Professional Documents
Culture Documents
Midterm in Estimate (Billy)
Midterm in Estimate (Billy)
MUNICIPALITY OF CAPUL
Province of Northern Samar
DEPARTMENT OF EDUCATION
Brgy,Jubang, Capul, Northern Samar
Program of Work
Name/Location of Project:
Appropriation: 2,805,711.35
PROPOSED TWO- STOREY RESIDENTIAL
Brgy. Jubang, Capul,Northern Samar Source of Fund:
Corporation
Project Duration:
Project Category: 73 weeks
Residential Desirable Starting Date:
Implementing Procedure:
CONSTRUCTION OF 2-STOREY RESIDENTIAL BUILDING
By Contractor
Contingencies/Reserves
1. Physical Contingencies
2. Price Escalation
3. Budgetary
TOTAL 100.00% 4,108,131.10
BOQ SUMMARY SHEET
ITEM Amount in Figures
Desription
NO. (Php)
1. SITE DEVELOPMENT WORKS
Amount in Words: Two thousand, and twenty-five 2,000.25
hundredths
2. EARTHWORKS one thousand, nine hundred
Amount in Words: eighty-four and thirty-eight 1,984.38
hundredths
3. CONCRETE WORKS one hundred fifty-eight thousand,
Amount in Words: five hundred fifty-nine and five 158,559.50
tenths
4. STEEL WORKS two hundred thirty-nine thousand,
Amount in Words: three hundred seventy-two and 239,372.78
seventy-eight hundredths
5. MASONRY WORKS three hundred thirty-two
Amount in Words: thousand, seven hundred seventy 332,770.16
and sixteen hundredths
6. FORMWORKS & SCAFFOLDINGS four hundred forty-nine thousand,
Amount in Words: five hundred ninety-nine and five 449,599.05
hundredths
7. STAIRCASE
eight thousand, forty-eight and
Amount in Words: 8,048.63
sixty-three hundredths
GRAND Fourteen Million Three Hundred Thirty Four Thousand Seven Hundred
2,805,711.35
TOTAL two million, eight hundred five thousand, seven hundred eleven and thirty-five hundredths
(In Words) (In Figures)
1. SITE DEVELOPMENT WORKS Qty Unit Price per Item
- Clearing and Grubing 63 sq.m 20
Total Material Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
2. EARTHWORKS Qty Unit Price per Item
- Backfilling 5 cu.m. 250
Total Material Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
3. CONCRETE WORKS Qty Unit Price per Item
- Portland Cement 299 bags 270
- Washed Sand 23 cu.m. 550
- Washed Gravel 5 cu.m. 1,300
Total Material Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
4. STEEL WORKS Price per Item
- 16mmØ x 6 m RSB 68 pcs. 302
- 12mmØ x 6 m RSB 150 pcs. 175
- 10mmØ x 6 m RSB 430 pcs. 125
20mmØ x 6 m RSB 17 pcs. 350
25mmØ x 6 m RSB 30 pcs. 530
32mmØ x 6 m RSB 16 pcs. 1,250
- #16 Tie Wire 105 kgs. 80
Total Material Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
5. MASONRY WORKS Price per Item
- 6" CHB 2229 pcs. 17
