Professional Documents
Culture Documents
Q.no 1. Abstract of Estimate (Form) Has
Q.no 1. Abstract of Estimate (Form) Has
testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Seat No -
Total number of questions : 60
1) All questions are Multiple Choice Questions having single correct option.
7) Use only black/blue ball point pen to darken the appropriate circle.
A : cum
B : sqm
C : rm
D : kg
Q.no 4. In long wall and short wall method wall are divided in to
How many groups.
A : one
B : three
C : eight
D : two
A : Roofing method
A : Quotation
B : Revised estimate
C : Labour cost
D : Earth work
A : Contractor
B : Supervisor
C : Engineer In charge
D : Client
A : cum
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 2/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
B : sqm
C : rm
D : kg
A : Plinth work
B : Architectural design
C : Project management
D : Supplementary estimate
A : 15-20%
B : 5-8%
C : 25-30%
D : 60-70%
Q.no 12. A rectangular room having size 7.5m x 3.0m. how many long wall are there?
A : one
B : four
C : two
D : five
A : P.C.C, Excavation,
Filling ,Footing
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 3/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
B : Footing,
P.C.C,
Excavation,
Filling
C : Excavation,
P.C.C,
Footing,
Filling
D : Filling,
Excavation,
Footing,
Filling
Q.no 15. The document in which the Contractor indicates the cost of the Works, on the basis of
the foreseen quantities of items of work and the fixed unit prices applicable to them.
A : Tender Notice
B : Measurement Sheet
C : BOQ
D : Retention
B : Indent of materials
C : Concept drawings
D : Approval drawings
Q.no 17. 150mm thick wall of 18 square meter area have opening for exhaust fan 0.30m x 0.30m.
The wall quantity will be
B : 18 square meter
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 4/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 18. Which sheets are used to work out the quantities.
A : Abstract sheet
B : Measurement sheet
C : BOQ sheet
D : Plain sheet
Q.no 19. Area of half thick brick masonary wall is 15 sqm. The door opening size in wall is 1.20m
x 2.50m. The quantity of wall will be
A : Detailed Estimate
B : Measurement sheet
C : Bill of Quantities
D : Indent of materials
Q.no 21. A chamber of size 1.00m x 1.00m x 1.50m is plastered from inside with base. The plaster
area will be
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 5/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 23. Money paid to confirm a contract. OR Deposit enclosed along with the sealed tender
documents
A : EMD
B : RA BILL
C : INVOICE
D : NOTICE
A : Extra Items of Work needed to be done on site for the additional instructions by the owner
B : Additional Quantities against some items may be required due to variation in site condition
Q.no 25. For the delay between the time prescribed in the Contract or the extended time for
completion, Contractor shall pay to the Employer the sum specified in the Contract is called as
A : Extra item
B : Sinking fund
C : liquidated damages
D : EMD
Q.no 26. To rest column shuttering on trapezoidal footing top, the minimum flat width on all
sides of column should be
A : 25mm
B : 300mm
C : 100mm
D : No projection
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 6/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 28. Room of 5.00m x 4.00m size has two door openings of 1.00m each in 230mm thick brick
wall. The flooring area will be
A : English Method
A : Tendering
B : Availability of materials
C : Plinth work
D : R C C work
A : Unit of measurement
B : RCC design
C : PCC design
D : Rate of material
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 7/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 33. In center line method what are L-junctions are called
A : Overlap joints
B : Free joints
C : Cross joint
D : Lap joint
A : Concept drawings
C : Detailed drawings
Q.no 35. State the unit of measurement of 115 mm thk brick masonary
A : cum
B : sqm
C : rm
D : kg
Q.no 36. In triangular room, Two walls in right angleare of 6m & 8m length. The length of
diagonal wall will be
A : 16 m
B : 12 m
C : 10m
D:8m
Q.no 37. Allowance agreed for the increase in price for major materials
A : Price escalation
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 8/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
B : Rate Agreement
C : Indent
D : Invoice
D : Tendering method
Q.no 39. Circular flower bed of 1.00m height and 2.00 meter internal diameter is plastered from
inside. The plaster area of will be
C : 6.28
square meter
D : 5.47
square meter
A : plastering
B : pointing
C : both
D : none
Q.no 41. If the room size is 5 m x4 m and wall thickness is 300 mm what is the total length of total
centerline.
