Professional Documents
Culture Documents
DECISION
NACHURA, J : p
Address:Harbour Center II, Railroad & Chicago Sts. Port Area, City of
Manila
(Signed)
BARRY CHIA SOO HOCK ______(Signed)______
(Printed Name/Signature (Printed Name/Signature
CD Technologies Asia, Inc. © 2021 cdasiaonline.com
Above Name) Above Name)
On February 8, 2000, in the course of its repair, M/V "Superferry 3" was
gutted by fire. Claiming that the extent of the damage was pervasive, WG&A
declared the vessel's damage as a "total constructive loss" and, hence, filed an
insurance claim with Pioneer.
On June 16, 2000, Pioneer paid the insurance claim of WG&A in the
amount of US$8,472,581.78. WG&A, in turn, executed a Loss and Subrogation
Receipt 9 in favor of Pioneer, to wit: AaDSEC
16 June 2000
Our Claim Ref: MH-NIL-H0-99-00018
US$8,472,581.78
Armed with the subrogation receipt, Pioneer tried to collect from KCSI,
but the latter denied any responsibility for the loss of the subject vessel. As
KCSI continuously refused to pay despite repeated demands, Pioneer, on
August 7, 2000, filed a Request for Arbitration before the Construction
Industry Arbitration Commission (CIAC) docketed as CIAC Case No. 21-2000,
seeking the following reliefs:
1. To pay to the claimant Pioneer Insurance and Surety
Corporation the sum of U.S.$8,472,581.78 or its equivalent amount in
Philippine Currency, plus interest thereon computed from the date of
the "Loss and Subrogation Receipt" on 16 June 2000 or from the date of
filing of [the] "Request for Arbitration", as may be found proper;
2. To pay to claimant WG&A, INC. and/or Aboitiz Shipping
Corporation and WG&A Jebsens Shipmanagement, Inc. the sum of
P500,000,000.00 plus interest thereon from the date of filing [of the]
"Request for Arbitration" or date of the arbitral award, as may be found
proper;
3. To pay to the claimants herein the sum of P3,000,000.00
for and as attorney's fees; plus other damages as may be established
during the proceedings, including arbitration fees and other litigation
expenses, and the costs of suit.
It is likewise further prayed that Clauses 1 and 2 on the unsigned
page 1 of the "Shiprepair Agreement" (Annex "A") as well as the hardly
legible Clauses 20 and 22 (a) and other similar clauses printed in very
fine print on the unsigned dorsal page thereof, be all declared illegal
and void ab initio and without any legal effect whatsoever. 10
As regards the disputed facts, below are the respective positions of the
parties, viz.:
Pioneer's Theory of the Case:
First, Pioneer (as Claimant) is the real party in interest in this case and
that Pioneer has been subrogated to the claim of its assured. The
Claimant claims that it has the preponderance of evidence over that of
the Respondent. Claimant cited documentary references on the
Statutory Source of the Principle of Subrogation. Claimant then
CD Technologies Asia, Inc. © 2021 cdasiaonline.com
proceeded to explain that the Right of Subrogation:
Is by Operation of Law
exists in Property Insurance
is not Dependent Upon Privity of Contract.
Claimant then argued that Payment Operates as Equitable Assignment
of Rights to Insurer and that the Right of Subrogation Entitles Insurer to
Recover from the Liable Party.
Second, Respondent Keppel had custody of and control over the M/V
"Superferry 3" while said vessel was in Respondent Keppel's premises.
In its Draft Decision, Claimant stated:
Third, the Vessel's Safety Manual cannot be relied upon as proof of the
Master's continuing control over the vessel.
Fourth, the Respondent Yard is liable under the Doctrine of Res Ipsa
Loquitur. According to Claimant, the Yard is liable under the ruling laid
down by the Supreme Court in the "Manila City" case. Claimant asserts
that said ruling is applicable hereto as The Law of the Case.
Fifth, the liability of Respondent does not arise merely from the
application of the Doctrine of Res Ipsa Loquitur, but from its negligence
in this case.
Sixth, the Respondent Yard was the employer responsible for the
negligent acts of the welder. According to Claimant;
2. The Ship [R]epair Agreement was not imposed upon the Vessel.
The Vessel knowingly and voluntarily accepted that agreement.
Moreover, there are no signing or other formal defects that can
invalidate the agreement.