- 4" CHB 1024 pcs. 14
- Portland Cement 427 bags 270
- Washed Sand 23 cu.m. 550
- 12mmØ x 6 m RSB 123 pcs. 175
- 10mmØ x 6 m RSB 57 pcs. 125
- #16 Tie Wire 10 kgs. 80
Total Material Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
6. FORMWORKS & SCAFFOLDINGS Price per Item
- 1/4" thk. Ordinary Plywood 108 shts. 360
- 2" x 3" x 10' Form Lumber 11696 bd.ft 18
- 2" x 2" x 10' Form Lumber 1808 bd.ft 18
- Nails 1 1/2 21 kgs. 60
Total Material Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
7. ROOFING WORKS Price per Item
- CEILING JOIST 36 pcs. 200
- PLYWOODS 124 pcs. 360
- METAL PURLINS 22 pcs. 300
- GAGE 26 RIB-TYPE 7 pcs. 888
- RIDGE ROLL 1 pcs. 350
- FLASHING 3 pcs. 2240
- GUTTER 7 pcs. 200
- STRAP 6096 pcs. 120
- RIVETS 133 pcs. 24
Total Material Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
8. CEILING WORKS Price per Item
3.50mm Hardililte Board 29 pcs. 738
2x2x10 183 pcs. 400
Nails 4 kgs. 60
1x2 Moulding 51 pcs. 380
1x3 Moulding 50 pcs. 350
Senepa Board 494 pcs. 330
Total Material Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
9. STAIRCASE Price per Item
- 2x12 Yakal Stair Tread 4 pcs. 180
- 2x12 Stringer 2 pcs. 145
6m Baluster for Handrail 1 pcs. 400
- Wood Baluster 3 pcs. 1200
- Nails 1 1/2 1 kg. 60
Total Material Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
10. DOORS AND WINDOWS Price per Item
- W-1 (SEE DETAIL) 1 pcs. 1,000
- W-2 (SEE DETAIL) 1 pcs. 660
- W-3 (SEE DETAIL) 1 pcs. 990
DOORS
- D-1 (SEE DETAIL) 1 pcs. 600
- D-2 (SEE DETAIL) 3 pcs. 580
- D-3 (SEE DETAIL) 4 pcs. 600
D-4 (SEE DETAIL) 1 pcs. 600
D-5 (SEE DETAIL) 2 pcs. 600
D-6 (SEE DETAIL) 1 pcs. 600
2"x 6" (set) 1 pcs. 250
2"x 4"(set) 8 pcs. 225
Aluminum Frame 3 pcs. 400
Total Material Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
11. PAINTING WORKS Price per Item
- PLEXIBOND 34 gal. 730
- Latex 2 gal. 440
- Semi-Gloss Latex 11 gal. 530
- Acrylic 1 gal. 670
- Flat Latex 4 gal. 600
- Enamel 3 gal. 600
Total Direct Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
12. TILE WORKS Price per Item
- 300X300mm Glazed floor Tile 351 pcs. 50
300x300mm Non-skid 254 pcs. 95
300x300mm Wall Tiles 582 pcs. 60
200x200mm Non-skid 165 pcs. 85
GROUT 19 kg 493(20kg)
Cement Mortar 53 bags 210
Sand 2 cu.m. 550
Total Direct Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
13. LANDSCAPE Price per Item
- Landscape 63 sq.m 100
Total Direct Cost
- Labor Cost
Direct Cost
- O.C.M.
- Contractor's Profit (8%)
- EVAT
Total Cost for this Item
14. Paintaing Works (excluded)
GRAND TOTAL
Total Price
1,260.00
1,260.00 2,000,012.00
315.00
1,575.00
