Professional Documents
Culture Documents
DETAILS
CONTRIBUTORS
GET THIS BOOK Parsons Brinckerhoff, Inc., Metro Tech Consulting Services, Engineering and
Architecture, P.C., Track Guy Consultants, and Ihrig and Associates Wilson,
Inc.; Transit Cooperative Research Program; Transportation Research Board;
National Academies of Sciences, Engineering, and Medicine
FIND RELATED TITLES
SUGGESTED CITATION
Visit the National Academies Press at NAP.edu and login or register to get:
Distribution, posting, or copying of this PDF is strictly prohibited without written permission of the National Academies Press.
(Request Permission) Unless otherwise indicated, all materials in this PDF are copyrighted by the National Academy of Sciences.
Table of Contents
14-ii
The designer should understand that once the system is designed, built, and turned over to the
owner, it will need to be maintained. All too often, the focus of the designers and constructors is
only on building the project with insufficient attention to the interests of the maintainers. In many
cases, it has been assumed by the owner that maintenance will not be required. The fallacy of
such assumptions is usually not apparent until conditions have deteriorated to a level where
corrective measures are difficult and expensive and cause significant inconvenience for all
parties, including the system users.
If a system of periodic inspections and preventative maintenance is in place from the beginning,
all properly designed and constructed LRT trackforms should last for decades without requiring
significant reconstruction. This is largely because of the small axle loads of rail transit vehicles.
The purpose of this chapter is to offer some recommendations for maintaining all trackforms so
that the designer has a basic understanding of the requirements. Much of maintenance is
generic to all trackforms, but some require more specific focus to achieve success. FRA, APTA,
and the FTA have developed some general criteria that can be useful, but it is the responsibility of
each owner to develop a maintenance program specific to its system.
The designer must set certain tolerances for the construction entity to build the project. These
standards are completely different than either maintenance standards or safety standards.
Construction standards are tolerances that must be met during the building portion of the LRT
system. See Chapters 4 and 13 for discussions on construction tolerances. Construction
tolerances typically reflect the use of new, unworn materials and typically cannot be achieved
once the system is in operation and the components have begun to wear.
Maintenance standards are for maintainers to use and not for new construction. They represent
desirable minimum limits so that satisfactory operations can continue. Maintenance standards,
like the safety standards discussed in the next article, are typically established for certain speeds
14-1
and classes of track. These standards will be unique to each transit property based on its needs
and objectives. Inherent in any maintenance standard is an expectation that a certain amount of
deterioration will occur before the next cycle of maintenance but that ride quality will not be
impaired to the degree that corrective action becomes mandatory.
Track maintenance standards and related requirements are typically codified in manuals and
other documents developed specifically for each railway. These procedures will address many
conditions and may include the following:
• Track charts of the property identifying speeds, alignment, curve radius, gauge, and
cross level
• Criteria for drainage and vegetation control
• Maximum allowable dimensions for track gauge and alignment, both vertical and horizontal
• Criteria for maximum acceptable ballast and cross tie deterioration
• A CWR plan (sometimes called “track buckling countermeasures”)
• Criteria for inspection and maintenance of plinth concrete and embedded track slabs
• Criteria concerning resuming operation after a severe weather event such as high water
• Torque limitations for anchor bolts and other threaded fasteners
• Inspection frequency and record-keeping requirements
The above is only a partial list, and reference should be made to standards and recommended
practices in the industry. Many properties will assign color codes to various criteria to establish
degree of severity and actions to be taken.
Track safety standards are criteria that signify absolute limits for safe operation at various
speeds. If the track structure deteriorates beyond these safety standards, then immediate action
must be taken. That action might be
• Correction of the defect so as to bring the track into compliance.
• Reduction of train speed to a level consistent with the conditions that exist.
• Removal of the track from service until such time as the condition has been corrected.
Typically, at least two of the actions noted above will be required in response to any individual
class defect. For example, if the defect cannot be corrected immediately upon detection, a speed
restriction would be imposed (first action) until a crew can be mobilized to correct the problem
(second action). Obviously, the preferred circumstance would be that the track never deteriorates
to a level where safety limits become a consideration because maintenance standards have been
adhered to.
