TECHNICAL REPORT ED017
DESIGN AND INSTALLATION OF
LIGHT STEEL EXTERNAL WALL SYSTEMS
Apart from any fair dealing for the purposes of Enquiries concerning reproduction outside the
research or private study or criticism or review, as terms stated here should be sent to SCI or FIS,
permitted under the Copyright Designs and Patents at the addresses given on the back page.
Act, 1988, this document may not be reproduced, Although care has been taken to ensure, to the best of
stored or transmitted, in any form or by any means, our knowledge, that all data and information contained
without the prior permission in writing of the publishers, herein are accurate to the extent that they relate to either
or in the case of reprographic reproduction only in matters of fact or accepted practice or matters of opinion
accordance with the terms of the licences issued by at the time of publication, SCI or FIS, the authors and
the UK Copyright Licensing Agency, or in accordance the reviewers assume no responsibility for any errors in
with the terms of licences issued by the appropriate or misinterpretations of such data and/or information or
Reproduction Rights Organisation outside the UK. any loss or damage arising from or related to their use.
2
CONTENTS
6 Installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
6.1 Site preparation. . . . . . . . . . . . . . . . . . . . . . . . . . . 20
6.2 Basic installation principles. . . . . . . . . . . . . . 20
3
“Light steel external wall
systems are used
extensively on a range
of building types and
are an economic and
efficient method of
providing façade walls,
for steel and concrete
framed buildings.”
4
FOREWORD
Light steel external wall systems are used extensively on a The Light Steel and Modular Framing Group now
range of building types and are an economic and efficient operates as the Light Steel Forum, an industry sector
method of providing façade walls, for steel and concrete group managed by the SCI. The group was set up
framed buildings. There are three generic types of light steel in 1993 to develop and promote the use of light
external wall system: infill; continuous; and panelised. Light steel construction through a wide range of technical
steel external walling is capable of resisting wind loads and and educational activities. The Light Steel Forum is
supporting a range of cladding types. This report has been supported by leading manufacturers in the light steel
prepared to provide guidance on the design and installation sector and is assisted by participation of plasterboard
of light steel external wall systems. manufacturers and specialist consultants involved
This revised guidance was carried out in conjunction with in the technology. www.lightsteelforum.co.uk
Steel Construction Institute (SCI) and Finishes and Interiors FIS SFS Special Interest Forum was formed by
Sector Limited (FIS) SFS Special Interest Forum. manufacturers, engineers, suppliers and contractors
The original report was prepared by Andrew Way and involved in the design, supply and construction
Mark Lawson, both of SCI, with the support and guidance of light gauge steel structures and façades, also
of the Light Steel and Modular Framing Group. It responds known as steel framed systems (SFS).
to the need to complement the general guidance on the Bringing industry together allows us to recognise the
design of light steel sections provided in Structural Design common issues around skills, education and understanding
to BS 5950-5: 1998, Section Properties and Load Tables within the specification sector. By highlighting these
(P276) 1 and Design of Light Steel Sections to Eurocode issues the industry who are best-placed to advise
3 (ED005) 2 by giving guidance on their application in on all these points can, with the help of FIS, pursue
external walling systems. a programme of engagement and education.
1 2 https://portal.steel-sci.com/documents.html 5
SUMMARY
This technical report provides guidance on the design and Detailed structural design guidance for light
installation of light steel external wall systems. Guidance on all steel sections is not provided in this report.
aspects of light steel external wall systems is provided, including: Guidance on the detailed structural design
• Choice of steel sections of light steel sections is given separately in
• Structural design issues Structural Design to BS 5950-5: 1998, Section
• Setting-out, tolerances and provision for movement Properties and Load Tables (P276) 1 and
• Fixing types and their spacing Design of Light Steel Sections to Eurocode 3
• Installation (ED005) 2 .
• Health and safety
• Secondary steelwork
• Special design cases
• Checklists for designers and installers.
6 1 2 https://portal.steel-sci.com/documents.html
1 INTRODUCTION
1.1 Background 1.2 Scope
Light steel external walling is used The guidance in this report covers the
extensively on a range of building types following aspects:
and is an economic and efficient method • Design of members in light steel external wall
of providing an external wall system, for systems
steel and concrete-framed buildings, that • Detailing of openings for doors and windows
is capable of resisting wind loads and • Installation of light steel external walls in
supporting a range of cladding types. framed buildings
The need for this report was originally • Interfaces, including to cladding and the
established during discussions at meetings supporting structure
of the Light Steel Forum. The group • Interaction with other trades eg drylining,
identified the need for practical guidance services, brickwork, external cladding
on light steel external walling that was systems, etc
aimed at: • Health and safety during installation.
• Assisting specifiers to understand the design
and installation requirements Three generic types of light steel external
• Ensuring best practice is adopted in design wall systems are covered:
and installation • Infill walls (so called stick-built, on-site)
• Providing guidance on detailing • Continuous walls (stick-built, on-site)
• Special design cases such as long windows • Panelised systems (prefabricated, often with
and parapet walls. sheathing attached).
