PRAM 2004
Initial Assessment (PID)
THREAT OPPORTUNITY
Very High Very High
PROBABILITY
PROBABILITY
High High
Medium Medium
Low Low
Very Low Low Medium High Very High Very High High Medium Low Very Low
IMPACT BENEFIT
Threats Opportunities
Avoid Terminate
Exploit
Transfer Transfer
Share
Mitigate Treat
Enhance
Accept Tolerate
Reject
Plan Fallback/Option
Plan of what to do if the risk occurs
Trigger Point
THREAT OPPORTUNITY
Very High Very High
PROBABILITY
PROBABILITY
High High
Medium Medium
Avoid/Exploit Low
Very Low
Very Low Low Medium High Very High Very High High Medium Low Very Low
Low
Very Low
IMPACT BENEFIT
PROBABILITY
PROBABILITY
High High
Medium Medium
Low Low
IMPACT
High Very High Very High High Medium
BENEFIT
Low Very Low
Very Low
PROBABILITY
PROBABILITY
High High
Medium Medium
Low Low
Very Low Low Medium High Very High Very High High Medium Low Very Low
IMPACT BENEFIT
PROBABILITY
PROBABILITY
High High
Accept/Reject
Medium Medium
Low Low
Very Low Low Medium High Very High Very High High Medium Low Very Low
Threats
– Active Decision
Other Treatments not viable
Monitor
• Technical/Financial
Plan Fallback
• Prob =VH, Impact =VL (Add to baseline - Raise Opportunity)
Level of Threat Acceptable (Prob =L, Impact =Low)
Opportunity
Other Treatments not viable (Financial)
Not in line with Company’s Strategic Direction
Questions
Avoid Change project scope Exploit
Proactive Responses
Plan Plan
Insure Invest
fallback option
Reduce Enhance
Share Share
negative positive
contractually contractually
impact impact
PRAM 2004