From 28 June to 4 July, I was assigned to Power House. In previous week I was stationed at Weir
and Intake where the concrete on return wall was started
At Power House they completed the concrete work on both storage tanks and also at draft tubes.
Now they place the spiral case on draft tubes which will help the turbine to run.