You are on page 1of 4

Week 11

Managing Risk
Risk is an uncertain event or condition that,
if it occurs, has a positive or negative effect
on project objectives.

Risk management attempts to recognize


and manage potential and unforeseen
trouble spots that may occur when the
project is implemented.

Risk Management Process

Step 1: Risk Identification- generate a list of Figure 2: Partial Risk Profile for Product
all the possible risks that could affect the Development Project
project. Uses brainstorming and other
problem identifying techniques to identify Good risk profiles, like RBSs, are tailored to
potential problems. the type of project in question.

Organizations use Risk Breakdown The risk identification process should not be
Structures (RBSS) in conjunction with Work limited to just the core team. Input from
Breakdown Structures (WBSS) to help customers, sponsors, subcontractors,
management teams identify and eventually vendors, and other stakeholders should be
analyze risks. solicited.

Step 2: Risk Assessment- Not all of these


risks deserve attention. Some are trivial and
can be ignored, while others pose serious
threats to the welfare of the project.

Scenario analysis is the easiest and most


commonly used technique for analyzing
risks. Team members assess the
significance of each risk event in terms of:
• Probability of the event.
 risks need to be evaluated in terms of
the likelihood the event is going to
Figure 1: The Risk Breakdown Structure (RBS) occur and the impact or
consequences of its occurrence.
A risk profile is another useful tool. A risk • Impact of the event
profile is a list of questions that address  impact ultimately needs to be
traditional areas of uncertainty on a project. assessed in terms of project
priorities, different kinds of
impact scales are used.
Some scales may simply use
rank-order descriptors, such
as “low,” “moderate,” “high,”
and “very high,” whereas The risk severity matrix provides a basis for
others use numeric weights prioritizing which risks to address. Red zone
(1–10) risks receive first priority followed by Yellow
zone risks. Green zone risks are typically
considered inconsequential and ignored
unless their status changes.

Failure Mode and Effects Analysis (FMEA)


extends the risk severity matrix by including
ease of detection in the equation:
Impact x Probability x Detection = Risk Value

Probability Analysis
1. Decision trees have been used to
Figure 3: Defined Conditions for Impact Scales of a assess alternative courses of action
Risk on Major Project Objectives using expected value.
2. Statistical variations of net present
Often organizations find it useful to value (NPV) have been used to
categorize the severity of different risks into assess cash flow risks in projects.
some form of risk assessment matrix. The 3. Correlations between past projects’
matrix is typically structured around the cash flow and S-curves have been
impact and likelihood of the risk event. used to assess cash flow risks.
4. PERT (program evaluation and
review technique) and PERT
simulation can be used to review
activity and project risk.

Step 3: Risk Response Development


When a risk event is identified and
assessed, a decision must be made
concerning which response is
Figure 4: Risk Assessment Form appropriate for the specific event.

a. Mitigating Risk
 reduce the likelihood that the
event will occur and/
 reduce the impact that the
adverse event would have on
the project.
Testing and prototyping are frequently
used to prevent problems from surfacing
later in a project.

Identifying the root causes of an event


is useful.

Figure 5: Risk Severity Matrix


b. Avoiding Risk
 Risk avoidance is changing the
project plan to eliminate the risk
or condition

c. Transferring Risk
 Passing risk to another party
is common; this transfer does Figure 6: Risk Response Matrix
not change risk. Passing risk
to another party almost Technical Risks - Technical risks are
always results in paying a normally those that involve specific
premium for this exemption. knowledge of the technology of the project
deliverables.
d. Retaining Risk Cost Risks- risk that the project costs more
 Some risks are so large it is than budgeted. Cost risk may lead to
not feasible to consider performance risk if cost overruns lead to
transferring or reducing the reductions in scope or quality to try to stay
event.
within the baseline budget.
 The risk is retained by Funding Risks
developing a contingency
plan to implement if the risk
materializes.
Opportunity Management
Contingency Planning An opportunity is an event that can have a
Contingency plan is an alternative plan that
positive impact on project objectives.
will be used if a possible foreseen risk event
becomes a reality. The contingency plan Four different types of response to an
represents actions that will reduce or opportunity
mitigate the negative impact of the risk event. 1. Exploit
2. Share
Risk response is part of the actual
3. Enhance
implementation plan and action is taken 4. Accept
before the risk can materialize.
Contingency plan is not part of the initial Contingency Funding and Time Buffers
implementation plan and only goes into Contingency funds are established to cover
effect after the risk is recognized. project risks—identified and unknown.
The absence of a contingency plan, when a The size and amount of contingency
risk event occurs, can cause a manager to reserves depend on uncertainty inherent in
delay or postpone the decision to implement
the project. Uncertainty is reflected in the
a remedy. “newness” of the project, inaccurate time and
cost estimates, technical unknowns,
unstable scope, and problems not
anticipated.

Budget Reserves- are identified for specific


work packages or segments of a project
found in the baseline budget or work Changes easily fall into three categories:
breakdown structure. 1. Scope changes in the form of design or
additions represent big changes; for
Management Reserves- funds are needed example, customer requests for a new
to cover major unforeseen risks and, hence, feature or a redesign that will improve the
are applied to the total project. product.
2. Implementation of contingency plans,
when risk events occur, represent changes
in baseline costs and schedules.
3. Improvement changes suggested by
project team members represent another
category.

Change management systems involve


reporting, controlling, and recording changes
Figure 7: Contingency Fund Estimate (Thousands to the project baseline. Most change
of Dollars) management systems are designed to
accomplish the following:
Time Buffers 1. Identify proposed changes.
Managers use time buffers to cushion 2. List expected effects of proposed
against potential delays in the project. The change(s) on schedule and budget.
amount of time is dependent upon the 3. Review, evaluate, and approve or
inherent uncertainty of the project disapprove changes formally.
4. Negotiate and resolve conflicts of change,
Step 4: Risk Response Control conditions, and cost.
The results of the first three steps of the risk 5. Communicate changes to parties affected.
management process are summarized in a 6. Assign responsibility for implementing
formal document often called the risk change.
register. A risk register details all identified 7. Adjust master schedule and budget.
risks, including descriptions, category, and 8. Track all changes that are to be
probability of occurring, impact, responses, implemented.
contingency plans, owners, and current
status. Weekly Task
1. Think of a project. Identify and
Risk Control involves executing the risk assess major and minor risks
response strategy, monitoring triggering inherent to the project. Decide on a
events, initiating contingency plans, and response type. Develop a
watching for new risks. Establishing a contingency plan for two to four
change management system to deal with identified risks. Estimate costs.
events that require formal changes in the Assign contingency reserves. How
scope, budget, and/or schedule of the project much reserve your estimate for the
is an essential element of risk control. whole project? Justify your choices
and estimates.
Change Control Management
Change management refers to the tools and
processes used to manage change within a
project and its team.

You might also like