You are on page 1of 26

Hz

Installation, Operation, and


Maintenance Manual
60
AMS ...
AM(X)...
AV(X) ...
AK(X) ...
Content
1.2. Preface..............................................................................................................................................................03
1.3. Proper use.........................................................................................................................................................03
1.4. Copyright...........................................................................................................................................................03

2. Safety..................................................................................................................................04
2.1. Instructions and safety information...................................................................................................................04
2.2. General safety...................................................................................................................................................04
2.3. Operating personnel..........................................................................................................................................04
2.4. Electrical work...................................................................................................................................................04
2.5. Operating procedure..........................................................................................................................................05
2.6. Safety and control devices................................................................................................................................05
2.7. Operation in an explosive atmosphere..............................................................................................................05
2.8. Sound Safety.....................................................................................................................................................05
2.9. Pumped fluids ...................................................................................................................................................05

3. General description...........................................................................................................06
3.1. Application.........................................................................................................................................................06
3.2. Types of use......................................................................................................................................................06
3.3. Construction......................................................................................................................................................06

4. Package, Transport, Storage............................................................................................09


4.1. Delivery..............................................................................................................................................................09
4.2. Transport............................................................................................................................................................09
4.3. Storage..............................................................................................................................................................09
4.4. Returning to the supplier ..................................................................................................................................10

5. Installation and initial commissioning............................................................................10


5.1. General..............................................................................................................................................................10
5.2. Installation.........................................................................................................................................................11
5.3. Use of chains.....................................................................................................................................................13
5.4. Initial operation..................................................................................................................................................14
5.5. Preparatory work...............................................................................................................................................14
5.7. Direction of rotation...........................................................................................................................................16
5.8. Motor protection................................................................................................................................................16
5.9. Variable Frequency Drives.................................................................................................................................16
5.10. Types of startups.............................................................................................................................................16

6. Maintenance......................................................................................................................17
6.1. General..............................................................................................................................................................17
6.2. Maintenance intervals.......................................................................................................................................17
6.3. Maintenance tasks............................................................................................................................................17
6.4. Sealing chamber................................................................................................................................................19

7. Repairs................................................................................................................................19
7.1. General..............................................................................................................................................................19
7.2. Changing the impeller and pump unit................................................................................................................19
7.3. Spare Parts........................................................................................................................................................20

8. Shutdown...........................................................................................................................20
8.1. Temporary shutdown.........................................................................................................................................20
8.2. Final shutdown / storage...................................................................................................................................20
8.3. Restarting after an extended period of storage.................................................................................................20
9. Troubleshooting................................................................................................................20
10. Connection of pumps and mixers..................................................................................23

02 | English
1.2. Preface “wet” installation type
This installation type requires the product to be immersed
Dear Customer,
in the pumped fluid. It is completely surrounded by the
Thank you for choosing one of our company’s products.
pumped fluid. Please observe the values for the maximum
You have purchased a product which has been manufac-
submersion depth and the minimum water coverage.
tured to the latest technical standards. Read this operat-
ing and maintenance manual carefully before you first use
“dry” installation type
it. This is the only way to ensure that the product is safely
In this installation type, the product is installed dry, i.e. the
and economically used.
pumped fluid is delivered to and discharged via a pipeline
system. The product is not immersed in the pumped fluid.
The documentation contains all the necessary specifica-
Please note that the surfaces of the product become very
tions for the product, allowing you to use it properly. In
hot!
addition, you will also find information on how to recog-
nize potential dangers, reduce repair costs and downtime,
“transportable” installation type
and increase the reliability and working life of the product.
With this installation type the product is equipped with a
pedestal. It can be installed and operated at any location.
All safety requirements and specific manufacturer’s re-
Please observe the values for the maximum submersion
quirements must be fulfilled before the product is put
depth and the minimum water coverage, and remember
into operation. This operating and maintenance manual
that the surfaces of the product become very hot.
supplements any existing national regulations on industri-
al safety and accident prevention. This manual must also
“S1” operating mode (continuous operation)
be accessible to personnel at all times and also be made
At the rated load, a constant temperature is reached that
available where the product is used.
does not increase even in prolonged operation. The oper-
ating equipment can operate uninterruptedly at the rated
1.3. Proper use load without exceeding the maximum permissible tem-
In the event of improper use, there is a danger to life for perature.
the user as well as for third parties. Moreover, the product
and/or attachments may be damaged or destroyed. “S2” operating mode (short-term operation)
The operating time is specified in minutes, for example,
It is important to ensure that the product is only operated S2-20. That means, that the machine can work 20 min-
in technically perfect condition and as intended. utes and should pauses after it, as long as the machine is
To do so, follow the operating instructions. cooled down to 2K over medium temperature.

The pumps can be used in the range specified by us at any Operating mode “S3“ (intermittent operation):
time, in accordance with the current HOP.SEL version. For these operating modes, after the abbreviation, the
We have selected the pump based on the data available to duty cycle is displayed as well as the cycle duration if it
us. Please note that the offered pumps may only be used deviates from 10 minutes. Example S3 30% means, that
in the defined field of application. Operating the pump out- the machine can work 3 minutes and afterwards should
side the range of application can lead to operational prob- pauses 7 minutes.
lems or significant damage to the unit. Particularly with
long pipes, it may be necessary to start the pump slowly Low Level Lockout
via VFD or soft start system. The low level lockout is designed to automatically shut
down the product if the water level falls below the mini-
1.4. Copyright mum water coverage value of the product. This is made
possible by installing a float switch.
This operation and maintenance manual has been copy-
righted by the manufacturer. This operation and mainte- Level control
nance handbook is intended for use by assembly, oper- The level control is designed to switch the product on or
ating and maintenance personnel. It contains technical off depending on the filling level. This is made possible by
specifications and diagrams which may not be reproduced installing a float switch.
or distributed, either completely or in part, or used for any
other purpose without the expressed consent of the man-
ufacturer.

1.5. Technical terms


Various technical terms are used in this operating and
maintenance manual.

Dry run
The product is running at full speed, however, there is no
liquid to be pumped. A dry run is to be strictly avoided. If
necessary, a safety device must be installed.

English | 03
2. Safety • Mobile working equipment for lifting loads should
be used in a manner that ensures the stability of the
This chapter lists all the generally applicable safety instruc- working apparatus during operation.
tions and technical information. Furthermore, every other • When using mobile working equipment for lifting
chapter contains specific safety instructions and techni- non guided loads, measures should be taken to avoid
cal information. All instructions and information must be tipping and sliding etc.
observed and followed during the various phases of the • Measures should be taken that no person is ever
product‘s lifecycle (installation, operation, maintenance, directly beneath a suspended load. Furthermore,
transport etc.). The operator is responsible for ensuring it is also prohibited to move suspended loads over
that personnel follow these instructions and guidelines. workplaces where people are present.
• If mobile working equipment is used for lifting loads,
2.1. Instructions and safety information a second person should be present to coordinate the
procedure if needed (for example if the operator‘s
This manual uses instructions and safety information for field of vision is blocked).
preventing injury and damage to property. • The load to be lifted must be transported in such a
To make this clear for the personnel, the instructions and manner that nobody can be injured in the case of a
safety information are distinguished as follows: power cut. Additionally, when working outdoors,
such procedures must be interrupted immediately if
Each safety instruction begins with one of the following weather conditions worsen.
signal words:
These instructions must be strictly observed.
Danger: Serious or fatal injuries can occur! Non-observance can result in injury or serious
Warning: Serious injuries can occur! damage to property.
Caution: Injuries can occur!
Caution (Instruction without symbol): Serious damage 2.3. Operating personnel
to property can occur, including irreparable damage!
All personnel who work on or with the product must be
Safety instructions begin with a signal word and descrip- qualified for such work; electrical work, for example may
tion of the hazard, followed by the hazard source and only be carried out by a qualified electrician. The entire
potential consequences, and end with information on personnel must be of age. Operating and maintenance
preventing it. personnel must also work according to local accident pre-
vention regulations. It must be ensured that personnel
2.2. General safety have read and understood the instructions in this operat-
ing and Maintenance handbook; if necessary this manual
• Never work alone when installing or removing the must be ordered from the manufacturer in the required
product. language.
• The machine must always be switched off before
any work is performed on it (assembly, dismantling,
maintenance, installation). The machine must be dis- 2.4. Electrical work
connected from the electrical system and secured
Our electrical products are operated with alternating or
against being switched on again. All rotating parts
industrial high-voltage current. The local regulations (e.g.
must be at a standstill.
VDE 0100) must be adhered to. The “Electrical connec-
• The operator should inform his/her superior immedi-
tion” data sheet must be observed when connecting
ately should any defects or irregularities occur.
the product. The technical specifications must be strictly
• It is of vital importance that the system is shut down
adhered to. If the machine has been switched off by a
immediately by the operator if any problems arise
protective device, it must not be switched on again until
which may endanger safety of personnel. Problems
the error has been corrected.
of this kind include:
• Failure of the safety and/or control devices
Beware of electrical current!
• Damage to critical parts
Incorrectly performed electrical work can result in
• Damage to electric installations, cables and
fatal injury! This work may only be carried out by a
insulation.
qualified electrician.
• Tools and other objects should be kept in a place
reserved for them so that they can be found quickly.
Beware of Moisture!
• Sufficient ventilation must be provided in enclosed
Moisture penetrating cables can damage them
rooms.
and render them useless. Furthermore, water can
• When welding or working with electronic devices,
penetrate into the terminal compartment or motor
ensure that there is no danger of explosion.
and cause damage to the terminals or the winding.
• Only use fastening devices which are legally defined
Never immerse cable ends in the pumped fluid or
as such and officially approved.
other liquids.
• The fastening devices should be suitable for the
conditions of use (weather, hooking system, load,
etc). If these are separated from the machine after
use, they should be expressly marked as fastening
devices. Otherwise they should be carefully stored.

