Professional Documents
Culture Documents
Leigh Sharpe, The Coal Authority, 200 Lichfield Lane, Mansfield, Nottingham, United Kingdom
Shallow coal mining has been undertaken historically in many urban areas throughout the UK, and it remains
a threat to construction. Masked by interim development the risks are often poorly appreciated. Their age,
and often unrecorded nature means that they are difficult to characterise or predict. This paper, explores the
diversity of coal mining related geohazards and their effect on urban construction. To prevent inappropriate
site development the Coal Authority has developed a robust permissions process to regulate activities which
affect its property. The need for this regulatory control is explained along with its objective to protect public
safety, the environment, and, by the promotion of current best practice, limit future liability. By reference to
recent urban examples the risks are explored, including the action or inactions leading to claims, damages,
or delays, all resulting in financial loss. An insight is given as to how the Authority, by using its GIS database
develop site specific conceptual models to assess applicants proposals against the known mining-related
risks. Finally, some of the remaining geotechnical challenges are discussed, which if overcome, will further
assist all involved, and the regulatory process.
PERMISSIONS HISTORY
The Coal Authority was established by the Coal Why Is Regulation Necessary?
Industry Act upon privatisation in 1994. As a result Throughout the UK over 2 million buildings are
of the duties vested in it by the state, the Authority affected by shallow coal mine workings,
must manage the liabilities arising from (approximately 8%), and of these 130,000 are
disturbance or interference of its property from known to lie within 20m of 1 or more shafts.
development. This function is carried out by the Surprisingly less than 50% of all property owners
Authority’s Permissions Department. When have obtained a coal mining report for their
satisfied with an applicants proposals a permit to property and as a result many owners will be
‘Enter or disturb the Coal Authority’s mining unaware of the risks. Although proportionally
interests’ is issued acknowledging agreement for small, on average 15 shaft collapses occur each
work to proceed. year.
The use of contaminated material as shaft infill or The visualisation of possible emission pathways is
intentional disposal of waste into shafts is particularly beneficial because of their complexity,
widespread. Whilst the Authority’s interpretative interaction and variety. The possible pathways
reports give some information, much activity is typically available can be classified as follows;
likely to be unrecorded. As a result ‘it should be
assumed that all materials encountered in 1. Discrete man-made emission points
boreholes… are potentially contaminated.’ BRE • Mine entries shafts and adits
(2006). Contractors should recognise the • Un-reinstated, poorly sealed or open
increased potential for contingency measures and boreholes and excavations
the client the unforeseen costs and liability.
2. Diffuse Natural Pathways
As might be expected a strict adherence of shaft • Permeable strata, particularly jointed
cap treatment to that recommended in CIRIA sandstone.
SP32 exists, and advice to structural engineers in • Geological faults
overcoming mining related problems continues to
reinforce this in the absence of updated guidance. 3. Diffuse man-made emission points
With sustainability, new standards and site • Shallow mine workings, including those
handling issues in mind it is recommended that from outcrop
designers depart from the practice of using an ‘off • Surface disturbance including made or
the shelf’ solution but individually design caps as backfilled porous ground
structural elements, to meet the specified • Service ducts & trenches
serviceability requirements, and in the process
• Mining induced fractures.
reduce structural redundancy.
It is important to consider that temporary migration
CONCEPTUAL MODELLING OF MINING
pathways can be created during construction,
GEOHAZARDS
gases may be under pressure as a result of
minewater recovery and that the release of mine
All permission applications are assessed on a site
gas is strongly influenced by the prevailing
specific basis following a dual assessment
atmospheric (barometric) pressure at the surface.
process. This considers the ground engineering
Basements, buried structures and confined
(stability) risk and secondly the geoenvironmental
rooms; and those with poor ventilation, are at an
risk. The latter include mine water and mine gases
increased risk. All excavation boreholes need to
which are accessed using the source-pathway-
be effectively sealed from the atmosphere to
receptor methodology. The need for
ensure they do not later become migration
conceptualisation of sites is a well accepted
pathways, especially where they are located
industry best practice, and supported from the
within the footprint of proposed buildings.
geotechnical viewpoint in the AGS Good Practice
Guidance Document (2007) which recommends
Drilling operations other than water flush in the
that a conceptual model should be developed for
urban environment need to set in place other
all sites. For gas, BS8485 (2008), makes the
effective control measures in agreement with the
Authority. Where relied upon barrier superficial Figure 3 Mine gas monitoring records from a
deposits or the case of flooded mine workings liability site, in Rotherham. Spot readings from a
need to be proven across the site, especially sealed drift vent installed in 1994.
since former construction on brownfield sites may
have disturbed or removed the natural superficial The classification of PFA as a waste material
cover. Flexibility to switch from air flush to water remains under review by the Environment Agency
flush whilst drilling may prove cost effective (2008). This, and the draft quality protocol
depending on thickness of superficial cover and covering the re-use of PFA is expected to
the size of investigation. The internal monitoring of recognise the valuable use (given certain control
receptor properties is generally always preferred measures described therein) of PFA as a reusable
rather than use of intervening monitoring points. and cost effective by-product of the power
Figure 2 provides an example conceptual site generation industry and bring present UK
model of a site where air-flush drilling was guidelines in line with the European Waste
undertaken with a requirement for internal gas Directive. The aforementioned report
monitoring. All the aforementioned reinforce the recommends that the BRE Code of Practise
need for detailed, high quality design and document is revised to take account of updated
reporting of Phase 1 and 2 investigations. legislation and terminology and the adoption of a
quality protocol using the reports own risk
assessment procedure.
