Professional Documents
Culture Documents
CONDITIONS OF CONTRACT
VOLUME 1, SECTION III
BLANK PAGE
Page 1 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
Contents
General Terms & Conditions of Contract (GCC)...................................................................................... 4
1. DEFINITION OF TERMS ................................................................................................................ 4
2. APPLICATION ............................................................................................................................... 7
3. STANDARDS................................................................................................................................. 7
4. LANGUAGE AND MEASURES ....................................................................................................... 7
5. CONTRACT DOCUMENTS ............................................................................................................ 8
6. USE OF CONTRACT DOCUMENTS AND INFORMATION .............................................................. 8
7. INDEPENDENT CONTRACTOR...................................................................................................... 9
8. CONSTRUCTION OF THE CONTRACT ........................................................................................... 9
9. AMENDMENT .............................................................................................................................. 9
10. JURISDICTION OF THE CONTRACT........................................................................................... 9
11. MANNER OF EXECUTION OF THE CONTRACT ....................................................................... 10
12. ENFORCEMENT OF TERMS .................................................................................................... 10
13. COMPLETION OF THE CONTRACT ......................................................................................... 10
14. TIME – THE ESSENCE OF THE CONTRACT.............................................................................. 11
15. Installation ............................................................................................................................ 12
16. EFFECTIVENESS OF THE CONTRACT ...................................................................................... 14
17. TAXES, PERMITS & LICENCES ................................................................................................ 14
18. PATENT RIGHTS AND LOYALTIES ........................................................................................... 14
19. DEFENCE OF SUITS ................................................................................................................ 15
20. LIMITATION OF LIABILITIES ................................................................................................... 15
21. ENGINEER’S DECISION........................................................................................................... 16
22. ASSIGNMENT AND SUB-LETTING OF CONTRACT .................................................................. 16
23. CHANGE OF QUANTITY ......................................................................................................... 17
24. NO WAIVER OF RIGHTS ......................................................................................................... 17
25. PROGRESS REPORTS AND PHOTOGRAPHS ........................................................................... 17
26. PAYMENTS ............................................................................................................................ 17
27. PENALTY FOR DELAY IN EXECUTION/NON- EXECUTION OF THE WORK. .............................. 18
28. DEDUCTIONS FROM CONTRACT PRICE ................................................................................. 18
29. INSURANCE ........................................................................................................................... 19
30. LIABILITY FOR ACCIDENTS AND DAMAGES ........................................................................... 19
31. DEMURRAGE, WHARFAGE, ETC. ........................................................................................... 20
32. FIRST AID ............................................................................................................................... 20
33. FORCE MAJEURE ................................................................................................................... 20
34. CONTRACTOR`S DEFAULT/LIQUIDATED DAMAGES .............................................................. 20
Page 2 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
Page 3 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
1. DEFINITION OF TERMS
1.1. ‘Contract’ means the agreement entered into between the Owner and the
Contractor as per the Contract Agreement signed by the parties,
including all attachments and appendices thereto and all documents
incorporated by reference therein.
1.4. ‘Sub-Contractor’ shall mean the person named in the Contract for any
part of the Works or any person to whom any part of the Contract has
been sublet by the Contractor with the consent in writing of the Engineer
and will include the legal representatives, successors and permitted
assigns of such person.
1.5. ‘Engineer’ shall mean the Deputy General Manager (SG&EV) or the
Executive Engineer of the division or the officer appointed by the Owner
to act as Engineer from time to time for the purpose of the Contract.
1.7. The terms ‘Equipment’, ‘Stores’ and ‘Materials’ shall mean and include
equipment, stores and materials to be provided by the Contractor under
the Contract.
1.8. ‘Works’ shall mean and include all the activities to be carried out as per
the detailed scope of the work.
1.10. The term ‘Contract price’ shall mean the percentage quoted by the
Contractor in his bid with additions and/or deletions as may be agreed
and incorporated in the Letter of Award, for the entire scope of the
works.
1.11. ‘Inspector’ shall mean the Owner or any person nominated by the Owner
from time to time, to inspect the equipment; stores or Works under the
Contract and/or the duly authorized representative of the Owner.
