You are on page 1of 3

Reliance v. Daewoo [CommRev] - [LCTR][LC] from Daewoo.

The SC agrees with the CA that the parties had a meeting of


13 the minds with respect of the subject matter of the contract, the price, and
[G.R. No. [Dec. 17, [Feliciano] [JTSY] other provisions. The opening of the LC in favor of Daewoo was an
100831] 1993] obligation of Reliance, and the performance of that obligation was a
Petitioner/s: Respondent/s: condition for enforcement of the reciprocal obligation of Daewoo to ship
Reliance Commodities Inc. Daewoo Industrial Co., Ltd. the subject matter of the contract.
Recit Ready Summary The Central Bank of the Philippines required, among others, the need of permits
or clearances from appropriate government agencies as one of the requirements
Reliance and Daewoo entered into a contract of sale on Jan. 9, 1980, under for opening a LC. Reliance entered into a transaction to import foundry pig iron,
which Daewoo undertook to deliver 2,000 metric tons of foundry pig iron to which is a regulated commodity that requires permission from the ISA, the
Reliance for USD 404,000.00, but the cargo it delivered was short 135.655 appropriate government agency. The record shows that the opening of the LC
metric tons. They entered into another contract for another 2,000 metric tons on became difficult because Reliance already exceeded its foreign exchange
July 31, by which Daewoo undertook to reduce the price, and was to be paid by allocation. As a rule, when the importer has exceeded the foreign exchange
an irrevocable sight letter of credit (LC). Reliance applied for an LC with allocation, the application will be denied; but, the ISA can reconsider on a case-
Chinabank, which application was endorsed to the Iron and Steel Authority for by-case basis. Thus, ISA required Reliance to support its application by
approval but was denied (because Reliance had already exceeded its foreign submitting purchase orders from end-users for the same quantity that it wished
exchange allocation for the year 1980, and was unable to present enough to import (but it was only able to present purchase order for 900 metric tons, not
purchase orders from end-users). Daewoo rejected the proposed LC because the total 2,000). For having exceeded its foreign exchange allocation and failed
the covered quantity fell short of the required tonnage, and Reliance to secure end-users purchase orders equivalent to 2,000 metric tons, only
withdrew the application (Daewoo subsequently sold the 2,000 metric tons to Reliance should be held responsible.
another buyer at a further reduced price). Reliance wrote Daewoo asking it to Daewoo had the right to demand compliance with the terms of the basic
pay for the short shipment; when Daewoo ignored the letter, Reliance filed suit. contract, and had no duty to accept any unilateral modification of that
Daewoo counterclaimed, claiming that Reliance was guilty of breach of contract. Compliance with Philippine legal requirements was the duty of
contract when it failed to open a LC per the July 31 contract. The trial court Reliance, not Daewoo, and the non-opening of the LC was due to
ruled that Daewoo had to pay for the short delivery, and Reliance was liable for Reliance’s failure to comply with its duty under the contract. The failure of
breach of contract when it failed to open a LC and thus had to pay the buyer seasonably to furnish an agreed LC is a breach of contract
damages; the CA affirmed. between buyer and seller. When the buyer fails to open a LC as stipulated,
the seller or exporter is entitled to claim damages for such breach.
I: If the importer fails to open a LC in favor of the exporter, will he be liable for Damages may include, in appropriate cases, the loss of profit which the seller
damages? YES would reasonably have made had the transaction been carried out.

