Professional Documents
Culture Documents
Process:
File Description:
Date:
Process Description:
Chemicals:
Purpose:
Scope:
Objectives:
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 1 of 14
Impianto di desolforazione Benzine da FCC
2. Low pressure in P-201A/B suction 2.1. Pumps P-201A/B fail to start 2.1. Verify the lowest pressure of the RAGE
start-up fluid circuit from OSBL
3. Valve downstream P-201A/B to 3.1. Start-up fluid sent to slop 3.1. FI 189 3.1. Add double block and bleed in SP
slop open during start-up fluid loading discharge line from P-201A/B to slop
3.2. Uncomplete dewaxing (6"-5210-P33) upstream existing
check valve
4. Hand valves on drain lines open 4.1. Start-up fluid sent to Drain KO 4.1. Hand valve at V-212 inlet 4.1. Include in the Dewaxing SP
Drum V-212 procedure to verify the closure of all
manual valves on drain lines to V-212
5. FV 109 on HP steam to CDHydro 5.1. Possible damage to E-103 5.1. Include in the procedure to SP
Steam Reboiler E-103 open before... tubes due to thermal stress ensure that E-103 stem side is ...
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 2 of 14
Impianto di desolforazione Benzine da FCC
6. Hand valves on condensate line 6.1. Loss of start-up fluid heating; 6.1. Highlight in the procedure the SP
from CDHydro Steam Reboiler E-103 pressure increase in E-103 tube side opening of hand valves on
closed when FV 109 opens condensate line from CDHydro Steam
Reboiler E-103
8. CDHydro Recycle Gas Compressor 8.1. N2 and HC vapors sent to K- 8.1. K-101 not in service 8.1. Add in the procedure the closure SP
K-101 not properly isolated 101 suction of 2 hand valves on K-101 suction
8.2. Hand valves on K-101 suction upstream and downstream FT115
9. TIC 106 fails opening FV109 (HP 9.1. Start-up fluid overheating in 9.1. T Indications in CDHydro column 9.1. Verify the CDHydro Catalyst CDTech
Steam) CDHydro column C-101; possible integrity in case of T in column rises
damage of the CDHydro Catalyst 9.2. FIC 109 gives indication due to FV109 fully open (P&ID SP
5210-GD-B-04502 and 04503)
10. Dewaxing is not completed 10.1. CDHydro catalyst reduction is 10.1. Dewaxing Operating Procedure 10.1. Define the methodology to CDTech
not effective with possible permanent verify complete Dewaxing Operation
and adverse changes in the catalyst (i. e. sampling)
activity, in case of exposure to FCC
naphtha 10.2. Verify adverse consequences ... CDTech
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 3 of 14
Impianto di desolforazione Benzine da FCC
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 4 of 14
Impianto di desolforazione Benzine da FCC
2. Level on CDHydro column C-101 2.1. Possible loss of level in C-101 2.1. Clarify the function of CDHydro CDTech
sump not automatically controlled sump sump level control LIC 103 during
(step 3) reduction procedure (step 3, 7.3.2)
3. Loss of Reflux Stream during H2 3.1. Loss of cooling in CDHydro 3.1. TAHH 114 A/B/C 3.1. Verify TAHH 114 and 115 CDTech
injection column C-101; T increase due to activation with H2 shutdown, during
Catalyst reduction reaction 3.2. TAHH 115 A/B/C CDHydro catalyst reduction
exothermicity
3.2. Verify the need of C-101 CDTech
depressurization (trough HIC 101) in
case of high T interlock action
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 5 of 14
Impianto di desolforazione Benzine da FCC
2. Valve downstream P-201A/B to 2.1. Start-up fluid sent to slop 2.1. FI 189 2.1. Add double block and bleed in SP
slop open during Dewaxing initial discharge line from P-201A/B to (6"-
steps 2.2. Incomplete dewaxing 5210-P33) upstream existing check
valve
3. Hand valves on drain lines open 3.1. Start-up fluid sent to Drain KO 3.1. Hand valve at V-212 inlet 3.1. Include in the Dewaxing SP
