Tuesday, February 8, 2022

To,

Indian Oil Corporation Limited


UPSO-I, Uttar Pradesh

Subject: Request for Issue time extension for Supply, Transportation & Installation of High Mast
Signage Vide PO No : 26851852

Dear Sir,

We are privileged to be associated with your esteemed organization for such a long period. This is to inform you that at present
we are going to execute the Work Contract of Supply & Installation of High Mast Signage on the war-footing level.

Pl’s note that the execution of the Project was undergoing during the Pandemic situation. An excel sheet with the details is
attached herewith for your ready reference defining the commencement date and completion date.

Revised Net Delay BY


Layout Layout Revised Date of Delay In Covid TPI Delays TPI Delay
Date of Sch. As Initial Date of Actual Total TPI NG Delay In LD
Sl No. Call Up No Provided Confirmation Commencement Executi Extension Days in in Stage Retail Outlet Name
per Call Up Delay Completion Completion Delay=I=G+H Brothers=J= Weeks Applicable
On Date (B) =C on =E Required= F Stage-1 =G 2=H
D= C+60 E-F-I
1 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 26-11-2021 210 90 0 4 11 109 16.00 8.00 M/s R.K. Fuels
2 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 29-11-2021 213 90 5 2 14 109 16.00 8.00 M/s Kisan Tel Apurti Kendra
3 26851852 02-03-2021 01-05-2021 10-04-2021 39 10-04-2021 08-06-2021 20-02-2022 257 90 0 0 0 167 20 10.00 M/s. RR & SONS FILLING STATION
4 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 21-10-2021 174 90 0 38 45 39 6.00 3.00 M/s Rajjan Lal Kanhaiya Lal
5 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 21-10-2021 174 90 5 38 50 34 5.00 2.50 ASHA FILLING CENTRE
6 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 21-10-2021 174 90 0 38 45 39 6.00 3.00 SHRI KAMADGIRI FILLING STATION
7 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 22-10-2021 175 90 0 44 51 34 5.00 2.50 M/s Rani Shankar
8 26851852 02-03-2021 01-05-2021 10-04-2021 39 10-04-2021 08-06-2021 26-10-2021 140 90 0 44 51 0 0.00 0.00 K P FILLING STATION
9 26851852 02-03-2021 01-05-2021 10-04-2021 39 10-04-2021 08-06-2021 29-11-2021 174 90 0 3 10 74 11.00 5.50 M/s Mileage FS
10 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 08-09-2021 131 90 0 0 2 39 6.00 3.00 M/s Sai Purushottam
11 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 09-10-2021 162 90 51 19 77 0 0.00 0.00 M/s Shiv Shakti SS
12 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 08-09-2021 131 90 0 0 7 34 5.00 2.50 M/s Mahavir FS
13 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 20-02-2022 296 90 0 0 0 206 20.00 10.00 M/s Kumar Oil Corporation
14 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 29-10-2021 182 90 39 20 66 26 4.00 2.00 M/s Jawahar FS
15 26851852 02-03-2021 01-05-2021 10-04-2021 39 10-04-2021 08-06-2021 25-02-2022 262 90 15 0 0 172 20.00 10.00 M/s Laxmi Auto
16 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 17-11-2021 201 90 4 47 58 53 8.00 4.00 M/s Shiva FS
17 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 17-11-2021 201 90 0 47 48 63 9.00 4.50 LALTA SINGH & SONS
18 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 25-02-2022 301 90 0 0 0 211 20.00 10.00 RAM FILLING STATION
19 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 26-11-2021 210 90 0 3 10 110 16.00 8.00 M/s Krishna Auto FC
20 26851852 02-03-2021 01-05-2021 02-03-2021 0 02-03-2021 30-04-2021 26-11-2021 210 90 20 2 29 91 13.00 6.50 SURYA PETROLEUM

Moreover, the situation of COVID-19 in the state of West Bengal & Uttar Pradesh was quite serious. There was are striction of the
movement of man, material & transportation throughout the state. Our factory was under the Containment Zone where the factory
was reopened with the minimum workforce and thus the fabrication was affected due to the non-availability of the trained
manpower from the village areas who had left for their hometown during the lockdown. Also, Ministry of Micro, Small & Medium
Enterprises, Govt of India, augmenting supplies of oxygen for medical purpose only (Liquid Oxygen used in industry application
from all types of Welding to MS pipe/Plate cutting, is one of the basic components for the production) and requested" to spare
empty oxygen cylinders in your possession and hand these cylinders over to the local administration, so that the same are utilized
for supplying oxygen to Covid-19 patients".

As there were restrictions in the movement of the man, material & transportation in the whole country. The availability of material
was also very difficult. Also, Complete Lockdown was Started on15th April 2021 in West Bengal & Uttar Pradesh. West Bengal
Government has extended the COVID-19 complete lockdown in the state till July 14, 2021 with certain relaxations.
In addition, to there are also delays in the account of TPI which caused a delay in execution. Considering the above scenario, you
are requested to please allow a time extension of above mentioned Table, and delays of TPI should not be counted in our delays.
Furthermore, we will not seek any escalation in the account of extension.

Your kind consideration for the same will be highly appreciated So we will submit our Invoice for Processing Payment.

Thanking You,
For N G Brothers