04 | English
2.4.1. Electrical connection 2.7. Operation in an explosive atmosphere
When the machine is connected to the electrical control Products marked as explosion-proof are suitable for op-
panel, especially when electronic devices such as soft eration in an explosive atmosphere. The products must
startup control or frequency drives are used, the relay meet certain guidelines for this type of use. Certain rules
manufacturer‘s specifications must be followed in order of conduct and guidelines must be adhered to by the op-
to conform to EMC. Special separate shielding measures erator as well. Products that have been approved for op-
e.g. special cables may be necessary for the power supply eration in an explosive atmosphere are marked as explo-
and control cables. sion-proof rated by FM. In addition, an “FM” symbol must
The connections may only be made if the equipment be included on the name plate!
meets NEC standards. Mobile radio equipment may
cause malfunctions. 2.8. Sound Safety
Depending on the size and capacity (kW), the products
Beware of electromagnetic radiation!
produce a sound pressure of up to110 dB. The actual
Electromagnetic radiation can pose a fatal risk for
sound pressure, however, depends on several factors.
people with pacemakers. Put up appropriate signs
These include, for example, the installation type (wet, dry,
and make sure anyone affected is aware of the
transportable), fastening of accessories (e.g. suspension
danger.
unit) and pipeline, operating site, immersion depth, etc.
Once the product has been installed, we recommend that
2.4.2. Ground connection
the operator make additional measurements under all op-
Our products (machine including protective devices and erating conditions.
operating position, auxiliary hoisting gear) must always be
grounded. If there is a possibility that people can come Caution: Wear ear protectors!
into contact with the machine and the pumped liquid (e.g. In accordance with the laws in effect, guidelines,
at construction sites), the grounded connection must be standards and regulations, ear protection must be
additionally equipped with a fault current protection de- worn if the sound pressure is greater than 85 dB (A)!
vice. The electrical motors conform to motor protection The operator is responsible for ensuring that this is
class IP 68 in accordance with the valid norms. observed!

2.5. Operating procedure 2.9. Pumped fluids


When operating the product, always follow the locally Each pumped fluid differs in regard to composition, cor-
applicable laws and regulations for work safety, accident rosiveness, abrasiveness, TS content and many other
prevention and handling electrical machinery. To help to aspects. Generally, our products can be used for many
ensure safe working practice, the responsibilities of em- applications. For more precise details, see chapter 3, the
ployees should be clearly set out by the owner. All per- machine data sheet and the order confirmation. It should
sonnel are responsible for ensuring that regulations are be remembered that if the density, viscosity or the general
observed. Certain parts such as the rotor and impeller ro- composition change, this can also alter many parameters
tate during operation in order to pump the fluid. Certain of the product. Different materials and impeller shapes
materials can cause very sharp edges on these parts. are required for different pumped fluids. The more exact
your specifications on your order, the more exactly we can
Beware of rotating parts! modify our product to meet your requirements.
The moving parts can crush and sever limbs. Never
reach into the pump unit or the moving parts during If the area of application and/or the pumped fluid change,
operation. Switch off the machine and let the moving we will be happy to offer supportive advice.
parts come to a rest before maintenance or repair
work! When switching the product into another pumped fluid,
observe the following points:
2.6. Safety and control devices
• Products which have been operated in sewage or
Our products are equipped with various safety and control waste water must be thoroughly cleaned with pure
devices. These include, for example moisture sensors and water or drinking water before use.
temperature sensors. These devices must never be dis- • Products which have pumped fluids which are haz-
mantled or disabled. Equipment such as thermo sensors, ardous to health must always be decontaminated
float switches, etc. must be checked by an electrician before changing to a new fluid. Also clarify whether
for proper functioning before start-up (see the “Electrical the product may be used in a different pumped fluid.
Connection” data sheet). Please remember equipment • With products which have been operated with a
such as PT100 temperature monitors or float switches lubricant or cooling fluid (such as oil), this can escape
require the use of a HOMA GO switch for connection. into the pumped fluid if the mechanical shaft seal is
Please contact your HOMA distributor for information. defective.
Personnel must be informed of the installations used and
how they work.
Danger - explosive fluids!
It is absolutely prohibited to pump explosive liquids
Caution! (e.g. gasoline, kerosene, etc.). The products are not
Never operate the machine if the safety and monitor- designed for these liquids!
ing devices have been removed or damage, or if they
do not work.

English | 05
3. General description 3.3. Construction
The pump consists of the motor and the pump housing as
3.1. Application well as the impeller which belongs to it.
Pump is suitable for pumping sewage, effluents, sludge
and surface water. The pumps are used for installations in 
public and private sector, trade and industry. The pumps 
can convey abrasive medium as surface water. For high- 
ly abrasive content, such as concrete-gravel and sand in
the medium, it is necessary to protect the impeller and
pump housing against excessive abrasion or to shorten
the maintenance interval. 

Before the pumping of chemically aggressive liquids, the


resistance of the pump materials must be checked.
The pumps are available in high quality materials of all
components (Stainless steel, bronze).

According to the type of installation and motor cool-
ing, the machine must be submerged in pumped liq- 
uid at least up to the top edge of the pump or mo-
tor housing. For continuous operation (S1) without a
cooling jacket, the motor housing must completely be
submerged. 

The temperature of the pumped medium may be up to


104°F or up to 140°F for a short period. The maximum No. Description
density of the medium is 0.03757 lbs/in³ and the pH may 1 Eye hooks for lifting
be from 6 – 11. Stainless steel variants can be used at 2 Name plate
a pH of 4 - 14. However, the pH alone only serves as a 3 Pump housing
guideline. Consult factory for assistance with chemically
4 Suction inlet
aggressive liquids. Depending on the composition, it may
be necessary to use special sealing materials. 5 Discharge
6 Motor housing
3.2. Types of use 7 Cable entry

The motors are designed for continuous operation (S1),


maximum 15 starts per hour. The hydraulic is designed for
permanent operation, e.g. supply of industrial water.

06 | English
3.3.1. Name plate General motor data
Service factor 1.15
Operating mode S1
Max. liquid tempe- 35°C / 95°F
Pump:  Sn: 
Cont. Duty: 40° C amb. Flow max.:  gpm rature
Hmax:  ft Hmin:  ft  lbs Insulation class H (180°C / 356°F)
Motor:  Date:  Degree of protection IP68
U:   V I:  A
Hz a ~ P:  HP  rpm cos φ:  Cable length 32 ft
Cl.I,DIV.1,GR.CD Nema code: 
Wiring Diagram:  Ins. cl.: Rotor shaft seal Silicon-carbide / Silicon-carbide
Mechanical shaft seal Silicon-carbide / Silicon-carbide
Thermally protected! See manual for cord replacement!
Do not remove covers while circuits are alive! Bearing One grooved ball bearing (above),
APPROVED double-row type angular ball bearing

(below)

3.3.3. Monitoring Equipment

No. Description The unit is equipped with various types of monitoring-safe-


a Pump name ty equipment. The following table shows an overview of
b Serial number the options available. The options may vary depending on
the size of the pressure outlet
c Flow max
d Hmax (Head max)
e Hmin (Head min) Motortype Motorversion
f Submersion depth .../C Temperature monitoring in the winding, Oil chamber
g Weight seal conditions sensor
h Motor name …U... Fully submerged motor, Temperature monitoring in the
i Date of manufacture winding, Oil chamber seal conditions sensor
j Voltage
…L... Fully submerged motor, closed liquid cooling,
k Motor Power
Temperature monitoring in the winding, Seal probe
l Nominal current
leakage chamber
m Frequency
ma Phase ...FM Temperature monitoring in the winding, Explosion
n Motor speed proof
o Cos phi .../C FM Temperature monitoring in the winding, Oil chamber
p tTemperature class seal conditions sensor and motor connecting chamber,
p Nema Code Letter Explosion proof
r Wiring diagram …U... FM Fully submerged motor, Temperature monitoring in the
s Insulation class winding, Oil chamber seal conditions sensor,
t comments Explosion proof

Temperature Sensor
3.3.2. Motor All pumps are equipped with a temperature sensor as-
sembly in the motor windings. In pumps with the stan-
The three-phase asynchronous motor consists of one sta-
dard design, the connections for the temperature sensor
tor and the engine shaft with impeller assembly. The cable
are fed via the power cable to the outside and are to be
for the power supply is designed for maximum mechan-
connected in the electric control box using the T1 and T3
ical performance in accordance with the characteristic or
power cable endings in such a way that the motor auto-
pump name plate. Both the cable entries and the line are
matically restarts after it has cooled down.
water-pressure tight with respect to the substance being
pumped. The shaft bearing assembly is supported via ro-
Instead of the standard sensor, the explosion-proof ver-
bust, maintenance-free and permanently lubricated roller
sions are equipped with a temperature sensor assem-
bearings. All motors can also be delivered in an explo-
bly that has a higher activation temperature. This is to
sion-proof version in accordance with FM Class I, Division
be connected via the power cable endings T1 and T2 in
1, Groups C & D.
such a way that after activation, a manual reset in the
switchgear is necessary using a special contactor com-
bination. The temperature sensor assembly must be
connected in the switching cabinet so that it switches
off when it overheats.