14-2
While the Federal Railroad Administration has a comprehensive set of track safety standards
(see 49CFR213) that are a useful reference, they technically do not apply to urban rail transit
systems that are not connected to the general railroad system. Moreover, there is much in the
FRA Track Safety Standards that could be misleading for a system that does not employ AAR
wheel profiles and wheel gauges. APTA published safety standards for the transit industry in
2007. They are great resources for an agency to develop both maintenance standards and
safety standards but are necessarily generic and therefore must be adapted to the specific
conditions of each rail transit line. As of 2010, the FRA has been charged by Congress to
develop safety standards for transit systems that are not connected to the general railway
system. This will ultimately result in fines for noncompliance.
14.3 ACCEPTANCE
Once a track is accepted by the owner, their maintenance organization (which might be either an
internal department or an outside contractor) will take over responsibility for the track from the
constructor. The designer should understand what is important to the owner before the
maintenance organization assumes responsibility. The following are some of the minimum
requirements prior to transferring responsibility from the constructor to the maintainer:
• Documentation—the proper documents will need to be turned over to the owner upon
completion of the project. These documents should have been gathered throughout the
course of construction according to the QA/QC program. These documents are an
integral part of the development of standards for maintenance. Not only will this pertain
to the track but also to systems, vehicles, structures, and other pertinent parts that make
the whole. It is common for maintenance manuals to be developed by the builder and
turned over to the owner upon completion. Sometimes these documents are not
produced because of the sense of urgency to start revenue service. Once revenue
service begins, many items are forgotten, and sometimes the forgotten items include
maintenance manuals. If proper audits and good quality control were maintained during
the construction phase, this should not be the case.
• Final Inspection—the owner should take part in the final inspection and acceptance. Only
after any discrepancies have been resolved should revenue service begin and the
maintenance group take over. The maintenance group should not be left with the task of
completing punch list items.
• Satisfying NCRs (Non-Conformance Reports)—any NCRs that were generated during
the course of the construction must be signed off on and accepted by the engineer prior
to acceptance and release of any retention money to the contractor. Refer to Chapter 13
for more detail about NCRs. A good QC program will track NCR disposition and put up
red flags if not satisfied during a reasonable amount of time.
Safety is more than just important, it is essential. Safety must both precede and be concurrent
with any actual maintenance work. Readers who are familiar with railroad engineering and
maintenance organizations know how they invariably start any activity, even a meeting within an
14-3
office, with a safety briefing. The purpose of the briefing is to make certain that everybody
understands the activity to be performed, the procedures for doing it in a safe and approved
manner, and, in the event of an emergency, what to do to minimize injury or other harm.
Following that example, this discussion on rail transit system maintenance will be prefaced with a
discussion of safety.
Maintaining the light rail transit line is distinctly different from building it because many
maintenance activities must be conducted during train operations. The approach toward safety
therefore needs to be different as well. Roadway worker protection has been an important topic
in the industry with recent changes and modifications. Understanding how the railway works and
how to be safe when working on the railway are paramount to the safety of every person.
The track designer must understand how people will maintain the track and the personal safety
procedures they will follow and then consider whether it may be necessary to include
infrastructure or systems features that will facilitate their safety. Protection of on-track workers
from approaching trains can take many forms depending on the configuration of the work zone,
the speed of approaching trains, and the type of work being done. At one extreme is
implementing temporary “trip stops” to absolutely stop a train if it enters a work zone. More
common is a simple line-of-sight procedure using flaggers who warn of an approaching train,
somewhat similar to how highway crews are protected during maintenance work. Determining
which protection is appropriate for various types of work is the decision of the owner and will
typically be codified in written procedures. Issues to be addressed by the procedures include
questions such as whether the maintainers will be permitted to work on live track, and, if so, how
they will be protected from being hit by a train. Training of the workers in the proper procedures
to follow and the possible dire consequences of not abiding by the rules is paramount.
Persons that observe train movement and are in contact with the dispatcher are commonly called
flaggers. Their sole responsibility is to ensure that the work crew is safe from passing trains. They
need a place to stand where they will have clear sight of both an approaching train and the work
zone. They and the workers also need a place to clear up from a passing train. The engineer must
give this some thought when designing a system in order to build in clearance areas and identify
no-clearance zones. A simple niche in the wall could prevent someone from getting hit by a train.