3. The proximate cause of the fire and damage to the Vessel was
not any negligence committed by Angelino Sevillejo in cutting
the bulkhead door or any other shortcoming by the Yard. On the
contrary, the proximate cause of the fire was Dr. Joniga's and the
Vessel's deliberate decision to have Angelino Sevillejo undertake
cutting work in inherently dangerous conditions created by them.
On October 28, 2002, the CIAC rendered its Decision 13 declaring both
WG&A and KCSI guilty of negligence, with the following findings and
conclusions —
The Tribunal agrees that the contractual obligation of the Yard is
to provide the welders and equipment to the promenade deck. [The]
Tribunal agrees that the cutting of the bulkhead door was not a
contractual obligation of the Yard. However, by requiring, according to
its own regulations, that only Yard welders are to undertake hotworks,
it follows that there are certain qualifications of Yard welders that
would be requisite of yard welders against those of the vessel welders.
To the Tribunal, this means that yard welders are aware of the Yard
safety rules and regulations on hotworks such as applying for a
hotwork permit, discussing the work in a production meeting, and
complying with the conditions of the hotwork permit prior to
implementation. By the requirement that all hotworks are to be done
by the Yard, the Tribunal finds that Sevillejo remains a yard employee.
The act of Sevillejo is however mitigated in that he was not even a
foreman, and that the instructions to him was (sic ) by an authorized
person. The Tribunal notes that the hotworks permit require[s] a
request by at least a foreman. The fact that no foreman was included
in the five welders issued to the Vessel was never raised in this dispute.
As discussed earlier by the Tribunal, with the fact that what was ask
(sic ) of Sevillejo was outside the work order, the Vessel is considered
equally negligent. This Tribunal finds the concurrent negligence of the
Yard through Sevillejo and the Vessel through Dr. Joniga as both
contributory to the cause of the fire that damaged the Vessel. 14
The Yard and The WG&A are hereby ordered to pay the
arbitration costs pro-rata.
SO ORDERED. 16
SO ORDERED. 18
II
V
THE COURT OF APPEALS ERRED IN NOT HOLDING THE YARD LIABLE
FOR INTEREST.
VI
THE COURT OF APPEALS ERRED IN NOT HOLDING THE YARD SOLELY
LIABLE FOR ARBITRATION COSTS. 19
On the other hand, KCSI cites the following grounds for the allowance of
its petition, to wit:
1. ABSENCE OF YARD RESPONSIBILITY
To our minds, these errors assigned by both Pioneer and KCSI may be
summed up in the following core issues:
A. To whom may negligence over the fire that broke out on
board M/V "Superferry 3" be imputed?
Pioneer contends that KCSI should be held liable because Sevillejo was
its employee who, at the time the fire broke out, was doing his assigned
task, and that KCSI was solely responsible for all the hot works done on
board the vessel. KCSI claims otherwise, stating that the hot work done was
beyond the scope of Sevillejo's assigned tasks, the same not having been
CD Technologies Asia, Inc. © 2021 cdasiaonline.com
authorized under the Work Order 25 dated January 26, 2000 or under the
Shiprepair Agreement. KCSI further posits that WG&A was itself negligent,
through its crew, particularly Dr. Raymundo Joniga (Dr. Joniga), for failing to
remove the life jackets from the ceiling void, causing the immediate spread
of the fire to the other areas of the ship.
We rule in favor of Pioneer.
First. The Shiprepair Agreement is clear that WG&A, as owner of M/V
"Superferry 3", entered into a contract for the dry docking and repair of the
vessel under KCSI's Standard Conditions of Contract for Shiprepair, and its
guidelines and regulations on safety and security. Thus, the CA erred when it
said that WG&A would renovate and reconstruct its own vessel merely using
the dry docking facilities of KCSI.