Drum V-212 procedure to verify the closure of all
manual valves on drain lines to V-212
4. FV124 on 8"-5210-P74 discharge 4.1. Start-up fluid sent to naphtha 4.1. FIC 124 gives indication 4.1. Add in the procedure to verify SP
line to Naphtha Stabiliser C-203 open Stabilizer C-203 the closure of FV124 (on P202A/B
4.2. LIC 113 gives indication discharge line to naphtha stabiliser C-
203)
5. Hand valve on P-202 A/B 5.1. Startup fluid sent to V-202 5.1. Add in the procedure to verify the SP
discharge line 10"-5210-P77 to EA- (CDHDS cold Separator) through EA- closure of hand valves on shutdown
203 open 203 instead of C-201; possible loss of line 10"-5210-P77 from P-202 A/B to
level in C-201 EA-203
6. Hand valve on P-202 A/B discharge 6.1. Startup fluid sent to CDHDS 6.1. Add in the procedure to verify the SP
line 8"-5210-P76 to E-202 openverso Steam/Bottom Exchangers E-202 closure of hand valves on E-202 shell
E-202 shell side; possible E-202 damage side for proper isolation
(tube side) do to thermal stress
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 6 of 14
Impianto di desolforazione Benzine da FCC
8. LIC 113 fails (on CDHDS column 8.1. Possible loss of level and P-202 8.1. LALL 114 A/B/C 8.1. Verify LALL 114 A/B/C activation SP
sump) (step 4) A/B cavitation during CDHDS Catalyst Drying
8.2. FALL 125 A/B/C operations
9. K-201 recycle Gas Compressor not 9.1. Star-up fluid vapors sent to K-201 9.1. K-201 not in operation 9.1. Add in the procedure the isolation
properly isolated suction of Recycle Gas Compressor K-201 by
closing of hand valve and blind on K-
201 suction line
10. Free water in F-201 tubes before 10.1. Possible water vaporization 10.1. Furnace Drying operation 10.1. Clarify the need to perform CDTech
furnace firing inside F-201 tubes furnace drying: a) before start-up
operation; b)during start-up operation;
c) otherwise
11. Filters MS-202 A/B plugged 11.1. No flow into C-201 through C- 11.1. PDI 134 11.1. Verify PDAH 134 is activated on SP
201 reflux line. Possible loss of level filters MS-202 during CDHDS Catalyst
in C-201 Drying operations
12. HC vapors present in V-202 12.1. Possible presence of 12.1. Verify the possibility to perform CDTech
connected to atmosphere before N2 flammable/explosive mixture N2 pressurization before start-up fluid
pressurization entrance in CDHDS column C-201
13. Vapor line from V-202 to E-204 13.1. Start-up fluid vapors sent to 13.1. Add in the procedure to verify SP
shell side open Naphtha Stabilizer C-203 and Gas the closure of hand valves on E-204
Amine Absorber C-204 shell side for proper isolation
14. FV 131 on V-201 outlet line to C- 14.1. Start-up fluid sent to C-203 14.1. Add in the procedure to verify SP
203 open 10"-5210-P109 the closure and isolation of valve
FV131 on V201 outlet line to C-203
15. T in CDHDS column C-201 rises 15.1. Possible catalyst deactivation 15.1. TI 147 A/B/C 15.1. Verify TAHH 147 A/B/C SP
over 150°C activation that carry out ESD L01 with
a set point of 155°C during CDHDS
Catalyst Drying
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 8 of 14
Impianto di desolforazione Benzine da FCC
2. DMDS concentration in CDHDS 2.1. Uncontrolled T increase in 2.1. Local flow control in DMDS 2.1. Relocate SC154 from FV124 to SP
column greater than 1% CDHDS column injection package suction / discharge of P-202 A/B
2.2. T Indication in CDHDS column 2.2. Add in the procedure to verify the SP
DMDS content by means of periodic
sampling (through SC-154)
3. Presence of HC/DMDS vapors in 3.1. Release of toxic / flammable 3.1. Evaluate the possibility of CDTech
V-202 connected to atmosphere vapors to atmosphere from V-202... controlling V-204 Pressure through ...