189.00
126.00
110.25
2,000.25
Total Price
1,250.00
1,250.00
312.50
1,562.50
187.50
125.00
109.38
1,984.38
Total Price
80,730.00
12,650.00
6,500.00
99,880.00
24,970.00
124,850.00
14,982.00
9,988.00
8,739.50
158,559.50
Total Price
20,536.00
26,250.00
53,750.00
5,950.00
15,900.00
20,000.00
8,400.00
150,786.00
37,696.50
188,482.50
22,617.90
15,078.60
13,193.78
239,372.78
Total Price
37,893.00
14,336.00
115,290.00
12,650.00
21,525.00
7,125.00
800.00
209,619.00
52,404.75
262,023.75
31,442.85
20,961.90
18,341.66
332,770.16
Total Price
38,880.00
210,528.00
32,544.00
1,260.00
283,212.00
70,803.00
354,015.00
42,481.80
28,321.20
24,781.05
449,599.05
Total Price
7190
44640
6600
6216
350
6720
1400
731520
3192
807,828.00
201,957.00
1,009,785.00
121,174.20
80,782.80
70,684.95
1,282,426.95
Total Price
21,402.00
73,200.00
240.00
19,380.00
17,500.00
163,020.00
294,742.00
73,685.50
368,427.50
44,211.30
29,474.20
25,789.93
99,475.43
Total Price
720.00
290.00
400
3,600.00
60.00
5,070.00
1,267.50
6,337.50
760.50
507.00
443.63
8,048.63
Total Price
1,000.00
660.00
990.00
600.00
1,740.00
2,400.00
600
1200
600
250
1800
1200
13,040.00
3,260.00
16,300.00
1,564.80
1,043.20
912.80
19,820.80
Total Price
24,820.00
880.00
5,830.00
670.00
2,400.00
1,800.00
36,400.00
9,100.00
45,500.00
5,460.00
3,640.00
3,185.00
57,785.00
Total Price
17,550.00
24130
34920
14025
493
11130
825
90,625.00
22,656.25
113,281.25
13,593.75
9,062.50
7,929.69
143,867.19
Total Price
6,300.00
6,300.00
1,575.00
7,875.00
945.00
630.00
551.25
10,001.25
2,805,711.35
Reinforcing Bars
FOOTINGS
F-1 Longitudinal 0.95 4 1
Traverse 0.95 4 1
F-2 Longitudinal 1.00 5 3
Traverse 1.00 5 3
F-3 Longitudinal 1.08 5 3
Traverse 1.08 5 3
F-4 Longitudinal 1.20 6 2
Traverse 1.20 6 2
F-5 Longitudinal 1.30 8 2
Traverse 1.30 8 2
Sub-Total
COLUMNS
C-1 Vert. Bars 3.00 4 4
0.25 x 0.25 Ties 0.83 48 4
C-2 Vert. Bars 3.00 4 6
0.30 x 0.30 Ties 1.13 48 6
C-3 Vert. Bars 3.00 4 2
0.30 x 0.30 Ties 1.13 96 2
C-4 Vert. Bars 3.00 8 5
0.40 x 0.40 Ties 1.53 96 5
C-5 Vert. Bars 3.00 4 4
0.30 x 0.30 Ties 1.13 96 4
C-6 Vert. Bars 3.00 14 1
0.40 x 0.40 Ties 1.53 96 1
Sub-Total
ROOF BEAMS
Along Grid Line 1
Continuous Bar 5.60 4 1
Stirrups (bet. A-B) 1.10 38 1
Along Grid Line 2
Continuous Bar 5.60 4 1
Stirrups (bet. A-B) 1.10 38 1
Along Grid Line 3
Continuous Bar 5.60 4 1
Stirrups (bet. A-B) 1.10 38 1
Sub-Total
BEAMS
B1
Continuous Bar 8.40 8 1
Stirrups 0.88 80 1
B2
Continuous Bar 4.28 4 1
Stirrups 0.88 46 1
B3
Continuous Bar 7.43 8 1
Stirrups 1.18 58 1
B4
Continuous Bar 1.86 4 1
Stirrups 0.88 20 1
B5
Continuous Bar 5.61 4 1