A : 18 m
B : 18.30 m
C : 18.60 m
D : 17.70 m
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 9/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 43. Two door opening of size 1.25m x 2.10m are placed on either side RCC column If lintel
bearing is 250mm then total length of lintel over two openings will be
A : 3.00 m
B : 2.75 m
C : 1.50 m
D : 1.75m
Q.no 44. Wall tile of 1.50m height is fixed in bath room of size 2.00m x 1.50m with door opening
0.80m x 2.10m. The wall tile area will be
Q.no 46. Each certificate supersedes previous certificates, and eventually the final account
supersedes all interim certificates issued during construction. Choose the correct option
A : false
B : PARTIALY TRUE
C : true
D : NOT APPLICABLE
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 10/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 47. A rolling shutter opening in 230mm thick brick wall is 4.00m x 5.00m high. The plaster
area of wall thickness (jam) will be
Q.no 48. What will be the deduction in 230 thk brick work ,if the room is having two doors of size
0.9x2.1 and three windows of size 1.5 x1.20
A : 5.0 cmt
B : 2.1114 cmt
C : 2.414 cmt
D : 2.141 cmt
B : Finding out the quantities of works from detailed measurement of various items
C : List of items which can be safely taken off from the proposed work
A : Plinth work
C : Construction management
D : Indent of materials
A : Table of content
C : Bottom to top
D : Top to bottom
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 11/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 52. The value of sum retained by employer for any future defects on the work done by
contractor.
A : Rate Analysis
B : Retention
C : Price escalation
D : Abstract
A : 18.56
B : 18.65
C : 18.35
D : 18.53
Q.no 54. Find the width, if the total quantity of P.C.C is 1.35 cmt.
L=7.5 m and Ht=0.15 m
A : 0.9 m
B : 1.35 m
C : 1.50 m
D : 1.20 m
B : 2% of actual
estimated cost of work
A : Approval drawing
B : Project management
C : Indent of materials
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 12/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
D : Quantity of materials
A : cum
B : sqm
C : rm
D : kg
D : Provision made for Unknown type of work whose details cannot be ascertained at the time of
preparing estimate
Q.no 60. Find the length of long wall for foundation step-1? if the total quantity is 2.232 cmt.
B=0.9m and Ht=0.40 m
A : 6.0 m
B : 6.20m
C : 5.90 m
D : 6.40 m
A : Rft.
B : Rmts.
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 13/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : Sqmts.
D : Cmts.
Q.no 2. A service window of size 1.50m x 1.00m is provided in brick wall. Both side deduction
from plaster area will be
D : No deduction
Q.no 3. What should be the order while entering the dimensions in measurement sheet.
B : Numbers ,
Length,
Width,
Height
C : Length,
Numbers.
Height,
Width
D : Width,
Length,
Numbers,
Height
A : cum
B : sqm
C : rm
D : kg
Q.no 5. Deduction against ‘Beam to Wall’ connection from plaster measurement will be
B : Number
C : 50% deduction
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 14/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
D : No deduction
A : IS 456
B : IS 1200
C : ISC1345
D : ISC457
A : cum
B : sqm
C : rm
D : kg
A : cum
B : sqm
C : rm
D : kg
Q.no 10. Essential document to verify the amount of work done claimed in bills
A : I card
B : Measurement sheet
C : Certificates
D : Indent
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 15/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : Wash basin
B : concreting
C : masonry
D : Both 2 and 3
Q.no 12. While recording measurement for toilet flooring, the floor trap grating area is deducted
A : 100%
B : 75%
C : 50%
D : No deduction
Q.no 13. A brickbat waterproof treatment in toilet sunken portion of 300mm deep is measured in
unit
A : Square meter
B : Number
C : Job
D : Cubic meter
A : Specifications
B : Concept drawings
C : Indent of materials
D : Approval drawings
Q.no 15. As per IS code 1200, the quantity for masonary wall above 230mm thick should be
recorded in
A : Square meter
B : Cubic meter
C : Running meter
D : Numbers
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 16/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 16. While recording the measurement of RCC item, the quantity of reinforcement steel to
be deducted
A : 50%
B : 25%
C : 100%
D : No Deduction
Q.no 17. The sum agreed in the Contract as payable to the Contractor for the execution and
completion of the Works and for remedying of any defects therein in accordance with the
Contract.