A LC transaction is a composite of at least three distinct but interrelated Facts + Procedural History
relationships:
a. Between the party applying for the LC (the account party or buyer or 1. Jan. 9, 1980 – Reliance and Daewoo entered into a contract of sale, under
importer) and the party for whose benefit the LC is issued (the which Daewoo undertook to deliver 2,000 metric tons of foundry pig iron to
beneficiary or seller or exporter). In this contract, the former (Reliance) Reliance for USD 404,000.00. Pursuant to this, Daewoo shipped 2,000
agrees to pay money to the latter (Daewoo) metric tons of foundry pig iron, but upon arrival in Manila, the cargo was
b. Between the account party and the issuing bank. Under this contract, the found to be short 135.655 metric tons (only 1,864.345 metric tons were
former applies to the issuing bank for a specified LC and agrees to discharged and delivered to Reliance)
reimburse the bank for amounts paid by that bank pursuant to the LC 2. May 2, 1980 – Reliance and Daewoo entered into another contract of sale.
c. Between the issuing bank and the beneficiary, in order to support the Daewoo acknowledged the previous short shipment and bound itself to
contract under (a) to pay certain monies to the latter reduce the price by USD1 to USD2 per metric ton. However, this contract
The issue in this case refers to the first relationship (between buyer-importer and was not consummated and later superseded
seller-exporter). Examining the terms of the July 31 contract, the SC concludes 3. July 31, 1980 – Reliance and Daewoo entered into a third contract, which
that the opening of a LC upon application of Reliance was not a condition provided that Daewoo would send 2,000 metric tons at USD 190.30 per
precedent for the birth of the obligation of Reliance to purchase foundry pig iron metric ton (total price USD 380,600.00), to be paid by an irrevocable sight

ALS B2021 1
letter of credit. buyer or importer) and the party for whose benefit the LC is
4. Aug. 1, 1980 – Reliance applied with Chinabank for a Letter of Credit (LC) issued (the beneficiary or seller or exporter). In this contract,
worth USD 380,600.00 in favour of Daewoo. The application was endorsed the former (Reliance) agrees to pay money to the latter
to the Iron and Steel Authority (ISA) for approval but was denied; Reliance (Daewoo)
was instead asked to submit purchase orders from end-users to support its b. Between the account party and the issuing bank. Under this
application for a LC but was unable to do so. Whatever the exact amount of contract, the former applies to the issuing bank for a specified
the purchase orders was,1 Daewoo rejected the proposed LC because the LC and agrees to reimburse the bank for amounts paid by that
covered quantity fell short of the contracted tonnage, and Reliance bank pursuant to the LC
withdrew the application for the LC c. Between the issuing bank and the beneficiary, in order to
5. Daewoo subsequently learned that Reliance failed to open the LC as support the contract under (a) to pay certain monies to the
stipulated in the July 31 contract because it exceeded its 1980 foreign latter
exchange allocation as early as May, and because of the failure of Reliance • The issue in this petition relates primarily to the first contractual
to comply with its undertaking, Daewoo sold the 2,000 metric tons to a relationship: that between the account party or importer Reliance
different buyer at a lower price and the beneficiary or exporter Daewoo
6. Sept. 3, 1980 – Reliance, through counsel, wrote Daewoo requesting • Examining the terms of the July 31 contract, the SC concludes that
payment of PHP 226,370.48, representing the value of the short delivery of the opening of a LC upon application of Reliance was not a
135.655 metric tons of foundry pig iron under the January 9 contract condition precedent for the birth of the obligation of Reliance to
7. Daewoo did not pay, so Reliance filed suit. Daewoo counterclaimed for purchase foundry pig iron from Daewoo. The SC agrees with the
damages, contending that Reliance was guilty of breach of contract when it CA that the parties had a meeting of the minds with respect of the
failed to open a LC as required in the July 31 contract subject matter of the contract, the price, and other provisions. The
8. The trial court ruled that (1) the July 31 contract did not extinguish failure of Reliance to open the appropriate LC did not prevent the
Daewoo’s obligation for the short delivery 2 and (2) Reliance is liable for birth of the contract nor extinguish it. The opening of the LC in favor
breach of contract for failure to open the LC and thus has to pay actual of Daewoo was an obligation of Reliance, and the performance of
damages3 that obligation was a condition for enforcement of the reciprocal
9. Reliance appealed the 2nd part of the decision, but the CA denied obligation of Daewoo to ship the subject matter of the contract. But
the contract itself between Reliance and Daewoo already existed
Issue/s Ruling and was enforceable
1. Does the failure of the importer (Reliance) to open a letter 1. Yes • The Central Bank of the Philippines required, among others, the
of credit on the date agreed upon make him liable to the need of permits or clearances from appropriate government
exporter (Daewoo) for damages? agencies as one of the requirements for opening a LC
Rationale • Reliance entered into a transaction to import foundry pig iron, which
1. The failure of the importer to open a LC on the date agreed upon is a regulated commodity that requires permission from the ISA, the
makes him liable to the exporter for damages appropriate government agency. Prior to the issuance of the permit,
the ISA asks the importer to comply with certain requirements
• The nature of a letter of credit was extensively discussed in Bank of • The record shows that the opening of the LC became difficult
America v. CA. It is one of the modes of payment by which because Reliance already exceeded its foreign exchange
commercial banks sell foreign exchange to service payments allocation. As a rule, when the importer has exceeded the foreign
• A letter of credit transaction is thus a composite of at least three exchange allocation, the application will be denied; but, the ISA can
distinct but intertwined relationships, each relationship being reconsider on a case-by-case basis. Thus, ISA required Reliance to
concretized in a contract: support its application by submitting purchase orders from end-
a. Between the party applying for the LC (the account party or users for the same quantity that it wished to import (but it was only
able to present purchase order for 900 metric tons, not the total
1
Reliance claimed that it was able to raise purchase orders for 1,900 metric tons, 2,000). For having exceeded its foreign exchange allocation and
failed to secure end-users purchase orders equivalent to 2,000
but Daewoo contends that Reliance was only able to raise 900 metric tons
2 metric tons, only Reliance should be held responsible.
Daewoo has to pay Reliance PHP 226,370.48
3 • Daewoo had the right to demand compliance with the terms of the
Reliance has to pay Daewoo PHP 331,920.97