1.12. ‘Site' shall mean and include the Land and other places on, into or
through which the Works and the related facilities are to be Erected or
Page 4 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
Installed and any adjacent Land, Paths, Street or Reservoir which may
be allocated or used by the Owner or Contractor in the Performance of
the Contract.
1.13. The term “Equipment/material Portion” of the Contract price shall mean
the total value of the equipment including all applicable taxes and
duties, F&I, Insurance etc.
1.14. The term “Erection Portion” of the Contract price shall mean the value of
field activities of the works including erection, testing and putting into
satisfactory operation including successful completion of performance
and guarantee tests to be performed at Site by the Contractor including
cost of insurances.
1.17. ‘Date of Contract’ shall mean the date on which Notice of Award of
Contract/Letter of Award has been issued.
1.18. ‘Month’ shall mean the calendar month. ‘Day’ or ‘Days’ unless herein
otherwise expressly defined shall mean calendar day or days of 24 hours
each.
1.21. Test on completion shall mean such tests as prescribed in the Contract
to be performed by the Contractor before the work is taken over by the
Owner.
1.22. “Start up” shall mean the time period required to bring the equipment
covered under the Contract from an inactive condition, when
construction is essentially complete, to the state ready for trial operation.
The start-up period shall include preliminary inspection and check-out
of equipment and supporting sub-system, initial operation of the
complete equipment covered under the Contract to obtain necessary pre-
trial operation data, perform calibration and corrective action, shut-
down, inspection and adjustment prior to the trial operation period
1.23. “Performance and Guarantee Tests”, shall mean all operational checks
and tests required to determine and demonstrate capacity, efficiency,
and operating characteristics as specified in the Contract Documents.
Page 5 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
1.24. The term “Final Acceptance”/ “Taking Over” shall mean the Owner’s
written acceptance of the Works performed under the Contract, after
successful commissioning/completion of Performance and Guarantee
Tests, as specified in the accompanying Technical Specifications or
otherwise agreed in the Contract
1.26. ‘Guarantee Period’ shall mean the period during which the Contractor
shall remain liable for repair or replacement of any defective part of the
works performed under the Contract.
1.27. ‘Engineer in charge of work’ shall mean the Executive Engineer of the
respective division awarded.
1.28. ‘Latent Defects’ shall mean such defects caused by faulty material or
work-man-ship which cannot be detected during inspection, testing etc,
based on the technology available for carrying out such tests.
1.29.3. Drawings submitted by the Contractor with his bid provided such
drawings are acceptable to the Owner/Consultant
1.29.4. Plans submitted by the Contractor for executing the works with
his bid provided such plans are acceptable to the
Owner/Consultant.
1.30. Words imparting the singular only shall also include the plural and vice
– versa where the context so requires.
1.32. Terms and expressions not herein defined shall have the same meaning
as are assigned to them in the Indian Sale of Goods Act (1930), failing
that in the Indian Contract Act (1872) and failing that in the General
Clauses Act (1897) including amendments thereof, if any.
Page 6 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
The various Acts and Regulations are normally available for sale from the
following addresses:
i. Deputy Controller
Publication Department
Government of India
Civil Lines,
DELHI-110 006
Or
1.33. Commissioning: Under this contract shall mean Charging the vehicle
after Completion of Erection, Testing and Completion of Pre-
Commissioning checks after necessary approvals from Electrical
Inspectorate (if applicable).
1.34. In addition to the above the following definitions shall also apply:
2. APPLICATION
2.1. These General Conditions shall apply to the extent that they are not
superseded by provisions in other parts of the Contract.
3. STANDARDS
3.1. The goods supplied under this Contract shall conform to the standards
mentioned in the Charging Station Standards as in Annexure-2, and,
when no applicable standard is mentioned, to the authoritative standard
appropriate to the goods and such standards shall be the latest issued
by the concerned institution.
5. CONTRACT DOCUMENTS
5.1. The term Contract Documents shall mean and include the following,
which shall be deemed to form an integral part of the Contract:
c) All the materials, literature, data and information of any sort given by
the Contractor along with his bid, subject to the approval of the
Owner /Consultant.
5.2. In the event of any conflict between the above mentioned documents, the
matter shall be referred to the Deputy General Manager (SG&EV) whose
decision shall be considered as final and binding upon the parties.