English | 07
Switch-off temperature of the sensors: • Stator or Motor cap installation: Probe used to detect
the presence of water only into the stator housing or
Motor Stator Winding Stator Lower Upper motor cap terminal board.
Frame T1+T3 Winding FM Bearing Bearing • Closed loop cooling Installation: Probe placed in sta-
Regulator T1+T2 Limiter tor housing to detect the presence of liquid in the dry
chamber.
T 140°C / 284°F 140°C / 284°F 80°C / n/a * GO switch is required for sensor operation.
176°F
P 150°C / 302°F 140°C / 284°F 80°C / n/a 3.3.5. Sealing / Seal Housing
176°F
Sealing is accomplished by two silicon carbide mechani-
F 150°C / 302°F 140°C / 284°F 90°C / 105°C / cal seals in a tandem arrangement, acting independently
194°F 221°F from each other. The seal housing is situated between the
G 150°C / 302°F 150°C / 302°F 90°C / 105°C / motor and the pump housing. It consists of the bearing
194°F 221°F housing and the pressure cover, which together form the
sealing cavity with containing white mineral oil. Monitor-
H 150°C / 302°F 150°C / 302°F 90°C / 105°C / ing possibilities are available using the inspection plug on
194°F 221°F the bearing housing and optional electronic monitoring.

Seal monitoring for non-jacketed and media-cooled


3.3.6. Jacketed Pump Option
pumps:
In case of a leak in the lower shaft seal, water enters the The cooling jacket has been supplied based upon the
oil chamber and changes the resistance of the oil. The specified operating conditions of this application. It is
conductivity of the oil is monitored via 2 sensors. The sen- important this jacket is function properly, or the internal
sors are to be connected via 2 cables (labeled S1 and S2) motor components could become damaged. Several cool-
from the pump connection cables in the switch cabinet to ing configurations are available depending upon customer
an evaluation instrument galvanically separated from the preference and system requirements.
probe circuit. The response sensitivity should be adjust- You must know what configuration of cooling system is
able from 0-100 kΩ, the standard setting being 50 kΩ. to be used with the pump prior to installation. In some
cases, field test results may indicate a change of cooling
Seal monitoring for pumps with closed-loop cooling: method is required. Consult factory for necessary chang-
The penetration of coolant (water-glycol mixture) into a es to the pump.
leakage chamber is registered via 2 sensors. This leakage
chamber is situated between the motor-side mechanical Cooling Requirements
seal and the bottom shaft bearing. If the motor-side shaft 1 - Standard Media Cooled –
bearing should leak, coolant leaks into the leakage cham- This construction does not require any external piping and
ber and establishes the contact between both sensors. it is completely self-contained. This design is suitable for
The sensors are to be connected via 2 cables (labeled S11 the routine collection system application. No pump modi-
and S12) from the pump connection cables in the switch fications are required.
cabinet to an evaluation instrument galvanically separated
from the probe circuit. • Required Hardware – Automatic air bleed valve
mounted in upper vent port or a ¼” or 3/8” elbow
3.3.4. Additional pump protection devices and small block valve for venting. A length of hose
routed to the sump should be attached to either air
Several optional pump protection devices are available to bleed or the block valve outlet.
protect submersible motors from damage, and may have • Start Up Requirements – This jacket must be vent-
provided in your pump. ed at start up. Additional venting may be required af-
ter situations where the suction or discharge piping
Temperature Sensing RTD*: PT100 sensors are avail- has been removed for maintenance and reinstalled.
able in two critical locations on larger machines, the lower Some adverse operating conditions can allow air to
bearings and motor windings. N.C. Circuit - 108 ohm become trapped in this jacket. This must be periodi-
cally vented off. If this occurs, it is recommended the
Moisture Sensors: Two styles of moisture sensors are small air bleed valve is utilized.
available on HOMA pumps.
2 - Media Cooled with External Flush -
Moisture Detectors*: These are micro float switches de- This construction requires an external flow of water, typ-
signed to detect small amounts of liquid. These are avail- ically re-use water. Applications which require this option
able in the stator housing of 50hp and larger size pumps. are typically heavy slurry or sludge service often found in
N.C. Circuit - 268 ohm the treatment plant. This option routes the externally sup-
plied water into the pumped media. No pump modifica-
Leakage Detectors*: These normally open, 2 wire probes tions are required.
are used to detect the presence of water in the pump.
Optional leak detectors can be installed as follows: • Required Hardware – Mounting a regulating valve,
pressure gauge and automated block valve between
• Stator Chamber installation: Probe placed in bottom the water supply and the upper jacket port is re-
of stator housing to detect presence of water in the quired. The supply valve should be adjusted to al-
chamber. low the supply of water to exceed pump discharge

08 | English
pressure. This assures a positive flow of water into 4. Package, Transport, Storage
the pump chamber. The block valve should be auto-
mated to open whenever the pump is operated. 4.1. Delivery
• Start Up Requirements – This jacket must be vented
at start up. Additional venting may be required if cool- On arrival, the delivered items must be inspected for dam-
ing water supply is interrupted. age and a check made that all parts are present. If any
parts are damaged or missing, the transport company or
3 - External Fluid Cooled - the manufacturer must be informed on the day of delivery.
This option requires an external flow of water like in op- Any claim made at a later date will be deemed invalid.
tion 2 above, but is used where dilution of the pumped Damage to parts must be noted on the delivery or freight
product is not desirable. The supply of water is internally documentation.
isolated from the pumped media. The water inlet is routed
into the jacket’s lowest port and returned out of the high- 4.2. Transport
est port. This option does NOT allow water to enter the Only the appropriate and approved fastening devices,
pumped media and pump must be ordered from factory transportation means and lifting equipment may be used.
this way. These must have sufficient load bearing capacity to en-
sure that the product can be transported safety. If chains
• Required Hardware – Mounting a regulating valve, are used they must be secured against slipping.
pressure gauge and automated block valve between The personnel must be qualified for the tasks and must
the water supply and the upper jacket port is re- follow all applicable national safety regulations during
quired. The supply valve should be adjusted to allow the work. The product is delivered by the manufacturer/
for a good supply of water to flow through the jacket. shipping agency in suitable packaging. This normally pre-
The block valve should be automated to open when- cludes the possibility of damage occurring during trans-
ever the pump is operated. port and storage.

3.3.7. Volute Never lift the pump by its power cable! Jacketed
The volute may be available rubber-coated inside. Some pump should never storage or shipped with the pump
volutes are supplied with a cleanout port to easily remove by the jacket. Damage to sealing O Rings may result.
blockages. The pump may be equipped with a stationary
wear ring which can be found in the intake port. This wear 4.3. Storage
ring determines the gap between the impeller and the in- Newly supplied products are prepared that they can be
take port. If this gap is too big, the performance of the stored for 1 year. The product should be cleaned thor-
pump decreases and it can lead to blockages. The rings oughly before interim storage.
can be replaced due to wear. The following should be taken into consideration for
storage:
3.3.8. Impeller
• Place the product on a firm surface and secure it
M: Enclosed single channel impeller, for liquids containing against falling over. Submersible mixers and aux-
impurities and sludge with solid particles or long fibres. iliary lifting devices should be stored horizontally,
K: Enclosed multi channel impeller, for liquids containing submersible sewage pumps and submersible motor
impurities and sludge with solid particles. pumps should be stored horizontally or vertically. It
should be ensured that they cannot bend if stored
V: Vortex impeller, for liquids containing a high level of horizontally.
impurities or fibrous matter and containing gas.
Falling Hazard!
Never leave the pump unsecured!

• The product has to be stored in a place free from


vibrations and agitation to avoid damage to the ball
bearings.
• The device should be stored in a dry place without
temperature fluctuation.
• The product may not be stored in rooms where weld-
ing work is conducted as the resulting gases and ra-
diation can damage the elastomer parts and coatings.
• Be careful to not remove or damage the corrosion
resistant coatings.
• Any suction or pressure connections on products
should be closed tightly before storage to prevent
impurities.
• The power supply cables should be protected against
kinking, damage and moisture.

English | 09
• The cable will wick water into the pump if it is not pro- 5. Installation and initial commissioning
tected properly. Power cable lead should be covered
with shrink tubing or suitable sealing material during 5.1. General
storage.
To avoid damage to the lifting unit during installation and
Beware of electrical current! operation, the following points must be observed:
Damaged power supply cables can cause fatal inju-
ry! Defective cables must be replaced by a qualified • The installation work must be performed by qualified
electrician immediately. personnel, in compliance with safety regulations.
• The pump must be inspected for damage prior to in-
Beware of moisture! stallation.
Moisture penetrating cables can damage them and • For level controls, pay attention to the minimum wa-
render them useless. Therefore, never immerse ca- ter coverage.
ble ends in the pumped fluid or other liquids. • Air bubbles in the volute and pipework must be avoid-
ed (by suitable ventilation devices or a slight incline
• The machine must be protected from direct sunlight, of the pump).
heat, dust, and frost. Heat and frost can cause con- • Protect the pump from frost.
siderable damage to impellers, rotors and coatings. • The lifting device must have a maximum load capaci-
• The impeller must be turned at monthly intervals. ty which is greater than the weight of the pump with
This prevents the bearing from locking and the film attachments and cable.
of lubricant on the mechanical shaft seal is renewed. • The power lines of the pump must be laid in such a
This also prevents the gear pinions (if present on the way, that a safe operation and easy assembly/disas-
product) from becoming fixed as they turn and also sembly is ensured.
renews the lubricating film on the gear pinions (pre- • The power lines must be fixed properly in the operat-
venting rust film deposits). ing room to prevent the cable from hanging loosely.
Depending on the cable length and weight, a cable
Beware of sharp edges! holder must be attached every 2-3 m.
Sharp edges can form on rotors and impellers. • The foundation/structure must have sufficient
There is a risk of injuries. Wear protective gloves. strength for secure and functionally correct fastening
of the pump. The operator is responsible for this.
• If the product has been stored for longer than six • Verify low level lockout is functioning.
month it should be cleaned of impurities such as dust • Use baffles for the inlet. This prevents air entry into
and oil deposits before start-up. Rotors and impellers the pumping medium, which can lead to unfavorable
should be checked for smooth running, housing coat- operating conditions and result in increased wear.
ing and damage. • Do not install more than one check valve into any pip-
• After remaining in storage for longer than one year, ing system or problems will occur.
it is necessary to change the oil in the seal chamber.
This is necessary even if the pump has never been
run, due to natural deterioration of mineral oil.