It is essential that Clients appoint a qualified Clients and developers should protect themselves
supervisor in accordance with PPG14 which in cases where contamination may affect water
states that those responsible for preparing the quality. By commissioning testing of pre-
Ground Stability Declaration should meet the construction ground water samples a benchmark
requirements of a Geotechnical Specialist as for water quality can be established.
defined by the ICE Site Investigations Steering
Group. Ownership of any specification should be The Authority operates several hundred ‘liability
clearly assigned and any contractor appointed sites’ across the country many of which perform a
should have BDA audited and qualified drilling vital function, whether by monitoring, treating or
staff. Clients should be clear of the implications of pumping mine water or actively withdrawing mine
warranty conditions set by a contractor especially gases. Associated with these are discharge
for undertaking treatment works. The significant consents and other operating licenses which have
benefits of specifying full-time supervision need to the potential to be affected by nearby
be realised. A consultant will take a degree of development. There is no reason however,
responsibility and therefore liability for works provided development is well planned in
undertaken under their supervision. consultation with the Authority, for works to be
prohibited near these liability sites, particularly in
With the economic downturn mothballed sites the case of beneficial regeneration. Recently in
have increased in number dramatically but clients Sunderland the Authority worked with the local
should not forget their Health and Safety authority and design consultants to install a new
obligations under the Occupier’s Liability Act public artwork that will enhance the visual
appearance of operational mine vents located planned any remedial works to either shaft and
next to the Stadium of Light, Figure 4. had not proven their location or condition. The site
itself had not been securely fenced from public
access despite a public car park adjoining the site.
As a construction site, plant was trafficking over
the area and concern was raised that despite
warnings to demarcate an area free from traffic
around the plotted locations of the shafts, this was
not being observed.
Figure 5 Ashington site, a) shafts prepared for Without a successful conclusion it is expected that
capping (inset shaft filling operation) and b) suitable comments will be placed on the mining
geophysical electromagnetic (EM31) plot showing records for the shaft which will affect the
limited coverage of the site resulting from access properties future price and desirability. At the time
constraints. of writing, the housing developer was faced with
the prospect of having to demolish the properties
All property conveyances were withheld until the or provide a substantial security fee against future
works were satisfactorily completed and the damage claims. The latter would only be
validation report including declarations was permissible on provided it could be satisfactorily
received in March 2009. This delay resulted in demonstrated that any future movement was likely
financial difficulties for the developer as their to result only in serviceability issues and not
lender refused to release further funds. The endanger the public or future occupiers.
constructed units could not be handed over to the
expectant leaseholders and contractual penalties
for the late delivery were due to commence. The
overall development costs in overcoming the
mining related hazards in this case are expected
to have exceeded £150k, an estimated 15% of the
total build cost.
3. The BGS ‘Derived Products’ team has A combination of smart technologies and multi-
commenced work on the ‘Underground Asset disciplinary approach is often required to resolve
Management tool’ to help determine what existing complexities intrinsic to the urban environment.
infrastructure could be potentially at risk from a Monitoring While Drilling (MWD) systems which
variety of hazards; mining included. A by-product record various useful parameters digitally would
again will be a much improved characterisation of greatly benefit the management and recording of
superficial deposits. treatment works and rigs with recirculation of
drilling fluids are increasingly in demand in the
Collaboration urban locations. The downhole Cavity
Autoscanning Laser System CAL-S has
The Authority is currently in discussions with applications particularly where open voids remain.
Network Rail to ratify and implement a working Where work may affect on or offsite properties the
procedure for referral and exchange of information monitoring of nearby structures should be
within its infrastructure boundaries. It is expected undertaken. Automation of digitally recorded data
that Network Rail will update its operating is now easier as plant can be fitted with GPS to
standards and procedures to regularise the provide spacially populated mapping across a
agreement. site. These techniques should not remain the
preserve of remedial treatments.