5.3. All the relevant Information/ Material furnished by the Contractor such
as Specifications of Material/ Equipment, Design, Literature, Drawings
or any other Data during the course of Contract will become the Property
of the Owner and Owner will have full rights to use the same elsewhere
6.2. The Contractor shall not, without the Owner’s prior written consent,
make use of any document or information enumerated in various
Contract documents except for the purpose of performing the Contract.
Page 8 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
6.4. Any document, other than the Contract itself, enumerated in various
Contract documents shall remain the property of the Owner and shall be
returned (in all copies) to the Owner on completion of the Contractor’s
performance under the Contract if so required by the Owner.
7. INDEPENDENT CONTRACTOR
7.1. The Contractor shall be an independent contractor performing the
Contract. The Contract does not create any agency, partnership, joint
venture or other joint relationship between the parties hereto.
8.2. The Contract shall in all respects be construed and governed according
to Indian Laws.
8.3. It is clearly understood that the total consideration for the Contract(s)
has been broken up into various components only for the convenience of
payment of advance under the Contract(s) and for the measurement of
deviations or modifications under the Contract(s).
9. AMENDMENT
9.1. No amendment or other variation of the contract shall be effective unless
it is in writing, is dated, expressly refers to the contract, and is signed by
a duly authorized representative of each party hereto.
Page 9 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
11.2. The Agreement, unless otherwise agreed to, shall be signed within 28
days of the Letter of Intent, at the office of the Owner on a date and time
to be mutually agreed. The Contractor shall provide for signing of the
Contract, Performance Bank Guarantee in four copies, appropriate
power of attorney and other requisite materials. In case the Contract is
to be signed beyond the stipulated time, the Bid Guarantee submitted
with the Proposal will have to be extended accordingly.
11.3. The Agreement will be signed in 2 (two) originals and the Contractor
shall be provided with one signed original and the other will be retained
by the Owner.
Page 10 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
14.2. The Contractor shall submit a detailed PERT Network Chart, within the
time frame agreed, consisting of adequate number of activities covering
various key Phases of the Work such as Design, Procurement,
Manufacturing, Shipment, Receiving of the Owner Supplied Equipment
(if any), and Field Erection activities within fifteen (15) days of the date of
Letter of Award. This Network shall also indicate the Interface facilities to
be provided by the Owner and the dates by which such facilities are
needed. The Contractor shall discuss the Network so submitted with the
Owner and the agreed Network shall form part of the Contract
Documents. During the Performance of the Contract, if in the opinion of
the Engineer, proper progress is not maintained, Suitable changes shall
be made in the Contractor's Operations to ensure proper progress
without any Cost implication to the Owner. The Interface Facilities to be
provided by the Owner in accordance with the agreed Network shall also
be reviewed while reviewing the progress of the Contract. The PERT
Network should be reviewed, updated, once every Month and submitted
to Engineer for approval.
14.6. The contractor shall also submit the item wise breakup / tax break up
while awarding the contract as and when requested by BESCOM.
14.8. The successful bidder shall complete the work of Supply, Installation,
and Commissioning of EVSE as detailed in the scope of the work within
180 days of the LoA. However consequent to delay in execution of works
attributable to the Owner, the Bidder shall not be held responsible for
the same.
14.10. The Selected Bidder shall also submit monthly compliance reports with
Page 11 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
14.11. The Selected Bidder shall submit the progress reports for number of
EVSE installed and commissioned on weekly basis.
14.12. The formats for reporting compliance of number of EVSE installed and
commissioned shall be as per Annexure-3 and as decided by DGM
(SG&EV).
15. Installation
15.1. Setting Out/Supervision/Labour
15.1.3. Labour
c. The Contractor shall at all times during the progress of the Contract
use its best endeavours to prevent any unlawful, riotous or disorderly
conduct or behaviour by or amongst its employees and the labour of
its Subcontractors.
d. The Contractor shall, in all dealings with its labour and the labour of
its Subcontractors currently employed on or connected with the
Page 12 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
15.2.2. Such Site regulations shall include, but shall not be limited to,
rules in respect of security, safety of the Facilities, gate control,
sanitation, medical care, and fire prevention.
