PANELS MAIN BREAKERS

SITE No. NAME NEMA AT P No. AT P


ALABEL 8 1. MTS-1 1 600 3 0 0 0
2. ELP 1 50 3 6 20 2
15 2
15 2
20 2
20 2
20 2
3. MOBILE BOX 4X 600 3 0 0 0
4. EPR 1 160 3 2 160 3
30 2
5. EMDP 1 250 3 6 200 3
160 3
160 3
50 3
100 3
50 3
6. ACU 4X 100 3 6 40 3
40 3
40 3
40 3
30 2
30 2
7. ECB-ACCU 4X 20 3 0 0 0
8. ECB-FCU 1 40 3 0 0 0

PANELS MAIN BREAKERS


SITE No. NAME NEMA AT P No. AT P
BAYUGAN 3 1. ACU 4X 200 3 6 40 3
40 3
40 3
40 3
40 3
40 3
2. ECB-ACCU 4X 20 3 0 0 0
3. ECB-FCU 1 40 3 0 0 0

PANELS MAIN BREAKERS


SITE No. NAME NEMA AT P No. AT P
CABADBARAN 5 1. EMDP 1 300 3 4 250 3
250 3
100 3
50 3
2. EPR 1 250 3 2 250 3
30 3
3. ACU 4X 100 3 4 40 3
40 3
40 3
40 3
4. ECB-ACCU 4X 40 3 0 0 0
5. ECB-FCU 1 20 2 0 0 0

PANELS MAIN BREAKERS


SITE No. NAME NEMA AT P No. AT P
LA CASTELLANA 5 1. MTS 1 350 2 0 0 0
2. MOBILE BOX 4X 350 3 0 0 0
3. MDP - 2 1 250 2 4 125 2
125 2
50 2
50 2
4. EPR-1 1 300 3 2 125 2
30 2
5. ACU 4X 50 2 4 30 2
30 2
30 2
30 2

PANELS MAIN BREAKERS


SITE No. NAME NEMA AT/A, T.L. P No. AT P
LISP 9 1. MCB 4X 400 3 0 0 0
2. MDP 1 400 30 4 400 3
400 3
100 2
30 2
3. MTS-G 1 400 3 0 0 0
4. MTS-L 1 400 3 0 0 0
5. MOBILE BOX 4X 400 3 0 0 0
6. EMDP 1 400 3 10 125 3
200 2
125 2
150 2
125 2
200 2
100 2
50 2
50 2
50 2
7. ACU 4X 125 2 6 40 2
40 2
40 2
40 2
40 2
40 2
8. ECB - ACCU 4X 40 2 0 0 0
9. ECB - FCU 1 20 2 0 0 0
PANELS MAIN BREAKERS
SITE No. NAME NEMA AT/A, T.L. P No. AT P
LUPON 5 1. EPR ECB 1 125 3 0 0 0
2. EPR PANEL-1 1 125 3 1 30 3
3. ACU 4X 100 2 4 40 2
40 2
40 2
40 2
4. ECB-ACCU 4X 40 2 0 0 0
5. ECB-FCU 1 20 2 0 0 0

PANELS MAIN BREAKERS


SITE No. NAME NEMA AT/A, T.L. P No. AT P
PIKIT 9 1. MCB 4X 700 3 0 0 0
2. MDP 1 700 3 4 700 3
700 3
75 3
30 3
3. MTS-1 1 700 3 0 0 0
4. MTS-G 1 700 3 0 0 0
5. MTS-2 1 700 3 0 0 0
6. EMDP 1 700 3 6 300 3
250 3
200 3
150 3
100 3
50 3
7. MOBILE BOX 4X 700 3 0 0 0
8. ELPP 1 50 3 6 30 2
30 2
20 2
20 2
20 2
20 2
9. EPR-1 1 250 3 2 250 3
30 3

PANELS MAIN BREAKERS


SITE No. NAME NEMA AT/A, T.L. P No. AT P
PONTEVEDRA 3 1. MDP-2 1 200 2 6 100 2
50 2
30 2
20 2
15 2
50 2
2. ACU 1 50 2 4 30 2
30 2
30 2
30 2
3. EPR-1 1 200 3 5 200 2
200 2
100 2
100 2
30 2

PANELS MAIN BREAKERS


SITE No. NAME NEMA AT/A, T.L. P No. AT P
TACURONG 13 1. MCB 4X 350 3 0 0 0
2. MDP 1 350 3 4 350 3
350 3
75 3
30 3
3. MTS-1 1 350 3 0 0 0
4. MTS-G 1 350 3 0 0 0
5. MTS-2 1 350 3 0 0 0
6. EMDP 1 350 3 8 250 3
250 3
200 3
100 3
100 3
50 3
50 3
50 3
7. MOBILE BOX 4X 350 3 0 0 0
8. ELPP 1 50 3 6 30 2
30 2
20 2
20 2
15 2
20 2
9. EPR 1 250 3 2 250 3
30 3
10. ELP 1 50 3 6 30 2
30 2
15 2
20 2
15 2
20 2
11. ACU 4X 100 3 4 40 3
40 3
40 3
40 3
12. ECB-FCU 1 20 2 0 0 0
13. ECB-ACCU 4X 40 3 0 0 0

PANELS MAIN BREAKERS


SITE No. NAME NEMA AT/A, T.L. P No. AT P
TALISAY 4 1. MTS-1 4X 1200 3 0 0 0
2. MTS-G 4X 1200 3 0 0 0
3. MOBILE BOX 4X 1200 3 0 0 0
4. ELPP 4X 50 3 6 30 2
20 2
15 2
20 2
20 2
20 2