Second. Pursuant to KCSI's rules and regulations on safety and
security, only employees of KCSI may undertake hot works on the vessel
while it was in the graving dock in Lapu-Lapu City, Cebu. This is supported
by Clause 3 of the Shiprepair Agreement requiring the prior written approval
of KCSI's Vice President for Operations before WG&A could effect any work
performed by its own workers or sub-contractors. In the exercise of this
authority, KCSI's Vice-President for Operations, in the letter dated January 2,
1997, banned any hot works from being done except by KCSI's workers, viz.:
The Yard will restrict all hot works in the engine room,
accommodation cabin, and fuel oil tanks to be carried out only by
shipyard workers . . . . 26
WG&A recognized and complied with this restrictive directive such that,
during the arrival conference on January 26, 2000, Dr. Joniga, the vessel's
passage team leader in charge of its hotel department, specifically
requested KCSI to finish the hot works started by the vessel's contractors on
the passenger accommodation decks. 27 This was corroborated by the
statements of the vessel's hotel manager Marcelo Rabe 28 and the vessel's
quality control officer Joselito Esteban. 29 KCSI knew of the unfinished hot
works in the passenger accommodation areas. Its safety supervisor Esteban
Cabalhug confirmed that KCSI was aware "that the owners of this vessel
(M/V 'Superferry 3') had undertaken their own (hot) works prior to arrival
alongside (sic) on 26th January", and that no hot work permits could
thereafter be issued to WG&A's own workers because "this was not allowed
for the Superferry 3". 30 This shows that Dr. Joniga had authority only to
request the performance of hot works by KCSI's welders as needed in the
repair of the vessel while on dry dock.
Third. KCSI welders covered by the Work Order performed hot works on
various areas of the M/V "Superferry 3", aside from its promenade deck. This
was a recognition of Dr. Joniga's authority to request the conduct of hot
works even on the passenger accommodation decks, subject to the provision
of the January 26, 2000 Work Order that KCSI would supply welders for the
promenade deck of the ship. IADaSE
KCSI denies the liability because, aside from its claim that it cannot be
held culpable for negligence resulting in the destructive fire, there was no
constructive total loss, as the amount of damage was only US$3,800,000.00
or P170,611,260.00, the amount of repair expense quoted by Simpson,
Spence & Young.
In the face of this apparent conflict, we hold that Section 139 of the
Insurance Code should govern, because (1) Philippine law is deemed
incorporated in every locally executed contract; and (2) the marine
insurance policies in question expressly provided the following:
IMPORTANT
Along the same vein, Clause 22 (a) cannot be upheld. The intention of
the parties to make each other a co-assured under an insurance policy is to
be gleaned principally from the insurance contract or policy itself and not
from any other contract or agreement, because the insurance policy
denominates the assured and the beneficiaries of the insurance contract.
Undeniably, the hull and machinery insurance procured by WG&A from
Pioneer named only the former as the assured. There was no manifest
intention on the part of WG&A to constitute KCSI as a co-assured under the
policies. To have deemed KCSI as a co-assured under the policies would have
had the effect of nullifying any claim of WG&A from Pioneer for any loss or
damage caused by the negligence of KCSI. No ship owner would agree to
make a ship repairer a co-assured under such insurance policy. Otherwise,
any claim for loss or damage under the policy would be rendered nugatory.
WG&A could not have intended such a result. 54
Nevertheless, we concur with the position of KCSI that the salvage
value of the damaged M/V "Superferry 3" should be taken into account in the
grant of any award. It was proven before the CIAC that the machinery and
the hull of the vessel were separately sold for P25,290,000.00 (or
US$468,333.33) and US$363,289.50, respectively. WG&A's claim for the
upkeep of the wreck until the same were sold amounts to P8,521,737.75 (or
US$157,809.96), to be deducted from the proceeds of the sale of the
machinery and the hull, for a net recovery of US$673,812.87, or equivalent
to P30,252,648.09, at P44.8977/$1, the prevailing exchange rate when the
Request for Arbitration was filed. Not considering this salvage value in the
award would amount to unjust enrichment on the part of Pioneer.
C.On the imposition of interest
Pursuant to our ruling in Eastern Shipping Lines, Inc. v. Court of
Appeals, 55 the award in favor of Pioneer in the amount of P350,146,786.89
should earn interest at 6% per annum from the filing of the case until the
award becomes final and executory. Thereafter, the rate of interest shall be
12% per annum from the date the award becomes final and executory until
its full satisfaction.
D.On the payment for the cost of arbitration
It is only fitting that both parties should share in the burden of the cost
of arbitration, on a pro rata basis. We find that Pioneer had a valid reason to
institute a suit against KCSI, as it believed that it was entitled to claim
reimbursement of the amount it paid to WG&A. However, we disagree with
Pioneer that only KCSI should shoulder the arbitration costs. KCSI cannot be
faulted for defending itself for perceived wrongful acts and conditions.
Otherwise, we would be putting a price on the right to litigate on the part of
Pioneer. CSHEAI
SO ORDERED.
Footnotes
1.Rollo (G.R. Nos. 180896-97), pp. 33-109.
2.Rollo (G.R. Nos. 180880-81), pp. 338-378.