FRA 49CFR214 lays out rules for the safety of “roadway workers” on any system connected to
the general railroad system. Agencies subject to FRA oversight must adhere to 49CFR214, or
fines can be imposed. While, strictly speaking, these rules may not be legally applicable to a
given agency’s LRT operation, they do represent “good practice.” The track designer should
therefore read this document as well as similar APTA-recommended standards to gain additional
understanding and knowledge of how the system must be maintained. This should lead to the
incorporation of system features that foster a safe working environment and facilitate
maintenance activities.
14-4
Mitigating risk to a safe level will reduce accidents. Thinking about what could happen might just
save someone’s life. Having an action plan for every conceivable problem that could go wrong
may get all the workers home safely to their families.
In some cases, a work zone can be viewed prior to actual maintenance being performed. This is
a good idea that will help develop good work plans and allow the proper tools to be available
during the work outage. For example, if a tie is to be changed and the workers arrive on the site
to find a piece of loose rail in the way, they will need a tool (rail tongs) to get the loose rail out of
the way that they may not have brought with them (because it is not necessary for changing a
tie). Now a worker must leave the safe work zone and retrieve rail tongs. This wastes valuable
track time as well as worker time. In order to prevent this, a good foreman would have inspected
the work zone, possibly by riding a revenue train the previous day, and thereby discovered that
rail tongs would be required for this task.
What constitutes a safe person? If an individual answers positively to five or more, they are
relatively safe. Less than five could be an unsafe person, and no positive responses are an
accident waiting to happen. We only offer this as general knowledge.
Only now, after discussing safety above, can we let the reader “get out on the railroad.” Much of
this is identified in the APTA track maintenance standards, which are patterned after the Federal
Railroad Administration’s Track Safety Standards, also known as 49 CFR Part 213. The FRA
document applies only to those agencies under its jurisdiction. Whichever document is used, the
designer should be familiar with it. The discussion below only briefly mentions some inspection
activities and priorities.
On railroads and on parts of rail transit routes that are subject to FRA regulations, the frequency
of inspection is typically based on the speed of trains, which in turn identifies a class of track.
The FRA Track Safety Standards then identify an inspection frequency based on that track
classification. No similar regulations apply to tracks that are not under FRA oversight. However,
APTA’s document RT-S-FS-002-02, Standard for Rail Transit Track Inspection and Maintenance,
14-5
stipulates that tracks used in revenue service should be inspected at least once a week and that
other tracks should be inspected monthly. An interval of at least 3 but not more than 11 calendar
days must elapse between inspections. In general, for the maximum speeds at which light rail
trains typically operate, the FRA rules and the APTA standards are consistent concerning
inspection frequency. However, rail transit systems that operate discrete track segments at
greater than 60 mph [97 km/hr] might consider following the FRA requirement for Class 4 track,
which requires twice-weekly inspections.
This list is a valuable tool for the maintainer. One would like to think they could do everything right
now, but that is not reality. Therefore, a priority list would be established and conveyed to the
maintainers for action.
14.5.3 Qualifications
Both the FRA and APTA have developed guidelines to qualify people to inspect track and to
oversee the performance of track maintenance tasks. The FRA has established a third
classification for persons who are qualified to maintain and supervise work on CWR. This third
category has a training component and experience levels since improper maintenance and
inspection of CWR has led to serious accidents and fatalities on railways. Understanding how
CWR reacts and how the forces due to temperature change and train dynamics must be
restrained is imperative. The engineer must have a full and complete understanding of this also.
The following discusses maintenance activities unique to each trackform. Writing a maintenance
manual may sometimes be the responsibility of the designer. Since each agency may have its
own unique character, some generic maintenance activities for certain trackforms will be
discussed as listed below.
A maintenance-of-way program requires appropriate equipment to fulfill its function. With the
exception of LRT/streetcar lines that are 100% embedded track, much of this equipment will need
to be designed to ride on the track. This will include hy-rail vehicles that can run on both the
highway and the rails and machines that are rail-only. Because the equipment requirements for
LRT maintenance can vary widely, this Handbook will not attempt to address the details of the
many types of equipment that might be included in a comprehensive maintenance-of-way
program. However, the following critical issues should be kept in mind when specifying and
procuring M/W equipment.
• The maintenance vehicles must be compatible with the track. This seems obvious, but is
often overlooked. The wheel contour and wheel gauge for M/W equipment should
ordinarily be identical to that adopted for the light rail vehicles. More than one project has
belatedly discovered that on-track maintenance equipment that was manufactured in
strict accordance with AREMA recommendations doesn’t fit a track structure designed
14-6
around transit parameters. Differences in back-to-back wheel gauge and the resulting
incompatibility with narrow flangeways are distressingly common occurrences.
Maintenance-of-way equipment with a long wheelbase may not be compatible with sharp
radius curves. Since widening the flangeways to accommodate the rare operation of
some machine with a long wheelbase would likely be detrimental to the compatibility of
the track with light rail vehicles, it may be necessary to either prohibit such equipment
from certain curves or procure an entirely different machine that is compatible with the
track.
• The track must be compatible with the maintenance vehicles. This is typically an issue
with hy-rail maintenance trucks. On one project, it was belatedly discovered that the
light-duty material used for walking surfaces on pedestrian crossings was being crushed
by the heavy rear tires of the maintenance department’s hy-rail trucks. On another
project, an extension to a system’s existing light rail line, it was discovered that the
hydraulic jacks on the transit authority’s tamper would not clear the station platforms
along the new track. Restraining rails that are elevated more than about ½ inch [13 mm]
above the running rails can be problematic, as they can lift the rear tires of hy-rail trucks,
which then lifts the rail wheels. Since this would occur in a sharp curve (hence the
presence of the restraining rail), the rail wheels can then climb over the rail and derail.
14-7
Corrugation is characterized by two main parameters. One is the length of the “waves.” This is
measured from crest to crest or valley to valley. Depending on the causes of the corrugation, the
wave length can be anywhere between ½ inch [1 cm] to 3 feet [1 meter]. The other parameter is
the depth. A good straight edge and taper gauge can measure this dimension. Each property
should have some criteria for these parameters. In many cases, the people in the neighborhood
will bring this roaring rail noise to the transit agency’s attention.
The stiffness of the track (track modulus) plays a role in corrugation also. If the track is either
too stiff or too soft, corrugations may develop. Finding the right stiffness for the loads imposed
on the track is a challenge. The track designer should have a good understanding of this before
selecting or specifying a rail fastener or setting the fastener spacing; see Chapter 9 for
additional guidance on this topic. The track stiffness will be different in switch areas and the
frog area also.
It is the maintainer’s job to identify corrugation and implement corrective action before it becomes
significant and causes wheels to jump or flutter. Left uncorrected, corrugations only get worse as
their vertical amplitude increases. The resulting oscillations in the vehicle trucks will also cause
the corrugation pattern to progress further and further down the track.
Rail grinding is commonly done to restore the original contour or make a new profile to better
suit the wheels. The key to success is to match the wheel to the rail whereby the contact patch
is optimized for proper load transfer. Besides the elimination of corrugations and the
associated noise and vibration, other benefits to rail grinding include removal of rail defects that
are initiated by rolling contact fatigue of the rail steel, lower rolling resistance, improved
traction, and reduced energy consumption. While it seems counterintuitive, removing rail steel
through grinding actually extends the life of the rail, because rail wear rates are reduced by
optimizing the rail/wheel interface. Grinding will also produce better contact between the rail
and wheel to both reduce electrical resistance for the negative return path and improve
shunting for the signal system.
14-8
valleys. Careful monitoring of corrugation growth rates are necessary to determine an optimum
grinding interval, which may be the time required for the corrugation amplitude to increase by a
factor of two or three relative to some reference condition. Corrugation growth is largely
exponential.
Very few transit agencies have the resources to own and maintain their own rail grinding
equipment. Instead, most agencies procure rail grinding services from specialty contractors.
This requires the preparation of a detailed contract specification. Whether the specification
defines specific methods or is performance based, it must convey a message tailored to the
needs of the individual LRT system. Since LRT systems vary a great deal, it is nearly impossible
to suggest that one size fits all.
• The characteristics of the rail system, particularly any factors that might impact the grinding
contractor’s equipment.
• The desired end product. This part could vary considerably depending on the owner’s
objectives, previous experiences with rail grinding, and the degree to which the owner wants
to depend on the contractor’s expertise to “do the job right.”
Rail system characteristic factors that should be defined include the following:
• Maximum grades and minimum curvature. This is best addressed by including complete
plan and profile drawings as an appendix to the specification.
14-9
• Time of day limitations. Can track time be made available during the day or will all of the
grinding need to be done on nights and weekends? How soon after the last train can the
contractor get started? How much time must be allowed at the end of a work shift to
clear the track?
