Professional Documents
Culture Documents
Managing Risk
Risk is an uncertain event or condition that,
if it occurs, has a positive or negative effect
on project objectives.
Step 1: Risk Identification- generate a list of Figure 2: Partial Risk Profile for Product
all the possible risks that could affect the Development Project
project. Uses brainstorming and other
problem identifying techniques to identify Good risk profiles, like RBSs, are tailored to
potential problems. the type of project in question.
Organizations use Risk Breakdown The risk identification process should not be
Structures (RBSS) in conjunction with Work limited to just the core team. Input from
Breakdown Structures (WBSS) to help customers, sponsors, subcontractors,
management teams identify and eventually vendors, and other stakeholders should be
analyze risks. solicited.
Probability Analysis
1. Decision trees have been used to
Figure 3: Defined Conditions for Impact Scales of a assess alternative courses of action
Risk on Major Project Objectives using expected value.
2. Statistical variations of net present
Often organizations find it useful to value (NPV) have been used to
categorize the severity of different risks into assess cash flow risks in projects.
some form of risk assessment matrix. The 3. Correlations between past projects’
matrix is typically structured around the cash flow and S-curves have been
impact and likelihood of the risk event. used to assess cash flow risks.
4. PERT (program evaluation and
review technique) and PERT
simulation can be used to review
activity and project risk.
a. Mitigating Risk
reduce the likelihood that the
event will occur and/
reduce the impact that the
adverse event would have on
the project.
Testing and prototyping are frequently
used to prevent problems from surfacing
later in a project.
c. Transferring Risk
Passing risk to another party
is common; this transfer does Figure 6: Risk Response Matrix
not change risk. Passing risk
to another party almost Technical Risks - Technical risks are
always results in paying a normally those that involve specific
premium for this exemption. knowledge of the technology of the project
deliverables.
d. Retaining Risk Cost Risks- risk that the project costs more
Some risks are so large it is than budgeted. Cost risk may lead to
not feasible to consider performance risk if cost overruns lead to
transferring or reducing the reductions in scope or quality to try to stay
event.
within the baseline budget.
The risk is retained by Funding Risks
developing a contingency
plan to implement if the risk
materializes.
Opportunity Management
Contingency Planning An opportunity is an event that can have a
Contingency plan is an alternative plan that
positive impact on project objectives.
will be used if a possible foreseen risk event
becomes a reality. The contingency plan Four different types of response to an
represents actions that will reduce or opportunity
mitigate the negative impact of the risk event. 1. Exploit
2. Share
Risk response is part of the actual
3. Enhance
implementation plan and action is taken 4. Accept
before the risk can materialize.
Contingency plan is not part of the initial Contingency Funding and Time Buffers
implementation plan and only goes into Contingency funds are established to cover
effect after the risk is recognized. project risks—identified and unknown.
The absence of a contingency plan, when a The size and amount of contingency
risk event occurs, can cause a manager to reserves depend on uncertainty inherent in
delay or postpone the decision to implement
the project. Uncertainty is reflected in the
a remedy. “newness” of the project, inaccurate time and
cost estimates, technical unknowns,
unstable scope, and problems not
anticipated.