It was recognised that it was in the
interest of the sector to produce an Variants of standard walls considered are:
industry accepted document that would • Curved walls
help to inform all concerned in this rapidly • Ribbon windows
developing steel technology. • Parapets and downstands
The report is intended to educate • Braced walls (in the same line as the infill
specifiers and contractors who may not walling)
be familiar with light steel external wall • Inclined walls and soffits
technology and the aspects of design • Balconies and patio walls.
and installation that are considered to be
recommended practice. Cladding systems are covered, in so far as
The target audience of the report is they affect the design of the light steel
identified as: walls. The following common types of
• Main contractors cladding are covered:
• Architects • Ground supported brickwork, and brickwork
• Structural engineers supported at each floor
• Installers • Insulated render (generally attached to
• Manufacturers. sheathing boards)
• Rainscreen cladding systems (eg tiles, boards,
metallic sheets, generally using sheathing
boards attached to the light steel external
wall system)
• Granite tiles and other high load systems
• Brick slips.
7
1.3 External wall systems Infill walls
The panels for infill walls are generally
In multistorey framed construction, it is constructed from individual elements, which
common practice to use light steel external are cut to length and installed on site (so
wall systems to create a ‘rapid dry envelope’ called stick-built). The panels fit between the
supporting the external cladding. The use elements of the primary structural frame,
of light steel external wall systems may be as shown in figure 1.1. The panels consist of
applied to any type of framed construction in a bottom track attached to the floor and a
steel or concrete. It is lightweight and provides head track attached to the underside of the
speed and ease of installation as important floor above. Vertical light steel C sections
constructional benefits. are fitted between the head and base tracks,
There are three generic types of light steel typically at 600mm centres (or reduced to 400
external wall systems: or 300mm where structural design requires
• Infill walls closer spacing). In some cases, the panels may
• Continuous walls be constructed such that they project past the
• Panelised systems. edge of the primary structure (see figure 9.2).
Continuous walls
The continuous wall panels (also known
as over-sail panels) are placed externally
to the primary structural frame, as
shown in figure 1.2. The system consists
of vertical light steel C sections and
bracket connections used to fix the
C sections to the primary frame.
Panelised systems
The panelised system uses prefabricated
light steel wall panels, often with insulation
and boards attached off-site. These are
craned into position and fixed to the primary
Figure 1.1 Typical infill wall panel within a steel or concrete primary structure
structural frame (see figure 1.3).
8
they are designed to resist wind loading
on the façades, and to support their own
weight and that of attached lightweight
cladding materials. Dead weight of masonry
cladding must be supported directly by
the primary structure or foundations.
However, light steel external wall systems
can generally provide horizontal support
against wind through the inclusion of a
proprietary system of brick tie channels and
brick ties positively fixed back to the stud.
In addition to structural requirements,
the design of external wall systems
must also consider fire resistance,
condensation risk, weathertightness, thermal Figure 1.2 Typical continuous walling fixed external to the primary structure – some openings may
require compound stud framing, refer to the designer/manufacturers details
insulation and acoustic performance, and
must allow for interfaces at windows,
patio door and balconies, etc.
The focus of this report is on non-
loadbearing infill walls which consist of
assemblies of site-installed sections; although
much of the guidance will also apply to
continuous walls and panelised systems.
“...the design of
external wall
systems must
also consider
fire resistance...”
9
2 LIGHT STEEL SECTIONS
2.1 Steel grade and coatings 2.2 Section sizes
External wall systems perform the The gauge and dimensions of the sections
significant structural functions of resisting to be used in construction must be verified
wind load and supporting the weight of by project-specific structural calculations.
cladding systems. Therefore, it is important The structural design may be carried out
that the systems have been adequately in accordance with BS 5950-5 5 or BS
designed, and in order to justify the EN 1993-1-3 6 . The principle designer,
structural design the components must be representing the client as defined in the CDM
formed from suitable quality steel designed Regulations, should indicate which code should
for use in SFS. be used. Mixing of codes is not acceptable.
Recommended steel grades for external The type of section used in external wall
walls are S350, S390, S420 and S450. systems is generally either a plain C section
Mechanical properties for these steel grades (also known as U sections) or a lipped C
are given in Table 2.1. section (see figure 2.1). The section sizes
used for external wall applications will depend
on the structural design (ie the size of sections
Minimum Minimum Minimum required to provide sufficient strength and
Recommended yield strength tensile strength elongation stiffness) and on practical considerations of
steel grade N/mm² N/mm² %
ease of construction and fixing other elements
S350GD 350 420 16 of the system to the sections.
S390GD 390 460 16 The main members used in an infill wall
panel are shown in figure 2.2. Lipped C
S420GD 420 480 15
sections are used for the vertical elements and
S450GD 450 510 14 plain C sections are used for the horizontal
3 https://shop.bsigroup.com/ProductDetail/?pid=000000000030280396
10 4 https://portal.steel-sci.com/documents.html
Head track members should be designed
to suit the load and allow for deflection
and construction tolerances. The head track
might be a different gauge to the stud and
bottom track. Ensure that the correct gauge
components are being used. Refer to the design
drawings at all stages.
5 https://shop.bsigroup.com/ProductDetail/?pid=000000000030155279
6 https://shop.bsigroup.com/ProductDetail/?pid=000000000030207055 11
3 STRUCTURAL DESIGN
This section presents guidance on structural
design issues that are specific to light steel
external walling. Generic structural design
guidance for light steel sections is provided in
SCI publications P276 1 and ED005 2 .