• Contractor storage location(s). Like all contractors, the rail grinding contractor will need
laydown space for the rail grinding train and off-track equipment and materials. The
maximum traveling speed of most rail grinding trains is relatively slow, and the contractor
will generally prefer to maximize his “spark time” by not running to and from the system’s
main storage yard at the end of his shift. Pocket tracks or spurs where the grinding train
can be stored when not in use can significantly increase the contractor’s productivity and
decrease costs.
• Environmental conditions. What are the maximum tolerable noise levels that will be
allowed during the work? Will they vary by time of day and/or location?
• The rail surface finish tolerances they will be expected to produce. These metrics are
often understated, especially by owners and consultants who have insufficient experience
in rail grinding work.
• Will the third rail or overhead catenary be energized while the contractor is performing the
work?
• Must the grinding equipment have the ability to shunt the rails?
The rail grinding contractor should make several detailed submittals prior to mobilizing equipment
to perform the work. Items that these submittals address could include the following:
• A detailed inspection report of the existing track, defining the existing condition of the rails
with respect to corrugation and wear and highlighting any areas that may need special
attention. This report may have been prepared in advance by the owner or a consultant
who has been retained by the owner. Even so, the rail grinding contractor should be
required to conduct an inspection and confirm whether this inspection corroborates the
owner’s or owner’s consultant’s findings.
• A detailed work plan describing how the contractor intends to perform the work. This
would include the following:
14-10
− Any limitations the equipment may have, such as the minimum radius the
equipment can traverse and whether it can operate on non-standard gauge track.
− Environmental controls such as the dust collection, fire protection, and spark-
arresting systems, as well as the system for collection and disposal of rail
grinding debris. The debris might be considered hazardous material in some
jurisdictions, and proper disposal is mandatory. The contractor should explain
how the drainage system will be protected from becoming clogged with grinding
stone particles and metal dust and also specifically explain how the metal dust
will be prevented from breaching the signal system or creating a path for stray
current.
− How the contractor intends to perform the work. This would include the size,
type, and number of grinding stones to be used, including the grit size, the
number of passes that will be made on each discrete segment of track, the pass
speed, and the number of facets that will remain on the rail head at the
completion of the work. The size of the grit in the grinding stones is an important
issue for rail transit. Rail grinding on freight railroads can generally use stones
with a fairly coarse grit since the heavy axle loadings will smooth the surface
fairly quickly. The same coarse finish on a transit line might take months to wear
away, especially with hardened rail. Moreover, during that wearing-in period,
noise levels could actually be increased, and the periodic grinding marks in the
running surface could initiate new patterns of corrugation.
− A schedule for when the work will be performed in each discrete segment of the
route, including how the work will interface with rail transit operations.
− A description of and references for previous similar work performed on other rail
transit properties.
• Rail grinders will produce sparks that can cause fires or damage, including eye injuries if
bystanders are watching the work. Since LRT rights-of-way are typically much closer to
the general public than freight railroad tracks, special measures are necessary to protect
the public.
• Rail grinding is a noisy operation. This issue must be addressed as part of the bid
documents for procurement of rail grinding services; otherwise, the operation might be
shut down on the first night by neighbors’ complaints.
• Rail grinding can be especially challenging on metro rail systems that use a third contact
rail for traction power distribution since metallic grinding dust can cause leakage around
insulators on both the negative and the positive sides of the traction power circuit.
14-11
• Rail grinding in embedded track has unique challenges; see Article 14.6.3.8 for a detailed
discussion of these issues.
14-12
The APTA documents are generally in the same format as the FRA regulations but also include a
color-coded priority system to offer guidelines on severity. The APTA documents are voluntary
standards and, as noted earlier, are necessarily generic because of the wide variation in transit
system infrastructure and systems from one transit agency to another.
14-13
At one LRT system in Germany, a specially equipped rail grinding vehicle also includes a
flangeway scraping tool with a vacuum system for cleaning the flangeways of groove rails. Such
a system might not work as well on embedded tracks using tee rail because the scraping tool
might damage the pavement and the rail boot or other rail isolation system. The LRT system in
Calgary has a vacuum truck that is designed specifically to clean flangeways.