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 9 of 14
Impianto di desolforazione Benzine da FCC
4. High T in catalytic beds during 4.1. Re-set TAHH 147 A/B/C from SP
Sulfiding operation 155°C to normal operating conditions
5. Washed gas (low MW) to blow 5.1. Very low P in Refinery blowdown 5.1. Add 6" line downstream PV141 SP
down recovery gas compressors suction to Refinery Recover Gas System (corr
102) and close 6"-BD70 to V-213
6. Loss of DMDS injection during 6.1. Possible reduction of catalyst 6.1. Local flow indication of DMDS 6.1. Provide manned DMDS RAGE
Sulfiding operations metal oxides injection unloading operation (Rage operators)
7. Loss of H2 flow during Sulfiding 7.1. Loss of catalyst sulfidation; 7.1. FI 123 7.1. Verify FAL 123 and FAL 186 are SP
operations DMDS content increase with active during Sulfiding operations;
consequent T increase due to 7.2. FI 186 setting the value at start-up
exothermic reaction conditions
8. Wrong procedure during 8.1. Toxic gas in atmosphere 8.1. Provide Sample connection in SP
H2Ssampling from atmospheric vent (Refinery sampling procedures do not PV141 (vapor line from V-204) for
in V-202 foresee utilisation of H2S Draeger H2S sampling during Sulfiding
samples) operations
9. DMDS and H2 flow are not 9.1. Possible catalyst reduction 9.1. Underline in the procedure the SP
reduced simultaneously need to perform simultaneously the
flow of H2 and DMDS
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 11 of 14
Impianto di desolforazione Benzine da FCC
2. CDHydro column C-101 initial 2.1. Steady reflux in C-101 cannot 2.1. Verify the possibility to de- CDTech
start-up is performed with diesel be established inventory the CDHydro Unit after
dewaxing and reduction operations
and subsequently feed olefinic
naphtha from FCC to allow a steady
reflux in CDHydro column (see
enclosed propsed procedure 7.4.3)
3. Initial off-spec products cannot be 3.1. Add a new 6" line from P202 SP/CDTec
deinventoried A/B discharge line 6"-P81 upstream h
HV103 in order to allow deinventory of
CDHDS Unit (see enclosed proposed
procedure 7.4.4)
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 12 of 14
Impianto di desolforazione Benzine da FCC
2. FV131 on outlet line from V-201 2.1. Possible loss of level in V-201 2.1. Switch automatic level control SP
closed and isolated due to loss of automatic level control in V-201 from FV131 (line to C-203) to
FV132 (P-203 A/B discharge line to C-
201) during Short Term Shutdown
operation
3. FV136 on outlet line from V-202 to 3.1. Possible loss of level in V-202 3.1. Relocate the emergency cool SP
C-203 closed and isolated due to loss of automatic level control down liquid line 6"-5210-P113 from
upstream FV136 to downstream
FV136 and switch the blind into open
position also during normal operation
4. No flow in CDHDS feed 4.1. T control in CDHDS column by 4.1. Switch off FFIC 124 control SP
TIC133 cannot be performed before Short Term Shutdown
operation
4.2. Sampling of CDHDS feed
cannot be performed (step 12) 4.2. Verify the possibility to run the CDTech
CDHydro/CDHDS Unit in total recycle
mode (see enclosed proposed
procedure 8.1.1)
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 13 of 14
Impianto di desolforazione Benzine da FCC
2. Loss of DMDS injection during 2.1. Possible catalyst de-sulfidation 2.1. Verify when DMDS injection stop CDTech
CDHDS column cold recirculation is required during CDHDS column
cold recirculation
3+$:RUNVE\3ULPDWHFK,QF
:RUNVKHHW
Raffineria di Gela 14 of 14
Impianto di desolforazione Benzine da FCC
2. Unit depressurization not carried 2.1. Unit quick cooling, under 150°C, 2.1. Verify the need of CDTECH
out in case of total H2 failure for more is not ensured CDHydro/CDHDS Units
than 1 hour depressurization in case of total fresh
H2 failure; otherwise verify the
attached procedure feasibility (see
atteched propose procedure 8.2.2.)