A : INVOICE
B : EMD
C : Retention
D : Contract Sum
A : true
B : false
C : Don’t know
D : May be
A : 6-8 Months
B : 2-2.5 Months
C : 12-15 Months
D : 1-3Months
A : Working Drawings
B : Specifications
C : Rates of Materials
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 17/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : cum
B : sqm
C : rm
D : kg
Q.no 22. Which Amount is kept to ensure that the contractor properly completes the activities
required of them under the contract.
A : Deposit
B : Retention
C : Sinking Fund
D : Advance
Q.no 24. Room of size 5.00m x 4.00m has two door openings of 1.00m each. The skirting length
will be
A : Wash basin
B : Kitchen sink
C : urinal
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 18/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
D : pipes
A : Plinth work
C : Indent of materials
A : Financial aspects
B : Architectural design
D : Tendering
A : Final bill
B : On Account payment
C : Retention
D : Earnest Money
Q.no 31. A formal request for payment made against the job completed or consumption of
material and resources that bills a specific amount.
A : Price escalation
B : Rate Agreement
C : Indent
D : Invoice
Q.no 32. Fixed period of time, starting from the date of practical completion, during which the
contractor has to rectify defects.
B : Completion Period
C : Contract
D : Interim period
A : cum
B : sqm
C : rm
D : kg
C : Electricity bills
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 20/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 37. The concrete volume of a circular column of 300mm diameter and 4.50m height will be
A : 0.23 cum
B : 0.36 cum
C : 0.32 cum
D : 0.30 cum
A : Market
B : DSR
C : FACTORY
D : MRP
Q.no 39. A room ceiling of size 3.00m x 6.00m have beam projection of 3.00m x 0.23m x 0.30m
deep. The ceiling plaster area will be
A : cum
B : sqm
C : rm
D : kg
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 21/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 41. Find the width, if the total quantity of P.C.C is 1.35 cmt.
L=7.5 m and Ht=0.15 m
A : 0.9 m
B : 1.35 m
C : 1.50 m
D : 1.20 m
A : cum
B : sqm
C : rm
D : kg
A : 18.56
B : 18.65
C : 18.35
D : 18.53
Q.no 44. What will be the deduction in 230 thk brick work ,if the room is having two doors of size
0.9x2.1 and three windows of size 1.5 x1.20
A : 5.0 cmt
B : 2.1114 cmt
C : 2.414 cmt
D : 2.141 cmt
B : 2% of actual
estimated cost of work
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 22/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 48. Each certificate supersedes previous certificates, and eventually the final account
supersedes all interim certificates issued during construction. Choose the correct option
A : false
B : PARTIALY TRUE
C : true
D : NOT APPLICABLE
B : Finding out the quantities of works from detailed measurement of various items
C : List of items which can be safely taken off from the proposed work
Q.no 50. If the room size is 5 m x4 m and wall thickness is 300 mm what is the total length of total
centerline.
A : 18 m
B : 18.30 m
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 23/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : 18.60 m
D : 17.70 m
Q.no 51. The value of sum retained by employer for any future defects on the work done by
contractor.
A : Rate Analysis
B : Retention
C : Price escalation
D : Abstract
Q.no 52. Find the length of long wall for foundation step-1? if the total quantity is 2.232 cmt.