6.The Shiprepair Agreement was duly acknowledged by the parties before a notary
public.
7.20. The Contractor shall not be under any liability to the Customer either in
contract or otherwise except for negligence and such liability shall itself be
subject to the following overriding limitations and exceptions, namely
(a) The total liability of the Contractor to the Customer (including the liability
to replace under Clause 17) or of any Sub-contractor shall be limited in
respect of any and/or defect(s) or event(s) to the sum of Pesos Philippine
Currency Fifty Million only . . . .
8.22(a) The Customer shall keep the vessel adequately insured for the vessel's hull
and machinery, her crew and the equipment on board and on other goods
owned or held by the Customer against any and all risks and liabilities and
ensure that such insurance policies shall include the Contractor as a co-
assured.
9.Rollo (G.R. Nos. 180896-97), p. 526.
10.Id. at 167.
11.Id. at 236.
12.Id. at 236-242.
13.Id. at 229-320.
14.Id. at 286.
CD Technologies Asia, Inc. © 2021 cdasiaonline.com
15.Id. at 319.
16.Id. at 143-144.
17.Now a member of this Court.
18.Id. at 163-164.
19.Rollo (G.R. No. 180896-97), pp. 46-48.
20.Rollo (G.R. Nos. 180880-81), pp. 356-357.
21.Prudential Shipping and Management Corporation v. Sta. Rita, G.R. No. 166580,
February 8, 2007, 515 SCRA 157.
22.The fire expert presented by Pioneer.
23.Dr. Eric Mullen, the fire expert presented by KCSI.
39.Note from the Publisher: Footnote text missing from the official document.
40.Ms. Aini Ling, WG&A's fire expert, specifically testified:
"Sir, if there is no life jacket, of course, there is no ignition of life jackets. . . .
That doesn't mean that they (sic ) might not be a fire, your Honor, because
there are other combustible materials in the ceiling void." (TSN, May 21,
2002, pp. 319-320, as quoted in the CIAC Decision, p. 38).
41.The pertinent testimony of Dr. Eric Mullen, The Yard's fire expert, is as follows:
ATTY. LOMBOS:
CD Technologies Asia, Inc. © 2021 cdasiaonline.com
Now, you also heard Ms. Ling say that even if she concedes that the removal
of the life jackets from under the ceiling void would have made the most
likely source of the fire, ah, would have eliminated the most likely source of
the fire, her opinion was still that there was a possibility of fire from say,
wires or the ceiling material which was plywood she says on top of the
Formica. Do you have any views regarding that?
DR. MULLEN:
In so far as my mechanism, which I firmly believe to be the case that the
material fell through the holes, it would have made that much difference.
Because you have the life jackets would ignite easily, the ceiling itself would
ignite easily because the material that is falling down is very incendive (sic )
and in some cases has flames on them. So, it wouldn't have made that much
difference had the life jackets been removed, there was still possibility for
fire. (TSN, May 23, 2002, pp. 132-133, as quoted in the CIAC Decision, p. 38-
39).
42.This fact was admitted during cross-examination by Geoff Phoon, The Yard's
president, who testified in this wise:
ATTY. LIM:
Q Did you require the vessel to take out the life jackets and put them
somewhere else or some place else on board or on shore?
MR. PHOON:
A We don't touch the ship property.
Q You, in fact, did not require that?
47.KCSI's Petition, pp. 31-32, Rollo (G.R. Nos. 180880-81), pp. 368-369.
48.Lorenzo Shipping Corp. v. Chubb and Sons, Inc., G.R. No. 147724, June 8, 2004,
431 SCRA 266.
49.PHILAMGEN v. Court of Appeals, 339 Phil. 455 (1997).
50.Exhibit "E-Bello", pp. 3-4.
51.ACI Philippines, Inc. v. Coguia, G.R. No. 174466, July 14, 2008, 558 SCRA 300;
CD Technologies Asia, Inc. © 2021 cdasiaonline.com
Development Bank of the Philippines vs. Perez, G.R. No. 148541, November
11, 2004, 442 SCRA 238.
52.Premiere Development Bank v. Central Surety & Insurance Company, Inc., G.R.
No. 176246, February 13, 2009.
53.Cebu Shipyard and Engineering Works, Inc. v. William Lines, Inc., G.R. No.
132607, May 5, 1999, 306 SCRA 762, 781.
54.Id. at 780.
55.G.R. No. 97412, July 12, 1994, 234 SCRA 78.