14-14
The concrete surface must be saw cut on either side of the rail a distance that will expose the
fastening system when the concrete is removed. The concrete is then chopped out to a depth
near the base of rail. The elevation is already preset by the elevation of the existing concrete
under the rail; therefore, the concrete can be rough adjacent to the base. The fasteners are
exposed and can be removed. The boot can be cut back to where the rail is to be cut, allowing
enough room for a repair cuff to be installed. The thermite weld and the rail boot repair cuff will
both require concrete demolition to well below the base of rail. Hydro-demolition is sometimes
convenient for that purpose, but the area must be thoroughly dried before the thermite weld is
made. After the rail is cut, the old rail can be removed as well as the old boot. The concrete
surface should be cleaned at this time and a visual inspection performed. Any damaged coatings
on exposed reinforcing steel will need to be patched. The new piece of rail can be booted and
set into the seat area established by the old rail. Fasteners can be reinstalled, welds made, and
the boot cuffed and tested. After a quality control check, the concrete can be replaced and
revenue service restored.
14-15
Many light rail systems in Europe have specially equipped rail vehicles for performing
preventative maintenance rail grinding. These cars are often older high-floor articulated
vehicles that are no longer being used for passenger service. The center truck on such cars is
equipped with grinding blocks that take the place of the magnetic track brakes. Hydraulic
pistons can maintain a constant downward pressure on the grinding stones. These rail grinding
cars are run over the system on a regular schedule, often running at relatively high speeds
between revenue service trains during daylight hours. The cars are often equipped with tanks
to spray cooling water on the grinding stone as well as a vacuum system for collecting the
spray water and any grinding residue. The routine use of such block grinding cars has been
proven to defer the need for corrective grinding with conventional rotary rail grinding equipment
and, in some cases, prevents corrugations from ever reaching a level where corrective grinding
is even necessary.
Curiously, many legacy North American streetcar systems used similar equipment in times past,
but the practice fell out of favor for reasons that are no longer clear. It may have been simply a
matter of the equipment getting old and difficult to maintain. As of 2010, at least one North
American LRT system was going to be procuring modern block grinding equipment based on
current European practices.
Direct fixation track is an “open” trackform with nearly all of the major components easily visible
and accessible for inspection and maintenance. Other open trackforms include ballasted track,
some forms of grass track, and open deck bridge track. The paragraphs below will discuss
various maintenance activities that are applicable to direct fixation track and may also be
applicable to other trackforms as well.
While the use of CWR eliminates most bolts in rail, direct fixation track is loaded with other bolts.
These include rail fastener anchor bolts, emergency guard rail bolts, and numerous nuts and
bolts within special work. Systems incorporating a contact rail instead of overhead catenary will
have dozens of other types of bolts. Every one of these bolts is subject to loosening. If one bolt
becomes loose, the adjacent bolts must restrain the dynamic forces triggering them to loosen or
break in turn. New track is particularly prone to bolt loosening until such time as mating parts
wear in and seat to each other.
The designer can assist in this by avoiding designs that incorporate threaded fastenings in
inaccessible locations where both inspection and tightening are difficult.
14-16
Designers should carefully consider whether particular trackway environments might not be
suitable for some products (such as a particular rail clip design) due to environmental conditions,
loadings, or both. Prior to soliciting bids for such items, the service environment where the
product will be used should be made very clear to potential vendors and their advice solicited
concerning the most appropriate products to be used. The manufacturer’s recommendations
concerning installation, inspection, and maintenance should be incorporated in the system
maintenance manuals and closely followed by maintenance staff.
14.6.4.3 Housekeeping
Direct fixation track can provide extremely long service if properly constructed and maintained. A
significant part of that maintenance is simple housekeeping. Trackways are dirty environments
and that dirt needs to be washed off the track at frequent intervals. For ordinary direct fixation
track out in the open, normal precipitation is sufficient to keep the track clean. But tracks in
tunnels obviously do not see rainfall and tend to accumulate all sorts of dust and dirt. If the tunnel
is damp, this material tends to be corrosive and attacks the rails, rail fasteners, and other
appurtenances.
LRT tunnels in regions that get snowfall and see heavy use of de-icing chemicals are particularly
susceptible to extremely severe trackway corrosion. The LRVs will pick up corrosive slush at
road crossings and embedded track segments and carry that material into the tunnels where it
will melt and land on the track system. This corrosive brine not only initiates corrosion
chemically, it provides paths for stray currents, causing even more accelerated corrosion.
Several LRT systems have needed to completely replace rails and rail fasteners in such tunnels,
while identical construction in other areas of those systems that were not subject to brine attack
remain in nearly new condition.
The primary defense against this sort of problem can be relatively simple. Completely washing
tunnel trackwork with the equivalent of a “fire hose” on a regular basis (say twice a year) can
remove the brine and other contaminants before they can cause significant corrosion. The debris
can be washed toward tunnel drains where solid particles should be collected rather than being
passed through to municipal sewer systems.
Direct fixation tracks in LRT stations tend to accumulate traction sand beneath the rails and
between the rail fasteners, sometimes mixed with lubricants that drip from the vehicles. This
compound can also cause corrosion and stray current problems and should be power washed
away on a regular basis.
14-17
It is also imperative that these activities be documented. If a rail break occurs near this location
again, then the rail may need to be de-stressed again for a much longer length. Refer to Chapter
13 for more detail on adjusting CWR for optimal zero thermal stress.
14-18
every fastener, and torque the hold-down bolts to the correct torque. While the fastener is not
there, it is wise to inspect the concrete under the fastener to determine what caused the fastener
to fail. If any voids are found under the fastener, they should be repaired before installing the new
fastener, or the new one will become broken in a period of time.
Sometimes it may be determined that the anchor inserts sit above the plane of the concrete
surface, causing point loads directly on top of the inserts. If this is the case, the top of the inserts
should be ground flush with the surface of the concrete and then epoxy paint applied to the bare
steel.
Fasteners that are anchored using threaded rods rather than female inserts require that the rail
be raised very high in order for the defective fastener to be removed. This requires the unclipping
of much more rail, which could result in the rail bucking in hot weather when compressive forces
in the rail are high. For this reason alone, the use of female inserts rather than threaded rod
anchors is preferable. In all cases, it is wise to do this activity when the rail temperature is below
the neutral temperature. In the maintenance manual for the system, stipulate the maximum
number of rail clips in a row that may be removed.
Several rail transit systems have needed to perform out-of-face replacement of long segments of
direct fixation rail fasteners, usually in track segments constructed in the 1970s or 1980s. Many
of the rail fasteners used at that time were inferior designs that did not hold up well under service.
These out-of-face replacement projects have more in common with new construction than with
ordinary maintenance work.
14-19
Many rail transit maintenance organizations, particularly on smaller systems, will not have the
proper equipment and trained personnel necessary to correctly and efficiently perform out-of-face
replacement of CWR. In such cases, it may be an activity best assigned to a qualified track
contractor.
Ballasted track, like direct fixation track, is an “open” trackform; thus, many of the maintenance
activities described above for direct fixation track will also apply to ballasted track. The
paragraphs below will address some of the activities that are unique to ballasted track.
14-20
Replacing timber ties is relatively simple because once the spikes have been pulled, the tie can
be pulled out to the side without raising the rail. This assumes there is sufficient lateral clearance
on one or both sides of the track to extract the old tie and insert the new one. If not, it may be
necessary to remove ballast and then respace several ties tightly while the defective tie is rotated
90 degrees and lifted out from between the two rails. The new tie is then installed, the tie spacing
is restored in the reverse order, the ballast is reinstalled, and all disturbed ties are tamped. This
is a tedious process that requires a lot of manual labor and, hence, is very expensive. For this
reason, curbed ballasted track sections are undesirable. So as to minimize future tie replacement
costs, it should be possible to extract and replace ties from at least one side of the track,
preferably without fouling the other track.
Concrete tie replacement can be more challenging because the shoulder embedded in the
concrete tie typically requires the rail to be raised by 2-inches [50 mm] so the tie can be
extracted. The rail clips on the adjacent ties will need to be removed so the rail can be lifted
without disturbing the bedding of the adjacent ties in the ballast, thereby risking “humping” the
track. As with timber ties, spot replacement of individual ties in a curbed ballast section can be
tedious and expensive, especially since the heavier concrete ties cannot be handled by manual
methods.
14-21
signals and must not interfere with track inspection or maintenance. There are professional
services that can be contracted in order to keep vegetation from becoming a defect. The track
alignment designer should attempt to configure crossings so that the sight triangles remain clear.
Sometimes, other disciplines on the design team, not understanding the safety and maintenance
issues involved, will wish to plant vegetation in locations where it would become a problem for the
maintenance organization.
14-22