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 1 of 13
Impianto di desolforazione Benzine da FCC
2. Low pressure in P-201A/B 2.1. Pumps P-201A/B fail to start 2.1. Verify the lowest pressure of the start-up fluid circuit from OSBL RAGE
suction
2.2. Verify the NPSH of P-201 A/B SP
3. Valve downstream P-201A/B to 3.1. Start-up fluid sent to slop 3.1. Add double block and bleed in discharge line from P-201A/B to slop (6"-5210- SP
slop open during start-up fluid P33) upstream existing check valve
loading 3.2. Uncomplete dewaxing
4. Hand valves on drain lines 4.1. Start-up fluid sent to Drain KO 4.1. Include in the Dewaxing procedure to verify the closure of all manual valves on SP
open Drum V-212 drain lines to V-212
4.2. When Dewaxing operations are completed, ensure that startup fluid is drained SP
from V-102 through 3"-5210-CD8 line to V-212 instead of 2"-5210-SW1 line to
SWS;
5. FV 109 on HP steam to 5.1. Possible damage to E-103 5.1. Include in the procedure to ensure that E-103 stem side is properly isolated SP
CDHydro Steam Reboiler E-103 tubes due to thermal stress before start-up fluid entrance
open before start-up fluid entrance
6. Hand valves on condensate line 6.1. Loss of start-up fluid heating; 6.1. Highlight in the procedure the opening of hand valves on condensate line from SP
from CDHydro Steam Reboiler E- pressure increase in E-103 tube CDHydro Steam Reboiler E-103
103 closed side when FV 109 opens
8. CDHydro Recycle Gas 8.1. N2 and HC vapors sent to 8.1. Add in the procedure the closure of 2 hand valves on K-101 suction upstream SP
Compressor K-101 not properly K-101 suction and downstream FT115
isolated
8.2. Add in the procedure the closure of the blind on K-101 suction line 6"-5210-P52 SP
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 2 of 13
Impianto di desolforazione Benzine da FCC
9. TIC 106 fails opening FV109 9.1. Start-up fluid overheating in 9.1. Verify the CDHydro Catalyst integrity in case of T in column rises due to CDTech
(HP Steam) CDHydro column C-101; possible FV109 fully open (P&ID SP 5210-GD-B-04502 and 04503)
damage of the CDHydro Catalyst
10. Dewaxing is not completed 10.1. CDHydro catalyst reduction 10.1. Define the methodology to verify complete Dewaxing Operation (i. e. CDTech
is not effective with possible sampling)
permanent and adverse changes
in the catalyst activity, in case of 10.2. Verify adverse consequences to CDHydro Catalyst in case of improper CDTech
exposure to FCC naphtha Dewaxing
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 3 of 13
Impianto di desolforazione Benzine da FCC
2. Level on CDHydro column C- 2.1. Possible loss of level in C- 2.1. Clarify the function of CDHydro sump level control LIC 103 during reduction CDTech
101 sump not automatically 101 sump procedure (step 3, 7.3.2)
controlled (step 3)
3. Loss of Reflux Stream during 3.1. Loss of cooling in CDHydro 3.1. Verify TAHH 114 and 115 activation with H2 shutdown, during CDHydro CDTech
H2 injection column C-101; T increase due to catalyst reduction
Catalyst reduction reaction
exothermicity 3.2. Verify the need of C-101 depressurization (trough HIC 101) in case of high T CDTech
interlock action
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 4 of 13
Impianto di desolforazione Benzine da FCC
2. Valve downstream P-201A/B to 2.1. Start-up fluid sent to slop 2.1. Add double block and bleed in discharge line from P-201A/B to (6"-5210-P33) SP
slop open during Dewaxing initial upstream existing check valve
steps 2.2. Incomplete dewaxing
3. Hand valves on drain lines 3.1. Start-up fluid sent to Drain KO 3.1. Include in the Dewaxing procedure to verify the closure of all manual valves on SP
open Drum V-212 drain lines to V-212
4. FV124 on 8"-5210-P74 4.1. Start-up fluid sent to naphtha 4.1. Add in the procedure to verify the closure of FV124 (on P202A/B discharge SP
discharge line to Naphtha Stabilizer C-203 line to naphtha stabiliser C-203)
Stabiliser C-203 open
