You are on page 1of 9

MEGAS ARCHITECTURA

Project- Kanpur Depot


Sr. NO. LOCATION OBSERVATION ACTION TAKEN

1 Warehouse Substandard panel arrangements.

2 Warehouse Cable glands not provided

Binding wire is being used instead


3 Warehouse
of cable tie at several place

Electrical installations fixed over


wooden ply instead of standard
4 Warehouse
IP44 panel, arrangements as per
SHE condition of contract
panel door arrangement system
5 Warehouse
not implemented

6 Warehouse No rubber mat provided in front


of electrical panel

7
8

Prepared by: Mohammad Jawed A

Verified by: Bilal Haji (Project co


AS ARCHITECTURAL SERVICES PVT LTD.
Date- 21-08-2021
OBSERVATION STATUS ACTION TAKEN BY EVIDENCE/PHOTOS

Closed Megas team

Closed Megas team

on going Megas team

Closed Megas team


Closed Megas team

Closed Megas team


Mohammad Jawed Ansari (EHS) Megas Architectural PVT LTD.