalanced load and harmonics, or will have lower flicker. equipment and results in more expensive equipment. In
contrast, Sweden purchases power from the electric grid, 2. Parallel operation of catenaries from adjacent
transforms it and then converts it into a lower frequency. substation:
France and some other countries have gone to higher
substation primary voltages and very restrictive power The catenaries of the traction system can be all in phase.
quality standards to feed the power system from the utility They can be paralleled on the secondary side. Paralleling the
grid[11]. Going to higher voltage levels obviously is an secondaries will enable the power to be drawn from two or
expensive alternative. more substations, thus decreasing the voltage drop further in
the catenary and also distributing the load on two or more
LOW FREQUENCY, LOW VOLTAGE SYSTEM FOR substations. There will be a smoother transition of load from
RAILWAY ELECTRIFICATION: one substation to the other as the train moves along.
Paralleling the catenaries could further help in increasing the
Frequency conversion is not only possible, but is distance between substations and reduce power losses in the
becoming an economically attractive alternative. The catenaries. This would also improve the effective utilization
frequency conversion is being used for accurate speed of the substations and reduce the peak load thereby
control and energy and power savings in several industrial increasing the substation load factor, and reducing substation
processes. The cost of power frequency conversion is size. With modern power electronics and an advanced ASD
dropping and the reliability is constantly improving. Modern control system, the voltage at a substation can be controlled
day control systems are making the conversion very precise for optimum loading on the substation. This will also
and efficient. Frequency conversion systems can be applied improve the utilization of the catenary system.
to the railway electrification systems to obtain the
advantages of industrial frequency for power generation and 3. Reduced voltage operation at 15-16.5 KV:
the low frequency system for power distribution on the
catenary. The 60 HZ frequency can be converted to 15 or 20 Since the substation beat can be increased because of a
HZ for railway electrification. When converting the lower frequency and parallel operation of the catenary
frequency, the low frequency system can be operated as a system, lower catenary voltage could be used and substantial
single phase system. The frequency conversion can be done savings are achieved in civil engineering modifications by
using a cyclo-converter, or it can be done using an reducing the electrical clearance requirements at the reduced
AC/DC/AC system conversion. The AC/DC/AC conversion voltage level. The lower voltages have been used in
is used extensively in Adjustable Speed Drives(ASD). This Germany and Sweden with success. Reducing the voltage
would solve multitudes of problems related to power quality, level; however, would increase the current in the catenary
reduce the cost of electrification, etc. and would increase losses which may require a higher size
A low frequency system decreases the cost of catenary conductor or an additional feeder circuit.
electrification by increasing the distance between two
successive substations, and reducing civil engineering 4. Lesser electrical clearances and civil engineering
modification costs by enabling lowering the catenary voltage requirements:
from the 25 KV voltage commonly used in the U.S. to 16.5
KV at 15/20 HZ. Such a system would enable paralleling the Lower voltages will result in lower clearance
catenaries between two substations on the secondary side, requirements. This could be useful where bridges have to be
thus increasing the capabilities of the catenaries and raised, tracks have to be lowered or when the tunnels do not
reducing the power quality and unbalance voltage problems. permit adequate clearances for the 25 KV system. In a recent
The various advantages that can be derived from low study conducted by the Los Angeles County Transportation
frequency operation are: Commission, a 25 KV railway electrification system was
being selected even though the electrification costs were
BENEFITS OF A LOW FREQUENCY, LOW lower for a 50 KV system primarily because of the higher
VOLTAGE ALTERNATIVE: electrical clearances required at 50 KV.

