Professional Documents
Culture Documents
Purple Line Traction Power Study Report Rev4
Purple Line Traction Power Study Report Rev4
SIMULATION – PRELIMINARY
REPORT
OCTOBER 31, 2013 – REV: 4
2012.01.06.TP.PE.11.TPSSStudy Report-04
Traction Power System Simulation Report Revision: 4
Revision History
Table of Contents
1 Executive Summary .......................................................................................................... 5
1.1 Objectives .....................................................................................................................................................5
2 Introduction ....................................................................................................................... 8
2.1 Main parameters..........................................................................................................................................8
2.1.1 Running rails ............................................................................................................................................8
2.1.2 Substation rectifier units .........................................................................................................................8
2.1.3 Train consists and operational headway .................................................................................................8
2.1.4 Train stops ...............................................................................................................................................9
List of Figures
List of Tables
1 Executive Summary
This revision of the report details the findings from the simulation study of the Purple Line
traction power system between Bethesda and New Carrollton.
The study takes into account the latest development in Design Criteria, Design Build Technical
Requirements, track alignment, substation locations and the light rail vehicle data.
1.1 Objectives
The simulation analysis is based on the MTA Red / Purple Line Design Criteria (Reference 2)
and the Design Build Technical Requirements (Reference 10). The objective of this study is to
confirm that the proposed traction power system configuration can meet the requirements of the
Design Criteria and the Design Build Technical Requirements.
The system should be able to support 2-car train operation at AW3 load at 5 minute headway.
Under normal operation, at least 90% of all train voltage observations during simulation shall
be above the minimum vehicle voltage for full performance, i.e., 650V.
Rectifier load should be within its 100% rating for normal operation.
Rectifier load should be within its 150% rating for 2 hours for contingency operation.
Recovery Service of four sequential maximum length trains operating at maximum allowable
speeds with AW4 loads at normal LRV performance levels at three minute headways at any
location on the Mainline with simultaneous service of maximum length Trains at five minute
headways on the other track (Reference 10). The performance requirements are the same as in
contingency operation listed above.
According to the latest site surveys and drawings, the locations of substations are listed in the
following table. The number of rectifier units for the substations are also listed in the same table.
A schematic diagram for the proposed traction power system is shown in Figure 11 in Appendix
B.
Under normal operation condition, the occurrence of train voltages below 650V is 0.28%
of all train voltage observations during simulation, i.e., 99.72% of all observed train
voltages are above 650V. The minimum train voltage identified is 622V (see Fig. 1).
Under all contingency operation conditions, all train voltages are above 525V. The
minimum train voltage identified is 568V (see Fig. 2).
Under recovery operation conditions, all train voltages are above 525V. The minimum
train voltage identified is 603V (see Fig. 3).
Rail potential is less than 50V under normal operation. The maximum rail potential
identified is 39V (see Fig. 4).
Rail potential is less than 75V under all contingency operation conditions. The maximum
rail potential identified is 61V (see Fig. 5).
Rail potential is less than 75V under all recovery operation conditions. The maximum rail
potential identified is 42V (see Fig. 6).
All rectifier loads are within 100% continuous rating under normal operation. The
maximum ratio identified is 54% (see Table 4).
All rectifier loads are within 150% 2-hour rating under all contingency operation
conditions. The maximum ratio identified is 73% (see Table 4).
All rectifier loads are within 150% 2-hour rating under all recovery operation conditions.
The maximum ratio identified is 73% (see Table 4).
1.5 Conclusions
The system configuration presented in this report conforms to the design criteria and the design
build technical requirements.
2 Introduction
The vehicles are based on 95 feet length per car. Maximum operation speed is 55 mph
(Ref.1 as listed in Appendix A);
Traction power is supplied by DC rectifiers at 750V nominal voltage (Ref.2);
The OCS has 6 segments, using Fixed Termination Single Contact Wire (FTSCW) and
Auto-Tension Simple Catenary (ATSC) as shown in Reference 7.
o In OCS Segments 1,2,3,4,6, OCS) has either one messenger wire of 500kcm
hard drawn copper or one parallel feeder cable of 500kcm hard drawn copper,
plus one contact wire of 350kcm hard drawn copper (Ref.7); The operating
temperature of the OCS is at 75oC, with the contact wire 30% worn as the worst
case (Ref.2).
o In OCS Segment 5 of the OCS, 2x1000 kcmil copper feeders will be used per
track for electro-magnetic interference mitigation (Ref.7), plus one contact wire of
350kcm of hard drawn copper. The feeders will be connected to the contact wire
through risers.
Running rails are of 115 RE rails. The working temperature of the rails is at 60oC, with 10%
worn as the worst case (Ref.2).
Both rails are used for traction return current on each track. The running rails on the two tracks
are assumed to be cross-bonded at approximately 2000’ intervals.
Each substation is assumed to have 1x2000kW rectifier unit, which is the standardized size for
MTA LRT rectifiers (Ref.2). The two end-of-line substations are equipped with 2x2000kW
rectifier units each.