Before start-up, the filling levels (oil, cooling fluid


etc.) of the individual products should be checked and
topped up if required. Please refer to the machine data
sheet for specifications on filling. Damaged coatings
should be repaired immediately. Only a coating that
is completely intact fulfills the criteria for intended
usage!

If these rules are observed, your product can be stored


for a longer period. Please remember that elastomer parts
and coatings become brittle naturally. If the product is
to be stored for longer than 6 months, we recommend
checking these parts and replacing them as necessary.
Please consult the manufacturer.

4.4. Returning to the supplier


Products which are delivered to the factory must be clean
and correctly packaged. In this context, clean means
that impurities have been removed and decontaminat-
ed if it has been used with materials which are hazard-
ous to health. The packaging must protect the product
against damage. Please contact the manufacturer before
returning!

10 | English




5.2. Installation

Risk of falling!
 When installing the pump and accessories, work is
carried out next to wetwell! Carelessness or wearing
the wrong shoes can lead to falling. This is life threat-
ening! Take all safety precautions to prevent this.

Torque Values
No. Description
1 Pipe PUMPump mo- Bolts SIZEize TORQUE
delInstallation Anchors
2 Coupling system
3” Autocoupling 8 M16X60mm 146 Nm / 108 ft lb
3 Service room 4 M16 100 Nm / 74 ft lb
4 Inlet 4” Autocoupling 8 M16X60mm 146 Nm / 108 ft lb
5 Baffle plate 4 M16 100 Nm / 74 ft lb
6 min. liquid level 3” & 4” Ring stand 4 M16x25mm 146 Nm / 108 ft lb
7 Pump 3” & 4” Dry sump 8 M16x40mm 146 Nm / 108 ft lb
4 M16 100 Nm / 74 ft lb

External Seal Probe Installation Procedure 6” Autocoupling 8 M20x70mm 200 Nm / 150 ft lb


4 M16 100 Nm / 74 ft lb
Mechanical Seal Leak Detection probe has been loose 6” Ring stand 4 M20x40mm 200 Nm / 150 ft lb
to protect from shipping damage. Please follow this
6” DRYry SUMP- 8 M20x45mm 200 Nm / 150 ft lb
procedure to install the probe.
sump 4 M16 100 Nm / 74 ft lb
(1 Piece)
1. Lay pump on its side with the plug on the seal cham-
ber facing upwards as indicated. 6” DRYry SUMP- 8 M20x65mm 200 Nm / 150 ft lb200
2. Unscrew the plug with the proper wrench, taking sump 6” 4 M16 Nm / 150 ft lb
care not to damage the sealing surface. (N/P Motor) 100 Nm / 74 ft lb
3. Verify that seal chamber oil level is within ¼” of the DRY SUMP 6” Dry 8 M20x70mm 100 Nm / 74 ft lb
indicated value. Measurement is from oil level to the sump 4 M16 200 Nm / 150 ft lb
top of hole. See IOM Manual for seal chamber oil vol- (F Motor) 100 Nm / 74 ft lb
ume, if required.
4. Remove the new sealing gasket from package and 8” Autocoupling 8 M20x70mm- 200 Nm / 150 ft lb
install it onto the seal probe plug. 4 M20x70m 200 Nm / 150 ft lb
5. Install the seal probe with gasket into the opening, M20x70mm 200 Nm / 150 ft lb
taking care not to damage the cable. Then tighten the M20
seal probe with the proper wrench until snug. Do not 8” Ring stand 4 M20x30mm 200 Nm / 150 ft lb
overtighten. Once tight, verify the seal gasket is prop- 8” DRYry SUMP- 8 M20x75mm 200 Nm / 150 ft lb
erly seated and the cable is not pinched or twisted. sump 4 M20 200 Nm / 150 ft lb
NOTE: At installation of the seal probe be careful not (2 Piece)
to bind the seal probe cord as it is being installed into
the pump.
6. Lift pump into a vertical position and inspect for any
leaks.
7. Secure seal probe cable to pump body and power ca-
ble with tyraps before installing pump.

English | 11
Notes: • Attach the chain to the pump handle or lifting lugs.
1. For pumps larger than 8” please consult factory. Insert the pump with the guide rails in the guide claw
2. Flange bolts must be tightened in cross pattern to ears. Lower the pump into the wet well. If the pump
avoid damage to the raise face flanges. is seated on the base elbow, it automatically seals it-
3. Standard flange bolts are 316SS self off to the pressure line and is ready for operation.
4. Standard anchors are plated steel. • Hang the end of the retrieval chain from a hook at the
5. Autocoupling systems include qty. 4 M12 anchors for wet well opening.
the upper bracket. Torque to 51 Nm / 38 ft lb. • Hang the motor connection cable of the pump in the
6. Anchor bolt holes should be drilled to the actual di- shaft at an appropriate length, with strain relief. Make
ameter of the anchor (M12 anchor requires 12mm sure that the cables can not be bent or damaged.
diameter hole).
Correct Incorrect
Submerged installation on ring stand
Attach the ring stand (available as an accessory) with
screws to the pump suction nozzle. 90° connection-el-
bow or connection loop to the pressure port of the pump,
mount pressure line. Gate valves and check valves may
need to be installed in accordance with local regulations.
The pressure line must be fitted free of tension, when Rubber Ring Rubber Ring
using a hose, ensure it is laid kink-free.
Secure the pump by the handle with a cable or chain, and
lower it into the pumping medium. Properly position pow-
er cable and chain so they stay above the pump and con-
nate enter the pump suction.
Dry Installation
Wet installation with automatic coupling system Foundation and Piping Requirements:
The following instructions apply to the installation of the
original HOMA Autocoupling system: General
The following recommendations are basic guidelines
• Determine the approximate position of the base el- which are intended to outline basic requirements in the
bow and the upper pipe bracket for the guide tubes, design of the dry pit station. It is essential that a licensed
using a plumb bob where necessary. professional engineer be retained by the owner to design
• Check the correct installation dimensions of the the station and all support structures.
pump(s) (see dimensional drawings in the appendix).
• Drill mounting holes for the guide rail bracket on the Foundations
inside edge of the shaft opening. If this is not possi- Foundations may consist of any structure heavy enough
ble due to the space available, the guide rail bracket to provide permanent rigid support for the pump and inlet
can also be mounted in an offset position with a 90° elbow stand. Concrete foundations built up from the solid
folded plate on the underside of the shaft cover. Pro- ground are the most commonly used. The concrete floor
visionally fasten the guide rail bracket with 2 screws. shall be level. The space required by the inlet stand and
• Align the base elbow to the shaft floor, use a plumb the location of the foundation anchor bolts are shown on
bob from the pipe bracket - the guide tubes must be the outline dimension drawing. Foundation bolts are to be
exactly perpendicular! Fasten the base elbow to the embedded in the concrete.
wet well floor using anchor bolts. Ensure that the
base elbow is exactly horizontal! If the wet well floor Suction Piping
is uneven, support the bearing surface accordingly. Suction piping should be at least as large as the pump
• Mount the pressure pipes with fittings free of tension inlet elbow suction. If reducers are utilized they should be
according to the usual mounting principles. of the conical type. If the liquid source level is below the
• Insert both guide rails into the eyelets on the base volute horizontal centerline, the reducer must be eccen-
elbow and cut to size according to the position of the tric and installed with the level side up. If the liquid level is
guise rail bracket. Partially unscrew the guide rails above the pump volute horizontal centerline, either eccen-
bracket, insert them into the guide rails and fasten tric or concentric reducers may be used. Suction piping
the bracket. The guide rails must be positioned with should be run as straight as possible. All pipe flange joints
no play at all, otherwise vibration will occur during op- should be gasketed to prevent air from entering the pipe.
eration of the pump. High points that may collect vapor are to be avoided. Iso-
• Clean the wet well of any solid material (debris, lation valves such as gate valves can be installed in order
stones, etc.) before commissioning. to facilitate the removal of the pump for maintenance. Any
• Mount the guide claw on the pump discharge (thread valve installed in the suction line should be installed with
or flange connection). Ensure that the rubber profile the stems horizontal.
is correctly seated in position in the guide claw (as a
seal against the coupling base), so that it will not fall Discharge Piping
out when lowering the pump. See graphic below A check valve and isolation valve shall be installed in the
discharge line. The check valve should be installed be-
tween the pump discharge flange and the isolation valve.
If pipe increasers are used on the discharge line, they
should be placed between the check valve and the pump.

12 | English
The inlet elbow stand allows the pump to be installed in
a stationary position in a dry pit. Place the inlet stand in
position and tighten the anchor nuts.

Lower the pump on to the top flange of the inlet stand.