Page 13 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
15.5.1. The Contractor shall provide and maintain at its own expense all
lighting, fencing, and watching when and where necessary for the
proper execution and the protection of the Facilities, or for the
safety of the owners and occupiers of adjacent property and for the
safety of the public
17.2. No claim for any increase towards the Statutory Variation regarding
enhancement of existing Tax or Duty or introduction of a new Tax or
Duty applicable shall be entertained by the owner during the extended
period of contract, if any, if extension of the Contract is required due to
the causes attributable to the Contractor.
17.3. The Owner will deduct Taxes applicable at Source as per applicable law
from the proceeds payable to the Contractor.
Page 14 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
have been included in the Contract Price. The Contractor shall satisfy
all demands that may be made at any time for such royalties or fees and
he alone shall be liable for any damages or claims for patent
infringements and shall keep the Owner indemnified in that regard. The
Contractor shall, at his own cost and expense, defend all suits or
proceedings that may be instituted for alleged infringement of any
patents involved in the Works, and, in case of an award of damages, the
Contractor shall pay for such award. In the event of any suit or other
proceedings instituted against the Owner, the same shall be defended at
the cost and expense of the Contractor who shall also satisfy/comply
with any decree, order or award made against the Owner. But it shall be
understood that no such machine, plant, work, material or thing has
been used by the Owner for any purpose or any manner other than that
for which they have been furnished and installed by the Contractor and
specified under these specifications. Final payment to the Contractor by
the Owner will not be made while any such suit or claim remains
unsettled. In the event any apparatus or equipment, or any part thereof
furnished by the Contractor, is in such suit or proceedings held to
constitute infringement, and its use is enjoined, the Contractor shall at
his option and at his own expense, either procure for the Owner, the
right to continue the use of said apparatus, equipment or part thereof,
replace it with non-infringing apparatus or equipment or modify it, so it
becomes non-infringing.
20.3. This limitation of liability provided in this Clause shall not limit the
Bidders liability for the indemnity obligations as agreed in this
Agreement.
20.4. The final payment by the Owner by releasing the Contract performance
Guarantee in pursuance of the Contract shall mean the release of the
Contractor from all his liabilities under the Contract. Such final
payment shall be made only at the end of the contract period, and till
such time as the Contractual liabilities and responsibilities of the
Contractor, shall prevail. All other payments made under the Contract
shall be treated as on-account payments.
21.2. If, in the opinion of the Contractor, a decision made by the Engineer is
not in accordance with the meaning and intent of the Contract, the
Contractor may file with the Engineer, within fifteen (15) days after
receipt of the decision, a written objection to the decision. Failure to file
an objection within the allotted time will be considered as an acceptance
of the Engineer’s decision and the decision shall become final and
binding.
21.3. The Engineer’s decision and the filing of the written objection thereto
shall be a condition precedent to the right to request arbitration. It is
the intent of the Agreement that there shall be no delay in the execution
of the works and the decision of the Engineer as rendered shall be
promptly observed.
Page 16 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
26. PAYMENTS
26.1. The revenue sharing shall be done between BESCOM and the
Concessionaire / bidder. As per the provisions of agreement all the
disputes regarding land related matters shall be resolved mutually
between BESCOM and the Concessionaire.
26.3. The CMS dashboard access shall be provided to BESCOM for verifying
the monthly revenue out of the charging / battery swapping stations.
Page 17 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
The payment shall be made on a monthly basis and the payment for any
month must be made before the 15th of the following month through e-
payment or electronic clearance system. For this BESCOM shall provide
the below mentioned details to the Concessionaire.
Page 18 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
C. RISK DISTRIBUTION
29. INSURANCE
29.1. The Contractor at his cost shall arrange, secure and maintain all
insurance as may be pertinent to the Works and obligatory in terms of
law to protect his interest and interests of the Owner against all perils.
The form and the limit of such insurance as defined herein together with
the under-writer in each case shall be acceptable to the Owner.
However, irrespective of such acceptance, the responsibility to maintain
adequate insurance coverage at all time during the period of Contract
shall be of Contractor alone. The Contractor’s failure in this regard shall
not relieve him of any of his contractual responsibilities and obligations.