Stirrups 1.18 58 1
B6
Continuous Bar 3.67 4 1
Stirrups 1.18 35 1
B7
Continuous Bar 5.61 4 1
Stirrups 0.88 60 1
B8
Continuous Bar 1.22 4 1
Stirrups 1.18 15 1
B9
Continuous Bar 3.08 4 1
Stirrups 1.18 30 1
B10
Continuous Bar 8.02 4 1
Stirrups 0.88 76 1
B11
Continuous Bar 3.63 4 1
Stirrups 2.08 38.709 1
TOTAL
MARKS
S-150 Longitudinal Bars 0.71 5 1
Transverse Bars 4.73 32 1
Longitudinal Bars 1.96 14 1
Transverse Bars 2.44 17 1
S-120 Longitudinal Bars 1.93 17 1
Transverse Bars 3.20 27 1
Longitudinal Bars 1.05 9 1
Transverse Bars 2.02 17 1
Longitudinal Bars 1.12 10 1
Transverse Bars 2.30 20 1
Longitudinal Bars 1.12 10 1
Transverse Bars 1.92 16 1
S-130 Longitudinal Bars 3.38 26 1
Transverse Bars 0.60 5 1
Longitudinal Bars 1.96 16 1
Transverse Bars 1.92 15 1
Longitudinal Bars 2.47 19 1
Transverse Bars 3.23 25 1
Sub-Total
SUMMARY:(Reinforcing Bars)
Particulars 32mm Ø 25 mm Ø 20 mm Ø 16 mm Ø
(6m/pc) (6m/pc) (6m/pc) (6m/pc)
Footings 24.00
Columns 16 30 17 5.00
Beams 39.00
Slab
TOTAL 16 30 17 68.00
(D)
16 mm Ø
(6m/pc)
(A*B*C)/6
0.63
0.63
2.50
2.50
2.69
2.69
2.40
2.40
3.47
3.47
23.38
12.60
4.20 4.20
21.00
8.40 8.40
7.35
(D)
16 mm Ø
(6m/pc)
((A*B*C)/6)+10%
4.11
4.11
4.11
12.32
(D)
16 mm Ø
(6m/pc)
((A*B*C)/6)+10%
4.55
4.55
9.09
6.16
11.73 4.53
3.14
6.75 2.60
5.45
11.41 3.28
1.36
2.93 1.13
4.11
11.41 3.28
2.69
6.88 1.98
4.11
8.80 3.40
0.89
2.95 0.85
2.26
5.90 1.70
5.88
11.15 4.30
2.66
13.42 2.19
38.71 93.33 29.25
(D) (E)
12mm Ø #16
(6m/pc) Tie Wire
((A*B*C)/6)+10% (kls)
0.65 0.91
27.73
5.03 1.35
7.60
6.02 2.60
15.83
1.73 0.87
6.28
2.05 1.13
8.43
2.05 0.91
5.62
16.09 0.74
0.55
5.75 1.36
5.27
8.59 2.69
14.80
140.08 12.54
12mm Ø 10mm Ø #16
(6m/pc) (6m/pc) Tie Wire
(kls)
8.00
9.00 336.00 54.00
94.00 30.00
141.00 13.00
150.00 430.00 105.00
MASONRY
GROUND FLOOR
Area 6" CHB 4" CHB
Ground Floor
(sq.m.) (pcs.) (pcs.)
Along Row B3 13.31 173.043
Along Row B4 13.26 124
Along Row B5 5.40 70
Along Row B6 3.19 41.418
Along Row B7 5.15 66.885
Along Row B8 3.19 41
TOTAL 39.80 296 248
e area by 13 to get the quantity of CHB. Round off to the nearest greater whole number.
SUMMARY:
PARTICULAR QTY UNITS QTY UNITS
6" CHB 2229 pcs
4" CHB 1024 pcs
Cement 427.00 bags
Sand 23.00 cu.m.
12mm Ø (6m/pc) 123.00 pcs. 655.59 kgs.
10mm Ø (6m/pc) 57.00 pcs. 210.90 kgs.
#16 Tie Wire 10.00 kgs.
GROUND FLOOR GROVE CEMENT FI
Area 6" CHB 4" CHB
Ground Floor
(sq.m.) (pcs.) (pcs.)
Along Grid Line 1A 33.54 335.4
Along Grid Line 1B 6.29 82
Along Grid Line 1C 6.15 80
Along Grid Line 1D 33.32 433.134
TOTAL 77.41 887 170
SECOND FLOOR
Area 6" CHB 4" CHB
Second Floor
(sq.m.) (pcs.) (pcs.)