A much needed rewrite of the CIRIA Special
Publication 32 has been agreed between the The extension of current AGS data format to
Authority and CIRIA and although a funding gap capture mine treatment and stabilisation works
currently exists it is hoped this major update will would be of great benefit but its uptake by the
draw on the existing guidance bringing it in line industry, as in the case of piling, Egan (2008), is
with recent UK and European legislative changes likely to remain a prohibitive factor. Successful
This document should complement the intended digital 4D representation of, for example, drilling
code of practice for drilling into coal measures. and grouting works is likely to remain the preserve
of larger, higher profile projects. Despite this has
Research been demonstrated to be highly beneficial for
urban projects where public consultation is
Work needs to be undertaken in the near future to essential, Hyder Consulting (2009).
promote the receipt of ‘Ground Stability
Declarations’ albeit in an updated format to that Geophysics should always be used in a
currently presented in Appendix 2E of PPG14. complementary manner to other often intrusive
Involvement of a ‘Geotechnical’ or ‘Ground investigation techniques forming a combined
Engineering’ Specialist is recommended as approach. It appears however that their full
mandatory for sites where a Coal Mining Risk potential is not being realised at present and this
Assessment (CMRA) is a planning requirement. may be helped by the publishing of summary data
Ideally this should subsequently form part of the and statistics to improve the situation.
permission application.
ACKNOWLEDGEMENTS
Experience has highlighted that the minimum
requirements for site investigation where shallow The author wishes to acknowledge Ian Wilson,
mine workings are suspected need to be more Director of Mining Projects and Property at the
clearly defined, whilst taking account of the Coal Authority for his kind permission to publish
benefits of a phased approach. this paper. Bill Denton, Coal Authority Operations
Manager is thanked for his review and comments
on the draft manuscript. The views and opinions Forster, A and Freeborough, K., 2006. A guide to
contained herein are those of the author, and are the communication of geohazards information to
not necessarily those of The Coal Authority. the public. Urban Geoscience and Geohazards
Programme British Geological Survey, Internal
REFERENCES Report IR/06/009 39pp.
AGS, 2006. Guidelines for Good Practice in Site Health and Safety Executive 2007. Position
Investigation Issue 2, March 2006. Statement, Carbon Monoxide. May 2007.
Association of Geotechnical and Healy, P, R., and Head, J, M., 1984. Construction
Geoenvironmental Specialists 2009, Loss over abandoned mine workings. CIRIA Special
Prevention Alert No. 40. Drilling into Coal Publication 32, ISBN 978-0-86017-218-5.
Authority Assets: a Review of the Coal Authority’s
Terms and Conditions for Entering or Disturbing Highways Agency, 1997. Manual of Contract
Coal Authority Mining Interests. Documents for Highway Works, (MCHW) Volume
http://www.ags.org.uk/site/aboutlossprevention/lp4 5 Section 3 Part 2 SA9/97 Ground Investigation
0.cfm. Procedure, Site Investigation procedure on land in
which the existence of abandoned mines and
BS8485 (2007) British Standard. Code of practice shafts is known or suspected. Amendment 1 May
for the characterisation and remediation from 2005.
ground gas in affected developments. ISBN 978 0
580 56934 0. Hyder Consulting UK Ltd. 2008. Briars Lane,
Hatfield, Chalk Mine Stabilisation, Validation
Building Research Establishment, 2006. Report, June 2008, Report No. 0001-LN00960-
Stabilising mine workings with pfa grouts, NHR-01.
Environmental Code of Practice. Report 488.
ISBN 1 86081 909 5. Pennell, S., and Banton, C., (2008) Ground Rules.
The Land Journal. November-December 2008.
Card, G., Hutchings, H., Mallet, H., Oliver, S., and Royal Institution of Chartered Surveyors.
Wilson, S., 2007. Assessing risks posed by
hazardous ground gases for buildings. CIRIA Royce, K, R., Rutter, H, K., and Entwisle, D, C.,
Report C665. (2009) Property attribution of 3D geological
models in the Thames Gateway, London: new
Culshaw, M, G., McCann, D. M., and Donnelly, L. ways of visualising geoscientific information.
J., 2000. Impacts of abandoned mine workings on Bulletin of Engineering Geology and the
aspects of urban development. Transactions of Environment, Volume 68, Number 1, pp1-16,
Institution of Mining and Metallurgy, Volume 109, February 2009.
A132-A139.
Smith, A., and Ellison, R, A., (1999) Applied
Department of the Environment, 1990. Planning geological maps for planning and development: A
Policy Guidance 14: Development on Unstable review of examples from England and Wales 1983
Land. Including Annex 2: Subsidence and to 1996. Quarterly Journal of Engineering Geology
Planning 2002. http://www.communities.gov.uk/. Vol. 32, S1-S44.
Egan, D., 2008. The Ground: clients remain The Law Society and Coal Authority 2006. Coal
exposed to unnecessary risk. Ground Engineering Mining and Brine Subsidence Claim Searches:
161, Issue GE4, pp169-195. Directory and Guidance. 6th Edition England &
Wales (2006 Edition Scotland) at
Environment Agency 2008. Pulverised Fuel Ash http://www.coal.gov.uk/services/propertysearch/ga
and furnace bottom ash: A technical report on the zetteer/index.cfm.
manufacture of products from pulverised fuel ash
(PFA) and furnace bottom ash (FBA). Sept 2008,
pp 60.