Professional Documents
Culture Documents
14. COTTAGES
Amount in Words: One Hundred Four Thousand Six Hundred Sixteen 104,616.25
Pesos and Twenty Five Centavos
15. PAINTING WORKS
128,422.40
Amount in Words: One Hundred Twenty Eight Thousand Four Hundred 128,422.40
Twenty Two Pesos and Forty Centavos
16. TILE WORKS
Amount in Words: Four Hundred Seventy Six Thousand Six Hundred 476,646.88
Forty Six and Eighty Eight Centavos
17. LANDSCAPE
Amount in Words: Two Hundred Thirty Eight Thousand One Hundred 238,125.00
Twenty Five Pesos
GRAND Three Million Five Hundred Sixty Three Thousand Three Hundred
3,563,345.36
TOTAL Forty Five Pesos and Thirty Six Centavos
(In Words) (In Figures)
Republic of the Philippines
MUNICIPALITY OF LAO-ANG
Province of Northern Samar
OFFICE OF THE MUNICIPAL MAYOR
Lao-ang, Northern Samar
Program of Work
Name/Location of Project:
Appropriation: 3,699,062.45
PROPOSED TWO - STOREY BUILDING
Onay Beach, Lao-ang, Northern Samar Source of Fund:
Corporation
Project Duration:
Project Category: 47 weeks
Resort Desirable Starting Date:
Project Description:
Implementing Procedure:
CONSTRUCTION OF 2-STOREY BUILDING
By Contractor
Item No. - Description Percent of Total Unit Quantity Unit Cost Total Direct Cost
B. INDIRECT COST
1. Overhead, Contigency and Miscellaneous (12% of A1 to A3) 12.00% 336,694.05
2. Profit (10% of A1 to A3) 8.00% 224,462.70
3. BIR Tax/VAT (5% of [(A1 to A3)+(B1 to B2)] 7.00% 196,404.86
4. Mobilizaion/Demobilization
SUB-TOTAL 96.33% 3,563,345.36
Contingencies/Reserves
1. Physical Contingencies
2. Price Escalation
3. Budgetary
TOTAL 100.00% 3,699,062.45
Jonathan C. Bulagao
Engineer Municipal Engineer
Approved :
Section VIII. Bill of Quantities
943,497.50
727,749.00
1,540,365.75
49,555.00
276,963.50
31,325.25
185,707.50
253,715.00
234,687.75
57,200.00
181,225.00
222,464.00
825,687.50
412,500.00
SCHEDULE OF ACTIVITIES
Week 10
Week 11
Week 12
Week 13
Week 14
Week 15
Week 16
Week 17
Week 18
Week 19
Week 20
Week 21
Week 22
Week 23
Week 24
Week 25
Week 26
Week 27
Week 28
Week 29
Week 30
Week 31
Week 32
Week 33
Week 34
Week 35
Week 36
Week 37
Week 38
Week 39
Week 40
Week 41
Week 42
Week 43
Week 44
Week 45
Week 46
Week 47
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Week 7
Week 8
Week 9
1 SITE DEVELOPMENT
1.1 Claring and Grubing
2 SITE PLANNING
2.1 Grading
2.2 Excavation
2.3 Backfilling
2.4 Final Grading
3 CIVIL WORKS
3.1 Footing
3.2 Ground Floor Column
3.3 2nd Floor Bams and Slabs
3.4 2nd Floor Column
3.5 Roof Deck Beams and Slabs
3.6 Roofing
3.7 Exterior Wall
3.8 Interior Wall
4 ARCHITECTURAL
4.1 Plumbing
4.2 Electrical
4.3 Ceilings
4.4 Doors and Windows
4.5 Painting and Tiles
5 EXTERIOR DESIGN
5.1 Landscaping
5.2 Cottages Installing
Republic of the Philippines
University of Eastern Philippines
PHYSICAL PLANT DEVELOPMENT OFFICE
University Town, Northern Samar
PROGRAM OF WORK
o Complete:
TOTAL
AMOUNT
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
ERDINAND S. REYES
Budget Officer
QUANTITY TAKE-OFF FOR DIRECT COSTS
2.1 Mobilization
2.1.1 Site Preparation
Demolition of Existing Structures
Clearing and Removal of Weeds, Shrubs, and Trees
2.1.2 Layout
2.2 Earthworks
2.2.1 Excavation
2.3.1 Concreting
2.3.2 SUMMARY:(Concreting)
Particulars Cement
(bag)
Reinforcing Bars
SUMMARY:(Reinforcing Bars)
Particulars 16 mm Ø 12mm Ø
(6m/pc) (6m/pc)
Footings 19.80
Columns 21.84 0.00
Roof Beams 21.41
Slab 68.26
TOTAL 63.05 68.26
(G) (H)
Sand Gravel
(cu.m.) (cu.m.)
D*SF D*GF
SF = 0.42 GF = 0.84
0.76 1.51
0.86 1.72
1.62 3.23
(G) (H)
Sand Gravel
(cu.m.) (cu.m.)
D*SF D*GF
2.10 4.19
2.10 4.19
(G) (H)
Sand Gravel
(cu.m.) (cu.m.)
D*SF D*GF
0.14 0.28
0.14 0.28
0.14 0.28
0.16 0.31
0.16 0.31
0.74 1.47
(G) (H)
Sand Gravel
(cu.m.) (cu.m.)
H*SF H*GF
1.76 3.53
0.21 0.61
0.09 0.26
2.06 4.40
Sand Gravel
(cu.m.) (cu.m.)