Along Row C1 7.08 92.092
Along Row C2 6.64 86
Along Row C3 6.72 87
Along Row C4 2.74 35.672
Btw Along Row C4-C5 5.20 67.5896
Along Row C5 9.03 117.39
Along Row C6 4.97 65
Along Row C7 3.50 46
TOTAL 45.90 213 415
SECOND FLOOR
Area 6" CHB 4" CHB
Second Floor
(sq.m.) (pcs.) (pcs.)
Along Grid Line 2A 28.62 372.008
Along Grid Line 2B 8.66 113
Along Grid Line 2C 3.64 47
Along Grid Line 2D 3.70 26.208 21.84
Along Grid Line 2E 30.38 394.94
TOTAL 74.99 833 191
GROVE CEMENT FINISH
(H)
Gravel
(cu.m.)
D*GF
GF = 0.84
0.32
8.62
8.62
15.32
8.62
15.32
17.55
(H)
Gravel
(cu.m.)
E*GF
GF = 0.84
0.33
0.15
0.18
0.25
0.31
0.15
0.10
0.15
0.15
0.16
0.15
0.98
0.06
0.23
0.25
0.29
0.10
0.39
0.25
0.29
0.25
0.29
0.10
0.30
0.43
6.26
(H)
Gravel
(cu.m.)
E*GF
GF = 0.84
0.39
0.42
0.81
0.32
0.38
0.30
1.19
0.60
0.21
4.61
Sand Gravel
(cu.m.) (cu.m.)
9.21 36.855
3.44 6.886
9.69 36.855
22.34 4.8405
PAINT
FLOOR TILES
TOTAL AREA
sq.m.
DINING AREA 27.3375
SERVICE YARD 11.0418
BALCONY 11.7878
5 4.1656
CR 6.5855
TOTAL (pcs.) 60.9182
WALL TILES
TOTAL AREA
sq.m.
CR 23.28
TOTAL (pcs.)
300mm x 300mm GLAZED FIL-HISPANO FLOOR 300mm x 300mm FIL-HISPANO, NON-SKID 200mm x 200mm NON-SKID,NON-
TILE(White) FLOOR TILE GLAZED BATHROM, FIL-HISPANO
FLOOR TILE
304
123
131
47
165
351 254 165
SUMMARY
PIECES
PARTICULARS
PLYWOOD 108
2'' x 2'' 1808
2'' x 3'' 1270
Nails 1 1/2'' 21
AFFOLDING
HORIZONTAL SUPPORT DIAGONAL BRACES
(2"x2" lumber) (2"x2" lumber)
1512 842.4
295.16
1808 843
STAIRS
length rise tread width No. of Steps 2x12 Yakal Stair Thread (pcs
1.1 0.25 0.5 0.25 13 4
Wood Baluster Wood Balsuter for Handra
2x12 Yakal Stair Thread (pcs.) 2 x 12 Stringers pcs. Nails(kg) (6m)
4 2 3 1 1
Wood Balsuter for Handrail
(6m)
1
A. DOOR FRAMES
MARK SETS LENGTH* 2" x 6" 2" x 4"
ft Bd. Ft. Bd. Ft.
D1 1 19.520997 19.520997
D2 3 15.91207 31.82414
D3 4 11.64698 69.88188
D4 1 19.78346 29.67519
D5* 2 2.15 x 1.75m
D6* 1 2.15 x 2.6m
Total 151 151
*ALUMINUM FRAME
B .WINDOW FRAMES
MARK SETS LENGTH* 2" x 6" 2" x 4"
ft Bd. Ft. Bd. Ft.