3.1 Loads
7 https://shop.bsigroup.com/ProductDetail/?pid=000000000030040684
12 8 https://shop.bsigroup.com/ProductDetail/?pid=000000000030206733
where restraint is not provided to both sides.
Attachment of members to boards will
provide restraint and increase the member’s
buckling resistance. However, the contribution
of board restraint should be ignored in design
unless there is supporting test data to confirm
the level of restraint that is provided. The level
of restraint provided by boards will depend on
many factors, including the board properties
and how it is fixed to the light steel elements.
For light steel external walls, ‘blocking and
bracing’ can be used to provide lateral
Figure 3.2 Typical ‘blocking and bracing’
restraint to members for the purpose of
increasing the member’s buckling resistance.
design because they are considered small in ‘Blocking and bracing’ consists of steel bracing
comparison to the effect of the wind load. straps fixed horizontally across the panels with
However, axial compression in stud sections will blocking pieces or ‘noggins’ (cut from C section)
reduce their bending resistance. Therefore, it is fixed between studs (usually every third bay
recommended that dead load may only and at ends). Blocking and bracing is shown in
be ignored when both of the following limits figure 3.2.
are met: ‘Blocking and bracing’ is normally provided on
• Panel height not more than 5m walls greater than 3.6m high, or as determined
• Load due to self-weight of the façade not by structural calculations. It may not be
more than 1.5kN/m² required where sheathing board is positively
The designer must consider the local fixed on the external face and gypsum based
effects and eccentricity of cladding loads (see board is positively fixed on the internal face.
section 3.3).
Effective length (buckling length)
3.2 Design resistance Buckling resistance of members is partly
dependant on their effective length (termed
Limit states buckling length in Eurocode design). The
The elements of light steel external wall panels effective length is equal to the actual length
should be designed for two limit states: multiplied by a factor which is dependent on
• Ultimate Limit State (ULS) the restraint provided by the connections at
• Serviceability Limit State (SLS). the ends of the member and the restraint along
ULS is concerned with the structural safety the length of the member.
and the strength of the panel and its elements. An effective length factor for bending of
Resistances are required to be not less than 0.85 may be used for vertical studs when the
the effects of design loads (characteristic loads following conditions are met:
multiplied by load factors). • Additional restraint provided by boards
SLS is concerned with the ‘fitness for use’, attached to studs is not included elsewhere
including deflections of the panel and its in the stud design
elements. Deflections due to (unfactored) SLS • Moment variation along the member is not
loads are required to be within specified limits. considered in the design of the member.
9 10 https://portal.steel-sci.com/documents.html
11 https://www.brebookshop.com/details.jsp?id=326937 13
Figure 3.3 Illustration of
cladding load eccentricity steel wall panel must consider the pull-out of
fixings, local deformation of the light steel
sections and the eccentricity of load.
3.4 Deflections
lateral restraint. Where the infill wall panel is that may be used for deflection calculations
connected to the primary columns, it is not (ISLS) should be taken as:
necessary to use slotted connections to allow
ISLS=(IGross+IEff)/2
differential movement between the infill wall
panel and primary column. Where IGross is the second moment of area for
The design of the primary frame column the full gross section and IEff is the second
is unaffected by the requirement to provide moment of area for the effective section in
lateral restraint to members in the infill wall bending including effects of local buckling.
panel because the lateral forces are generally For design to BS EN 1993-1-3 (see ED005
insignificant compared to the primary frame 2 ) the second moment of area that may be
14 12 https://portal.steel-sci.com/documents.html
The elements around the opening must be
designed to resist the effects of the wind load
that would be applied to the area of the opening.
The area of the opening should be divided
between the adjacent elements; one approach
for dividing the area is shown in figure 3.4a.
Alternatively, for simplicity, the window may be
assumed to span vertically between the lintel
and the cill, as shown in figure 3.4b. The loads
are then transferred as point loads applied to
the jambs either side of the opening.
In many cases the framing members will
Figure 3.4 Division of opening • L/250 limit for plasterboard consist of several sections forming one
area into loading on the
members • L/360 limit for brittle finishes compound section. Typical compound sections
• L/360 for glazing along the length of are shown in figure 3.5.
window openings Some general guidance on the use of
• Absolute deflection of members above or compound sections around openings is given
below an opening is recommended as 15mm below. However, this is not intended to replace
if this is less than span/360 (ie for spans structural design for sections around openings
greater than 5.4m). because project-specific conditions will be
significant in the selection of a suitable solution.
3.5 Openings • For windows up to 1.5m width, it may be
expected that single sections are used
Openings in external wall panels are required at vertically and horizontally (ie for lintels, cills
window and door locations. Additional members and jambs)
are required to frame around openings: jambs • For windows up to 2.4m width, it may be
either side of the opening; a lintel above the expected that compound sections are used
opening; and a cill below the opening (as shown vertically (jambs) and single sections are used
in figure 2.2). horizontally (cills and lintels)
• For windows up to 3m width, it may be
Figure 3.5 Typical single,
boxed, and compound sections
expected that compound sections are used
horizontally and vertically (lintels, cills and
jambs)
• Alternatively, for wide windows, compound
sections as illustrated in figure 3.5, or wind
A) Jambs posts may be utilised (see section 9.1).