The dc no-load voltage is at 795V and the nominal load voltage at 750V, giving an inherent
voltage regulation of 6%. With a minimum short circuit capacity of 100MVA for the ac supply,
2.2% extra regulation is added to the overall regulation.
Trains consists are based on 2-car trains (Reference 3 as listed in Appendix A).
In normal operation, the minimum headway is 5-minutes for weekday peak period operations,
with train weight at AW3 (Reference 10).
Recovery Service of four sequential maximum length Trains operating at maximum allowable
speeds with AW4 loads at normal LRV performance levels at three minute headways at any
location on the Mainline with simultaneous service of maximum length Trains at five minute
headways on the other track. (Reference 10).
Train stops and dwell times are according to Scenario 2 as contained in the reference 8
(Simulation study report Rev4).
In addition to regular passenger stops, all traffic signal stops and pedestrian crossing stops are
also included in the simulation model.
In practical operation, a train may not necessarily stop at every traffic signal, depending on the
status of the signal and timing. There is a degree of randomness on where each train might stop
when it encounters a traffic signal. By including all traffic signal stops, the model captures the
worst case loads for the traction power system.
2.2 Methodology
Simulations have been carried out to assess the traction power system performance under both
normal operation, contingency operation and recovery operation conditions.
Simulation runs and the number of rectifiers in service in each run are listed in the following
table.
For Q01 and Q18 substations, 1 rectifier unit is out of service while the other rectifier
remains in service. DC bus and feeders also remain in service.
For all other substations, the rectifier, dc positive bus and positive feeders are all
taken out of service. The section break bypass switches are closed at the affected
substations so that electrical continuity of the OCS conductors is maintained on each
track while the two tracks are not electrically connected in parallel.
All contingency conditions are covered by 6 simulation runs listed in the above table, labeled
Outage-1 through Outage-6. Each contingency run covers 3 substations that are in
contingency conditions. The substations with contingency conditions in each contingency
run are separated by five substations that are in normal operation. In this way, the effect of
one contingency on another in the same run is minimized. The number of simulation runs is
minimized while the accuracy of the simulation results is not compromised.
EB trains with AW3 weight and 5 minute headway; WB trains with AW4 weight and 3
minute headway
EB trains with AW4 weight and 3 minute headway; WB trains with AW3 weight and 5
minute headway
By assigning a regular headway of three minutes at AW4 weight, these two runs cover all
recovery operation conditions that will have four sequential trains operating at three minute
headway at all location throughout the line.
Under each condition, train dispatching from the two ends of the track are simulated with
different time offsets, so that trains on the two tracks may meet at different locations and the
worst cases of power demands can be captured. The simulation results in this report reflect the
following offsets:
3 Simulation Results
Power demands for other headway offsets are similar as those listed above. They are not listed
in this report for brevity.
The above table indicates that the rectifiers have sufficient capacities to support the normal
operation, all the contingency operation conditions and the recovery operations. The system
meets the requirements of the design criteria in terms of rectifier ratings.
For each simulation, an RMS load current for each feeder in each substation is derived from the
simulation results. These include both positive feeders and negative feeders. The maximum
values from all the simulation runs are summarized for each feeder, which represent the worst
case load for the feeder.
Of all the positive feeders, the maximum is 487A under normal operation, 609A for contingency
operation and 777A for recovery operation.
Of all the negative feeders, the maximum is 756A under normal operation, 1010A for
contingency operation and 1067A for recovery operation.
There are instants when train voltages are below 650V under normal operations but the
frequency of such occurrence is below the specified limit of 10% of all observed train
voltage, per the Design Criteria.
All train voltages are above 525V under all contingency operation conditions.
All train voltages are above 525V under all recovery operations.
The system meets the requirements of the design criteria in terms of train voltages.
Rail potential is within 50V across the system under normal operations.
Rail potential is within 75V across the system under all contingency operation conditions.
Rail potential is within 75V across the system under all recovery operation conditions.
The system meets the requirements of the design criteria in terms of rail potential.
The maximum OCS RMS current in the system is 735A under normal operation.
The maximum OCS RMS current in the system is 1033A under all contingency operation
conditions.
The maximum OCS RMS current in the system is 1183A under all recovery operation
conditions
According to Reference 5, allowable ampacity for 500kcm messenger is 810A and for 350kcm
contact wire 650A, making a total ampacity of 1460A (continuous current rating) for the OCS
(based on 75oC conductor temperature, 25oC ambient temperature, wind velocity of 2
feet/second, under sun light).
If the contact wire is 30% worn, its cross-sectional area is reduced to 245kcm and its ampacity
is reduced to 520A. The total OCS ampacity is reduced to 1330A. This is sufficient to support
normal operations, contingency operations and recovery operations. (Ampacity for 245kcm is
not given in reference 5, as it is not a standard size. Using the ampacity of 530A for a 250kcm
contact wire, the ampacity of 245kcm contact is calculated to be 524A. It is rounded down to
520A.)
1. “MTA Purple/Red Line Design Criteria Manual; Chapter 04 – Light Rail Vehicles”, July,
2013.