DO NOT ALLOW SLACK ON THE LIFTING CABLE UNTIL
THE PUMP IS BOLTED DOWN. Make sure the flange bolt
holes align with the mounting holes on the underside of
the volute. Secure the pump to the mounting flange with
the fasteners that are specified in the accessory fastener
selection table below.

Vent Valve Installation


HOMA dry pit pumps are supplied with a valve and fitting
that must be installed and maintained to ensure the prop-
er performance of these pumps.
The opening for this valve is located on the base of
the motor cap near the mounting screws. The pump is
shipped with a plug installed which must be removed pri-
or to start up.
This opening is a metric straight thread and requires an
adapter included with the valve and fitting hardware. It is
also recommended that a length of hose be attached to
the valve and routed back to the sump. Note: Leave vent valve open in wet pit pump application
to prevent air entrapment in jacket.
Pumps with cooling jackets must be vented!
The screw plug 903.02 must be removed and
replaced with the supplied vent valve.
5.3. Use of chains
Chains are used to lower a pump in the operating space
or to pull it out. They are not intended to secure a floating
pump. Intended use is as follows:

• Fasten one end of the chain on the handle of the


pump provided for this purpose. If your pump has
two ring bolts as an attachment point, you must use
a double-strand chain. When doing so, the angle of
inclination of the chain strands must be between 0°
and 45°.
• Attach the other end to the lifting device.
• Ensure tension on the chain, and then lift the pump in
a slow and controlled manner.
• Gently lower the pump into operating space and low-
er it gently.
• Lower the pump to the operating point and make
sure that the pump has a secure footing or the cou-
pling system is engaged correctly.
• Remove the chain from the lifting device and secure
it to the safety chain, which is located at the top of
the operating room. This ensures that the chain can
not fall into the operating area and constitute a dan-
ger to anyone.

English | 13
Please note the following diagrams during installation. • Activate all safety devices and emergency stop
switches before initial operation.
• Electrical and mechanical adjustments may only be
performed by professionals.
• This machine is only suitable for use at the specified
 operating conditions.

5.5. Preparatory work


This pump has been designed so that it will operate re-
liably and for long periods under normal operating con-
ditions. This requires, however, that you comply with all
advice and instructions.

Please check the following points:

• Cable routing - no loops, slightly taut


• Liquid temperature and immersion depth check - see
machine data sheet
• If a hose is used on the discharge side, it should be
 flushed before use with fresh water so that no depos-
its cause blockages
 • For wet installation, the wet well must be cleaned
• The pressure and suction side pipe systems are to be
clean and all valves are to be opened.
• If the pump is jacketed with media cooling, the jacket
must be completely bled of air, i.e. it must be com-
pletely filled with the medium and there may be no
more air in it. The venting can be done by suitable
ventilation devices in the system, or, if available, by
venting screws at the outlet nozzle.
No. Description • Check the accessories, pipe system and suspension
1 Chain guard unit for firm and correct fit
2 Chain • Review the present level control.
• An isolation test and a level control must be carried
3 Handle
out before commissioning.
4 Pump
5.4. Initial operation 5.6. Electrical

This chapter contains all the important instructions for op- When installing and selecting of electrical lines and when
erating personnel for the safe commissioning and opera- connecting the motor, the relevant local and NEC regula-
tion of the machine. The following information must be tions must be observed. The motor must be protected by
strictly adhered to and checked: a motor protection circuit breaker. Connect the motor per
the wiring diagram. Pay attention to the direction of rota-
• Type of installation tion! If rotation is in the wrong direction, the machine will
• Operating mode not perform to specifications. And can be damaged under
• Minimum/max water coverage. Immersion depth adverse circumstances. Check the operating voltage, and
ensure there is uniform power consumption by all phases
After a long downtime, these specifications are also to in accordance with the machine data sheet.
be checked and any defects are to be rectified!
The operation and maintenance manual must always Make sure that all temperature sensors and monitoring
be kept with the machine, or be kept in a designated devices, e.g. sealing chamber control, are connected and
place where it is always accessible for all of the oper- tested for function.
ating personnel.
Risk of electrocution!
To avoid injury to persons or damage during operation of Improper use of electricity can be fatal! All pumps
the machine, the following points must be observed: with exposed cable ends must be connected by a
qualified electrician.
• The initial operation may only be carried out by qual-
ified and trained personnel accompanied by an au- All electrical work shall be carried out under the super-
thorized HOMA representative following the safety vision of an authorized, licensed electrician. The present
instructions. state adopted edition of the National Electrical Code as
• All staff working on the machine must receive, read, well as all local codes and regulations shall be complied
and understand the instructions. with.

14 | English
5.6.1 Verification of power supply 5.6.5 Start / Run Capacitors and Relays
Prior to making any electrical connections or applying All single phase motors require start and run capacitors
power to the pump, compare the power supply available along with a start relay to operate. Capacitors and relays
at the pump station to the data on the unit‘s nameplate. must be sized for the specific motor.
Confirm that both voltage and phase match between Capacitors are sized based on ideal conditions.
pump and control panel. The run capacitor may need to be resized to match the
available field voltage. Each cap kit shipped is supplied
5.6.2 Power lead wiring with a wiring diagram and start up procedure.
HOMA pumps may be provided with 1 or more cables,
5.6.6 Single Phase Pump Start-Up Procedure
depending on motor horsepower and operating voltage.
Power leads U1, U2, & Z2 for single phase and U, V, W Run Capacitor sizing can vary depending on the incoming
for three phase pumps may be provided as single conduc- supply voltage provided. HOMA Single Phase pumps are
tor, or as multiple conductors. Multiple conductor config- provided with Start and Run Capacitor(s) sized for 220-
urations may use leads from separate cables, or may use 230V under load. Frequently, the available line voltage is
two conductors within one cable. Please refer to wiring considerable different than indicated, and the Run capac-
diagram in the appendix for specific connection details. itor(s) may need to be resized to match the available field
The pump must be connected electrically through a motor voltage. The following procedure will allow you to verify
starter with proper circuit breaker protection in order to proper operation of your single phase pump, and/or make
validate warranty. Do not splice cables. necessary changes to you capacitors to correct for your
power supply.
5.6.3 Thermal switch wiring
After verifying wiring is in accordance with your pump re-
Pumps are equipped with thermal switches embedded in quirements, start pump and record the following readings
the stator windings which are normally closed, automat- from each of the (3) pump cable leads.
ically resetting switches. Switches will open when the
internal temperature rises above the design temperature, Current under load:
and will close when the temperature returns to normal.
Thermal switches must be wired to a current regulated U1________Amps,>U2________Amps,>Z2________Amps
control circuit in accordance with the NEC.
Identify thermal switch leads marked T1 and T3 in the U1: (Should be) highest reading
power or control cable. U2: middle reading
The resistance across the leads will be 0.5 Ohms. Ther- Z2: lowest reading
mal leads must be connected to the thermal overload
relay located in the control panel. Thermal switch leads Lead U1 (common) should have the highest current read-
must be connected to validate warranty. ing. Lead Z2 (start) should have the lowest reading.
Note: All sizes of Class 1, Div. 1 pumps for hazardous If Z2 current draw is greater than the current draw of ei-
service must have thermal switch leads connected to a ther U1 or U2, a smaller size Run capacitor (lower micro-
current regulated control circuit in accordance with NEC. farad rating) is required to correct the condition. Example:
If a 60 µf Run capacitor was supplied, change to a 50 µf
5.6.4 Seal probe wiring Run capacitor and check current readings. Typically, only
one step down in capacitor size is required, but in certain
The mechanical seal leak detector probe utilized in the instances 2 steps may be required.
pump is a conductive probe which is normally open. The
intrusion of water into the seal chamber completes the ( ) The standard capacitor kit provided includes:
electrical circuit. Control panel provisions will sense this
circuit closure, and will provide indication or alarm func- ____________ µf start capacitor
tions depending on the panel design.
Either single or dual wire systems may be provided. Sin- ____________ µf run capacitor.
gle wire systems utilize one energizing conductor, and
the pump casing and neutral lead as the ground or return ( ) Additional run capacitors have been included for use
portion of the circuit. The dual wire systems utilize two in tuning the pump to match available line voltages for
separate conductors for each leg of the circuit. optimum performance.
With either system, the seal probe leads must be wired
into a control circuit provided in the control panel. This ____________ µf run capacitor
control circuit must energize the probe with a regulated
power source, and sense the closed circuit in event of ____________ µf run capacitor
water intrusion Indication and alarm functions must also
be provided in the control circuit. Please see control panel ____________ µf run capacitor
wiring diagram for seal probe connection points.
This form is provided for your use in optimizing the perfor-
For Hazardous Area Classification Pumps, leak de- mance and service life of your single phase pumps, and is
tector circuit must be in conformance with applica- applicable to most Capacitor Start/Capacitor Run motors.
ble NEC codes and regulations. Please contact our customer service with any questions
or if you require any additional information or assistance.