B=0.9m and Ht=0.40 m
A : 6.0 m
B : 6.20m
C : 5.90 m
D : 6.40 m
A : Plinth work
C : Construction management
D : Indent of materials
Q.no 54. Two door opening of size 1.25m x 2.10m are placed on either side RCC column If lintel
bearing is 250mm then total length of lintel over two openings will be
A : 3.00 m
B : 2.75 m
C : 1.50 m
D : 1.75m
A : Approval drawing
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 24/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
B : Project management
C : Indent of materials
D : Quantity of materials
D : Provision made for Unknown type of work whose details cannot be ascertained at the time of
preparing estimate
Q.no 57. A rolling shutter opening in 230mm thick brick wall is 4.00m x 5.00m high. The plaster
area of wall thickness (jam) will be
A : Table of content
C : Bottom to top
D : Top to bottom
Q.no 59. Wall tile of 1.50m height is fixed in bath room of size 2.00m x 1.50m with door opening
0.80m x 2.10m. The wall tile area will be
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 25/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : 15-20%
B : 5-8%
C : 25-30%
D : 60-70%
Q.no 2. 150mm thick wall of 18 square meter area have opening for exhaust fan 0.30m x 0.30m.
The wall quantity will be
B : 18 square meter
Q.no 3. The document in which the Contractor indicates the cost of the Works, on the basis of the
foreseen quantities of items of work and the fixed unit prices applicable to them.
A : Tender Notice
B : Measurement Sheet
C : BOQ
D : Retention
A : Roofing method
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 26/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : Contractor
B : Supervisor
C : Engineer In charge
D : Client
A : Detailed Estimate
B : Measurement sheet
C : Bill of Quantities
D : Indent of materials
A : Plinth work
B : Architectural design
C : Project management
D : Supplementary estimate
A : cum
B : sqm
C : rm
D : kg
Q.no 12. Area of half thick brick masonary wall is 15 sqm. The door opening size in wall is 1.20m
x 2.50m. The quantity of wall will be
A : P.C.C, Excavation,
Filling ,Footing
B : Footing,
P.C.C,
Excavation,
Filling
C : Excavation,
P.C.C,
Footing,
Filling
D : Filling,
Excavation,
Footing,
Filling
Q.no 14. Which sheets are used to work out the quantities.
A : Abstract sheet
B : Measurement sheet
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 28/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : BOQ sheet
D : Plain sheet
Q.no 16. A rectangular room having size 7.5m x 3.0m. how many long wall are there?
A : one
B : four
C : two
D : five
A : Quotation
B : Revised estimate
C : Labour cost
D : Earth work
B : Indent of materials
C : Concept drawings
D : Approval drawings
Q.no 19. In long wall and short wall method wall are divided in to
How many groups.
A : one
B : three
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 29/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : eight
D : two
A : cum
B : sqm
C : rm
D : kg
Q.no 21. State the unit of measurement of 115 mm thk brick masonary
A : cum
B : sqm
C : rm
D : kg
Q.no 22. Money paid to confirm a contract. OR Deposit enclosed along with the sealed tender
documents
A : EMD
B : RA BILL
C : INVOICE
D : NOTICE
Q.no 23. Room of 5.00m x 4.00m size has two door openings of 1.00m each in 230mm thick brick
wall. The flooring area will be
A : English Method
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 30/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : Unit of measurement
B : RCC design
C : PCC design
D : Rate of material
A : Tendering
B : Availability of materials
C : Plinth work
D : R C C work
Q.no 27. In triangular room, Two walls in right angleare of 6m & 8m length. The length of
diagonal wall will be
A : 16 m
B : 12 m
C : 10m
D:8m
Q.no 28. In center line method what are L-junctions are called
A : Overlap joints
B : Free joints
C : Cross joint
D : Lap joint
A : plastering
B : pointing
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 31/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : both
D : none
Q.no 31. A chamber of size 1.00m x 1.00m x 1.50m is plastered from inside with base. The plaster
area will be
A : Extra Items of Work needed to be done on site for the additional instructions by the owner
B : Additional Quantities against some items may be required due to variation in site condition
Q.no 33. To rest column shuttering on trapezoidal footing top, the minimum flat width on all
sides of column should be
A : 25mm
B : 300mm
C : 100mm
D : No projection
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 32/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 35. Circular flower bed of 1.00m height and 2.00 meter internal diameter is plastered from
inside. The plaster area of will be
C : 6.28
square meter
D : 5.47
square meter
A : Concept drawings
C : Detailed drawings
Q.no 37. For the delay between the time prescribed in the Contract or the extended time for
completion, Contractor shall pay to the Employer the sum specified in the Contract is called as
A : Extra item
B : Sinking fund
C : liquidated damages
D : EMD
D : Tendering method
Q.no 39. Allowance agreed for the increase in price for major materials
A : Price escalation
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 33/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
B : Rate Agreement
C : Indent
D : Invoice
C : Electricity bills
Q.no 41. A rolling shutter opening in 230mm thick brick wall is 4.00m x 5.00m high. The plaster
area of wall thickness (jam) will be
A : cum
B : sqm
C : rm
D : kg
Q.no 43. Find the width, if the total quantity of P.C.C is 1.35 cmt.