2. “MTA Purple/Red Line Design Criteria Manual; Chapter 16 - Traction Power
Substations”, July, 2013.
3. “MTA Purple/Red Line Design Criteria Manual; Chapter 3 – Operational characteristics
and requirements”, July, 2013.
4. 2013.08.01.PE.Preliminary Engineering Drawings-Vol1-00 (Preliminary Engineering
Submission; August 1, 2013)
5. South Wire Copper Product Catalogue – Bare Copper Wire and Cable.
6. GEC Red Line Team Meeting Minutes – Car Interfaces (to Traction Power Design);
Dated December 7, 2011. With characteristic curves contained in a separate Excel file.
7. Purple Line OCS - Draft preliminary engineering – master overlap plan sheets 1-6; not
dated
8. MTA Purple Line: Draft Computer Simulation Analyses - Running Times/Vehicle Braking,
Rev.4; Dated September 17, 2013; DCN 2011.12.22.SU.PE.11.Computer Simulation
Analyses-04.
9. “MTA Purple/Red Line Design Criteria Manual; Chapter 15 – Signaling”, July, 2013.
10. Draft Request for Proposals, Volume II Book 2, Technical Provisions Part 1 – Design
Build Requirements : Section 11 - Systems General Requirements, September, 2013.
Details of track alignment, speed limits and train stop scenarios are listed in a separate
document for the train performance simulation (Reference 8).
Traffic signal and pedestrian crossing locations are listed in the following table.
At this stage, the precise locations of track cross-bonds have not been determined. A nominal
spacing of 2000’ between cross-bonds is assumed, per Design Criteria Chapter 15 - Signaling
(Reference 9). The following table lists the locations of the cross-bonds relative to substations
based on this assumption. Also listed in the table are the distances between adjacent cross-
bonds or between cross-bonds and their nearest substations.
As shown in the above table, a total of 26 cross bonds are assumed, including one at each end
of the line: SOL (start of line) and EOL (end of line).
It is further assumed that the distance between two adjacent cross-bonds, or between one
cross-bond and its nearest substation return connection, should not exceed 2500’. Based on
this assumption and the distance between adjacent substations, the number of cross-bonds is
determined.
Where there is only one cross-bond between two adjacent substations, the cross-bond is
located at the mid-point within the feeding section.
Where there are two cross-bonds between two adjacent substations, the cross-bonds
are located at ⅓ and ⅔ points with the feeding section.
For segment 5, where 2x1000 kcmil copper cables are used to run in parallel with the contact wire, the resultant OCS resistance is
0.03113 Ohms/mile, in comparison with 0.09307 Ohms/mile for other segments where only 1x500 kcmil messenger or cable is used
in parallel with the contact wire.
Single line diagram for the system is shown in the following figure, including both positive and negative circuits.
Figure 11. Single line diagram for the traction power system
The traction power system voltage levels are listed in the following table (Reference 1).
Table 11. System voltage levels
Maximum sustained supply voltage 900 VDC
Nominal supply voltage 750 VDC
Minimum voltage for full performance 650 VDC
Minimum sustained supply voltage 525 VDC
Regeneration cut-off 900 VDC
The inherent regulation of the rectifier equipment is at 6%. When the ac supply impedance is
added (with minimum short circuit capacity at 100MVA for the ac supply), the total regulation is
at 8.2%. Calculations are detailed in the following table.
Substation feeder cables are assumed to be of 2x1000 kcm copper for each feeder circuit, with
300’ length from dc bus to the OCS connection. The lump resistance for each feeder circuit is
1.65 milli-Ohms.
Each negative feeder circuit is assumed to be of 4x1000kcm copper. With 300’ from the dc
negative bus to the track connection, the lump resistance for each circuit is 0.825 milli-Ohms.
For substation Q07, the length of the feeder cables is assumed to be 640’, due to the distance
between the substation location and the sectionalization gaps. The resultant feeder resistances
are 3.52 milli-Ohms for each positive feeder circuit and 1.76 milli-Ohms for each negative feeder
circuit.
For track cross-bonds at each location, 2x1000 kcmil copper cables are assumed, with a
maximum length of 100’. The resultant circuit resistance is 0.55 milli-Ohms.
The vehicle used for simulation is based on the 95 feet car. The vehicle and passenger weights
are listed in the following table (Reference 1).
AW3 weight is used in simulation for normal operation and contingency operation; AW4 weight
is used for recovery operation.
Power conversion efficiency is at 0.85 for both auxiliary power converter and propulsion unit
(Ref.6).
The onboard auxiliary load is assumed to be 80kW per car on the pantograph side (Ref.1).
The maximum acceleration rate is 3.0 mph/s. The maximum Braking rate is 3.0 mph/s. The jerk
rate limit is 1.5 mph/s/s.
The following figures show the vehicle characteristic curves that accompany Reference 1.
In the traction power system load flow study, regenerative braking power is utilized only for
onboard auxiliary loads. This produces the worst case power demand and energy consumption.
The maximum line draw per vehicle is 1650 amperes, including both propulsion and auxiliary
loads.