29.3. The perils required to be covered under the insurance shall include, but
not be limited to fire and allied risks, miscellaneous accidents (erection
risks) workman compensation risks, loss or damage in transit, theft,
pilferage, riot and strikes and malicious damages, civil commotion,
weather conditions, accidents of all kinds, etc. The scope of such
insurance shall be adequate to cover the cost of erection of transformer
centre as per new design inclusive of supply of materials, erection at site
and inspectorate charges. The insurance policies to be taken should be
on cost of transformer center as per new design incorporating escalation
clause. Notwithstanding the extent of insurance cover and the amount
of claim available from the underwriters, the Contractor shall be liable to
make good the full replacement/rectification value of all
equipment/materials and to ensure their availability as per project
requirements.
29.4. All costs on account of insurance liabilities covered under the Contract
will be on Contractor’s account and will be included in Contract Price,
Page 19 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
Provided either party shall within fifteen (15) days from the
occurrence of such a cause notify the other in writing of such causes.
33.2. The Contractor or the Owner shall not be liable for delays in performing
his obligations resulting from any force majeure cause as referred to
and/or defined above
from the Contractor a penalty at the rate of INR 15,000 for each site per
week up to a maximum of INR 1,50,000/-. The amount of penalty can be
recovered from any amount including performance security due to the
[
bidder from Purchaser.
[[
35. TERMINATION OF CONTRACT ON OWNER`S INITIATIVE
35.1. The Owner reserves the right to terminate the Contract either in part or
in full due to reasons other than those mentioned under clause entitled
‘Contractor’s Default’. The Owner shall in such an event give fifteen (15)
days notice in writing to the Contractor of his decision to do so.
35.2. The Contractor upon receipt of such notice shall discontinue the work on
the date and to the extent specified in the notice, make all reasonable
efforts to obtain cancellation of all orders and Contracts to the extent
they are related to the work terminated and terms satisfactory to the
Owner or purchasing activity related to the work terminated.
36.4. In the event referred to in sub-clauses 36.1 & 36.2 above the parties
shall mutually discuss to arrive at reasonable settlement on all issues
including amounts due to either party for the work already done on
“Quantum merit” basis, which shall be determined by mutual agreement
between the parties.
Page 22 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12
GENERAL TERMS & CONDITIONS OF CONTRACT Vol-1, Section III
D. RESOLUTION OF DISPUTES
38.2. If any dispute or difference of any kind, whatsoever, shall arise between
the Owner and the Contractor, arising out of the Contract for the
performance of the Works whether during the progress of the Works or
after its completion or whether before or after the termination,
abandonment or breach of the Contract, it shall, be referred to and
settled by the MD,BESCOM who, within a period of thirty (30) days after
being requested by either party to do so, shall give written notice of his
decision to the Owner and the Contractor.
38.4. If after the Engineer has given written notice of his decision to the
parties, no claim to arbitration has been communicated to him by either
party within thirty (30) days from the receipt of such notice, the said
decision shall become final and binding on the parties.
38.5. In the event of the Engineer failing to notify his decision as aforesaid
within thirty (30) days after being requested as aforesaid, or in the event
of either the Owner or the Contractor being dissatisfied with any such
decision, or within thirty (30) days after the expiry of the first mentioned
period of thirty days, as the case may be, either party may require that
the matters in dispute be referred to arbitration as hereinafter provided.
39. ARBITRATION
39.1. All disputes or differences in respect of which the decision, if any, of the
Engineer has not become final or binding as aforesaid shall be settled by
arbitration in the manner hereinafter provided
India.
39.4. The decision of the majority of the arbitrators shall be final and binding
upon the parties. The arbitrators may, from time to time with the
consent of all the parties enlarge the time for making the award. In the
event of any of the aforesaid arbitrators dying, neglecting, resigning or
being unable to act for any reason, it will be lawful for the party
concerned to nominate another arbitrator in place of the outgoing
arbitrator.
39.5. The arbitrator shall have full powers to review and/or revise any
decision, opinion, direction, certification or valuation of the Engineer in
accordance with the Contract, and neither party shall be limited in the
proceedings before such arbitrators to the evidence or arguments put
before the Engineer for the purpose of obtaining the said decision.
Sd/-
Deputy General Manager,
SG&EV, BESCOM.
Page 24 of 24
BESCOM/BC-53/DGM(SG&EV)/2021-22/Enq-12