1.70 3.39
2.20 4.40
0.81 1.62
2.16 4.62
6.87 14.04
(F) (G)
10mm Ø #16
(6m/pc) Tie Wire
(kls)
2.17
2.17
0.72
2.80 0.72
0.72
2.53 0.72
5.33 7.25
(F) (G)
10mm Ø #16
(6m/pc) Tie Wire
((A*B*C)/6) (kls)
3.53
44.20
44.20 3.53
(F) (G)
10mm Ø #16
(6m/pc) Tie Wire
(kls)
6.97 1.29
6.97 2.15
6.97 2.15
20.90 5.59
(F) (G)
10mm Ø #16
(6m/pc) Tie Wire
(kls)
4.03 1.49
4.95 1.83
4.03 0.75
4.95 0.92
17.97 4.99
(E)
#16
Tie Wire
(kls)
2.72
0.41
0.19
3.31
10mm Ø #16
(6m/pc) Tie Wire
(kls)
5.33 7.25
44.20 3.53
38.87 10.58
22.77 3.31
111.17 24.67
2.2 Masonry Works
GROUND FLOOR
Ground Floor Area 6" CHB 4" CHB 2nd Floor Area
(sq.m.) (pcs.) (pcs.) (sq.m.)
Along Row 1 25.20 327.6
Along Row 2 15.65 203
Btw. Row 2 & 3 6.64 86
Along Row 3 23.52 305.76
Along Row A 24.75 321.75
Btw. Row A & B 33.86 440
Along Row B 26.65 346.45
Porch 8.96 116
TOTAL 165.23 1367 889
NOTE: Multiply the area by 13 to get the quantity of CHB. Round off to the nearest greater whole number.
SUMMARY:
PARTICULAR QTY UNITS QTY UNITS
6" CHB 1367 pcs
4" CHB 889 pcs
Cement 286.00 bags
Sand 16.00 cu.m.
12mm Ø (6m/pc) 75.00 pcs. 399.75 kgs.
10mm Ø (6m/pc) 49.00 pcs. 181.30 kgs.
#16 Tie Wire 7.00 kgs.
Septic Vault
Septic Vault
SV 2.80 1.2 1.3 11.96 155.48
SUMMARY:
PARTICULAR QTY UNITS QTY UNITS
6" CHB 155 pcs
4" CHB 0 pcs
Cement 24.67 bags
Sand 1.31 cu.m.
Gravel 0.53 cu.m.
12mm Ø (6m/pc) 0.00 pcs. 0 kgs.
10mm Ø (6m/pc) 20.36 pcs. 75.35 kgs.
#16 Tie Wire 0.82 kgs.
Wall
4.67 0.36
1.25 0.36
4.67 0.36
1.25 0.36
11.83 0.36
FORMWORKS SCAFFOLDING
Column Column
Beam Beam
Total Area 0
Footing
support
PLYWOOD For 2"x3" Wood Fram 0
Lateral Perimeter (P) 4m
Total Area 36.96 sq.m.
No. of Plywood 12.83333 say 13 pieces
WOOD FRAME
For 2"x2" Wood Frame 325.78 say 326 bd.ft.
Slab
PLYWOOD
stairs
no. of steps 2
area of landing 0.125
risers 0.17
tread 0.25
length of stringers 1.12
width of thread 0.5
length Qty./Lengt12mm dia. Bar (6m) 10mm dia. Bar (6m) Tie Wires
Stringers 1.12 2 0.373333 0.042264
0 0
width of thread 0.5 3.733333 0.311111
0 0
risers 0.17 6.666667 0.188889 0.075472
thread 0.25 6.666667 0.277778
Total 0.373333 0.777778 0.117736
CHB
TOTAL AREA
4" CHB
W-1 1 1 1 800
W-2 0.5 0.5 0.25 225
1902 pcs
189 pcs
D-1 0.8 2.1 1.68 1176
D-2 0.8 2.1 1.68 1176
D-3 0.7 2.1 1.47 882
D-4 0.8 2.1 1.68 1176
3.333333
8.857143
6.222222
MORTAR
29 pcs
Paint
EXTERIOR MASONRY PAINT
Primer
Acrylic Semi-Gloss Latex (2 coats
INTERIOR MASONRY PAINT
Primer
Flat wall enamel (2 coats)
CEILING
Primer
Flat Enamel (2 coats)
3 sq.m.
per gallon
160.0175 sq.m. 4.571929
mi-Gloss Latex (2 coats 160.0175 sq.m. 7.111889 EXTERIOR
6" Wall
103 sq.m. 2.942857 L H OPEN OPEN
enamel (2 coats) 103 sq.m. 4.577778 6 4
7 3.5 4.2
6 4 D-1 1.68
47 sq.m. 1.342857 7 4 W-1 1 W-2
47 sq.m. 2.088889
Interior
6 3.5
7 3.5 4.2
6 3.5 D-1 1.68
7 3.5 W-1 1 W-2
2.975 3.5
2.825 3.5
3.75 3.5 D-4 1.68
3.85 3.5 D-4 1.68
3.825 3.5 D-2 1.68
3.825 3.5 D-2 1.68
1.475 3.5
1.5 3.5 D-3 1.47
OPEN OPEN Net Area
24
20.3
22.32
0.25 26.75
TOTAL AREA 93.37
21
20.3
19.32
0.25 23.5
10.4125
9.8875
11.445
11.795
11.7075
11.7075
5.1625
3.78
Total 160.0175
pieces
sq.m.