The points discussed during the 23rd meeting held on 09.03.2015 and the
following decisions are arrived at:
1.2.1 Shifting of Cables. Out off 324 EB boxes identified for removal for 26 footpath
works, 322 EB boxes were removed and 2 are to be removed. 2 nos of EB Boxes not
shifted even after repeated follow ups. 1 No of Transformer not been shifted at the
junction of Shanthi Colony & 5 th Avenue (Near Palamuthir solai). Roads and BRR
Department to expedite by contacting in person the TNEB officials and to complete
the shifting by 15.02.2015. 2nos of EB Boxes not shifted even after repeated follow
ups. 1no of Transformer not been shifted at shanthi colony 5th avenue junction (near
Palamuthir solai). Again a letter has been sent to EB Department on 02.03.2015.
EE/ South / TNEB has assured that 2 nos. of EB boxes and 1 no. of transformer will
be shifted by this week end.
1.3 Phase II
1.3.1 20 footpath works-estimates were prepared and administration sanction were
obtained from council held on 30.09.2014. Tender under packages were called
and due date is 20.02.2015. Tender received and Tender files are put up to
Deputy Commissioner for approval and work order can be issued in one week
anticipating the ratification of council of corporation of Chennai. Financial bid to be
opened. Tenders to be finalized by next week. Work order will be issued at the
earliest.
1.3.2 For 48 footpath works, for 28works Architect have been selected and for 16
works designs were received. Letters were sent to 13 Urban design architects
who are experts in Foot Path design works for empanelled list of Architect for
design of footpath work. As directed by Principal Secretary / Commissioner
empanelment of architect for footpath design has been initiated by BBR
department and till today only 3nos of architect have given their interest, despite
the follow up by BRR with ITDP. By before next CUMTA meeting BRR will be in a
position to finalize the architect and TOR and will off load the remaining roads to
take-up design work by empanelled architect. ITDP has stated that 4 to 5 no. of
architects are willing to get empanelment. Principal Secretary / Commissioner has
requested ITDP to handover the list to BRR Department.
(Action: TNEB &CoC)
2. Setting Bench Marks:
As a pilot project, it was suggested that the Bench Marks need to be set in
order to assess the impact of improvements on pedestrians in the roads. Chennai
Data Portal (CDP) team were instructed to carry out survey for making Pre and
Post Construction Bench Mark scenario for proposed 20 Footpaths. They survey
work is in progress. CDP have completed the survey of inventories in all the 20
Footpaths. Survey of Pedestrian count and Vehicular speed have to be studied.
Chennai Data Portal and Dashboard team is in the process of surveying for
setting Bench Mark.
(Action: CDP and COC)
3. Highways Roads Velachery
3.1. Removal of Encroachments:
In the January meeting Highways department has assured that temporary
encroachment in the footpath will be removed by January end and permanent
encroachment footpath if found it will be removed in phased manner. Highways
has reported that for removal of temporary encroachment in the footpath
Tirumangalam Mugappair road, necessary notices have been issued to the
Vendors and had a joint inspection with Tashildhar concerned. Eviction will be
done shortly.(Ambattur Sub Dn). Regarding removal of Permanent
Encroachments particularly in Velachery area, demarcation of Highways
Boundary is being perused with Revenue Officials. District Collector, Chennai has
been addressed in this regard to take appropriate action (Tambaram Sub Dn). In
the major corridors like GST road, GWT road and IRR, presently revamping of the
Footpath is being carried out .During this work Encroachment on Footpath sides
are being removed.(City Sub Dn).
Highways has informed that for Eviction of vendors in Ambattur Tahsildar it
needs two weeks time. For Velachery area demarcation work is going on.
Principal Secretary / Commissioner has instructed to complete the demarcation
work by this month end. Further Highways has informed that Major corridors like
GST road, GWT road and IRR revamping of the footpath is taking up. Accidents
reports to be received from city police. As per survey conducted 8492 people
crossing the roads per hour. In front of G.H. Road has to be revamped. We have
to integrate traffic in crossing locations like near Iswarya Mahal and Vadapalani in
IRR.
Principal Secretary / Commissioner has instructed to modify the road
designs, by improving the footpath in IRR where METRO work is progressing.
Conduct pedestrian traffic survey on IRR and Redesign the footpath near Metro
Rail Stations.
Additional Commissioner of Police (Traffic) suggested to redesign the road
without reducing carriageway.
Principal Secretary / Commissioner has also instructed High Ways to
follow the MOUD guideless in construction of footpath facilities such as height of
Kerb at 150 mm, level at gate location, Table Top etc.,
3.3 Professor K.P.Subramanian (Retd) has pointed out that the Approach
Road to the Velacherry Rly Station MRTS Railway Station from Kai Veli to be
improved. The Highway Department has stated that the points raised by the
Professor K.P.Subramanian (Retd.) are already studied and foot path proposals
for Southern Sector of IRR from Velacherry Junction point and From Kaiveli
Junction to Southern Sector of IRR have also been initiated. The Highways
Department has reported that Administrative sanction has been obtained from the
Government in G.0(M.S)No.23/Highways and Minor Ports Dept,dt.20.02.2015
for the work of Widening end to end and construction of Drain & Footpath in the
newly extended Corporation areas in Chennai City Roads and Thiruvallur
Divisions. Estimates are under preparation and Tenders will be floated shortly.