L=7.5 m and Ht=0.15 m
A : 0.9 m
B : 1.35 m
C : 1.50 m
D : 1.20 m
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 34/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
B : 2% of actual
estimated cost of work
A : Approval drawing
B : Project management
C : Indent of materials
D : Quantity of materials
A : Table of content
C : Bottom to top
D : Top to bottom
Q.no 48. The value of sum retained by employer for any future defects on the work done by
contractor.
A : Rate Analysis
B : Retention
C : Price escalation
D : Abstract
Q.no 49. What will be the deduction in 230 thk brick work ,if the room is having two doors of size
0.9x2.1 and three windows of size 1.5 x1.20
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 35/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : 5.0 cmt
B : 2.1114 cmt
C : 2.414 cmt
D : 2.141 cmt
Q.no 50. Each certificate supersedes previous certificates, and eventually the final account
supersedes all interim certificates issued during construction. Choose the correct option
A : false
B : PARTIALY TRUE
C : true
D : NOT APPLICABLE
Q.no 51. Two door opening of size 1.25m x 2.10m are placed on either side RCC column If lintel
bearing is 250mm then total length of lintel over two openings will be
A : 3.00 m
B : 2.75 m
C : 1.50 m
D : 1.75m
Q.no 52. Wall tile of 1.50m height is fixed in bath room of size 2.00m x 1.50m with door opening
0.80m x 2.10m. The wall tile area will be
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 36/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
B : Finding out the quantities of works from detailed measurement of various items
C : List of items which can be safely taken off from the proposed work
A : 18.56
B : 18.65
C : 18.35
D : 18.53
A : Plinth work
C : Construction management
D : Indent of materials
Q.no 57. Find the length of long wall for foundation step-1? if the total quantity is 2.232 cmt.
B=0.9m and Ht=0.40 m
A : 6.0 m
B : 6.20m
C : 5.90 m
D : 6.40 m
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 37/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
D : Provision made for Unknown type of work whose details cannot be ascertained at the time of
preparing estimate
Q.no 59. If the room size is 5 m x4 m and wall thickness is 300 mm what is the total length of total
centerline.
A : 18 m
B : 18.30 m
C : 18.60 m
D : 17.70 m
Q.no 2. A brickbat waterproof treatment in toilet sunken portion of 300mm deep is measured in
unit
A : Square meter
B : Number
C : Job
D : Cubic meter
A : cum
B : sqm
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 38/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : rm
D : kg
A : cum
B : sqm
C : rm
D : kg
Q.no 5. While recording measurement for toilet flooring, the floor trap grating area is deducted
A : 100%
B : 75%
C : 50%
D : No deduction
A : Rft.
B : Rmts.
C : Sqmts.
D : Cmts.
