THIS MONTH’S QUESTION

Did W. Edwards Deming What could be the most important


invent the plan-do-check- Study the results. What accomplishments of the team? What
did we learn? What changes might be desirable? What
act (PDCA) cycle? 4 1
can we predict? data are available? Are new observations
needed? If yes, plan a change or test.
Decide how to use the observations.

OUR RESPONSE

Observe the effects 3 2 Carry out the change or test decided upon,
o, Deming did not invent or of the change or test.
preferably on a small scale.

N
originate PDCA; it emerged
in Japan. Deming’s earlier
Step 5. Repeat step 1, with knowledge accumulated.
teaching in Japan may have Step 6. Repeat step 2, and onward.
influenced PDCA, but he never
fully embraced it. He later published
the plan-do-study-act (PDSA) cycle New Economics,2 will help. In the book, between PDCA and PDSA, but the
and credited Walter A. Shewhart. the Shewhart Cycle figure is updated to common theme of the scientific method
Attributing PDCA to Deming is a a now recognizable form, complete with persists. PDCA has prevailed, while
common misconception. An informal letters P, D, S and A (see Online Figure 1, Deming arguably has become the
poll of LinkedIn users, conducted in which can be found on this department’s most recognizable name in quality.
mid-2020, found that 72% of respon- webpage at qualityprogress.com). The Misattribution and misunder-
dents thought it was Deming’s idea. new form carries the title “The Shewhart standing of the improvement cycle
Analysis of the poll data indicated the Cycle for Learning and Improvement; the is pervasive and not new. Deming
misunderstanding spans across conti- PDSA Cycle.” addressed it so succinctly in a footnote
nents, industries and job functions. Given Deming’s evidence, it’s fair in Out of the Crisis that it is reasonable
Some may find the distinction trivial, to credit Shewhart with the origin of to believe he was aware of the issue
and it is fair to admit that understanding PDSA, but it’s important to recognize more than 35 years ago:
the origin of the PDCA cycle has little that all continuous improvement cycles “I called it in Japan in 1950 and
or no effect on the application of such draw on fundamental concepts from onward the Shewhart cycle. It went
concepts. Still, it is a point of heritage— much earlier. The underlying scientific into immediate use in Japan under the
heritage concerning important forebears method is found in Deming’s PDSA name of the Deming cycle, and so it has
of our field. and the Japanese PDCA cycles. The been called there ever since.”4
Deming’s work is a good place to hypothesis-experiment-evaluation This was Deming’s attempt to set the
seek clarity. In his 1986 canonical process, written by Francis Bacon in record straight, and we do the same.  QP
quality classic Out of the Crisis,1 there is 1620, 3 is a common ancestor linking all
EDITOR’S NOTE
a figure labeled “The Shewhart Cycle” continuous improvement cycles to the References listed in this department can be found on
(see Figure 1). It doesn’t yet carry the scientific method. the department’s webpage at qualityprogress.com.
catchy PDCA title (nor the PDSA varia- Debate persists on the differences
tion), but identifies a cycle of planning, between PDCA and PDSA, but the This response was written by W. Frazier Pruitt,
iStock.com/orsonsurf

doing, checking and acting, and credits entwined lineage suggests the differ- senior engineer and quality assurance supervisor,
a 1939 work by Shewhart for the idea. ences may be more trivial than the Southco Inc., Rochester, NY, and S.M. Waqas Imam,
To further connect the dots to the proper attribution of the terms’ origins. management system consultant, Exoexcellence (SMC)
PDSA cycle, Deming’s 1994 book, The There are arguments for uniqueness Pvt. Lt , Karachi, Sindh, Pakistan.

6 || QP || April 2021