5. Hand valve on P-202 A/B 5.1. Startup fluid sent to V-202 5.1. Add in the procedure to verify the closure of hand valves on shutdown line 10"- SP
discharge line 10"-5210-P77 to (CDHDS cold Separator) through 5210-P77 from P-202 A/B to EA-203
EA-203 open EA-203 instead of C-201;
possible loss of level in C-201
6. Hand valve on P-202 A/B 6.1. Startup fluid sent to CDHDS 6.1. Add in the procedure to verify the closure of hand valves on E-202 shell side SP
discharge line 8"-5210-P76 to E- Steam/Bottom Exchangers E-202 for proper isolation
202 openverso E-202 shell side; possible E-202 damage
(tube side) do to thermal stress
7. Loss of water supply to CDHDS 7.1. Possible damage to E-216 7.1. Ensure line-up of BFW line and steam line on E-216 before CDHDS Catalyst SP
Steam Generator E-216 (tube side) due to thermal stress Drying. Ensure BFW flow to E-216 during Catalyst Drying operations
8. LIC 113 fails (on CDHDS 8.1. Possible loss of level and P- 8.1. Verify LALL 114 A/B/C activation during CDHDS Catalyst Drying operations SP
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 5 of 13
Impianto di desolforazione Benzine da FCC
9. K-201 recycle Gas Compressor 9.1. Star-up fluid vapors sent to K- 9.1. Add in the procedure the isolation of Recycle Gas Compressor K-201 by closing
not properly isolated 201 suction of hand valve and blind on K-201 suction line
10. Free water in F-201 tubes 10.1. Possible water vaporization 10.1. Clarify the need to perform furnace drying: a) before start-up operation; CDTech
before furnace firing inside F-201 tubes b)during start-up operation; c) otherwise
11. Filters MS-202 A/B plugged 11.1. No flow into C-201 through 11.1. Verify PDAH 134 is activated on filters MS-202 during CDHDS Catalyst Drying SP
C-201 reflux line. Possible loss of operations
level in C-201
12. HC vapors present in V-202 12.1. Possible presence of 12.1. Verify the possibility to perform N2 pressurization before start-up fluid CDTech
connected to atmosphere before flammable/explosive mixture entrance in CDHDS column C-201
N2 pressurization
12.2. Alternatively, evaluate the possibility to collect to blow down through PV141 CDTech
vapors from V-202, V-203, C-204 and V-204
13. Vapor line from V-202 to E- 13.1. Start-up fluid vapors sent to 13.1. Add in the procedure to verify the closure of hand valves on E-204 shell side SP
204 shell side open Naphtha Stabilizer C-203 and Gas for proper isolation
Amine Absorber C-204
14. FV 131 on V-201 outlet line to 14.1. Start-up fluid sent to C-203 14.1. Add in the procedure to verify the closure and isolation of valve FV131 on SP
C-203 open 10"-5210-P109 V201 outlet line to C-203
15. T in CDHDS column C-201 15.1. Possible catalyst 15.1. Verify TAHH 147 A/B/C activation that carry out ESD L01 with a set point of SP
rises over 150°C deactivation 155°C during CDHDS Catalyst Drying
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 6 of 13
Impianto di desolforazione Benzine da FCC
2. DMDS concentration in 2.1. Uncontrolled T increase in 2.1. Relocate SC154 from FV124 to suction / discharge of P-202 A/B SP
CDHDS column greater than 1% CDHDS column
2.2. Add in the procedure to verify the DMDS content by means of periodic sampling SP
(through SC-154)
2.3. Verify the methodology and parameters to analyse DMDS content on CDHDS CDTech
bottom line (through SC-154)
2.4. Provide 6"tie-in from line 6"-P81 upstream HV103 for CDHDS unit deinventory SP
2.5. Add in the Sulfiding procedure the need for star-up fluid drainage and feed of SP
fresh start-up fluid in case of DMDS content greater than 1%
2.6. Set design pressure of EA-204 A/B according to P-202 A/B shut off pressure SP
3. Presence of HC/DMDS vapors 3.1. Release of toxic / flammable 3.1. Evaluate the possibility of controlling V-204 Pressure through PV141 closing CDTech
in V-202 connected to atmosphere vapors to atmosphere from V-202 atmospheric vent
vent
4. High T in catalytic beds during 4.1. Re-set TAHH 147 A/B/C from 155°C to normal operating conditions SP
Sulfiding operation