(Action: Highways Dept.,)
4. Cycle Sharing
Feasibility report, financial model, cost benefit analysis have to be studied
through consultant, consultant to be selected from the empanelled list of
consultancy firm from TNIDB. Letter has been send to TNIDB through MAWS
Dept on 20.11.2014 for taking up the project under PPP mode. Clarification was
sought from TNIDB through MAWS Dept and the clarification was send to MAWS
Dept on 21.01.2015. Remarks from TNIDB is awaited. The file is in process in
TNIDB, It is followed closely and progress is monitored by Special Projects
Department. After getting remarks from TNIDB further action will be taken up. The
file is at finance Department for clearance.
5. Parking Policy
Feasibility report, financial model, cost benefit analysis have to be studied
through consultant, consultant to be selected from the empanelled list of
consultancy firm from TNIDB. Letter has been send to TNIDB through MAWS
Dept on 20.11.2014 for taking up the project under PPP mode. Clarification was
sought from TNIDB through MAWS Dept and the clarification was send to MAWS
Dept on 21.01.2015. Remarks from TNIDB is awaited. The file is in process in
TNIDB, It is followed closely and progress is monitored by Special Projects
Department. After getting remarks from TNIDB further action will be taken up. The
file is at finance Department for clearance.
(Action: COC)
Padianallur,
Work commenced. To be completed in
2. Kundrathur,Mahakavi Bharathi
one year
Nagar and Chromepet
8.2. Additional requirements of new buses ie 1500 nos has been sent to
Government. Principal Secretary / Commissioner has instructed MTC to furnish
the requirements to BRR department.
(Action : MTC)
2 MLA Fund 73 45 13 15
3 MP Fund 16 16 - -
5 Mayor Fund 5 2 - 3
6 SSS 1 1
7 TNRDC 65 65
CMRL has requested to form footpath wherever the width of road is wide and also
to provide street signages. Further additional street lights have to be provided in the
approach road to CMRL. Principal Secretary / Commissioner has suggested to provide
lighting below the CMRL conducts. Letters were already sent to the Zonal Officers of
Zone 8, 10, 12 & 13 on 24.02.2015 and also instructed the Zonal Officers not only to
black top the road, but also to improve the roads to International Standards with all
amenities such as street furniture, sign boards, thermo plastic paints, studs & speed
breaker for all wider roads immediately and to report the status to the committee before
the next CUMTA meeting. Police suggested that roads have to be laid wherever CMRL
work completed. (Action: CoC & CMRL)
13. Multi Modal Integration plan around MRTS and Sub-urban Stations:
The CMDA has taken up the study under 4 packages for the 4 rail corridors (each
corridor one package) by engaging 4 consultants.
Stage of Multi Modal Integration plan
Southern sub urban Rail Draft final report under progress
Package I
Package II West sub urban Rail Draft final report under progress
Package III Northern sub urban Rail Draft final report under progress
(Action: CMDA)
14. All one way roads list can be put up to the subcommittee to resolve,
evaluate to recommend for promoting pedestrian movement. As suggested by
Professor K.P.Subramanian (Retd) study on one way in Chennai city have to taken
up through Anna University or IIT. Lr has been sent to Anna University and IIT-
Madras on 23.01.2015 requesting to carryout study as research Projects on one
way road in Chennai other than CMRL locations. Letter have been sent to Additional
Commissioner Traffic on 18.02.2015 requesting to provide separate list of one ways
in Chennai separately for CMRL Corridor and for other areas . Mean while, a over all
list of all one way in Chennai obtained from Traffic Police by ITDB was forwarded to
IIT- Madras/Anna university for reference. As a pilot project Anna university is going
to takeup 1.Halda junction and 2.Sterling road junction , IIT madras is going to
takeup 1.Mandaveli-near intersection of RK Mutt road and greenways road and
2.Ashok piller – Udhayam theatre. IIT – Madras informed that traffic data to be
collected from police department such as Accident detail, Speed details and also
FIR details. Police informed that survey regarding accident locations have been
completed and the same can be furnished. (Action:COC)
15. All the speed breakers are to be rectified as per IRC standard.
As of now out of 139 speed breakers were taken up, 40 speed breakers has been
completed & the remaining will be dropped as BRR is going to take up 197 roads
laying work during which the balance Speed breakers will be continued as per the
direction of Principal Secretary/Commissioner. A list of 139 Speed breakers taken
up has been sent to Mr. Sivanandham (DCP Traffic) on 29.01.15
Status of Speed Breakers
Total No of Speed Breakers
Region Completed In progress To be taken up
identified
North 46 15 13 18
Central 46 17 1 28
South 47 18 2 27
Total 139 40 26 73
(Action: COC)
16. ITDP has made a presentation on Namma Chennai Namakke -A
campaign to celebrate Chennai’s Streets. A street event was proposed in Besent
nagar. The Principal Secretary / Commissioner has instructed ITDP to organise the
event by the end of February after getting clearance from all stakeholders. Letter has
been send to MAWS Dept 18.02.2015 seeking permission to organize campaign in
chennai’s streets ITDP has informed that MAWS Department has instructed to
conduct a stakeholders meeting and residents opinion and through articles in News
papers and Internet.
(Action: ITDP)
The meeting concluded with the decision to hold the next Committee Meeting on
09.04.2015 at 11.00 a.m. in the Commissioner’s conference hall, Corporation of
Chennai.
Signed
Principal Secretary / Commissioner