Professional Documents
Culture Documents
Power
Sl. No. Description of Machine Activity Unit Rate Remarks
(in HP)
P&M-1001 Dozer - 240 HP 240 Hour 3005.00 Equipment Rate
P&M-1002 Dozer - 175 HP 175 Hour 2099.00 Equipment Rate
P&M-1003 Dozer - 90 HP 90 Hour 1267.00 Equipment Rate
P&M-2001 Motor Grader 4.3 metre blade 186 Hour 5796.00 Equipment Rate
P&M-2002 Motor Grader 3.7 metre blade 171 Hour 5316.00 Equipment Rate
P&M-2003 Motor Grader 3.35 metre blade 110 Hour 1576.00 Equipment Rate
P&M-3003 Hydraulic Excavator of 1.2 cum bucket 188 Hour 1748.00 Equipment Rate
P&M-3004 Hydraulic Excavator of 1.1 cum bucket 162 Hour 1748.00 Equipment Rate
P&M-3005 Hydraulic Excavator of 0.9 cum bucket 138 Hour 2570.00 Equipment Rate
P&M-4001 Jack Hammer (attachment of Hydraulic Excavator) - Hour 206.00 Equipment Rate
P&M-5001 Front End loader 3.1 cum bucket capacity 221 Hour 3907.00 Equipment Rate
P&M-5002 Front End loader 2.1 cum bucket capacity 150 Hour 2393.00 Equipment Rate
P&M-5003 Backhoe-loader 1 cum bucket capacity 92 Hour 1633.00 Equipment Rate
P&M-6001 Tipper-18 Cum 280 Hour 2621.00 Equipment Rate
P&M-6002 Tipper-14 Cum 220 Hour 2331.00 Equipment Rate
P&M-6003 Tipper-10 Cum 178 Hour 2077.00 Equipment Rate
P&M-6004 Tipper-5.5 Cum 90 Hour 1590.00 Equipment Rate
P&M-7001 Vibratory Soil Compactor (10 tonne) 99 Hour 2335.00 Equipment Rate
P&M-8001 Smooth Wheeled Roller 8 tonne 98 Hour 1864.00 Equipment Rate
P&M-9001 Tandem Roller 99 Hour 2325.00 Equipment Rate
P&M-9002 Mini Tandem Roller 44 Hour 1303.00 Equipment Rate
P&M-10001 Pneumatic Road Roller 114 Hour 2333.00 Equipment Rate
P&M-11001 Water Tanker (16 KL) 150 Hour 1357.00 Equipment Rate
P&M-11002 Water Tanker (12 KL) 150 Hour 1187.00 Equipment Rate
P&M-11003 Water Tanker (6 KL) 100 Hour 904.00 Equipment Rate
P&M-12001 Tractor-trolley 42 Hour 820.00 Equipment Rate
P&M-13001 Rotavator - Hour Equipment Rate
P&M-14001 Ripper - Hour 21.00 Equipment Rate
P&M-15001 Air Compressor -250 cfm 5 Hour 550.00 Equipment Rate
P&M-15002 Air Compressor -500 cfm 148 Hour 2413.00 Equipment Rate
P&M-16001 Integrated Stone Crusher Stone (3 Stage) 250 TPH - Hour 14570.00 Equipment Rate
P&M-17001 Wet Mix Plant - 250 TPH Capacity - Hour 850.00 Equipment Rate
P&M-17002 Wet Mix Plant - 200 TPH Capacity - Hour 556.00 Equipment Rate
P&M-17003 Wet Mix Plant - 100 TPH Capacity - Hour 531.00 Equipment Rate
P&M-18001 Hotmix Plant - 200 TPH Capacity - Hour 13298.00 Equipment Rate
P&M-18002 Hotmix Plant - 160 TPH Capacity - Hour 9323.00 Equipment Rate
P&M-18003 Hotmix Plant - 120 TPH capacity - Hour 7568.00 Equipment Rate
P&M-19001 Batching and Mixing Plant - 240 cum Capacity - Hour 5971.00 Equipment Rate
P&M-19002 Batching and Mixing Plant - 120 cum Capacity - Hour 3877.00 Equipment Rate
P&M-20001 Mobile Concrete Batching / Mixing Plant 60 Hour 886.00 Equipment Rate
P&M-21001 Concrete Mixer - 0.4/0.28 cum 10 Hour 451.00 Equipment Rate
P&M-21002 Concrete Mixer - 1 cum 15 Hour 487.00 Equipment Rate
P&M-22001 Generator 725 KVA 777 Hour 10098.00 Equipment Rate
P&M-22002 Generator 500 KVA 536 Hour 6985.00 Equipment Rate
P&M-22003 Generator 400 KVA 430 Hour 5635.00 Equipment Rate
P&M-22004 Generator 250 KVA 303 Hour 3970.00 Equipment Rate
P&M-22005 Generator 125 KVA 154 Hour 2083.00 Equipment Rate
P&M-22006 Generator 100 KVA 129 Hour 1781.00 Equipment Rate
P&M-22007 Generator 62.5 KVA 80 Hour 1146.00 Equipment Rate
P&M-22008 Generator 33 KVA 42 Hour 659.00 Equipment Rate
P&M-22009 Generator 15 KVA 20 Hour 374.00 Equipment Rate
P&M-23001 Mechanical Broom Hydraulic 50 Hour 951.00 Equipment Rate
P&M-24001 Bitumen Pressure Distributor 170 Hour 1550.00 Equipment Rate
P&M-25001 Emulsion Pressure Distributor 170 Hour 1550.00 Equipment Rate
P&M-26001 Bitumen Boiler Oil Fired 50 Hour 664.00 Equipment Rate
P&M-27001 Mastic Cooker 10 Hour 600.00 Equipment Rate
P&M-28001 Paver Finisher Mechanical 123 Hour 2374.00 Equipment Rate
P&M-29001 Paver Finisher Hydrostatic with sensor control -240 HP 240 Hour 8638.00 Equipment Rate
P&M-29002 Paver Finisher Hydrostatic with sensor control -170 HP 170 Hour 6848.00 Equipment Rate
P&M-30001 Paver Finisher Concrete with 300 HP Motor 300 Hour 26584.00 Equipment Rate
P&M-30002 Paver Finisher Concrete with 241 HP Motor 241 Hour 17178.00 Equipment Rate
P&M-30003 Paver Finisher Concrete with 118 HP Motor 118 Hour 4204.00 Equipment Rate
P&M-31001 Texture Curing Machine (TCM) - upto 18 m 55 Hour 4543.00 Equipment Rate
P&M-31002 Texture Curing Machine (TCM) - upto 9 m 55 Hour 3570.00 Equipment Rate
P&M-32001 Hydraulic Chip Spreader 200 Hour 1989.00 Equipment Rate
P&M-33001 Pot-Hole Repair Machine 178 Hour 1596.00 Equipment Rate
P&M-34001 Transit Mixer - 6 Cum 178 Hour 2198.00 Equipment Rate
P&M-35001 Concrete Pump 15 Hour 1218.00 Equipment Rate
P&M-36001 Boom Placer 178 Hour 4033.00 Equipment Rate
P&M-37001 Kerb Casting Machine 50 Hour 1788.00 Equipment Rate
Page 1 of 253
P&M-38001 Piling Rig with Bentonite Pump 360 Hour 18344.00 Equipment Rate
P&M-39001 Pneumatic Sinking Plant 250 Hour 6253.00 Equipment Rate
P&M-40001 Road marking machine 90 Hour 1728.00 Equipment Rate
P&M-41001 Mobile Slurry Seal Equipment 115 Hour 3674.00 Equipment Rate
P&M-42001 Joint Cutting Machine 5 Hour 452.00 Equipment Rate
P&M-43001 Bar Bending & Cutting Machine 5 Hour 468.00 Equipment Rate
P&M-44001 Needle Vibrator 5 Hour 520.00 Equipment Rate
P&M-45001 Jack Hammer for air compressor - Hour 11.00 Equipment Rate
P&M-46001 Plate Compactor 8 Hour 528.00 Equipment Rate
P&M-47001 Milling Machine with 1 meter Drum Width 155 Hour 4449.00 Equipment Rate
P&M-47002 Milling Machine with 1.2 meter Drum Width 208 Hour 5193.00 Equipment Rate
P&M-47003 Milling Machine With 1.3 meter Drum Width 330 Hour 7433.00 Equipment Rate
P&M-47004 Milling Machine With 2 meter Drum Width 500 Hour 11083.00 Equipment Rate
P&M-48001 Cold in Situ recycling of bitumen's pavement with foam bitumen technology 602 Hour 28922.00 Equipment Rate
P&M-49001 In situ stabilisation of WMM/GSB/Sub grade 602 Hour 25129.00 Equipment Rate
P&M-50001 Cement spreader 350 Hour 7687.00 Equipment Rate
P&M-51001 Mobile cold recycling mixing plant 300 Hour 21137.00 Equipment Rate
P&M-52001 Hot in place recycling 322 Hour 103276.00 Equipment Rate
P&M-53001 Pre heater unit for hot in place recycling 101 Hour 1114.00 Equipment Rate
P&M-54001 Single boom Hydraulic Drill Jumbo 78 Hour 4969.00 Equipment Rate
P&M-55001 Two boom Hydraulic Drill Jumbo 160 Hour 7468.00 Equipment Rate
P&M-56001 Three boom Hydraulic Drill Jumbo 240 Hour 10911.00 Equipment Rate
P&M-57001 Hydraulic Rock bolt drill 90 Hour 7199.00 Equipment Rate
P&M-58001 Rotating Telehandlers 101 Hour 1091.00 Equipment Rate
P&M-59001 Shotcrete Machine 90 Hour 1535.00 Equipment Rate
P&M-60001 Grouting machine 8 Hour 708.00 Equipment Rate
P&M-61001 Dewatering Pump 10 HP 10 Hour 289.00 Equipment Rate
P&M-61002 Concrete cutting machine 5 Hour 200.00 Equipment Rate
P&M-62001 Crawler mounted Crane 35 tonne capacity 170 Hour 5898.00 Equipment Rate
P&M-62002 Crawler mounted Crane 80 tonne capacity 230 Hour 6100.00 Equipment Rate
P&M-62003 Crawler mounted Crane 100 tonne capacity 300 Hour 9293.00 Equipment Rate
P&M-63001 Mobile Hydraulic Crane 3 tonne capacity 42 Hour 966.00 Equipment Rate
P&M-63002 Mobile Hydraulic Crane 5 tonne capacity 45 Hour 1007.00 Equipment Rate
P&M-63003 Mobile Hydraulic Crane 10 tonne capacity 48 Hour 1110.00 Equipment Rate
P&M-63004 Mobile Hydraulic Crane 15 tonne capacity 49 Hour 1145.00 Equipment Rate
P&M-63005 Mobile Hydraulic Crane 20 tonne capacity 101 Hour 1411.00 Equipment Rate
P&M-63006 Mobile Hydraulic Crane 35 toone capacity 173 Hour 2133.00 Equipment Rate
P&M-64001 Concrete Bucket Hour 136.00 Equipment Rate
P&M-65001 Prestressing Jack with Pump & Access (400 tonne) Hour 513.00 Equipment Rate
P&M-66001 Boat to carry atleast 20 persons hour 888.00
P&M-67001 Crane with grab 0.75 cum capacity hour 980.00
P&M-68001 Epoxy Injection gun hour 339.00
Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic
P&M-69001 hour 9444.00
method of well sinking.
P&M-70001 Jack for Lifting 40 tonne lifting capacity. hour 339.00
P&M-71001 Vibrating Pile driving hammer complete with power unit and accessories. hour 17223.00
P&M-72001 Tipper-18 Cum (Surface Road) excluding OH & CP 275 Per Tonne Km. 5.62
P&M-72002 Tipper-18 Cum (Unsurfaced Gravelled Road) excluding OH & CP 275 Per Tonne Km. 6.830
P&M-72003 Tipper-18 Cum (Katcha Track) excluding OH & CP 275 Per Tonne Km. 13.66
P&M-73001 Tipper -14 Cum (Surface Road) excluding OH & CP 220 Per Tonne Km. 6.40
P&M-73002 Tipper -14 Cum (Unsurfaced Gravelled Road) excluding OH & CP 220 Per Tonne Km. 7.77
P&M-73003 Tipper -14 Cum (Katcha Track) excluding OH & CP 220 Per Tonne Km. 15.54
P&M-74001 Tipper -10 Cum (Surface Road) excluding OH & CP 178 Per Tonne Km. 7.92
P&M-74002 Tipper -10 Cum (Unsurfaced Gravelled Road) excluding OH & CP 178 Per Tonne Km. 9.62
P&M-74003 Tipper -10 Cum (Katcha Track) excluding OH & CP 178 Per Tonne Km. 19.24
P&M-75001 Tipper- 5.5 Cum (Surface Road) excluding OH & CP 90 Per Tonne Km. 10.91
P&M-75002 Tipper- 5.5 Cum (Unsurfaced Gravelled Road) excluding OH & CP 90 Per Tonne Km. 13.25
P&M-75003 Tipper- 5.5 Cum (Katcha Track) excluding OH & CP 90 Per Tonne Km. 26.50
P&M-76001 Transit Mixer - 6 Cum excluding OH & CP Per Tonne Km. 12.22
Loading and unloading of stone boulder / stone aggregates / sand / kanker / moorum (Using by 18 cum capacity
P&M-77001 Tipper & 3.1 Cum capacity Loader) excluding OH & CP Cum 84.60
Loading and unloading of stone boulder / stone aggregates / sand / kanker / moorum (Using by 14 cum capacity
P&M-77002 Tipper & 2.1 Cum capacity Loader) excluding OH & CP Cum 84.52
Loading and unloading of stone boulder / stone aggregates / sand / kanker / moorum (Using by 10 cum capacity
P&M-77003 Tipper & 1.0 Cum capacity Loader) excluding OH & CP Cum 117.86
Loading and unloading of stone boulder / stone aggregates / sand / kanker / moorum (Using by 5 cum capacity
P&M-77004 Tipper & 1.0 Cum capacity Loader) excluding OH & CP Cum 133.16
P&M-77005 Loading and Unloading of Cement or Steel by Manual Means and Stacking tonne 532.38
P&M-78001 Centrifugal water pump Hour 344.00
P&M-79001 Shredding Machine Hour 500.00
Page 2 of 253
(B) Labour
(C) Materials
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 350.00
Including Carriage -
M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 470.14
( L7) - 4 Km.
Including Carriage -
M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 420.14
( L7) - 4 Km.
Including Carriage -
M-004 Coarse sand at Mixing Plant cum 955.78
( L6) - 2 Km.
Including Carriage -
M-005 Coarse sand at Site cum 955.78
( L5) - 2 Km.
Including Carriage -
M-006 Fine sand at Site cum 805.78
( L5) - 2 Km.
Including Carriage -
M-007 Moorum at Site cum 405.78
( L3) - 2 Km.
Including Carriage -
M-008 Gravel/Quarry spall at Site Cum 302.41
( L7) - 4 Km.
Including Carriage -
M-009 Granular Material or hard murrum for GSB works at Site Cum 725.78
( L3) - 2 Km.
Including Carriage -
M-010 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant Cum 153.28
( L4) - 2 Km.
Including Carriage -
M-011 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) at Site Cum 716.17
( L7) - 4 Km.
Rate at Plant
Description Unit Rate at Site
(HMP/Batching)
M-012 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 903.49 920.35
M-013 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 903.49 920.35
M-014 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 906.19 923.05
M-015 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 843.90 860.76
M-016 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 564.72 581.58
M-017 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 285.55 302.41
Page 3 of 253
M-018 Close graded Granular sub-base Material 4.75mm to 75 micron mm cum 285.55 302.41
M-019 Close graded Granular sub-base Material 2.36 mm cum 285.55 302.41
M-020 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 285.55 302.41
M-021 Coarse graded Granular sub-base Material 2.36 mm & below cum 285.55 302.41
M-022 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm cum 285.55 302.41
M-023 Granular sub-base Material 4.75 mm to 2.36 mm cum 285.55 302.41
M-024 Granular sub-base Material 9.5 mm to 4.75 mm cum 843.90 860.76
M-025 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 906.19 923.05
M-026 Granular sub-base Material 26.5 mm to 9.5 mm cum 906.19 923.05
M-027 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 903.49 920.35
M-028 Granular sub-base Material 53 mm to 26 .5mm cum 903.49 920.35
M-029 Aggregates below 5.6 mm cum 285.55 302.41
M-030 Aggregates 22.4 mm to 2.36 mm cum 699.31 716.17
M-031 Aggregates 22.4 mm to 5.6 mm cum 699.31 716.17
M-032 Aggregates 45 mm to 2.8 mm cum 749.00 765.86
M-033 Aggregates 45 mm to 22.4 mm cum 749.00 765.86
M-034 Aggregates 53 mm to 2.8 mm cum 749.00 765.86
M-035 Aggregates 53 mm to 22.4 mm cum 933.29 950.15
M-036 Aggregates 63 mm to 2.8 mm cum 749.00 765.86
M-037 Aggregates 63 mm to 45 mm cum 898.08 914.94
M-038 Aggregates 90 mm to 45 mm cum 898.08 914.94
M-039 Aggregates 10 mm to 5 mm cum 564.72 581.58
M-040 Aggregates 11.2 mm to 0.09 mm cum 564.72 581.58
M-041 Aggregates 13.2 mm to 0.09 mm cum 564.72 581.58
M-042 Aggregates 13.2 mm to 5.6 mm cum 843.90 860.76
M-043 Aggregates 13.2 mm to 10 mm cum 843.90 860.76
M-044 Aggregates 20 mm to 10 mm cum 906.19 923.05
M-045 Aggregates 25 mm to 10 mm cum 906.19 923.05
M-046 Aggregates 19 mm to 6 mm cum 906.19 923.05
M-047 Aggregates 37.5 mm to 19 mm cum 933.29 950.15
M-048 Aggregates 37.5 mm to 25 mm cum 933.29 950.15
M-049 Aggregates 6 mm nominal size cum 843.90 860.76
M-050 Aggregates 10 mm nominal size cum 843.90 860.76
M-051 Aggregates 13.2/12.5 mm nominal size cum 843.90 860.76
M-052 Aggregates 20 mm nominal size cum 968.49 985.35
M-053 Aggregates 25 mm nominal size cum 968.49 985.35
M-054 Aggregates 40 mm nominal size cum 898.08 914.94
M-055 Crushing of stone aggregates (GSB Crusher Run) cum 584.36 601.22
Sl. No. Description Unit Rate at Site
Including Carriage -
M-074 Bitumen (60-70 grade) tonne 34512.45
( L9) - 2 Km.
Including Carriage -
M-075 Bitumen (80-100 grade ) tonne 35012.45
( L9) - 2 Km.
Including Carriage -
M-076 Bitumen (Cutback ) tonne 35012.45
( L9) - 2 Km.
Including Carriage -
M-077 Bitumen (emulsion) tonne 35012.45
( L9) - 2 Km.
Including Carriage -
M-078 Bitumen (modified graded) tonne 35012.45
( L9) - 2 Km.
Page 4 of 253
M-084 Coller for joints 300 mm dia nos 180.00
M-085 Compressible Fibre Board(20mm thick) sqm 115.00
M-086 Connectors/ Staples each 55.00
M-087 Copper Plate(12m long x 250mmwide) kg 620.00
M-088 Corrosion resistant Structural steel tonne 75000.00
M-089 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg 65.00
M-090 Credit for excavated rock found suitable for use cum 350.00
M-091 Curing compound liter 60.00
M-092 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 210.00
M-093 Earth Cost or compensation for earth taken from private land cum 45.00
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause 915.1 of IRC:
M-094 metre 16500.00
83 (part II),
M-095 Epoxy compound with accessories for preparing epoxy mortar kg 600.00
M-096 Epoxy mortar kg 400.00
M-097 Epoxy primer kg 155.00
M-098 Epoxy resin-hardner mix for prime coat kg 250.00
M-099 Flag of red color cloth 600 x 600 mm each 30.00
M-100 Flowering Plants each 30.00
M-101 Galvanised MS flat clamp nos 10.00
M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 210.00
M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 95.00
M-104 Geo grids sqm 190.00
M-105 Geomembrane sqm 110.00
M-106 Geonets sqm 135.00
M-107 Geotextile sqm 145.00
M-108 Geotextile filter fabric sqm 105.00
M-109 GI bolt 10 mm Dia nos 25.00
M-110 Grouting pump with agitator hour 300.00
M-111 Grass (Doob) kg 3.50
M-112 Grass (Fine) kg 21.00
M-113 HDPE pipes 75mm dia metre 120.00
M-114 HDPE pipes 90mm dia metre 150.00
M-115 Hedge plants each 5.00
M-116 Helical pipes 600mm diameter metre 140.00
M-117 Hot applied thermoplastic compound litre 160.00
Including Carriage -
M-118 HTS strand tonne 78525.27
( L10) - 2 Km.
Page 5 of 253
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips) metre 150.00
M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 180.00
M-158 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 190.00
M-159 Rivets each 1.50
M-160 Sand bags (Cost of sand and Empty cement bag) nos 28.00
M-161 Sapling 2 m high 25 mm dia each 55.00
M-162 Scrap tyres of size 900 x 20 nos 60.00
M-163 Seeds kg 12.00
M-164 Selected earth cum 75.00
M-165 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 15.00
M-166 Sheathing duct metre 60.00
M-167 Shrubs each 22.00
M-168 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 150.00
M-169 Sodium vapour lamp each 7800.00
M-170 Square Rubble Coursed Stone cum 470.14
M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each 35000.00
M-172 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each 62500.00
M-173 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 110.00
M-174 Steel helmet and cushion block on top of pile head during driving. kg 70.00
M-175 Steel pipe 25 mm external dia as per IS:1239 metre 130.00
M-176 Steel pipe 50 mm external dia as per IS:1239 metre 220.00
M-177 Steel pipe 100 mm external dia as per IS:1239 metre 380.00
M-178 Steel wire rope 20 mm kg 55.00
M-179 Steel wire rope 40 mm kg 90.00
M-180 Strip seal expansion join metre 15200.00
M-181 Structural Steel tonne 65000.00
M-182 Super plastisizer admixture IS marked as per 9103-1999 kg 25.00
M-183 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 150.00
M-184 Through and bond stone each 25.00
M-185 Tie rods 20mm diameter nos 65.00
M-186 Tiles size 300 x 300 mm and 25 mm thick each 12.00
M-187 Timber cum 650.00
M-188 Traffic cones with 150 mm reflective sleeve nos 450.00
M-189 Tube anchorage set complete with bearing plate, permanent wedges etc nos 27.00
M-190 Unstaked lime tonne 6500.00
M-191 Water KL 74.54
M-192 Water based cement paint litre 120.00
M-193 Welded steel wire fabric kg 75.00
M-194 Wire mesh 50mm x 50mm size of 3mm wire kg 75.00
M-195 Wooden ballies 2" Dia for bracing each 5.00
M-196 Wooden ballies 8" Dia and 9 m long each 150.00
M-197 Wooden packing cum 2000.00
M-198 Wooden staff for fastening of flag 25 mm dia, one m long each 12.00
M-199 Silica Fume Kg 20.00
M-200 Synthetic Geogrid Ultimate tensile strength- 100 kN/m sqm 200.00
M-201 Synthetic Geogrid Ultimate tensile strength- 150 kN/m sqm 220.00
M-202 Synthetic Geogrid Ultimate tensile strength- 200 kN/m sqm 300.00
M-203 Synthetic Geogrid Ultimate tensile strength- 250 kN/m sqm 330.00
M-204 Synthetic Geogrid Ultimate tensile strength- 300 kN/m sqm 350.00
M-205 Synthetic Geogrid Ultimate tensile strength- 350 kN/m sqm 390.00
M-206 Synthetic Geogrid Ultimate tensile strength- 400 kN/m sqm 420.00
M-207 Synthetic Geogrid Ultimate tensile strength- 500 kN/m sqm 500.00
M-208 Synthetic Geogrid Ultimate tensile strength- 600 kN/m sqm 550.00
M-209 Synthetic Geogrid Ultimate tensile strength- 700 kN/m sqm 708.00
M-210 Synthetic Geogrid Ultimate tensile strength- 800 kN/m sqm 841.00
M-211 Synthetic Geogrid Ultimate tensile strength- 900 kN/m sqm 950.00
M-212 Synthetic Geogrid Ultimate tensile strength- 1000 kN/m sqm 1000.00
M-213 Synthetic Geogrid Ultimate tensile strength- 1100 kN/m sqm 1088.00
M-214 Synthetic Geogrid Ultimate tensile strength- 1200 kN/m sqm 1150.00
M-215 Explosives for blasting Kg 55.00
M-216 Delay Detonators for Nos. 55.00
M-217 Electric Detonators Nos. 12.00
M-218 Detonation fuse coil Meter 105.00
M-219 3.7 m long extension rod boom Hydraulic Drill Jumbo Nos 350.00
M-220 32 mm coupling sleeve boom Hydraulic Drill Jumbo Nos 950.00
M-221 Difter rod boom Hydraulic Drill Jumbo Nos 650.00
M-222 R32 shank adapter boom Hydraulic Drill Jumbo Nos 1050.00
M-223 45 mm dia Button Bit boom Hydraulic Drill Jumbo Nos 150.00
M-224 51 mm dia button bit boom Hydraulic Drill Jumbo Nos 250.00
M-225 Steel Fiber tonne 58500.00
M-226 Microsilica Kg 25.00
M-227 Accelerator Kg 30.00
M-228 Wiremesh Kg 75.00
M-229 Bamboos Meter 25.00
M-230 Live Stake Stump Meter 25.00
M-231 Hard wood sticks Nos. 20.00
M-232 Live Sods (0.6m Length) Nos. 10.00
Page 6 of 253
M-233 Live Sods ( 2m Length) tonne 25.00
M-234 Coal Tar Epoxy Kg. 220.00
M-235 Binding Material Meter 5.00
M-236 Spring post 700 mm each 610.00
M-237 Spring post 450 mm each 490.00
M-238 Water Filled Barricades Work zone sheeting (Trapezoidal Shape 800 mm to 1000 mm in length, 700 mm in height) each 3200.00
M-239 GI Pipe 100 mm Dia Meter 340.00
M-240 Bracket for GI pipe fixing Kg 55.00
M-241 Flange for GI pipe fixing Kg 55.00
M-242 Neem Cake Quintal 25.00
M-243 Supplying Sludge cum 115.00
M-244 Control Centre Server Nos. 840000.00
M-245 Hot Standby Backup Server Nos. 840000.00
M-246 NAS Video Server with storage Minimum 70 TB Nos. 1080000.00
M-247 Backup Video (Only Incidents) Server Nos. 840000.00
M-248 Graphic Display (70" LED DLP in 3x2 matrix) Set 2400000.00
M-249 Graphic Display Controller and software including Video Switches Set 1160000.00
M-250 CCTV Monitoring Workstation Nos. 68000.00
M-251 Emergency Telephone (1033) console Nos. 180000.00
M-252 VIDS- Workstation Nos. 68000.00
M-253 Administrative Workstation Nos. 44000.00
M-254 ATMS Operator Workstation Nos. 44000.00
M-255 CCTV Joystick Nos. 76000.00
M-256 Operations Laser Printer (Colour) Nos. 108000.00
M-257 Operations Laser Printer (Black) Nos. 76000.00
M-258 Rack 19" Nos. 46400.00
M-259 ATMS Control Room Software (integrated with VIDS, ATCC, VMS, MOS) LS 1200000.00
M-260 Video Management Software with atleast 150 VMS Lic. LS 780000.00
M-261 Facility Monitoring System Controller Software LS 440000.00
M-262 Server & Database license LS 800000.00
M-263 Antivirus license LS 160000.00
M-264 PTZ Camera (including CCTV Controller) Set 96000.00
M-265 Solar System with UPS, battery & 12m Pole & Cabinet Set 68000.00
M-266 VIDS Camera (including Image Processing unit) Set 132000.00
M-267 Warning amber lights with hooters, 72 Hrs solar backup, 5m poles and foundation Set 91200.00
M-268 Cabinet Nos. 22800.00
M-269 12 m Pole (including manufacturing and galvanizing) Nos. 20160.00
M-270 Solar System with UPS & batteries Set 18000.00
M-271 Equipment, Sensor unit, Processing unit, Solar power supply and civil works for 4 Lanes Set 660000.00
M-272 Solar System with UPS, batteries Set 74880.00
M-273 VMS (Variable Message Sign - M type) Nos. 920000.00
M-274 Gantry (including manufacturing and galvanizing) Nos. 760000.00
M-275 Solar System with UPS, battery and cabinet for M type VMS Set 312000.00
M-276 Uninterruptible Power Supply (UPS) For Server Rack (10 KVA) Set 520000.00
M-277 Uninterruptible Power Supply (UPS) For TMC (30 KVA) Set 1160000.00
M-278 Power Distribution Board (Essential & Critical Supply) Set 44000.00
M-279 MOS sensor Equipment (including MOS Controller) Set 848000.00
M-280 Cabinet Nos. 22800.00
M-281 Pole Nos. 25600.00
M-282 Steel fence for protection Set 60000.00
M-283 24 Core Armoured OFC + all accessories Meter 384.00
M-284 40 mm PLB HDPE duct as per latest TSEC specifications + all accessories Meter 456.00
M-285 Trenching of 1.8 meters, Laying & Backfilling for PLB HDPE duct Meter 160.00
M-286 Bi-Axial Extruded GeoGrids of Minimum Tensile Strength 15 kN/m sqm 95.00
M-287 Bi-Axial Extruded GeoGrids of Minimum Tensile Strength 20 kN/m sqm 109.00
M-288 Bi-Axial Extruded GeoGrids of Minimum Tensile Strength 30 kN/m sqm 178.00
M-289 Bi-Axial Extruded GeoGrids of Minimum Tensile Strength 40 kN/m sqm 260.00
M-290 Geosynthetic Drainage Composite ( tensile strength of 18 kN/m) sqm 504.00
M-291 Geosynthetic Drainage Composite (tensile strength of 13.5 kN/ m) sqm 600.00
L3 Lead for Moorum/ Natural Granular material borrow area to site 2 1 1 Included
Page 7 of 253
L7 Lead for Aggregate from Quarry to working site 4 1 3 Included
Page 8 of 253
Overheads for Road Works 8% 10% 12%
Page 9 of 253
Summary of Rate Analysis
Rate As Per Proposed Data Book
CHAPTER-1
CARRIAGE OF MATERIALS
Loading and unloading of stone boulder / stone aggregates / sand / kanker / moorum. (Placing tipper at loading
1.1 point, loading with front end loader, dumping, turning for return trip, excluding time for haulage and return trip)
Crushing of stone aggregates 10 mm nominal size. (Crushing of stone boulders of 150 mm size in an integrated
1.6 stone crushing unit of 250 tonnes per hour capacity comprising of primary and secondary crushing units, belt cum 879.90 879.90 879.90
conveyor and vibrating screens to obtain stone aggregates of different nominal size
Crushing of stone aggregates 20 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated
1.7 stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt cum 1027.90 1027.90 1027.90
conveyor and vibrating screens to obtain stone aggregates of 20 mm nominal size.)
Crushing of stone aggregates 40 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated
1.8 stone crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt cum 944.20 944.20 944.20
conveyor and vibrating screens to obtain stone aggregates of 40 mm nominal size.)
Crushing of stone aggregates Dust (Crushing of stone boulders of 150 mm size in an integrated stone crushing
1.9 unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and cum 216.50 216.50 216.50
vibrating screens to obtain stone aggregates of .)
Crushing of stone boulders of 150 mm size in an integrated stone crushing unit of 250 tonnes per hour capacity
1.10 comprising of primary and secondary crushing units, belt conveyor and vibrating screens to obtain crusher run cum 571.50 571.50 571.50
(all in aggregate) for GSB.
CHAPTER-2
SITE CLEARANCE
Cutting of trees, excluding removal of stumps and roots of trees (Cutting of trees, trunks and branches
2.1 (A) excluding removal of stumps and roots of trees and stacking of serviceable material with all lifts and up to a lead
of 1000 mtrs )
(i) Girth from 300 mm to 600 mm each 545.60 569.90 607.30
(ii) Girth from 600 mm to 900 mm each 590.50 623.50 731.10
(iii) Girth from 900 mm to 1800 mm each 974.50 1011.00 1109.60
(iv) Girth above 1800 mm each 1533.30 1605.80 1775.40
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Removal of stumps, roots, stacking of
2.1 (B) serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit.)
Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of dismantled material with all
2.8 metre 24.20 24.70 25.10
lifts and up to a lead of 1000 metre)
Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means and disposal of dismantled
2.9 metre 32.60 33.20 33.80
material with all lifts and up to a lead of 1000 metre)
Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of earth, foundation and disposal
2.10
of dismantled material with all lifts and lead upto 1000 m and back filling of pit.)
A 5th KM stone each 741.10 754.90 768.60
B Ordinary KM Stone each 444.80 453.10 461.30
C Hectometre Stone each 89.00 90.60 92.30
Summary of Rate Analysis
Rate As Per Proposed Data Book
Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation
concrete, back filling of pit by manual means including disposal of dismantled material with all lifts and up to a
2.11 lead of 1000 metres, stacking serviceable material and unserviceable material separately. ) metre 93.60 95.30 97.00
Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including disposal with all lifts
2.12 and lead upto 1000 metres and stacking of serviceable material and unserviceable material separately under metre 262.80 267.60 272.50
supervision of concerned department)
Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of sewer gutter 1500 mm
dia under the supervision of concerned department including disposal with all lifts and up to a lead of 1000
2.13 metres and stacking of serviceable and unserviceable material separately but excluding earth excavation and metre 398.50 405.90 413.20
dismantling of masonry works.)
Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles including excavation
and dismantling of foundation concrete and lines under the supervision of concerned department, disposal with
2.14 all lifts and up to a lead of 1000 metres and stacking the serviceable and unserviceable material separately) each 331.60 337.70 343.80
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means including loading in
3.1 truck for carrying of cut earth to embankment site with all lifts and lead upto1000 metres.) cum 406.00 413.50 421.00
Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual means including
3.2 loading in a truck and carrying of excavated material to embankment site with in all lifts and leads upto 1000 cum 550.70 560.90 571.10
metres )
Excavation in Soil with Dozer with lead upto 1000 metres (EExcavation for road way in soil by mechanical
means including cutting and transporting the earth to site of embankment/dumping area with lead upto 1000
3.3 metres, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross cum 141.50 145.90 192.50
sections.)
Excavation in Ordinary Rock with Dozer with lead upto 1000 metres (Excavation for roadway in ordinary rock by
deploying a dozer, including cutting and transporting the earth to site of embankment/dumping area with lead
3.4 upto 1000 metres, trimming bottom and side slopes in accordance with the requirements of lines, grades and cum 198.20 204.10 260.80
cross sections.)
Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for roadway in hard
rock (requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance
3.5 with requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads cum 380.70 389.50 448.30
upto 1000 metres )
Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 metres. (Excavation for
roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side
3.6 slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the cum 72.40 87.00 123.20
embankment location within all lifts and lead upto 1000m)
Excavation in Ordinary Rock using Hydraulic Excavator and Tippers with disposal upto 1000 metres.
(Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom
3.7 and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the cum 418.50 477.00 707.40
embankment location within all lifts and lead upto 1000m.)
Excavation in Hard Rock (blasting prohibited) (Excavation for roadwork in Hard Rock (blasting prohibited) with
hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with
3.8 requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and
lead upto 1000 m.)
A Mechanised cum 339.00 418.70 775.00
B Manual Method cum 1974.40 2011.00 2047.50
Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres (EExcavation for roadway in hard
rock (requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance
3.9 with requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads cum 836.30 846.50 923.50
upto 1000 metres )
Excavation in Marshy Soil (Excavation for roadwork in Marshy Soil with hydraulic excavator including cutting and
loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross
3.10 sections, and transporting to the embankment location within all lifts and lead upto 1000 m.) cum 150.20 165.00 261.30
Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil including
3.11 excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall cum 73.50 81.10 125.40
be paid separately as per clause 305..)
Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a specified slope of the
rock face by controlled use of explosives and blasting accessories in properly aligned and spaced drill holes,
3.12 collection of the excavated rock by a dozer, loading in tipper by a front end loader and disposing of the material sqm 111.70 112.60 132.00
with all lifts and lead upto 1000 m, all as specified in clause No. 303)
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical
specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious
3.13 matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the
remaining earth locally for road work.)
(i) Ordinary soil
A Manual Means (Depth upto 3 m) cum 555.90 566.20 576.50
B Mechanical Means (Depth upto 3 m) cum 68.30 75.20 119.20
(ii) Ordinary rock (not requiring blasting)
A Manual Means (Depth upto 3 m) cum 694.80 707.70 720.60
B Mechanical Means cum 405.30 471.40 726.70
(iii) Hard rock ( requiring blasting )
Summary of Rate Analysis
Rate As Per Proposed Data Book
Scarifying existing bituminous surface to a depth of 50 mm by mechanical means ( using Hydraulic excavator)
(ii) (Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all sqm 4.70 5.10 7.90
lifts and lead upto 1000 metres.)
Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Using Motor Grader)
(iii) (Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all sqm 7.60 8.00 9.10
lifts and lead upto 1000 metres.)
3.15 Scarifying Existing bituminous surface to a depth of 50 mm
Scarifying existing bituminous surface to a depth of 50 mm by mechanical means Hydraulic excavator
(i) (Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all sqm 5.50 6.10 9.50
lifts and lead upto 1000 metres.)
Scarifying existing bituminous surface to a depth of 50 mm by mechanical means using Motor Grader (Scarifying
(ii) the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and sqm 7.70 8.10 9.30
lead upto 1000 metres.)
Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with approved
3.16 material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required cum 199.50 215.70 242.90
slope and compacting to meet requirement of table 300-2)
Construction of Embankment with Material Deposited from Roadway Cutting (Construction of embankment with
3.17 approved materials deposited at site from roadway cutting and excavation from drain and foundation of other cum 60.30 65.90 44.60
structures graded and compacted to meet requirement of table 300-2)
Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen shoulders with
3.18 approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to cum 203.00 219.80 248.00
required slope and compacted to meet requirement of table No. 300-2)
Construction of Subgrade and Earthen Shoulders with Material Deposited from Roadway Cutting(Construction of
embankment with approved materials deposited at site from roadway cutting and excavation from drain and
3.19 foundation of other structures graded and compacted to meet requirement of table 300-2.) cum 61.40 67.10 46.10
Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass on embankment slope,
3.23 verges or other locations shown on the drawing or as directed by the engineer including preparation of ground, sqm 59.20 63.30 75.60
fetching of rods and watering)
Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing and placing of seeds,
3.24 fertilizer, mulching material, applying bituminous emulsion at the rate of0.23 litres per sqm and laying and fixing sqm 157.20 170.00 209.70
jute netting, including watering for 3 months all as per clause 308)
Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to
3.25 specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to
be used in embankment within a lead of50 metres (average lead 25 metres))
A Mechanical means metre 68.90 70.20 71.40
B Manual Means metre 219.10 223.10 227.20
Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross sectional area 0.4 sqm
3.26 in ordinary rock to specified lines, grades, levels and dimensions as per approved design and to the requirement
of clause 301 to 309. Excavated material to be used in embankment at site.)
A Mechanical Means metre 94.80 96.60 98.30
B Manual Means metre 310.20 315.90 321.70
Surface Drains in Hard Rock (Rate per metre may be worked out based on quantity of hard rock as per design.)
3.27 metre
Sub Surface Drains with Perforated Pipe (Construction of subsurface drain with perforated pipe of 100 mm
internal diameter of metal/ asbestos cement/ cement concrete/PVC, closely jointed, perforations ranging from 3
3.28 mm to 6 mm depending upon size of material surrounding the pipe, with 150 mm bedding below the pipe and 1765.80 1798.50 1831.20
300 mm cushion above the pipe, cross section of excavation 450 x 550 mm. Excavated material to be utilised in
roadway at site )
Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm with
3.29 metre 216.10 220.10 224.10
aggregates conforming to table 300-4, excavated material to be utilised in roadway )
Underground Drain at Edge of Pavement (Construction of an underground drain 1 m x 1 m (inside dimensions)
3.30 metre 5050.66 5050.66 5050.66
lined with RCC-20 cm thick and covered with RCC slab10 cm in thickness on urban roads)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Preparation and Surface Treatment of formation. (Preparation and surface treatment of formation by removing
mud and slurry, watering to the extent needed to maintain the desired moisture content, trimming to the required
3.31 line, grade, profile and rolling with 8-10 tonne smooth wheeled roller, complete as per clause 310.) sqm 4.40 4.50 4.90
Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard rock requiring
3.32 blasting, by mechanical means including trimming of slopes and disposal of cut material with all lifts and lead cum 111.30 120.10 143.90
upto 1000 metres.)
Work in Urban Roads (The cost of earth work in urban roads inhabited area will be comparatively higher due to
3.33
following reasons:)
Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal Plants as waste
material. (Construction of embankment with fly ash conforming to table 1 of IRC: SP: 58 obtained from coal or
3.34 lignite burning thermal power stations as waste material, spread and compacted in layer of 200mm thickness cum 89.10 96.80 84.20
each at OMC, all as specified in IRC: SP: 58 and as per approved plans.)
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical
A mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on
prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per
clause 401 )
(i) for grading- I Material cum 1351.21 1372.47 1508.73
(ii) for grading- II Material cum 1225.84 1244.78 1378.72
(iii) for grading-III Material cum 1548.92 1573.84 1713.76
(iv) for grading-IV Material cum 1500.29 1524.31 1663.33
(v) for grading-V Material cum 1373.53 1395.21 1531.88
(vi) for grading-VI Material cum 1314.59 1335.18 1470.76
By Mix in Place Method (Construction of granular sub-base by providing close graded material, spreading in
B uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and
compacting with vibratory roller to achieve the desired density, complete as per clause 401)
(i) for grading- I Material cum 1259.29 1258.59 1255.78
(ii) for grading- II Material cum 1133.92 1154.20 1172.28
(iii) for grading-III Material cum 1457.00 1483.26 1507.32
(iv) for grading-IV Material cum 1408.37 1433.73 1456.89
(v) for grading-V Material cum 1281.62 1304.63 1325.44
(vi) for grading-VI Material cum 1206.35 1244.60 1264.32
Using Crusher Run Method (Construction of granular sub-base by providing close graded material, spreading in
C uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and
compacting with vibratory roller to achieve the desired density, complete as per clause 401)
(i) for grading- I Material cum 1146.44 1183.24 1211.98
(ii) for grading- II Material cum 1146.44 1183.24 1211.98
(iii) for grading-III Material cum 1146.44 1183.24 1211.98
(iv) for grading-IV Material cum 1146.44 1183.24 1211.98
(v) for grading-V Material cum 1146.44 1183.24 1211.98
(vi) for grading-VI Material cum 1146.44 1167.67 1188.90
4.2 Lime Stabilisation for Improving Subgrade
A By Manual Means
Laying and spreading available soil in the subgrade on a prepared surface, pulverising, mixing the spread soil
in place with rotavator with 3 % slaked lime having minimum content of 70% of CaO, grading with motor
grader and compacting with the road roller at OMC to the desired density to form a layer of improved sub 743.00 553.11 581.09 607.71
grade)
B By Mechanical Means
Laying and spreading available soil in the sub-grade on a prepared surface, pulverising, mixing the spread soil
in place with Soil Stabilizer & Binder Spreader with 2 per cent slaked lime using Binder spreader Machine,
(i) having minimum content of 70 per cent of CaO, grading with motor grader and compacting with the road roller cum 879.44 913.46 946.12
at OMC to the desired density to form a layer of improved sub grade
Laying and spreading available soil in the sub-grade on a prepared surface, pulverising, mixing the spread soil
in place with Soil Stabilizer with 2 per cent slaked lime mannualy spreaded having minimum content of 70
(ii) per cent of CaO, grading with motor grader and compacting with the road roller at OMC to the desired density cum 814.48 847.30 878.76
to form a layer of improved sub grade
4.3 Cement Stabilisation for Improving Subgrade
A By Manual Means
Laying and spreading available soil in the sub-grade on a prepared surface, pulverising, mixing the spread soil
in place with Soil Stabilizer & Binder Spreader with 2 per cent cement using Binder spreader Machine,
grading with motor grader and compacting with the road roller at OMC to the desired density to form a layer of cum 553.11 581.09 607.71
improved sub grade
B By Mechanical Means
Laying and spreading available soil in the sub-grade on a prepared surface, pulverising, mixing the spread soil
in place with Soil Stabilizer & Binder Spreader with 2 per cent cement using Binder spreader Machine,
(i) grading with motor grader and compacting with the road roller at OMC to the desired density to form a layer of cum 879.44 913.46 946.12
improved sub grade
Summary of Rate Analysis
Rate As Per Proposed Data Book
Laying and spreading available soil in the sub-grade on a prepared surface, pulverising, mixing the spread soil
in place with Soil Stabilizer with 2 per cent cement mannualy spreaded, grading with motor grader and
(ii) compacting with the road roller at OMC to the desired density to form a layer of improved sub grade cum 814.48 847.30 878.76
Laying and spreading available soil in the emabankment n a prepared surface, pulverising, mixing the spread
soil in place with Soil Stabilizer with 2 per cent slaked lime mannualy spreaded having minimum content of
(ii) 70 per cent of CaO, grading with motor grader and compacting with the road roller at OMC to the desired cum 762.50 793.31 820.90
density to form a layer of improved sub grade
Laying and spreading available soil in the emabankment n a prepared surface, pulverising, mixing the spread
soil in place with Soil Stabilizer & Binder Spreader with 2 per cent cement using Binder spreader Machine,
(iii) grading with motor grader and compacting with the road roller at OMC to the desired density to form a layer of cum 827.46 859.48 888.27
improved sub grade
Laying and spreading available soil in the emabankment on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per cent cement mannualy spreaded, grading with motor grader
(iv) and compacting with the road roller at OMC to the desired density to form a layer of improved sub grade cum 762.50 793.31 820.90
Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared sub grade, pulverising,
mixing the spread soil in place with rotavator with 3 % slaked lime with minimum content of 70% of CaO, grading
4.5 with motor grader and compacting with the road roller at OMC to achieve at least 98%of the max dry density to cum 751.09 787.34 864.00
form a layer of sub base.)
Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a prepared sub grade,
pulverising, adding the designed quantity of cement to the spread soil, mixing in place with rotavator, grading
4.6 with the motor grader and compacting with the road roller at OMC to achieve the desired unconfined cum 878.70 916.04 990.28
compressive strength and to form a layer of sub-base/base.)
Cement Treated Crushed Rock or combination as per clause 403 and table 400.4 in Sub base/ Base (Providing,
laying and spreading Material on a prepared sub grade, adding the designed quantity of cement to the spread
4.7 Material, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at
OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base/base.)
(i) For Sub-Base course cum 1896.07 1939.41 1940.29
(ii) For Base course cum 1557.29 1594.35 1588.97
Cement Treated Crushed Stone Sub base (Construction of granular sub-base by providing graded Material,
mixing with cement in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in
4.8 uniform layers with Mechanical Paver on prepared surface and compacting with vibratory power roller to achieve
the desired density, complete as per clause 401 )
(c) Using Screening Type-B (11.2mm Agg.) cum 2165.32 2209.85 2266.58
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 2215.92 2261.39 2319.05
(b) Using Screening Type-B (11.2mm Agg.) cum 2111.90 2155.44 2211.17
B By Mechanical Means:
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1982.01 2044.35 2112.60
(b) Using Screening Type-A (13.2mm Agg.) cum 1749.36 1783.98 1824.50
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1747.78 1782.75 1823.62
(b) Using Screening Type-A (13.2mm Agg.) cum 1746.13 1780.49 1821.15
(c) Using Screening Type-B (11.2mm Agg.) cum 1850.16 1886.64 1929.03
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 1900.76 1938.19 1981.51
(b) Using Screening Type-B (11.2mm Agg.) cum 1796.74 1832.23 1873.63
Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material obtained by breaking damaged
cement concrete slabs to size range not exceeding 75 mm as specified in table 400.9 transporting the
4.12 aggregates obtained from breaking of cement concrete slabs at a lead of L km., laying and compacting the same cum 397.67 419.24 431.85
as sub base/ base course, constructed as WBM to clause 404 except the use of screening or binding Material.)
Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen over cleaned dry
surface of crushed cement concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure distributor,
4.13 spreading of key aggregates at the rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface sqm 23.19 23.62 24.05
as per clause 506.3.8)
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
5.1 Prime coat
A Prime Coat over WMM/WBM
Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing
(i) of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means sqm 36.90 37.62 38.41
Providing and applying primer coat with cutback MC 30 bitumen emulsion on prepared surface of granular Base
(ii) including clearing of road surface and spraying primer at the rate of 0.60 to 0.90 kg/sqm using mechanical means. sqm 32.74 33.38 34.10
Providing and applying primer coat with SS1 grade bitumen emulsion on prepared surface of granular Base
(i) including clearing of road surface and spraying primer at the rate of 0.90 to 1.20 kg/sqm using mechanical means. sqm 45.22 46.09 47.04
Providing and applying primer coat with cutback MC 70 bitumen emulsion on prepared surface of granular Base
(ii) including clearing of road surface and spraying primer at the rate of 0.90 to 1.20 kg/sqm using mechanical means. sqm 45.22 46.09 47.04
Tack Coat on Cement concrete pavement (Providing and applying tack coat with bitumen emulsion using
(iii) emulsion pressure distributor at the rate of 0.30 to 0.35 kg per sqm on the prepared bituminous surface cleaned sqm 14.76 15.03 15.31
with mechanical broom.)
Dense Graded Bituminous Macadam-II (Providing and laying dense graded bituminous macadam with higher
capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5
per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver
(ii) finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and cum 6493.70 6629.10 6851.50
tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all
respects.)
Bituminous Concrete Grading -II (Providing and laying bituminous concrete with higher capacity batch type hot
mix plant using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 per cent of
(ii) mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to cum 7612.03 7777.31 8037.99
the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the
desired compaction as per MORTH specification clause No. 507 complete in all respects)
Surface Dressing (Providing and laying surface dressing as wearing course in single coat using crushed stone
5.6 aggregates of specified size on a layer of bituminous binder laid on prepared surface and rolling with 8-10 tonne
smooth wheeled steel roller)
Case -1 :-19 mm nominal chipping size sqm 77.29 78.54 80.32
Case - II 13 mm nominal size chipping sqm 60.29 61.19 62.45
Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded premix surfacing of 20 mm
thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or
5.7 emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including sqm 107.60 109.92 113.93
mixing in a suitable plant HMP, laying and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to
required level and grades.)
Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of appropriate capacity
not less than 75 tonnes/hour. Providing, laying and rolling of close-graded premix surfacing material of 20 mm
thickness composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using
5.8 penetration grade bitumen to the required line, grade and level to serve as wearing course on a previously
prepared base, including mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne
capacity, and finishing to required level and grade. )
Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate capacity not less
(ii) than 75 tonnes/ hours using crushed stone chipping 6.7 mm size and penetration bitumen of suitable grade.) sqm 38.34 39.09 40.17
Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved sources
confirming to the physical requirement, specified in the respective specified clauses, including royalties, fees
rents, collection, transportation, stacking and testing and measured in cum as per clause 520 Competitive
5.10 market rates to be ascertained. Alternatively, rates for stone crushing given in chapter 1may be adopted, if found cum
economical. In case for supply of aggregates at site are not available, nearest crusher site may be ascertained.
Loading and un-loading charges and cost of carriage may be added to these rates to arrive at the cost at site.)
Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen
meeting the requirements given in table 500-39, prepared by using mastic cooker and laid to required level and
slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine-grained hard
5.11 stone chipping of 13.2 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of sqm 1315.09 1339.45 1363.80
10 cm center to center in both directions, pressed into surface when the temperature of surfaces not less than
1000C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 516.)
Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates, portland cement filler,
5.12 bituminous emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable
mobile plant, laying and compacting to provide even riding surface)
(i) 5 mm thickness sqm 58.48 59.55 60.91
(ii) 3 mm thickness sqm 41.94 42.69 43.65
(iii) 1.5 mm thickness sqm 26.84 27.30 27.91
Recycling of Bituminous Pavement with Central Recycling Plant (Recycling pavement by cold milling of exiting
bituminous layers, planning the surface after cold milling, reclaiming excavated material to the extent of 30 % of
the required quantity, hauling and stock piling the reclaimed material near the central recycling plant after
5.13 carrying out necessary checks and evaluation, adding fresh material including rejuvenators as required, mixing cum 5487.53 5557.69 5715.33
in a hot mix plant, transporting and laying at site and compacting to the required grade, level and thickness, all
as specified in clause 519.)
Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing and laying of a stress
absorbing membrane over a cracked road surface, with crack width 6 to 9 mm after cleaning with a
(ii) mechanical broom, using modified binder complying with IRC:SP: 53,, sprayed at the rate of 11 kg per 10 sqm sqm 59.64 60.74 61.85
and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to clause 902.)
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % (Providing and
laying a single coat of a stress absorbing membrane over a cracked road surface, with crack width above 9
(iii) mm and cracked area above 50 % after cleaning with a mechanical broom, using modified binder complying sqm 78.46 79.92 81.37
with IRC:SP: 53,, sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of aggregates and surface finished to
conform to clause 902.)
Case - IV : Bitumen Impregnated Geotextile (Providing and laying a bitumen impregnated geotextile layer after
(iv) cleaning the road surface, geotextile conforming to requirements of clause 708.2, laid over a tack coat with sqm 237.26 241.65 246.04
1.05 kg per sqm of paving grade bitumen 80 - 100 penetration and constructed to the requirement of clause
708.3.4)
Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a
5.18 batch type cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tyred roller
initially and finished with a smooth steel wheel roller, all as per clause 518.3)
(i) 75 mm thickness cum 6554.45 6698.87 6933.15
(ii) 40 mm thickness cum 8656.97 8840.11 9115.23
(iii) 25 mm thickness cum 9914.01 10122.18 10416.78
5.19 Bituminous Concrete with waste plastic
Bituminous Concrete Grading -I with waste plastic(Providing and laying bituminous concrete with higher
capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous
(i) binder @ 5.2 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver cum 7055.30 7208.90 7458.80
finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all
respects)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Bituminous Concrete Grading -II with waste plastic (Providing and laying bituminous concrete with higher
capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous
(ii) binder @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver cum 7255.60 7414.30 7668.30
finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all
respects)
CHAPTER-6
CEMENT CONCRETE PAVEMENTS
Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub- base over a prepared
sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25
mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1,
6.1 cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length cum 3118.21 3183.58 3263.46
construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to
site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.)
Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain cement concrete pavement over
a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383,
maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved
mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a
6.2 cum 6382.85 6511.95 6688.54
continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint
filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as per drawing )
Transition section between rigid and flexible pavement (Due to change in the properties of materials and type of
construction, a gradual changeover from rigid pavement to flexible pavement is desirable to avoid any damage
6.3 at the butting joint. After provision of an expansion joint in the cement concrete slab, the thickness of slab should
be tapered to 10 cm over a length of 3 m towards the flexible pavement. The deficiency of thickness caused due
to tapering of the slab should be made up by the asphaltic layers.)
Construction of Base/Sub-base of pavement with lean concrete - fly ash. (Construction of Base/sub-base using
cement, sand, fly ash and coarse aggregates proportioned as per table 4 of IRC: 74/1979 and with water
content ratio, slump and compressive strength as defined in the said table, mix prepared in a batching and
6.4 mixing plant and compacted with a vibratory roller 8-10 tonnes capacity within the time limit laid down vide cum 2955.93 3018.29 3095.17
clause 7.6.3 of IRC: 74-1979, construction joints properly formed at the end of day's work, cured for 14 days, all
as specified in IRC: 74-1979 and as per approved plans.)
Cement - Fly ash concrete pavement. (Construction reinforced-reinforced, dowel jointed, plain cement concrete
pavement over a prepared sub base with 43 grade cement, coarse and fine aggregate conforming to IS 383,
maximum size of coarse aggregate not exceeding 25 mm, replacing cement by fly ash to the extent of 15% and
sand by 10%, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a
6.5 cum 5970.57 6097.74 6260.94
fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer,
joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines
and grades as per drawing )
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Sub- Surface Drain with Geotextiles (Construction of sub surface drain 200 mm dia using geotextiles treated with
carbon black with physical properties as given in clause 702.2.3 formed in to a stable network and a planar
7.1 geocomposite structure, joints wrapped with geotextile to prevent ingress of soil, all as per clause 702 and metre 1186.00 1208.00 1230.00
approved drawings including excavation and backfilling)
Laying Paving Fabric Beneath a Pavement Overlay (Providing and laying paving fabric with physical
requirements as per Table 700-16 over a tack coat of paving grade Bitumen 80-100 penetration, laid at the rate
7.2 of 1 kg per sqm over thoroughly cleaned and repaired surface to provide a water resistant membrane and crack sqm 205.00 209.00 213.00
retarding layer. Paving fabric to be free of wrinkling and folding and to be laid before cooling of tack coat,
brooming and rolling of surface with pneumatic roller to maximise paving fabric contact with pavement surface)
Laying Boulder Apron in Crates of Synthetic Geogrids (Providing, preparing and laying of geogrid crated apron 1
m x 5 m, 600 mm thick including excavation and backfilling with baffles at 1 metre interval, made with geogrids
having characteristics as per clause 703.2, joining sides with connectors/ring staples, top corners to be tie
tensioned, placing of suitable cross interval ties in layers of 300 mm connecting opposite side with lateral braces
7.3 and tied with polymer braids to avoid bulging, constructed as per clause 703.3. filled with stone with minimum cum 1142.00 1163.00 1185.00
size of 200 mm and specific gravity not less than 2.65, packed with stone spalls, keyed to the foundation recess
in case of sloping ground and laid over a layer of geotextile to prevent migration of fines, all as per clause 703
and laid as per clause 2503.3 and approved design.)
Reinforced Earth Retaining Wall (Reinforced earth retaining walls have four main components as under: a)
Excavation for foundation, foundation concrete and cement concrete grooved seating in the foundation for facing
7.4 elements (facia material). b) Facia material and its placement. c) Assembling, joining with facing elements and
laying of the reinforcing elements. d) Earthfill with granular material which is to be retained by the wall.)
(i) Assembling, joining and laying of reinforcing elements. Sqm
A With reinforcing element of steel / Aluminium strips / polymeric strips.
Type 1 1.Galvanised carbon steel strips metre 253.00 257.00 262.00
Type 2 2.Copper Strips metre 260.00 264.00 269.00
Type 3 3.Aluminium Strips metre 267.00 271.00 276.00
Type 4 4.Stainless steel strips metre 253.00 257.00 262.00
Type 5 5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips metre 222.00 226.00 230.00
B With reinforcing elements of synthetic geogrids sqm 208.00 212.00 216.00
(ii) Facing elements of RCC sqm 1607.00 1608.00 1608.00
7.5 Bi-axial extruded high modulus polypropylene geogrid
Summary of Rate Analysis
Rate As Per Proposed Data Book
Supplying & laying of bi-axial extruded high modulus polypropylene geogrid conforming to MORT&H
specification for base/sub-base reinforcement having minimum tensile strength 15kN/m in the longitudinal and
(i) transverse direction, with 5kN/m and 7kN/m tensile strength at 2% and 5% strain respectively in the longitudinal sqm 136.00 138.00 141.00
and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening.
Supplying & laying of bi-axial extruded high modulus polypropylene geogrid conforming to MORT&H
specification for base/sub-base reinforcement having minimum tensile strength 20kN/m in the longitudinal and
(ii) transverse direction, with 7kN/m and 14kN/m tensile strength at 2% and 5% strain respectively in the longitudinal sqm 154.00 157.00 160.00
and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening.
Supplying & laying of bi-axial extruded high modulus polypropylene geogrid conforming to MORT&H
specification for base/sub-base reinforcement having minimum tensile strength 30kN/m in the longitudinal and
(iii) transverse direction, with 10.5kN/m and 21kN/m tensile strength at 2% and 5% strain respectively in the sqm 244.00 249.00 253.00
longitudinal and transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh
opening.
Supplying & laying of bi-axial extruded high modulus polypropylene geogrid coforming to MORT&H specification
for base/sub-base reinforcement having minimum tensile strength 40kN/m in the longitudinal and transverse
(iv) direction, with 14kN/m and 28kN/m tensile strength at 2% and 5% strain respectively in the longitudinal and sqm 352.00 358.00 365.00
transverse direction, junction efficiency not less than 95% and with 38mm X 38mm mesh opening.
Supplying and laying high strength flexible geogrids (HSFG) as soil reinforcement / basal reinforcement as per
MORTH 3100 and IRC 113, made of high tenacity polyester core with polyethylene coating with minimum Long
7.6 Term Design Strength (LTDS) of more than 50% of ultimate tensile strength at 30 degree Celcius corresponding
to 12 % strain etc. complete and as directed by Engineer - In - Charge.
(i) Synthetic Geogrid Ultimate tensile strength- 100 kN/m sqm 273.00 278.00 283.00
(ii) Synthetic Geogrid Ultimate tensile strength- 150 kN/m sqm 299.00 305.00 310.00
(iii) Synthetic Geogrid Ultimate tensile strength- 200 kN/m sqm 404.00 411.00 419.00
(iv) Synthetic Geogrid Ultimate tensile strength- 250 kN/m sqm 443.00 451.00 459.00
(v) Synthetic Geogrid Ultimate tensile strength- 300 kN/m sqm 469.00 478.00 487.00
(vi) Synthetic Geogrid Ultimate tensile strength- 350 kN/m sqm 521.00 531.00 541.00
(vii) Synthetic Geogrid Ultimate tensile strength- 400 kN/m sqm 561.00 571.00 581.00
(viii) Synthetic Geogrid Ultimate tensile strength- 500 kN/m sqm 665.00 678.00 690.00
(ix) Synthetic Geogrid Ultimate tensile strength- 600 kN/m sqm 731.00 744.00 758.00
(x) Synthetic Geogrid Ultimate tensile strength- 800 kN/m sqm 937.00 954.00 972.00
(xi) Synthetic Geogrid Ultimate tensile strength- 900 kN/m sqm 1111.00 1131.00 1152.00
(xii) Synthetic Geogrid Ultimate tensile strength- 1000 kN/m sqm 1253.00 1277.00 1300.00
(xiii) Synthetic Geogrid Ultimate tensile strength- 1100 kN/m sqm 1319.00 1343.00 1367.00
(xiv) Synthetic Geogrid Ultimate tensile strength- 1200 kN/m sqm 1434.00 1460.00 1487.00
Supplying & laying of drainage composite for use behind walls, between two different fills, alongside drains of
road, below concrete lining of canals etc. Geocomposite for planar drainage, realized by thermobonding a
draining core in extruded monofilaments with two filtering nonwoven geotextiles that may also be working as
separation or protecting layers. The draining three dimensional core will have a “W” configuration as longitudinal
parallel channels. Minimum thickness to be 7.2mm, with two filtering UV stabilized polypropylene nonwoven
geotextile of minimum thickness of 0.75 mm having pores of 150 micron and tensile strength of 8.0 kN/m that will
7.8 sqm 670.00 683.00 695.00
be working as separation or protecting layer, geocomposite having in plane flow capacity of 2.1 L / (m.s) at
hydraulic gradient of 1.0 & 20 kpa pressure and tensile strength of 18 kN/m , with mass per unit area of 740
gsm, supplied in the form of roll for easy transportation to site of work as per detailed specification all complete
as per directions of Engineer in charge.
Supplying & laying of drainage composite for use behind walls, between two different fills, alongside drains of
road, below concrete lining of canals etc. Geocomposite for planar drainage, realized by thermobonding a
draining core in extruded monofilaments with two filtering nonwoven geotextiles that may also be working as
separation or protecting layers. The draining three dimensional core will have a “W” configuration as longitudinal
parallel channels. Minimum thickness to be 7.2mm, with two filtering UV stabilized polypropylene nonwoven
geotextile of minimum thickness of 0.75 mm having pores of 150 micron and tensile strength of 8.0 kN/m that will
7.9 sqm 796.00 811.00 825.00
be working as separation or protecting layer, geocomposite having in plane flow capacity of 2.1 L / (m.s) at
hydraulic gradient of 1.0 & 20 kpa pressure and tensile strength of 18 kN/m , with mass per unit area of 740
gsm, supplied in the form of roll for easy transportation to site of work as per detailed specification all complete
as per directions of Engineer in charge.
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and bottom width 115
and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation
8.1 having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408)
A Using Concrete Batching and Mixing Plant
(i) PCC M15 for Kerb base metre 168.00 171.00 174.00
(ii) PCC M20 for Kerb (Cast in Situ) metre 206.00 210.00 214.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction of cement concrete kerb with channel with
top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M10 grade foundation
8.2 150 mm thick, kerb channel 300 mm wide, 50 mm thick in PCC M20 grade, sloped towards the kerb, kerb stone
with channel laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 408)
A Using Concrete Batching and Mixing Plant
(i) PCC M15 for Kerb base metre 143.00 145.00 148.00
(ii) PCC M20 for Kerb (Cast in Situ) metre 240.00 244.00 249.00
Printing new letter and figures of any shade (Printing new letter and figures of any shade with synthetic enamel
8.3 paint black or any other approved colour to give an even shade)
Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be counted as half ) cm height
(i) 1.50 1.50 1.50
per letter
English and Roman cm height
(ii) 0.90 0.90 0.90
per letter
Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised cautionary, mandatory and
informatory sign as per IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over
8.4 aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed
to the ground by means of properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60
cm, 60 cm below ground level as per approved drawing)
Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing and erecting direction
and place identification retro- reflectorised sign asper IRC :67 made of encapsulated lens type reflective
sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported
8.6 on a mild steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly sqm 9640.00 9818.00 9997.00
designed foundation with M 15 grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per
approved drawing)
Overhead Signs (Providing and erecting overhead signs with a corrosion resistant aluminium alloy sheet
reflectorised with high intensity retro-reflective sheeting of encapsulated lense type with vertical and lateral
8.7 clearance given in clause 802.2 and 802.3 and installed as per clause 802.7 over a designed support system of
aluminium alloy or galvanised steel trestles and trusses of sections and type as per structural design
requirements and approved plans)
A Truss and Vertical Support tonne 100188.00 102044.00 103899.00
B Aluminium alloy plate for over head sign tonne 5883.00 5992.00 6100.00
Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the surface with synthetic enamel
8.8 paint in all shades on new plastered concrete surfaces) sqm 102.00 104.00 106.00
Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved brand on steel
8.9 surface after through cleaning of surface to give an even shade) sqm 77.00 80.00 83.00
Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved brand on wood
8.10 surface after through cleaning of surface to give an even shade) sqm 83.00 85.00 87.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines, dashes, arrows etc on
8.11 roads in two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous
surface, including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic
control )
(i) Over 10 cm in width sqm 191.00 194.00 198.00
(ii) Up to 10 cm in width sqm 161.00 164.00 167.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes, arrows etc on
8.12 roads in two coats on old work with ready mixed road marking paint confirming to IS: 164 on bituminous surface,
including cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )
(i) Over 10 cm in width sqm 134.00 137.00 139.00
(ii) Up to 10 cm in width sqm 145.00 148.00 151.00
Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous
Surface (Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass
8.13 beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per sqm 529.00 539.00 549.00
IRC:35 .The finished surface to be level, uniform and free from streaks and holes.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980,
8.14 fixing in position including painting and printing etc)
(i) 5th kilometre stone (precast) each 4984.00 5016.00 5049.00
(ii) Ordinary Kilometer stone (Precast) each 2829.00 2844.00 2859.00
(iii) Hectometer stone (Precast) each 854.00 861.00 868.00
Road Delineators (Supplying and installation of delineators (road way indicators, hazard markers, object
markers), 80-100 cm high above ground level, painted black and white in 15 cm wide stripes, fitted with 80 x 100
8.15 mm rectangular or 75 mm dia circular reflectorised panels at the top, buried or pressed into the ground and each 298.00 303.00 309.00
confirming toIRC-79 and the drawings.)
Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design as per IRC:25-
8.16 1967, fixed in position including finishing and lettering but excluding painting) each 711.00 718.00 724.00
G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire fencing with 1.8 m
angle iron posts 40 mm x 40 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement
8.17 concrete, 0.6 metre below ground level, every 15th post, last but one end post and corner post shall be strutted metre 339.00 345.00 351.00
on both sides and end post on one side only and provided with 9 horizontal lines and 2 diagonals interwoven
with horizontal wires, fixed with GI staples, turn buckles etc complete as per clause 808 )
G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI barbed wire fencing with 2.4 m
angle iron posts 50 mm x 50 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement
8.18 concrete, 0.6 metre below ground level, every 15th post, last but one end post and corner post shall be strutted metre 567.00 577.00 587.00
on both sides and end post on one side only and provided with 12 horizontal lines and 2 diagonals interwoven
with horizontal wires, fixed with GI staples, turn buckles etc complete as per clause 808 )
Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing 1.20 metre high fencing with
angle iron posts 50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40 metre embedded in M15 grade
8.19 cement concrete, corner, end and every 10th post to be strutted, provided with welded steel wire fabric of 75 mm metre 1986.00 2023.00 2059.00
x 50 mm mesh or 75 mm x 25 mm mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete in
all respects.)
Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm (Providing, fixing and
8.20 erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 metre 1959.00 1959.00 1974.00
mm x 50 mm, 1.2 metres high above ground, 2 m centre to centre, complete as per approved drawings)
Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing and erecting 50
8.21 mm dia painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m metre 4235.00 4250.00 4265.00
above GL) with 3 holes 50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing)
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at the
edges of the road, approaches to bridge structures and medians, constructed with M-20 grade concrete with
HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled
8.22 with pre-moulded asphalt filler board, keyed to the structure on which it is built and installed as per design given
in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the
approved drawing and at locations directed by the Engineer, all as specified)
Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground
B level, all steel parts and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and metre 4628.00 4714.00 4800.00
IS:1364, metal beam rail to be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546
mm long complete as per clause 811)
Road Traffic Signals electrically operated (Since it is a ready made item commercially produced and erected by
8.24 specialised firm in the electrical and electronic field, rate may be taken based on market enquiry from firms
specialised in this field and ISI certified for the approved design and drawing.)
Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety barrier with vertical
posts of medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above
ground and 0.65 m below ground level, split at the bottom for better grip, embedded in M 15 grade cement
concrete 450 x 450 x 450 mm, 1.50 m center to center and with 4 horizontal steel wire rope 40 mm dia and
8.25 anchored at terminal posts 15 m apart. Terminal post to be embedded in M 15 metre 1998.00 2034.00 3134.00
gradecementconcretefoundation2400 x 450 x 900 mm (depth), strengthened by a strut of RS joist 100 x 75 mm,
2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation
concrete as per approved design and drawing, rate excluding excavation and cement concrete.)
Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting anti - glare screen with
rectangular vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6
C mm at an angle of 450 to the direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m metre 1213.00 1235.00 1257.00
above ground level, vertical post firmly embedded in cement concrete foundation 0.60 m below ground level,
applying 2 coats of paint on exposed faces, all complete as per approved design and drawings)
Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of standard
8.27 specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the
median and on one side if fixed on the footpath, fitted with sodium vapour lamp and fixed firmly in concrete
foundation.)
(i) For Fixing in Median each 84499.00 86055.00 91942.00
(ii) For fixing in Footpath each 84412.00 85969.00 91856.00
Lighting on Bridges (Providing and fixing lighting on bridges, mounted on steel hollow circular poles of standard
8.28 specifications, 5 m high fixed on parapets with cement concrete, 20 m apart and fitted with sodium vapour lamp) each 51488.00 52437.00 53914.00
Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct, 300 mm dia,
across the road (new construction), extending from drain to drain in cuts and toe of slope to toe of slope in fills,
constructing head walls at both ends, providing a minimum fill of granular material over top and sides of RCC
pipe as per IRC:98-1997, bedded on a 0.3 m thick layer of granular material free of rock pieces, outer to outer
8.29
distance of pipe at least half dia of pipe subject to minimum 450 mm in case of double and triple row ducts, joints
to be made leak proof, invert level of duct to be above higher than ground level to prevent entry of water and
dirt, all as per IRC: 98 - 1997 and approved drawings.)
(i) Single Row for one utility service metre 6457.00 6565.00 6673.00
(ii) Double Row for two utility services metre 12332.00 12759.00 13194.00
(iii) Triple Row for three utility services metre 18763.00 19113.00 19462.00
Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post every 50-60 km of the
8.30 highway. )
Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The items involved for underpass/
subway/ overhead bridge/ overhead foot bridge are earthwork, plain cement concrete, plastering, painting,
8.31 information sign etc. The rates for these items are available in respective chapters which can be adopted for the
quantities derived from the approved designs and drawings)
Traffic Control System and Communication system (Providing a traffic control centre and communication system
including telecommunication facilities and related accessories, CCTV, radar, vehicle detection camera, central
computer system These are specialised item of telecommunication system and are the commercial products.
8.32 The designer is required to contact the manufacturers to ascertain market prices. In case of civil works required
to be executed for these installations, pricing may be done as per rates in relevant chapters for quantities
derived approved design and drawing.)
Gantry Mounted Variable Message Sign board (Providing and erecting gantry mounted variable message sign
8.33 board electronically operated capable of flashing the desired message over a designed support system of
aluminium alloy or galvanised steel, erected as per approved design and drawings and with lateral clearance as
per clause 802.3)
(i) Gantry Support System tonne 98101.00 99918.00 6469.00
Message Display (Message display board 6 sqm electronically operated with complete electronic fitments for
(ii) flashing the pre-determined messages.)
8.34 Traffic Impact Attenuators at Abutments and Piers
With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of flyovers bridges using
A scrap tyres of size 100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one above the other and tied with sqm 988.00 1007.00 1025.00
20 mm wire rope as per approved design and drawings.)
Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact attenuator at
B abutment/pier of flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in sqm 1041.00 1060.00 1080.00
three rows and tied with20 mm steel wire rope as per approved design and drawings)
With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system, water gets discharged from
C plastic tubes on impact over a pre-determined time, thus absorbing the energy)) sqm 1533.00 1561.00 1597.00
Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm, die cast in
aluminium, resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or
8.35 asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or each 314.00 320.00 326.00
epoxy mortar, all as per BS 873 part 4:1973)
Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of low density
8.36 polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, each 541.00 551.00 561.00
placed at 1.5 m interval, all as per BS 873)
8.37 Roadside Amenities
Rest Areas (Providing plainly furnished accommodation for rest rooms, dormitories, restaurants, stalls, shops,
petrol pump, telephone booth, first aid room, traffic aid post, police assistance booth, including electricity, toilet
A and sewerage system Pricing may be done based on current plinth area rates approved by PWD/CPWD/MES
for a particular zone. Area is required to be assessed for specific location as per actual site conditions)
Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of parking areas may be done for
B the quantities of various items based on the approved dimensions and pavement design for a particular terrain
and soil. Rates for items may be from respective chapters.)
C Lawn (Providing a lawn planted with grass and its maintenance )
Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous carpet, 15-20 mm high at
8.38 center, 250 mm wide placed at 1 m center to center at approved locations to control speed, marked with white sqm
strips of road marking paint.)
Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic policeman at road crossings,
8.39 where necessary, installed on a raised platform, built on a central support of a steel pipe 100 mm dia, roof made each 4642.12 4781.57 4921.02
of 25 mm dia steel pipe to provide covered area of 3 sqm, roofed with CGI sheets, all steel parts to be given 2
coats of paint)
Summary of Rate Analysis
Rate As Per Proposed Data Book
High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high mast pole lighting with 30
m high hot dip galvanised mast designed to withstand forces exerted with wind speeds of 180 km per hour with
3 seconds gust, as per IS:875 (Part 3) - 1978, fitted with a base flange, door at the base of mast with heavy
duty internal lock, lantern carriage, suitable winching arrangement for safe working load of 750 kg and high
powered electrically driven power tools for raising and lowering of lantern carriage, flexible 8 core electric cable,
8.40 lightening conductor, earthing terminal, and fixing 2 nos aviation obstruction lights on top of the mast, all
complete as per approved design and drawings This is a specialised work and is generally done by firms who
specialise in such jobs. The detailed designs and estimates are submitted by the firms alongwith their tender for
checks by the Department. The cost of this work is required to be worked out based on approved design,
drawings and estimate of the lowest tender. A separate contract for this work is concluded as the contractors for
road and bridge works generally donot undertake such jobs.)
Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken into separate items of
8.41 work as under based on the approved design and drawings:-)
Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs for limited period at suitable
locations in construction zone comprising of warning zone, approach transition zone, working zone and
terminal transition zone with a minimum distance of 60 cm from the edge of the kerb in case of kerbed roads and
2 to 3 m from the edge of the carriageway in case of un-kerbed roads, the bottom edge of the lowest sign plate
8.42
to be not less than 2 m above the road level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded and
installed as per approved design and drawings, removed and disposed of after completion of construction work,
all as per IRC:SP:55-2001)
Portable Barricade in Construction Zone (Installation of a steel portable barricade with horizontal rail 300 mm
wide, 2.5 m in length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in height,
8.43 horizontal rail painted (2 coats) with yellow and white stripes, 150 mm in width at an angle of 450, 'A' frame each 3903.00 4049.00 4197.00
painted with 2 coats of yellow paint, complete as per IRC:SP:55-2001 )
8.44 Permanent Type Barricade in Construction Zone
With Steel Components (Construction of a permanent type barricade made of steel components, 1.5 m high
from road level, fitted with 3 horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron vertical
A support, painted with yellow and white strips, 150 mm in width at an angle of450, complete as per each 6199.00 6314.00 6429.00
IRC:SP:55-2001 )
With Wooden Components (Construction of a permanent type barricade made of wooden components, 1.5 m
high from road level, fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x 100mm wooden
B vertical post, painted with yellow and white striups, 150 mm in width at an angle of450, complete as per each 1264.00 1287.00 1310.00
IRC:SP:55-2001 )
With Bricks (Construction of a permanent type barricade made with brick work in mud mortar, 1.5 m high, 4
C m long, 600 mm thick, plastered with cement mortar 1:6, painted with yellow and white strips) each 15577.00 15865.00 16154.00
Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen drum delineator, 300 mm in
8.45 diameter, 800 mm high, filled with earth for stability, painted in circumferential strips of alternate black and each 586.00 596.00 607.00
white 100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001)
Water Filled Barricades Work zone sheeting (Providing water filled barricades made up of LDPE to segregate
8.46 the vehicular movement and workzone as per IRC SP 55 shall be in Trapezoidal Shape 800 mm to 1000 mm in each 3983.00 4056.00 4130.00
length, 700 mm in height for Major Roads and expressway and 500 mm tall for other roads with interlocking
arrnagements, To be placed 0.5 m from the edge of the carriageway for expressway and 0.3 m for other roads.
Providing Tubular Marker made up of Polyurethane used to divide opposing lanes of road users shall be flexible
It should have reboubdable workzone sheeting as per ASTM D 4956 S2.)
8.47 in nature. Tubular maker having minimum height 450 mm shall be having minimum 75 mm Reboundable each 763.00 777.00 791.00
workzone retroreflective sheeting as per ASTM 4956 S2. Application of Tubular Marker Shall be done as per
IRC SP 55.
Providing Tubular Marker made up of Polyurethane used to divide opposing lanes of road users shall be flexible
8.48 in nature. Tubular maker having minimum height 700 mm shall be having minimum 75 mm Reboundable each 906.00 923.00 939.00
workzone retroreflective sheeting as per ASTM 4956 S2. Application of Tubular Marker Shall be done as per
IRC SP 55.
Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600 x 600 mm
8.49 securely fastened to a staff 1 m in length for guiding the traffic) each 745.00 759.00 772.00
Advanced Traffic Management Systems (ATMS) work shall cover design, supply, installation, commissioning
and/or operation and maintenance of Advance Traffic Management Systems (which is one of the components of
Intelligent Transport Systems - ITS). The system would include out-door equipment including emergency call
boxes, variable message sign systems, meteorological data system, close circuit TV camera (CCTV) system,
8.50 traffic counting and classification system and transmission system. The indoor equipment would comprise a
large display board, central computer (with Network Management System - NMS), CCTV monitor system, call
centre system or management of emergency call boxes housed in a control centre with uninterrupted power
supply.
VIDS- Workstation
Nos. 68000.00 68000.00 68000.00
Administrative Workstation
Nos. 44000.00 44000.00 44000.00
CCTV Joystick
Nos. 76000.00 76000.00 76000.00
Rack 19"
Nos. 46400.00 46400.00 46400.00
Antivirus license
Nos. 160000.00 160000.00 160000.00
Solar System with UPS, battery & 12m Pole & Cabinet
Set 68000.00 68000.00 68000.00
Warning amber lights with hooters, 72 Hrs solar backup, 5m poles and foundation
Set 91200.00 91200.00 91200.00
Cabinet
Nos. 22800.00 22800.00 22800.00
Solar System with UPS, battery and cabinet for M type VMS
Set 312000.00 312000.00 312000.00
MOS sensor Equipment (including MOS Controller) Set 848000.00 848000.00 848000.00
40 mm PLB HDPE duct as per latest TSEC specifications + all accessories Meter 456.00 456.00 456.00
Trenching of 1.8 meters, Laying & Backfilling for PLB HDPE duct Meter 160.00 160.00 160.00
CHAPTER-9
CULVERTS & BOX CELL
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical
9.1 specification, including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and backfilling with approved material.)
I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 270.00 270.00 270.00
(ii) 3 m to 6 m depth cum 347.00 347.00 347.00
(iii) Above 6 m depth cum 463.00 463.00 463.00
B Mechanical Means
(i) Depth upto 3 m cum 76.00 84.00 149.00
(ii) Depth 3 m to 6 m cum 84.00 93.00 164.00
(iii) Depth above 6m cum 93.00 104.00 184.00
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 386.00 386.00 386.00
B Mechanical Means cum 461.00 523.00 771.00
III Hard rock ( requiring blasting )
A Manual Means cum 798.00 798.00 798.00
B Mechanical Means cum 498.00 508.00 585.00
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 598.00 718.00 1198.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 1061.00 1061.00 1061.00
B Mechanical Means cum 265.00 281.00 405.00
VI Back Filling in Marshy Foundation Pits cum 747.00 747.00 747.00
Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate may be taken as
9.2 per item 9.4.) cum 4810.00 4813.00 4826.00
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size
9.4 mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. cum 4810.00 4813.00 4826.00
Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per
9.5 Drawing and Technical Specifications. cum 6827.00 6829.00 6836.00
9.6 Cement Mortar
A Cement Mortar 1:3 (1 cement : 3 sand) cum 4847.00 4847.00 4847.00
B Cement Mortar1:2 (1cement :2 sand) cum 5786.00 5786.00 5786.00
C Cement Mortar1:4 (1cement :4 sand) cum 4220.00 4220.00 4220.00
D Cement Mortar1:6 (1cement :6 sand) cum 3679.00 3679.00 3679.00
Stone Masonry Work in Cement Mortar 1:3 in Foundation complete as per Drawing and Technical
9.7 Specifications.
A Square Rubble Coursed Rubble Masonry (first sort) cum 5520.00 5520.00 5520.00
B Random Rubble Masonry cum 5332.00 5332.00 5332.00
Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per drawing and
9.8 Technical Specifications cum 6515.00 6517.00 6525.00
Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical Specifications
9.9 Sqm. 1007.00 1007.00 1007.00
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical Specifications
9.10 Sqm. 1759.00 1760.00 1762.00
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications
9.11
A Random Rubble Masonry cum 5055.00 5059.00 5325.00
B Coursed rubble masonry (first sort ) cum 5677.00 5681.00 5695.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing
9.21 cum 12793.00 12793.00 12793.00
and Technical Specifications
Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab excluding prime coat with
paving grade bitumen meeting the requirements given in Table 500-39, prepared by using mastic cooker and laid
to required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated
9.22 Sqm. 470.00 470.00 470.00
fine grained hard stone chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an
approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of
surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 516.
(iv) Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand and
Sqm. 44.00 44.00 44.00
6 per cent bitumen by weight
9.26 Back filling behind abutment, wing wall and return wall complete as per drawing and Technical Specification
A Granular material cum 1870.00 1870.00 1870.00
B Sandy material cum 1998.00 1998.00 1998.00
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements
laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size
9.27 towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall 1763.00 1763.00 1763.00
and return wall to the full height compacted to a firm condition complete as per drawing and Technical
Specification.
CHAPTER-10
MAINTENANCE OF ROADS
Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a mixture of these, clearing the
10.1 loose soil, benching for 300 mm width, laying fresh material in layers not exceeding 250 mm and compacting cum 194.00 200.00 212.00
with plate compactor or power rammers to restore the original alignment, levels and slopes)
Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of material/ irregularities on shoulder to
10.2 the design level by adding fresh approved soil and compacting it with appropriate equipment.) sqm 109.00 111.00 114.00
Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from the shoulder surface to
10.3 achieve the approved level and compacting with plate compactor) sqm 42.00 43.00 44.00
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm. (Removal of all failed material,
trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on
10.4 the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per sqm 117.00 119.00 121.00
clause 510, compacting, trimming and finishing the surface to form a smooth continuous surface, all as per
clause 3004.2)
Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm. (Removal of all failed material,
trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the
10.5 sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per
clause 504, compacting, trimming and finishing the surface to form a smooth continuous surface, all as per
clause 3004.2)
(i) for grading I Material sqm 285.00 288.00 295.00
(ii) for grading II Material sqm 297.00 301.00 307.00
Crack Filling (Filling of crack using slow - curing bitumen emulsion and applying crusher dust in case crack are
10.6 wider than 3mm.) metre 4.00 4.00 4.00
10.7 Dusting (Applying crusher dust to areas of road where bleeding of excess bitumen has occurred.) sqm 1.04 1.06 1.08
10.8 A Fog Seal (ref item 5.17) sqm 32.46 33.06 33.66
B Crack Prevention courses. (ref item 5.21)
(i) Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 51.32 52.27 53.22
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 59.64 60.74 61.85
(iii) Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % sqm 78.46 79.92 81.37
(iv) Bitumen Impregnated Geotextile sqm 237.26 241.65 246.04
C Slurry Seal (ref item 5.15)
(i) 5 mm thickness sqm 58.48 59.55 60.91
(ii) 3 mm thickness sqm 41.94 42.69 43.65
(iii) 1.5 mm thickness sqm 26.84 27.30 27.91
D Surface Dressing for maintance works. (ref item 5.9)
(i) 19 mm nominal chipping size sqm 77.29 78.54 80.32
(ii) 13 mm nominal size chipping sqm 60.29 61.19 62.45
Repair of joint Grooves with Epoxy Mortar Repair of spalled joint grooves of contraction joints, longitudinal joints
10.9 and expansion joints in concrete pavements using epoxy mortar or epoxy concrete) metre 833.00 849.00 864.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Repair of old Joints Sealant (Removal of existing sealant and re sealing of contraction, longitudinal or
10.10 expansion joints in concrete pavement with fresh sealant material) metre 48.00 49.00 50.00
Hill Side Drain Clearance (Removal of earth from the choked hill side drain and disposing it on the valley side
10.11 manually) metre 72.00 74.00 75.00
Land Slide Clearance in soil (Clearance of land slides in soil and ordinary rock by a bull-dozer 175 HP and
10.12 disposal of the same on the valley side) cum 49.00 49.00 50.00
Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard rock requiring blasting for
10.13 50% of the boulders and disposal of the same on the valley side.) cum 96.00 98.00 99.00
Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bull- dozer 165 Hp and disposing
10.14 it on the valley side) cum 3.00 3.00 3.00
Snow Clearance on Roads with Snow Blowers (Snow clearance from road surface by a snow blower and
10.15 disposing on the valley side.) cum 5.00 5.00 5.00
CHAPTER-11
HORTICULTURE
Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge farm yard manure or/ and good
11.1 earth in required thickness (cost of sludge, farm- yard manure or/and good earth to be paid for separately)) cum 46.00 47.00 48.00
Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and maintenance of the lawn for
11.2 30 days or more till the grass forms a thick lawn free from weeds and fit for moving including supplying good
earth if needed)
(i) In rows 15 cm apart in either direction sqm 22.00 23.00 23.00
(ii) In rows 7.5 cm apart in either direction sqm 33.00 34.00 34.00
Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of Clod (Making lawns including
11.3 ploughing and breaking of clod, removal of rubbish, dressing and supplying doobs grass roots and planting at sqm 42.00 43.00 44.00
15 cm apart, including supplying and spreading of farm yard manure at rate of 0.18 cum per 100 sqm)
Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or Turfing of slopes (rough grassing) for a
11.4 period of one year including watering etc) sqm 311.00 317.00 323.00
Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns with fine grassing including
11.5 ploughing, dressing including breaking of clods, removal of rubbish, dressing and supplying doobs grass roots sqm 51.00 51.00 52.00
at 10 cm apart, including supplying and spreading of farm yard manure at rate of0.6 cum per 100 sqm)
11.6 Maintenance of Lawns with Fine Grassing for the First Year sqm 338.00 345.00 351.00
a) Planting Permanent Hedges including Digging of Trenches (Planting permanent hedges including digging of
11.7 trenches, 60 cm wide and 45 cm deep, refilling the excavated earth mixed with farmyard manure, supplied at metre 161.00 164.00 167.00
the rate of 4.65 cum per 100 metres and supplying and planting hedge plants at 30 cm apart)
(b) Maintenance of Hedge for one year metre 311.00 317.00 322.00
11.8 a) Planting Flowering Plants and Shrubs in Central Verge km 57998.00 59072.00 60146.00
(b) Maintenance of Flowering Plants and Shrubs in Central Verge for one Year km 386966.00 394132.00 401298.00
Planting of Trees and their Maintenance for one Year (Planting of trees by the road side (Avenue trees) in 0.60
11.9 m dia holes, 1 m deep dug in the ground, mixing the soil with decayed farm yard/sludge mannure, planting the each 1672.00 1703.00 1734.00
saplings, backfilling the trench, watering, fixing the tree guard and maintaining the plants for one year)
Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with Forked Soil (Renovation lawns
including, weeding, forking the ground, top dressing with forked soil, watering and maintenance the lawns, for
11.10 30 days or more, till the grass forms a thick lawn, free from weeds, and fit for moving and disposal of rubbish sqm 29.00 29.00 30.00
as directed, including supplying good earth, if needed but excluding the cost of well decayed farm yard
manure)
Supply at Site Well Decayed Farm Yard Manure (Supply at site of work well decayed farm yard manure, from
11.11 any available source, approved by the engineer in charge including screening and stacking) cum 178.00 182.00 185.00
Supply at Site of Work/ Store - Deoiled Neem Cake (Supply at site of work/ store- deoiled neem cake duly
11.12 quintal 30.00 30.00 31.00
packed in used gunny bags)
11.13 Supplying Sludge (Supplying sludge duly stacked at site/ store) cum 137.00 139.00 142.00
Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre 1.25 metres, and height 1.2 metres,
above ground and 0.20 metre below ground (Half brick circular tree guard, in 2nd class brick, internal diametre
11.14 1.25 metres, and height 1.2 metres, above ground and 0.20 metre below ground, bottom two courses laid dry, each 1864.00 1899.00 1933.00
and top three courses in cement mortar 1:6 ( 1 cement 6 sand) and the intermediate courses being in dry
honey comb masonry, as per design complete)
Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class bricks, laid dry lengthwise, including
11.15 excavation, refilling, consolidation, with a hand packing and spreading nearly surplus earth within a lead of 50 metre 37.00 38.00 38.00
metres)
Making Tree Guard 53 cm dia and 1.3 m high as per design from empty bitumen drum (Making tree guard 53 cm
dia and 1.3 m high as per design from empty bitumen drum, slit suitably to permit sun and air, (supplied by the
11.16 department at stock issue rate) including providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets, each 392.00 400.00 407.00
complete in all respect)
Making Tree Guard 53 cm dia and 2 metres high as per design from empty bitumen drums (Making tree guard
53 cm dia and 2 metres high as per design from empty bitumen drums, slit suitably to permit sun and air,
11.17 ( supplied by the department at stock issue rate) including providing and fixing four legs 40 cm long of 30 x 3 each 746.00 760.00 774.00
mm MS riveted to tree guard and providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets complete in
all respects)
Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded work) (using angles, square
bars, tees and channel grills, grating frames, gates and tree guards of any size and design etc. including cost
11.18 of screens and welding rods or bolts and nuts complete fixed in position but without the cost of excavation and quintal 11852.00 12071.00 12291.00
concrete for fixing which will be paid separately)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2 metre high above ground
level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6 mm) iron rings in each tree
11.19 two halves, bolted together with 8 mm dia and 30 mm long bolts including painting two coats with paint of 2787.00 2836.00 2885.00
guard
approved brand over a coat of priming, complete in all respects.)
Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60 metre square, 2.00 metre
high fabricated with MS angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm and steel wire3 mm dia welded and each tree
11.20 3843.00 3912.00 3981.00
fabricated as per design in two halves bolted together) guard
Compensatory Afforestation (Planting trees as compensatory afforestation at the rate of 290 trees per hectare at
a spacing of 6 m by grubbing and leveling the ground upto a depth of 150 mm, digging holes 0.9 m dia, 1 m
11.21 deep, mixing farm yard/sludge manure with soil, planting of sapling 2 m high with 25 cm dia stem, backfilling hectare 130870.00 133293.00 135717.00
the hole and watering)
CHAPTER-12
FOUNDATIONS
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical
12.1 specification, including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and backfilling with approved material.)
I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 270.21 270.21 270.21
(ii) 3 m to 6 m depth cum 347.42 347.42 347.42
(iii) Above 6 m depth cum 463.22 463.22 463.22
B Mechanical Means
(i) Depth upto 3 m cum 75.89 84.48 148.87
(ii) Depth 3 m to 6 m cum 83.51 92.98 164.35
(iii) Depth above 6m cum 92.99 103.55 183.66
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 386.02 386.02 386.02
B Mechanical Means cum 460.61 523.00 770.69
III Hard rock ( requiring blasting )
A Manual Means cum 498.97 512.28 593.27
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 598.46 667.92 1017.21
V Marshy soil
(i) upto 3 m depth
A Manual means cum 1061.04 1061.04 1061.04
B Mechanical Means cum 264.57 280.62 404.53
VI Back Filling in Marshy Foundation Pits cum 746.82 746.82 746.82
Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate may be taken as
12.2
per items 13.4.)
12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification cum 1557.29 1560.27 1571.20
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate
12.4 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for cum 4809.75 4813.33 4826.44
14 days.)
Brick masonry work in cement mortar 1:3 in foundation complete excluding pointing and plastering, as per
12.5 cum 6826.71 6828.70 6836.04
drawing and technical specifications
12.6 A Cement mortar1:3 (1cement :3 sand) cum 4888.87 4888.87 4888.87
B Cement mortar1:2 (1cement :2 sand) cum 5840.34 5840.34 5840.34
C Cement mortar1:4 (1cement :4 sand) cum 4252.90 4252.90 4252.90
D Cement mortar1:6 (1cement :6 sand) cum 3702.28 3702.28 3702.28
Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification
12.7
(a) Square Rubble Coursed rubble masonry( first sort ) cum 5520.13 5520.13 5520.13
(b) Random Rubble Masonry cum 5331.78 5331.78 5331.78
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications
12.8
A PCC Grade M15
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 4974.42 4983.45 5016.61
Case II With Batching Plant, Transit Mixer and Manual placing cum 5352.74 5361.77 5394.93
B PCC Grade M20
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5594.95 5603.98 5637.14
Case II With Batching Plant, Transit Mixer and Manual placing cum 5973.27 5982.30 6015.46
C RCC Grade M20
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5627.34 5636.38 5669.53
Case II With Batching Plant, Transit Mixer and Manual placing cum 6059.19 6068.23 6101.38
D PCC Grade M25
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6093.20 6102.24 6135.39
Case II With Batching Plant, Transit Mixer and Manual placing cum 6471.52 6480.56 6513.71
E RCC Grade M25
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6183.77 6192.81 6225.96
Case II With Batching Plant, Transit Mixer and Manual placing cum 6588.85 6597.89 6631.04
F PCC Grade M30
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6141.76 6150.80 6183.95
Case II With Batching Plant, Transit Mixer and Manual placing cum 6520.08 6529.11 6562.27
G RCC Grade M30
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6229.34 6238.38 6271.53
Summary of Rate Analysis
Rate As Per Proposed Data Book
Case II With Batching Plant, Transit Mixer and Manual placing cum 6634.43 6643.46 6676.61
H RCC Grade M35
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6382.86 6391.89 6425.04
Case II With Batching Plant, Transit Mixer and Manual placing cum 6787.94 6796.97 6830.13
I RCC Grade M40
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6514.70 6523.73 6556.89
Case II With Batching Plant, Transit Mixer and Manual placing cum 6919.78 6928.82 6961.97
J RCC Grade M45
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6544.21 6553.25 6586.40
Case II With Batching Plant, Transit Mixer and Manual placing cum 6949.29 6958.33 6991.48
Providing and constructing temporary island 16 m diameter for construction of well foundation for 8m dia. Well.
12.9
A Assuming depth of water 1.0 m and height of island to be 1.25m. each 332326.69 332326.69 332326.69
B Assuming depth of water 4.0 m and height of island 4.5 m. each 1219147.44 1219147.44 1219147.44
Providing and constructing one span service road to reach island location from one pier location to another
C metre 5313.89 5313.89 5313.89
pier location
Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation complete as per
12.10 tonne 134241.50 134244.10 134249.23
drawing and technical specification.
Plain/Reinforced cement concrete, in well foundation complete as per drawing and technical specification
12.11
A Well curb
(i) RCC M20 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6351.33 6351.33 6351.33
Case II With Batching Plant, Transit Mixer and Manual placing cum 6770.77 6770.77 6770.77
(ii) RCC M25 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6962.48 6962.48 6962.48
Case II With Batching Plant, Transit Mixer and Manual placing cum 7381.92 7381.92 7381.92
(iii) RCC M30Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7015.06 7015.06 7015.06
Case II With Batching Plant, Transit Mixer and Manual placing cum 7434.51 7434.51 7434.51
(iv) RCC M35 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7192.19 7192.19 7192.19
Case II With Batching Plant, Transit Mixer and Manual placing cum 7611.64 7611.64 7611.64
(v) RCC M40Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7344.32 7344.32 7344.32
Case II With Batching Plant, Transit Mixer and Manual placing cum 7763.76 7763.76 7763.76
B Well steining
(I) PCC M15 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5131.46 5131.46 5131.46
Case II With Batching Plant, Transit Mixer and Manual placing cum 5515.95 5515.95 5515.95
(ii) PCC M20 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5787.79 5787.79 5787.79
Case II With Batching Plant, Transit Mixer and Manual placing cum 6172.28 6172.28 6172.28
(iii) RCC M20 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5822.05 5822.05 5822.05
Case II With Batching Plant, Transit Mixer and Manual placing cum 6206.54 6206.54 6206.54
(iv) PCC M25 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6314.79 6314.79 6314.79
Case II With Batching Plant, Transit Mixer and Manual placing cum 6699.28 6699.28 6699.28
(v) RCC M25 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6382.28 6382.28 6382.28
Case II With Batching Plant, Transit Mixer and Manual placing cum 6766.76 6766.76 6766.76
(vi) PCC M30 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6366.15 6366.15 6366.15
Case II With Batching Plant, Transit Mixer and Manual placing cum 6750.64 6750.64 6750.64
(vii) RCC M30 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6430.48 6430.48 6430.48
Case II With Batching Plant, Transit Mixer and Manual placing cum 6814.97 6814.97 6814.97
(viii) RCC M35 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6592.84 6592.84 6592.84
Case II With Batching Plant, Transit Mixer and Manual placing cum 6977.33 6977.33 6977.33
(ix) RCC M40 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6732.29 6732.29 6732.29
Case II With Batching Plant, Transit Mixer and Manual placing cum 7116.78 7116.78 7116.78
C Bottom Plug
(i) PCC Grade M20
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5555.70 5555.70 5555.70
Case II With Batching Plant, Transit Mixer and Manual placing cum 5966.10 5966.10 5966.10
(ii) PCC Grade M25
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6058.75 6058.75 6058.75
Case II With Batching Plant, Transit Mixer and Manual placing cum 6469.15 6469.15 6469.15
(iii) PCC Grade M30
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6107.77 6107.77 6107.77
Case II With Batching Plant, Transit Mixer and Manual placing cum 6518.17 6518.17 6518.17
(iv) PCC Grade M35
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6299.01 6299.01 6299.01
Summary of Rate Analysis
Rate As Per Proposed Data Book
Case II With Batching Plant, Transit Mixer and Manual placing cum 6709.41 6709.41 6709.41
D Intermediate plug
(I) Grade M20 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5291.88 5291.88 5291.88
Case II With Batching Plant, Transit Mixer and Manual placing cum 5682.60 5682.60 5682.60
(ii) Grade M25 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5771.04 5771.04 5771.04
Case II With Batching Plant, Transit Mixer and Manual placing cum 6161.76 6161.76 6161.76
(iii) Grade M30 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5817.24 5817.24 5817.24
Case II With Batching Plant, Transit Mixer and Manual placing cum 6207.96 6207.96 6207.96
E Top plug
(i) Grade M15 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 4783.68 4792.92 4824.60
Case II With Batching Plant, Transit Mixer and Manual placing cum 5148.00 5155.92 5187.60
(ii) Grade M20 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5380.32 5389.56 5421.24
Case II With Batching Plant, Transit Mixer and Manual placing 5744.64 5752.56 5784.24
(iii) Grade M25 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5859.48 5868.72 5900.40
Case II With Batching Plant, Transit Mixer and Manual placing cum 6223.80 6231.72 6263.40
(iv) Grade M30 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5905.68 5914.92 5914.92
Case II With Batching Plant, Transit Mixer and Manual placing cum 6270.00 6279.24 6310.92
F Well cap
(i) RCC Grade M20
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 5627.34 5636.38 5669.53
Case II With Batching Plant, Transit Mixer and Manual placing cum 6005.66 6014.70 6047.85
(ii) RCC Grade M25
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6157.01 6166.04 6199.20
Case II With Batching Plant, Transit Mixer and Manual placing cum 6535.33 6544.36 6577.52
(iii) RCC Grade M30
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6202.58 6211.62 6244.77
Case II With Batching Plant, Transit Mixer and Manual placing cum 6580.90 6589.93 6623.09
(iv) RCC Grade M35
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6356.09 6365.13 6398.28
Case II With Batching Plant, Transit Mixer and Manual placing cum 6734.41 6743.45 6776.60
(v) RCC M40 Grade cum
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6487.93 6496.97 6530.12
Case II With Batching Plant, Transit Mixer and Manual placing cum 6866.25 6875.29 6908.44
(vi) RCC M40 Grade cum
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 6517.45 6526.48 6559.64
Case II With Batching Plant, Transit Mixer and Manual placing cum 6895.77 6904.80 6937.96
Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
12.12 specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 5288.76 5288.76 5288.76
(ii) Beyond 3m upto 10m depth metre 7322.44 7322.44 7322.44
(iii) Beyond 10m upto 20m 9671.00 9671.00 9671.00
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 483.50 483.50 483.50
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 18141.00 18141.00 18141.00
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . 21769.30 21769.30 21769.30
(v) Beyond 30m upto 40 m metre
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a 43101.40 43101.40 43101.40
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 51721.70 51721.70 51721.70
B Clayey soil ( 6m dia. Well )
(i) Depth below bed level upto 3.0 M metre 7322.44 7322.44 7322.44
(ii) Beyond 3m upto 10m depth metre 16274.02 16274.02 16274.02
(iii) Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 21492.60 21492.60 21492.60
b Add for dewatering @ 5% of cost, if required. metre 22567.10 22567.10 22567.10
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 40312.90 40312.90 40312.90
b Add 5% of cost for dewatering of the cost, if required metre 50391.30 50391.30 50391.30
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 48375.50 48375.50 48375.50
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 95779.20 95779.20 95779.20
Summary of Rate Analysis
Rate As Per Proposed Data Book
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 15123.68 15123.68 15123.68
(ii) Beyond 3m upto 10m depth metre 10067.59 10067.59 10067.59
(iii) Beyond 10m upto 20m 13297.20 13297.20 13297.20
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 665.00 665.00 665.00
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 24942.10 24942.10 24942.10
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour) . metre 4988.40 4988.40 4988.40
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 59258.40 59258.40 59258.40
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 11851.70 11851.70 11851.70
B Clayey soil ( 7m dia. Well )
(I) Depth below bed level upto 3.0 M metre 10067.59 10067.59 10067.59
(ii) Beyond 3m upto 10m depth metre 16087.23 16087.23 16087.23
(iii) Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 21247.50 21247.50 21247.50
b Add for dewatering @ 5% of cost, if required. metre 1062.50 1062.50 1062.50
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 39856.40 39856.40 39856.40
b Add 5% of cost for dewatering on the cost, if required metre 1992.80 1992.80 1992.80
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 9964.30 9964.30 9964.30
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 94692.80 94692.80 94692.80
b Add 5% of cost for dewatering, if required metre 4734.70 4734.70 4734.70
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 107689.90 107689.90 107689.90
C Soft rock (7 m dia well )
(i) Extra over item no. 12.13 (A) & (B) irrespective of depth for sinking in Soft Rock metre 40950.44 40950.44 40950.44
D Hard rock (7 m dia well )
(i) Extra over item no. 12.13(A) & (B) irrespective of depth for sinking in Soft Rock metre 43006.51 43006.51 43006.51
E Bouldery strata(7 m dia well )
(i) Extra over item no. 12.13 (A) & (B) irrespective of depth for sinking in rock bouldery strata metre 34496.52 34496.52 34496.52
Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
12.14 specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 9356.11 9356.11 9356.11
(ii) Beyond 3m upto 10m depth metre 11422.62 11422.62 11423.00
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 15086.20 15086.20 15086.20
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 28299.10 28299.10 28299.10
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 5659.80 5659.80 5659.80
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 67236.20 67236.20 67236.20
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 80683.40 80683.40 80683.40
B Clayey soil ( 8m dia. Well )
(i) Depth upto 3.0 M metre 12304.83 12304.83 12304.83
(ii) Beyond 3m upto 10m depth metre 17121.57 17121.57 17121.57
(iii) Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 22613.20 22613.20 22613.20
b Add for dewatering @ 5% of cost, if required. metre 1130.80 1130.80 1130.80
(iv) Beyond 20m upto 30 m
Summary of Rate Analysis
Rate As Per Proposed Data Book
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 42417.40 42417.40 42417.40
b Add 5% of cost for dewatering on the cost, if required metre 2120.80 2120.80 2120.80
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 10604.40 10604.40 10604.40
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 100777.90 100777.90 100777.90
b Add 5% of cost for dewatering, if required metre 5038.90 5038.90 5038.90
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 20155.60 20155.60 20155.60
C Soft rock (8 m dia well )
(i) Extra over item no. 12.14 (A) & (B) irrespective of depth for sinking in Soft Rock metre 51318.81 51318.81 51318.81
D Hard rock (8 m dia well )
(i) Extra over item no. 12.14 (A) & (B) irrespective of depth for sinking in Soft Rock metre 49516.78 49516.78 49516.78
E Bouldery strata(8 m dia well )
(i) Extra over item no. 12.14 (A) & (B) irrespective of depth for sinking in rock bouldery strata metre 43432.77 43432.77 43432.77
Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
12.15 sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 9559.68 9559.68 9559.68
(ii) Beyond 3m upto 10m depth metre 12541.24 12541.24 12541.24
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 16561.50 16561.50 16561.50
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 31063.80 31063.80 31063.80
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 6212.90 6212.90 6212.90
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 73803.48 73803.48 73803.48
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 14760.80 14760.80 14760.80
B Clayey soil ( 9m dia. Well )
(i) Depth below bed level upto 3.0 M metre 13067.71 13067.71 13067.71
(ii) Beyond 3m upto 10m depth metre 18443.84 18443.84 18443.84
(iii) Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 24359.00 24359.00 24359.00
b Add for dewatering @ 5% of cost, if required. metre 1218.10 1218.10 1218.10
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 45691.60 45691.60 45691.60
b Add 5% of cost for dewatering on the cost, if required metre 2284.50 2284.50 2284.50
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 53884.90 53884.90 53884.90
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 108556.80 108556.80 108556.80
b Add 5% of cost for dewatering, if required metre 5427.90 5427.90 5427.90
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 21711.40 21711.40 21711.40
C Soft rock (9 m dia well )
(i) Extra over item no. 12.15 (A) & (B) irrespective of depth for sinking in Soft Rock metre 62832.87 62832.87 62832.87
D Hard rock (9 m dia well )
(i) Extra over item no. 12.15(A) & (B) irrespective of depth for sinking in Soft Rock metre 61588.65 61588.65 61588.65
E Bouldery strata (9 m dia well )
(i) Extra over item no. 12.15 (A) & (B) irrespective of depth for sinking in rock bouldery strata metre 53323.77 53323.77 53323.77
Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
12.16 specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 11186.21 11186.21 11186.21
(ii) Beyond 3m upto 10m depth metre 13320.54 13320.54 13320.54
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 17592.40 17592.40 17592.40
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 32997.90 32997.90 32997.90
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 6599.50 6599.50 6599.50
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 78397.10 78397.10 78397.10
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 15679.50 15679.50 15679.50
B Clayey soil (10m dia. Well )
(i) Depth below bed level upto 3.0 M metre 14994.54 14994.54 14994.54
(ii) Beyond 3m upto 10m depth metre 18766.70 18766.70 18766.70
Summary of Rate Analysis
Rate As Per Proposed Data Book
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 24922.18 24922.18 24922.18
(ii) Beyond 3m upto 10m depth metre 22067.87 22067.87 22067.87
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 29144.90 29144.90 29144.90
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 54668.10 54668.10 54668.10
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 10933.50 10933.50 10933.50
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 129884.50 129884.50 129884.50
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 25976.80 25976.80 25976.80
B Clayey soil (11 m dia. Well )
(i) Depth from bed level upto 3.0 M metre 24815.26 24815.26 24815.26
(ii) Beyond 3m upto 10m depth metre 39162.12 39162.12 39162.12
(iii) Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 51720.50 51720.50 51720.50
b Add for dewatering @ 5% of cost, if required. metre 2586.10 2586.10 2586.10
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 97014.20 97014.20 97014.20
b Add 5% of cost for dewatering on the cost, if required metre 4850.80 4850.80 4850.80
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 114410.40 114410.40 114410.40
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 230494.40 230494.40 230494.40
b Add 5% of cost for dewatering, if required metre 11524.80 11524.80 11524.80
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 46098.90 46098.90 46098.90
C Soft rock (11 m dia well )
(i) Extra over item no. 12.17(A) & (B) irrespective of depth for sinking in Soft Rock metre 89298.05 89298.05 89298.05
D Hard rock (11 m dia well )
(i) Extra over item no. 12.17 (A) & (B) irrespective of depth for sinking in Soft Rock metre 83917.49 83917.49 83917.49
E Bouldery strata (11 m dia well )
(i) Extra over item no. 12.17 (A) & (B) irrespective of depth for sinking in rock bouldery strata metre 75969.99 75969.99 75969.99
Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
12.18 specifications. Depth of sinking is reckoned from bed level.