15
3.7 Holes in members The steel sections should never be cut
by flame-cutting because it will impact the
Light steel members can be delivered to site strength of the steel.
with pre-punched holes for services. Notches should not be formed without
When the following recommendations are confirmation that the structural adequacy of
observed, holes in the webs of sections primarily the member is maintained; the engineer or
subjected to bending, have negligible influence designer responsible for the element should
on the structural performance of the member. provide the confirmation.
• The maximum width of an unstiffened
rectangular hole or slot in a light steel 3.8 Splices
member should not exceed 40% of the
overall width of the section. The length of In some situations, it may be necessary to
the hole should be less than three times the join light steel sections together with a splice
width of the hole connection. The adequacy of splice connections
• The diameter of circular holes should not should be confirmed by structural calculations.
exceed 60% of the depth of the section In continuous external wall systems, studs are
• Holes should be positioned on the centreline commonly spliced into manageable lengths to
of the section facilitate safe site installation, see section 8.2.
• Unstiffened holes should be at least the Wherever possible, members of the infill
depth of the section apart and should be at walling system should be formed from full
least 1.5 times the depth of the section away lengths of section. Off-cuts of sections
from the end of the member should never be joined together to form
• All holes should be formed by punching. lengths of sections.
Larger openings in the steel sections may require
reinforcing by the addition of steel plate attached 3.9 Load tables
to the web around the opening or by creating an
opening with a swaged (lipped) edge (see figure 3.7). Manufacturers of light steel external wall
systems will be able to provide system-specific
load/span tables or design software that takes
into account:
• Height of wall
• Wind load
• Opening size.
16
4 SETTING OUT, TOLERANCES AND MOVEMENT
4.1 Setting out • Out of verticality (plumb) of wall = ±5mm
in 3m height (H) or H/600 for walls over
Support length 3m in height
The minimum length bearing width of • Acceptable deviation in level of slab or
support under sections is two-thirds of the beam soffit = ±10mm over 3m length
section width or 80mm for sections less than • Tolerance in length of C section = ±5mm
120mm wide. The maximum projection over in 3m length (positive deviation could
the slab edge is given in figure 4.1. compromise movement at head detail)
• Tolerances for position of base track =
±10mm from intended centre line
• For fixing details of C sections to the
base track, refer to system manufacturer’s
technical manual
• For tolerance on noggin length, refer to
system manufacturer’s technical manual.
13 https://www.ridba.org.uk/2017/06/27/national-structural-steelwork-specification-building-construction/
14 https://shop.bsigroup.com/ProductDetail/?pid=000000000030016643 17
4.4 Deflection head detail
Deflection allowance (mm)
To allow the floors of the primary structural
Edge New build in-situ
frame to deflect during service without beam Renovation of or precast
inducing axial loads into the infill wall, the span Steel existing concrete concrete framed
head track must incorporate a deflection (m) framed building framed building building
head detail. 4 ±10 ±10 ±16
The deflection head detail is required
5 ±10 ±13 ±20
to restrain the vertical members against
horizontal movement but to allow the head 6 ±12 ±15 ±24
track to move vertically, independently of 7 ±14 ±18 ±28
the studs. Various deflection head details are
8 ±16 ±20 ±32
used in practice. Some examples are shown
in figure 4.2. Note: the higher deflection allowance for new build concrete buildings is to
take account of the long term creep and shrinkage effects of the concrete.
The required deflection head allowance
should be specified by the designer of the Table 4.1 Typical deflection allowances
supporting primary frame. Typical values
for deflection allowance are given in table
4.1. The clear space between the top of the
studs and the web of the head track after
installation should be at least equal to the
appropriate value from table 4.1.
Boards should not be screwed to the
head track, to avoid compromising the free
movement relative to the structure.
18
5 FIXING DETAILS AND FASTENERS
5.1 Fixing details the studs are required from both applications, place an acoustic tape
sides of the wall panel. on the slab surface prior to location
Generally, members for infill walling • Do not use drylining screws for steel of the bottom track.
are cut to length on-site. Therefore, connections. • For a ground floor slab, use a damp
connections are generally formed on site • Fixings should be galvanized. proof course (DPC) below the
without the use of pre-drilled holes or • Fixings should have a European bottom ‘track’.
pre-marked fastener positions. System Technical Approval or an equivalent • The distance from the edge of the
suppliers will have standard construction independent technical assessment. slab to the fixing and the distance
details which should be followed. • Fixing centres for compounding to be between fixings should meet
Fixing details should generally calculated by the engineer designing the manufacturers guidance and
comply with the following the light steel members. recommendations.
recommendations.
Fixing between infill wall panels and Fixing between infill wall panels and
Fixing between members of infill primary structural frame board materials
wall panels • For connection of tracks to the • Board manufacturers’ literature
• For connection between light steel concrete slab or soffit, use 6mm should be consulted to confirm
members where a ‘flush’ finish is diameter concrete screws, with 5mm recommended fixing details and
required, use pan head 5.5mm diameter hole in the concrete. minimum edge distances.
diameter screws (to outer threads) • For connection of tracks to the • The use of gas-applied fixings is not
or 4.2mm (shank diameter). Screws steel beams, use 5.5mm self-fixing recommended.
have a 2mm projecting head. self-drilling (SFSD) screws or 3.2mm
• For connection between light steel diameter powder actuated fixings. 5.2 Types of fastener
members where a ‘flush’ finish is • Spacing of fasteners should not
not required, use hex head 5.5mm exceed 600mm. Typical types of fastener used in
diameter screws (to outer threads) or • Additional fixings will be required at light steel infill walling systems are
4.2mm (shank diameter). track ends and split points; within presented in table 5.1. For all types
• The minimum edge distance for a 100mm of the track ends. of fastener, the manufacturer’s
screw fixing into a light steel section • The fixing manufacturer’s advice installation instructions should be
should be three times the fixing should be sought for the use of shot- followed.
diameter (to outer threads) and not fired nails into concrete without pre-
less than 10mm. drilling the concrete.
