Professional Documents
Culture Documents
21. When sequencing project activities in the schedule, you should ensure—
successor
attributes
22. A schedule performance index of less than 1.0 indicates that the—
accomplish
d. Project may not be on schedule, but the project manager need not be
concerned
23. Assume you are working to sequence the activities in your schedule. You
have focused on the need for predecessors and successors for your tasks.
24. To meet regulatory requirements, you need to crash your project schedule.
Your first step is to compute—
a. The cost and time slope for each critical activity that can be expedited
c. The time saved in the overall schedule when tasks are expedited on the
critical path
d. Three probabilistic time estimates of PERT for each critical path activity
d. Project charter
interfaces
27. Project managers should pay attention to critical and subcritical activities
a. Variance analysis
b. Simulation
d. Trend analysis
28. An activity has an early start date of the 10th and a late start date of the
19th. The activity has a duration of four days. There are no non-workdays.
From the information given, what can be concluded about the activity?
b. The early finish date of the activity is the end of the day on the 14th.
are doubled.
the work, where the work will be performed, activity type, and WBS
a. Activity attributes
b. Constraints
d. Refinements
60 ◾ PMP® Exam Preparation: Test Questions, Practice Test, and Simulated Exam
30. There are purposes and benefits in the Control Schedule process. Its benefit
is—
b. It minimizes risk
31. It is important to use the critical path method in Control Schedule because—
plan
32. Several types of float are found in project networks. Float that is used by a
particular activity and does NOT affect the float in later activities is called—
a. Extra float
b. Free float
c. Total float
d. Expected float
33. Assume your organization has decided to use agile for most of it projects.
You are managing a project using agile and are working to develop your
schedule. In doing so, you are using agile release planning. Your schedule is
based on the—
a. Resources available
d. Product roadmap