A Sandy soil
(i) I) Depth below bed level upto 3.0 M metre 52846.68 52846.68 52846.68
(ii) Beyond 3m upto 10m depth metre 60873.86 60873.86 60873.86
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 80395.48 80396.60 80396.60
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 150801.50 150804.00 150804.00
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 30160.30 30160.70 30160.70
(v) Beyond 30m upto 40 m
Summary of Rate Analysis
Rate As Per Proposed Data Book
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 358284.20 358288.70 358288.70
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 71656.90 71657.80 71657.80
B Clayey soil (12 m dia. Well )
(i) Depth below bed level upto 3.0 M metre 60002.45 60002.45 60002.45
(ii) Beyond 3m upto 10m depth metre 94127.88 94127.88 94127.88
(iii) Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 124313.00 124313.00 124313.00
b Add for dewatering @ 5% of cost, if required. metre 6215.70 6215.70 6215.70
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 233178.60 233178.60 233178.60
b Add 5% of cost for dewatering on the cost, if required metre 11658.90 11658.90 11658.90
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 58294.80 58294.80 58294.80
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 554000.00 554000.00 554000.00
b Add 5% of cost for dewatering, if required metre 27700.00 27700.00 27700.00
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 110800.00 110800.00 110800.00
C Soft rock (12 m dia well )
(i) Extra over item no. 12.18 (A) & (B) irrespective of depth for sinking in Soft Rock metre 104249.18 104249.18 104249.18
D Hard rock (12 m dia well )
(i) Extra over item no. 12.18 (A) & (B) irrespective of depth for sinking in Soft Rock metre 96503.40 96503.40 96503.40
E Bouldery strata (12 m dia well )
(i) Extra over item no. 12.18 (A) & (B) irrespective of depth for sinking in rock bouldery strata metre 88725.21 88725.21 88725.21
Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all types of strata namely sandy
12.19 soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications.
Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 11897.69 11897.69 11897.69
(ii) Beyond 3m upto 10m depth metre 12911.24 12911.24 12911.24
(iii) Beyond 10m upto 20m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 17052.10 17052.10 17052.10
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 31986.60 31986.60 31986.60
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 6397.40 6397.40 6397.40
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 75995.90 75995.90 75995.90
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 15199.10 15199.10 15199.10
B Clayey soil (Twin D Type Well )
(i) Depth below bed level upto 3.0 M metre 14186.33 14186.33 14186.33
(ii) Beyond 3m upto 10m depth metre 20754.51 20754.51 20755.00
(iii) Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 27409.50 27409.50 27409.50
b Add for dewatering @ 5% of cost, if required. metre 1370.40 1370.40 1370.40
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 51412.50 51412.50 51412.50
b Add 5% of cost for dewatering on the cost, if required metre 2570.70 2570.70 2570.70
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 12853.20 12853.20 12853.20
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
a metre 122149.00 122149.00 122149.00
b Add 5% of cost for dewatering, if required metre 6107.60 6107.60 6107.60
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 24429.80 24429.80 24429.80
C Soft rock (Twin D Type well )
(i) Extra over item no. 12.19 (A) & (B) irrespective of depth for sinking in Soft Rock metre 63312.12 63312.12 63312.12
D Hard rock (Twin D Type well )
(i) Extra over item no. 12.19(A) & (B) irrespective of depth for sinking in Soft Rock metre 62404.91 62404.91 62404.91
E Bouldery strata (Twin D Type well )
(i) Extra over item no. 12.19 (A) & (B) irrespective of depth for sinking in rock bouldery strata metre 53723.15 53723.15 53723.15
Pneumatic sinking of wells with equipment of approved design, drawing and specifications worked by competent
and trained personnel and comprising of compression and decompression chambers, reducers, two air locks
separately for men and plant & materials, arrangement for supply of fresh air to working chambers, check
valves, exhaust valves, shafts made from steel plates of riveted construction not less than 6 mm thick to
withstand an air pressure of 0.50 MPa, controlled blasting of hard rock where required, staircases and 1 m wide
12.20 landing plateforms with railing, arrangement for compression and decompression, electric lighting of 50 V 258290.58 258290.58 258290.58
maximum, proper rooms for rest and medical examinations and compliance with safety precautions as per
IS:4138, all as per clause1208.8 of MoRTH Specifications.
Summary of Rate Analysis
Rate As Per Proposed Data Book
12.21 Sand filling in wells complete as per drawing and technical specifications cum 1506.32 1506.32 1506.32
Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells including fabricating and setting
12.22 tonne 118076.11 118076.11 122580.61
out as per detailed drawing
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical
12.23 specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-750 mm) metre 10116.56 10124.05 10208.53
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical
12.24 specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1000 mm) metre 13278.76 13294.30 13444.48
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical
12.25 specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1200 mm) metre 17429.33 17451.71 17667.96
Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per drawing and &
12.26 metre 10116.56 10124.05 10208.53
Technical Specification (Pile diameter - 750 mm)
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.27 metre 13278.76 13294.30 13444.48
Technical Specification (Pile diameter - 1000 mm)
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.28 metre 17429.33 17451.71 17667.96
Technical Specification (Pile diameter - 1200 mm)
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.29 metre 24255.62 24290.58 24628.48
Technical Specification (Pile diameter - 1500 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.30 metre 4332.60 4332.60 4332.60
Technical Specification (Pile Diameter=500 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.31 metre 6476.22 6476.22 6476.22
Technical Specification (Pile Diameter=750 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.32 metre 10431.93 10431.93 10431.93
Technical Specification (Pile Diameter=1000 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.33 metre 3607.69 3607.69 3607.69
Technical Specification (Size of pile - 300 mm x 300 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.34 metre 5108.14 5108.14 5108.14
Technical Specification (Size of pile - 500 mm x 500 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
12.35 metre 8004.92 8004.92 8004.92
Technical Specification (Size of pile - 750 mm x 750 mm)
Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section
12.36 metre 9685.67 9685.67 9685.67
steel column 400 x 250 mm (ISHB Series) )
Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section
12.37 metre 10855.90 10855.90 10855.90
steel column 450 x 250 mm (ISHB Series) )
12.38 Pile load test on single vertical pile in accordance with IS:2911(Part-IV) 500.00 500.00 500.00
Dismantling of Reinforced Concrete Pile head complete as per Drawing and Technical Specification
12.39 1601.66 1642.29 1670.28
Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical Specification
12.40
A RCC Grade M20
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 5476.30 5476.30 5476.30
(ii) With Batching Plant, Transit Mixer and Manual placing cum 5502.43 5502.43 5502.43
B RCC Grade M25
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 6005.97 6005.97 6005.97
(ii) With Batching Plant, Transit Mixer and Manual placing cum 6032.10 6032.10 6032.10
C RCC Grade M30
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 6051.54 6051.54 6051.54
(ii) With Batching Plant, Transit Mixer and Manual placing cum 6077.67 6077.67 6077.67
D RCC Grade M35
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 6205.05 6205.05 6205.05
(ii) With Batching Plant, Transit Mixer and Manual placing cum 6231.18 6231.18 6231.18
E RCC Grade M40
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 6336.89 6336.89 6336.89
(ii) With Batching Plant, Transit Mixer and Manual placing cum 6363.02 6363.02 6363.02
F RCC Grade M45
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 6366.41 6366.41 6366.41
(ii) With Batching Plant, Transit Mixer and Manual placing cum 6392.54 6392.54 6392.54
12.39 Levelling course for Pile cap
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 4783.10 4791.78 4823.66
(ii) With Batching Plant, Transit Mixer and Manual placing cum 5146.86 5155.55 5187.43
Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per drawing and
12.40 tonne 89099.75 89162.07 89283.90
technical specifications
Supplying, fitting and placing un-coated Mild steel reinforcement complete in foundation as per drawing and
12.41 tonne 83555.75 83618.07 83739.90
technical specification
CHAPTER-13
SUB-STRUCTURE
Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per drawing and
13.1 cum 6515.00 6517.00 6525.00
technical specifications
Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical specifications
13.2 sqm 100.66 100.66 100.66
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical specifications
13.3 sqm 1759.00 1760.00 1762.00
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications
13.4
Summary of Rate Analysis
Rate As Per Proposed Data Book
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm
13.8 dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. each 341.00 341.00 341.00
Complete as per drawing and Technical specifications
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification
13.9
A Granular material cum 1870.26 1870.26 1870.26
B Sandy material cum 1998.00 1998.00 1998.00
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind
13.10 abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and cum 1763.43 1763.43 1763.43
Technical Specification.
Supplying & laying of drainage composite for use behind walls, between two different fills, alongside drains of
road, below concrete lining of canals etc. Geocomposite for planar drainage, realized by thermos bonding a
draining core in extruded monofilaments with two filtering nonwoven geotextiles that may also be working as
separation or protecting layers. The draining three dimensional core will have a “W” configuration as longitudinal
parallel channels. Minimum thickness to be 7.2mm, with two filtering UV stabilized polypropylene nonwoven
geotextile of minimum thickness of 0.75 mm having pores of 150 micron and tensile strength of 8.0 kN/m that will
13.11 be working as separation or protecting layer, geocomposite having in plane flow capacity of 2.1 L / (m.s) at Sqm 670.00 670.00 670.00
hydraulic gradient of 1.0 & 20 kpa pressure and tensile strength of 18 kN/m , with mass per unit area of 740
gsm, supplied in the form of roll for easy transportation to site of work as per detailed specification all complete
as per directions of Engineer in charge.
Supplying & laying of drainage composite for use behind walls, between two different fills, alongside drains of
road, below concrete lining of canals etc. having thermobonding a draining core - HDPE geonet comprises of
two sets of parallel overlayed ribs integrally connected to have a rhomboidal shape with a polyethylene film and
a nonwoven geotextile having mass per unit area 130 g/m2 and tensile strength of 8.0 kN/m that will be working
as separation or protecting layer, geocomposite having in plane flow capacity of 0.7 L / (m.s) at hydraulic
gradient of 1.0 & 20 kPa pressure and tensile strength of 13.5 kN/ m , with mass per unit area of 830 gsm, at
13.12 easily accessible location including top and bottom, with all leads and lifts, manpower and machinery, materials, Sqm 795.91 795.91 795.91
labour etc. complete and as directed by Engineer - In - Charge.
Supplying, fitting and fixing in position true to line and level cast steel rocker bearing conforming to IRC: 83(Pt.-
1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and tonne
13.13 431.34 431.34 431.34
Technical Specifications. capacity
Supplying, fitting and fixing in position true to line and level forged steel roller bearing conforming to IRC: 83(Pt.-
1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and tonne
13.14 707.85 707.85 707.85
Technical Specifications. capacity
Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as per drawing and Technical Specifications and BS: 5400, tonne
13.15 section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications. 298.71 298.71 298.71
capacity
Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC: 83 (Part-II)
section IX and clause 2005 of MoRTH specifications complete including all accessories as per drawing and cubic
13.16 1.23 1.23 1.23
Technical Specifications. centimetre
Supplying, fitting and fixing in position true to line and level sliding plate bearing with stainless steel plate sliding
on stainless steel plate with mild steel matrix complete including all accessories as per drawing and Technical tonne
13.17 190.74 190.74 190.74
Specifications. capacity
Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston
supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE
surface sliding against stainless steel mating surface, completre assembly to be of cast steel/fabricated
structural steel, metal and elastomer elements to be as per IRC: 83 part-I & II respectively and other parts tonne
13.18 271.73 271.73 271.73
conforming to BS: 5400, section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete asper drawing capacity
and approved technical specifications.
13.19 Providing structural steel for sub-structure complete as per drawing and technical specifications tonne 157789.00 157789.00 157789.00
CHAPTER-14
SUPER-STRUCTURE
Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing and
14.1
Technical Specification
A RCC Grade M20
Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6439.00 6450.00 6488.00
(q) Height 5m to 10m cum 6708.00 6718.00 6758.00
(r) Height above 10m cum 6976.00 6987.00 7029.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6708.00 6718.00 6758.00
(q) Height 5m to 10m cum 6976.00 6987.00 7029.00
(r) Height above 10m cum 7244.00 7256.00 7299.00
B RCC Grade M25
Summary of Rate Analysis
Rate As Per Proposed Data Book
For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of concrete
(i)
(p) Height upto 5m cum 9265.00 9277.00 9320.00
(q) Height 5m to 10m cum 9952.00 9964.00 10010.00
(r) Height above 10m cum 10638.00 10651.00 10701.00
J PSC Grade M- 65
For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of concrete
(i)
(p) Height upto 5m cum 9265.00 9277.00 9320.00
(q) Height 5m to 10m cum 9952.00 9964.00 10010.00
(r) Height above 10m cum 10638.00 10651.00 10701.00
a) Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and
14.2 tonne 89676.00 89738.00 89860.00
technical specifications
High tensile steel wires/strands including all accessories for stressing, stressing operations and grouting
14.3 tonne 150849.00 150849.00 150849.00
complete as per drawing and Technical Specifications
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per
14.4 cum 12757.00 12757.00 12757.00
drawing and Technical Specifications
Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab excluding
prime coat with paving grade bitumen meeting the requirements given in table 500-39, prepared by using mastic
cooker and laid to required level and slope after cleaning the surface, including providing antiskid surface with
14.5 bitumen precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm sqm 470.00 470.00 470.00
and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the
temperature of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as
per clause 516.)
Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line and
grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not
14.6 to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved metre 2253.00 2253.00 2253.00
drawings and technical specifications.
Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line and grade,
tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to
14.7 exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved metre 2181.00 2181.00 2181.00
drawings and technical specifications.
Providing, fitting and fixing mild steel railing complete as per drawing and Technical Specification
14.8 metre 4458.00 4458.00 4458.00
14.9 Drainage Spouts complete as per drawing and Technical specification each 3785.00 3785.00 3785.00
PCC M15 Grade leveling course below approach slab complete as per drawing and Technical specification
14.10 cum
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 4974.00 4983.00 5017.00
(ii) With Batching Plant, Transit Mixer and Manual placing cum 5353.00 5362.00 5395.00
Reinforced cement concrete approach slab including reinforcement and formwork complete as per drawing and
14.11 cum 7077.00 7077.00 7077.00
Technical specification
Providing anti-corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy Coating (FBEC) (To be
14.12 tonne 7077.00 7077.00 7077.00
taken as per the prevailing market rates.)
Precast - pretensioned Girders (Providing, precasting, transportation and placing in position precast
14.13 cum 24906.00 31102.00 37323.00
pretensioned concrete girders as per drawing and technical specifications)
14.14 Providing and fixing Helical pipes in voided concrete slabs metre 481.00 481.00 481.00
Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement concrete, semi-rigid crash barrier
14.15 with metal beam and flexible crash barrier with wire ropes have been made and included in chapter-8 on Traffic Rmt
and Transportation.)
Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered
14.16 concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 Sqm 120.00 120.00 120.00
litre for 2 Sq.m. )
14.17 Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete as per drawing & Technical
(i) metre 3817.00 3817.00 3817.00
Specification.
Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing &
(ii) metre 51.00 51.00 51.00
Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply
supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm, covered with sealant
(iii) complete as per drawing and technical specifications. metre 83.00 83.00 83.00
Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand and
(iv) metre 44.00 44.00 44.00
6% bitumen by weight
Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for horizontal movement of 25 mm and
vertical movement of 2 mm, depth of joint varying from 75 mm to 100 mm, width varying from 500 mm to 750
mm (in traffic direction), covered with a closure plate of 200mm x 6mm of wieldable structural steel conforming
14.18 to IS: 2062, asphaltic plug to consist of polymer modified bitumen binder, carefully selected single size metre 1820.00 1820.00 1820.00
aggregate of 12.5 mm nominal size and a heat resistant foam caulking/backer rod, all as per approved drawings
and specifications.)
Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab steel expansion joint,
catering to right or skew (less than 20 deg., moderately curved with maximum horizontal movement upto 50 mm,
complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or
14.19 their authorised representative ensuring compliance to the manufacturer's instructions for installation and clause metre 22967.00 22967.00 22967.00
2605 of MoRTH specifications for road & bridge works..)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Compression Seal Joint (Providing and laying of compression seal joint consisting of steel armoured nosing at
two edges of the joint gap suitably anchored to the deck concrete and a preformed chloroprene elastomer or
14.20 closed cell foam joint sealer compressed and fixed into the joint gap with special adhesive binder to cater for a metre 5002.00 5002.00 5002.00
horizontal movement upto 40 mm and vertical movement of 3 mm.)
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to maximum horizontal
movement upto 70 mm, complete as per approved drawings and standard specifications to be installed by the
14.21 manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions metre 21153.00 21153.00 21153.00
for installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel expansion joint including
anchorage catering to a horizontal movement beyond 70 mm and upto 140mm, complete as per approved
14.22 drawings and standard specifications to be installed by the manufacturer/supplier or their authorised metre 21475.00 21475.00 21475.00
representative ensuring compliance to the manufacturer's instructions for installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal expansion joint catering to a
horizontal movement beyond 140mm and upto 210mm, complete as per approved drawings and standard
14.23 specifications to be installed by the manufacturer/supplier or their authorised representative ensuring metre 20706.00 20706.00 20706.00
compliance to the manufacturer's instructions for installation.)
Painting two coats after filling the surface with synthetic enamel paint bridge No. and span arrangements as per
14.24 as directed by Engineer. Nos. 227.00 227.00 227.00
14.25 Providing structural steel for super-structure complete as per drawing and technical specifications tonne 171509.00 171509.00 171509.00
CHAPTER-15
RIVER TRAINING AND PROTECTION WORKS
Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not
15.1 less than 40 kg each complete as per drawing and Technical specification.
A Boulder laid dry without wire crates. cum 1509.00 1509.00 1509.00
Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire crates made with 4mm dia
15.2 GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh (weaved diagonally) including 10% extra for cum 2346.00 2346.00 2346.00
laps and joints laid with stone boulders weighing not less than 40 kg each.)
Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with cement concrete blocks of
15.3 size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15 grade cement concrete with a minimum cum 3704.00 3704.00 3704.00
cement content of 250 kg/cum as per IRC: 21-2000.)
Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of
15.4 toe of embankment complete as per drawing and Technical specifications
Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case of dry rubble pitching or
pitching with stones in wire crates or it can be in PCC M15 nominal mix if cement concrete block have been
15.7 used for pitching . Rates for toe wall can be adopted from respective clauses depending upon approved design.
The rate for excavation for foundation, dry rubble masonry and PCC M15 have been analysed and given in
respective chapters.)
Providing and laying Flooring complete as per drawing and Technical specifications laid over cement concrete
15.8
bedding.
A Rubble stone laid in cement mortar 1:3 cum 4309.00 4309.00 4309.00
B Cement Concrete blocks Grade M15 cum 4878.00 4878.00 4878.00
15.9 Dry rubble Flooring cum 2252.00 2252.00 2252.00
15.10 Curtain wall complete as per drawing and Technical specification
A Stone masonry in cement mortar (1:3) cum 5520.00 5520.00 5520.00
B Cement concrete Grade M15 cum 4974.00 4974.00 4974.00
Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone boulders weighing not less
15.11 cum 1636.00 1636.00 1636.00
than 40 kg beyond curtain wall.
Gabian Structure for Retaining Earth (Providing and construction of a gabain structure for retaining earth with
segments of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5 m compartments by cross netting, made
from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming
15.12 to IS:280 and galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh size not cum 2412.00 2412.00 2412.00
exceeding 100 x 100 mm, filled with boulders with least dimension of 200 mm, all loose ends to be tied with 4
mm galvanised steel wire)
Gabian Structure for Erosion Control, River Training Works and Protection works (Providing and constructing
gabain structures for erosion control, river training works and protection works with wire crates of size 2 m x 1 m
x 0.3 m each divided into 1m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg
15.13 per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating cum 4095.00 4095.00 4095.00
conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 mm x 100 mm, filled
with boulders with least dimension of 200 mm, all loose ends to be securely tied with 4 mm galvanised steel
wire.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh
Gabion Boxes as per IS 16014:2012, MORT&H Clause 2500, of required size, Mesh Type 10x12 (D=100 mm
with tolerance of ± 2%) Zinc coated, Mesh wire diameter 3.0 mm, mechanically edged/selvedged with partitions
at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist,
15.14 tying with lacing wire of diameter 2.2 mm, supplied @3% by weight of Gabion boxes, filled with boulders with cum 1900.00 1900.00 1900.00
least dimension of 200 mm, as per drawing, all complete as per direction of Engineer-in-charge.
Laying of a fine aggregate concrete grade M30 filled fabric form for erosion protection of embankments
15.16 (Embankment Erosion Protection using Fine Aggregate Concrete Filled Fabric Form Mattress system) cum 4545.80 4545.80 4714.10
CHAPTER-16
REPAIR AND REHABILITATION
Removal of existing cement concrete wearing coat including its disposal complete as per Technical specification
without causing any detrimental effect to any part of the bridge structure and removal of dismantled material with
16.1 all lifts and lead upto 1000m(Thickness 75 mm) sqm 223.00 223.00 223.00
Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concrete laid over 12 mm thick
16.2 sqm 169.00 169.00 169.00
mastic asphalt including disposal with all lift and lead upto 1000m.
Guniting concrete surface with cement mortar applied with compressor after cleaning surface and spraying with
16.3 sqm 1271.00 1271.00 1271.00
epoxy complete as per Technical specification
Providing and inserting nipples with approved fixing compound after drilling holes for grouting as per Technical
16.4 specifications including subsequent cutting/removal and sealing of the hole as necessary of nipples after each 240.00 240.00 240.00
completion of grouting with Cement/Epoxy
Sealing of cracks/porous concrete by injection process through nipples/Grouting complete as per Technical
16.5
specification.
A Cement Grout kg 118.00 118.00 118.00
B Cement mortar (1:1) Grouting kg 285.00 285.00 285.00
Patching of damaged concrete surface with polymer concrete and curing compounds, initiator and promoter,
16.6 available in present formulations, to be applied as per instructions of manufacturer and as approved by the sqm 18233.00 18233.00 18233.00
Engineer.
Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as per clause 2803.1.
16.7 kg 1228.00 1228.00 1228.00
Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed steel
16.8 sqm 381.00 381.00 381.00
reinforcement complete as per Technical specification
Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture mechanically
with compressed air under pressure, comprising of cement, sand, coarse aggregates, water and quick setting
compound in the proportion as per clause 2807.1., sand and coarse aggregates conforming to IS: 383 and table
16.9 1 of IS: 9012 respectively, water cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 sqm 539.00 539.00 539.00
kg/cum, strength not less than 25 Mpa and workmanship conforming to clause 2807.6.
Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days for replacement of spalled
16.10 sqm 802.00 802.00 802.00
concrete
16.11 Eproxy bonding of new concrete to old concrete sqm 381.00 381.00 381.00
Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing
16.12 steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical tonne 433650.00 433650.00 433650.00
specification
Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing
16.13 steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical tonne 430642.00 430642.00 430642.00
specification
Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing
16.14 steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical tonne 394358.00 394358.00 394358.00
specification
16.15 Replacement of bearings complete as per Technical specification each 119549.00 119549.00 119549.00
16.16 Rectification of bearings as per Technical specifications each 16589.00 16589.00 16589.00
16.17 Replacement of Expansion Joints complete as per drawings metre 3450.00 3450.00 3450.00
16.18 Replacement of damaged concrete railing. metre 535.00 535.00 535.00
16.19 Replacement of crash barrier. metre 954.00 954.00 954.00
16.20 Replacement of damaged mild steel railing metre 452.00 452.00 452.00
Repair of crash barrier (Repair of concrete crash barrier with cement concrete of M-30 grade by cutting and
16.21 trimming the damaged portion to a regular shape, cleaning the area to be repaired thoroughly, applying cement metre 245.00 245.00 245.00
concrete after erection of proper form work.)
16.22 Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original shape.) metre 151.00 151.00 151.00
16.23 Repair of steel Railing (Repair of steel railing to bring it to the original shape) metre 423.00 423.00 423.00
Soil Nailing with fully threaded hot-dip galvanized solid geotechnical bars as soil nails (galvanization minimum
16.24 500 grams per sqm) of minimum 25 mm diameter, having yield strength > 670N/mm2 and tensile strength > metre 3995.00 3995.00 3995.00
800N/mm2
Precasting and Installation of precast concrete arch units followed by stage wise filling with selected fill materials
on both side of the arch units. This includes construction of reinforced earth head walls and wing walls to provide
confinement to the selected fill material, complete as per approved drawings and standard specifications to be
16.25 precasted, stacked, transported and installed as per the methodology, design and drawings of system suppliers metre 1048044.00 1048044.00 1048044.00
or their authorised representative ensuring compliance to the system supplier's instruction.
Summary of Rate Analysis
Rate As Per Proposed Data Book
Supply and installation of In-Situ Soil reinforcement with fully threaded hot-dip galvanized solid geotechnical
bars as soil nails (galvanization minimum 500 grams per sqm) of minimum 25 mm diameter, having yield
strength > 670N/mm2 and tensile strength > 800N/mm2 as per technical specifications and drawings etc.
16.26 complete including drilling, flushing,grouting, and all Supply and installation of all components listed as per metre 4052.00 4052.00 4052.00
technical specifications and drawings etc and considering all lead, lift and machinery .
CHAPTER-17
TUNNEL WORK
Excavation for Portal in Ordinary Rock with hydraulic excavator including cutting and loading in tippers, trimming
17.1 bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and disposal of Cum 602.10
excavated materials including all lifts and lead upto 1000 m
Excavation for Portal in Hard Rock (blasting prohibited) with hydraulic excavator including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections,
17.2 and and disposal of excavated materials including all lifts and lead upto 1000m Cum 487.70
Excavation for portal in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and
17.3 side slopes, in accordance with requirements of lines, grades and cross sections, and and disposal of excavated Cum 97.60
materials including all lifts and lead upto 1000m
Excavation for tunnel by using drilling & blasting methods in all types of rock including cost of all
materials,machinery, labour, scaling excavated surface, marking, ventilation, lighting, drainage, removing and
17.4 hauling the excavated muck outside tunnel upto specified dump area and all other ancillary operations etc. Cum 1335.80
Dewatering in tunnel by pumping out water collected by natural drainage inside tunnel including providing sump
17.5 wherever necessary, cost of all materials, machinery, labour, drainage and all other ancillary operations etc., 507.80
complete.
Providing , Fitting and Placing of Ribs including Fabrication, Erection,Temporary fixture, Handling of material
17.6 inside fabrication workshop, final matching, field welding and complete as per Drawing and Technical tonne 129901.70
Specifications.
Shotcreting to upper bench / lower bench with steel fiber reinforced shotcrete (SFRS) , shotcrete compressive
17.7 strength shall be 25 N/mm2 and complete as per Drawing and Technical Specifications. cum 14158.70
Shotcreting to upper bench / lower bench with welded wiremesh , shotcrete compressive strength shall be 25
17.8 cum 10597.10
N/mm2 and complete as per Drawing and Technical Specifications.
Providing and fixing 25 mm diameter 3 meter long steel rock bolts including drilling 45 mm dia holes, plate,
17.9 nuts, cement grout, cost of all materials, machinery, labour, ventilation, lighting, drainage and all other ancillary Nos. 2622.30
operations etc. complete as per Drawing and Technical Specifications.
Providing and fixing 32 mm diameter 7 meter long steel rock bolts including drilling 51 mm dia holes, plate,
17.10 nuts, cement grout, cost of all materials, machinery, labour, ventilation, lighting, drainage and all other ancillary Nos. 6781.00
operations etc. complete as per Drawing and Technical Specifications.
Grouting cement slurry in grout holes under specified pressure for consolidation / contact grouting including cost
of all materials, machinery, labour, redrilling wherever necessary, ventilation,lighting, drainage and other
17.11 ancillary operations etc. complete as per Drawing and Technical Specifications. tonne 17680.50
Mass Concrete for Tunnel (Furnishing and Placing Reinforced cement concrete in Tunnel Work as per drawing
17.12
and Technical Specificatio.)
A RCC Grade M20
(i) With Batching Plant, Transit Mixer and Manual placing Cum 7428.00
B RCC Grade M25
(i) With Batching Plant, Transit Mixer and Manual placing Cum 8113.00
C RCC Grade M30
(i) With Batching Plant, Transit Mixer and Manual placing Cum 8202.00
D RCC Grade M35
(i) With Batching Plant, Transit Mixer and Manual placing Cum 8409.00
E RCC Grade M40
(i) With Batching Plant, Transit Mixer and Manual placing Cum 8586.00
F RCC Grade M45
(i) With Batching Plant, Transit Mixer and Manual placing Cum 8626.00
G RCC Grade M50
(i) With Batching Plant, Transit Mixer and Manual placing Cum 9381.00
H RCC Grade M55
(i) With Batching Plant, Transit Mixer and Manual placing Cum 9524.00
I RCC Grade M60
(i) With Batching Plant, Transit Mixer and Manual placing Cum 9772.00
J RCC Grade M65
(i) With Batching Plant, Transit Mixer and Manual placing Cum 9845.00
Supplying, fitting and placing HYSD bar reinforcement in Tunnel Work complete as per drawing and technical
17.13 tonne 90015.00
specifications
CHAPTER-18
ENVIRONMENTAL MANAGEMENT & BIO ENGINEERING
18.1 Construction of bamboo crib wall complete as per drawing and Technical specification. Rm. 478.00
18.2 Construction of Fascines with a bundle of sticks complete as per drawing and Technical specification. Rm. 295.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
18.3 Contruction and laying of brush Layers across the slope complete as per drawing and Technical specification. Sqm. 202.00
Construction of vegetative Palisades in Rills using hard wood cutting complete as per drawing and Technical
18.4 Rm. 871.00
specification.
18.5 Laying of Palisades in Slopes complete as per drawing and Technical specification. Sqm. 202.00
Sprinkling of water in the sellement and working area as per instruction of CSC (May to Sept month of each year
18.6 is excluded for any claim by Contructor Sprinkling. Any isolated water sprinkling required shall be carried by Rm. 478.00
Contractor and shall be considered as incidental to the Cotract)
CHAPTER-1
CARRIAGE OF MATERIALS
Reference to
Rate Amount Remarks/ Input
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) ref.
Specification
1.1 A Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding
time for haulage and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point Min 1.00
ii) Loading by front end loader 1 cum bucket Min 6.63
capacity
iii) Maneuvering, reversing, dumping and turning Min 2.00
for return
iv) Waiting time, unforeseen contingencies etc Min 4.00
CARRIAGE OF MATERIALS
Reference to
Rate Amount Remarks/ Input
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) ref.
Specification
iv) Waiting time, unforeseen contingencies etc Min 4.00
CARRIAGE OF MATERIALS
Reference to
Rate Amount Remarks/ Input
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) ref.
Specification
Per Cum Basic Cost of Labour & Machinery (a+b) 532.38
excluding OH & CP
b) Overheads @ 8% on (a) 766.62
c) Contractors profit @ 10% on (a+b) 1034.94
Cost for 18 tonnes = a+b+c+d 11384.33
Rate per tonnes = (a+b+c+d)/18 632.46
Say, 632.50
CARRIAGE OF MATERIALS
Reference to
Rate Amount Remarks/ Input
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) ref.
Specification
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 32 tonnes load and lead 10 km = 320 t.km
CARRIAGE OF MATERIALS
Reference to
Rate Amount Remarks/ Input
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) ref.
Specification
Per tonne km Basic Cost of Machinery (a) 7.77
excluding OH & CP
b) Overheads @ 8% on (a) 155.40
c) Contractors profit @ 10% on (a+b) 209.79
Cost for 250 t .km = a+b+c 2307.69
Rate per t.Km = (a+b+c)/250 9.23
Say, 9.20
CARRIAGE OF MATERIALS
Reference to
Rate Amount Remarks/ Input
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) ref.
Specification
C Case-III : Katcha Track and Track in river bed /
nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 25 tonnes load and lead 10 km = 250 t.km
Unit : t.km
Taking output 15 tonnes load and lead 10 km = 150 t.km
CARRIAGE OF MATERIALS
Reference to
Rate Amount Remarks/ Input
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) ref.
Specification
Speed while returning empty : 30 km / hour
a) Machinery
I) Transit Mixture 6 cum capacity P&M-34001
Time taken for onward hanlage with load hour 0.500 2198.00 1099.00 P&M-34001
Time taken for empty return trip hour 0.333 2198.00 732.67 P&M-34001
Per tonne km Basic Cost of Machinery (a) 12.22
excluding OH & CP
b) Overheads @ 8% on (a) 146.53
c) Contractors profit @ 10% on (a+b) 197.82
Cost for 150 t .km = a+b+c 2176.02
Rate per t.Km = (a+b+c)/150 14.51
Say, 14.50
Unit : cum
Taking Output = 1125 tonne (750 cum)
a) Labour
Mate day 0.320 622.00 199.04
Mazdoor Skilled day 2.000 592.00 1184.00 L-15
Mazdoor day 6.000 560.00 3360.00 L-13
b) Material
Stone Boulder of size 150 mm and below cum 750.000 350.00 262500.00 M-001
c) Machinery
Integrated stone crusher of 250 TPH including Hour
belt conveyor and vibrating screens 6.000 14570.00 87420.00 P&M-16001
CHAPTER-1
CARRIAGE OF MATERIALS
Reference to
Rate Amount Remarks/ Input
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) ref.
Specification
Generator 725 KVA Hour 6.000 10098.00 60588.00 P&M-22001
Front end loader 3.1 cum bucket capacity at Hour
quarry and crusher 5.515 3907.00 21545.96 P&M-5001
Tipper 14 cum capacity for loading at quarry site Hour
5.515 2331.00 12854.78 P&M-6002
Tipper 14 cum capacity for transportation within
1 km t.km 1125.000 15.54 17482.50 P&M-73003
d) Cost for 750 cum = (a+b+c) 467134.28
e) Crushing Pattern
40 mm (tonne) 22.71% 255.488
20 mm (tonne) 23.00% 258.750
10 mm (tonne) 25.86% 290.925
Dust (tonne) 28.43% 319.838
f) % Cost distribution { (d) x (f) / (e ) x 1.5 }
40 mm Cum 28.98% 794.81 Basic Cost
20 mm Cum 31.95% 865.21 Basic Cost
10 mm Cum 30.75% 740.62 Basic Cost
Dust Cum 8.32% 182.27 Basic Cost
g) Overheads @ 8% on (f)
40 mm 63.58
20 mm 69.22
10 mm 59.25
Dust 14.58
h) Contractors profit @ 10% on (f) and (g)
40 mm 85.84
20 mm 93.44
10 mm 79.99
Dust 19.69
i) Rate per cum = (f+g+h)
40 mm 944.23
20 mm 1027.87
10 mm 879.86
Dust 216.54
Say, 944.20
Say, 1027.90
Say, 879.90
Say, 216.50
Note: The average density of 1.5 tonne/cum is only a
reference density in this Data Book.
Unit : cum
Taking Output = 1125 tonne (750 cum)
a) Labour
Mate day 0.320 622.00 199.04 L-12
Mazdoor Skilled day 2.000 592.00 1184.00 L-15
Mazdoor day 6.000 560.00 3360.00 L-13
b) Material
Stone Boulder of size 150 mm and below cum 750.000 350.00 262500.00 0.00
c) Machinery
Integrated stone crusher of 250 TPH including
belt conveyor and vibrating screens (for
producing crusher run production capacity will Hour 4.615 14570.00 67246.15 P&M-16001
increas by 30%)
Generator 725 KVA Hour 4.615 10098.00 46606.15 P&M-22001
Front end loader 3.1 cum bucket capacity at
quarry and crusher Hour 5.515 3907.00 21545.96 P&M-5001
Tipper 14 cum capacity for loading at quarry site
Hour 5.515 2331.00 12854.78 P&M-6002
Tipper 14 cum capacity for transportation within
1 km t.km 1125.000 15.54 17482.50 P&M-73003
CARRIAGE OF MATERIALS
Reference to
Rate Amount Remarks/ Input
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) ref.
