Professional Documents
Culture Documents
EVA Class Practice
EVA Class Practice
testing and commissioning of 3,000 desktop computers of the same specification at a cost of `600
lakhs. The company had estimated that it could supply, install, test and commission 100 computers
per day so that the entire work can be completed in 30 days. The project status was reviewed
after the completion of 20 days. It was noted at the time of review that 1,800 computers have been
installed and the cost incurred was `380 lakhs. It was estimated at the time of the review that a
sum of `260 lakhs would be required for completion of the pending work, i.e., installation of the
remaining 1,200 computers.
1) Budgeted cost of work scheduled at the end of 20 days, which is the review period.
(ii) Budgeted cost of work performed till the review period.
(iii) Actual cost of work performed.
(iv) Cost variance
(v) Schedule variance in cost terms
(vi) Cost performance index
(vii) Schedule performance index
(viii) Additional cost for completing the project
(ix) Project duration and whether the project can be completed within the 30 days duration
ly, installation,
cost of `600
00 computers
Budget 250
Duration 80
BCWP 170
ACWP 180
BCWS 187
Find the following:
(i) Cost variance
(ii) Schedule variance in cost terms
(iii) CPI
(iv) SPI
(v) Cost of completion
(vi) Time of completion
4 A project has a budget of Rs. 5,00,000 and is scheduled to be completed in 1 year. Table 13.2 shows
the cumulative values of planned costs, earned value and actual costs at the end of each of the first
4 months.
BCWS BCWP ACWP
Planned Earned Actual
Month Cost Value Cost CPI
1 20000 24000 23500
2 60000 58000 62000
3 110000 95000 105000
4 220000 190000 205000
SPI
The following data (Table 13.4) are known about a project when the project review was conducted:
CV
-2
-0.5
-1.2
-0.5
-1
0
0
0
0
0
-5.2
The following information (Table 13.6) is available at the end of day 40 of a new plant erection
project. Determine if the project is under control based on earned value evaluation system, and if
not, what is the likely extent of cost and time overruns at completion.