Professional Documents
Culture Documents
Construction
Costs
Ramp Up
Traffic &
Revenue
O&M
er
-2
-1
10
0
ov
d
an
H
Year
Toll Forecast Accuracy/ Reliability
Average initial year traffic: 70% of forecast
• For lender-commissioned studies: 82%
• For other studies: 66%
– Bain, R. and Wilkins, M. “Credit Implications of Traffic Risk in Start-Up Toll Facilities”,
Standard & Poor’s, September 2002
Due to Ramp Up?
• Can last 3-5 years
– Streeter, W. and McManus, K. “Challenges of Start-Up Toll Roads”, Project Finance
Special Report, Fitch ICBA, 1999
Or optimism bias constant up to year 5?
– Bain, R. and Polakovic, L, “Traffic Forecasting Risk Study Update 2005: Through Ramp-
Up and Beyond”, Standard & Poor’s, August 2005
1,400
1,200
(BDT per vehicle per Hour)
Behavioural Value of Time
1,000
800
600
400
200
0
0 1,000 2,000 3,000 4,000 5,000 6,000
Number of Respondents (Sorted by BVOT per Vehicle)
1,400
1,200
(BDT per vehicle per Hour)
Behavioural Value of Time
1,000
800
600
400
200
0
0 2,000 4,000 6,000 8,000 10,000 12,000
Number of Respondents (Sorted by BVOT per Vehicle)