• Fixings between the base track and • For acoustically sensitive
Table 5.1 Typical fasteners
Hot rolled fine thread Typically 5.5mm diameter. Used to connect light
screw steel sections to hot-rolled steel.
19
6 INSTALLATION
Light steel external wall systems should
be installed by companies approved as
installers by the external wall system supplier.
The installers will generally be working as
subcontractors to the main contractor, who is
responsible for the construction of the building.
20
The base track should be aligned to the the webs of the studs are providing the sides
setting out lines and then fixed to the of the structural opening. The fixings must be
substrate using the specified fixings at the installed before any boards or finishes cover
required centres. Care should be taken to the studs.
ensure that the track does not move out of The simplest method of stud installation is to
place as the initial fixings are drilled through set out the studs at the edge of the structural
the member. In some cases, the member may opening, then measure off the required
need to be pre-drilled with a high speed steel centres of the rest of the studs within the bay
drill before fixing. Fixing of base track is shown (generally 600mm), or use a block cut to size
in figure 6.1. as a template. However, attention should be
The head track can be fitted using the paid to the installation of the internal boarding
same methodology. However, the alignment that may require the studs to be set out from
of the two tracks (one above the other) specific grids from one end of an elevation to
should be checked using a length of stud the other.
cut to size and a spirit level. This will ensure
that the wall will not lean out of plumb. Final Setting out openings
fixing should only occur after these checks, The jamb studs either side of an opening should
or time and cost will be incurred if either be set to provide the width of the structural
track has to be repositioned. opening and to provide a surface to fix the
Ensure that the specified fixings at the track door or window frame.
ends and split points are provided; generally, The contractor’s engineer is responsible
this will require double the amount of fixings for putting horizontal datum lines on the
at these points, and within 100mm of the track structural columns. These marks will have an
edges. Check that there is sufficient bearing on offset to the structural slab, usually this is 1m
the substrate at both the base and the head from structural slab level (SSL), but must be
of the panel; there will be a specific dimension clarified before proceeding. The position of
for each situation on site. As a general rule, the the cill can be marked on the column before
bottom track of the light steel infill walling can transferring the mark across the studs to the
overhang the edge of the structure by up to relevant structural opening. On occasion the
one third of its width (see section 4.1). Check datum mark will be given offset to finished
that acoustic tape and DPC is installed under floor level (FFL). Care must be taken to
base track where specified. consider the possibility of screed sitting on the
structural slab.
General stud installation Cill construction will consist of studs fitted
Initial stud positions should be measured from to the jamb studs. These will be the full
the grid using a tape measure and should be length between base track and cill height.
determined from the centre of a structural The cill member will then fit above these
opening. If there are no openings within the studs, fixed at each end and to the studs in
bay, then the elevation drawing will usually the zone under the cill (according to the stud
specify the position of the first stud and centres in the bay).
provide stud spacing requirements across the The lintel position can then be ascertained
rest of the bay. from the cill using the opening dimension shown
The bay height should be checked, and the on the drawings. The lintel is fitted in much the
studs cut to size, with appropriate allowance same way as the cill. The lengths of stud above
for deflection and the head track web (see the lintel should include the same method of
section 4.4). accommodating deflection as the general studs.
The studs should be placed into position The installer must make provision for any
and fixed as specified through the base track. compound members required for the jambs,
Ensure that jamb studs are oriented so that cills and lintels (see section 3.5).
21
7 HEALTH AND SAFETY
Most of the health and safety considerations
related to the installation of light steel external
“Under no circumstances
wall systems are common to many construction should persons be exposed
activities. Therefore, much of the information
presented in this section will have wider
to working at height
application beyond that of light steel external without suitable control
wall systems.
This section is not intended to be measures in place.”
comprehensive, only those aspects of health
and safety which have particular relevance Installation of parapets, ribbon windows and
to the installation of light steel external wall walls at balconies or patios may require special
systems are included. safety procedures.