Specification
d) Overheads @ 8% on (a+b+c) 34638.29
e) Contractors profit @ 10% on (a+b+c+d) 46761.69
Cost for 900 cum = (a+b+c+d+e) 514378.56
Rate per cum = (a+b+c+d+e)/900 571.53
Say, 571.50
Note: Considering Crushed volume will be 1.2 times the
volume of boulder
CHAPTER-2
SITE CLEARANCE
Amount
Quantity
Reference to (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.000 1748.000 8740.000 P&M-3003
(ii) 1.1 cum bucket capacity hour 5.500 1748.000 9614.000 P&M-3004
(iii) 0.9 cum bucket capacity hour 6.500 2570.000 16705.000 P&M-3005
Tipper
(i) 18 cum capacity hour 0.758 2621.000 1985.606 P&M-6001
(ii) 14 cum capacity hour 1.000 2331.000 2331.000 P&M-6002
(iii) 10 cum capacity hour 1.471 2077.000 3054.412 P&M-6003
c) Overhead charges @ 8% on @ 10% on @ 12% on 904.839 1252.988 2441.315
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1221.532 1378.287 2278.561
(a+b+c) (a+b+c) (a+b+c)
Rate for each tree = (a+b+c+d)/25 537.474 606.446 1002.567
Say, 537.50 606.40 1002.60
(iv) Girth above 1800 mm
Unit = Each
Taking output = 20 nos
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoors day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.000 1748.000 8740.000 P&M-3003
(ii) 1.1 cum bucket capacity hour 5.500 1748.000 9614.000 P&M-3004
(iii) 0.9 cum bucket capacity hour 6.500 2570.000 16705.000 P&M-3005
Tipper
(i) 18 cum capacity hour 0.714 2621.000 1872.143 P&M-6001
(ii) 14 cum capacity hour 1.000 2331.000 2331.000 P&M-6002
(iii) 10 cum capacity hour 1.429 2077.000 2967.143 P&M-6003
c) Overhead charges @ 8% on @ 10% on @ 12% on 895.762 1252.988 2430.843
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1209.278 1378.287 2268.787
(a+b+c) (a+b+c) (a+b+c)
Rate for each tree = (a+b+c+d)/20 665.103 758.058 1247.833
Say, 665.10 758.10 1247.80
All the serviceable material resulting from girth removal
Note: would be handed over to the employer for the all above
items.
2.2 201 Clearing Grass and Removal of Rubbish
Clearing grass and removal of rubbish up to a distance
of 50 metres outside the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate day 2.000 2.000 2.000 622.000 1244.000 1244.000 1244.000 L-12
Mazdoor day 50.000 50.000 50.000 560.000 28000.000 28000.000 28000.000 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on 2339.520 2924.400 3509.280
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on 3158.352 3216.840 3275.328
(a+b) (a+b) (a+b)
Rate per Hectare = a+b+c 34741.872 35385.240 36028.608
Say, 34741.90 35385.20 36028.60
2.3 201 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting
rank vegetation, grass, bushes, shrubs, saplings and
trees girth up to 300 mm, removal of stumps of trees
cut earlier and disposal of unserviceable materials and
stacking of serviceable material to be used or
auctioned, up to a lead of 1000 metres including
removal and disposal of top organic soil not exceeding
150 mm in thickness.
Unit = Hectare
Taking output = 1 Hectare
(i) By Manual Means:-
A In area of light jungle
a) Labour
Mate day 6.000 6.000 6.000 622.000 3732.000 3732.000 3732.000 L-12
Mazdoor day 150.000 150.000 150.000 560.000 84000.000 84000.000 84000.000 L-13
b) Machinery
Tractor-trolley hour 122.222 122.222 122.222 820.00 100222.222 100222.222 100222.222 P&M-12001
c) Overhead charges @ 8% on (a+b) 15036.338 18795.422 22554.507
d) Contractor's profit @ 10% on (a+b+c) 20299.056 20674.964 21050.873
Rate per Hectare = a+b+c+d 223289.616 227424.609 231559.602
Say, 223289.60 227424.60 231559.60
B In area of thorny jungle
a) Labour
Mate day 8.000 8.000 8.000 622.000 4976.000 4976.000 4976.000 L-12
Mazdoor day 200.000 200.000 200.000 560.000 112000.000 112000.000 112000.000 L-13
b) Machinery
Tractor-trolley hour 122.222 122.222 122.222 820.00 100222.222 100222.222 100222.222 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 17375.858 21719.822 26063.787
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 23457.408 23891.804 24326.201
(a+b+c) (a+b+c) (a+b+c)
Rate per Hectare = a+b+c+d 258031.488 262809.849 267588.210
Say, 258031.50 262809.80 267588.20
2.3 (ii) By Mechanical Means using Dozer
A In area of light jungle
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Dozer
(i) Dozer (240HP) hour 5.952 3005.00 17886.905 P&M-1001
(ii) Dozer (175 HP) hour 7.692 2099.00 16146.154 P&M-1002
(iii) Dozer (90 HP) hour 13.889 1267.00 17597.222 P&M-1003
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 1500.000 6.830 10245.000 P&M-72002
(ii) 14 cum capacity t.km 1500.000 7.770 11655.000 P&M-73002
(iii) 10 cum capacity t.km 1500.000 9.620 14430.000 P&M-74002
Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1000.000 84.60 84600.00 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1000.000 84.52 84520.00 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum cum 1000.000 117.86 117860.00 P&M-77003
capacity Loader
c) Overhead charges @ 8% on @ 10% on @ 12% on 9112.133 11349.091 18126.838
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 12301.380 12484.001 16918.382
(a+b+c) (a+b+c) (a+b+c)
Rate per Hectare = a+b+c+d 135315.178 137324.006 186102.202
Say, 135315.20 137324.00 186102.20
2.3 B In area of thorny jungle
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Dozer
(i) Dozer (240HP) hour 7.440 3005.00 22358.631 P&M-1001
(ii) Dozer (175 HP) hour 9.615 2099.00 20182.692 P&M-1002
(iii) Dozer (90 HP) hour 17.361 1267.00 21996.528 P&M-1003
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 1500.000 6.830 10245.000 P&M-72002
(ii) 14 cum capacity t.km 1500.000 7.770 11655.000 P&M-73002
(iii) 10 cum capacity t.km 1500.000 9.620 14430.000 P&M-74002
Loading & unloading charges for disposed of
grabbed material
CHAPTER-2
SITE CLEARANCE
Amount
Quantity
Reference to (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1000.000 84.60 84600.00 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1000.000 84.52 84520.00 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum cum 1000.000 117.86 117860.00 P&M-77003
capacity Loader
c) Overhead charges @ 8% on @ 10% on @ 12% on 9469.871 11752.745 18654.755
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 12784.326 12928.020 17411.104
(a+b+c) (a+b+c) (a+b+c)
Rate per Hectare = a+b+c+d 140627.588 142208.217 191522.147
Say, 140627.60 142208.20 191522.10
2.3 (iii) By Mechanical Means using Motor Grader
A In area of light jungle
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 4.032 5796.000 23370.968 P&M-2001
(ii) Motor grader 3.70 metre blade hour 4.864 5316.000 25856.031 P&M-2002
(iii) Motor grader 3.35 metre blade hour 5.423 1576.000 8547.190 P&M-2003
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 1500.000 6.830 10245.000 P&M-72002
(ii) 14 cum capacity t.km 1500.000 7.770 11655.000 P&M-73002
(iii) 10 cum capacity t.km 1500.000 9.620 14430.000 P&M-74002
Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1000.000 84.60 84600.00 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1000.000 84.52 84520.00 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum cum 1000.000 117.86 117860.00 P&M-77003
capacity Loader
c) Overhead charges @ 8% on @ 10% on @ 12% on 9504.068 12261.591 16970.648
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 12830.492 13487.750 15839.272
(a+b+c) (a+b+c) (a+b+c)
Rate per Hectare = a+b+c+d 141135.407 148365.252 174231.990
Say, 141135.40 148365.30 174232.00
2.3 B In area of thorny jungle
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 5.040 5796.000 29213.710 P&M-2001
(ii) Motor grader 3.70 metre blade hour 6.080 5316.000 32320.039 P&M-2002
(iii) Motor grader 3.35 metre blade hour 6.779 1576.000 10683.987 P&M-2003
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 1500.000 6.830 1475.280 P&M-72002
(ii) 14 cum capacity t.km 1500.000 7.770 1678.320 P&M-73002
(iii) 10 cum capacity t.km 1500.000 9.620 2077.920 P&M-74002
Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1000.000 84.60 84600.00 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1000.000 84.52 84520.00 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum cum 1000.000 117.86 117860.00 P&M-77003
capacity Loader
c) Overhead charges @ 8% on @ 10% on @ 12% on 9269.910 11910.324 15744.814
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 12514.378 13101.356 14695.160
(a+b+c) (a+b+c) (a+b+c)
Rate per Hectare = a+b+c+d 137658.157 144114.919 161646.762
Say, 137658.20 144114.90 161646.80
2.4 202 Dismantling of Structures
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of
masonry, cement concrete, wood work, steel work,
including T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 metres
Unit = cum
Taking output = 1.25 cum
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade M-10 and
below
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor for dismantling and loading day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Tractor-trolley (considering 15 min loading time) hour 0.299 0.299 0.299 820.00 244.861 244.861 244.861 P&M-12001
b) Machinery
Tractor-trolley (considering 15 min loading time) hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
b) Machinery
Air Compressor 250 cfm hour 0.625 0.625 0.625 550.000 343.750 343.750 343.750 P&M-15001
Pneumatic breaker @ 1 cum per hour hour 1.250 1.250 1.250 11.000 13.750 13.750 13.750 P&M-45001
Tipper
For transportation to dumping yard considering
lead @ 1 km
(i) 18 cum capacity t.km 1.875 6.830 12.806 P&M-72002
(ii) 14 cum capacity t.km 1.875 7.770 14.569 P&M-73002
(iii) 10 cum capacity t.km 1.875 9.620 18.038 P&M-74002
Loading & unloading charges for disposed of
material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1.250 84.60 105.75 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1.250 84.52 105.65 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum cum 1.250 117.86 147.33 P&M-77003
capacity Loader
c) Overhead charges @ 8% on @ 10% on @ 12% on 61.480 77.016 97.836
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 82.998 84.717 91.314
(a+b+c) (a+b+c) (a+b+c)
Cost for 1.25 cum = a+b+c+d 912.974 931.892 1004.453
Rate per cum = (a+b+c+d)/ 1.25 730.379 745.514 803.562
Say, 730.40 745.50 803.60
2.4 B Prestressed / reinforced cement concrete grade M-20
& above
Unit = cum
Taking output = 1.25 cum
a) Labour
Mate day 0.050 0.050 0.050 622.000 31.100 31.100 31.100 L-12
Mazdoor with Pneumatic breaker and for loading day 0.910 0.910 0.910 560.000 509.600 509.600 509.600 L-13
and unloading
Blacksmith day 0.250 0.250 0.250 622.000 155.500 155.500 155.500 L-02
b) Machinery
Air Compressor 250 cfm hour 0.625 0.625 0.625 550.000 343.750 343.750 343.750 P&M-15001
Pneumatic breaker @ 1 cum per hour hour 1.250 1.250 1.250 11.000 13.750 13.750 13.750 P&M-45001
Tipper
For transportation to dumping yard considering
lead @ 1 km
(i) 18 cum capacity t.km 1.875 6.830 12.806 P&M-72002
(ii) 14 cum capacity t.km 1.875 7.770 14.569 P&M-73002
(iii) 10 cum capacity t.km 1.875 9.620 18.038 P&M-74002
Loading & unloading charges for disposed of
material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1.250 84.60 105.75 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1.250 84.52 105.65 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum cum 1.250 117.86 147.33 P&M-77003
capacity Loader
c) Overhead charges @ 8% on @ 10% on @ 12% on 93.781 117.392 146.288
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 126.604 129.131 136.535
(a+b+c) (a+b+c) (a+b+c)
Cost for 1.25 cum = a+b+c+d 1392.640 1420.442 1501.885
Rate per cum = (a+b+c+d)/ 1.25 1114.112 1136.353 1201.508
Say, 1114.10 1136.40 1201.50
2.4 (ii) Dismantling Brick / Tile work
By Manual Means
A In lime mortar
a) Labour
Mate day 0.020 0.020 0.020 622.000 12.440 12.440 12.440 L-12
Mazdoor for dismantling, loading and unloading day 0.500 0.500 0.500 560.000 280.000 280.000 280.000 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
c) Overhead charges @ 8% on (a+b) 40.251 50.313 60.376
d) Contractor's profit @ 10% on (a+b+c) 54.339 55.345 56.351
Cost for 1.25 cum = a+b+c+d 597.724 608.793 619.862
Rate per cum = (a+b+c+d)/ 1.25 478.179 487.034 495.889
Say, 478.20 487.00 495.90
2.4 B In cement mortar
a) Labour
Mate day 0.030 0.030 0.030 622.000 18.660 18.660 18.660 L-12
Mazdoor for dismantling, loading and unloading day 0.750 0.750 0.750 560.000 420.000 420.000 420.000 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 51.948 64.935 77.923
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 70.130 71.429 72.728
(a+b+c) (a+b+c) (a+b+c)
Cost for 1.25 cum = a+b+c+d 771.433 785.719 800.005
Rate per cum = (a+b+c+d)/ 1.25 617.146 628.575 640.004
Say, 617.10 628.60 640.00
2.4 C In mud mortar
a) Labour
Mate day 0.016 0.016 0.016 622.000 9.952 9.952 9.952 L-12
Mazdoor for dismantling and loading day 0.400 0.400 0.400 560.000 224.000 224.000 224.000 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 35.572 44.465 53.358
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 48.022 48.911 49.800
(a+b+c) (a+b+c) (a+b+c)
Cost for 1.25 cum = a+b+c+d 528.240 538.022 547.804
Rate per cum = (a+b+c+d)/ 1.25 422.592 430.418 438.244
Say, 422.60 430.40 438.20
2.4 D Dry brick pitching or brick soling
a) Labour
Mate day 0.014 0.014 0.014 622.000 8.708 8.708 8.708 L-12
Mazdoor for Dismantling, loading and unloading day 0.350 0.350 0.350 560.000 196.000 196.000 196.000 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 33.232 41.540 49.848
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 44.863 45.694 46.525
(a+b+c) (a+b+c) (a+b+c)
Cost for 1.25 cum = a+b+c+d 493.498 502.637 511.776
Rate per cum = (a+b+c+d)/ 1.25 394.798 402.110 409.421
Say, 394.80 402.10 409.40
2.4 (iii) Dismantling Stone Masonry
I By Manual Means
A Rubble stone masonry in lime mortar
a) Labour
Mate day 0.024 0.024 0.024 622.000 14.928 14.928 14.928 L-12
Mazdoor for dismantling, loading and unloading. day 0.600 0.600 0.600 560.000 336.000 336.000 336.000 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 44.930 56.162 67.395
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 60.655 61.778 62.902
(a+b+c) (a+b+c) (a+b+c)
Cost for 1.25 cum = a+b+c+d 667.207 679.563 691.919
Rate per cum = (a+b+c+d)/ 1.25 533.766 543.651 553.535
Say, 533.80 543.70 553.50
2.4 B Rubble stone masonry in cement mortar.
a) Labour
Mate day 0.030 0.030 0.030 622.000 18.660 18.660 18.660 L-12
Mazdoor for dismantling, loading and unloading. day 0.750 0.750 0.750 560.000 420.000 420.000 420.000 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 51.948 64.935 77.923
(a+b) (a+b) (a+b)
CHAPTER-2
SITE CLEARANCE
Amount
Quantity
Reference to (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 40.251 50.313 60.376
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 54.339 55.345 56.351
(a+b+c) (a+b+c) (a+b+c)
Cost for 1.25 cum = a+b+c+d 597.724 608.793 619.862
Rate per cum = (a+b+c+d)/ 1.25 478.179 487.034 495.889
Say, 478.20 487.00 495.90
2.4 D Dry rubble masonry
a) Labour
Mate day 0.018 0.018 0.018 622.000 11.196 11.196 11.196 L-12
Mazdoor for dismantling, loading and unloading. day 0.450 0.450 0.450 560.000 252.000 252.000 252.000 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 37.911 47.389 56.867
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 51.180 52.128 53.076
(a+b+c) (a+b+c) (a+b+c)
Cost for 1.25 cum = a+b+c+d 562.982 573.407 583.833
Rate per cum = (a+b+c+d)/ 1.25 450.385 458.726 467.066
Say, 450.40 458.70 467.10
2.4 E Dismantling stone pitching/ dry stone spalls.
a) Labour
Mate day 0.016 0.016 0.016 622.000 9.952 9.952 9.952 L-12
Mazdoor for dismantling, loading and unloading. day 0.400 0.400 0.400 560.000 224.000 224.000 224.000 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 35.572 44.465 53.358
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 48.022 48.911 49.800
(a+b+c) (a+b+c) (a+b+c)
Cost for 1.25 cum = a+b+c+d 528.240 538.022 547.804
Rate per cum = (a+b+c+d)/ 1.25 422.592 430.418 438.244
Say, 422.60 430.40 438.20
2.4 F Dismantling boulders laid in wire crates including
opening of crates and stacking dismantled materials.
a) Labour
Mate day 0.020 0.020 0.020 622.000 12.440 12.440 12.440 L-12
Mazdoor for dismantling, loading and unloading day 0.500 0.500 0.500 560.000 280.000 280.000 280.000 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 40.251 50.313 60.376
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 54.339 55.345 56.351
(a+b+c) (a+b+c) (a+b+c)
Cost for 1.25 cum = a+b+c+d 597.724 608.793 619.862
Rate per cum = (a+b+c+d)/ 1.25 478.179 487.034 495.889
Say, 478.20 487.00 495.90
II By Mechanical Means
2.4 A Dismantling Brick / Tile work/ rubble masonary/
pitching/ etc by mechanical means
Unit = cum
Taking output = 20 cum
a) Labour
Mate day 0.008 0.008 0.008 622.000 4.976 4.976 4.976 L-12
Mazdoor day 0.200 0.200 0.200 560.000 112.000 112.000 112.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.523 1748.000 915.002 P&M-3003
(ii) 1.1 cum bucket capacity hour 0.603 1748.000 1053.767 P&M-3004
(iii) 0.9 cum bucket capacity hour 0.843 2570.000 2165.992 P&M-3005
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 30.000 6.830 204.900 P&M-72002
(ii) 14 cum capacity t.km 30.000 7.770 233.100 P&M-73002
(iii) 10 cum capacity t.km 30.000 9.620 288.600 P&M-74002
Loading & unloading time
(i) 18 cum capacity hour 0.523 2621.000 1371.980 P&M-6001
(ii) 14 cum capacity hour 0.603 2331.000 1405.223 P&M-6002
(iii) 10 cum capacity hour 0.843 2077.000 1750.492 P&M-6003
c) Overhead charges @ 8% on @ 10% on @ 12% on 208.709 280.907 518.647
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 281.757 308.997 484.071
(a+b+c) (a+b+c) (a+b+c)
Cost for 20 cum = a+b+c+d 3099.324 3398.970 5324.778
Rate per cum = (a+b+c+d)/ 20 154.966 169.949 266.239
Say, 155.00 169.90 266.20
2.4 (iv) Wood Work wrought framed and fixed in frames of
trusses upto a height of 5 m above plinth level
Unit = Cum
Taking output = 1.25 Cum
a) Labour
Mate day 0.060 0.060 0.060 622.000 37.320 37.320 37.320 L-12
Carpenter day 0.500 0.500 0.500 622.000 311.000 311.000 311.000 L-04
Mazdoor for dismantling, loading and unloading. day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 820.00 210.694 210.694 210.694 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 89.521 111.901 134.282
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 120.854 123.092 125.330
(a+b+c) (a+b+c) (a+b+c)
Cost for 1.25 cum = a+b+c+d 1329.389 1354.007 1378.626
Rate per cum = (a+b+c+d)/ 1.25 1063.511 1083.206 1102.901
Say, 1063.50 1083.20 1102.90
2.4 (v) Steel Work in all types of sections upto a height of 5 m
above plinth level excluding cutting of rivet.
Unit = tonne
Taking output = 1 tonne
A Including dismembering
a) Labour
Mate day 0.140 0.140 0.140 622.000 87.080 87.080 87.080 L-12
Blacksmith day 1.000 1.000 1.000 622.000 622.000 622.000 622.000 L-02
Mazdoor for dismantling, loading and unloading day 2.500 2.500 2.500 560.000 1400.000 1400.000 1400.000 L-13
Blacksmith day 0.500 0.500 0.500 622.000 311.000 311.000 311.000 L-02
Add 2.5 per cent of cost of labour for gas cutting,
39.196 39.196 39.196
ropes, pulleys etc.
b) Machinery
Tractor-trolley hour 0.123 0.123 0.123 820.00 101.133 101.133 101.133 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 136.654 170.817 204.980
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 184.482 187.899 191.315
(a+b+c) (a+b+c) (a+b+c)
Rate per tonne = a+b+c+d 2029.305 2066.885 2104.465
Say, 2029.30 2066.90 2104.50
2.4 C Extra over item No( v ) A and( v ) B for cutting rivets.
Unit = each
Taking output = 10 rivets
a) Labour
Mate day 0.010 0.010 0.010 622.000 6.220 6.220 6.220 L-12
Blacksmith day 0.130 0.130 0.130 622.000 80.860 80.860 80.860 L-02
Mazdoor day 0.130 0.130 0.130 560.000 72.800 72.800 72.800 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on 12.790 15.988 19.186
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on 17.267 17.587 17.907
(a+b) (a+b) (a+b)
Cost for 10 rivets = a+b+c 189.937 193.455 196.972
Rate for each rivet = ( a+b+c)/10 18.994 19.345 19.697
Say, 19.00 19.30 19.70
2.4 (vi) Scraping of Bricks Dismantled from Brick Work
including Stacking.
Unit = numbers
Taking output = 1000 numbers
A In lime/Cement mortar
a) Labour
Mate day 0.140 0.140 0.140 622.000 87.080 87.080 87.080 L-12
Mazdoor day 3.500 3.500 3.500 560.000 1960.000 1960.000 1960.000 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on 163.766 204.708 245.650
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on 221.085 225.179 229.273
(a+b) (a+b) (a+b)
Rate per 1000 Nos = a+b+c 2431.931 2476.967 2522.003
Say, 2431.90 2477.00 2522.00
2.4 B In mud mortar
a) Labour
Mate day 0.050 0.050 0.050 622.000 31.100 31.100 31.100 L-12
Mazdoor day 1.250 1.250 1.250 560.000 700.000 700.000 700.000 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on 58.488 73.110 87.732
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on 78.959 80.421 81.883
(a+b) (a+b) (a+b)
Rate per1000 Nos = a+b+c 868.547 884.631 900.715
Say, 868.50 884.60 900.70
2.4 (vii) Scraping of Stone from Dismantled Stone Masonry
Unit = cum
Taking output = 1 cum
A In cement and lime mortar
a) Labour
Mate day 0.060 0.060 0.060 622.000 37.320 37.320 37.320 L-12
Mazdoor day 1.400 1.400 1.400 560.000 784.000 784.000 784.000 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on 65.706 82.132 98.558
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on 88.703 90.345 91.988
(a+b) (a+b) (a+b)
Rate per cum = a+b+c 975.728 993.797 1011.866
Say, 975.70 993.80 1011.90
2.4 B In Mud mortar
a) Labour
Mate day 0.010 0.010 0.010 622.000 6.220 6.220 6.220 L-12
Mazdoor day 0.300 0.300 0.300 560.000 168.000 168.000 168.000 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on 13.938 17.422 20.906
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on 18.816 19.164 19.513
(a+b) (a+b) (a+b)
Rate per cum = a+b+c 206.973 210.806 214.639
Say, 207.00 210.80 214.60
2.4 (viii) Scarping Plaster in Lime or Cement Mortar from Brick/
Stone Masonry
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.160 0.160 0.160 622.000 99.520 99.520 99.520 L-12
Mazdoor for scarping and loading day 4.000 4.000 4.000 560.000 2240.000 2240.000 2240.000 L-13
b) Machinery
Tractor-trolley hour 0.308 0.308 0.308 820.000 252.833 252.833 252.833 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 207.388 259.235 311.082
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 279.974 285.159 290.344
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 sqm = a+b+c+d 3079.716 3136.748 3193.779
Rate per sqm = (a+b+c+d)/100 30.797 31.367 31.938
Say, 30.80 31.40 31.90
2.4 (ix) Removing all type of Hume Pipes and Stacking within a
lead of 1000 metres including Earthwork and
Dismantling of Masonry Works.
A Up to 600 mm dia
Unit = metre
Taking output = 15 metre
a) Labour
Mate day 0.084 0.094 0.105 622.000 51.955 58.379 65.121 L-12
Mazdoor day 2.088 2.346 2.617 560.000 1169.412 1314.000 1465.739 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 2.176 1748.000 3804.471 P&M-3003
(ii) 1.1 cum bucket capacity hour 2.693 1748.000 4707.114 P&M-3004
(iii) 0.9 cum bucket capacity hour 3.235 2570.000 8313.391 P&M-3005
Tipper
For loading & Unloding Time & For transportation
of excess material to dumping yard considering
lead @ 1km
(i) 18 cum capacity hour 2.226 2621.000 5835.579 P&M-6001
(ii) 14 cum capacity hour 2.743 2331.000 6393.600 P&M-6002
(iii) 10 cum capacity hour 3.285 2077.000 6822.493 P&M-6003
c) Overhead charges @ 8% on @ 10% on @ 12% on 868.913 1247.309 2000.009
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1173.033 1372.040 1866.675
(a+b+c) (a+b+c) (a+b+c)
Rate for 15 metre = a+b+c+d 12903.363 15092.443 20533.429
Rate per metre = (a+b+c+d)/15 860.224 1006.163 1368.895
Say, 860.20 1006.20 1368.90
B Above 600 mm to 900 mm dia
Unit = metre
Taking output = 15 metre
a) Labour
Mate day 0.094 0.104 0.115 622.000 58.175 64.599 71.341 L-12
Mazdoor day 2.338 2.596 2.867 560.000 1309.412 1454.000 1605.739 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 2.676 1748.000 4678.471 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.193 1748.000 5581.114 P&M-3004
(iii) 0.9 cum bucket capacity hour 3.735 2570.000 9598.391 P&M-3005
Tipper for Loading & unloading
For loading & Unloding Time & For transportation
of excess material to dumping yard considering
lead @ 1km
(i) 18 cum capacity hour 2.726 2621.000 7146.079 P&M-6001
(ii) 14 cum capacity hour 3.243 2331.000 7559.100 P&M-6002
(iii) 10 cum capacity hour 3.785 2077.000 7860.993 P&M-6003
CHAPTER-2
SITE CLEARANCE
Amount
Quantity
Reference to (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
b) Machinery
Tractor-trolley hour 0.167 0.167 0.167 820.00 136.667 136.667 136.667 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 81.119 101.399 121.678
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 109.511 111.539 113.567
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = a+b+c+d 1204.616 1226.924 1249.232
Say, 1204.60 1226.90 1249.20
2.5 B Granular courses
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor for dismantling, loading and unloading. day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Tractor-trolley hour 0.167 0.167 0.167 820.00 136.667 136.667 136.667 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 57.724 72.155 86.586
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 77.927 79.370 80.813
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = a+b+c+d 857.197 873.071 888.945
Say, 857.20 873.10 888.90
2.5 Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres,
stacking serviceable and unserviceable materials
separately
(ii) By Mechanical Means
A Bituminous courses
Unit = cum
Taking output = 20 cum
a) Labour
Mate day 0.024 0.027 0.033 622.000 14.635 16.587 20.733 L-12
Mazdoor for dismantling, loading and unloading day 0.588 0.667 0.833 560.000 329.412 373.333 466.667 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity considering output 85 hour 2.353 1748.000 4112.941 P&M-3003
sqm/8.5 cum per hour
(ii) 1.1 cum bucket capacity considering output 75 hour 2.667 1748.000 4661.333 P&M-3004
sqm/7.5 cum per hour
(iii) 0.9 cum bucket capacity considering output 60 hour 3.333 2570.000 8566.667 P&M-3005
sqm/6 cum per hour
Tipper for transportation
(i) 18 cum capacity t.km 46.000 6.830 314.180 P&M-72002
(ii) 14 cum capacity t.km 46.000 7.770 357.420 P&M-73002
(iii) 10 cum capacity t.km 46.000 9.620 442.520 P&M-74002
c) Overhead charges @ 8% on @ 10% on @ 12% on 381.693 540.867 1139.590
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 515.286 594.954 1063.618
(a+b+c) (a+b+c) (a+b+c)
Rate for 20 metre = a+b+c+d 5668.148 6544.495 11699.795
Rate per metre = (a+b+c+d)/20 283.407 327.225 584.990
Say, 283.40 327.20 585.00
B Granular courses
Unit = cum
Taking output = 250 cum
a) Labour
Mate day 0.029 0.033 0.046 622.000 17.868 20.577 28.768 L-12
Mazdoor for dismantling, loading and unloading day 0.718 0.827 1.156 560.000 402.168 463.159 647.516 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 2.873 1748.000 5021.355 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.308 1748.000 5782.867 P&M-3004
(iii) 0.9 cum bucket capacity hour 4.625 2570.000 11886.540 P&M-3005
Tipper for transportation
(i) 18 cum capacity t.km 575.000 6.830 3927.250 P&M-72002
(ii) 14 cum capacity t.km 575.000 7.770 4467.750 P&M-73002
(iii) 10 cum capacity t.km 575.000 9.620 5531.500 P&M-74002
c) Overhead charges @ 8% on @ 10% on @ 12% on 749.491 1073.435 2171.319
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1011.813 1180.779 2026.564
(a+b+c) (a+b+c) (a+b+c)
Rate for 250 metre = a+b+c+d 11129.945 12988.567 22292.207
Rate per metre = (a+b+c+d)/250 44.520 51.954 89.169
Say, 44.50 52.00 89.20
2.6 202 Dismantling of Cement Concrete Pavement
Dismantling of cement concrete pavement by
mechanical means using pneumatic tools, breaking to
pieces not exceeding 0.02 cum in volume and stock
piling at designated locations and disposal of
dismantled materials up to a lead of 1000 metres,
stacking serviceable and unserviceable materials
separately
Unit = cum
Taking output = 60 cum
a) Labour
Mate day 0.050 0.050 0.050 622.000 31.100 31.100 31.100 L-12
CHAPTER-2
SITE CLEARANCE
Amount
Quantity
Reference to (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mazdoor day 3.000 3.000 3.000 560.000 1680.000 1680.000 1680.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 6.841 1748.000 11957.815 P&M-3003
(ii) 1.1 cum bucket capacity hour 8.048 1748.000 14068.017 P&M-3004
(iii) 0.9 cum bucket capacity hour 9.121 2570.000 23441.330 P&M-3005
Jack Hammer hour 6.841 9.146 12.162 206.000 1409.216 1883.979 2505.273 P&M-4001
Air Compressor 250 cfm with 2 leads of pneumatic hour 2.880 2.880 2.880 550.000 1584.000 1584.000 1584.000 P&M-15001
breaker @ 1 cum per hour
Pneumatic breaker hour 5.760 5.760 5.760 11.000 63.360 63.360 63.360 P&M-45001
Concrete Joint Cutting Machine hour 8.000 8.000 8.000 452.000 3616.000 3616.000 3616.000 P&M-42001
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 180.000 6.830 1229.400 P&M-72002
(ii) 14 cum capacity t.km 180.000 7.770 1398.600 P&M-73002
(iii) 10 cum capacity t.km 180.000 9.620 1731.600 P&M-74002
For Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 72.000 84.60 6091.20 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 72.000 84.52 6085.44 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum cum 72.000 117.86 8485.92 P&M-77003
capacity Loader
c) Overhead charges @ 8% on @ 10% on @ 12% on 2212.967 3041.050 5176.630
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 2987.506 3345.155 4831.521
(a+b+c) (a+b+c) (a+b+c)
Cost for 60 cum = a+b+c+d 32862.564 36796.700 53146.735
Rate per cum = (a+b+c+d)/ 60 547.709 613.278 885.779
Say, 547.70 613.30 885.80
2.7 202 Dismantling of Guard Rails
Dismantling guard rails by manual means and disposal
of dismantled material with all lifts and up to a lead of
1000 metres, stacking serviceable materials and
unserviceable materials separately.
Unit = Each
Taking output = one KM stone
A 5th KM stone
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.130 0.130 0.130 622.000 80.860 80.860 80.860 L-12
Mazdoor day 0.750 0.750 0.750 560.000 420.000 420.000 420.000 L-13
b) Machinery
Tractor-trolley hour 0.150 0.150 0.150 820.00 123.000 123.000 123.000 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 49.909 62.386 74.863
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 67.377 68.625 69.872
(a+b+c) (a+b+c) (a+b+c)
Rate for one 5th KM stone = a+b+c+d 741.146 754.871 768.596
Say, 741.10 754.90 768.60
B Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a) Labour
Mate day 0.020 0.020 0.020 622.000 12.440 12.440 12.440 L-12
Mazdoor day 0.500 0.500 0.500 560.000 280.000 280.000 280.000 L-13
b) Machinery
Tractor-trolley hour 0.100 0.100 0.100 820.00 82.000 82.000 82.000 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 29.955 37.444 44.933
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 40.440 41.188 41.937
(a+b+c) (a+b+c) (a+b+c)
Rate for one ordinary KM stone = a+b+c+d 444.835 453.072 461.310
Say, 444.80 453.10 461.30
C Hectometre Stone
Quantity of cement concrete = 0.048 cum
a) Labour
Mate day 0.004 0.004 0.004 622.000 2.488 2.488 2.488 L-12
Mazdoor day 0.100 0.100 0.100 560.000 56.000 56.000 56.000 L-13
b) Machinery
Tractor-trolley hour 0.020 0.020 0.020 820.00 16.400 16.400 16.400 P&M-12001
c) Overhead charges @ 8% on @ 10% on @ 12% on 5.991 7.489 8.987
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 8.088 8.238 8.387
(a+b+c) (a+b+c) (a+b+c)
Rate for one Hectometre stone = a+b+c+d 88.967 90.614 92.262
Say, 89.00 90.60 92.30
2.11 202 Dismantling of Fencing
CHAPTER-2
SITE CLEARANCE
Amount
Quantity
Reference to (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = each
Taking output = 30 Nos
a) Labour
Mate day 0.480 0.480 0.480 622.000 298.560 298.560 298.560 L-12
Mazdoor day 10.000 10.000 10.000 560.000 5600.000 5600.000 5600.000 L-13
Electrician/Lineman day 2.000 2.000 2.000 622.00 1244.000 1244.000 1244.000 L-02
b) Machinery
Tractor-trolley hour 1.500 1.500 1.500 820.00 1230.000 1230.000 1230.000 P&M-12001
c) Overhead charges for large @ 10% on @ 12% on 669.805 837.256 1004.707
Project @ 8% (a+b) (a+b)
on (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 904.236 920.982 937.727
(a+b+c) (a+b+c) (a+b+c)
Cost for 30 poles = a+b+c+d 9946.601 10130.798 10314.994
Rate per pole = (a+b+c+d)/30 331.553 337.693 343.833
Say, 331.60 337.70 343.80
All the serviceable material resulting from removal of
Note: Telephone / Electric Poles and Lines would be handed
over to the employer.
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Amount
Quantity
(Rs.)
Reference to MORT&H Rate
Sr No Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
Specification (Rs.) Large Project Small Project
Project Project Project Project
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 1.800 1.800 622.000 1119.600 1119.600 1119.600 L-12
Mazdoor day 45.000 45.000 45.000 560.000 25200.000 25200.000 25200.000 L-13
b) Machinery
Truck 5.5 cum capacity hour 9.236 9.236 9.236 1590.000 14685.818 14685.818 14685.818 P&M-6004
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 3280.433 4100.542 4920.650
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 4428.585 4510.596 4592.607
(a+b+c) (a+b+c) (a+b+c)
Cost of 120 cum = a+b+c+d 48714.437 49616.556 50518.675
Rate per cum = (a+b+c+d)/120 405.954 413.471 420.989
Say, 406.00 413.50 421.00
Note In case there is a situation where the cross-section is of
cut and fill and cut earth is required to be used in
embankment in the immediate vicinity, the item of carriage
in the truck shall be omitted.
3.3 301 Excavation in Soil with Dozer with lead upto 1000 metres
Unit = cum
Taking output = 500 cum 800 Tonne
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Dozer
Dozer (240HP) hour 3.731 3005.00 11212.687 P&M-1001
Dozer (175 HP) hour 5.342 2099.00 11212.607 P&M-1002
Dozer (90 HP) hour 8.621 1267.00 10922.414 P&M-1003
Tipper
(i) 18 cum capacity t.km 800.000 6.830 5464.000 P&M-72002
(ii) 14 cum capacity t.km 800.000 7.770 6216.000 P&M-73002
(iii) 10 cum capacity t.km 800.000 9.620 7696.000 P&M-74002
Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 500.000 84.60 42300.00 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 500.000 84.52 42260.00 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 500.000 117.86 58930.00 P&M-77003
Loader
Unit = cum
Taking output = 300 cum 720 Tonne
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Dozer
Dozer (240HP) hour 4.688 3005.00 14085.938 P&M-1001
Dozer (175 HP) hour 6.667 2099.00 13993.333 P&M-1002
Dozer (90 HP) hour 10.714 1267.00 13575.000 P&M-1003
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 720.000 6.830 4917.600 P&M-72002
(ii) 14 cum capacity t.km 720.000 7.770 5594.400 P&M-73002
(iii) 10 cum capacity t.km 720.000 9.620 6926.400 P&M-74002
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 360.000 84.60 30456.00 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 360.000 84.52 30427.20 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 360.000 117.86 42429.60 P&M-77003
Loader
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 4003.553 5059.981 7621.906
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 5404.797 5565.979 7113.779
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 cum = a+b+c+d 59452.768 61225.774 78251.564
Rate per cum = (a+b+c+d)/300 198.176 204.086 260.839
Say, 198.20 204.10 260.80
3.5 301 Excavation in Hard Rock (requiring blasting) with
disposal upto 1000 metres
Excavation for roadway in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines,
grades and cross sections, loading and disposal of cut
road with in all lifts and leads upto 1000 metres
Unit = cum
Taking output = 180 cum 360 Tonne
a) Labour
Mate day 0.210 0.210 0.210 622.000 130.620 130.620 130.620 L-12
Mazdoor day 3.000 3.000 3.000 560.000 1680.000 1680.000 1680.000 L-13
Driller day 2.000 2.000 2.000 592.00 1184.000 1184.000 1184.000 L-06
Blaster day 0.250 0.250 0.250 560.00 140.000 140.000 140.000 L-03
b) Machinery
Air Compressor 250 cfm hour 27.500 27.500 27.500 550.00 15125.000 15125.000 15125.000 P&M-15001
Pneumatic breaker for drilling holes (@ 4.5 m per hour 55.000 55.000 55.000 11.00 605.000 605.000 605.000 P&M-45001
hour)
Dozer
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Amount
Quantity
(Rs.)
Reference to MORT&H Rate
Sr No Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
Specification (Rs.) Large Project Small Project
Project Project Project Project
Unit = cum
Taking output = 350 cum
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.926 1748.000 6862.519 P&M-3003
(ii) 1.1 cum bucket capacity hour 5.024 1748.000 8781.390 P&M-3004
(iii) 0.9 cum bucket capacity hour 6.321 2570.000 16244.938 P&M-3005
Tipper
For transportation considering lead @ 1 km
(i) 18 cum capacity t.km 525.000 6.830 3585.750 P&M-72002
(ii) 14 cum capacity t.km 525.000 7.770 4079.250 P&M-73002
(iii) 10 cum capacity t.km 525.000 9.620 5050.500 P&M-74002
For loading & unloading time
(i) 18 cum capacity hour 3.926 2621.000 10289.852 P&M-6001
(ii) 14 cum capacity hour 5.024 2331.000 11710.195 P&M-6002
(iii) 10 cum capacity hour 6.321 2077.000 13128.691 P&M-6003
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 1705.840 2515.572 4201.081
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 2302.884 2767.129 3921.009
(a+b+c) (a+b+c) (a+b+c)
Cost for 350 cum = a+b+c+d 25331.724 30438.415 43131.100
Rate per cum = (a+b+c+d)/350 72.376 86.967 123.232
Say, 72.40 87.00 123.20
3.7 301 Excavation in Ordinary Rock using Hydraulic Excavator
and Tippers with Disposal upto 1000 metres.
Unit = cum
Taking output = 60 cum 120 Tonne
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Hydraulic Excavator for Jack Hammer
(i) 1.2 cum bucket capacity hour 6.982 1748.000 12204.218 P&M-3003
(ii) 1.1 cum bucket capacity hour 8.214 1748.000 14357.904 P&M-3004
(iii) 0.9 cum bucket capacity hour 8.727 2570.000 22429.091 P&M-3005
Jack Hammer hour 6.982 8.214 8.727 206.000 1438.255 1692.064 1797.818 P&M-4001
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 120.000 6.830 819.600 P&M-72002
(ii) 14 cum capacity t.km 120.000 7.770 932.400 P&M-73002
(iii) 10 cum capacity t.km 120.000 9.620 1154.400 P&M-74002
For loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 72.000 84.60 6091.20 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 72.000 84.52 6085.44 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 72.000 117.86 8485.92 P&M-77003
Loader
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 1691.052 2365.269 4134.253
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 2282.920 2601.796 3858.636
(a+b+c) (a+b+c) (a+b+c)
Cost for 60 cum = a+b+c+d 25112.125 28619.752 42444.998
Rate per cum = (a+b+c+d)/60 418.535 476.996 707.417
Say, 418.50 477.00 707.40
3.8 301 Excavation in Hard Rock (blasting prohibited)
Excavation for roadwork in Hard Rock (blasting
prohibited) with hydraulic excavator including cutting and
loading in tippers, trimming bottom and side slopes, in
accordance with requirements of lines, grades and cross
sections, and transporting to the embankment location
within all lifts and lead upto 1000m
A Unit = cum
Taking output = 50 cum 100 Tonne
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Hydraulic Excavator for Jack Hammer
(i) 1.2 cum bucket capacity hour 8.533 1748.000 14916.267 P&M-3003
(ii) 1.1 cum bucket capacity hour 10.039 1748.000 17548.549 P&M-3004
(iii) 0.9 cum bucket capacity hour 11.378 2570.000 29240.889 P&M-3005
Jack Hammer hour 8.533 10.039 11.378 206.000 1757.867 2068.078 2343.822 P&M-4001
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 100.000 6.830 683.000 P&M-72002
(ii) 14 cum capacity t.km 100.000 7.770 777.000 P&M-73002
(iii) 10 cum capacity t.km 100.000 9.620 962.000 P&M-74002
For loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 60.000 84.60 5076.00 P&M-77001
capacity Loader
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Amount
Quantity
(Rs.)
Reference to MORT&H Rate
Sr No Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
Specification (Rs.) Large Project Small Project
Project Project Project Project
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 60.000 84.52 5071.20 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 60.000 117.86 7071.60 P&M-77003
Loader
Credit for excavated rock found suitable for use @ 50 cum 25.000 25.000 25.000 350.00 (8750.000) (8750.000) (8750.000) M-090
per cent of excavated quantity
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 1141.441 1729.971 3774.383
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1540.945 1902.968 3522.757
(a+b+c) (a+b+c) (a+b+c)
Cost for 50 cum = a+b+c+d 16950.400 20932.646 38750.331
Rate per cum = (a+b+c+d)/50 339.008 418.653 775.007
Say, 339.00 418.70 775.00
3.8 B Manual Method
Unit = cum
Taking output = 16 cum
a) Labour
Mate day 1.640 1.640 1.640 622.000 1020.080 1020.080 1020.080 L-12
Mazdoor including loading in truck day 16.000 16.000 16.000 560.000 8960.000 8960.000 8960.000 L-13
Chiseller day 24.000 24.000 24.000 592.00 14208.000 14208.000 14208.000 L-05
Blacksmith (IInd class) day 1.000 1.000 1.000 592.00 592.000 592.000 592.000 L-01
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 2.900 2.900 1590.000 4611.000 4611.000 4611.000 P&M-6004
Credit for excavated rock found suitable for use @ 50 cum 8.000 8.000 8.000 350.00 (2800.000) (2800.000) (2800.000) M-090
per cent of excavated
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 2127.286 2659.108 3190.930
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 2871.837 2925.019 2978.201
(a+b+c) (a+b+c) (a+b+c)
Cost for 16 cum = a+b+c+d 31590.203 32175.207 32760.211
Rate per cum = (a+b+c+d)/16 1974.388 2010.950 2047.513
Say, 1974.40 2011.00 2047.50
Note 1. Credit is considered for 50 per cent of quantity of work.
Unit = cum
Taking output = 180 cum 360 Tonne
a) Labour
Mate day 0.210 0.210 0.210 622.000 130.620 130.620 130.620 L-12
Mazdoor day 3.000 3.000 3.000 560.000 1680.000 1680.000 1680.000 L-13
Driller day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-06
Blaster day 0.250 0.250 0.250 560.000 140.000 140.000 140.000 L-03
b) Machinery
Air Compressor 250 cfm hour 27.500 27.500 27.500 550.00 15125.000 15125.000 15125.000 P&M-15001
Pneumatic breaker for drilling holes (@ 4.5 m per hour 55.000 55.000 55.000 11.00 605.000 605.000 605.000 P&M-45001
hour)
Dozer
Dozer (240HP) hour 3.375 3005.00 10141.875 P&M-1001
Dozer (175 HP) hour 4.320 2099.00 9067.680 P&M-1002
Dozer (90 HP) hour 7.714 1267.00 9774.000 P&M-1003
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 360.000 6.830 2458.800 P&M-72002
(ii) 14 cum capacity t.km 360.000 7.770 2797.200 P&M-73002
(iii) 10 cum capacity t.km 360.000 9.620 3463.200 P&M-74002
For loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 216.000 84.60 18273.60 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 216.000 84.52 18256.32 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 216.000 117.86 25457.76 P&M-77003
Loader
c) Materials
Small dia.Explosive at 0.40 kg / cum for 180 cum ( 180 kg 73.800 73.800 73.800 55.00 4059.000 4059.000 4059.000 M-215
x 0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of
the total volume ( 180 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes no 103.000 103.000 103.000 12.00 1236.000 1236.000 1236.000 M-217
(21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 10.000 10.000 10.000 55.00 550.000 550.000 550.000 M-216
holes( required for 5% of the total quantity @ 0.6 m
per hole for I cum )
Detonating fuse coil m 320.000 320.000 320.000 105.00 33600.000 33600.000 33600.000 M-218
Credit for excavated rock found suitable for use @ 50 cum 90.000 90.000 90.000 350.00 31500.000 31500.000 31500.000 M-090
per cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling
arrangements to guard against any rock fly off during 6034.19 5996.54 6425.23
blasting
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 10137.447 12592.736 16191.577
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 13685.554 13852.010 15112.139
(a+b+c) (a+b+c) (a+b+c)
Cost for 180 cum = a+b+c+d+e 150541.091 152372.107 166233.525
Rate per cum = (a+b+c+d+e)/180 836.339 846.512 923.520
Say, 836.30 846.50 923.50
Note 1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced/restricted to that extent.
Unit = cum
Taking output = 325 cum 487.5 Tonne
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 8.506 1748.000 14868.790 P&M-3003
(ii) 1.1 cum bucket capacity hour 9.796 1748.000 17123.711 P&M-3004
(iii) 0.9 cum bucket capacity hour 13.695 2570.000 35197.366 P&M-3005
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 487.500 6.830 3329.625 P&M-72002
(ii) 14 cum capacity t.km 487.500 7.770 3787.875 P&M-73002
(iii) 10 cum capacity t.km 487.500 9.620 4689.750 P&M-74002
For loading & unloading time
(i) 18 cum capacity hour 8.506 2621.000 22294.679 P&M-6001
(ii) 14 cum capacity hour 9.796 2331.000 22834.880 P&M-6002
(iii) 10 cum capacity hour 13.695 2077.000 28445.498 P&M-6003
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 3286.238 4433.135 8270.099
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 4436.421 4876.448 7718.759
(a+b+c) (a+b+c) (a+b+c)
Cost for 325 cum = a+b+c+d 48800.633 53640.929 84906.353
Rate per cum = (a+b+c+d)/325 150.156 165.049 261.250
Say, 150.20 165.00 261.30
3.11 301 Removal of Unserviceable Soil with Disposal upto 1000
metres
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Amount
Quantity
(Rs.)
Reference to MORT&H Rate
Sr No Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
Specification (Rs.) Large Project Small Project
Project Project Project Project
Unit = Sqm
Taking output = 400 sqm 240 Tonne
a) Labour
Mate day 0.210 0.210 0.210 622.000 130.620 130.620 130.620 L-12
Mazdoor day 3.000 3.000 3.000 560.000 1680.000 1680.000 1680.000 L-13
Driller day 2.000 2.000 2.000 592.00 1184.000 1184.000 1184.000 L-06
Blaster day 0.250 0.250 0.250 560.00 140.000 140.000 140.000 L-03
b) Machinery
Air Compressor 250 cfm hour 17.000 17.000 17.000 550.00 9350.000 9350.000 9350.000 P&M-15001
Pneumatic breaker for drilling holes (@ 4.5 m per hour 34.000 34.000 34.000 11.00 374.000 374.000 374.000 P&M-45001
hour)
Dozer
(i) Dozer (240HP) hour 1.875 3005.00 5634.375 P&M-1001
(ii) Dozer (175 HP) hour 2.400 2099.00 5037.600 P&M-1002
(iii) Dozer (90 HP) hour 4.286 1267.00 5430.000 P&M-1003
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 240.000 6.830 1639.200 P&M-72002
(ii) 14 cum capacity t.km 240.000 7.770 1864.800 P&M-73002
(iii) 10 cum capacity t.km 240.000 9.620 2308.800 P&M-74002
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 144.000 84.60 12182.40 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 144.000 84.52 12170.88 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 144.000 117.86 16971.84 P&M-77003
Loader
c) Materials
Small dia.Explosive at 0.40 kg / cum for 400 cum ( 400 kg 49.200 49.200 49.200 55.00 2706.000 2706.000 2706.000 M-215
x 0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of
the total volume ( 400 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes no 69.000 69.000 69.000 12.00 828.000 828.000 828.000 M-217
(21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 7.000 7.000 7.000 55.00 385.000 385.000 385.000 M-216
holes( required for 5% of the total quantity @ 0.6 m
per hole for I cum )
Detonating fuse coil m 213.000 213.000 213.000 105.00 22365.000 22365.000 22365.000 M-218
Credit for excavated rock found suitable for use @ 50 cum 60.000 60.000 60.000 350.00 (21000.000) (21000.000) (21000.000) M-090
per cent quantity blasted
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 3007.888 3721.590 5142.391
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 4060.648 4093.749 4799.565
(a+b+c) (a+b+c) (a+b+c)
Cost for 400 Sqm = a+b+c+d+e 44667.131 45031.239 52795.216
Rate per cum = (a+b+c+d+e)/400 111.668 112.578 131.988
Say, 111.70 112.60 132.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced/restricted to that extent.
Jack Hammer hour 5.818 6.845 7.273 206.000 1198.545 1410.053 1498.182 P&M-4001
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 40.000 6.830 273.200 P&M-72002
(ii) 14 cum capacity t.km 40.000 7.770 310.800 P&M-73002
(iii) 10 cum capacity t.km 40.000 9.620 384.800 P&M-74002
For loading & unloading time
(i) 18 cum capacity hour 0.523 2621.000 1371.980 P&M-6001
(ii) 14 cum capacity hour 0.603 2331.000 1405.223 P&M-6002
(iii) 10 cum capacity hour 0.843 2077.000 1750.492 P&M-6003
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 1364.484 1948.005 3539.280
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1842.054 2142.806 3303.328
(a+b+c) (a+b+c) (a+b+c)
Cost for 50 cum = a+b+c+d 20262.592 23570.865 36336.611
Rate per cum = (a+b+c+d)/50 405.252 471.417 726.732
Say, 405.30 471.40 726.70
3.13 (iii) Hard Rock ( requiring blasting )
A Mechanical Means
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a dozer, loading
in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified
in clause No. 303
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 0.210 0.210 0.210 622.000 130.620 130.620 130.620 L-12
Mazdoor day 3.000 3.000 3.000 560.000 1680.000 1680.000 1680.000 L-13
Driller day 2.000 2.000 2.000 592.00 1184.000 1184.000 1184.000 L-06
Blaster day 0.250 0.250 0.250 560.00 140.000 140.000 140.000 L-03
b) Machinery
Air Compressor 250 cfm hour 17.000 17.000 17.000 572.00 9724.000 9724.000 9724.000 P&M-15001 + P&M-
45001 x 2
Pneumatic breaker for drilling holes (@ 4.5 m per hour 34.000 34.000 34.000 11.00 374.000 374.000 374.000 P&M-45001
hour)
Hydraulic Excavator for Jack Hammer & backfilling ,
loading
(i) 1.2 cum bucket capacity hour 3.537 1748.000 6181.964 P&M-3003
(ii) 1.1 cum bucket capacity hour 4.174 1748.000 7295.521 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.411 2570.000 13905.667 P&M-3005
Jack Hammer (consider 5% of the volume for dressing) hour 1.024 1.280 1.365 11.00 11.264 14.080 15.019 P&M-45001
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 96.000 6.830 655.680 P&M-72002
(ii) 14 cum capacity t.km 96.000 7.770 745.920 P&M-73002
(iii) 10 cum capacity t.km 96.000 9.620 923.520 P&M-74002
For loading & unloading time
(i) 18 cum capacity hour 1.005 2621.000 2634.202 P&M-6001
(ii) 14 cum capacity hour 1.157 2331.000 2698.029 P&M-6002
(iii) 10 cum capacity hour 1.618 2077.000 3360.945 P&M-6003
c) Materials
Small dia.Explosive at 0.40 kg / cum for 120 cum ( 120 kg 49.200 49.200 49.200 55.00 2706.000 2706.000 2706.000 M-215
x 0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of
the total volume ( 120 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes no 69.000 69.000 69.000 12.00 828.000 828.000 828.000 M-217
(21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 7.000 7.000 7.000 55.00 385.000 385.000 385.000 M-216
holes( required for 5% of the total quantity @ 0.6 m
per hole for I cum )
Detonating fuse coil m 213.000 213.000 213.000 105.00 22365.000 22365.000 22365.000 M-218
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 3919.978 5027.017 6926.612
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 5291.971 5529.719 6464.838
(a+b+c) (a+b+c) (a+b+c)
Cost for 120 cum = a+b+c+d+e 58211.679 60826.905 71113.222
Rate per cum = (a+b+c+d+e)/120 485.097 506.891 592.610
Say, 485.10 506.90 592.60
3.13 (iv) Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 35 cum
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Hydraulic Excavator used for Jack hammer & loading
(i) 1.2 cum bucket capacity hour 9.571 1748.000 16729.583 P&M-3003
(ii) 1.1 cum bucket capacity hour 11.244 1748.000 19655.371 P&M-3004
(iii) 0.9 cum bucket capacity hour 13.783 2570.000 35422.990 P&M-3005
Jack Hammer hour 8.960 10.541 12.800 206.000 1845.760 2171.482 2636.800 P&M-4001
Tipper
For transportation to dumping yard considering lead @
1km
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Amount
Quantity
(Rs.)
Reference to MORT&H Rate
Sr No Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
Specification (Rs.) Large Project Small Project
Project Project Project Project
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 625.000 84.60 52875.00 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 625.000 84.52 52825.00 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 625.000 117.86 73662.50 P&M-77003
Loader
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 6380.379 8266.650 11056.257
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 8613.511 9093.315 10319.173
(a+b+c) (a+b+c) (a+b+c)
Cost for 12500 sqm = a+b+c+d 94748.623 100026.462 113510.905
Rate per sqm = (a+b+c+d)/12500 7.580 8.002 9.081
Say, 7.60 8.00 9.10
Note In case material is to be reused at site, transportation cost
catered above for disposal shall be deleted.
Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.048 1748.000 8823.238 P&M-3003
(ii) 1.1 cum bucket capacity hour 5.813 1748.000 10161.323 P&M-3004
(iii) 0.9 cum bucket capacity hour 8.127 2570.000 20886.349 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 450x1.6 x L2 6.830 9835.200 P&M-72002
(ii) 14 cum capacity t.km 450x1.6 x L2 7.770 11188.800 P&M-73002
(iii) 10 cum capacity t.km 450x1.6 x L2 9.620 13852.800 P&M-74002
For Loading & unloading time
(i) 18 cum capacity hour 5.048 2621.000 13229.810 P&M-6001
(ii) 14 cum capacity hour 5.813 2331.000 13550.368 P&M-6002
(iii) 10 cum capacity hour 8.127 2077.000 16879.746 P&M-6003
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5796.000 12620.323 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.626 5316.000 13962.257 P&M-2002
(iii) Motor grader 3.35 metre blade hour 2.929 1576.000 4615.482 P&M-2003
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Unit = cum
Taking output = 450 cum
a) Labour
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Amount
Quantity
(Rs.)
Reference to MORT&H Rate
Sr No Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
Specification (Rs.) Large Project Small Project
Project Project Project Project
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5796.000 12620.323 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.626 5316.000 13962.257 P&M-2002
(iii) Motor grader 3.35 metre blade hour 2.929 1576.000 4615.482 P&M-2003
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.048 1748.000 8823.238 P&M-3003
(ii) 1.1 cum bucket capacity hour 5.813 1748.000 10161.323 P&M-3004
(iii) 0.9 cum bucket capacity hour 8.127 2570.000 20886.349 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 450x1.75 x L2 6.830 10757.250 P&M-72002
(ii) 14 cum capacity t.km 450x1.75 x L2 7.770 12237.750 P&M-73002
(iii) 10 cum capacity t.km 450x1.75 x L2 9.620 15151.500 P&M-74002
For Loading & unloading time
(i) 18 cum capacity hour 5.048 2621.000 13229.810 P&M-6001
(ii) 14 cum capacity hour 5.813 2331.000 13550.368 P&M-6002
(iii) 10 cum capacity hour 8.127 2077.000 16879.746 P&M-6003
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5796.000 12620.323 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.626 5316.000 13962.257 P&M-2002
(iii) Motor grader 3.35 metre blade hour 2.929 1576.000 4615.482 P&M-2003
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5796.000 12620.323 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.626 5316.000 13962.257 P&M-2002
(iii) Motor grader 3.35 metre blade hour 2.929 1576.000 4615.482 P&M-2003
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
(i) Motor grader 4.30 metre blade hour 2.192 5796.000 12702.808 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.637 5316.000 14017.011 P&M-2002
(iii) Motor grader 3.35 metre blade hour 2.804 1576.000 4418.455 P&M-2003
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Motor grader for ripping & grading
(i) Motor grader 4.30 metre blade hour 3.487 5796.000 20209.013 P&M-2001
(ii) Motor grader 3.70 metre blade hour 4.197 5316.000 22309.192 P&M-2002
(iii) Motor grader 3.35 metre blade hour 4.497 1576.000 7087.881 P&M-2003
Unit = cum
Taking output = 250 cum
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Motor grader
(i) Motor grader 4.30 metre blade hour 1.680 5796.000 9737.903 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.027 5316.000 10773.346 P&M-2002
(iii) Motor grader 3.35 metre blade hour 2.260 1576.000 3561.329 P&M-2003
Hydraulic Excavator for reapplication
(i) 1.2 cum bucket capacity hour 2.804 1748.000 4901.799 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.230 1748.000 5645.179 P&M-3004
(iii) 0.9 cum bucket capacity hour 4.515 2570.000 11603.527 P&M-3005
Tipper
For transportation considering lead @ 1 km (20% of
the material needs to be transported)
(i) 18 cum capacity t.km 75.000 6.830 512.250 P&M-72002
(ii) 14 cum capacity t.km 75.000 7.770 582.750 P&M-73002
(iii) 10 cum capacity t.km 75.000 9.620 721.500 P&M-74002
For loading (20% of the material needs to be
transported)
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 50.000 84.60 4230.00 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 50.000 84.52 4226.00 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 50.000 117.86 5893.00 P&M-77003
Loader
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 1597.347 2181.216 2683.708
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 2156.418 2399.337 2504.794
(a+b+c) (a+b+c) (a+b+c)
Cost for 250 sqm = a+b+c+d 23720.597 26392.708 27552.739
Rate per sqm = (a+b+c+d)/250 94.882 105.571 110.211
Say, 94.90 105.60 110.20
3.22 Stripping, Storing and Re-laying Top Soil from Borrow
Areas in Agriculture Fields.
Stripping of top soil from borrow areas located in
agriculture fields, storing at a suitable place, spreading
and re-laying after taking the borrow earth to maintain
fertility of the agricultural field, finishing it to the required
levels and satisfaction of the farmer.
Unit = cum
Taking output = 250 cum
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Motor grader
(i) Motor grader 4.30 metre blade hour 1.680 5796.000 9737.903 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.027 5316.000 10773.346 P&M-2002
(iii) Motor grader 3.35 metre blade hour 2.260 1576.000 3561.329 P&M-2003
Hydraulic Excavator for reapplication
(i) 1.2 cum bucket capacity hour 2.804 1748.000 4901.799 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.230 1748.000 5645.179 P&M-3004
(iii) 0.9 cum bucket capacity hour 4.515 2570.000 11603.527 P&M-3005
Tipper
For transportation
(i) 18 cum capacity t.km 250x1.6 x L2 6.830 5464.000 P&M-72002
(ii) 14 cum capacity t.km 250x1.6 x L2 7.770 6216.000 P&M-73002
(iii) 10 cum capacity t.km 250x1.6 x L2 9.620 7696.000 P&M-74002
For loading & unloading
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 250.000 84.60 21150.00 P&M-77001
capacity Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 250.000 84.52 21130.00 P&M-77002
capacity Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 250.000 117.86 29465.00 P&M-77003
Loader
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 3347.087 4434.941 6349.288
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 4518.567 4878.435 5926.002
(a+b+c) (a+b+c) (a+b+c)
Cost for 250 sqm = a+b+c+d 49704.236 53662.781 65186.027
Rate per sqm = (a+b+c+d)/250 198.817 214.651 260.744
Say, 198.80 214.70 260.70
3.23 307 Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 622.000 74.640 74.640 74.640 L-12
Mazdoor for preparation of ground and fetching of sods day 3.000 3.000 3.000 560.000 1680.000 1680.000 1680.000 L-13
b) Machinery
Water tanker including watering for 3 months
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Unit = sqm
Taking output = 240 sqm
a) Labour
Mate day 0.400 0.400 0.400 622.000 248.800 248.800 248.800 L-12
Mazdoor day 10.000 10.000 10.000 560.000 5600.000 5600.000 5600.000 L-13
b) Machinery
Water tanker including watering for 3 months
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Bitumen Emulsion litre 55.200 55.200 55.200 35.012 1932.687 1932.687 1932.687 M-077 /1000
Jute netting, open weave, 2.5 cm square opening sqm 264.000 264.000 264.000 15.000 3960.000 3960.000 3960.000 M-120
Cost of water for 3 months KL 84.000 84.000 84.000 74.540 6261.360 6261.360 6261.360 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 2541.289 3370.974 4900.936
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 3430.741 3708.071 4574.207
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 240 sqm = a+b+c+d+e 37738.147 40788.784 50316.281
Rate per sqm = (a+b+c+d+e)/240 157.242 169.953 209.651
Say, 157.20 170.00 209.70
3.25 309 Surface Drains in Soil
Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301
and 309. Excavated material to be used in embankment
within a lead of 1000 metres
Unit = metre
Taking output = 10 metres 4 Cum
A Mechanical means
a) Labour
Mate day 0.010 0.010 0.010 622.000 6.220 6.220 6.220 L-12
Mazdoor for dressing of bed and side of drain day 0.250 0.250 0.250 560.000 140.000 140.000 140.000 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity hour 0.090 0.090 0.090 2570.000 232.071 232.071 232.071 P&M-3005
Tractor-trolley
Tractor-trolley for transportation & for loading & hour 0.246 0.246 0.246 820.000 201.601 201.601 201.601 P&M-12001
Unloding Time
Unit = metre
Taking output = 10 metres 4 Cum
A Mechanical Means
a) Labour
Mate day 0.020 0.020 0.020 622.000 12.440 12.440 12.440 L-12
Mazdoor for dressing of bed and side of drain day 0.500 0.500 0.500 560.000 280.000 280.000 280.000 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity hour 0.112 0.112 0.112 2570.000 286.675 286.675 286.675 P&M-3005
Tractor-trolley
Tractor-trolley for transportation & for loading & hour 0.267 0.267 0.267 820.000 219.024 219.024 219.024 P&M-12001
Unloding Time
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor for excavation and back filling day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
c) Material
Perforated pipe of cement concrete, internal dia 100 metre 10.000 10.000 10.000 1200.00 12000.000 12000.000 12000.000 M-134
mm
Crushed stone as per table 300-3 cum 2.400 2.400 2.400 716.17 1718.813 1718.813 1718.813 M-011
d) Overhead charges @ 8% on (a+b+c) 1189.095 1486.369 1783.643
e) Contractor's profit @ 10% on (a+b+c+d) 1605.279 1635.006 1664.734
Cost for 10 metres = a+b+c+d+e 17658.068 17985.069 18312.070
Rate per metre = (a+b+c+d+e)/10 1765.807 1798.507 1831.207
Say, 1765.80 1798.50 1831.20
Note Type of pipe may be modified depending upon provision in
design.
b) Material
Crushed stone as per table 300-3 cum 1.350 1.350 1.350 716.17 966.832 966.832 966.832 M-011
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 145.542 181.927 218.313
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 196.481 200.120 203.759
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 metres = a+b+c+d 2161.296 2201.320 2241.344
Rate per metre = (a+b+c+d)/10 216.130 220.132 224.134
Say, 216.10 220.10 224.10
3.30 309 Underground Drain at Edge of Pavement
Construction of an underground drain 1 m x 1 m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.
Unit = sqm
Taking output = 3500 sqm 525 Cum
a) Labour
Mate day 0.280 0.280 0.280 622.000 174.160 174.160 174.160 L-12
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
Mazdoor skilled day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
b) Machinery
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Unit = cum
Taking output = 500 cum
a) Labour
Mate day 0.040 0.040 0.040 622.000 24.880 24.880 24.880 L-12
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Dozer
Dozer (240HP) hour 3.731 3005.00 11212.687 P&M-1001
Dozer (175 HP) hour 4.808 2099.00 10091.346 P&M-1002
Dozer (90 HP) hour 8.621 1267.00 10922.414 P&M-1003
Tipper for transportation of rock considering lead @ 5
km
(i) 18 cum capacity t.km 4000.000 6.830 27320.000 P&M-72002
(ii) 14 cum capacity t.km 4000.000 7.770 31080.000 P&M-73002
(iii) 10 cum capacity t.km 4000.000 9.620 38480.000 P&M-74002
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
(i) Motor grader 4.30 metre blade hour 2.177 5796.000 12620.323 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.626 5316.000 13962.257 P&M-2002
(iii) Motor grader 3.35 metre blade hour 2.929 1576.000 4615.482 P&M-2003
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Unit = cum
Taking output = 400 cum 840 tonne
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor skilled day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 4.480 850.000 3808.000 P&M-17001
(ii) 200 tonne per hour hour 4.480 556.000 3808.000 P&M-17002
(iii) 100 tonne per hour hour 11.200 531.000 9520.000 P&M-17003
Electric generator
(i) 125 KVA hour 4.480 2083.000 9331.840 P&M-22005
(ii) 100 KVA hour 4.480 1781.000 9331.840 P&M-22006
(iii) 62.5 KVA hour 11.200 1146.000 23329.600 P&M-22007
Front end loader
(i) 3.1 Cum Capacity hour 9.502 3907.000 37125.339 P&M-5001
(ii) 2.1 Cum Capacity hour 14.047 2393.000 33614.047 P&M-5002
(iii) 1 Cum Capacity hour 29.371 1633.000 47962.238 P&M-5003
Tipper
For transportation
(i) 18 cum capacity t.km 840 x L1 6.830 11474.400 P&M-72002
(ii) 14 cum capacity t.km 840 x L1 7.770 13053.600 P&M-73002
(iii) 10 cum capacity t.km 840 x L1 9.620 16161.600 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 4.480 2621.000 11742.080 P&M-6001
(ii) 14 cum capacity hour 4.480 2331.000 10442.880 P&M-6002
(iii) 10 cum capacity hour 11.200 2077.000 23262.400 P&M-6003
Motor grader
(i) Motor grader 4.30 metre blade hour 3.226 5796.000 18696.774 P&M-2001
(ii) Motor grader 3.70 metre blade hour 3.891 5316.000 20684.825 P&M-2002
(iii) Motor grader 3.35 metre blade hour 4.339 1576.000 6837.752 P&M-2003
Vibratory roller hour 2.589 2.589 2.589 2335.000 6045.307 6045.307 6045.307 P&M-7001
c) Material
Close graded Granular sub-base Material as per
table 400-1
For Grading-I Material
53 mm to 26.5 mm @27.5 per cent cum 148.077 148.077 148.077 903.490 133785.958 133785.958 133785.958 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 121.154 121.154 121.154 906.193 109788.810 109788.810 109788.810 M-026
9.5 mm to 4.75 mm @ 10% cum 53.846 53.846 53.846 843.898 45440.650 45440.650 45440.650 M-024
4.75 mm below @ 40 per cent cum 215.385 215.385 215.385 285.550 61503.062 61503.062 61503.062 M-023
Cost of water KL 67.200 67.200 67.200 74.540 5009.088 5009.088 5009.088 M-191
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 188.462 188.462 188.462 906.193 170782.593 170782.593 170782.593 M-026
9.5 mm to 4.75 mm @ 12.5 % cum 67.308 67.308 67.308 843.898 56800.813 56800.813 56800.813 M-024
4.75 mm below @ 52.5 per cent cum 282.692 282.692 282.692 285.550 80722.768 80722.768 80722.768 M-023
Cost of water KL 67.200 67.200 67.200 74.540 5009.088 5009.088 5009.088 M-191
OR
For Grading-III Material
26.5 mm to 9.5 mm @ 68 per cent cum 366.154 366.154 366.154 906.193 331806.182 331806.182 331806.182 M-026
9.5 mm to 4.75 mm @ 12 % cum 64.615 64.615 64.615 843.898 54528.780 54528.780 54528.780 M-024
4.75 mm below @ 20 per cent cum 107.692 107.692 107.692 285.550 30751.531 30751.531 30751.531 M-023
Cost of water KL 67.200 67.200 67.200 74.540 5009.088 5009.088 5009.088 M-191
OR
For Grading-IV Material
26.5 mm to 9.5 mm @ 64 per cent cum 344.615 344.615 344.615 906.193 312288.171 312288.171 312288.171 M-026
9.5 mm to 4.75 mm @ 11 % cum 59.231 59.231 59.231 843.898 49984.715 49984.715 49984.715 M-024
4.75 mm below @ 25 per cent cum 134.615 134.615 134.615 285.550 38439.413 38439.413 38439.413 M-023
Cost of water KL 67.200 67.200 67.200 74.540 5009.088 5009.088 5009.088 M-191
OR
For Grading-V Material
53 mm to 26.5 mm @27.5 per cent cum 148.077 148.077 148.077 903.490 133785.958 133785.958 133785.958 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 121.154 121.154 121.154 906.193 109788.810 109788.810 109788.810 M-026
9.5 mm to 4.75 mm @ 12.50 % cum 67.308 67.308 67.308 843.898 56800.813 56800.813 56800.813 M-024
4.75 mm below @ 37.5 per cent cum 201.923 201.923 201.923 285.550 57659.120 57659.120 57659.120 M-023
Cost of water KL 67.200 67.200 67.200 74.540 5009.088 5009.088 5009.088 M-191
OR
For Grading-VI Material
53 mm to 26.5 mm @12.5 per cent cum 67.308 67.308 67.308 903.490 60811.799 60811.799 60811.799 M-028
26.5 mm to 9.5 mm @22.5 per cent cum 121.154 121.154 121.154 906.193 109788.810 109788.810 109788.810 M-026
9.5 mm to 4.75 mm @ 22.5 % cum 121.154 121.154 121.154 843.898 102241.463 102241.463 102241.463 M-024
4.75 mm below @ 42.5 per cent cum 228.846 228.846 228.846 285.550 65347.003 65347.003 65347.003 M-023
Cost of water KL 67.200 67.200 67.200 74.540 5009.088 5009.088 5009.088 M-191
4.1A (i) Rate per cum for grading-I Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 36396.246 45370.983 58781.787
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 49134.931 49908.081 54863.001
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 540484.246 548988.891 603493.013
Rate per cum = (a+b+c+d+e)/400 1351.211 1372.472 1508.733
Say, 1351.21 1372.47 1508.73
4.1A (ii) Rate per cum for grading-II Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 33019.261 41149.752 53716.310
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 44576.002 45264.727 50135.223
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 490336.027 497912.001 551487.453
Rate per cum = (a+b+c+d+e)/400 1225.840 1244.780 1378.719
Say, 1225.84 1244.78 1378.72
4.1A (iii) Rate per cum for grading-III Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 41721.687 52027.784 66769.948
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 56324.277 57230.562 62318.619
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 619567.045 629536.186 685504.804
Rate per cum = (a+b+c+d+e)/400 1548.918 1573.840 1713.762
Say, 1548.92 1573.84 1713.76
4.1A (iv) Rate per cum for grading-IV Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 40411.751 50390.365 64805.045
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 54555.864 55429.401 60484.709
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 600114.504 609723.412 665331.799
Rate per cum = (a+b+c+d+e)/400 1500.286 1524.309 1663.329
Say, 1500.29 1524.31 1663.33
4.1A (v) Rate per cum for grading-V Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 36997.543 46122.605 59683.734
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 49946.683 50734.865 55704.818
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 549413.517 558083.519 612752.998
Rate per cum = (a+b+c+d+e)/400 1373.534 1395.209 1531.882
Say, 1373.53 1395.21 1531.88
4.1A (vi) Rate per cum for grading-VI Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 35409.893 44138.042 57302.258
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 47803.356 48551.846 53482.108
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 525836.913 534070.311 588303.186
Rate per cum = (a+b+c+d+e)/400 1314.592 1335.176 1470.758
Say, 1314.59 1335.18 1470.76
Note Any one of the grading for material may be adopted
as per design
4.1 B By Mix in Place Method
Construction of granular sub-base by providing close
graded material, spreading in uniform layers with
motor grader on prepared surface, mixing by mix in
place method with front end loader at OMC, and
compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 250 cum 525 tonne
a) Labour
Mate day 0.160 0.160 0.160 622.000 99.520 99.520 99.520 L-12
Mazdoor skilled day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
Mazdoor day 3.000 3.000 3.000 560.000 1680.000 1680.000 1680.000 L-13
b) Machinery
Front end loader for mixing at stock pile location
Unit = cum
Taking output = 250 cum 525 tonne
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor skilled day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Front end loader for loading to Tipper
(i) 3.1 Cum Capacity hour 1.548 3907.000 6047.988 P&M-5001
(ii) 2.1 Cum Capacity hour 2.283 2393.000 5463.470 P&M-5002
(iii) 1 Cum Capacity hour 4.808 1633.000 7850.962 P&M-5003
Tipper
For transportation
(i) 18 cum capacity t.km 525 x L1 6.830 7171.500 P&M-72002
(ii) 14 cum capacity t.km 525 x L1 7.770 8158.500 P&M-73002
(iii) 10 cum capacity t.km 525 x L1 9.620 10101.000 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 1.548 2621.000 4057.276 P&M-6001
(ii) 14 cum capacity hour 2.283 2331.000 5321.918 P&M-6002
(iii) 10 cum capacity hour 4.808 2077.000 9985.577 P&M-6003
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 3
km/hr )
(i) 16 KL capacity hour 1.361 1357.000 1847.028 P&M-11001
(ii) 12 KL capacity hour 1.815 1187.000 2154.185 P&M-11002
(iii) 6 KL capacity hour 3.630 904.000 3281.185 P&M-11003
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.016 5796.000 11685.484 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.432 5316.000 12928.016 P&M-2002
(iii) Motor grader 3.35 metre blade hour 2.712 1576.000 4273.595 P&M-2003
Vibratory roller hour 1.618 1.618 1.618 2335.000 3778.317 3778.317 3778.317 P&M-7001
c) Material
Close graded Granular sub-base Material as per
table 400-1
For Grading-I Material
53 mm to 4.75 mm below cum 336.538 336.538 336.538 601.222 202334.433 202334.433 202334.433 M-055
Cost of water KL 42.000 42.000 42.000 74.540 3130.680 3130.680 3130.680 M-191
OR
For Grading-II Material
26.5 mm to 4.75 mm below cum 336.538 336.538 336.538 601.222 202334.433 202334.433 202334.433 M-055
Cost of water KL 42.000 42.000 42.000 74.540 3130.680 3130.680 3130.680 M-191
OR
For Grading-III Material
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) ref.
Specification Large Project Medium Project Small Project
Project Project Project
26.5 mm to 4.75 mm below cum 336.538 336.538 336.538 601.222 202334.433 202334.433 202334.433 M-055
Cost of water KL 42.000 42.000 42.000 74.540 3130.680 3130.680 3130.680 M-191
OR
For Grading-IV Material
26.5 mm to 4.75 mm below cum 336.538 336.538 336.538 601.222 202334.433 202334.433 202334.433 M-055
Cost of water KL 42.000 42.000 42.000 74.540 3130.680 3130.680 3130.680 M-191
OR
For Grading-V Material
53 mm to 4.75 mm below cum 336.538 336.538 336.538 601.222 202334.433 202334.433 202334.433 M-055
Cost of water KL 42.000 42.000 42.000 74.540 3130.680 3130.680 3130.680 M-191
OR
For Grading-VI Material
53 mm to 4.75 mm below cum 336.538 336.538 336.538 601.222 202334.433 202334.433 202334.433 M-055
Cost of water KL 42.000 42.000 42.000 74.540 3130.680 3130.680 3130.680 M-191
4.1C (i) Rate per cum for grading-I Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 19300.357 24447.128 29512.501
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 26055.482 26891.841 27545.001
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 286610.304 295810.247 302995.010
Rate per cum = (a+b+c+d+e)/250 1146.441 1183.241 1211.980
Say, 1146.44 1183.24 1211.98
4.1C (ii) Rate per cum for grading-II Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 19300.357 24447.128 29512.501
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 26055.482 26891.841 27545.001
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 286610.304 295810.247 302995.010
Rate per cum = (a+b+c+d+e)/250 1146.441 1183.241 1211.980
Say, 1146.44 1183.24 1211.98
4.1C (iii) Rate per cum for grading-III Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 19300.357 24447.128 29512.501
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 26055.482 26891.841 27545.001
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 286610.304 295810.247 302995.010
Rate per cum = (a+b+c+d+e)/250 1146.441 1183.241 1211.980
Say, 1146.44 1183.24 1211.98
4.1C (iv) Rate per cum for grading-IV Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 19300.357 24447.128 29512.501
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 26055.482 26891.841 27545.001
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 286610.304 295810.247 302995.010
Rate per cum = (a+b+c+d+e)/250 1146.441 1183.241 1211.980
Say, 1146.44 1183.24 1211.98
4.1C (v) Rate per cum for grading-V Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 19300.357 24447.128 29512.501
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 26055.482 26891.841 27545.001
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 286610.304 295810.247 302995.010
Rate per cum = (a+b+c+d+e)/250 1146.441 1183.241 1211.980
Say, 1146.44 1183.24 1211.98
4.1C (vi) Rate per cum for grading-VI Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 19300.357 24125.446 28950.536
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 26055.482 26537.991 27020.500
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 286610.304 291917.902 297225.501
Rate per cum = (a+b+c+d+e)/250 1146.441 1167.672 1188.902
Say, 1146.44 1167.67 1188.90
Note Any one of the grading for material may be adopted
as per design
4.2 A 402 Lime Stabilisation for Improving Sub-grade
Laying and spreading available soil in the sub-grade
on a prepared surface, pulverising, mixing the
spread soil in place with rotavator with 2 per cent
slaked lime having minimum content of 70 per cent
of CaO, grading with motor grader and compacting
with the road roller at OMC to the desired density to
form a layer of improved sub grade
A By Manual Means
a) Labour
Mate day 0.360 0.360 0.360 622.000 223.920 223.920 223.920 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 560.000 4480.000 4480.000 4480.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 1748.000 5882.159 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.875 1748.000 6774.215 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.418 2570.000 13924.233 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.830 7171.500 P&M-72002
(ii) 14 cum capacity t.km 525 x L2 7.770 8158.500 P&M-73002
(iii) 10 cum capacity t.km 525 x L2 9.620 10101.000 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2621.000 8819.873 P&M-6001
(ii) 14 cum capacity hour 3.875 2331.000 9033.579 P&M-6002
(iii) 10 cum capacity hour 5.418 2077.000 11253.164 P&M-6003
Tractor with ripper and rotavator attachments @
250 cum per hour for mixing P&M-12001
hour 1.200 1.200 1.200 841.000 1009.200 1009.200 1009.200 +P&M-13001
+P&M-14001
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 3.602 1357.000 4888.027 P&M-11001
(ii) 12 KL capacity hour 4.803 1187.000 5700.897 P&M-11002
(iii) 6 KL capacity hour 9.606 904.000 8683.422 P&M-11003
c) Material
Lime at site tonne 10.500 10.500 10.500 6500.000 68250.000 68250.000 68250.000 M-190
Cost of water including water for curing KL 99.750 99.750 99.750 74.540 7435.365 7435.365 7435.365 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
By Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
Mazdoor day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 1748.000 5882.159 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.875 1748.000 6774.215 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.418 2570.000 13924.233 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.830 7171.500 P&M-72002
(ii) 14 cum capacity t.km 525 x L2 7.770 8158.500 P&M-73002
(iii) 10 cum capacity t.km 525 x L2 9.620 10101.000 P&M-74002
For loading & unloading Time
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) ref.
Specification Large Project Medium Project Small Project
Project Project Project
(i) 18 cum capacity hour 3.365 2621.000 8819.873 P&M-6001
(ii) 14 cum capacity hour 3.875 2331.000 9033.579 P&M-6002
(iii) 10 cum capacity hour 5.418 2077.000 11253.164 P&M-6003
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 25129.000 67010.667 67010.667 67010.667 P&M-49001
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 7687.000 20498.667 20498.667 20498.667 P&M-50001
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 3.602 1357.000 4888.027 P&M-11001
(ii) 12 KL capacity hour 4.803 1187.000 5700.897 P&M-11002
(iii) 6 KL capacity hour 9.606 904.000 8683.422 P&M-11003
c) Material
Lime at site tonne 10.500 10.500 10.500 6500.000 68250.000 68250.000 68250.000 M-190
Cost of water including water for curing KL 99.750 99.750 99.750 74.540 7435.365 7435.365 7435.365 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
Unit = cum
Taking output = 300 cum 525 tonne
By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 622.000 223.920 223.920 223.920 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 560.000 4480.000 4480.000 4480.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 1748.000 5882.159 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.875 1748.000 6774.215 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.418 2570.000 13924.233 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.830 7171.500 P&M-72002
(ii) 14 cum capacity t.km 525 x L2 7.770 8158.500 P&M-73002
(iii) 10 cum capacity t.km 525 x L2 9.620 10101.000 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2621.000 8819.873 P&M-6001
(ii) 14 cum capacity hour 3.875 2331.000 9033.579 P&M-6002
(iii) 10 cum capacity hour 5.418 2077.000 11253.164 P&M-6003
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 25129.000 67010.667 67010.667 67010.667 P&M-49001
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 3.602 1357.000 4888.027 P&M-11001
(ii) 12 KL capacity hour 4.803 1187.000 5700.897 P&M-11002
(iii) 6 KL capacity hour 9.606 904.000 8683.422 P&M-11003
c) Material
Lime at site tonne 10.500 10.500 10.500 6500.000 68250.000 68250.000 68250.000 M-190
Cost of water including water for curing KL 99.750 99.750 99.750 74.540 7435.365 7435.365 7435.365 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
Mazdoor for spraying lime day 8.000 8.000 8.000 560.000 4480.000 4480.000 4480.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 1748.000 5882.159 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.875 1748.000 6774.215 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.418 2570.000 13924.233 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.830 7171.500 P&M-72002
(ii) 14 cum capacity t.km 525 x L2 7.770 8158.500 P&M-73002
(iii) 10 cum capacity t.km 525 x L2 9.620 10101.000 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2621.000 8819.873 P&M-6001
(ii) 14 cum capacity hour 3.875 2331.000 9033.579 P&M-6002
(iii) 10 cum capacity hour 5.418 2077.000 11253.164 P&M-6003
Tractor with ripper and rotavator attachments @ P&M-12001
250 cum per hour for mixing hour 1.200 1.200 1.200 841.000 1009.200 1009.200 1009.200 +P&M-13001
+P&M-14001
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 3.602 1357.000 4888.027 P&M-11001
(ii) 12 KL capacity 4.803 1187.000 5700.897 P&M-11002
(iii) 6 KL capacity 9.606 904.000 8683.422 P&M-11003
c) Material
Cement at site tonne 10.500 10.500 10.500 6500.000 68250.000 68250.000 68250.000 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 74.540 7435.365 7435.365 7435.365 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
By Mechanical Means
Unit = cum
Taking output = 300 cum 525 tonne
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
Mazdoor for spraying lime day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 1748.000 5882.159 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.875 1748.000 6774.215 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.418 2570.000 13924.233 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.830 7171.500 P&M-72002
(ii) 14 cum capacity t.km 525 x L2 7.770 8158.500 P&M-73002
(iii) 10 cum capacity t.km 525 x L2 9.620 10101.000 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2621.000 8819.873 P&M-6001
(ii) 14 cum capacity hour 3.875 2331.000 9033.579 P&M-6002
(iii) 10 cum capacity hour 5.418 2077.000 11253.164 P&M-6003
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 25129.000 67010.667 67010.667 67010.667 P&M-49001
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 7687.000 20498.667 20498.667 20498.667 P&M-50001
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 3.602 1357.000 4888.027 P&M-11001
(ii) 12 KL capacity hour 4.803 1187.000 5700.897 P&M-11002
(iii) 6 KL capacity hour 9.606 904.000 8683.422 P&M-11003
c) Material
Cement at site tonne 10.500 10.500 10.500 6500.000 68250.000 68250.000 68250.000 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 74.540 7435.365 7435.365 7435.365 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
a) Labour
Mate day 0.360 0.360 0.360 622.000 223.920 223.920 223.920 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 560.000 4480.000 4480.000 4480.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 1748.000 5882.159 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.875 1748.000 6774.215 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.418 2570.000 13924.233 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.830 7171.500 P&M-72002
(ii) 14 cum capacity t.km 525 x L2 7.770 8158.500 P&M-73002
(iii) 10 cum capacity t.km 525 x L2 9.620 10101.000 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2621.000 8819.873 P&M-6001
(ii) 14 cum capacity hour 3.875 2331.000 9033.579 P&M-6002
(iii) 10 cum capacity hour 5.418 2077.000 11253.164 P&M-6003
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 25129.000 67010.667 67010.667 67010.667 P&M-49001
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 3.602 1357.000 4888.027 P&M-11001
(ii) 12 KL capacity hour 4.803 1187.000 5700.897 P&M-11002
(iii) 6 KL capacity hour 9.606 904.000 8683.422 P&M-11003
c) Material
Cement at site tonne 10.500 10.500 10.500 6500.000 68250.000 68250.000 68250.000 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 74.540 7435.365 7435.365 7435.365 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
A By Manual Means
a) Labour
Mate day 0.360 0.360 0.360 622.000 223.920 223.920 223.920 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 560.000 4480.000 4480.000 4480.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 1748.000 5882.159 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.875 1748.000 6774.215 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.418 2570.000 13924.233 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.830 6147.000 P&M-72002
(ii) 14 cum capacity t.km 450 x L2 7.770 6993.000 P&M-73002
(iii) 10 cum capacity t.km 450 x L2 9.620 8658.000 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2621.000 8819.873 P&M-6001
(ii) 14 cum capacity hour 3.875 2331.000 9033.579 P&M-6002
(iii) 10 cum capacity hour 5.418 2077.000 11253.164 P&M-6003
P&M-12001
Tractor with ripper and rotavator attachments @
hour 1.200 1.200 1.200 841.000 1009.200 1009.200 1009.200 +P&M-13001
250 cum per hour for mixing
+P&M-14001
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) ref.
Specification Large Project Medium Project Small Project
Project Project Project
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 3.088 1357.000 4189.738 P&M-11001
(ii) 12 KL capacity hour 4.117 1187.000 4886.483 P&M-11002
(iii) 6 KL capacity hour 8.233 904.000 7442.933 P&M-11003
c) Material
Lime at site tonne 9.000 9.000 9.000 6500.000 58500.000 58500.000 58500.000 M-190
Cost of water including water for curing KL 85.500 85.500 85.500 74.540 6373.170 6373.170 6373.170 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
By Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000
Mazdoor for spraying lime day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 1748.000 5882.159 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.875 1748.000 6774.215 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.418 2570.000 13924.233 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.830 6147.000 P&M-72002
(ii) 14 cum capacity t.km 450 x L2 7.770 6993.000 P&M-73002
(iii) 10 cum capacity t.km 450 x L2 9.620 8658.000 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2621.000 8819.873 P&M-6001
(ii) 14 cum capacity hour 3.875 2331.000 9033.579 P&M-6002
(iii) 10 cum capacity hour 5.418 2077.000 11253.164 P&M-6003
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 25129.000 67010.667 67010.667 67010.667 P&M-49001
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 7687.000 20498.667 20498.667 20498.667 P&M-50001
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 3.088 1357.000 4189.738 P&M-11001
(ii) 12 KL capacity hour 4.117 1187.000 4886.483 P&M-11002
(iii) 6 KL capacity hour 8.233 904.000 7442.933 P&M-11003
c) Material
Lime at site tonne 9.000 9.000 9.000 6500.000 58500.000 58500.000 58500.000 M-190
Cost of water including water for curing KL 85.500 85.500 85.500 74.540 6373.170 6373.170 6373.170 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 622.000 223.920 223.920 223.920 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000
Mazdoor for spraying lime day 8.000 8.000 8.000 560.000 4480.000 4480.000 4480.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 1748.000 5882.159 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.875 1748.000 6774.215 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.418 2570.000 13924.233 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.830 6147.000 P&M-72002
(ii) 14 cum capacity t.km 450 x L2 7.770 6993.000 P&M-73002
(iii) 10 cum capacity t.km 450 x L2 9.620 8658.000 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2621.000 8819.873 P&M-6001
(ii) 14 cum capacity hour 3.875 2331.000 9033.579 P&M-6002
(iii) 10 cum capacity hour 5.418 2077.000 11253.164 P&M-6003
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 25129.000 67010.667 67010.667 67010.667 P&M-49001
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 3.088 1357.000 4189.738 P&M-11001
(ii) 12 KL capacity hour 4.117 1187.000 4886.483 P&M-11002
(iii) 6 KL capacity hour 8.233 904.000 7442.933 P&M-11003
c) Material
Lime at site tonne 9.000 9.000 9.000 6500.000 58500.000 58500.000 58500.000 M-190
Cost of water including water for curing KL 85.500 85.500 85.500 74.540 6373.170 6373.170 6373.170 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
By Mechanical Means
a) Labour
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) ref.
Specification Large Project Medium Project Small Project
Project Project Project
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000
Mazdoor for spraying lime day 1.000 1.000 1.000 560.000 560.000 560.000 560.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 1748.000 5882.159 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.875 1748.000 6774.215 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.418 2570.000 13924.233 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.830 6147.000 P&M-72002
(ii) 14 cum capacity t.km 450 x L2 7.770 6993.000 P&M-73002
(iii) 10 cum capacity t.km 450 x L2 9.620 8658.000 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2621.000 8819.873 P&M-6001
(ii) 14 cum capacity hour 3.875 2331.000 9033.579 P&M-6002
(iii) 10 cum capacity hour 5.418 2077.000 11253.164 P&M-6003
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 25129.000 67010.667 67010.667 67010.667 P&M-49001
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 7687.000 20498.667 20498.667 20498.667 P&M-50001
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 3.088 1357.000 4189.738 P&M-11001
(ii) 12 KL capacity hour 4.117 1187.000 4886.483 P&M-11002
(iii) 6 KL capacity hour 8.233 904.000 7442.933 P&M-11003
c) Material
Cement at site tonne 9.000 9.000 9.000 6500.000 58500.000 58500.000 58500.000 M-190
Cost of water including water for curing KL 85.500 85.500 85.500 74.540 6373.170 6373.170 6373.170 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 622.000 223.920 223.920 223.920 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000
Mazdoor for spraying lime day 8.000 8.000 8.000 560.000 4480.000 4480.000 4480.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 1748.000 5882.159 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.875 1748.000 6774.215 P&M-3004
(iii) 0.9 cum bucket capacity hour 5.418 2570.000 13924.233 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.830 6147.000 P&M-72002
(ii) 14 cum capacity t.km 450 x L2 7.770 6993.000 P&M-73002
(iii) 10 cum capacity t.km 450 x L2 9.620 8658.000 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2621.000 8819.873 P&M-6001
(ii) 14 cum capacity hour 3.875 2331.000 9033.579 P&M-6002
(iii) 10 cum capacity hour 5.418 2077.000 11253.164 P&M-6003
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 25129.000 67010.667 67010.667 67010.667 P&M-49001
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 3.088 1357.000 4189.738 P&M-11001
(ii) 12 KL capacity hour 4.117 1187.000 4886.483 P&M-11002
(iii) 6 KL capacity hour 8.233 904.000 7442.933 P&M-11003
c) Material
Cement at site tonne 9.000 9.000 9.000 6500.000 58500.000 58500.000 58500.000 M-190
Cost of water including water for curing KL 85.500 85.500 85.500 74.540 6373.170 6373.170 6373.170 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
Unit = cum
Taking output = 300 cum 525 tonne
a) Labour
Mate day 0.480 0.48 0.48 622.000 298.560 298.560 298.560 L-12
Mazdoor skilled day 2.000 2.00 2.00 592.000 1184.000 1184.000 1184.000 L-15
Mazdoor day 10.000 10.00 10.00 560.000 5600.000 5600.000 5600.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 7.852 1748.000 13725.037 P&M-3003
(ii) 1.1 cum bucket capacity hour 9.04 1748.000 15806.502 P&M-3004
(iii) 0.9 cum bucket capacity hour 12.64 2570.000 32489.877 P&M-3005
Tipper
For Transportation of Soil
(i) 18 cum capacity t.km 525 x L2 6.830 7171.500 P&M-72002
(ii) 14 cum capacity t.km 525 x L2 7.770 8158.500 P&M-73002
(iii) 10 cum capacity t.km 525 x L2 9.620 10101.000 P&M-74002
For loading & unloading
(i) 18 cum capacity hour 7.852 2621.000 20579.704 P&M-6001
(ii) 14 cum capacity hour 9.04 2331.000 21078.351 P&M-6002
(iii) 10 cum capacity hour 12.64 2077.000 26257.383 P&M-6003
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.92 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.25 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.46 1.46 2335.000 3400.485 3400.485 3400.485 P&M-7001
P&M-12001
Tractor with ripper and rotavator attachments @
hour 1.200 1.20 1.20 841.000 1009.200 1009.200 1009.200 +P&M-13001
250 cum per hour for mixing
+P&M-14001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and spreading speed @ 2.5 km/hr )
c) Material
Lime at site tonne 15.750 15.75 15.75 6500.000 102375.000 102375.000 102375.000 M-190
Compensation for earth taken from private land cum 300.000 300.00 300.00 45.000 13500.000 13500.000 13500.000 M-093
Cost of water KL 52.500 52.5 52.50 74.540 3913.350 3913.350 3913.350 M-191
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) ref.
Specification Large Project Medium Project Small Project
Project Project Project
d) Overhead charges @ 8% on @ 10% on @ 12% on 15173.496 19520.733 25246.786
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 20484.219 21472.806 23563.667
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 225326.411 236200.868 259200.332
Rate per cum= (a+b+c+d+e)/300 751.088 787.336 864.001
Say, 751.09 787.34 864.00
4.6 403 Cement Treated Soil Sub Base/ Base
Providing, laying and spreading soil on a
prepared sub grade, pulverising, adding the
designed quantity of cement to the spread soil,
mixing in place with rotavator, grading with the
motor grader and compacting with the road roller
at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-
base/base.
Unit = cum
Taking output = 300 cum 525 tonne
For 4 per cent quantity of cement by weight of soil
a) Labour
Mate day 0.480 0.480 0.480 622.000 298.560 298.560 298.560 L-12
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
Mazdoor day 10.000 10.000 10.000 560.000 5600.000 5600.000 5600.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 7.852 1748.000 13725.037 P&M-3003
(ii) 1.1 cum bucket capacity hour 9.043 1748.000 15806.502 P&M-3004
(iii) 0.9 cum bucket capacity hour 12.642 2570.000 32489.877 P&M-3005
Tipper
For Transportation of Soil
(i) 18 cum capacity t.km 525 x L2 6.830 7171.500 P&M-72002
(ii) 14 cum capacity t.km 525 x L2 7.770 8158.500 P&M-73002
(iii) 10 cum capacity t.km 525 x L2 9.620 10101.000 P&M-74002
For loading & unloading
(i) 18 cum capacity hour 7.852 2621.000 20579.704 P&M-6001
(ii) 14 cum capacity hour 9.043 2331.000 21078.351 P&M-6002
(iii) 10 cum capacity hour 12.642 2077.000 26257.383 P&M-6003
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Tractor with ripper and rotavator attachments @ P&M-12001
250 cum per hour for mixing hour 1.200 1.200 1.200 841.000 1009.200 1009.200 1009.200 +P&M-13001
+P&M-14001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 0.729 1357.000 989.479 P&M-11001
(ii) 12 KL capacity hour 0.972 1187.000 1154.028 P&M-11002
(iii) 6 KL capacity hour 1.944 904.000 1757.778 P&M-11003
c) Material
Cement at site (@ 4 per cent of 525 tonne) tonne 21.000 21.000 21.000 6500.000 136500.000 136500.000 136500.000 M-081
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.000 13500.000 13500.000 13500.000 M-093
Cost of water KL 52.500 52.500 52.500 74.540 3913.350 3913.350 3913.350 M-191
d) Overhead charges @ 8% on (a+b+c) 17751.512 22711.660 28936.794
e) Contractor's profit @ 10% on (a+b+c+d) 23964.541 24982.825 27007.674
Unit = cum
Taking output = 300 cum 600 tonne
Quantity of cement assumed as 4 per cent of
quantity of crushed rock by weight.
a) Labour
Mate day 0.480 0.480 0.480 622.000 298.560 298.560 298.560 L-12
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
Mazdoor day 10.000 10.000 10.000 560.000 5600.000 5600.000 5600.000 L-13
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.419 5796.000 14022.581 P&M-2001
(ii) Motor grader 3.70 metre blade hour 2.918 5316.000 15513.619 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.254 1576.000 5128.314 P&M-2003
Vibratory roller hour 1.456 1.456 1.456 2335.000 3400.485 3400.485 3400.485 P&M-7001
Tractor with ripper and rotavator attachments @ P&M-12001
250 cum per hour for mixing hour 1.200 1.200 1.200 841.000 1009.200 1009.200 1009.200 +P&M-13001
+P&M-14001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 2.433 1357.000 3302.033 P&M-11001
(ii) 12 KL capacity hour 3.244 1187.000 3851.156 P&M-11002
(iii) 6 KL capacity hour 6.489 904.000 5865.956 P&M-11003
c) Material
Cement at site @ 4 per cent by weight of tonne 24.000 24.000 24.000 6500.000 156000.000 156000.000 156000.000 M-081
crushed aggregate (600 tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent cum 211.200 211.200 211.200 920.350 194377.833 194377.833 194377.833 M-027
9.5 mm to 4.75 mm @ 20 per cent cum 76.800 76.800 76.800 860.758 66106.198 66106.198 66106.198 M-024
4.75 mm to 75 micron @ 25 per cent cum 96.000 96.000 96.000 302.410 29031.353 29031.353 29031.353 M-022
Cost of water KL 60.000 60.000 60.000 74.540 4472.400 4472.400 4472.400 M-191
or
Grading of material for Base course
37.5 mm to 9.5 mm @ 32.5 per cent cum 124.800 124.800 124.800 920.350 114859.629 114859.629 114859.629 M-027
9.5 mm to 4.75 mm @ 5 per cent cum 19.200 19.200 19.200 860.758 16526.550 16526.550 16526.550 M-024
4.75 mm to 75 micron @ 62.5 per cent cum 240.000 240.000 240.000 302.410 72578.383 72578.383 72578.383 M-022
Cost of water KL 60.000 60.000 60.000 74.540 4472.400 4472.400 4472.400 M-191
4.7 (i) For Sub-Base course
d) Overhead charges @ 8% on (a+b+c) 38304.372 48084.480 56696.916
e) Contractor's profit @ 10% on (a+b+c+d) 51710.902 52892.928 52917.122
Unit = cum
Taking output = 250 cum 525 tonne
By Mechanical Means
a) Labour
Mate day 0.400 0.400 0.400 622.000 248.800 248.800 248.800 L-12
Skilled mazdoor for alignment and geometrics day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 560.000 4480.000 4480.000 4480.000 L-13
b) Machinery
Front end loader for mixing at stock pile location
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
(i) 25mm deep furrow cutting
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Tractor-trolley hour 0.200 0.200 0.200 820.000 164.000 164.000 164.000 P&M-12001
c) Overhead charges @ 8% on (a+b) 106.701 133.376 160.051
d) Contractor's profit @ 10% on (a+b+c) 144.046 146.714 149.381
Cost for 210 sqm= a+b+c+d 1584.507 1613.850 1643.192
Rate per sqm =(a+b+c+d)/210 7.545 7.685 7.825
Say, 7.55 7.68 7.82
(ii) 50mm deep furrow cutting
a) Labour
Mate day 0.160 0.160 0.160 622.000 99.520 99.520 99.520 L-12
Mazdoor day 4.000 4.000 4.000 560.000 2240.000 2240.000 2240.000 L-13
b) Machinery
Tractor-trolley hour 0.400 0.400 0.400 820.000 328.000 328.000 328.000 P&M-12001
c) Overhead charges @ 8% on (a+b) 213.402 266.752 320.102
d) Contractor's profit @ 10% on (a+b+c) 288.092 293.427 298.762
Cost for 210 sqm= a+b+c+d 3169.014 3227.699 3286.385
Rate per sqm =(a+b+c+d)/210 15.091 15.370 15.649
Say, 15.09 15.37 15.65
4.10 404.3.2 Inverted Choke
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) ref.
Specification Large Project Medium Project Small Project
Project Project Project
Construction of inverted choke by providing, laying,
spreading and compacting screening B type/ coarse
sand of specified grade in uniform layer on a
prepared surface with motor grader and compacting
with power roller etc
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.920 0.920 0.920 622.000 572.240 572.240 572.240 L-12
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
Mazdoor day 21.000 21.000 21.000 560.000 11760.000 11760.000 11760.000 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 4.839 5796.000 28045.161 P&M-2001
(ii) Motor grader 3.70 metre blade hour 5.837 5316.000 31027.237 P&M-2002
(iii) Motor grader 3.35 metre blade hour 6.508 1576.000 10256.627 P&M-2003
Vibratory roller 8-10 tonnes @ 60 cum per hour hour 6.000 6.000 6.000 2335.000 14010.000 14010.000 14010.000 P&M-7001
A By Manual Means
Unit = cum
Taking output = 360 Cum 756 tonne
a) Labour
Mate day 10.080 10.080 10.080 622.000 6269.760 6269.760 6269.760 L-12
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
Mazdoor day 250.000 250.000 250.000 560.000 140000.000 140000.000 140000.000 L-13
b) Machinery
Vibratory roller hour 2.330 2.330 2.330 2335.000 5440.777 5440.777 5440.777 P&M-7001
or
Smooth 3 wheeled steel roller @ 30cum/hour hour 4.660 4.660 4.660 0.000 0.000 0.000
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per cum 97.200 97.200 97.200 860.758 83665.657 83665.657 83665.657 M-051
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 108.000 108.000 108.000 405.775 43823.700 43823.700 43823.700 M-007
grading-I @ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for cum 28.800 28.800 28.800 405.775 11686.320 11686.320 11686.320 M-007
grading I material
Cost of water KL 144.000 144.000 144.000 74.540 10733.760 10733.760 10733.760 M-191
4.11 A (i) (a) Using Scrining Crushable type such as Moorum or Gravel
d) Overhead charges @ 8% on (a+b+c) 53236.313 66677.181 80592.880
e) Contractor's profit @ 10% on (a+b+c+d) 71869.023 73344.899 75220.021
Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per cum 57.600 57.600 57.600 860.758 49579.649 49579.649 49579.649 M-051
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 405.775 42845.782 42845.782 42845.782 M-007
grading II &III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.18 cum per cum 86.400 86.400 86.400 860.758 74369.473 74369.473 74369.473 M-050
10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for cum 28.800 28.800 28.800 405.775 11686.320 11686.320 11686.320 M-007
grading II material
Cost of water KL 144.000 144.000 144.000 74.540 10733.760 10733.760 10733.760 M-191
4.11 A (ii) (a) Using Scrining Crushable type such as Moorum or Gravel
Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per cum 86.400 86.400 86.400 860.758 74369.473 74369.473 74369.473 M-050
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 405.775 42845.782 42845.782 42845.782 M-007
grading II &III @ 0.22 cum per 10 sqm
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) ref.
Specification Large Project Medium Project Small Project
Project Project Project
Binding material
Binding Material @ 0.06cum per 10 sqm for cum 28.800 28.800 28.800 405.775 11686.320 11686.320 11686.320 M-007
grading II material
Cost of water KL 144.000 144.000 144.000 74.540 10733.760 10733.760 10733.760 M-191
4.11 A (iii) (a) Using Scrining Crushable type such as Moorum or Gravel
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per cum 97.200 97.200 97.200 860.758 83665.657 83665.657 83665.657 M-051
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 108.000 108.000 108.000 405.775 43823.700 43823.700 43823.700 M-007
grading-I @ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for cum 28.800 28.800 28.800 405.775 11686.320 11686.320 11686.320 M-007
grading I material
Cost of water KL 144.000 144.000 144.000 74.540 10733.760 10733.760 10733.760 M-191
4.11 B (i) (a) Using Scrining Crushable type such as Moorum or Gravel
d) Overhead charges @ 8% on (a+b+c) 78706.721 98449.525 118422.946
e) Contractor's profit @ 10% on (a+b+c+d) 64865.736 66906.140 69139.745
Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per cum 57.600 57.600 57.600 860.758 49579.649 49579.649 49579.649 M-051
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 405.775 42845.782 42845.782 42845.782 M-007
grading II &III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.18 cum per cum 86.400 86.400 86.400 860.758 74369.473 74369.473 74369.473 M-050
10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for cum 28.800 28.800 28.800 405.775 11686.320 11686.320 11686.320 M-007
grading II material
Cost of water KL 144.000 144.000 144.000 74.540 10733.760 10733.760 10733.760 M-191
4.11 B (ii) (a) Using Scrining Crushable type such as Moorum or Gravel
Stone Screening
Type B11.2 mm for grading-III @ 0.18 cum per cum 86.400 86.400 86.400 860.758 74369.473 74369.473 74369.473 M-050
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 405.775 42845.782 42845.782 42845.782 M-007
grading II &III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for cum 28.800 28.800 28.800 405.775 11686.320 11686.320 11686.320 M-007
grading II material
Cost of water KL 144.000 144.000 144.000 74.540 10733.760 10733.760 10733.760 M-191
4.11 B (iii) (a) Using Scrining Crushable type such as Moorum or Gravel
Unit = cum
Taking output = 360 cum 720.000 Tonne
a) Labour
Mate day 4.160 4.160 4.160 622.000 2587.520 2587.520 2587.520 L-12
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
Mazdoor for crushing broken cement concrete day 102.000 102.000 102.000 560.000 57120.000 57120.000 57120.000 L-13
pavement/slabs into aggregate
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.903 5796.000 16827.097 P&M-2001
(ii) Motor grader 3.70 metre blade hour 3.502 5316.000 18616.342 P&M-2002
(iii) Motor grader 3.35 metre blade hour 3.905 1576.000 6153.976 P&M-2003
Vibratory roller 8 - 10 tonne@ 60 cum per hour hour 6.000 6.000 6.000 2335.000 14010.000 14010.000 14010.000 P&M-7001
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000 12.000 12.000 0.000 0.000 0.000
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day 0.560 0.560 0.560 622.000 348.320 348.320 348.320 L-12
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
Mazdoor day 12.000 12.000 12.000 560.000 6720.000 6720.000 6720.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.232 2.232 2.232 951.000 1388.393 1388.393 1388.393 P&M-23001
Hydraulic self propelled chips spreader hour 5.140 5.140 5.140 1989.000 10223.067 10223.067 10223.067 P&M-32001
Front end loader 1 cum bucket capacity hour 6.000 6.000 6.000 1633.000 9798.000 9798.000 9798.000 P&M-5003
Tipper 10 tonne capacity hour 6.000 6.000 6.000 1590.000 9540.000 9540.000 9540.000 P&M-6004
Vibratory roller 8 -10 tonnes hour 5.140 5.140 5.140 2335.000 12001.439 12001.439 12001.439 P&M-7001
Bitumen pressure distributor @ 1750 sqm per hour 4.280 4.280 4.280 1550.000 2662.160 2662.160 2662.160 P&M-24001
hour
c) Material
Crushed stone aggregate 11.2 mm size cum 97.500 97.500 97.500 860.758 83923.884 83923.884 83923.884 M-050
Bitumen (60-70 grade) tonne 0.250 0.250 0.250 34512.450 8628.113 8628.113 8628.113 M-074
d) Overhead charges @ 8% on @ 10% on @ 12% on 11713.390 14641.738 17570.085
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 15813.077 16105.911 16398.746
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7500 sqm = a+b+c+d+e 173943.843 177165.025 180386.208
Rate per sqm = (a+b+c+d+e)/7500 23.193 23.622 24.051
Say, 23.19 23.62 24.05
Note Though vibratory roller is required only for 3 hours as
per norms, the same is required to be available at
site for 6 hours to match with other machines. The
usage rates of vibratory roller may be multiplied with
a factor of 0.65.
4.14 406 A Wet Mix Macadam (Plant Mix Method)
Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC
in mechanical mix plant carriage of mixed Material
by tipper to site, laying in uniform layers with paver in
sub- base / base course on well prepared surface
and compacting with vibratory roller to achieve the
desired density.