1. Longer substation beat/less substation installations: 5. Reduced substation voltage capacity or better
utilization of substation and catenary capacity:
A lower frequency system will reduce the inductive
voltage drop in the catenary. A 15 HZ system would have With the 25 KV single-phase, 60 HZ system, each
approximately one fourth the inductive voltage drop as substation has to be designed to provide full power for the
compared to a 60 HZ system, thus it would enable the trains within the substation beat and half the adjacent
substations to be located at 3 to 4 times the distance substation. By paralleling the traction system on the
compared to a 60 HZ system based just on the voltage drop secondary side and sharing the loads among the adjacent
criterion. The number of substations required could be substations, it is quite possible to reduce the substation
reduced to 30-40 percent. capacity or to provide larger train frequency.
6. Reduced unbalance voltage problem:
Lower traction frequency at the locomotive will require
The traction load, as explained earlier, is one of the a bigger transformer and motors in the electric locomotive.
worst kinds of load as it is often supplied from one or two These low frequency locomotives have, however, been used
phases of a power system. The single phase load creates extensively in Germany, Sweden and some other countries.
voltage unbalance and other power quality problems. Very The lower frequency at the locomotive will increase the size
often the substation voltage level selection is based on or is and the weight of the locomotive slightly. The cost would
dictated by the acceptable unbalanced voltage levels which also increase slightly. Higher weight of the electric
have to be supplied by the utility. Because of large traction locomotive would improve the traction.
loads (60 - 100 MVA), the US utility grid would have to
supply the power from a short circuit duty source of about CONCLUSIONS
10,000 MVA. This short circuit duty source is only available
at 230 KV substations or above. The unbalanced load also What America needs is an optimized system which will
generates negative sequence currents and the substation will enable electrification at the lowest overall cost including the
have to be separated adequately from the generators. A railway electrification costs, the electrical utility costs and
balanced load would have to be supplied by a high voltage the associated civil engineering costs. The electrical utility
system so that the traction load is separated from the other costs can become significant to meet the power quality
customers or the generators. requirements and needs to be included when considering the
With a low frequency traction system, the load will overall cost of railway electrification. This will reduce the
appear as a balanced load on the utility system. There would overall investment required by the railway industry.
be little unbalanced voltage or current problems. The Learning from experience with low frequency, low voltage
frequency conversion system would also separate traction electrification systems such as those utilized in Sweden
load from the rest of the customers. could enable the US to select an optimum, cost effective
railway electrification system.
7. Reduced harmonics into the system:
NOTE
With the low frequency system, harmonics would be This paper represents the views of its author and
generated in the conversion equipment. Appropriate filtering does not necessarily represent the views of Southern
can be provided along with the conversion equipment to California Edison Co. or its parent organization SCE Corp.
limit the harmonics to acceptable levels. The modern day
electric locomotives have onboard power factor correction REFERENCES
and harmonic filtering. The frequency conversion equipment
filters on the system would further reduce the harmonics [1] Ali F. Imece, Hubert Potard and John P. Daniel,
generated from the locomotives and reduce the harmonics “Electromagnetic Impact of Railway Electrification”
entering into the utility system. presented at the 1994 Mass Transit Conference held in
Dallas, Texas, in October, 1994.
8. Lower voltage utility substations:
[2] J. J. Burke, A. P. Engle, S. R. Gilligan and N. A.
The unbalance voltage caused by the trains can become Mincer,“Increasing the Power System Capability of the 50
the single most important factor which will dictate the KV Black Mesa and Lake Powell Railroad through
selection of the substation primary voltage. Adequate short Harmonic Filtering and Series Compensation”, IEEE paper
circuit duty and voltage levels are required to limit the No. F79284, presented at the IEEE Winter Power Meeting,
voltage unbalance and the harmonics at the substation. New York, February 4-9, 1979.
Additional substations had to be installed by British Rail to
reduce the voltage unbalance in their Eastern Corridor [3] Tristan Kneshke, “Power Supply Systems for
Railway line. British Rail has developed extremely Electrification of the New Jersey Coast Line,” IEEE Paper
conservative power quality (unbalance, harmonics) No. CH2617-5/85/0000-0029 in IEEE Publication No.
standards for the Channel electrification which would 85CH2167-5 presented at the Joint IEEE/ASME Railroad
require high voltage substations. SNIFF builds 275 or 400 Conference in New York, New York, in April 1985.
KV substations to provide the power for TGV (Ref. 11).
Since a low frequency, low voltage system would eliminate [4] Tristan Kneshke,“ Simple Method for Determination of
or reduce the power quality problems, a 40 to 60 MW load Substation Spacings for AC and DC Electrification
could easily be served by a 69 KV or a 115 KV substation. Systems”, IEEE Paper No. CH2207-9/85/0000-0274 in
SCE’s typical 69 KV or 115 KV substations are designed to IEEE Publication No. 85CH2207-9 presented at the
serve up to 112 MW loads. Industrial Application Society annual meeting held in
Toronto, Canada, in October, 1985.
9. Locomotive transformer and AC motor size:
[5] Tristan Kneshke, “Substation Spacing for AC California. He is actively involved in transient analysis and
Electrified Railroads - Some Influencing Factors,” IEEE power system studies such as SSR, System Dynamics,
Paper No. 82-RT-4 in IEEE Publication No. 82-CH1778-0 Power System Stabilizers, Power Quality, Railway
presented at the Joint IEEE/ASME Railroad Conference in Electrification, capacitor switching studies, etc. Mr.
Erie, Pennsylvania, in April 1982. Bhargava has been involved in several research projects
such as the NGH SSR protective device, and recently in the
[6] P Stecuik, J. J.Burke, “The Impact of Railroad procurement, installation and testing of an Energy Source
Electrification on Utility System Power Quality”, presented Power System Stabilizer for a 10 MW/40 MWH Battery
at the 1994 Mass Transit Conference held in Dallas , Texas Energy Storage System at Chino Substation. Mr. Bhargava
in October, 1994. was a member of the team from SCE that visited four
European countries in December 1991 to study the various
[7] Tristan Kneshke, “Control of Utility System Unbalance railway electrification systems in Europe. This paper is
Caused by Single Phase Electric Traction”, IEEE Paper No. based on that visit.
CH2060-2/84/0000-0259 in IEEE Publication No. Mr. Bhargava graduated from Delhi University in 1961
85CH2060-2 presented at the Industrial Application Society with a Masters from Rensselear Polytechnic Institute in
annual meeting held at Chicago, Illinois in October, 1984. 1976. He worked with UP State Electricity Board in India
[8] R. Bedrune , F. Gallon, A. Maher, J. S. Finn and J. M. from 1961 to 1975. Mr. Bhargava is a Senior Member of
Lucas, “Load Balances for the Channel Tunnel”, CIGRE IEEE PAS, IAS and Vehicular Societies, and a Member of
1992, Paper No. 36-207. CIGRE.
[9] ANSI C84.1 -1989, Appendix D, Polyphase Voltage
Unbalance

[10] IEEE Standard 519-1992, “IEEE Recommended


Practices and Requirements for Harmonic Control in
Electrical Power Systems.”

[11] Bharat Bhargava, “What America Can Learn from


Railway Electrification Systems in Europe,” presented at the
1994 Mass Transit Conference at Dallas, Texas, October,
1994.

Bharat Bhargava

Mr. Bharat Bhargava is a Senior Engineer in the


Transmission / Substation Engineering Reliability Group of
the Southern California Edison Company in Rosemead,

View publication stats

You might also like