Edge protection is particularly relevant to the Light steel external walling is constructed from
installation of external wall systems due to lightweight components; therefore, manual
their location within a building. handling is undemanding in comparison to
Under no circumstances should persons be alternative solutions.
exposed to working at height without suitable In the case of compound sections assembled
control measures in place. and fixed on the floor, the total weight of the
When there is no scaffold present at the assembly will require consideration as to safe
edge of the slab the main contractor will have handling during erection.
installed some form of edge protection. A For all sites, a specific plan and risk
common method of protecting the exposed assessment should be developed by the installer
edges of a building is to fix a fencing frame to that will evaluate the risks attached with
the structure; attached to posts fixed into the handling light steel sections and equipment.
structural slab, to the face of the structure or Manual Handling at Work – A Brief Guide 15 is
fixed to the soffit of the floor below. As the available from the HSE on reducing the risk of
external wall installation progresses the edge manual handling injuries.
protection will be removed. The external wall Continuous (oversail) walling systems also
will provide a satisfactory barrier to falls from require consideration as to the appropriate
the building once completed. However, this method for safe handling during erection
may lead to areas above or below the works because longer stud lengths are heavier
having an exposed edge; other forms of barrier and have a high level of flex due to their
will then be needed. At the exposed edge, slenderness.
operatives will need to be harnessed to the General guidelines in management of manual
structure to prevent the possibility of a fall. handling are:
The method of edge protection will depend on • Workers should receive training in kinetic
the type of access equipment used (see section lifting
7.6). Possible types of edge protection include: • Plan material use and adopt good practice
• Temporary or permanent barriers when stacking materials
• Scaffolding • Use mechanical lifting equipment where
• Netting practicable
• Harness / lanyard – only when the options • Use team lifting for awkward and heavy loads
above are not possible. • Good housekeeping standards should be
There may be areas around stairs and lifts that maintained in all work areas
require special protection as they are more heavily • All spillages or general rubbish should be
trafficked. These areas should be identified. cleared in a timely fashion.
22 15 https://books.hse.gov.uk/Industry-Guidance-INDG/?DI=647950
7.3 Cutting 7.6 Access equipment
Procedures for cutting of light steel sections Various types of access equipment can be used
should be defined and safety procedures for the installation of light steel external wall
followed. Operatives should hold a current systems. Some of the common methods are
‘Abrasive Wheel’ certificate for on-site cutting. given below with brief descriptions of issues
Normal handling precautions for cut edges that need to be considered before selection.
should be observed.
Care must be taken to ensure that guards
and handles are properly fitted to tools and
“All operatives involved on site
that there are plenty of blades available on the should read and understand
cutting disc, operatives must use the specified
personal protection equipment (PPE) according the information within the risk
to the manufacturer’s specification. ‘Hot works’ assessments. The site
permits may be required on some sites, as well
as the use of baffles or spark boxes. operatives should then sign
7.4 Method statements
and date their acceptance of
these documents.”
The method statement is the installer’s
interpretation of how the installation is Scaffolding
actually going to be carried out. Usually the Scaffolding is a series of steel poles and
method statement is a simple, brief document wooden planks, designed with calculation, to
that demonstrates competence to the main provide platforms that can be worked off.
contractor and is a guide to the individual Scaffolding is generally set with 2m working
operatives, who should all read, sign and date heights along the outside of the elevations and
the document to signify their understanding is nearly always used on tall structures and
and acceptance. It should also form part when the footprint of the site allows.
of a checklist/handover document that the Scaffolding is expensive, and its use requires
main contractor can use to check that the careful planning and coordination with other
installation has been carried out correctly. trades. There can be problems with tying into
the building through the external wall that can
7.5 Risk assessments prevent completion of works at the first visit.
When set up correctly, scaffold provides good
Risk assessments for the project should be access to the outside of the wall and good
carried out before the installation of the light storage of materials, however other trades may
steel external walling system. Risk assessments also use scaffold, which can create obstacles to
should consider general hazards as well as any progress of external walling installation.
site-specific risks. Any actions to reduce risk Dependant on finishes and external wall
that are identified should be carried out and build-up, there is a potential for unsafe
documented before site works commence. working conditions due to gaps between
All operatives involved on site should read the scaffold edge and the wall, individuals
and understand the information within the often pull back boards making work areas
risk assessments. The site operatives should unsafe. Therefore, careful coordination with
then sign and date their acceptance of these scaffolding contractors is necessary. Scaffold
documents. The risk assessment system should can provide excellent defence against damage
be backed up with a series of health and safety to the wall; it can be sheeted and canopied
toolbox talks about a specific site related issue to provide a barrier to wind, rain and general
or a general health and safety concern. poor weather conditions.
23
Scissor lifts Access from floor slab
Scissor lifts are moving platforms that have a When working off the floor slab it will usually
flat platform on which to work. They are often be necessary to use some form of equipment
diesel fuelled extendable platforms that can to allow access to the top of the external wall
reach out to over 18m. They are considered panel at the soffit of the floor slab above.
a cheaper alternative to scaffolding, but care A hop-up including all safety rails is an
must be exercised to avoid using scissor lifts individual platform that provides a base of up
where it is inappropriate or dangerous (eg to 1m². More than one hop-up may be required
where ground conditions are uneven). when handling long lengths of steel.
Operators working from scissor lifts A mobile tower is a clip-together scaffolding
need to be qualified. Untrained operators tower that provides a base at a level that is
may cause accidents and damage. Ground adjusted to the height required. A mobile tower
conditions are crucial – often where will have a larger size platform than a hop-up.
landscaping is required the contractor does However, this can lead to accidents because
not want to pay to put down hard standing tools and materials stored on the platform
materials. Combined with poor weather this can cause trip hazards. Mobile towers must be
can cause the ground to turn muddy with erected and signed off by a competent person.
forklifts and scissor lifts churning up the Stepladders are not allowed on most sites
ground, getting stuck and causing delay. as there is an increased risk of accidents due
Scissor lifts are generally slow to manoeuvre, to falls.
lift and drop. Deviations in the ground can
prevent the lift going up and the lift height
is limited. There are often difficulties with
fuelling up, flat batteries and flat tyres causing
“Scissor lifts do not provide
delays on site. any protection to the
With scissor lifts there are often delays
getting to the point of work in comparison workface or the workers
with scaffold. Scissor lifts do not provide any
protection to the workface or the workers
located on the building.”
located on the building.