W1* 1 1.7 x 1.75m
W2* 1 1.2 x 0.9m
W3* 1 1.2 x 0.9m
Total 0
*ALUMINUM FRAME
c. PLASTERING 25 mm THK
Face Area Cement Sand
m2 A m3
WALL 2 32 28 2
DETAILS: UNIT(m)
D1 2.1 x 1.0 2"x 6"
D2 1.7 x 0.7 2"x 4"
D3 1.0 x 1.0 2"x 4"
D4 2.25 x 0.88 2"x 4"
D5 2.1 x 1.6 Aluminum Frame
D6 2.05 x2.6 Aluminum Frame
Quantity of cement and sand for plaster per square meter area
Mixture Cement in bags Thickness of Plaster
class 8 mm 12mm 16mm 20mm
A 0.144 0.216 0.288 0.36
B 0.096 0.144 0.192 0.24
C 0.072 0.108 0.144 0.18
D 0.06 0.09 0.12 0.15
Sand 0.008 0.012 0.016 0.02
e meter area
ess of Plaster
25mm
0.45
0.3
0.225
0.188
0.025
ROOFING AND CEILING MATERIALS
PARTICULAR
CEILING JOIST
TOTAL
SUMMARY
PARTICULAR QUANTITY
CEILING JOIST 35.95 pcs.
PLYWOODS 124 pcs.
METAL PURLINS 21.17 pcs.
GAGE 26 RIB-TYPE 7 pcs.
RIDGE ROLL 1 pcs.
FLASHING 2.12 pcs.
GUTTER 7 pcs.
STRAP 6096 pcs.
RIVETS 133 pcs.
NO. OF JOIST NO. OF JOIST AREA OF BD. FT.
TRANSVERSAL LONGITUDINAL CEILING JOIST PER SQ. M.
12.95 23 42.88 275.14
12.95 23 42.88 275.14
Say:
36
22
3
SAY NO. OF PLYWOODS NO. OF METAL PURLINS
1.2 x 2.4 2 x 6 x 1.2
276 123.48 21.17
276 124 21.17
NO. OF GAGE 26 RIB-TYPE NO. OF GAGE 26 RIB-TYPE RIDGE ROLL
2x6x1.2(LEFT) 2x6x1.2(RIGHT) 5m
4 3 1
4 3 1
FLASHING GUTTER NO. OF NO. OF
STRAP RIVETS/SHEET
2.12 7 6096 133
2.12 7 6096 133
Reflected Ceiling Plans Total Area of Ceiling Unit
2"x2" lumber 41.74 sq.m.
SUMMARY:
PARTICULAR QTY UNITS
3.50mm Hardililte Board 29 pcs
2x2x10 183 pcs
Nails 4.00 Kgs
1x2 Moulding 51 pcs
1x3 Moulding 50 pcs
Senepa Board 494 pcs
CEILING WORKS
316
95
3.50mm Hardilite Board
15
BD. Ft Lumber
Nails
316
bd. Ft.
pieces
pieces
Quantity (kg)
2
Quantity
23.3133333333333
22.8066666666667
229.4032
SCHEDULE OF ACTIVITIES
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
SITE
DEVELOPMEN
1 T
Claring and
1.1 Grubing
SITE
2 PLANNING
2.1 Grading
2.2 Excavation
2.3 Backfilling
2.4 Final Grading
3 CIVIL WORKS
3.1 Footing
Ground Floor
3.2 Column
Week 8
Week 9
Week 10
Week 11
Week 12
Week 13
Week 14
Week 15
Week 16
Week 17
Week 18
Week 19
Week 20
Week 21
Week 22
Week 23
Week 24
Week 25
Week 26
Week 27
Week 28
Week 29
Total Duration: 75 weeks
Week 30
Week 31
Week 32
Week 33
Week 34
Week 35
Week 36
Week 37
Week 38
Week 39
Week 40
Week 41
Week 42
Week 43
Week 44
Week 45
Week 46
Week 47
Week 48
Week 49
Week 50
Week 51
Week 52
Week 53
Week 54
Week 55
Week 56
Week 57
Week 58
Week 59
Week 60
Week 61
Week 62
Week 63
Week 64
Week 65
Week 66
Week 67
Week 68
Week 69
Week 70
Week 71
Week 72
Week 73