List of all On-going Government & Private Construction Contracts including Contracts awarded but not Yet Started

Business Name : SAVER’S BUILDERS CORPORATION

Business Address : Purok 7 JP. Rizal, Butuan City 8600, Aqusan del Norte
a. Owner’s Name a. Date Awarded
Nature of Work Bidder Rate % of Accomplishment Value of Outstanding
Name of Contract/ Project Cost b. Address b. Date Started Works/Undelivered
Portion
c. Telephone No. Description % c. Date Completion Planned Actual
Government
1. Upgrading of Butuan Medical Center a. DOH-Region Office Installation of Fire Straight a. Dec. 15, 2017 3,189,905.30
and Installation of Five Sprinklet System, b. Butuan City Sprinklet System Contract 100% b. Jan. 15, 2018 20% 25% (Suspended due to revised
Butuan City (Phase I Reg.HFEP) c. c. May 24, 2018 plan)
P4,253,207.07
2. Upgrading of Butuan Medical Center a. DOH-Region Office Installation of Fire Straight a. Dec. 15, 2017 2,335,308.24
and Installation of Five Sprinklet System, b. Butuan City Sprinklet System Contract 100% b. Jan. 15, 2018 30% 35% (Suspended due to revised
Butuan City (Phase II) c. c. May 24, 2018 plan)
P3,592,791.91
3. Construction of Multi Purpose Covered a. COA-RO XIII Construction of Straight a. Jan. 17, 2018
Court, Phase I COA RA XIII, South Montilla b. Butuan City Covered Court Contract 100% b. Feb. 16, 2018 95% 95% 324,437.74
Blvd., Butuan City c. c. Oct. 03, 2018
P7,137,039.28
4. Completion of State of the Art Library a. CSU-Cabadbaran Completion of Library Straight a. Jan. 24, 2018
((Phase III) T. Curato St. Cabadbaran City, b. Cabadbaran City Building Contract 100% b. Feb. 26, 2018 92% 95% 619,192.54
Agusan del Norte c. c. Sept. 25, 2018
P12,383,850,76
5. Construction of Line Canal Brgy. a. DA- Caraga Region Straight a. June 28, 2018
Taguibo, Butuan City b. Butuan City Line Canal Contract 100% b. July 13, 2018 65% 75% 526,589.93
P2,106,359.72 c. c. Nov. 21, 2018
6. Const. of Information Communication a. Caraga State Straight a. Aug. 17, 2018
Technology (ICT) Center, CSU Ampayon, University ICT Center Contract 100% b. Sept. 07, 2018 20% 30% 6,670,079.20
Butuan City b. Ampayon, Butuan c. Dec. 17, 2018
P9,528,684.57 City
c.
7. Completion of D.O. Plaza Memorial a. DOH- Region Office Completion of Hospital Straight a. Sept. 19, 2018
Hospital (Phase VII) Patin-ay, Agusan del b. Butuan City Contract 100% 0% 0% 3,559,288.20
Sur c.
P3,559,288.20
TOTAL 17,224,801.15

Submitted By : ADRIENNE BOSTON


Designation : Authorized Managing Officer
Date : October 04, 2108
`
Statement of all Competed & Private Construction Contracts which are similar in nature

Business Name : SAVER’S BUILDERS CORPORATION

Business Address : Purok 7 JP. Rizal, Butuan City 8600, Aqusan del Norte

a. Owner’s Name a. Amount at Awarded a. Date Awarded

Name of Contract b. Address Bidder’s Rate b. Amount at Completion b. Date Started


Nature of Work
Description %
c. Telephone No. Date Completion
c. Duration
Government
1. Construction of Field Office Perimeter Fence DSWD Caraga Region Straight P 512,675.95 a. Dec. 31, 2013
Capitol Site, Butuan City XIII, Capitol Site Butuan Perimeter Fence Contract 100% P 512,675.95 b. Jan. 16, 2015
City 53 C.D. c. Feb. 28, 2014
2. Construction of One (1) Unit Day Care Center DSWD Caraga Region One (1) Storey Straight P 897, 954.42 a. Mar. 05, 2014
Suyangan, General Luna, Surigao del Norte XIII, Capitol Site Butuan Building Contract 100% P 897, 954.42 b. Mar. 14, 2014
City 65 C.D. c. May 12, 2014
3. Construction of DTRC Perimeter Fence DOH Region XIII, Pizzaro Perimeter Fence, Straight P 6,360816.20 a. Nov. 24, 2014
Anomar, Surigao City St., Butuan City Drainage and Contract 100% P 6,911,491.44 b. Feb. 08, 2015
Guard House 150 C.D. c. July 23, 2015
4. Construction of Roof Deck BIR R17 J. Rosales Ave., Construction of Straight P 1,563,898.35 a. Oct. 22, 2015
BIR RDO No. 104, Bayugan City Butuan City Roof Deck Contract 100% P 1,719,656.54 b. Nov. 15, 2015
135 C.D. c. May 06, 2016
5. Construction of Magpayang BHS Birthing DOH Region XIII, Pizzaro One (1) Storey Straight P 987,589.70 a. Sept. 24, 2015
Facility Magpayang, Mainit Surigao del Norte St, Butuan City Building Contract 100% P 999,730.99 b. Oct. 12, 2015
60 C.D. c. Dec. 25, 2015

`
Submitted By : ADRIENNE BOSTON
Designation : Authorized Managing Officer
Date : December 03, 2018.

ORIGINAL/APPROVED 1st Month 2nd Month 3rd Month


ITEM NO. DESCRIPTION % WEIGHT
TOTAL COST 15 DAYS 15 DAYS 15 DAYS 15 DAYS 15 DAYS 15 DAYS

B.7(2) Occupational Safety & Health Program 170,424.25 8.39%

Part A Earthworks 67,738.70 3.34%

Part B Plain and Reinforced Concrete Works 213,708.38 10.52%

C1 MASONRY WORKS 72,371.86 3.56%

C2 FABRICATED MATERIALS 130,160.69 6.41%

C3 FINISHING WORKS 216,110.58 10.64%

C4 PAINTING WORKS 248,161.09 12.22%

C5 ROOF FRAMING ROOFING WORKS 518,435.29 25.53%

C6 PLUMBING/SANITARY WORKS 101,686.38 5.01%

PART D ELECTRICAL WORKS 291,846.78 14.37%

TOTAL PROJECT COST 2,030,643.99 100%


3.34 % 10.52% 10.64% 29.09% 33.18% 13.22%
Cumulative Accomplishment 3.34% 13.86% 24.50% 53.60% 86.78% 100.00%

Cumulative Actual Accomplishment

Slippage

`
Contract Name : Extension of Quality Assurance and Hydrology Division
Location of Contract : Brgy. Doongan, Butuan City
Contractor : SAVER’S BUILDERS CORPORATION
Duration : 90 Calendar Days
Submitted by:
ADRIENNE BOSTON
Authorized Managing Officer

SAVER’S BUILDERS CORPORATION