Professional Documents
Culture Documents
net/publication/323705337
CITATIONS READS
0 2,009
1 author:
Tim Sandle
The University of Manchester
689 PUBLICATIONS 1,153 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Tim Sandle on 12 March 2018.
ABSTRACT: This article considers some of the risk considerations that need to be accounted for
when replacing a steam sterilization autoclave within a pharmaceutical processing facility. In outlining the
key risk considerations, the article adopts a risk assessment approach – Failure Modes and Effects Analysis
(FMEA).
KEYWORDS:
Risk assessment, risk control, risk review, risk communication, failure modes, effects analysis, steam
sterilization, engineering systems,cross comparison, risk management, autoclaving, autoclave.
CLASSIFICATION OF RISK
Impact Likelihood
Low Medium High
Low LOW LOW MEDIUM
Medium LOW MEDIUM HIGH
High MEDIUM HIGH HIGH
Record the risk priority based upon the risk classification and probability of detection from the table.
RISK PRIORITY
Probability Of Detection
Risk Classification
High Medium Low
Low LOW LOW MEDIUM
Medium LOW MEDIUM HIGH
High MEDIUM HIGH HIGH
Risk process
The risk assessment process is outlined in
In formulating the risk assessment a group Appendix I. In terms of an example:
was assembled consisting of engineering,
validation, microbiology and the end-users. Equipment preparation
The process began by identifying the key risk
factors and potential failure modes. These With equipment loading, an important sub-
were described as “functional details.” Once functional detail is with equipment loading. The
these were defined, these primary categories relevance of loading an autoclave incorrectly is
were broken down into sub-steps (termed an impact on product quality. Here the risk
“sub-functional details.” scenario is an incorrect sterilization of the load.
In this case:
Once these were selected and agreed, the a) The severity of impact would be high;
steps were grouped together. The group then b) The likelihood of impact could be
proceeded to assess the risk for each step, medium.
using the FMEA schema outlined above. This
consisted of: This produces, according to Table 1, a high
risk class.
a) Considering the relevance of each
sub-functional detail (for example, The probability of detection would be low,
whether it could potentially impact because the activity is operator dependent and
upon product quality). there are no system aspects that prevent an
b) The possible risk scenarios were incorrect load from being prepared. Therefore,
considered. using Table 2, the risk priority is high.
c) The severity of impact was then
assessed as either “high”, “medium” or However, in terms of risk mitigation and risk
“low”, using the definitions outlined management, a clear SOP can be put in place
above. and operators can be trained in order to lower
d) The likelihood of impact was then the possibility of an incorrect load being
assessed, using the same descriptors. prepared. In addition:
e) With the severity and likelihood
assessed, the risk class was • Photos of the loads can be prepared
determined using Table 1 (above). (during the Operational Qualification).
f) The probability of detection was • Schematics to be included in the SOP.
assessed next. • Worst-case loads can be verified
g) Knowing the probability of detection during both the Operational
allowed the overall risk priority to be Qualification and Performance
determined (using Table 2 above). Qualification.
h) The penultimate step was to consider
whether any controls or risk mitigation This example is included in Appendix I. Other
factors were in place. sub-functional steps were derived using similar
i) The final step was to reach a processes.
conclusion in relation to risk
management.
Photos of the
loads (OQ).
Schematics to
Step 1 Equipment Loading pattern be included in
Product Quality High Medium High Low High None
Equipment Loading incorrect the SOP.
Preparation Temperature
Mapping Of
The Loads.
BI - Biological Indicator
IQ - Installation Qualification
O&M - Operation and Maintenance
OQ - Operational Qualification
PQ - Performance Qualification
PC - Personal Computer
SOP - Standard Operating Procedure
SAT - Site Acceptance Test
UPS - Uninterruptable Power Supply