In last two weeks they started placing concrete on the bed of still basin. They have placed concrete up to
EL:2293. They still have to put 0.5m concrete to reach EL:2293.5. The depth of bed is 2.8m up to 5m length and
2m depth up to 6m length and 1m up to 5.4m. The concrete used at bed is G28 and mostly reinforcement used
is 25mm.
They also placed concrete on bed of Approach slab and Ogee. They placed concrete up to EL:2295.50 and have
to place 0.5m more concrete to reach EL:2296. The depth of bed is 1m. The concrete used is G28 and mostly
reinforcement used is 25mm.