English | 15
5.7. Direction of rotation As a minimum, properly sized load reactors and filters
must be installed between the inverter and the pump to
Rotation Direction Check
protect the pump motor from damaging voltage spikes.
All pumps have the proper rotation direction when con-
nected to a clockwise field of rotation leads. If the pump
Warranty coverage will not be provided on any pump mo-
rotation is backwards, swap two lead and reconnect. For
tor that is operated with a variable frequency drive, unless
smaller pumps, the check can be done by observing the
the load side of the inverter is properly isolated from the
pump’s movement while starting. To do this, set the pump
pump.
lightly on the ground in a perpendicular fashion and switch
it on briefly. When observing from above, the pump itself
5.10. Types of startups
moves slightly in a counter-clockwise direction when ro-
tating in the right direction. Types of startup using with cables with exposed ends

The correct direction of rotation of the pump is achieved Direct start up


once the pump moves counter-clockwise, since when At full load, the motor protection circuit breaker should
viewed from above, the motor starts in a clockwise be set to the rated current. In partial load operation it is
direction. recommended to set the motor protection circuit breaker
5% above the measured current at the operating point.
ATTENTION ATTENTION
ROTOR REACTION
START REACTION

The direction of rotation The start reaction is


is correct if the counter clockwise Soft start
impeller/propeller rotates At full load, the motor protection should be set to the rat-
in a clockwise manner
when viewing down from ed current. In partial load operation, it is recommended to
top of the placed unit set the motor protection 5% above the measured current
at the operating point. The starting time must be max.
5s. The starting voltage is to be set at 40% of the rated
For large pumps, the direction can also be determined by voltage according to the rating plate.
looking through the pump discharge into the volute. Brief-
ly run the motor in order to verify it is running clockwise. Start up with HOMA GO switch
Plug the connector into the socket provided and press the
Caution – Rotating Impeller! on/off switch on the GO switch.
Do not touch the rotating impeller or reach into the
volute through the pressure outlets! Never reach into 5.10.1. After start up
the volute or touch any rotating parts during opera-
tion. Switch the machine off and wait until all rotating The nominal current is briefly exceeded on start-up. Af-
parts have come to a stop prior to carrying out main- ter completion of this operation, the operating current
tenance and repair work! should not exceed the nominal current. If the motor does
not start immediately after switching on, it must be shut
It is also possible to check the direction of rotation with a down immediately. The switch breaks specified in the
“motor and phase rotation indicator”. This measurement technical data must be adhered to before turning on again.
device is held from the outside up to the motor housing If there is a new fault, the machine must again be shut
of the switched-on pump and displays the direction of ro- down immediately. The machine may only be started up
tation via an LED. again after troubleshooting.
The following items should be checked:
5.8. Motor protection
• Current consumption (permissible deviation between
The minimum requirement is a thermal relay/motor pro- phases max. 5%)
tection circuit breaker with temperature compensation, • Voltage difference between the individual phases
differential triggering, and reclosing lock in accordance (max. 1%)
with VDE 0660 or similar national regulations. If the equip- • Switching frequency and pauses (see Technical Data)
ment is connected to power grids where problems often • Air entry at the inlet - if necessary, a baffle plate must
occur, we recommend the additional use of protective be attached
devices (e.g. overvoltage protection or under voltage pro- • Minimum water coverage, level control, dry run pro-
tection or phase failure relays, lightning protection, etc.). tection
When connecting the machine, the local and legal require- • Smooth running
ments must be adhered to. • Check for leaks: if necessary, take the necessary
steps according to the chapter “Maintenance”
5.9. Variable Frequency Drives
Special considerations must be taken when operating
pumps with variable frequency drives (inverters).The in-
verter circuit design, horsepower required by pump, mo-
tor cooling system, power cable length, operating voltage,
and anticipated turndown ratio must be fully evaluated
during the design stage of the installation.

16 | English
6. Maintenance Oil type: white mineral oil. Used oil is to be disposed ac-
cordingly.
6.1. General
When using white mineral oil, note the following:
The machine and the entire system must be inspected
and maintained at regular intervals. The time limit for • Machines which have previously been operated us-
maintenance is set by the manufacturer and applies to ing other lubricants must first be thoroughly cleaned
the general conditions of use. The manufacturer should before they can be operated using white mineral oil.
be consulted if the system is to be used with corrosive
and/or abrasive pumped liquids, as the time limit between
inspections may need to be reduced.

Note the following information:

• The operating and maintenance manual must be


available to the maintenance personnel and its in-
structions followed. Only the repair and maintenance
measures listed here may be performed.
• All maintenance, inspection and cleaning work on the
machine and the system may only be carried out by 6.2. Maintenance intervals
trained specialists exercising extreme care in a safe
workplace. Proper protective clothing is to be worn. Before initial start-up or after a longer period of
The machine must be disconnected from the electric- storage:
ity supply before any work is carried out. There must • Check insulation resistance
be no way that it can be inadvertently switched on. • Check oil level in seal chamber
• Above a weight of 50kg, only hoisting gear which has • Check that impeller rotates freely by hand
been officially approved and which is in a technical-
ly perfect condition should be used for lowering and Monthly:
raising the machine. • Monitor the amperage and voltage
• Check the used relays for proper operation
Make sure that all fastening devices, ropes and safe-
ty devices are in a technically perfect condition. Work Every six months:
may only commence if the auxiliary hoisting gear has • Visual inspection of the power supply cable
been checked and found to be in perfect working order. • Visual inspection of the cable holder and the cable
If it is not inspected, danger to personnel may result! bracing
• Visual inspection of accessories, e.g. the suspension
• Wiring work on the machine and system must be device and hoisting gears
carried out by an electrician. For machines approved
for work in areas subject to explosion danger, please 8,000 operating hours or after two years, whichever
refer to the “Explosion protection in accordance with is earlier:
the regulation” chapter. • Check the insulation resistance
• When working with inflammable solvents and clean- • Check the lubricant in the seal chamber
ing agents, fires, unshielded lighting and smoking are • Functional inspection of all safety and control devices
prohibited.
• Machines which circulate fluids hazardous to health, 15,000 operating hours or after five years, whichever
or which come into contact with them, must be de- is earlier:
contaminated. It must be ensured that no dangerous • General overhaul
gases can form or are present. If it is used in highly abrasive or corrosive material, the
• Ensure that all necessary tools and materials are maintenance intervals should be reduced!
available. Tidiness and cleanliness guarantee safe and
problem-free operation of the machine. After work- 6.3. Maintenance tasks
ing on the machine all cleaning materials and tools
Monitoring the current consumption and voltage
should be removed from it. All materials and tools
The current consumption and voltage is to be monitored
should be stored in an appropriate place.
periodically for all winding phases. This remains constant
• Operating supplies such as oil and lubricants must
during normal operation. Slight fluctuations are a result
be collected in appropriate vessels and proper-
of the composition of the pumped fluid. The current con-
ly disposed. Appropriate protective clothing is
sumption can assist in early detection and correction of
to be worn for cleaning and maintenance jobs.
damage and/ or faulty operation in the impeller/propeller,
Only lubricants expressly recommended by the
bearings and/or the motor. More extensive resulting dam-
manufacturer may be used. Oils and lubricants should
age can thus be largely prevented and the risk of a total
not be mixed. Only use genuine parts made by the
failure can be reduced.
manufacturer.

A trial run or functional test of the machine must be


performed as instructed in the general operating con-
ditions.

English | 17
Checking the used relays for posistors, oil chamber Oil Condition
monitors, etc. The condition of the mechanical seals can be visually in-
Check the relays used are functioning fault-free. Defective spected as follows: Put the pump in horizontal position, so
devices must be immediately replaced, because these that the oil chamber drain plug is on top (for larger pumps:
cannot ensure safe operation of the machine. The test one of both oil chamber screws). Remove the drain plug
procedure details should be followed closely (in the oper- and take out a small quantity of oil. The oil becomes grey-
ating instructions for each relay). ish white like milk if it contains water. This may be the
result of defective shaft seals. In this case the condition
Checking the insulation resistance of the shaft seals should be checked by a HOMA Service
To check the insulation resistance, the power supply ca- shop. Oil type: Mineral Oil
ble must be disconnected. The resistance can then be Used oil has to be disposed according to the existing en-
measured with an insulation tester (measuring voltage = vironmental rules and regulations.
1000V DC).
Visual Inspection of Coolant Chamber (Closed Loop
The following values may not be exceeded: Pumps Only):

• The insulation resistance may not be below 20 MΩ Quantity of Coolant


during initial operation. For all further measurements Please take the precise filling quantity from the spare
the value must be greater than 2 MΩ. parts list or contact the manufacturer with the pump serial
• Insulation resistance too low: Moisture may have number.
penetrated the cable and/or the motor.
The condition of the mechanical seals can be inspected
Do not connect the machine, consult manufacturer! controlled as follows: Set up the pump vertically and un-
screw the ventilation screw located above and remove a
Visual inspection of power supply cables small quantity of coolant. If the cooling liquid becomes
The power supply line must be examined for bubbles, grey (original color: light pink or light orange) this may be
cracks, scratches, chafed areas and/or crushed sections. the result of defective shaft seals. In this case the con-
If damage is found, the power cable must be exchanged dition of the shaft seals should be checked by a HOMA
immediately. Service shop. Type: Silica-free propylene glycol-based an-
tifreeze (available on request). Used cooling liquid has to
The cables may only be changed by the manufactur- be disposed according to the existing environmental rules
er or an authorized/certified service workshop. The and regulations.
machine may not be used again until the damage has
been adequately rectified. Functional inspection of safety and control devices
Monitoring devices are temperature sensors in the motor,
Visual examination of the cable holders (carabiners) oil chamber monitors, motor protection relays, overvolt-
and the cable bracing age relays, etc.
When the machine is used in basins or pits, the lifting Motor protection and overvoltage relays and other trip
cables/cable holders (carabiners) and the cable bracing elements can generally be triggered manually for test
are subject to constant wear. Regular inspections are nec- purposes. To inspect the oil chamber monitor or the tem-
essary in order to prevent the lifting cables/cable holders perature sensor, the machine must be cooled to ambient
(carabiners) and/or cable bracing from wearing out and to temperature and the electrical supply cable of the moni-
prevent the electricity cable from being damaged. toring device in the switch cabinet must be disconnected.
The lifting cables/cable holders (carabiners) and the The monitoring device is then tested with an ohmmeter.
cable bracing are to be immediately replaced if any
signs of wear appear. The following values should be measured:
Bi-metal sensor: Value = “0” - throughput
Visual inspection of accessories PTC sensor: A PTC sensor has a cold resistance of be-
Inspect accessories such as suspension units and hoist- tween 20 and 100 Ω. For 3 sensors in series this would
ing gear to check whether they are secured in a stable result in a value of between 60 and 300 Ω.
manner. Loose and/or defective accessories should be PT 100 sensor: PT 100 sensors have a value of 100ohms
repaired immediately or replaced. at 0°C. Between 0°C and 100°C this value increases by
0.385 Ω per 1°C.
Oil Level check in Seal Chamber Moisture sensor: This value must approach infinity. If
there is a low value, there may be water in the oil.
Visual Inspection of Oil Chamber: Also observe the instructions of the optionally available
evaluation relay. In the case of larger deviations, please
Oil Level consult the manufacturer. Please consult the appropri-
Please take the precise filling quantity from the spare ate operating manual for details on inspecting the safety
parts list or contact the manufacturer with the pump serial and monitoring devices on the auxiliary lifting gear.
number.

