You are on page 1of 2

The consultant team will specify the client's requirements early in December 2021 and

release a tender to the consulting firms and architectural firm's contractors. As a result, in order
to price the project based on the architect's drawing, the selected contractor must have a
conceptual design. The contractor can begin preparing the project's precise design once the
customer has chosen and approved the contractor. As a result, construction might start as early
as January 2022. The project probably will be finished in last week of October 2022.

Acivity ID Task Name Duration Start Finish


1 Pre-Construction Stage 14 days Dec 15, 2021 Jan 4, 2022
1.1 Appoint design consultant team 2 days Dec 15, 2021 Dec 16, 2021
1.2 Appoint D & B Contractor 3 days Dec 18, 2021 Dec 20, 2021
1.3 Detailed Design 7 days Dec 22, 2021 Dec 31, 2021
1.4 Obtain building permits 2 days Jan 3, 2022 Jan 4, 2022
         
2 Construction Stage 283 days Jan 6, 2022 Oct 22,2022
2.1 Site Preparation 13 days Jan 6, 2022 Jan 21, 2022
2.1.1 Soil investigation 2 days Jan 6, 2022 Jan 7, 2022
2.1.2 Site Clearing 2 days Jan 9, 2022 Jan 10, 2022
2.1.3 Install temporary power 1 day Jan 12, 2022 Jan 12, 2022
2.1.4 Install temporary water service 1 day Jan 13, 2022 Jan 13, 2022
2.1.5 Set up site office 2 days Jan 15, 2022 Jan 16, 2022
2.1.6 Temporary Fencing 2 days Jan 17, 2022 Jan 18, 2022
2.1.7 Mobilize on site 3 days Jan 19, 2022 Jan 21, 2022
         
2.2 Substructure      
2.2.1 Earthworks 14 days Jan 22, 2022 Feb 5, 2022
2.2.1.1 Excavation 14 days Jan 22, 2022 Feb 5, 2022
2.2.1 Foundation 20 days Feb 7, 2022 Feb 26, 2022
2.2.2.1 Piling 20 days Feb 7, 2022 Feb 26, 2022
2.3 Superstructure      
2.3.1 Frame and Upper Floor 42 days Feb 28, 2022 Apr 10, 2022
2.3.1.1 Columns 22 days Feb 28, 2022 Mar 21, 2022
2.3.1.2 Beams 20 days Mar 22, 2022 Apr 10, 2022
         
2.3.2 Upper Floor 15 days Apr 11, 2022 Apr 25, 2022
2.3.2.1 Floor slab 15 days Apr 11, 2022 Apr 25, 2022
         
2.3.3 Staircase 10 days Apr 26, 2022 May 5, 2022
2.3.3.1 Staircase structure 10 days Apr 26, 2022 May 5, 2022
         
2.3.4 Roof 14 days May 6, 2022 May 20, 2022
2.3.4.1 Roof structures 9 days May 6, 2022 May 14, 2022
2.3.4.2 Roof covering 6 days May 15, 2022 May 20, 2022
         
2.3.5 Doors and Windows 10 days May 21, 2022 May 29, 2022
2.3.5.1 Door & window frame 6 days May 21, 2022 May 25, 2022
2.3.5.2 Door and window leaves 4 days May 26, 2022 May 29, 2022
         
2.3.6 External And Internal Wall 14 days May 31, 2022 Jun 13, 2022
2.3.6.1 Masonry 7 days May 31, 2022 Jun 6, 2022
2.3.6.2 Partitions 7 days Jun 7, 2022 Jun 13, 2022
         
2.3.7 Finishes 35 days Jun 15, 2022 Jul 19, 2022
2.3.7.1 Internal wall finishes 4 days Jun 15, 2022 Jun 18, 2022
2.3.7.2 External wall finishes 4 days Jun 19, 2022 Jun 22, 2022
2.3.7.3 Floor finishes `12 days Jun 23, 2022 Jul 4, 2022
2.3.7.4 Ceiling Finishes 10 days Jul 5, 2022 Jul 14, 2022
2.3.7.5 Staircase finishes 5 days Jul 15, 2022 Jul 19, 2022
         
2.3.8 Furnishings and Fittings 31 days Jul 20, 2022 Aug 19, 2022
2.3.8.1 Furniture 8 days Jul 20, 2022 Jul 27, 2022
2.3.8.2 Equipment 12 days Jul 28, 2022 Aug 8, 2022
2.3.8.3 Sanitary wares 11 days Aug 9, 2022 Aug 19, 2022
         
2.4 Services 25 days Aug 20, 2022 Sept 13, 2022
2.4.1 Plumbing installation 8 days Aug 20, 2022 Aut 27, 2022
2.4.2 Electrical installation 4 days Aug 28, 2022 Aug 31, 2022
2.4.3 Air-conditioning & ventilating installation 5 days Sept 1, 2022 Sept 5, 2022
2.4.4 Fire protection installation 8 days Sept 6, 2022 Sept 13, 2022
         
         
2.5 Infrastructure Works 40 days Sept 14, 2022 Oct 22, 2022
2.5.1 Sewerage works 5 days Sept 14, 2022 Sept 18, 2022
2.5.2 Surface water drainage 10 days Sept 18, 2022 Sept 27, 2022
2.5.3 Road works 10 days Sept 28, 2022 Oct 7, 2022
2.5.4 Walkway 7 days Oct 8, 2022 Oct 14, 2022
2.5.5 Fencing 3 days Oct 15, 2022 Oct 17, 2022
2.5.6 Landscaping 5 days Oct 18, 2022 Oct 22, 2022
         
3 Completion Stage 9 days Oct 23, 2022 Oct 31, 2022
3.1 Complete Final Inspections 3 days Oct 23, 2022 Oct 25, 2022
3.2 Demobilization 3 days Oct 26, 2022 Oct 28, 2022
3.3 Cleaning and Clearing 3 days Oct 29, 2022 Oct 31, 2022

You might also like