% Planned Description of Works % Actual Accomp. Remarks Accomp 1. GENERAL REQUUIREMENTS 1.90% 1.90% 2. EARTHWORKS 5.00% 5.00% 3. CONCRETE WORKS 7.28% 7.00% 4. REINFORCING STEEL BARS AND TIE WIRE 7.13% 7.00% 5. FORMWORKS AND SCAFFOLDINGS 9.20% 9.00% 6. STRUCTURAL STEEL WORKS 31.60% 31.60% 7. MASONRY WORKS 8.90% 8.00% 8. DOORS AND WINDOWS 4.30% 3.50% 9. STEEL WORKS 8.60% 7.30% 10. ROOFING WORKS 2.60% 2.40% 11. CARPENTRY WORKS 3.10% 2.00% 12. ELECTRICAL WORKS 1.80% 1.00% 13. PLUMBING WORKS 1.40% 1.00% 14. SANITARY WORKS 2.00% 1.50% 15. PAINTING WORKS 4.00% 3.00% 16. TILE WORKS 0.30% 0.10%
Total 99.10% 91.30%
Manpower Loading Weather Condition/Holiday Worked Stoppedd (Y/N) Male 8 Monday RAINY Skilled Female 0 Tuesday RAINY Male 7 Wednesday RAINY Unskilled Female 0 Thursday FAIR Total 15 Friday RAINY I. Saturday FAIR II. Sunday FAIR Other Issues and Concerns III. IV. General Contractor Project : PROPOSED 2-STOREY 6-CLASSROOMS School Name : UNIVERSITY OF EASTERN PHILIPPINES Start Date : MARCH 2, 2020 Actual Start Date : MARCH 5, 2020 End Date : Project Proponent Prepared by : JQD CONSTRUCTION & GENERAL SERVICES Noted by : Submitted to : WILBERT BRUA Date : Jan. 19 - Jan. 25, 2021 (Week 32) Sheet No. : 1 of 3 PROJECT PHOTOS
General Contractor Project : PROPOSED 2-STOREY 6-CLASSROOMS
Location : UNIVERSITY OF EASTERN PHILIPPINES Start Date : MARCH 2, 2020 0 New Start Date : MARCH 5, 2020 End Date : Project Proponent Prepared by : JQD CONSTRUCTION & GENERAL SERVICES Noted by : Submitted to : WILBERT BRUA Date : Jan. 19 - Jan. 25, 2021 (Week 32) Sheet No. : 2 of 3 PROJECT PHOTOS
General Contractor Project : PROPOSED 2-STOREY 6-CLASSROOMS
Location : UNIVERSITY OF EASTERN PHILIPPINES Start Date : MARCH 2, 2020 0 New Start Date : MARCH 5, 2020 End Date : Project Proponent Prepared by : JQD CONSTRUCTION & GENERAL SERVICES Noted by : Submitted to : WILBERT BRUA Date : Jan. 19 - Jan. 25, 2021 (Week 32) Sheet No. : 3 of 3