18 | English
General overhaul 7. Repairs
During this the bearings, shaft seals, O rings and power
supply cables are inspected and replaced as required in 7.1. General
addition to normal maintenance work. This work may only
be conducted by the manufacturer or an authorized ser- When carrying out repair work, the following information
vice workshop. should always be noted:

Changing the oil • Round sealing rings as well as existing seals should
The drained oil must be checked for dirt and water con- always be replaced.
tent. If the oil is very dirty and shows water intrusion, it • Screw fixings such as spring washers should always
must be changed again after four weeks. If there is again be replaced.
water in the oil then, it seems likely that a seal is defec- • The correct torques must be observed.
tive. In this case, please consult the manufacturer. If a oil
chamber or leakage monitoring system is being used, the In general, the following applies to repairs:
display will light up again within four weeks of changing Switch off the machine, disconnect it from the pow-
the oil if a seal is defective. er supply (have this done by an electrician), clean it
and place it on a solid base in a horizontal position.
The general procedure for changing oil is as follows: Secure it from falling over and/or slipping.
Switch off the machine, let it cool down, disconnect it
from the power supply (have this done by an electri- If not otherwise stated, the torque values of the
cian), lock out tag out the control panel, clean it and below tables should be used. Values stated are for clean,
place it vertically on a solid base. Warm or hot oil may lubricated screws. Fixing torque [ft lbs] for screws A2/A4
be pressurized. The leaking oil may cause burns. For (Coefficient of friction = 0.2)
that reason, let the machine cool down to ambient
temperature before you touch it. A2/A4, A2/A4,
Hardeness class 70 Hardeness class 80
6.4. Sealing chamber
DIN912/DIN933 DIN912/DIN933
As there are several versions and designs of these mo- M6 5 ft lbs 9 ft lbs
tors, the exact location of the screw plugs varies depend-
ing on the pump unit used. M8 12.5 ft lbs 21 ft lbs
M10 24 ft lbs 43 ft lbs
• Slowly and carefully remove the filling plug from the
M12 42 ft lbs 73.5 ft lbs
seal chamber.
M16 103 ft lbs 180.5 ft lbs
Caution: The oil may be pressurized! M20 201.5 ft lbs 364.5 ft lbs
• Remove the drain plug. Drain the oil and collect it in
a suitable reservoir. Clean the drain plug, fit with a
new sealing ring and screw it in again. For complete 7.2. Changing the impeller and pump unit
drainage, the machine must be slightly tipped on to
its side. Changing the impeller and the pump unit.
• • Loosen and remove the screws holding the volute to
the oil chamber.
Make sure that the pump is on its side and secure! • Secure and remove the volute from the oil chamber
• Fill lubricant by means of the opening in the filling with suitable equipment, e.g. hoisting gear. Place on
plug. Comply with the specified lubricants and filling a secure base.
quantities. • Fasten the impeller with suitable equipment, loosen
• Clean the filling plug, fit with a new sealing ring and and remove the impeller fastening (cylindrical screw
screw it in again. with socket hex).

Pay attention to the locking screw!


• Remove the impeller from the shaft using a suitable
extractor.
• Clean the shaft
• Attach a new impeller to the shaft.

Make sure that the sliding surfaces do not become


damaged!
• Screw a new impeller bolt and clamping disk back
onto the shaft. Fasten the impeller and tighten the
impeller bolt. See table below for toque values.
• Place the motor assembly with impeller back onto
the volute and fasten it with screws.
• It must be possible to turn the impeller by hand.

English | 19
Impeller Bolt Size Torque Note the following information concerning storage:

10mm 35 Nm / 26 ft lb Beware of hot parts!


12mm 61 Nm / 45 ft lb When removing the machine, be careful of the tem-
perature of the housing components. These can heat
16mm 146 Nm / 108 ft lb
up to well above 104°F. Let the machine cool down to
20mm 285 Nm / 210 ft lb ambient temperature before you touch it.

Changing wear ring • Clean the machine.


The stationary and mobile wear ring determine the gap • Store it in a clean, dry place, protect the machine
between the impeller (mobile wear ring) and the intake against frost.
port (stationary wear ring). If this gap is too big, the per- • Place it down vertically onto a firm foundation and
formance of the machine decreases, and/or it can lead to secure it against falling.
entanglements. • Support the cable at the cable entry assembly to help
avoid a permanent deformation.
If the stationary ring shows signs of wear, it should be • Protect the ends of the electric power cable from
replaced. This minimizes wear on the intake port and and moisture.
impeller, consequently reducing expense for spare parts. • Protect the machine from direct sunshine as a pre-
ventive measure against brittleness in elastomer
Only OEM Parts may be used for replacement! parts and the impeller and casing coating.
• When storing the machine in a shop please remem-
Inspecting and replacing these parts is performed by the ber: Radiation and gases which occur during electric
manufacturer during the general overhaul or by specially welding destroy the elastomers of the seals.
trained personnel. • During lengthy periods of storage, regularly (for ex-
ample every six months) turn the impeller or propeller
7.3. Spare Parts by hand. This prevents indentations in the bearings
and stops the rotor from rusting up.
In order to obtain spare parts identify the required parts,
and contact authorized HOMA customer service with your
8.3. Restarting after an extended period of storage
order. Authentic HOMA parts shall be used to maintain
warranty. Before restarting the pump, it should be completely re-
commissioned. Clean it of dust and oil deposits, then car-
Explosion Proof pumps must be identified as such, ry out the necessary maintenance actions (see “Mainte-
and the pump serial number must be referenced for nance”). Check that the mechanical shaft seal is in good
proper parts identification. order and working properly. Once this work has been
completed, the machine can be installed (see “Installa-
tion”) and connected to the electricity supply by a special-
ist. See “Start-up” for instructions on restarting.

Only restart the machine if it is in perfect condition and


ready for operation.

8. Shutdown

8.1. Temporary shutdown


9. Troubleshooting
For this type of shutdown, the machine remains installed
and is not cut off from the electricity supply. For tempo- In order to prevent damage or serious injury while rec-
rary shutdown, the machine must remain completely sub- tifying machine faults, the following points must be
merged so that it is protected from frost and ice. Make observed:
sure the operating room and the pumped fluid cannot be
covered by ice. This ensures that the machine is always • Only attempt to rectify a fault if you have qualified
ready for operation. Carry out a monthly start-up and run personnel. This means each job must be carried out
the pump in operating conditions for 5 minutes. by trained specialist personnel, for example electrical
work must be performed by a trained electrician.
Caution! • Always secure the machine against an accidental
Only test the pump under the proper conditions of op- restart by disconnecting it from the electric system.
eration and use. Never run the machine dry. This can Take appropriate safety precautions.
result in irreparable damage! • Always have a second person make sure the ma-
chine is switched off in an emergency.
8.2. Final shutdown / storage • Secure moving parts to prevent injury.
• Independent work on the machine is at one‘s own
Switch off the system, disconnect the machine from the
risk and releases the manufacturer from any warranty
electricity supply and dismantle and store it.
obligation.