Q.no 7. As per IS code 1200, the quantity for masonary wall above 230mm thick should be
recorded in
A : Square meter
B : Cubic meter
C : Running meter
D : Numbers
Q.no 8. Deduction against ‘Beam to Wall’ connection from plaster measurement will be
B : Number
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 39/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : 50% deduction
D : No deduction
A : Specifications
B : Concept drawings
C : Indent of materials
D : Approval drawings
Q.no 10. Essential document to verify the amount of work done claimed in bills
A : I card
B : Measurement sheet
C : Certificates
D : Indent
A : IS 456
B : IS 1200
C : ISC1345
D : ISC457
Q.no 12. The sum agreed in the Contract as payable to the Contractor for the execution and
completion of the Works and for remedying of any defects therein in accordance with the
Contract.
A : INVOICE
B : EMD
C : Retention
D : Contract Sum
A : Working Drawings
B : Specifications
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 40/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : Rates of Materials
A : Wash basin
B : concreting
C : masonry
D : Both 2 and 3
Q.no 15. What should be the order while entering the dimensions in measurement sheet.
B : Numbers ,
Length,
Width,
Height
C : Length,
Numbers.
Height,
Width
D : Width,
Length,
Numbers,
Height
A : 6-8 Months
B : 2-2.5 Months
C : 12-15 Months
D : 1-3Months
A : true
B : false
C : Don’t know
D : May be
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 41/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : cum
B : sqm
C : rm
D : kg
Q.no 19. While recording the measurement of RCC item, the quantity of reinforcement steel to
be deducted
A : 50%
B : 25%
C : 100%
D : No Deduction
Q.no 20. A service window of size 1.50m x 1.00m is provided in brick wall. Both side deduction
from plaster area will be
D : No deduction
A : Final bill
B : On Account payment
C : Retention
D : Earnest Money
Q.no 22. Which Amount is kept to ensure that the contractor properly completes the activities
required of them under the contract.
A : Deposit
B : Retention
C : Sinking Fund
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 42/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
D : Advance
A : Market
B : DSR
C : FACTORY
D : MRP
A : cum
B : sqm
C : rm
D : kg
Q.no 25. A formal request for payment made against the job completed or consumption of
material and resources that bills a specific amount.
A : Price escalation
B : Rate Agreement
C : Indent
D : Invoice
Q.no 26. Room of 5.00m x 4.00m size has two door openings of 1.00m each in 230mm thick brick
wall. The flooring area will be
Q.no 27. Money paid to confirm a contract. OR Deposit enclosed along with the sealed tender
documents
A : EMD
B : RA BILL
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 43/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : INVOICE
D : NOTICE
A : cum
B : sqm
C : rm
D : kg
A : Wash basin
B : Kitchen sink
C : urinal
D : pipes
Q.no 33. A room ceiling of size 3.00m x 6.00m have beam projection of 3.00m x 0.23m x 0.30m
deep. The ceiling plaster area will be
Q.no 34. Fixed period of time, starting from the date of practical completion, during which the
contractor has to rectify defects.
B : Completion Period
C : Contract
D : Interim period
Q.no 36. The concrete volume of a circular column of 300mm diameter and 4.50m height will be
A : 0.23 cum
B : 0.36 cum
C : 0.32 cum
D : 0.30 cum
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 45/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : cum
B : sqm
C : rm
D : kg
Q.no 39. Room of size 5.00m x 4.00m has two door openings of 1.00m each. The skirting length
will be
Q.no 40. State the unit of measurement of 115 mm thk brick masonary
A : cum
B : sqm
C : rm
D : kg
Q.no 41. Two door opening of size 1.25m x 2.10m are placed on either side RCC column If lintel
bearing is 250mm then total length of lintel over two openings will be
A : 3.00 m
B : 2.75 m
C : 1.50 m
D : 1.75m
A : 18.56
B : 18.65
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 46/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : 18.35
D : 18.53
Q.no 43. Find the length of long wall for foundation step-1? if the total quantity is 2.232 cmt.
B=0.9m and Ht=0.40 m
A : 6.0 m
B : 6.20m
C : 5.90 m
D : 6.40 m
Q.no 44. Find the width, if the total quantity of P.C.C is 1.35 cmt.
L=7.5 m and Ht=0.15 m
A : 0.9 m
B : 1.35 m
C : 1.50 m
D : 1.20 m
Q.no 45. Wall tile of 1.50m height is fixed in bath room of size 2.00m x 1.50m with door opening
0.80m x 2.10m. The wall tile area will be
A : Approval drawing
B : Project management
C : Indent of materials
D : Quantity of materials
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 47/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
D : Provision made for Unknown type of work whose details cannot be ascertained at the time of
preparing estimate
Q.no 48. If the room size is 5 m x4 m and wall thickness is 300 mm what is the total length of total
centerline.
A : 18 m
B : 18.30 m
C : 18.60 m
D : 17.70 m
Q.no 49. Each certificate supersedes previous certificates, and eventually the final account
supersedes all interim certificates issued during construction. Choose the correct option
A : false
B : PARTIALY TRUE
C : true
D : NOT APPLICABLE
Q.no 50. The value of sum retained by employer for any future defects on the work done by
contractor.
A : Rate Analysis
B : Retention
C : Price escalation
D : Abstract
B : Finding out the quantities of works from detailed measurement of various items
C : List of items which can be safely taken off from the proposed work
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 48/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 53. A rolling shutter opening in 230mm thick brick wall is 4.00m x 5.00m high. The plaster
area of wall thickness (jam) will be
A : Plinth work
C : Construction management
D : Indent of materials
A : cum
B : sqm
C : rm
D : kg
B : 2% of actual
estimated cost of work
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 49/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : Table of content
C : Bottom to top
D : Top to bottom
Q.no 59. What will be the deduction in 230 thk brick work ,if the room is having two doors of size
0.9x2.1 and three windows of size 1.5 x1.20
A : 5.0 cmt
B : 2.1114 cmt
C : 2.414 cmt
D : 2.141 cmt
Q.no 1. The document in which the Contractor indicates the cost of the Works, on the basis of the
foreseen quantities of items of work and the fixed unit prices applicable to them.
A : Tender Notice
B : Measurement Sheet
C : BOQ
D : Retention
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 50/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : Roofing method
A : Quotation
B : Revised estimate
C : Labour cost
D : Earth work
A : cum
B : sqm
C : rm
D : kg
A : 15-20%
B : 5-8%
C : 25-30%
D : 60-70%
Q.no 7. A rectangular room having size 7.5m x 3.0m. how many long wall are there?
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 51/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : one
B : four
C : two
D : five
A : Plinth work
B : Architectural design
C : Project management
D : Supplementary estimate
Q.no 11. Which sheets are used to work out the quantities.
A : Abstract sheet
B : Measurement sheet
C : BOQ sheet
D : Plain sheet
Q.no 13. Area of half thick brick masonary wall is 15 sqm. The door opening size in wall is 1.20m
x 2.50m. The quantity of wall will be
A : Contractor
B : Supervisor
C : Engineer In charge
D : Client
A : P.C.C, Excavation,
Filling ,Footing
B : Footing,
P.C.C,
Excavation,
Filling
C : Excavation,
P.C.C,
Footing,
Filling
D : Filling,
Excavation,
Footing,
Filling
B : Indent of materials
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 53/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : Concept drawings
D : Approval drawings
A : Detailed Estimate
B : Measurement sheet
C : Bill of Quantities
D : Indent of materials
Q.no 18. In long wall and short wall method wall are divided in to
How many groups.
A : one
B : three
C : eight
D : two
A : cum
B : sqm
C : rm
D : kg
Q.no 20. 150mm thick wall of 18 square meter area have opening for exhaust fan 0.30m x 0.30m.
The wall quantity will be
B : 18 square meter
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 54/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
Q.no 22. A chamber of size 1.00m x 1.00m x 1.50m is plastered from inside with base. The plaster
area will be
A : Extra Items of Work needed to be done on site for the additional instructions by the owner
B : Additional Quantities against some items may be required due to variation in site condition
Q.no 24. In triangular room, Two walls in right angleare of 6m & 8m length. The length of
diagonal wall will be
A : 16 m
B : 12 m
C : 10m
D:8m
Q.no 25. In center line method what are L-junctions are called
A : Overlap joints
B : Free joints
C : Cross joint
D : Lap joint
Q.no 26. Allowance agreed for the increase in price for major materials
A : Price escalation
B : Rate Agreement
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 55/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
C : Indent
D : Invoice
A : plastering
B : pointing
C : both
D : none
A : Plinth work
C : Indent of materials
A : Tendering
B : Availability of materials
C : Plinth work
D : R C C work
A : English Method
A : Concept drawings
C : Detailed drawings
Q.no 34. Circular flower bed of 1.00m height and 2.00 meter internal diameter is plastered from
inside. The plaster area of will be
C : 6.28
square meter
D : 5.47
square meter
C : Electricity bills
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 57/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
D : Tendering method
Q.no 37. To rest column shuttering on trapezoidal footing top, the minimum flat width on all
sides of column should be
A : 25mm
B : 300mm
C : 100mm
D : No projection
Q.no 38. For the delay between the time prescribed in the Contract or the extended time for
completion, Contractor shall pay to the Employer the sum specified in the Contract is called as
A : Extra item
B : Sinking fund
C : liquidated damages
D : EMD
A : Financial aspects
B : Architectural design
D : Tendering
A : Unit of measurement
B : RCC design
C : PCC design
D : Rate of material
Q.no 41. What will be the deduction in 230 thk brick work ,if the room is having two doors of size
0.9x2.1 and three windows of size 1.5 x1.20
A : 5.0 cmt
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 58/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
B : 2.1114 cmt
C : 2.414 cmt
D : 2.141 cmt
A : cum
B : sqm
C : rm
D : kg
B : 2% of actual
estimated cost of work
A : 18.56
B : 18.65
C : 18.35
D : 18.53
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 59/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
B : Finding out the quantities of works from detailed measurement of various items
C : List of items which can be safely taken off from the proposed work
Q.no 47. Each certificate supersedes previous certificates, and eventually the final account
supersedes all interim certificates issued during construction. Choose the correct option
A : false
B : PARTIALY TRUE
C : true
D : NOT APPLICABLE
Q.no 49. Find the length of long wall for foundation step-1? if the total quantity is 2.232 cmt.
B=0.9m and Ht=0.40 m
A : 6.0 m
B : 6.20m
C : 5.90 m
D : 6.40 m
Q.no 50. The value of sum retained by employer for any future defects on the work done by
contractor.
A : Rate Analysis
B : Retention
C : Price escalation
D : Abstract
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 60/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
A : Table of content
C : Bottom to top
D : Top to bottom
A : Plinth work
C : Construction management
D : Indent of materials
Q.no 54. A rolling shutter opening in 230mm thick brick wall is 4.00m x 5.00m high. The plaster
area of wall thickness (jam) will be
Q.no 55. If the room size is 5 m x4 m and wall thickness is 300 mm what is the total length of total
centerline.
A : 18 m
B : 18.30 m
C : 18.60 m
D : 17.70 m
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 61/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
D : Provision made for Unknown type of work whose details cannot be ascertained at the time of
preparing estimate
Q.no 57. Find the width, if the total quantity of P.C.C is 1.35 cmt.
L=7.5 m and Ht=0.15 m
A : 0.9 m
B : 1.35 m
C : 1.50 m
D : 1.20 m
Q.no 58. Two door opening of size 1.25m x 2.10m are placed on either side RCC column If lintel
bearing is 250mm then total length of lintel over two openings will be
A : 3.00 m
B : 2.75 m
C : 1.50 m
D : 1.75m
A : Approval drawing
B : Project management
C : Indent of materials
D : Quantity of materials
Q.no 60. Wall tile of 1.50m height is fixed in bath room of size 2.00m x 1.50m with door opening
0.80m x 2.10m. The wall tile area will be
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 62/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 63/63