Question: 126

Due to an error in the process, a defect is occurring in a deliverable. You identified the

root cause of the problem and made some changes to the process to stop the defect from

occurring. This process is known as:

(a) Root cause analysis

(b) Corrective action

(c) Defect repair

(d) Preventive action

Go to the Answer

Question: 127

You are working in a large organization and managing a project to construct a road. To

help you in your project, your PMO is providing you with their support and require you

to comply with them. What kind of PMO is this?

(a) Supportive

(b) Controlling

(c) Directive

(d) Helping
Go to the Answer

Question: 128

During the planning phase, you have created the WBS for the work that you are about

to complete. However, because of a lack of information you are not able to create the

WBS for the rest of the work, so you leave it until you get the correct and detailed

information. This is an example of:

(a) Progressive elaboration

(b) Improper collecting requirement process

(c) Rolling wave planning

(d) Improper scope statement

Go to the Answer

Question: 129

During the project execution, a stakeholder comes to you and argues against a particular

deliverable. You investigated it and found that this particular deliverable was based on
his requirement. To prove this, what document will you show to him?

(a) Scope statement

(b) Requirement traceability matrix

(c) Statement of work

(d) Scope management plan

Go to the Answer

Question: 130

You calculated the cost of constructing the walls by multiplying the cost per square foot

with the total area of the wall. This is an example of which of the following?

(a) Parametric Estimation

(b) Bottom Up

(c) Top Down

(d) Analogous
Go to the Answer

Question: 131

A team of experts come to your project and ask for approved procedures to verify your

team is following these procedures. This is an example of which of the following?

(a) Quality control

(b) Manage quality

(c) Verify scope

(d) Control scope

Go to the Answer

Question: 132

You are working on a project to build a canal for irrigation purposes. Six months have

passed, and now the team is working as a well-organized unit. Team members are

interdependent, working smoothly, and working effectively. What team formation stage

is this?
(a) Performing

(b) Storming

(c) Norming

(d) Forming

Go to the Answer

Question: 133

You are in a conference room meeting with bidders and answering their queries. Some

bidders brought their laptops and are busy with them, many of them are busy with

asking you questions. There is also a cleaner who is vacuuming the floor outside your

conference room. Which of the following is an example of noise?

(a) Questions asked by bidders

(b) Laptop

(c) Telephone

(d) The sound of the vacuum cleaner outside the room

Go to the Answer
Question: 134

You have identified a risk that at a certain point in your project you may need extra

quantities of a consumable which you thought of earlier. The chance of this event

occurring is 20% and if it occurs it will cost you 150 USD. So, you develop a

contingency plan for this risk and assign a risk owner. What kind of risk response

strategy is this?

(a) Transfer

(b) Avoid

(c) Mitigation

(d) Accept

Go to the Answer

Question: 135

Your project is behind schedule and over budget, and the actual cost is on its way to

being higher than the target cost. You and the client both are worried about the project’s

progress and there is a high probability that the point of total assumption will be

crossed. Which of the following assumptions is true about the point of total

assumption?
(a) Above PTA, you will bear the cost

(b) Above PTA, the client will bear the cost

(c) Above PTA, the cost will be equally shared

(d) Above PTA, the cost will be shared by a set ratio

Go to the Answer

Question: 136

You are over budget and it is impossible to complete the project with the given budget.

Therefore, you raise the change request which management approves. After the change

request is approved, you update the cost baseline and update other project documents.

The document used to register any changes which occur during the project execution is

known as:

(a) Risk register

(b) Issue log

(c) Change log

(d) RACI matrix