20 | English
The machine will not start
Cause Remedy
Electricity supply interrupted – short circuit or earth Have the motor and wires checked by a specialist and replaced if
connection in the cable or motor windings necessary
Fuses, the motor protection switch and/or monitoring Have a specialist inspect the connection and correct them as necessary
devices are triggered Have the motor protection switch adjusted according to the technical
specifications, and reset monitoring equipment.
Check that the impeller/propeller runs smoothly.
Clean it or free it as necessary
The moisture sensors (option) has interrupted the power circuit (operator- See fault: Mechanical shaft seal leaks, seal chamber monitor reports
related) fault and switches the machine off

Machine runs but does not pump


Cause Remedy
No pumped fluid Open the container intake or valves
Intake blocked Clean the intake, valve, suction port or intake strainer
Impeller/propeller blocked or obstructed Switch off the machine, secure it against being switched on again and
free the impeller/ propeller
Defective hose or piping Replace defective parts
Intermittent operation Check the control panel

The motor starts, but the motor protection switch triggers shortly after start-up
Cause Remedy
The thermal trigger on the motor protection switch is incorrectly set Have a specialist compare the setting of the trigger with the technical
specifications and adjust it if necessary

Increased power consumption due to major voltage drop Have an electrician check the voltage on each phase and rewire if
necessary
Excessive voltage differences on the three phases Have a specialist inspect the connection and the switching system and
correct it as necessary
Incorrect direction of rotation Swap the 2 phases from the mains supply
Impeller/propeller impeded by adhesive material, blockages and/or solid Switch off the machine, secure it against being switched on again and
matter, increased current consumption free the impeller/ propeller or clean the suction port
The pumped fluid is too dense Contact the manufacturer

The machine runs, but not at the stated operating levels


Cause Remedy
Intake blocked Clean the intake, valve, suction port or intake strainer
Valve in the discharge line closed Fully open the valve
Impeller/propeller blocked or obstructed Switch off the machine, secure it against being switched on again and
free the impeller/ propeller
Incorrect direction of rotation Replace 2 phases on the mains supply
Air in the system Check the pipes, pressure shroud and/or pump unit, and bleed if
necessary
Machine pumping against excessive pressure Check the valve in the discharge line, if necessary open it completely
Signs of wear Replace worn parts
Defective hose or piping Replace defective parts
Inadmissible levels of gas in the pumped liquid Contact the factory
Two-phase operation Have a specialist inspect the connection and correct it as necessary

English | 21
The machine does not run smoothly and is noisy
Cause Remedy
Machine is running in an impermissible operation range Check the operational data of the machine and correct if necessary and/
or adjust the operating conditions
The suction port, strainer and/or impeller/propeller is blocked Clean the suction port, strainer and/or impeller/ Propeller
The impeller is blocked Switch off the machine, secure it against being switched on again and
free the impeller
Inadmissible levels of gas in the pumped liquid Contact the factory
Two-phase operation Have a specialist inspect the connection and correct it as necessary
Incorrect direction of rotation Incorrect direction of rotation
Signs of wear Replace worn parts
Defective motor bearing Contact the factory
The machine is installed with mechanical strain Check the installation, use rubber spacers if necessary

Mechanical shaft seal leaks, sealing chamber monitor reports fault and switches the machine off
Cause Remedy
Increased leakage when running in new mechanical shaft seals Change the oil
Defective sealing chamber cables Replace the moisture sensors
Mechanical shaft seal is defective Replace the mechanical shaft seal after contacting the factory

Further steps for troubleshooting


If the items listed here do not help you rectify the fault,
contact our customer service. They can help you as fol-
lows:

• Telephone or written help from customer service


• On-site support from customer service
• Checking and repairing the machine at the factory

Note that you may be charged for some services provided


by our customer support. Customer service will provide
you with details on this.

22 | English
10. Connection of pumps and mixers

Danger from electric current!


Incorrect working with electric current brings danger to life! All pumps with bare cable ends must be connected by a skilled
electrician.

10.1 Power cables


Pumps in Star 3-phase version

Cable identification Motor Terminal in control cabinet


U1 U1
V1 V1
W1 W1
U2 U2
V2 V2
W2 W2

Pumps in Direct start version

Cable identification Motor Terminal in control cabinet


U U1
V V1
W W1

10.2 Control cables


Depending on the design of the pump/agitator, it may be that no separate control cable is used. In this case monitoring
devices are run from the power cable.

Cable identification Motor Monitoring system


Monitoring in winding
T1 / T2 Temperature limiter (2 switches in series)
T1 / T4 Temperature controller (2 switches in series)
T1 / T2 / T3 Temperature limiter and controller
K1 / K2 PTC – Thermistor (3 thermistors in series)
PT1 / PT2
PT3 / PT4
3 x PT100 individually installed
PT6 / PT6
Bearings monitoring
P1 / P2 PT100 upper bearing
P3 / P4 PT100 lower bearing
Seal monitoring
S1 / S2 Seal monitoring in oil chamber
S3 / S4 Seal monitoring in connection compartment
S5 / S6 Seal monitoring in Motor compartment with 2 Electrodes
S7 / S8 Seal monitoring in Motor compartment with float switch
S9 / S10 Seal monitoring in Gearbox (Agitator)
S11 / S12 Seal monitoring in Leakage compartment (internal cooling)
Heating
H1 / H2 Heating system

English | 23
Version 04/2018

HOMA Pump Technology Inc


390 Birmingham Blvd Ansonia, CT 06401
Phone: 203-736-8890 Fax: 203-736-8899
e-Mail: info@homapump.com Internet: www.homapump.com
START-UP REPORT
This report is designed to ensure the customer that customer service and a quality product are the number one
priority with HOMA Pump Technology. Please answer the following questions completely and as accurately as
possible. Mail this form to:

HOMA PUMP TECHNOLOGY


390 BIRMINGHAM BOULEVARD
ANSONIA, CT 06401
ATTN: SERVICE MANAGER
Receipt of completed report will initiate operational warranty.
Reports that are not returned can delay or void warranty.

1.) Pump User's Name: _____________________________________________________________


Site Location: __________________________________________________________________
Site Contact: ___________________________________________________________________
Distributor: _______________________________ Phone Number: ________________________
Contractor: _______________________________ Phone Number: ________________________
Engineer: ________________________________ Phone Number: ________________________
Owner: __________________________________ Phone Number: ________________________

2.) HOMA Pumps Model __________________________________ Serial No._____________________


Voltage____________ Phase_________________ Hertz________________ Horsepower_________
Method Used to Check Rotation (viewed from bottom) __________________________________
Does Impeller Turn Freely By Hand: YES________ NO _________

3.) Condition of Equipment: EXCELLENT____________ GOOD____________ AVERAGE____________


Condition of Cable Jacket: EXCELLENT____________ GOOD ___________ AVERAGE____________
Resistance of Cable and Pump Motor (measured at pump control)
1 Phase: U1 – U2 _________ Ohms; U1 - Z2 ________ Ohms; U2 – Z2 _________Ohms; T1 – T2 ________Ohms
3 Phase: U - V____________ Ohms; V - W __________Ohms; U -W ___________Ohms, T1 – T2 ________Ohms
Single Phase Capacitor Sizes Installed: _________________ Start Capacitor; __________________ Run Capacitor
Resistance of Ground Circuit Between Control Panel and Outside of Pump __________ Ohms
MEG Ohm Check of Insulation:
U to Ground _______________ V to Ground _______________ W to Ground____________
Hour Meter installed in panel? ______
Chains/Cables for retrieval? ________
Date Code: __________

4.) Condition of Equipment at Start-Up: Dry __________ Wet _____________ Muddy_________


Was Equipment Stored: _______________ Length of Storage ________________________
Describe Station Layout ___________________________________________________________
Wet Well Diameter ________ ft
Volume per Inch __________ Gal

5.) Liquid Level Controls: Model _____________________________ Type ______________________


Is Control Installed Away From Turbulence? ___________________________________________
Operation Check: (IF FLOAT SWITCHES SUPPLIED).
Tip lowest float (stop float), all pumps should remain off.
Tip second float (and stop float), one pump comes on.
Tip third float (and stop float), both pumps on (alarm on simplex).
Tip fourth float (and stop float), high level alarm on (omit on simplex).
Control Voltage: _________
VFD Manufacturer: _____________
Soft Start Manufacturer: ____________
Running Hz: __________
Phase Monitor Number: __________

Pump Technology,Inc  390 Birmingham Blvd. Ansonia, CT 06401 (203) 736-8890 Fax:(203) 736-8899
6.) Electrical Readings:
Single Phase:
Voltage Supply at Panel Line Connection, Pump Off, U1-U2 _______ U1-Ground ________ U2-Ground ________
Voltage Supply at Panel Line Connection, Pump On, U1-U2 _______ U1-Ground ________ U2-Ground ________
Amperage: Load Connection, Pump On, U1 ___________ U2 ___________ Z2 ___________
Voltage across Run Capacitor Terminals ________ volts (note: value will be over 300V)
Resistance across Thermal Switch leads T1-T2 _______ ohms (switches are NC 0.4 ohm is normal)
No Load Voltage: AB_______ AC_______ BC_______ AN_______BN_______ CN_______
Full Load Amps: __________
Service Factor: ___________

Three Phase:
Voltage Supply at Panel Line Connection, Pump Off, U-V _________ V-W _______ U-W ______
Voltage Supply at Panel Line Connection, Pump On, U-V _________ V-W _______ U-W ______
Amperage Load Connection, Pump On, U_____________ V_____________ W______________
Resistance Across Thermal Switch leads T1-T2 _______ ohms (switches are NC 0.4 ohm is normal)
Overloads: U________ V________ W________
No Load Voltage: AB_______ AC_______ BC_______ AN_______BN_______ CN_______
Full Load Amps: __________
Service Factor: ___________

7.) Final Check:


Are Thermal Switches properly wired? _______ What Overtemperature Relay is being used? ____________
Is Pump Seated On Discharge Properly? ______________ Check For Leaks? __________________
Does Check Valves Operate Properly? _________________________________________________
Flow: Does Station Appear To Operate At Proper Rate ____________________________________
Vibration Level: Measured _____________________ Observed_____________________________
Design Point: Flow ___________ Head ___________
Draw Down _________ inch Flow:_________ gpm Discharge:_________ psi Discharge:_________ ft
Static:_________ ft Friction loss:_________ ft Total Head:_________ft

COMMENTS: _____________________________________________________________________

8.) Equipment Difficulties During Start-Up: _________________________________________________


_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________

9.) I Certify this Report to be accurate.


Authorized Homa Service Representative:

___________________________________________________________ Phone #____________________


(Signature)

DATE_______________________

Pump Station Owner/ Operator

___________________________________________________________ Phone # ____________________


(Signature)
DATE _______________________

Pump Technology,Inc  390 Birmingham Blvd. Ansonia, CT 06401 (203) 736-8890 Fax:(203) 736-8899

You might also like