Cherry picker
A cherry picker is a small basket on an
extendable arm that is fixed to a movable
base (diesel powered); it is not suitable for
general light steel infill walling installation but
can be used for small remedial works or the
installation of continuous walling brackets to
a slab face (see section 8). Operatives will
need specific training and will be required to
wear harnesses.
Mast climber
A mast climber can have a platform width of
up to 20m. They are generally pushed and fixed
into place through the external wall. They have
limited mobility and are fairly slow to lift and
lower. They do not provide any protection to
the workers or working edge.
24
8 CONTINUOUS WALLING
Continuous walling (also known as oversail walling)
is placed externally to the primary structure.
The components used in continuous walling are
similar to those used for infill walling. However,
there are some significant differences that
must be considered in design and construction.
The main differences are the connection of the
walling system to the primary structure and the
longer length of the vertical studs as they can be
continuous over several storeys.
For continuous walling, the self-weight of the Figure 8.1 Angle bracket for support of continuous walling
8.2 Splices
25
9 SECONDARY STEELWORK
9.2 Projection brackets
26
10 SPECIAL CASES
Where special arrangements are needed,
it is important that advice is sought from
both the project engineer and from the
walling manufacturer.
There are many situations within buildings
using light steel external walling where special
arrangements are needed, these include:
• Parapets
• Curved walls
• Ribbon windows
• Inclined walls
• Balconies
• Application below DPC/lower than a minimum
of 75mm above finished external ground
level
Figure 10.1 Curved infill
• Up-stands and down-stands walling – during and
after construction
• Fitting of infill walls around bracing
• Support for very heavy cladding.
27
11 CHECKLISTS
This section provides a series of checklists • Have deflection head details been clearly
for people involved in the design and specified with appropriate deflection gaps?
installation of light steel external walling. • Have setting out assumptions (eg to
minimise waste of all lining board) been
11.1 Checklist for external wall clearly noted on the drawings?
designers and specifiers • Have the implications of BR135 16 and the
18m rule in AD B2 17 been addressed?
The designers and specifiers of the external
walling should check the following: 11.2 Checklist for external
wall supplier
Structural design
• Have site-specific loads been provided or The external wall supplier should check
calculated (eg wind loads)? the following:
• Have all special connection details
been specified? Material ordering
• Have all fixing types, including spacing and • Have all materials been ordered in
edge distances, been specified? good time?
• Has an erection method statement been • Have additional lengths been ordered in
provided which clearly shows any special case of damage on site?
requirements for access?
• Is the specification of steel and coating Delivery
suitable for the relevant environment • Are deliveries properly scheduled to ensure
category class? that the correct material is on site at the
right time? Generally, sections should be
Interfaces delivered in the sequence in which they
• Are all interface details clearly shown on would be installed.
the drawings and are special requirements • Are all materials properly marked, and has
such as isolating gaskets clearly identified? the correct quantity been supplied?
• Where unfamiliar materials are specified,
has advice been sought from specialists 11.3 Checklist for main contractors
and have any special requirements been
noted on the drawings? The main contractor should check the
following aspects of the construction.
Installation drawings
• Is each element appropriately marked (eg Structure interfaces
manufacturer’s name and gauge)? • Has the external wall supplier been
• Do the drawings clearly specify the fixings provided with full information to allow the
to be used? elements to be manufactured?
16 https://www.brebookshop.com/details.jsp?id=327137
28 17 https://www.planningportal.co.uk/info/200135/approved_documents/63/part_b_-_fire_safety/2
11.4 Checklist for erection 11.5 Checklist for infill wall
supervisors manufacturer
The erection supervisor responsible for The manufacturer of the infill wall system
the external wall erection should check the being installed may carry out site audits for
following aspects of the construction. quality assurance purposes. The questions
given overleaf are typical questions that may
Fabrication be included.
• Has each element been appropriately
marked (eg manufacturer’s name, gauge of
steel)?
• Are the section sizes as specified?
• Delivery
• Have any panels or components been
damaged?
• Have all materials been stored flat on
clean level areas and stacked for ease of
retrieval?
• Have all steel components been kept out of
contact with dry cement, lime, plaster and
mortar?
External walling
After installation the following should be
checked:
• Are panel cills square and level?
• Are panels plumb and square?
• Are fixings of the correct type and installed
as specified?
• Have all damaged areas of galvanizing been
wire brushed and recoated?
• Have service holes been fitted with sleeves
or grommets where specified (eg where
electrical wiring is used)?
• Have all secondary components (eg
longitudinal ties) been properly installed?
• Have fixings to primary structure been
installed as specified?
• Are all noggins and joints fitted flush to
facilitate attachment of the plasterboard?
• Are all service holes aligned?
• Are all bottom tracks clear of debris, and
are drainage holes unobstructed?
