NOTE:

1. PROCESS CONNECTION
USE OF DBAB (DOUBLE BLOCK AND BLEED) IS SERVICE DEPENDANT

2. PRE-INSULATED TUBING TO BE USED WHERE REQUIRED

3. 6mm TEST CONNECTION WITH BLIND PLUG

NOTE 2

INSTRUMENT STAND
316 SST
NOTE 3
50mm NB 1:12
PIPE
NORKOK

STAND
1:12

INSTR. NOTE 1

PIPING

OW
FL
NOTE:
THIS ITEM MAY VARY DEPENDING
ON PROCESS VARIABLE
(REFER TO PIPING SPECIFICATION)

PROJECT NAME:

NORSOK TITLE:
INSTRUMENT HOOK-UP DIAGRAM
DIFF.PRESS. TRANSMITTER GAS SERVICE
01 01.06.07 ORIGINAL RP GG GG

SCALE: SYSTEM WORK DRAWING NO:


CONTRACTOR COMPANY NO: PACK I-001-111 01
NO:
REV. DATE DESCRIPTION
PREPERED CHECKED APPROVED REVIEW ACCEPTED PROJECT DISC DOC.TYPE SEQ.NO. SHT.NO. REV.