5. Washed gas (low MW) to blow 5.1. Very low P in Refinery 5.1. Add 6" line downstream PV141 to Refinery Recover Gas System (corr 102) SP
down blowdown recovery gas and close 6"-BD70 to V-213
compressors suction
5.2. Add in the procedure the closure and isolation of FV139 valve on vapor line SP
from Amine Absorber Column C-204 to Refinery Recovery (corr 102)
6. Loss of DMDS injection during 6.1. Possible reduction of catalyst 6.1. Provide manned DMDS unloading operation (Rage operators) RAGE
Sulfiding operations metal oxides
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 7 of 13
Impianto di desolforazione Benzine da FCC
8. Wrong procedure during 8.1. Toxic gas in atmosphere 8.1. Provide Sample connection in PV141 (vapor line from V-204) for H2S SP
H2Ssampling from atmospheric (Refinery sampling procedures do sampling during Sulfiding operations
vent in V-202 not foresee utilisation of H2S
Draeger samples) 8.2. Remove from sulfiding procedure the gas washing in Amine Absorber column, SP
to allow the check of the H2S breakthrough from SC in PV141 on vapor line from V-
204. The acid off gas will be sent to recovery and afterwashing refinery plant.
9. DMDS and H2 flow are not 9.1. Possible catalyst reduction 9.1. Underline in the procedure the need to perform simultaneously the flow of H2 SP
reduced simultaneously and DMDS
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 8 of 13
Impianto di desolforazione Benzine da FCC
2. CDHydro column C-101 initial 2.1. Steady reflux in C-101 2.1. Verify the possibility to de-inventory the CDHydro Unit after dewaxing and CDTech
start-up is performed with diesel cannot be established reduction operations and subsequently feed olefinic naphtha from FCC to allow a
steady reflux in CDHydro column (see enclosed propsed procedure 7.4.3)
3. Initial off-spec products cannot 3.1. Add a new 6" line from P202 A/B discharge line 6"-P81 upstream HV103 in SP/CDT
be deinventoried order to allow deinventory of CDHDS Unit (see enclosed proposed procedure 7.4.4) ech
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 9 of 13
Impianto di desolforazione Benzine da FCC
2. FV131 on outlet line from V-201 2.1. Possible loss of level in V- 2.1. Switch automatic level control in V-201 from FV131 (line to C-203) to FV132 SP
closed and isolated 201 due to loss of automatic level (P-203 A/B discharge line to C-201) during Short Term Shutdown operation
control
3. FV136 on outlet line from V-202 3.1. Possible loss of level in V- 3.1. Relocate the emergency cool down liquid line 6"-5210-P113 from upstream SP
to C-203 closed and isolated 202 due to loss of automatic level FV136 to downstream FV136 and switch the blind into open position also during
control normal operation
4. No flow in CDHDS feed 4.1. T control in CDHDS column 4.1. Switch off FFIC 124 control before Short Term Shutdown operation SP
by TIC133 cannot be performed
4.2. Verify the possibility to run the CDHydro/CDHDS Unit in total recycle mode CDTech
4.2. Sampling of CDHDS feed (see enclosed proposed procedure 8.1.1)
cannot be performed (step 12)
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 10 of 13
Impianto di desolforazione Benzine da FCC
2. Loss of DMDS injection during 2.1. Possible catalyst de- 2.1. Verify when DMDS injection stop is required during CDHDS column cold CDTech
CDHDS column cold recirculation sulfidation recirculation
2.2. Verify the need to stop make up H2 injection in Reboiler Furnace F-201 and CDTech
CDHDS feed/CDHDS Ovhd Exchanger E-201 in case of loss of DMDS injection
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 11 of 13
Impianto di desolforazione Benzine da FCC
2. Unit depressurization not 2.1. Unit quick cooling, under 2.1. Verify the need of CDHydro/CDHDS Units depressurization in case of total CDTEC
carried out in case of total H2 150°C, is not ensured fresh H2 failure; otherwise verify the attached procedure feasibility (see atteched H
failure for more than 1 hour propose procedure 8.2.2.)