29
SITE AUDIT REPORT
Project name
Site auditor
Audit date
Project reference
Site contact
Areas inspected
INFORMATION CONTROL
Are the latest revisions of drawings being used on site?
Yes No Other
Has the client read and understood all elements of design including isometrics and specific details?
Yes No Other
Does the client have specific COSHH and product information for all sections and fixings?
Yes No Other
PRODUCT MANAGEMENT
Is the material stored safely and securely in accordance with the specification?
Yes No Other
Are installers taking the required health and safety precautions in product handling and installation?
Yes No Other
DESIGN INSTALLATION CHECKS
Is the installation in accordance with the details for head and base tracks?
Yes No Other
Are fixings installed to design details and specification?
Yes No Other
Are deflection head details constructed to design?
Yes No Other
Is the deflection zone clear?
Yes No Other
Are jambs, cills and lintels constructed to design?
Yes No Other
Are noggins, cleats and special construction details installed to design?
Yes No Other
Are sheathing boards installed in accordance with specification?
Yes No Other
What is the general standard of workmanship?
1 Best practice achieved – no remedial works required
2 Best practice not achieved – minor remedial works required
3 Major remedial works and further inspections required
Are there any special conditions and observations to be noted?
Item Observation
30
13 REFERENCE
1 Building Design Using Cold Formed Steel Sections
Structural design to BS 5950-5: 1998 – Section Properties and Load Tables (P276)
SCI 2002
https://portal.steel-sci.com/documents.html
3 BS EN 10346: 2015
Continuously hot-dip coated steel flat products for cold forming. Technical delivery conditions.
https://shop.bsigroup.com/ProductDetail/?pid=000000000030280396
5 BS 5950-5: 1998
Structural use of steelwork in building. Code of practice for design of cold formed thin gauge sections
BSI 1998
https://shop.bsigroup.com/ProductDetail/?pid=000000000030155279
6 BS EN 1993-1-3: 2006
Eurocode 3: Design of steel structures – general rules
Supplementary rules for cold formed members and sheeting (incorporating corrigendum November 2009)
BSI 2006
https://shop.bsigroup.com/ProductDetail/?pid=000000000030207055
7 BS 6399-2: 1997
Loading for buildings. Part 2: Code of practice for wind loads (incorporating amendment no.1 and corrigendum no.1)
BSI 2002
https://shop.bsigroup.com/ProductDetail/?pid=000000000030040684
31
9 Guide to evaluating design wind loads to BS 6399-2: 1997 (P286)
SCI 2003
https://portal.steel-sci.com/documents.html
11 BRE Digest 346: The assessment of wind loads. Part 8: Internal pressures
https://www.brebookshop.com/details.jsp?id=326937
14 BS EN 10162: 2003
Cold rolled steel sections. Technical delivery conditions. Dimensional and cross-sectional tolerances.
BSI 2003
https://shop.bsigroup.com/ProductDetail/?pid=000000000030016643
16 BR 135 – Fire performance of external insulation for walls of multistorey buildings – third edition
BRE 2013
https://www.brebookshop.com/details.jsp?id=327137
17 AD B2
https://www.planningportal.co.uk/info/200135/approved_documents/63/part_b_-_fire_safety/2
32
14 ACKNOWLEDGMENTS
FIS has grown over the past 50 years to The Steel Construction Institute (SCI) is the leading,
become the leading trade association for the independent provider of technical expertise and
fit-out sector of the construction industry. disseminator of best practice to the steel construction
FIS represents companies involved in the sector. We work in partnership with clients, members
manufacture, supply and installation of all and industry peers to help build businesses
aspects of interior fit outs and refurbishment. and provide competitive advantage through the
FIS members operate in retail and commercial commercial application of our knowledge. We are
offices, the public sector, banks and building committed to offering and promoting sustainable
societies, hotels and leisure, airports, hospitals, and environmentally responsible solutions.
and so on. Most work nationally and an increasing
number operate in Europe and beyond. Our service spans the following areas:
Quality and integrity lie at the heart of FIS’s
Membership
philosophy - each member is expected to act
Individual and corporate membership
with the utmost integrity, and to exercise the
highest standards of business practice and Advice
Members’ advisory service
workmanship. At the same time, the Association
seeks to continually raise, maintain and ensure Information
Publications; education; events and training
the perpetuation of standards in order to remain
a source of quality membership. Consultancy
FIS membership is not automatic and Development; product development; engineering
support; sustainability
applicants are subject to strict vetting
procedures on application, as well as ongoing Assessment
vetting. In the case of contractors, this includes SCI Assessment
inspection of recent contracts to assess Specification
workmanship standards. Websites; engineering software
www.thefis.org www.steel-sci.org
33
NOTES
34
35
SUPPORTERS
The work leading to the original report was funded by Ayrshire Metals Ltd,
BW Industries Ltd, Fusion Building Systems, Kingspan Steel Building Solutions,
Metek Plc and Tata Steel Strip Products UK.
This revised guide has been supported by Acoustic and Insulation Manufacturing
Ltd, Caledan, EOS Facades Ltd, Etag Fixings UK Ltd, Etex Building Performance Ltd,
Euroform Products Ltd, Knauf Ltd, Stanmore Contractors Ltd, Trimble Solutions (UK)
Ltd, Veitchi Group Ltd, Vertex Systems Oy and voestalpine Metsec Plc.