Due to an error in the process, a defect is occurring in a deliverable. You identified the
root cause of the problem and made some changes to the process to stop the defect from
Go to the Answer
Question: 127
You are working in a large organization and managing a project to construct a road. To
help you in your project, your PMO is providing you with their support and require you
(a) Supportive
(b) Controlling
(c) Directive
(d) Helping
Go to the Answer
Question: 128
During the planning phase, you have created the WBS for the work that you are about
to complete. However, because of a lack of information you are not able to create the
WBS for the rest of the work, so you leave it until you get the correct and detailed
Go to the Answer
Question: 129
During the project execution, a stakeholder comes to you and argues against a particular
deliverable. You investigated it and found that this particular deliverable was based on
his requirement. To prove this, what document will you show to him?
Go to the Answer
Question: 130
You calculated the cost of constructing the walls by multiplying the cost per square foot
with the total area of the wall. This is an example of which of the following?
(b) Bottom Up
(d) Analogous
Go to the Answer
Question: 131
A team of experts come to your project and ask for approved procedures to verify your
Go to the Answer
Question: 132
You are working on a project to build a canal for irrigation purposes. Six months have
passed, and now the team is working as a well-organized unit. Team members are
interdependent, working smoothly, and working effectively. What team formation stage
is this?
(a) Performing
(b) Storming
(c) Norming
(d) Forming
Go to the Answer
Question: 133
You are in a conference room meeting with bidders and answering their queries. Some
bidders brought their laptops and are busy with them, many of them are busy with
asking you questions. There is also a cleaner who is vacuuming the floor outside your
(b) Laptop
(c) Telephone
Go to the Answer
Question: 134
You have identified a risk that at a certain point in your project you may need extra
quantities of a consumable which you thought of earlier. The chance of this event
occurring is 20% and if it occurs it will cost you 150 USD. So, you develop a
contingency plan for this risk and assign a risk owner. What kind of risk response
strategy is this?
(a) Transfer
(b) Avoid
(c) Mitigation
(d) Accept
Go to the Answer
Question: 135
Your project is behind schedule and over budget, and the actual cost is on its way to
being higher than the target cost. You and the client both are worried about the project’s
progress and there is a high probability that the point of total assumption will be
crossed. Which of the following assumptions is true about the point of total
assumption?
(a) Above PTA, you will bear the cost
Go to the Answer
Question: 136
You are over budget and it is impossible to complete the project with the given budget.
Therefore, you raise the change request which management approves. After the change
request is approved, you update the cost baseline and update other project documents.
The document used to register any changes which occur during the project execution is
known as: