Total number of questions : 60

10307_Quantity Surveying and Estimation I


Time : 1hr
Max Marks : 50
N.B

1) All questions are Multiple Choice Questions having single correct option.

2) Attempt any 50 questions out of 60.

3) Use of calculator is allowed.

4) Each question carries 1 Mark.

5) Specially abled students are allowed 20 minutes extra for examination.

6) Do not use pencils to darken answer.

7) Use only black/blue ball point pen to darken the appropriate circle.

8) No change will be allowed once the answer is marked on OMR Sheet.

9) Rough work shall not be done on OMR sheet or on question paper.

10) Darken ONLY ONE CIRCLE for each answer.

Q.no 1. Abstract of Estimate (Form) has

A : Length, Breadth, Height, Quantity

B : Number of Items , Quality, Make

C : Quantity, Unit, Rate, Unit of Rate

D : % of Total Quantity method

Q.no 2. State the unit of measurement of External wall plaster

A : cum

B : sqm

C : rm

D : kg

Q.no 3. Measurement Form has

A : Number of items, Quality , Make


https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 1/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Length, Breadth, Height, Quantity

C : Quantity, Unit, Rate, Unit of Rate

D : Quality, brand, Heavy, Medium

Q.no 4. In long wall and short wall method wall are divided in to
How many groups.

A : one

B : three

C : eight

D : two

Q.no 5. One of the methods of computing quantities

A : Roofing method

B : Long wall and Short wall method

C : Frame analysis method

D : Framed construction method

Q.no 6. One of the Type of detailed estimate

A : Quotation

B : Revised estimate

C : Labour cost

D : Earth work

Q.no 7. The RA BILLS should be verified by

A : Contractor

B : Supervisor

C : Engineer In charge

D : Client

Q.no 8. State the unit of measurement of steel reinforcement

A : cum

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 2/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : sqm

C : rm

D : kg

Q.no 9. One of the Type of detailed estimate

A : Plinth work

B : Architectural design

C : Project management

D : Supplementary estimate

Q.no 10. One of the methods of computing quantities

A : Load bearing method

B : Framed construction method

C : Working drawing method

D : Center line method

Q.no 11. Retention amount can be how much % of project cost

A : 15-20%

B : 5-8%

C : 25-30%

D : 60-70%

Q.no 12. A rectangular room having size 7.5m x 3.0m. how many long wall are there?

A : one

B : four

C : two

D : five

Q.no 13. What sequence to be considered for execution of work.

A : P.C.C, Excavation,
Filling ,Footing

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 3/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Footing,
P.C.C,
Excavation,
Filling

C : Excavation,
P.C.C,
Footing,
Filling

D : Filling,
Excavation,
Footing,
Filling

Q.no 14. Purpose of Estimating is to

A : Ascertain amount of money required by owner

B : Ascertain quantities of material

C : Fix completion period

D : All the above

Q.no 15. The document in which the Contractor indicates the cost of the Works, on the basis of
the foreseen quantities of items of work and the fixed unit prices applicable to them.

A : Tender Notice

B : Measurement Sheet

C : BOQ

D : Retention

Q.no 16. Factor which is considered while preparing a detailed estimate

A : Availability of local labour

B : Indent of materials

C : Concept drawings

D : Approval drawings

Q.no 17. 150mm thick wall of 18 square meter area have opening for exhaust fan 0.30m x 0.30m.
The wall quantity will be

A : 2.70 cubic meter

B : 18 square meter
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 4/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : 17.91 square meter

D : 2.68 cubic meter

Q.no 18. Which sheets are used to work out the quantities.

A : Abstract sheet

B : Measurement sheet

C : BOQ sheet

D : Plain sheet

Q.no 19. Area of half thick brick masonary wall is 15 sqm. The door opening size in wall is 1.20m
x 2.50m. The quantity of wall will be

A : 12.00 Square meter

B : 9.00 Square meter

C : 13.50 Square meter

D : 6.00 Square meter

Q.no 20. Abstract form is commonly known as

A : Detailed Estimate

B : Measurement sheet

C : Bill of Quantities

D : Indent of materials

Q.no 21. A chamber of size 1.00m x 1.00m x 1.50m is plastered from inside with base. The plaster
area will be

A : 6.00 square meter

B : 4.00 Square meter

C : 7.00 Square meter

D : 8.00 Square meter

Q.no 22. The Accuracy of the Estimate

A : Depends on the skill & experience of Estimator

B : Does not depend on the skill & experience of Estimator

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 5/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : Depends on the App used by the Estimator

D : Does not depend on the App used by the Estimator

Q.no 23. Money paid to confirm a contract. OR Deposit enclosed along with the sealed tender
documents

A : EMD

B : RA BILL

C : INVOICE

D : NOTICE

Q.no 24. Provisional Quantities refers to

A : Extra Items of Work needed to be done on site for the additional instructions by the owner

B : Additional Quantities against some items may be required due to variation in site condition

C : Provisions made in bulk for the labourers residing on site

D : Extra payment done on site due to change in contractor

Q.no 25. For the delay between the time prescribed in the Contract or the extended time for
completion, Contractor shall pay to the Employer the sum specified in the Contract is called as

A : Extra item

B : Sinking fund

C : liquidated damages

D : EMD

Q.no 26. To rest column shuttering on trapezoidal footing top, the minimum flat width on all
sides of column should be

A : 25mm

B : 300mm

C : 100mm

D : No projection

Q.no 27. Government Engineering Dept. Schedule of Rates

A : Changes for every district

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 6/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Does not Change for every district

C : Changes for every 1000 Km.

D : Changes for every 500 Km.

Q.no 28. Room of 5.00m x 4.00m size has two door openings of 1.00m each in 230mm thick brick
wall. The flooring area will be

A : 20.23 Square meter

B : 20.46 Square meter

C : 20.00 Square meter

D : 22.00 Square meter

Q.no 29. What P.W.D Method also called as.

A : English Method

B : Center Line method

C : Plinth Area Method

D : Long wall And short wall method

Q.no 30. Factor which is considered while preparing a detailed estimate

A : Tendering

B : Availability of materials

C : Plinth work

D : R C C work

Q.no 31. IS 1200 is referred for

A : Unit of measurement

B : RCC design

C : PCC design

D : Rate of material

Q.no 32. Approximate cost of building can be found out by

A : Project management method

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 7/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Construction management method

C : Approximate quantities method

D : Plinth work method

Q.no 33. In center line method what are L-junctions are called

A : Overlap joints

B : Free joints

C : Cross joint

D : Lap joint

Q.no 34. A detailed estimate is comprised of

A : Concept drawings

B : National building code

C : Detailed drawings

D : Structural framing plans

Q.no 35. State the unit of measurement of 115 mm thk brick masonary

A : cum

B : sqm

C : rm

D : kg

Q.no 36. In triangular room, Two walls in right angleare of 6m & 8m length. The length of
diagonal wall will be

A : 16 m

B : 12 m

C : 10m

D:8m

Q.no 37. Allowance agreed for the increase in price for major materials

A : Price escalation

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 8/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Rate Agreement

C : Indent

D : Invoice

Q.no 38. Approximate cost of building can be found out by

A : Slab and beam method

B : Service Unit method

C : Load bearing method

D : Tendering method

Q.no 39. Circular flower bed of 1.00m height and 2.00 meter internal diameter is plastered from
inside. The plaster area of will be

A : 6.91 square meter

B : 7.54 square meter

C : 6.28
square meter

D : 5.47
square meter

Q.no 40. Which item will be measured in sqm

A : plastering

B : pointing

C : both

D : none

Q.no 41. If the room size is 5 m x4 m and wall thickness is 300 mm what is the total length of total
centerline.

A : 18 m

B : 18.30 m

C : 18.60 m

D : 17.70 m

Q.no 42. A revised estimate is necessary when

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 9/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

A : Some new works or change of design is made

B : Some change of rate or quantity of material change is made

C : New Contractor is to be introduced

D : When property is up for sale

Q.no 43. Two door opening of size 1.25m x 2.10m are placed on either side RCC column If lintel
bearing is 250mm then total length of lintel over two openings will be

A : 3.00 m

B : 2.75 m

C : 1.50 m

D : 1.75m

Q.no 44. Wall tile of 1.50m height is fixed in bath room of size 2.00m x 1.50m with door opening
0.80m x 2.10m. The wall tile area will be

A : 9.30 Square meter

B : 10.50 Square meter

C : 8.82 Square meter

D : 9.85 Square meter

Q.no 45. Approximate cost of building can be found out by

A : Plinth area method

B : Cubic meter method

C : Typical bay method

D : Framed structure method

Q.no 46. Each certificate supersedes previous certificates, and eventually the final account
supersedes all interim certificates issued during construction. Choose the correct option

A : false

B : PARTIALY TRUE

C : true

D : NOT APPLICABLE

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 10/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

Q.no 47. A rolling shutter opening in 230mm thick brick wall is 4.00m x 5.00m high. The plaster
area of wall thickness (jam) will be

A : 3.22 Square meter

B : 2.30 Square meter

C : 4.14 Square meter

D : 14.00 Running meter

Q.no 48. What will be the deduction in 230 thk brick work ,if the room is having two doors of size
0.9x2.1 and three windows of size 1.5 x1.20

A : 5.0 cmt

B : 2.1114 cmt

C : 2.414 cmt

D : 2.141 cmt

Q.no 49. Quantity takeoff is

A : List of materials needed to take off the project to completion

B : Finding out the quantities of works from detailed measurement of various items

C : List of items which can be safely taken off from the proposed work

D : List of material quantities not mentioned in BOQ

Q.no 50. A detailed estimate is comprised of

A : Plinth work

B : Design data and calculations

C : Construction management

D : Indent of materials

Q.no 51. Generally items of estimate is arranged according to

A : Table of content

B : Progress of construction of work

C : Bottom to top

D : Top to bottom

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 11/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

Q.no 52. The value of sum retained by employer for any future defects on the work done by
contractor.

A : Rate Analysis

B : Retention

C : Price escalation

D : Abstract

Q.no 53. Find the length of excavation if total quantity=25.45 cmt.


B=1.3 m H=1.05 m

A : 18.56

B : 18.65

C : 18.35

D : 18.53

Q.no 54. Find the width, if the total quantity of P.C.C is 1.35 cmt.
L=7.5 m and Ht=0.15 m

A : 0.9 m

B : 1.35 m

C : 1.50 m

D : 1.20 m

Q.no 55. Contingency Fund consists of

A : 6%-8% of actual estimated cost of work

B : 2% of actual
estimated cost of work

C : 10% of actual estimated cost of work

D : 3% - 5% of actual estimated cost of work

Q.no 56. Factor which is considered while preparing a detailed estimate

A : Approval drawing

B : Project management

C : Indent of materials

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 12/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

D : Quantity of materials

Q.no 57. State the unit of measurement of T.W. Railing

A : cum

B : sqm

C : rm

D : kg

Q.no 58. In the formula to work out trapezoidal quantity in footing


, The character ‘h’ means

A : Height of base of footing

B : Total Height of footing

C : Height of Trapezoidal portion

D : Slant length of Trapezoidal portion

Q.no 59. Provisional Sum is

A : Provision made in estimate for Unforeseen Natural Calamities

B : Provision made in estimate separately for breakage & damages

C : Provision made for payment to another contractor

D : Provision made for Unknown type of work whose details cannot be ascertained at the time of
preparing estimate

Q.no 60. Find the length of long wall for foundation step-1? if the total quantity is 2.232 cmt.
B=0.9m and Ht=0.40 m

A : 6.0 m

B : 6.20m

C : 5.90 m

D : 6.40 m

Q.no 1. What is the Mode of measurement of D.P.C

A : Rft.

B : Rmts.

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 13/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : Sqmts.

D : Cmts.

Q.no 2. A service window of size 1.50m x 1.00m is provided in brick wall. Both side deduction
from plaster area will be

A : 3.00 Square meter

B : 1.50 Square meter

C : 0.75 Square meter

D : No deduction

Q.no 3. What should be the order while entering the dimensions in measurement sheet.

A : Height, Depth, Width , Length

B : Numbers ,
Length,
Width,
Height

C : Length,
Numbers.
Height,
Width

D : Width,
Length,
Numbers,
Height

Q.no 4. State the unit of measurement of flooring

A : cum

B : sqm

C : rm

D : kg

Q.no 5. Deduction against ‘Beam to Wall’ connection from plaster measurement will be

A : At actual in Square meter

B : Number

C : 50% deduction

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 14/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

D : No deduction

Q.no 6. unit of measurement is referred from which code

A : IS 456

B : IS 1200

C : ISC1345

D : ISC457

Q.no 7. State the unit of measurement of R.C.C Columns

A : cum

B : sqm

C : rm

D : kg

Q.no 8. Extra Items of Works refers to

A : Extra work done on site in addition to contractual work

B : Extra work done at another site on owner’s request

C : Extra work done using plant and machinery

D : Extra item due to change in specification

Q.no 9. State the unit of measurement of Internal wall plaster

A : cum

B : sqm

C : rm

D : kg

Q.no 10. Essential document to verify the amount of work done claimed in bills

A : I card

B : Measurement sheet

C : Certificates

D : Indent
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 15/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

Q.no 11. Which item will be measured in cum

A : Wash basin

B : concreting

C : masonry

D : Both 2 and 3

Q.no 12. While recording measurement for toilet flooring, the floor trap grating area is deducted

A : 100%

B : 75%

C : 50%

D : No deduction

Q.no 13. A brickbat waterproof treatment in toilet sunken portion of 300mm deep is measured in
unit

A : Square meter

B : Number

C : Job

D : Cubic meter

Q.no 14. A detailed estimate is comprised of

A : Specifications

B : Concept drawings

C : Indent of materials

D : Approval drawings

Q.no 15. As per IS code 1200, the quantity for masonary wall above 230mm thick should be
recorded in

A : Square meter

B : Cubic meter

C : Running meter

D : Numbers

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 16/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

Q.no 16. While recording the measurement of RCC item, the quantity of reinforcement steel to
be deducted

A : 50%

B : 25%

C : 100%

D : No Deduction

Q.no 17. The sum agreed in the Contract as payable to the Contractor for the execution and
completion of the Works and for remedying of any defects therein in accordance with the
Contract.

A : INVOICE

B : EMD

C : Retention

D : Contract Sum

Q.no 18. An Estimate is never the actual cost of the work…..

A : true

B : false

C : Don’t know

D : May be

Q.no 19. Span for Defect Liability period is

A : 6-8 Months

B : 2-2.5 Months

C : 12-15 Months

D : 1-3Months

Q.no 20. Data required for preparing Detail Estimate

A : Working Drawings

B : Specifications

C : Rates of Materials

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 17/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

D : Working Drawings&Specifications&Rates of Materials

Q.no 21. State the unit of measurement of SS railing

A : cum

B : sqm

C : rm

D : kg

Q.no 22. Which Amount is kept to ensure that the contractor properly completes the activities
required of them under the contract.

A : Deposit

B : Retention

C : Sinking Fund

D : Advance

Q.no 23. A Detailed Estimate is prepared using

A : % of Total Quantity method

B : Thumb rule Quantity method

C : Unit Quantity method

D : Unit Quality method

Q.no 24. Room of size 5.00m x 4.00m has two door openings of 1.00m each. The skirting length
will be

A : 20.00 Running meter

B : 19.00 Running meter

C : 18.00 Running meter

D : 17.00 Running meter

Q.no 25. Which item will not be measured in number

A : Wash basin

B : Kitchen sink

C : urinal

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 18/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

D : pipes

Q.no 26. Prime Cost is

A : Cost of Material + Labour

B : Cost of material + loading / unloading charge

C : Net cost of Articles at Shop

D : Cost of Articles + 5% Profit

Q.no 27. Detailed estimate comprises the cost of

A : Plinth work

B : Establishment charges for supervision

C : Indent of materials

D : Cubic meter work

Q.no 28. Reason for preparing approximate estimate is

A : Financial aspects

B : Architectural design

C : Approval from local authorities

D : Tendering

Q.no 29. A payment made on a running account,

A : Final bill

B : On Account payment

C : Retention

D : Earnest Money

Q.no 30. Detailed estimate comprises the cost of

A : Total cost of various items of work

B : Concept Design drawings

C : Furniture design drawings

D : Development control rules


https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 19/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

Q.no 31. A formal request for payment made against the job completed or consumption of
material and resources that bills a specific amount.

A : Price escalation

B : Rate Agreement

C : Indent

D : Invoice

Q.no 32. Fixed period of time, starting from the date of practical completion, during which the
contractor has to rectify defects.

A : Defect Liability period

B : Completion Period

C : Contract

D : Interim period

Q.no 33. Day work denotes

A : To be able to prepare lump sum billing

B : That the Contractor can quote rates on lump sum basis

C : The call for lump sum Tenders excluding contingencies

D : Payment as per quantity of material and labour hours per job

Q.no 34. State the unit of measurement of skirting

A : cum

B : sqm

C : rm

D : kg

Q.no 35. Important factors for detailed estimate

A : Structural design drawings

B : National building code

C : Electricity bills

D : Availability of local labour

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 20/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

Q.no 36. For Preparing Detailed Estimate

A : Lead and Lift is to be taken into consideration

B : Lead and Lift is not to be taken into consideration

C : Should consider non availability of Contractor

D : Should consider availability of Contractor

Q.no 37. The concrete volume of a circular column of 300mm diameter and 4.50m height will be

A : 0.23 cum

B : 0.36 cum

C : 0.32 cum

D : 0.30 cum

Q.no 38. In Abstract sheet rates are taken from

A : Market

B : DSR

C : FACTORY

D : MRP

Q.no 39. A room ceiling of size 3.00m x 6.00m have beam projection of 3.00m x 0.23m x 0.30m
deep. The ceiling plaster area will be

A : 17.31 Square meter

B : 18.00 Square meter

C : 20.49 Square meter

D : 19.80 Square meter

Q.no 40. State the unit of measurement of 230 thkBr.masonry

A : cum

B : sqm

C : rm

D : kg

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 21/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

Q.no 41. Find the width, if the total quantity of P.C.C is 1.35 cmt.
L=7.5 m and Ht=0.15 m

A : 0.9 m

B : 1.35 m

C : 1.50 m

D : 1.20 m

Q.no 42. State the unit of measurement of T.W. Railing

A : cum

B : sqm

C : rm

D : kg

Q.no 43. Find the length of excavation if total quantity=25.45 cmt.


B=1.3 m H=1.05 m

A : 18.56

B : 18.65

C : 18.35

D : 18.53

Q.no 44. What will be the deduction in 230 thk brick work ,if the room is having two doors of size
0.9x2.1 and three windows of size 1.5 x1.20

A : 5.0 cmt

B : 2.1114 cmt

C : 2.414 cmt

D : 2.141 cmt

Q.no 45. Contingency Fund consists of

A : 6%-8% of actual estimated cost of work

B : 2% of actual
estimated cost of work

C : 10% of actual estimated cost of work

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 22/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

D : 3% - 5% of actual estimated cost of work

Q.no 46. In the formula to work out trapezoidal quantity in footing


, The character ‘h’ means

A : Height of base of footing

B : Total Height of footing

C : Height of Trapezoidal portion

D : Slant length of Trapezoidal portion

Q.no 47. A revised estimate is necessary when

A : Some new works or change of design is made

B : Some change of rate or quantity of material change is made

C : New Contractor is to be introduced

D : When property is up for sale

Q.no 48. Each certificate supersedes previous certificates, and eventually the final account
supersedes all interim certificates issued during construction. Choose the correct option

A : false

B : PARTIALY TRUE

C : true

D : NOT APPLICABLE

Q.no 49. Quantity takeoff is

A : List of materials needed to take off the project to completion

B : Finding out the quantities of works from detailed measurement of various items

C : List of items which can be safely taken off from the proposed work

D : List of material quantities not mentioned in BOQ

Q.no 50. If the room size is 5 m x4 m and wall thickness is 300 mm what is the total length of total
centerline.

A : 18 m

B : 18.30 m

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 23/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : 18.60 m

D : 17.70 m

Q.no 51. The value of sum retained by employer for any future defects on the work done by
contractor.

A : Rate Analysis

B : Retention

C : Price escalation

D : Abstract

Q.no 52. Find the length of long wall for foundation step-1? if the total quantity is 2.232 cmt.
B=0.9m and Ht=0.40 m

A : 6.0 m

B : 6.20m

C : 5.90 m

D : 6.40 m

Q.no 53. A detailed estimate is comprised of

A : Plinth work

B : Design data and calculations

C : Construction management

D : Indent of materials

Q.no 54. Two door opening of size 1.25m x 2.10m are placed on either side RCC column If lintel
bearing is 250mm then total length of lintel over two openings will be

A : 3.00 m

B : 2.75 m

C : 1.50 m

D : 1.75m

Q.no 55. Factor which is considered while preparing a detailed estimate

A : Approval drawing

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 24/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Project management

C : Indent of materials

D : Quantity of materials

Q.no 56. Provisional Sum is

A : Provision made in estimate for Unforeseen Natural Calamities

B : Provision made in estimate separately for breakage & damages

C : Provision made for payment to another contractor

D : Provision made for Unknown type of work whose details cannot be ascertained at the time of
preparing estimate

Q.no 57. A rolling shutter opening in 230mm thick brick wall is 4.00m x 5.00m high. The plaster
area of wall thickness (jam) will be

A : 3.22 Square meter

B : 2.30 Square meter

C : 4.14 Square meter

D : 14.00 Running meter

Q.no 58. Generally items of estimate is arranged according to

A : Table of content

B : Progress of construction of work

C : Bottom to top

D : Top to bottom

Q.no 59. Wall tile of 1.50m height is fixed in bath room of size 2.00m x 1.50m with door opening
0.80m x 2.10m. The wall tile area will be

A : 9.30 Square meter

B : 10.50 Square meter

C : 8.82 Square meter

D : 9.85 Square meter

Q.no 60. Approximate cost of building can be found out by

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 25/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

A : Plinth area method

B : Cubic meter method

C : Typical bay method

D : Framed structure method

Q.no 1. Retention amount can be how much % of project cost

A : 15-20%

B : 5-8%

C : 25-30%

D : 60-70%

Q.no 2. 150mm thick wall of 18 square meter area have opening for exhaust fan 0.30m x 0.30m.
The wall quantity will be

A : 2.70 cubic meter

B : 18 square meter

C : 17.91 square meter

D : 2.68 cubic meter

Q.no 3. The document in which the Contractor indicates the cost of the Works, on the basis of the
foreseen quantities of items of work and the fixed unit prices applicable to them.

A : Tender Notice

B : Measurement Sheet

C : BOQ

D : Retention

Q.no 4. One of the methods of computing quantities

A : Roofing method

B : Long wall and Short wall method

C : Frame analysis method

D : Framed construction method

Q.no 5. The RA BILLS should be verified by

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 26/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

A : Contractor

B : Supervisor

C : Engineer In charge

D : Client

Q.no 6. Abstract form is commonly known as

A : Detailed Estimate

B : Measurement sheet

C : Bill of Quantities

D : Indent of materials

Q.no 7. Purpose of Estimating is to

A : Ascertain amount of money required by owner

B : Ascertain quantities of material

C : Fix completion period

D : All the above

Q.no 8. One of the Type of detailed estimate

A : Plinth work

B : Architectural design

C : Project management

D : Supplementary estimate

Q.no 9. One of the methods of computing quantities

A : Load bearing method

B : Framed construction method

C : Working drawing method

D : Center line method

Q.no 10. Abstract of Estimate (Form) has

A : Length, Breadth, Height, Quantity


https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 27/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Number of Items , Quality, Make

C : Quantity, Unit, Rate, Unit of Rate

D : % of Total Quantity method

Q.no 11. State the unit of measurement of steel reinforcement

A : cum

B : sqm

C : rm

D : kg

Q.no 12. Area of half thick brick masonary wall is 15 sqm. The door opening size in wall is 1.20m
x 2.50m. The quantity of wall will be

A : 12.00 Square meter

B : 9.00 Square meter

C : 13.50 Square meter

D : 6.00 Square meter

Q.no 13. What sequence to be considered for execution of work.

A : P.C.C, Excavation,
Filling ,Footing

B : Footing,
P.C.C,
Excavation,
Filling

C : Excavation,
P.C.C,
Footing,
Filling

D : Filling,
Excavation,
Footing,
Filling

Q.no 14. Which sheets are used to work out the quantities.

A : Abstract sheet

B : Measurement sheet
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 28/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : BOQ sheet

D : Plain sheet

Q.no 15. Measurement Form has

A : Number of items, Quality , Make

B : Length, Breadth, Height, Quantity

C : Quantity, Unit, Rate, Unit of Rate

D : Quality, brand, Heavy, Medium

Q.no 16. A rectangular room having size 7.5m x 3.0m. how many long wall are there?

A : one

B : four

C : two

D : five

Q.no 17. One of the Type of detailed estimate

A : Quotation

B : Revised estimate

C : Labour cost

D : Earth work

Q.no 18. Factor which is considered while preparing a detailed estimate

A : Availability of local labour

B : Indent of materials

C : Concept drawings

D : Approval drawings

Q.no 19. In long wall and short wall method wall are divided in to
How many groups.

A : one

B : three

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 29/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : eight

D : two

Q.no 20. State the unit of measurement of External wall plaster

A : cum

B : sqm

C : rm

D : kg

Q.no 21. State the unit of measurement of 115 mm thk brick masonary

A : cum

B : sqm

C : rm

D : kg

Q.no 22. Money paid to confirm a contract. OR Deposit enclosed along with the sealed tender
documents

A : EMD

B : RA BILL

C : INVOICE

D : NOTICE

Q.no 23. Room of 5.00m x 4.00m size has two door openings of 1.00m each in 230mm thick brick
wall. The flooring area will be

A : 20.23 Square meter

B : 20.46 Square meter

C : 20.00 Square meter

D : 22.00 Square meter

Q.no 24. What P.W.D Method also called as.

A : English Method

B : Center Line method

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 30/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : Plinth Area Method

D : Long wall And short wall method

Q.no 25. IS 1200 is referred for

A : Unit of measurement

B : RCC design

C : PCC design

D : Rate of material

Q.no 26. Factor which is considered while preparing a detailed estimate

A : Tendering

B : Availability of materials

C : Plinth work

D : R C C work

Q.no 27. In triangular room, Two walls in right angleare of 6m & 8m length. The length of
diagonal wall will be

A : 16 m

B : 12 m

C : 10m

D:8m

Q.no 28. In center line method what are L-junctions are called

A : Overlap joints

B : Free joints

C : Cross joint

D : Lap joint

Q.no 29. Which item will be measured in sqm

A : plastering

B : pointing

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 31/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : both

D : none

Q.no 30. Government Engineering Dept. Schedule of Rates

A : Changes for every district

B : Does not Change for every district

C : Changes for every 1000 Km.

D : Changes for every 500 Km.

Q.no 31. A chamber of size 1.00m x 1.00m x 1.50m is plastered from inside with base. The plaster
area will be

A : 6.00 square meter

B : 4.00 Square meter

C : 7.00 Square meter

D : 8.00 Square meter

Q.no 32. Provisional Quantities refers to

A : Extra Items of Work needed to be done on site for the additional instructions by the owner

B : Additional Quantities against some items may be required due to variation in site condition

C : Provisions made in bulk for the labourers residing on site

D : Extra payment done on site due to change in contractor

Q.no 33. To rest column shuttering on trapezoidal footing top, the minimum flat width on all
sides of column should be

A : 25mm

B : 300mm

C : 100mm

D : No projection

Q.no 34. The Accuracy of the Estimate

A : Depends on the skill & experience of Estimator

B : Does not depend on the skill & experience of Estimator

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 32/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : Depends on the App used by the Estimator

D : Does not depend on the App used by the Estimator

Q.no 35. Circular flower bed of 1.00m height and 2.00 meter internal diameter is plastered from
inside. The plaster area of will be

A : 6.91 square meter

B : 7.54 square meter

C : 6.28
square meter

D : 5.47
square meter

Q.no 36. A detailed estimate is comprised of

A : Concept drawings

B : National building code

C : Detailed drawings

D : Structural framing plans

Q.no 37. For the delay between the time prescribed in the Contract or the extended time for
completion, Contractor shall pay to the Employer the sum specified in the Contract is called as

A : Extra item

B : Sinking fund

C : liquidated damages

D : EMD

Q.no 38. Approximate cost of building can be found out by

A : Slab and beam method

B : Service Unit method

C : Load bearing method

D : Tendering method

Q.no 39. Allowance agreed for the increase in price for major materials

A : Price escalation

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 33/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Rate Agreement

C : Indent

D : Invoice

Q.no 40. Important factors for detailed estimate

A : Structural design drawings

B : National building code

C : Electricity bills

D : Availability of local labour

Q.no 41. A rolling shutter opening in 230mm thick brick wall is 4.00m x 5.00m high. The plaster
area of wall thickness (jam) will be

A : 3.22 Square meter

B : 2.30 Square meter

C : 4.14 Square meter

D : 14.00 Running meter

Q.no 42. State the unit of measurement of T.W. Railing

A : cum

B : sqm

C : rm

D : kg

Q.no 43. Find the width, if the total quantity of P.C.C is 1.35 cmt.
L=7.5 m and Ht=0.15 m

A : 0.9 m

B : 1.35 m

C : 1.50 m

D : 1.20 m

Q.no 44. Approximate cost of building can be found out by

A : Plinth area method

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 34/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Cubic meter method

C : Typical bay method

D : Framed structure method

Q.no 45. Contingency Fund consists of

A : 6%-8% of actual estimated cost of work

B : 2% of actual
estimated cost of work

C : 10% of actual estimated cost of work

D : 3% - 5% of actual estimated cost of work

Q.no 46. Factor which is considered while preparing a detailed estimate

A : Approval drawing

B : Project management

C : Indent of materials

D : Quantity of materials

Q.no 47. Generally items of estimate is arranged according to

A : Table of content

B : Progress of construction of work

C : Bottom to top

D : Top to bottom

Q.no 48. The value of sum retained by employer for any future defects on the work done by
contractor.

A : Rate Analysis

B : Retention

C : Price escalation

D : Abstract

Q.no 49. What will be the deduction in 230 thk brick work ,if the room is having two doors of size
0.9x2.1 and three windows of size 1.5 x1.20

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 35/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

A : 5.0 cmt

B : 2.1114 cmt

C : 2.414 cmt

D : 2.141 cmt

Q.no 50. Each certificate supersedes previous certificates, and eventually the final account
supersedes all interim certificates issued during construction. Choose the correct option

A : false

B : PARTIALY TRUE

C : true

D : NOT APPLICABLE

Q.no 51. Two door opening of size 1.25m x 2.10m are placed on either side RCC column If lintel
bearing is 250mm then total length of lintel over two openings will be

A : 3.00 m

B : 2.75 m

C : 1.50 m

D : 1.75m

Q.no 52. Wall tile of 1.50m height is fixed in bath room of size 2.00m x 1.50m with door opening
0.80m x 2.10m. The wall tile area will be

A : 9.30 Square meter

B : 10.50 Square meter

C : 8.82 Square meter

D : 9.85 Square meter

Q.no 53. A revised estimate is necessary when

A : Some new works or change of design is made

B : Some change of rate or quantity of material change is made

C : New Contractor is to be introduced

D : When property is up for sale

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 36/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

Q.no 54. Quantity takeoff is

A : List of materials needed to take off the project to completion

B : Finding out the quantities of works from detailed measurement of various items

C : List of items which can be safely taken off from the proposed work

D : List of material quantities not mentioned in BOQ

Q.no 55. Find the length of excavation if total quantity=25.45 cmt.


B=1.3 m H=1.05 m

A : 18.56

B : 18.65

C : 18.35

D : 18.53

Q.no 56. A detailed estimate is comprised of

A : Plinth work

B : Design data and calculations

C : Construction management

D : Indent of materials

Q.no 57. Find the length of long wall for foundation step-1? if the total quantity is 2.232 cmt.
B=0.9m and Ht=0.40 m

A : 6.0 m

B : 6.20m

C : 5.90 m

D : 6.40 m

Q.no 58. Provisional Sum is

A : Provision made in estimate for Unforeseen Natural Calamities

B : Provision made in estimate separately for breakage & damages

C : Provision made for payment to another contractor

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 37/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

D : Provision made for Unknown type of work whose details cannot be ascertained at the time of
preparing estimate

Q.no 59. If the room size is 5 m x4 m and wall thickness is 300 mm what is the total length of total
centerline.

A : 18 m

B : 18.30 m

C : 18.60 m

D : 17.70 m

Q.no 60. In the formula to work out trapezoidal quantity in footing


, The character ‘h’ means

A : Height of base of footing

B : Total Height of footing

C : Height of Trapezoidal portion

D : Slant length of Trapezoidal portion

Q.no 1. Extra Items of Works refers to

A : Extra work done on site in addition to contractual work

B : Extra work done at another site on owner’s request

C : Extra work done using plant and machinery

D : Extra item due to change in specification

Q.no 2. A brickbat waterproof treatment in toilet sunken portion of 300mm deep is measured in
unit

A : Square meter

B : Number

C : Job

D : Cubic meter

Q.no 3. State the unit of measurement of Internal wall plaster

A : cum

B : sqm

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 38/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : rm

D : kg

Q.no 4. State the unit of measurement of R.C.C Columns

A : cum

B : sqm

C : rm

D : kg

Q.no 5. While recording measurement for toilet flooring, the floor trap grating area is deducted

A : 100%

B : 75%

C : 50%

D : No deduction

Q.no 6. What is the Mode of measurement of D.P.C

A : Rft.

B : Rmts.

C : Sqmts.

D : Cmts.

Q.no 7. As per IS code 1200, the quantity for masonary wall above 230mm thick should be
recorded in

A : Square meter

B : Cubic meter

C : Running meter

D : Numbers

Q.no 8. Deduction against ‘Beam to Wall’ connection from plaster measurement will be

A : At actual in Square meter

B : Number

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 39/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : 50% deduction

D : No deduction

Q.no 9. A detailed estimate is comprised of

A : Specifications

B : Concept drawings

C : Indent of materials

D : Approval drawings

Q.no 10. Essential document to verify the amount of work done claimed in bills

A : I card

B : Measurement sheet

C : Certificates

D : Indent

Q.no 11. unit of measurement is referred from which code

A : IS 456

B : IS 1200

C : ISC1345

D : ISC457

Q.no 12. The sum agreed in the Contract as payable to the Contractor for the execution and
completion of the Works and for remedying of any defects therein in accordance with the
Contract.

A : INVOICE

B : EMD

C : Retention

D : Contract Sum

Q.no 13. Data required for preparing Detail Estimate

A : Working Drawings

B : Specifications

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 40/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : Rates of Materials

D : Working Drawings&Specifications&Rates of Materials

Q.no 14. Which item will be measured in cum

A : Wash basin

B : concreting

C : masonry

D : Both 2 and 3

Q.no 15. What should be the order while entering the dimensions in measurement sheet.

A : Height, Depth, Width , Length

B : Numbers ,
Length,
Width,
Height

C : Length,
Numbers.
Height,
Width

D : Width,
Length,
Numbers,
Height

Q.no 16. Span for Defect Liability period is

A : 6-8 Months

B : 2-2.5 Months

C : 12-15 Months

D : 1-3Months

Q.no 17. An Estimate is never the actual cost of the work…..

A : true

B : false

C : Don’t know

D : May be
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 41/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

Q.no 18. State the unit of measurement of flooring

A : cum

B : sqm

C : rm

D : kg

Q.no 19. While recording the measurement of RCC item, the quantity of reinforcement steel to
be deducted

A : 50%

B : 25%

C : 100%

D : No Deduction

Q.no 20. A service window of size 1.50m x 1.00m is provided in brick wall. Both side deduction
from plaster area will be

A : 3.00 Square meter

B : 1.50 Square meter

C : 0.75 Square meter

D : No deduction

Q.no 21. A payment made on a running account,

A : Final bill

B : On Account payment

C : Retention

D : Earnest Money

Q.no 22. Which Amount is kept to ensure that the contractor properly completes the activities
required of them under the contract.

A : Deposit

B : Retention

C : Sinking Fund

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 42/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

D : Advance

Q.no 23. In Abstract sheet rates are taken from

A : Market

B : DSR

C : FACTORY

D : MRP

Q.no 24. State the unit of measurement of 230 thkBr.masonry

A : cum

B : sqm

C : rm

D : kg

Q.no 25. A formal request for payment made against the job completed or consumption of
material and resources that bills a specific amount.

A : Price escalation

B : Rate Agreement

C : Indent

D : Invoice

Q.no 26. Room of 5.00m x 4.00m size has two door openings of 1.00m each in 230mm thick brick
wall. The flooring area will be

A : 20.23 Square meter

B : 20.46 Square meter

C : 20.00 Square meter

D : 22.00 Square meter

Q.no 27. Money paid to confirm a contract. OR Deposit enclosed along with the sealed tender
documents

A : EMD

B : RA BILL

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 43/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : INVOICE

D : NOTICE

Q.no 28. State the unit of measurement of SS railing

A : cum

B : sqm

C : rm

D : kg

Q.no 29. Which item will not be measured in number

A : Wash basin

B : Kitchen sink

C : urinal

D : pipes

Q.no 30. For Preparing Detailed Estimate

A : Lead and Lift is to be taken into consideration

B : Lead and Lift is not to be taken into consideration

C : Should consider non availability of Contractor

D : Should consider availability of Contractor

Q.no 31. Approximate cost of building can be found out by

A : Project management method

B : Construction management method

C : Approximate quantities method

D : Plinth work method

Q.no 32. Detailed estimate comprises the cost of

A : Total cost of various items of work

B : Concept Design drawings

C : Furniture design drawings


https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 44/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

D : Development control rules

Q.no 33. A room ceiling of size 3.00m x 6.00m have beam projection of 3.00m x 0.23m x 0.30m
deep. The ceiling plaster area will be

A : 17.31 Square meter

B : 18.00 Square meter

C : 20.49 Square meter

D : 19.80 Square meter

Q.no 34. Fixed period of time, starting from the date of practical completion, during which the
contractor has to rectify defects.

A : Defect Liability period

B : Completion Period

C : Contract

D : Interim period

Q.no 35. A Detailed Estimate is prepared using

A : % of Total Quantity method

B : Thumb rule Quantity method

C : Unit Quantity method

D : Unit Quality method

Q.no 36. The concrete volume of a circular column of 300mm diameter and 4.50m height will be

A : 0.23 cum

B : 0.36 cum

C : 0.32 cum

D : 0.30 cum

Q.no 37. Prime Cost is

A : Cost of Material + Labour

B : Cost of material + loading / unloading charge

C : Net cost of Articles at Shop

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 45/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

D : Cost of Articles + 5% Profit

Q.no 38. State the unit of measurement of skirting

A : cum

B : sqm

C : rm

D : kg

Q.no 39. Room of size 5.00m x 4.00m has two door openings of 1.00m each. The skirting length
will be

A : 20.00 Running meter

B : 19.00 Running meter

C : 18.00 Running meter

D : 17.00 Running meter

Q.no 40. State the unit of measurement of 115 mm thk brick masonary

A : cum

B : sqm

C : rm

D : kg

Q.no 41. Two door opening of size 1.25m x 2.10m are placed on either side RCC column If lintel
bearing is 250mm then total length of lintel over two openings will be

A : 3.00 m

B : 2.75 m

C : 1.50 m

D : 1.75m

Q.no 42. Find the length of excavation if total quantity=25.45 cmt.


B=1.3 m H=1.05 m

A : 18.56

B : 18.65

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 46/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : 18.35

D : 18.53

Q.no 43. Find the length of long wall for foundation step-1? if the total quantity is 2.232 cmt.
B=0.9m and Ht=0.40 m

A : 6.0 m

B : 6.20m

C : 5.90 m

D : 6.40 m

Q.no 44. Find the width, if the total quantity of P.C.C is 1.35 cmt.
L=7.5 m and Ht=0.15 m

A : 0.9 m

B : 1.35 m

C : 1.50 m

D : 1.20 m

Q.no 45. Wall tile of 1.50m height is fixed in bath room of size 2.00m x 1.50m with door opening
0.80m x 2.10m. The wall tile area will be

A : 9.30 Square meter

B : 10.50 Square meter

C : 8.82 Square meter

D : 9.85 Square meter

Q.no 46. Factor which is considered while preparing a detailed estimate

A : Approval drawing

B : Project management

C : Indent of materials

D : Quantity of materials

Q.no 47. Provisional Sum is

A : Provision made in estimate for Unforeseen Natural Calamities

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 47/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Provision made in estimate separately for breakage & damages

C : Provision made for payment to another contractor

D : Provision made for Unknown type of work whose details cannot be ascertained at the time of
preparing estimate

Q.no 48. If the room size is 5 m x4 m and wall thickness is 300 mm what is the total length of total
centerline.

A : 18 m

B : 18.30 m

C : 18.60 m

D : 17.70 m

Q.no 49. Each certificate supersedes previous certificates, and eventually the final account
supersedes all interim certificates issued during construction. Choose the correct option

A : false

B : PARTIALY TRUE

C : true

D : NOT APPLICABLE

Q.no 50. The value of sum retained by employer for any future defects on the work done by
contractor.

A : Rate Analysis

B : Retention

C : Price escalation

D : Abstract

Q.no 51. Quantity takeoff is

A : List of materials needed to take off the project to completion

B : Finding out the quantities of works from detailed measurement of various items

C : List of items which can be safely taken off from the proposed work

D : List of material quantities not mentioned in BOQ

Q.no 52. A revised estimate is necessary when

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 48/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

A : Some new works or change of design is made

B : Some change of rate or quantity of material change is made

C : New Contractor is to be introduced

D : When property is up for sale

Q.no 53. A rolling shutter opening in 230mm thick brick wall is 4.00m x 5.00m high. The plaster
area of wall thickness (jam) will be

A : 3.22 Square meter

B : 2.30 Square meter

C : 4.14 Square meter

D : 14.00 Running meter

Q.no 54. A detailed estimate is comprised of

A : Plinth work

B : Design data and calculations

C : Construction management

D : Indent of materials

Q.no 55. State the unit of measurement of T.W. Railing

A : cum

B : sqm

C : rm

D : kg

Q.no 56. Contingency Fund consists of

A : 6%-8% of actual estimated cost of work

B : 2% of actual
estimated cost of work

C : 10% of actual estimated cost of work

D : 3% - 5% of actual estimated cost of work

Q.no 57. Generally items of estimate is arranged according to

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 49/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

A : Table of content

B : Progress of construction of work

C : Bottom to top

D : Top to bottom

Q.no 58. Approximate cost of building can be found out by

A : Plinth area method

B : Cubic meter method

C : Typical bay method

D : Framed structure method

Q.no 59. What will be the deduction in 230 thk brick work ,if the room is having two doors of size
0.9x2.1 and three windows of size 1.5 x1.20

A : 5.0 cmt

B : 2.1114 cmt

C : 2.414 cmt

D : 2.141 cmt

Q.no 60. In the formula to work out trapezoidal quantity in footing


, The character ‘h’ means

A : Height of base of footing

B : Total Height of footing

C : Height of Trapezoidal portion

D : Slant length of Trapezoidal portion

Q.no 1. The document in which the Contractor indicates the cost of the Works, on the basis of the
foreseen quantities of items of work and the fixed unit prices applicable to them.

A : Tender Notice

B : Measurement Sheet

C : BOQ

D : Retention

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 50/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

Q.no 2. One of the methods of computing quantities

A : Roofing method

B : Long wall and Short wall method

C : Frame analysis method

D : Framed construction method

Q.no 3. One of the Type of detailed estimate

A : Quotation

B : Revised estimate

C : Labour cost

D : Earth work

Q.no 4. One of the methods of computing quantities

A : Load bearing method

B : Framed construction method

C : Working drawing method

D : Center line method

Q.no 5. State the unit of measurement of steel reinforcement

A : cum

B : sqm

C : rm

D : kg

Q.no 6. Retention amount can be how much % of project cost

A : 15-20%

B : 5-8%

C : 25-30%

D : 60-70%

Q.no 7. A rectangular room having size 7.5m x 3.0m. how many long wall are there?
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 51/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

A : one

B : four

C : two

D : five

Q.no 8. One of the Type of detailed estimate

A : Plinth work

B : Architectural design

C : Project management

D : Supplementary estimate

Q.no 9. Purpose of Estimating is to

A : Ascertain amount of money required by owner

B : Ascertain quantities of material

C : Fix completion period

D : All the above

Q.no 10. Abstract of Estimate (Form) has

A : Length, Breadth, Height, Quantity

B : Number of Items , Quality, Make

C : Quantity, Unit, Rate, Unit of Rate

D : % of Total Quantity method

Q.no 11. Which sheets are used to work out the quantities.

A : Abstract sheet

B : Measurement sheet

C : BOQ sheet

D : Plain sheet

Q.no 12. Measurement Form has

A : Number of items, Quality , Make


https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 52/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Length, Breadth, Height, Quantity

C : Quantity, Unit, Rate, Unit of Rate

D : Quality, brand, Heavy, Medium

Q.no 13. Area of half thick brick masonary wall is 15 sqm. The door opening size in wall is 1.20m
x 2.50m. The quantity of wall will be

A : 12.00 Square meter

B : 9.00 Square meter

C : 13.50 Square meter

D : 6.00 Square meter

Q.no 14. The RA BILLS should be verified by

A : Contractor

B : Supervisor

C : Engineer In charge

D : Client

Q.no 15. What sequence to be considered for execution of work.

A : P.C.C, Excavation,
Filling ,Footing

B : Footing,
P.C.C,
Excavation,
Filling

C : Excavation,
P.C.C,
Footing,
Filling

D : Filling,
Excavation,
Footing,
Filling

Q.no 16. Factor which is considered while preparing a detailed estimate

A : Availability of local labour

B : Indent of materials
https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 53/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : Concept drawings

D : Approval drawings

Q.no 17. Abstract form is commonly known as

A : Detailed Estimate

B : Measurement sheet

C : Bill of Quantities

D : Indent of materials

Q.no 18. In long wall and short wall method wall are divided in to
How many groups.

A : one

B : three

C : eight

D : two

Q.no 19. State the unit of measurement of External wall plaster

A : cum

B : sqm

C : rm

D : kg

Q.no 20. 150mm thick wall of 18 square meter area have opening for exhaust fan 0.30m x 0.30m.
The wall quantity will be

A : 2.70 cubic meter

B : 18 square meter

C : 17.91 square meter

D : 2.68 cubic meter

Q.no 21. The Accuracy of the Estimate

A : Depends on the skill & experience of Estimator

B : Does not depend on the skill & experience of Estimator

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 54/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : Depends on the App used by the Estimator

D : Does not depend on the App used by the Estimator

Q.no 22. A chamber of size 1.00m x 1.00m x 1.50m is plastered from inside with base. The plaster
area will be

A : 6.00 square meter

B : 4.00 Square meter

C : 7.00 Square meter

D : 8.00 Square meter

Q.no 23. Provisional Quantities refers to

A : Extra Items of Work needed to be done on site for the additional instructions by the owner

B : Additional Quantities against some items may be required due to variation in site condition

C : Provisions made in bulk for the labourers residing on site

D : Extra payment done on site due to change in contractor

Q.no 24. In triangular room, Two walls in right angleare of 6m & 8m length. The length of
diagonal wall will be

A : 16 m

B : 12 m

C : 10m

D:8m

Q.no 25. In center line method what are L-junctions are called

A : Overlap joints

B : Free joints

C : Cross joint

D : Lap joint

Q.no 26. Allowance agreed for the increase in price for major materials

A : Price escalation

B : Rate Agreement

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 55/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : Indent

D : Invoice

Q.no 27. Government Engineering Dept. Schedule of Rates

A : Changes for every district

B : Does not Change for every district

C : Changes for every 1000 Km.

D : Changes for every 500 Km.

Q.no 28. Which item will be measured in sqm

A : plastering

B : pointing

C : both

D : none

Q.no 29. Detailed estimate comprises the cost of

A : Plinth work

B : Establishment charges for supervision

C : Indent of materials

D : Cubic meter work

Q.no 30. Factor which is considered while preparing a detailed estimate

A : Tendering

B : Availability of materials

C : Plinth work

D : R C C work

Q.no 31. What P.W.D Method also called as.

A : English Method

B : Center Line method

C : Plinth Area Method


https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 56/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

D : Long wall And short wall method

Q.no 32. A detailed estimate is comprised of

A : Concept drawings

B : National building code

C : Detailed drawings

D : Structural framing plans

Q.no 33. Day work denotes

A : To be able to prepare lump sum billing

B : That the Contractor can quote rates on lump sum basis

C : The call for lump sum Tenders excluding contingencies

D : Payment as per quantity of material and labour hours per job

Q.no 34. Circular flower bed of 1.00m height and 2.00 meter internal diameter is plastered from
inside. The plaster area of will be

A : 6.91 square meter

B : 7.54 square meter

C : 6.28
square meter

D : 5.47
square meter

Q.no 35. Important factors for detailed estimate

A : Structural design drawings

B : National building code

C : Electricity bills

D : Availability of local labour

Q.no 36. Approximate cost of building can be found out by

A : Slab and beam method

B : Service Unit method

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 57/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

C : Load bearing method

D : Tendering method

Q.no 37. To rest column shuttering on trapezoidal footing top, the minimum flat width on all
sides of column should be

A : 25mm

B : 300mm

C : 100mm

D : No projection

Q.no 38. For the delay between the time prescribed in the Contract or the extended time for
completion, Contractor shall pay to the Employer the sum specified in the Contract is called as

A : Extra item

B : Sinking fund

C : liquidated damages

D : EMD

Q.no 39. Reason for preparing approximate estimate is

A : Financial aspects

B : Architectural design

C : Approval from local authorities

D : Tendering

Q.no 40. IS 1200 is referred for

A : Unit of measurement

B : RCC design

C : PCC design

D : Rate of material

Q.no 41. What will be the deduction in 230 thk brick work ,if the room is having two doors of size
0.9x2.1 and three windows of size 1.5 x1.20

A : 5.0 cmt

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 58/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : 2.1114 cmt

C : 2.414 cmt

D : 2.141 cmt

Q.no 42. State the unit of measurement of T.W. Railing

A : cum

B : sqm

C : rm

D : kg

Q.no 43. Contingency Fund consists of

A : 6%-8% of actual estimated cost of work

B : 2% of actual
estimated cost of work

C : 10% of actual estimated cost of work

D : 3% - 5% of actual estimated cost of work

Q.no 44. A revised estimate is necessary when

A : Some new works or change of design is made

B : Some change of rate or quantity of material change is made

C : New Contractor is to be introduced

D : When property is up for sale

Q.no 45. Find the length of excavation if total quantity=25.45 cmt.


B=1.3 m H=1.05 m

A : 18.56

B : 18.65

C : 18.35

D : 18.53

Q.no 46. Quantity takeoff is

A : List of materials needed to take off the project to completion

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 59/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

B : Finding out the quantities of works from detailed measurement of various items

C : List of items which can be safely taken off from the proposed work

D : List of material quantities not mentioned in BOQ

Q.no 47. Each certificate supersedes previous certificates, and eventually the final account
supersedes all interim certificates issued during construction. Choose the correct option

A : false

B : PARTIALY TRUE

C : true

D : NOT APPLICABLE

Q.no 48. Approximate cost of building can be found out by

A : Plinth area method

B : Cubic meter method

C : Typical bay method

D : Framed structure method

Q.no 49. Find the length of long wall for foundation step-1? if the total quantity is 2.232 cmt.
B=0.9m and Ht=0.40 m

A : 6.0 m

B : 6.20m

C : 5.90 m

D : 6.40 m

Q.no 50. The value of sum retained by employer for any future defects on the work done by
contractor.

A : Rate Analysis

B : Retention

C : Price escalation

D : Abstract

Q.no 51. Generally items of estimate is arranged according to

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 60/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

A : Table of content

B : Progress of construction of work

C : Bottom to top

D : Top to bottom

Q.no 52. A detailed estimate is comprised of

A : Plinth work

B : Design data and calculations

C : Construction management

D : Indent of materials

Q.no 53. In the formula to work out trapezoidal quantity in footing


, The character ‘h’ means

A : Height of base of footing

B : Total Height of footing

C : Height of Trapezoidal portion

D : Slant length of Trapezoidal portion

Q.no 54. A rolling shutter opening in 230mm thick brick wall is 4.00m x 5.00m high. The plaster
area of wall thickness (jam) will be

A : 3.22 Square meter

B : 2.30 Square meter

C : 4.14 Square meter

D : 14.00 Running meter

Q.no 55. If the room size is 5 m x4 m and wall thickness is 300 mm what is the total length of total
centerline.

A : 18 m

B : 18.30 m

C : 18.60 m

D : 17.70 m

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 61/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

Q.no 56. Provisional Sum is

A : Provision made in estimate for Unforeseen Natural Calamities

B : Provision made in estimate separately for breakage & damages

C : Provision made for payment to another contractor

D : Provision made for Unknown type of work whose details cannot be ascertained at the time of
preparing estimate

Q.no 57. Find the width, if the total quantity of P.C.C is 1.35 cmt.
L=7.5 m and Ht=0.15 m

A : 0.9 m

B : 1.35 m

C : 1.50 m

D : 1.20 m

Q.no 58. Two door opening of size 1.25m x 2.10m are placed on either side RCC column If lintel
bearing is 250mm then total length of lintel over two openings will be

A : 3.00 m

B : 2.75 m

C : 1.50 m

D : 1.75m

Q.no 59. Factor which is considered while preparing a detailed estimate

A : Approval drawing

B : Project management

C : Indent of materials

D : Quantity of materials

Q.no 60. Wall tile of 1.50m height is fixed in bath room of size 2.00m x 1.50m with door opening
0.80m x 2.10m. The wall tile area will be

A : 9.30 Square meter

B : 10.50 Square meter

C : 8.82 Square meter

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 62/63
12/28/2020 https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5

D : 9.85 Square meter

https://sppu.wheebox.com/WAC-3/allqusdownloadhtml.ils?testNo=120&code=1052000&showTest=319&actForm=edit&set=5 63/63

You might also like