ALS B2021 2
basic contract, and had no duty to accept any unilateral
modification of that contract. Compliance with Philippine legal
requirements was the duty of Reliance, not Daewoo, and the non-
opening of the LC was due to Reliance’s failure to comply with its
duty under the contract
• The failure of the buyer seasonably to furnish an agreed LC is a
breach of contract between buyer and seller. When the buyer fails
to open a LC as stipulated, the seller or exporter is entitled to claim
damages for such breach. Damages may include, in appropriate
cases, the loss of profit which the seller would reasonably have
made had the transaction been carried out

Disposition

Petition denied, CA affirmed


Annex: discussion of nature of letter of credit

A letter of credit is a financial device developed by merchants as a convenient


and relatively safe mode of dealing with sales of goods to satisfy the seemingly
irreconcilable interests of a seller, who refuses to part with his goods before he is
paid, and a buyer, who wants to have control of the goods before paying. To
break the impasse, the buyer may be required to contract a bank to issue a letter
of credit in favor of the seller so that, by virtue of the letter of credit, the issuing
bank can authorize the seller to draw drafts and engage to pay them upon their
presentment simultaneously with tender of documents required by the letter of
credit. The buyer and seller agree on what documents are to be presented for
payment, but ordinarily they are documents of title evidencing or attesting to the
shipment of the goods to the buyer.

Once the credit is established, the seller ships the goods to the buyer and in the
process secures the required shipping documents or documents of title. To get
paid, the seller executes a draft and presents it together with the required
documents to the issuing bank. The issuing bank redeems the draft and pays
cash to the seller if it finds that the documents submitted by the seller conform
with what the letter of credit requires. The bank then obtains possession of the
documents upon paying the seller. The transaction is completed when the buyer
reimburses the issuing bank and acquires the documents entitling him to the
goods. Under this arrangement, the seller gets paid only if he delivers the
documents of title over the goods, while the buyer acquires the said documents
and control over the goods only after reimbursing the bank.

ALS B2021 3

You might also like