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 12 of 13
Impianto di desolforazione Benzine da FCC
1.3. Verify the need of unit depressurization in case of fuel gas failure. Otherwise CDTEC
verify the attached propose procedure 8.1.1 feasibility H
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV
Raffineria di Gela 13 of 13
Impianto di desolforazione Benzine da FCC
3+$:RUNVE\3ULPDWHFK,QF
$FWLRQ,WHPV,QGH[
System 1: 7.3.1. Dewaxing the CDHydro Naphtha Splitter Catalyst 1
System 2: 7.3.2. Reduce CDHydro Naphtha Splitter Catalyst 3
System 3: 7.3.3. CDHDS Catalyst Drying 4
System 4: 7.3.4. Sulfide CDHDS Catalyst 6
System 5: 7.4 Initial Startup Procedure 8
System 6: 8.1.1. Short Term Shutdown 9
System 7: 8.1.2. Long Term Shutdown 10
System 8: 8.2 Emergency Shutdown 11
Subsystem 1: 8.2.2 Loss of Fresh Hydrogen 11
Subsystem 2: 8.2.8 Fuel Gas Failure 12
Subsystem 3: 8.2.3 Instrument Air Failure 13
3+$:RUNVE\3ULPDWHFK,QF
-2% 81,7
63& =$(
0L;
5HY
$//(*$72%
3523267$',352&('85(
,QLWLDO6WDUWXS&'+\GUR1DSKWKD6SOLWWHU6\VWHP
Pressurize CDHydro column to 4.3kg/cm2g with N2 by means of the N2 line at the column BTM.
Start feeding FCC olefinic naptha from OSBL to CDHydro Feed Drum V-101.
As level in V-101 rises, start feeding olefinic naptha from V-101 to C-101 running P-103 at
minimum flow
As the level in C-101 rises, start P-201 to feed V-102, using the shutdown line to CDHydro
condenser EA-102.
As the level in V-102 rises, start reflux flow to column by P-102.
Stabilize cold reflux in CDHydro column using shutdown line and maintaining feed from FCC.
Open line to slop from P-201 to send out start-up diesel from CDHydro while keeping level in the
column btm.
Slowly start HP Steam to CDHydro Steam Reboiler E-103.
As the column warms up, condensed vapors are collected in the Reflux Drum V-102. When level in
Reflux Drum rises, close shutdown line from P-201.
Once a steady reflux flow is established and sustained, start feeding H2 to CDHydro column at
reduced flow.
Once the level in CDHydro Reflux drum is stable, and a stable temperature profile is established in
the column, establish the normal flow of H2.
Control T in column regulating heat input to the reboiler, until T profile in the column reaches
normal set point.
At this point, the CDHydro Unit is operating in “once through” H2 mode, sending off-spec product
from P-201 to slop.
-2% 81,7
63& =$(
0L;
5HY
,QLWLDO6WDUWXS&'+'6&ROXPQ6\VWHP
Start sending feed to the CDHDS column from CDHydro btms through P-201 and close slop line.
When CDHDS btm level rises, start sending naptha to slop through the new 6” line, added on the
start-up/shutdown line upstream HV103. (SP dwg. 04511).
Continue sending naptha to slop until depletion of start-up light diesel from CDHDS Unit, while
following CDTech procedure 7.4.4. from step 3 to 6.
Start sending product from CDHDS btms to C-203 and close line to slop.
Note 2: Naphtha Stabilizer column C-203 is pressurized with N2 at 2.3 kg/cm2g by means of N2
stripping line.
-2% 81,7
63& =$(
0L;
5HY
6KRUW7HUP6KXWGRZQ
63& =$(
0L;
5HY
(PHUJHQF\6KXWGRZQ/RVVRI)UHVK+\GURJHQ