Unit = cum
Taking output = 21 cum 46.2 tonne
a) Labour
Mate day 0.240 0.240 0.240 622.000 149.280 149.280 149.280 L-12
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
b) Machinery
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 0.039 1357.000 52.814 P&M-11001
(ii) 12 KL capacity hour 0.052 1187.000 61.597 P&M-11002
(iii) 6 KL capacity hour 0.104 904.000 93.823 P&M-11003
Plate compactor @ 3.5 cum per hour hour 6.000 6.000 6.000
c) Material
Cost of water KL 2.520 2.520 2.520 74.540 187.841 187.841 187.841 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 299.995 375.872 454.913
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 404.993 413.459 424.586
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 21 cum = a+b+c+d+e 4454.923 4548.049 4670.443
Rate per cum = (a+b+c+d+e)/21 212.139 216.574 222.402
Say, 212.14 216.57 222.40
Note This analysis provides for median and island with
earthen top. In case the surface is required to be
turfed or planted with shrubs, the same is required to
be provided separately as per analysis given in the
chapter on horticulture. In case granular fill is
required to be paved, quantities of paving are
required to be calculated as per approved design
and paid separately.
Unit = cum
Taking output = 21 cum 31.5 tonne
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.236 1748.000 411.751 P&M-3003
(ii) 1.1 cum bucket capacity hour 0.271 1748.000 474.195 P&M-3004
(iii) 0.9 cum bucket capacity hour 0.379 2570.000 974.696 P&M-3005
Tipper
For Transportation
(i) 18 cum capacity t.km 31.5 x L2 6.830 430.290 P&M-72002
(ii) 14 cum capacity t.km 31.5 x L2 7.770 489.510 P&M-73002
(iii) 10 cum capacity t.km 31.5 x L2 9.620 606.060 P&M-74002
For loading & unloading time
(i) 18 cum capacity hour 0.236 2621.000 617.391 P&M-6001
(ii) 14 cum capacity hour 0.271 2331.000 632.351 P&M-6002
(iii) 10 cum capacity hour 0.379 2077.000 787.721 P&M-6003
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 0.039 1357.000 52.814 P&M-11001
(ii) 12 KL capacity hour 0.052 1187.000 61.597 P&M-11002
(iii) 6 KL capacity hour 0.104 904.000 93.823 P&M-11003
Plate compactor hour 1.400 1.400 1.400 528.000 739.200 739.200 739.200 P&M-46001
c) Material
Compensation for earth taken from private land cum 21.000 21.000 21.000 45.000 945.000 945.000 945.000 M-093
Cost of water KL 2.520 2.520 2.520 74.540 187.841 187.841 187.841 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 364.324 469.945 660.492
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 491.837 516.940 616.459
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 21 cum = a+b+c+d+e 5410.208 5686.339 6781.053
Rate per cum = (a+b+c+d+e)/21 257.629 270.778 322.907
Say, 257.63 270.78 322.91
Note This analysis provides for median and island with
earthen top. In case the surface is required to be
turfed or planted with shrubs, the same is required to
be provided separately as per analysis given in the
chapter on horticulture. In case surface finish is of
hard type, the same may be provided separately as
per approved design.
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 1.360 1.360 622.000 845.920 845.920 845.920 L-12
Mason day 4.000 4.000 4.000 622.000 2488.000 2488.000 2488.000 L-11
Mazdoor day 30.000 30.000 30.000 560.000 16800.000 16800.000 16800.000 L-13
b) Machinery
Vibratory roller hour 0.750 0.750 0.750 2335.000 1751.250 1751.250 1751.250 P&M-7001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 0.487 1357.000 660.407 P&M-11001
(ii) 12 KL capacity hour 0.649 1187.000 770.231 P&M-11002
(iii) 6 KL capacity hour 1.298 904.000 1173.191 P&M-11003
Concrete mixer 0.4/0.28 cum per hour hour 6.000 6.000 6.000 451.000 2706.000 2706.000 2706.000 P&M-21001
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 20.790 20.790 950.145 19753.525 19753.525 19753.525 M-035
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 26.730 26.730 716.172 19143.283 19143.283 19143.283 M-030
2.36 mm below @ 20 per cent cum 11.880 11.880 11.880 860.758 10225.803 10225.803 10225.803 M-049
ii) For cement concrete grade M15 7.5 cum
Aggregate 12 mm crushed @ 0.9 cum of cum 6.750 6.750 6.750 860.758 5810.115 5810.115 5810.115 M-051
concrete
Sand @ 0.45 cum/cum of concrete cum 3.380 3.380 3.380 805.775 2723.520 2723.520 2723.520 M-006
Cement tonne 1.880 1.880 1.880 6500.000 12220.000 12220.000 12220.000 M-081
iii) For cement plaster 1:3
Sand cum 3.840 3.840 3.840 805.775 3094.176 3094.176 3094.176 M-006
Cement tonne 1.830 1.830 1.830 6500.000 11895.000 11895.000 11895.000 M-081
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 3300.000 3300.000 12.000 39600.000 39600.000 39600.000 M-186
v) RCC pipes
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) ref.
Specification Large Project Medium Project Small Project
Project Project Project
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 22.500 22.500 1200.000 27000.000 27000.000 27000.000 M-136
vi) Cost of water KL 12.000 12.000 12.000 74.540 894.480 894.480 894.480 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 14208.918 17772.130 21374.911
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 19182.040 19549.343 19949.917
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 sqm = a+b+c+d+e 211002.436 215042.776 219449.091
Rate per sqm = (a+b+c+d+e)/300 586.118 597.341 609.581
Say, 586.12 597.34 609.58
4.20 410 Crusher Run Macadam Base
Providing crushed stone aggregate, depositing on a
prepared surface by hauling vehicles, spreading and
mixing with a motor grader, watering and compacting
with a vibratory roller to clause 417 to form a layer of
sub-base/Base
Unit = cum
Taking output = 360 cum 720 tonne
A By Mix in Place Method
a) Labour
Mate day 0.480 0.480 0.480 622.000 298.560 298.560 298.560 L-12
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
Mazdoor day 10.000 10.000 10.000 560.000 5600.000 5600.000 5600.000 L-13
b) Machinery
Tractor attached with rotavator @ 25 cum per P&M-12001
hour hour 12.000 12.000 12.000 841.000 10092.000 10092.000 10092.000 +P&M-13001
+P&M-14001
Front end loader for mixing at stock pile location
Unit = cum
Taking output = 480 cum (720 tonne, density 1.50
t/cum)
Assumptions made
Total mass taken for analysis = 720 t 720.00 Tonne
Lime + Flyash admixture @ 20 per cent = 0.2 x
720=144 t
Soil = 720 -144 = 576 t 576.00 Tonne
576 /1.6 = 360 cum 360.00 Cum
Lime + Flyash = 144 t 144.00 Tonne
Ratio Lime 4 : Flyash 16 49.40 Cum
Lime = 29 kg. 409.40 Cum
Flyash = 115 kg.
a) Labour
Mate day 0.240 0.240 0.240 622.000 149.280 149.280 149.280 L-12
Mazdoor day 6.000 6.000 6.000 560.000 3552.000 3552.000 3552.000 L-13
Mazdoor skilled day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 4.038 1748.000 7058.590 P&M-3003
(ii) 1.1 cum bucket capacity hour 4.650 1748.000 8129.058 P&M-3004
(iii) 0.9 cum bucket capacity hour 6.502 2570.000 16709.079 P&M-3005
Tipper
For transportation
(i) 18 cum capacity t.km 720 x L1 6.830 9835.200 P&M-72002
(ii) 14 cum capacity t.km 720 x L1 7.770 11188.800 P&M-73002
(iii) 10 cum capacity t.km 720 x L1 9.620 13852.800 P&M-74002
For Loading & unloading time
(i) 18 cum capacity hour 4.038 2621.000 10583.848 P&M-6001
(ii) 14 cum capacity hour 4.650 2331.000 10840.295 P&M-6002
(iii) 10 cum capacity hour 6.502 2077.000 13503.797 P&M-6003
Tractor with disc harrows for pulverisation hour 6.000 6.000 6.000 820.000 4920.000 4920.000 4920.000 P&M-12001
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 3.302 5796.000 19136.000 P&M-2001
(ii) Motor grader 3.70 metre blade hour 3.982 5316.000 21170.754 P&M-2002
(iii) Motor grader 3.35 metre blade hour 4.441 1576.000 6998.385 P&M-2003
Vibratory roller hour 6.000 6.000 6.000 2335.000 14010.000 14010.000 14010.000 P&M-7001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and spreading speed @ 2.5
km/hr )
(i) 16 KL capacity hour 2.172 1357.000 2947.518 P&M-11001
(ii) 12 KL capacity hour 2.896 1187.000 3437.685 P&M-11002
(iii) 6 KL capacity hour 5.792 904.000 5236.170 P&M-11003
c) Material
Slaked Lime tonne 29.000 29.000 29.000 6500.000 188500.000 188500.000 188500.000 M-190
Compensation for earth taken from private source cum 360.000 360.000 360.000 45.000 16200.000 16200.000 16200.000 M-093
Cost of water (considering 5% additional KL 43.200 43.200 43.200 74.540 3220.128 3220.128 3220.128 M-191
moisture required)
d) Overhead charges @ 8% on @ 10% on @ 12% on 22456.365 28591.000 34493.237
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 30316.093 31450.100 32193.688
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 480 cum = a+b+c+d+e 333477.022 345951.100 354130.563
Rate per cum= (a+b+c+d+e)/480 694.744 720.731 737.772
Say, 694.74 720.73 737.77
Note 1.Compensation for earth will vary from place to
place and will have to be assessed realistically as
per particular ground situation. In case earth is
available from Govt. land, compensation for earth
will not be required. The position is required to be
clearly stated in the cost estimate.
(i) Providing and applying primer coat with SS1 grade bitumen
emulsion on prepared surface of granular Base including
clearing of road surface and spraying primer at the rate of
0.70 to 1.00 kg/sqm using mechanical means.
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 951.000 1981.250 1981.250 1981.250 P&M-23001
Air compressor 250 cfm hour 2.083 2.083 2.083 550.000 1145.833 1145.833 1145.833 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.944 1.944 1.944 1550.000 3013.889 3013.889 3013.889 P&M-24001
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 951.000 1981.250 1981.250 1981.250 P&M-23001
Air compressor 250 cfm hour 2.083 2.083 2.083 550.000 1145.833 1145.833 1145.833 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.944 1.944 1.944 1550.000 3013.889 3013.889 3013.889 P&M-24001
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 951.000 1981.250 1981.250 1981.250 P&M-23001
Air compressor 250 cfm hour 2.083 2.083 2.083 550.000 1145.833 1145.833 1145.833 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.944 1.944 1.944 1550.000 3013.889 3013.889 3013.889 P&M-24001
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 951.000 1981.250 1981.250 1981.250 P&M-23001
Air compressor 250 cfm hour 2.083 2.083 2.083 550.000 1145.833 1145.833 1145.833 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.944 1.944 1.944 1550.000 3013.889 3013.889 3013.889 P&M-24001
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 951.000 1981.250 1981.250 1981.250 P&M-23001
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Amount
Quantity
(Rs.)
Reference to Rate Remarks/ Input
Sr No Description Unit For Large For Medium For Small Medium
MORT&H Specification (Rs.) Large Project Small Project ref.
Project Project Project Project
Air compressor 250 cfm hour 2.083 2.083 2.083 550.000 1145.833 1145.833 1145.833 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.944 1.944 1.944 1550.000 3013.889 3013.889 3013.889 P&M-24001
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 1.750 1.750 1.750 35012.450 61271.788 61271.788 61271.788 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 5486.602 6858.252 8229.902
e) Contractor's profit @ 10% on @ 10% on @ 10% on 7406.912 7544.077 7681.242
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 81476.033 82984.849 84493.664
Rate per Sqm = (a+b+c+d+e)/7000 11.639 11.855 12.071
Say, 11.64 11.85 12.07
Note 1. Bitumen emulsion has been provided @ 0.25 kg per sqm
as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
5.2 503 (ii) Tack Coat on Granular surfaces treated with primer
Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.25 to 0.30
kg per sqm on the prepared bituminous surface cleaned with
mechanical broom.
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 951.000 1981.250 1981.250 1981.250 P&M-23001
Air compressor 250 cfm hour 2.083 2.083 2.083 550.000 1145.833 1145.833 1145.833 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.944 1.944 1.944 1550.000 3013.889 3013.889 3013.889 P&M-24001
c) Material
Bitumen emulsion @ 0.275 kg per sqm tonne 1.925 1.925 1.925 35012.450 67398.966 67398.966 67398.966 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 5976.776 7470.970 8965.164
e) Contractor's profit @ 10% on @ 10% on @ 10% on 8068.647 8218.067 8367.486
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 88755.122 90398.735 92042.349
Rate per Sqm = (a+b+c+d+e)/7000 12.679 12.914 13.149
Say, 12.68 12.91 13.15
Note 1. Bitumen emulsion has been provided @ 0.275 kg per sqm
as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 622.000 49.760 49.760 49.760 L-12
Mazdoor day 2.000 2.000 2.000 560.000 1120.000 1120.000 1120.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 951.000 1981.250 1981.250 1981.250 P&M-23001
Air compressor 250 cfm hour 2.083 2.083 2.083 550.000 1145.833 1145.833 1145.833 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.944 1.944 1.944 1550.000 3013.889 3013.889 3013.889 P&M-24001
c) Material
Bitumen emulsion @ 0.325 kg per sqm tonne 2.275 2.275 2.275 35012.450 79653.324 79653.324 79653.324 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 6957.124 8696.406 10435.687
e) Contractor's profit @ 10% on @ 10% on @ 10% on 9392.118 9566.046 9739.974
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 103313.298 105226.508 107139.717
Rate per Sqm = (a+b+c+d+e)/7000 14.759 15.032 15.306
Say, 14.76 15.03 15.31
Note 1. Bitumen emulsion has been provided @ 0.325 kg per sqm
as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
Unit = cum
Taking output = 205 cum 451.00 tonnes
a) Labour
Mate day 0.440 0.440 0.440 622.000 273.680 273.680 273.680 L-12
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
Mazdoor skilled day 5.000 5.000 5.000 592.000 2960.000 2960.000 2960.000 L-15
b) Machinery
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 3.007 13298.000 39982.653 P&M-18001
(ii) HMP 160 TPH hour 3.758 9323.000 35038.942 P&M-18002
(iii) HMP 120 TPH hour 5.011 7568.000 37924.089 P&M-18003
Mechanical broom (2.1m sweeping width) hour 0.697 0.697 0.697 951.000 663.112 663.112 663.112 P&M-23001
Air compressor 250 cfm hour 0.697 0.697 0.697 550.000 383.503 383.503 383.503 P&M-15001
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
Unit = cum
Taking output = 205 cum 451.00 tonnes
a) Labour
Mate day 0.440 0.440 0.440 622.000 273.680 273.680 273.680 L-12
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
Mazdoor skilled day 5.000 5.000 5.000 592.000 2960.000 2960.000 2960.000 L-15
b) Machinery
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 3.007 13298.000 39982.653 P&M-18001
(ii) HMP 160 TPH hour 3.758 9323.000 35038.942 P&M-18002
(iii) HMP 120 TPH hour 5.011 7568.000 37924.089 P&M-18003
Mechanical broom (2.1m sweeping width) hour 0.976 0.976 0.976 951.000 928.357 928.357 928.357 P&M-23001
Air compressor 250 cfm hour 0.976 0.976 0.976 550.000 536.905 536.905 536.905 P&M-15001
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.007 8638.000 25971.587 P&M-29001
(ii) Paver (240HP) hour 3.758 8638.000 32464.483 P&M-29001
(iii) Paver (174HP) hour 5.011 6848.000 34316.089 P&M-29002
Electric generator
(i) 500 KVA hour 3.007 6985.000 21001.567 P&M-22002
(ii) 400 KVA hour 3.758 5635.000 21178.208 P&M-22003
(iii) 250 KVA hour 5.011 3970.000 19894.111 P&M-22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.125 3907.000 20025.260 P&M-5001
(ii) 2.1 Cum Capacity hour 7.577 2393.000 18131.282 P&M-5002
(iii) 1 Cum Capacity hour 15.842 1633.000 25870.639 P&M-5003
Tipper
For Transportation
(i) 18 cum capacity t.km 451 x L1 6.830 6160.660 P&M-72002
(ii) 14 cum capacity t.km 451 x L1 7.770 7008.540 P&M-73002
(iii) 10 cum capacity t.km 451 x L1 9.620 8677.240 P&M-74002
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.013 2621.000 15760.947 P&M-6001
(ii) 14 cum capacity hour 7.517 2331.000 17521.350 P&M-6002
(iii) 10 cum capacity hour 10.022 2077.000 20816.156 P&M-6003
Smooth steel wheeled tandem roller for static and hour 10.159 10.159 10.159 1864.000 18935.873 18935.873 18935.873 P&M-8001
vibratory passaes
c) Material
i) Bitumen@ 3.4 per cent of mix tonne 15.334 15.334 15.334 34512.450 529213.908 529213.908 529213.908 M-074
weight of mix = 205 x 2.2 = 451 tonne
ii) Aggregate
Total weight of mix = 451.00 tonnes
Weight of bitumen = 15.33 tonnes
Weight of aggregate = 435.67 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading II(19 mm nominal size)
25 - 10 mm 40 per cent cum 116.178 116.178 116.178 906.193 105279.369 105279.369 105279.369 M-045
10 - 5 mm 40 per cent cum 116.178 116.178 116.178 564.724 65608.263 65608.263 65608.263 M-039
5 mm and below 20 per cent cum 58.089 58.089 58.089 285.550 16587.253 16587.253 16587.253 M-029
* Any one of the alternative may be adopted as per approved
design
(ii) for Grading II(19 mm nominal size)
d) Overhead charges @ 8% on @ 10% on @ 12% on 69806.902 87502.641 106941.832
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 94239.318 96252.905 99812.376
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 1036632.501 1058781.960 1097936.139
Rate per cum = (a+b+c+d+e)/205 5056.744 5164.790 5355.786
Say, 5056.74 5164.79 5355.79
Note *1.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
Unit = cum
Taking output = 195 cum 450.45 tonnes
a) Labour
Mate day 0.440 0.440 0.440 622.000 273.680 273.680 273.680 L-12
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
Mazdoor skilled day 5.000 5.000 5.000 592.000 2960.000 2960.000 2960.000 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.003 13298.000 39933.894 P&M-18001
(ii) HMP 160 TPH hour 3.754 9323.000 34996.211 P&M-18002
(iii) HMP 120 TPH hour 5.005 7568.000 37877.840 P&M-18003
Mechanical broom (2.1m sweeping width) hour 0.663 0.663 0.663 951.000 630.765 630.765 630.765 P&M-23001
Air compressor 250 cfm hour 0.663 0.663 0.663 550.000 364.796 364.796 364.796 P&M-15001
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.003 8638.000 25939.914 P&M-29001
(ii) Paver (240HP) hour 3.754 8638.000 32424.893 P&M-29001
(iii) Paver (174HP) hour 5.005 6848.000 34274.240 P&M-29002
Electric generator
(i) 500 KVA hour 3.003 6985.000 20975.955 P&M-22002
(ii) 400 KVA hour 3.754 5635.000 21152.381 P&M-22003
(iii) 250 KVA hour 5.005 3970.000 19869.850 P&M-22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.138 3907.000 20075.376 P&M-5001
(ii) 2.1 Cum Capacity hour 7.596 2393.000 18176.659 P&M-5002
(iii) 1 Cum Capacity hour 15.882 1633.000 25935.384 P&M-5003
Tipper
For Transportation
(i) 18 cum capacity t.km 450.45 x L1 6.830 6153.147 P&M-72002
(ii) 14 cum capacity t.km 450.45 x L1 7.770 6999.993 P&M-73002
(iii) 10 cum capacity t.km 450.45 x L1 9.620 8666.658 P&M-74002
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.006 2621.000 15741.726 P&M-6001
(ii) 14 cum capacity hour 7.508 2331.000 17499.983 P&M-6002
(iii) 10 cum capacity hour 10.010 2077.000 20790.770 P&M-6003
Smooth steel wheeled tandem roller for static and hour 9.663 9.663 9.663 1864.000 18012.172 18012.172 18012.172 P&M-8001
vibratory passaes
c) Material
i) Bitumen@ 4 per cent of mix tonne 18.018 18.018 18.018 34512.450 621845.324 621845.324 621845.324 M-074
weight of mix = 205 x 2.2 = 451 tonne
ii) Aggregate
Total weight of mix = 450.45 tonnes
Weight of bitumen = 18.02 tonnes
Weight of aggregate = 432.43 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.423 63.423 63.423 933.285 59192.102 59192.102 59192.102 M-048
25 - 10 mm 13 per cent cum 37.477 37.477 37.477 906.193 33961.807 33961.807 33961.807 M-045
10 -4.75 mm 19 per cent cum 54.775 54.775 54.775 564.724 30932.591 30932.591 30932.591 M-039
4.75 mm and below 44 per cent cum 126.847 126.847 126.847 285.550 36221.072 36221.072 36221.072 M-029
Filler @ 2 per cent of weight of aggregates. tonne 8.649 8.649 8.649 6500.000 56216.160 56216.160 56216.160 M-081
* Any one of the alternative may be adopted as per approved
design
Grading - I40 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on 79423.238 99522.059 121366.225
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 107221.372 109474.265 113275.144
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 195 cum = a+b+c+d+e 1179435.091 1204216.912 1246026.580
Rate per cum = (a+b+c+d+e)/195 6048.385 6175.471 6389.880
Say, 6048.39 6175.47 6389.88
Note *1.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
Unit = cum
Taking output = 195 cum 450.45 tonnes
a) Labour
Mate day 0.440 0.440 0.440 622.000 273.680 273.680 273.680 L-12
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
Mazdoor skilled day 5.000 5.000 5.000 592.000 2960.000 2960.000 2960.000 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.003 13298.000 39933.894 P&M-18001
(ii) HMP 160 TPH hour 3.754 9323.000 34996.211 P&M-18002
(iii) HMP 120 TPH hour 5.005 7568.000 37877.840 P&M-18003
Mechanical broom (2.1m sweeping width) hour 0.663 0.663 0.663 951.000 630.765 630.765 630.765 P&M-23001
Air compressor 250 cfm hour 0.663 0.663 0.663 550.000 364.796 364.796 364.796 P&M-15001
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.003 8638.000 25939.914 P&M-29001
(ii) Paver (240HP) hour 3.754 8638.000 32424.893 P&M-29001
(iii) Paver (174HP) hour 5.005 6848.000 34274.240 P&M-29002
Electric generator
(i) 500 KVA hour 3.003 6985.000 20975.955 P&M-22002
(ii) 400 KVA hour 3.754 5635.000 21152.381 P&M-22003
(iii) 250 KVA hour 5.005 3970.000 19869.850 P&M-22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.112 3907.000 19970.817 P&M-5001
(ii) 2.1 Cum Capacity hour 7.556 2393.000 18081.989 P&M-5002
(iii) 1 Cum Capacity hour 15.799 1633.000 25800.304 P&M-5003
Tipper
For Transportation
(i) 18 cum capacity t.km 450.45 x L1 6.830 6153.147 P&M-72002
(ii) 14 cum capacity t.km 450.45 x L1 7.770 6999.993 P&M-73002
(iii) 10 cum capacity t.km 450.45 x L1 9.620 8666.658 P&M-74002
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.006 2621.000 15741.726 P&M-6001
(ii) 14 cum capacity hour 7.508 2331.000 17499.983 P&M-6002
(iii) 10 cum capacity hour 10.010 2077.000 20790.770 P&M-6003
Smooth steel wheeled tandem roller for static and hour 9.663 9.663 9.663 1864.000 18012.172 18012.172 18012.172 P&M-8001
vibratory passaes
c) Material
i) Bitumen@ 4.5 per cent of mix tonne 20.270 20.270 20.270 34512.450 699575.990 699575.990 699575.990 M-074
ii) Aggregate
Total weight of mix = 450.45 tonnes
Weight of bitumen = 20.27 tonnes
Weight of aggregate = 430.18 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.036 86.036 86.036 906.193 77965.206 77965.206 77965.206 M-045
10 - 5 mm 28 per cent cum 80.300 80.300 80.300 564.724 45347.450 45347.450 45347.450 M-039
5 mm and below 40 per cent cum 114.715 114.715 114.715 285.550 32756.746 32756.746 32756.746 M-029
Filler @ 2 per cent of weight of aggregates. cum 8.604 8.604 8.604 6500.000 55923.368 55923.368 55923.368 M-081
* Any one of the alternative may be adopted as per approved
design
Grading - II19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on 85270.850 106832.562 130133.980
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 115115.647 117515.818 121458.381
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 195 cum = a+b+c+d+e 1266272.122 1292674.002 1336042.196
Rate per cum = (a+b+c+d+e)/195 6493.703 6629.097 6851.498
Say, 6493.70 6629.10 6851.50
Note *1.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
Unit = cum
Taking output = 191 cum 450.76 tonnes
a) Labour
Mate day 0.440 0.440 0.440 622.000 273.680 273.680 273.680 L-12
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
Mazdoor skilled day 5.000 5.000 5.000 592.000 2960.000 2960.000 2960.000 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 13298.000 39961.377 P&M-18001
(ii) HMP 160 TPH hour 3.756 9323.000 35020.296 P&M-18002
(iii) HMP 120 TPH hour 5.008 7568.000 37903.908 P&M-18003
Mechanical broom (2.1m sweeping width) hour 1.137 1.137 1.137 951.000 1081.196 1081.196 1081.196 P&M-23001
Air compressor 250 cfm hour 1.137 1.137 1.137 550.000 625.298 625.298 625.298 P&M-15001
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.005 8638.000 25957.766 P&M-29001
(ii) Paver (240HP) hour 3.756 8638.000 32447.207 P&M-29001
(iii) Paver (174HP) hour 5.008 6848.000 34297.828 P&M-29002
Electric generator
(i) 500 KVA hour 3.005 6985.000 20990.391 P&M-22002
(ii) 400 KVA hour 3.756 5635.000 21166.938 P&M-22003
(iii) 250 KVA hour 5.008 3970.000 19883.524 P&M-22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.078 3907.000 19838.077 P&M-5001
(ii) 2.1 Cum Capacity hour 7.506 2393.000 17961.803 P&M-5002
(iii) 1 Cum Capacity hour 15.694 1633.000 25628.818 P&M-5003
Tipper
For Transportation
(i) 18 cum capacity t.km 450.76 x L1 6.830 6157.382 P&M-72002
(ii) 14 cum capacity t.km 450.76 x L1 7.770 7004.810 P&M-73002
(iii) 10 cum capacity t.km 450.76 x L1 9.620 8672.622 P&M-74002
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.010 2621.000 15752.559 P&M-6001
(ii) 14 cum capacity hour 7.513 2331.000 17512.026 P&M-6002
(iii) 10 cum capacity hour 10.017 2077.000 20805.078 P&M-6003
Smooth steel wheeled tandem roller for static and hour 11.831 11.831 11.831 1864.000 22053.364 22053.364 22053.364 P&M-8001
vibratory passaes
Pnumetic Tyre roller hour 2.404 3.005 4.007 2333.000 5608.656 7010.821 9347.761 P&M-10001
c) Material
i) Bitumen@ 5.2 per cent of mix tonne 23.440 23.440 23.440 34512.450 808955.262 808955.262 808955.262 M-074
ii) Aggregate
Total weight of mix = 450.76 tonnes
Weight of bitumen = 23.44 tonnes
Weight of aggregate = 427.32 tonnes
Taking density of aggregate = 1.5 ton/cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.708 99.708 99.708 906.193 90354.828 90354.828 90354.828 M-045
10 - 5 mm 23 per cent cum 65.522 65.522 65.522 564.724 37002.104 37002.104 37002.104 M-039
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Amount
Quantity
(Rs.)
Reference to Rate Remarks/ Input
Sr No Description Unit For Large For Medium For Small Medium
MORT&H Specification (Rs.) Large Project Small Project ref.
Project Project Project Project
5 mm and below 40 per cent cum 113.952 113.952 113.952 285.550 32539.022 32539.022 32539.022 M-029
Filler @ 2 per cent of weight of aggregates. cum 8.546 8.546 8.546 6500.000 55551.662 55551.662 55551.662 M-081
* Any one of the alternative may be adopted as per approved
design
* Grading - I-19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on 95121.810 119288.032 145355.515
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 128414.443 131216.835 135665.147
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 191 cum = a+b+c+d+e 1412558.878 1443111.506 1492042.938
Rate per cum = (a+b+c+d+e)/191 7395.596 7555.558 7811.743
Say, 7395.60 7555.56 7811.74
Note *1.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
Unit = cum
Taking output = 191 cum 450.76 tonnes
a) Labour
Mate day 0.440 0.440 0.440 622.000 273.680 273.680 273.680 L-12
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
Mazdoor skilled day 5.000 5.000 5.000 592.000 2960.000 2960.000 2960.000 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 13298.000 39961.377 P&M-18001
(ii) HMP 160 TPH hour 3.756 9323.000 35020.296 P&M-18002
(iii) HMP 120 TPH hour 5.008 7568.000 37903.908 P&M-18003
Mechanical broom (2.1m sweeping width) hour 1.624 1.624 1.624 951.000 1544.566 1544.566 1544.566 P&M-23001
Air compressor 250 cfm hour 1.624 1.624 1.624 550.000 893.282 893.282 893.282 P&M-15001
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.005 8638.000 25957.766 P&M-29001
(ii) Paver (240HP) hour 3.756 8638.000 32447.207 P&M-29001
(iii) Paver (174HP) hour 5.008 6848.000 34297.828 P&M-29002
Electric generator
(i) 500 KVA hour 3.005 6985.000 20990.391 P&M-22002
(ii) 400 KVA hour 3.756 5635.000 21166.938 P&M-22003
(iii) 250 KVA hour 5.008 3970.000 19883.524 P&M-22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.004 3907.000 19550.568 P&M-5001
(ii) 2.1 Cum Capacity hour 7.378 2393.000 17654.764 P&M-5002
(iii) 1 Cum Capacity hour 15.553 1633.000 25397.927 P&M-5003
Tipper
For Transportation
(i) 18 cum capacity t.km 450.76 x L1 6.830 6157.382 P&M-72002
(ii) 14 cum capacity t.km 450.76 x L1 7.770 7004.810 P&M-73002
(iii) 10 cum capacity t.km 450.76 x L1 9.620 8672.622 P&M-74002
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.010 2621.000 15752.559 P&M-6001
(ii) 14 cum capacity hour 7.513 2331.000 17512.026 P&M-6002
(iii) 10 cum capacity hour 10.017 2077.000 20805.078 P&M-6003
Smooth steel wheeled tandem roller for static and hour 1864.000 31504.806 31504.806 31504.806 P&M-8001
vibratory passaes 16.902 16.902 16.902
Pneumatic Tyre roller hour 2.404 3.005 4.007 2333.000 5608.656 7010.821 9347.761 P&M-10001
c) Material
i) Bitumen@ 5.4 per cent of mix tonne 24.341 24.341 24.341 34512.450 840068.926 840068.926 840068.926 M-074
ii) Aggregate
Total weight of mix = 450.76 tonnes
Weight of bitumen = 24.34 tonnes
Weight of aggregate = 426.42 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm 30 per cent cum 99.708 99.708 99.708 843.898 84143.455 84143.455 84143.455 M-043
10 - 5 mm 25 per cent cum 65.522 65.522 65.522 564.724 37002.104 37002.104 37002.104 M-039
5 mm and below 43 per cent cum 113.952 113.952 113.952 285.550 32539.022 32539.022 32539.022 M-029
Filler @ 2 per cent of weight of aggregates. cum 8.546 8.546 8.546 6500.000 55551.662 55551.662 55551.662 M-081
* Any one of the alternative may be adopted as per approved
design
* Grading - I-19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on 97905.616 122765.837 149538.018
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 132172.582 135042.420 139568.817
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 191 cum = a+b+c+d+e 1453898.402 1485466.624 1535256.988
Rate per cum = (a+b+c+d+e)/191 7612.034 7777.312 8037.995
Say, 7612.03 7777.31 8037.99
Note *1.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
Unit = sqm
Taking output = 9000 sqm
5.6 Case -I :-19 mm nominal chipping size
a) Labour
Mate day 0.440 0.440 0.440 622.000 273.680 273.680 273.680 L-12
Mazdoor day 9.000 9.000 9.000 560.000 5040.000 5040.000 5040.000 L-13
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.679 2.679 2.679 951.000 2547.321 2547.321 2547.321 P&M-23001
Air compressor 250 cfm hour 2.679 2.679 2.679 550.000 1473.214 1473.214 1473.214 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.250 1.250 1.250 1550.000 1937.500 1937.500 1937.500 P&M-24001
Hydraulic self propelled chip spreader hour 7.401 7.401 7.401 1989.000 14721.217 14721.217 14721.217 P&M-32001
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 0.823 3907.000 3216.128 P&M-5001
(ii) 2.1 Cum Capacity hour 1.216 2393.000 2910.405 P&M-5002
(iii) 1 Cum Capacity hour 2.547 1633.000 4159.528 P&M-5003
Tipper
For Transportation
(i) 18 cum capacity t.km 202.5 x L1 6.830 2766.150 P&M-72002
(ii) 14 cum capacity t.km 202.5 x L1 7.770 3146.850 P&M-73002
(iii) 10 cum capacity t.km 202.5 x L1 9.620 3896.100 P&M-74002
For loading & unloading time
(i) 18 cum capacity hour 8.224 2621.000 21556.379 P&M-6001
(ii) 14 cum capacity hour 8.618 2331.000 20087.467 P&M-6002
(iii) 10 cum capacity hour 9.948 2077.000 20663.005 P&M-6003
Smooth steel wheeled tandem roller for static and hour 5.973 5.973 5.973 1864.000 11133.897 11133.897 11133.897 P&M-8001
vibratory passaes
Pnumetic Tyre roller hour 5.973 5.973 5.973 2333.000 13935.291 13935.291 13935.291 P&M-10001
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 10.800 10.800 34512.450 372734.460 372734.460 372734.460 M-074
Crushed stone chipping,19 mm nominal size @ 0.015 cum 135.000 135.000 135.000 985.349 133022.104 133022.104 133022.104 M-052
cum per sqm
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Amount
Quantity
(Rs.)
Reference to Rate Remarks/ Input
Sr No Description Unit For Large For Medium For Small Medium
MORT&H Specification (Rs.) Large Project Small Project ref.
Project Project Project Project
Hydraulic self propelled chip spreader hour 7.401 7.401 7.401 1989.000 14721.217 14721.217 14721.217 P&M-32001
Front end loader for loading
(i) 3.1 Cum Capacity hour 0.544 3907.000 2126.794 P&M-5001
(ii) 2.1 Cum Capacity hour 0.804 2393.000 1922.946 P&M-5002
(iii) 1 Cum Capacity hour 1.688 1633.000 2755.688 P&M-5003
Tipper
For Transportation
(i) 18 cum capacity t.km 135 x L1 6.830 1844.100 P&M-72002
(ii) 14 cum capacity t.km 135 x L1 7.770 2097.900 P&M-73002
(iii) 10 cum capacity t.km 135 x L1 9.620 2597.400 P&M-74002
For loading & unloading time
(i) 18 cum capacity hour 7.946 2621.000 20825.603 P&M-6001
(ii) 14 cum capacity hour 8.205 2331.000 19125.592 P&M-6002
(iii) 10 cum capacity hour 9.089 2077.000 18877.470 P&M-6003
Smooth steel wheeled tandem roller for static and hour 3.982 3.982 3.982 1864.000 7422.598 7422.598 7422.598 P&M-8001
vibratory passaes
Pnumetic Tyre roller hour 3.982 3.982 3.982 2333.000 9290.194 9290.194 9290.194 P&M-10001
c) Material
Bitumen@ 1.20 kg per sqm tonne 9.000 9.000 9.000 34512.450 310612.050 310612.050 310612.050 M-074
Crushed stone chipping,13 mm nominal size @ 0.015 cum 90.000 90.000 90.000 860.758 77468.201 77468.201 77468.201 M-051
cum per sqm
d) Overhead charges @ 8% on @ 10% on @ 12% on 36541.318 45511.641 54744.064
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 49330.779 50062.806 51094.460
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 9000 sqm = a+b+c+d+e 542638.570 550690.862 562039.058
Rate per sqm = (a+b+c+d+e)/9000 60.293 61.188 62.449
Say, 60.29 61.19 62.45
Note 1.Where the proposed aggregate fails to pass the stripping
test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the same
as per the Ist coat mentioned above
5.7 510 Open - Graded Premix Surfacing
Providing, laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2 mm to 5.6
mm aggregates using Viscocity grade bitumen to required
line, grade and level to serve as wearing course on a
previously prepared base, including mixing in a suitable hot
mix plant of appropriate capacity not less than 200
tonnes/hour, laying and rolling with a smooth wheeled roller,
finished to required level and grades.
* Bitumen@ 22 kg per 10 sqm tonne 22.550 22.550 22.550 34512.450 778255.748 778255.748 778255.748 M-074
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum cum 276.750 276.750 276.750 564.724 156287.328 156287.328 156287.328 M-040
per 10 sqm
or
Type - B
Bitumen @ 19 kg per 10 sqm tonne 19.475 19.475 19.475 34512.450 672129.964 672129.964 672129.964 M-074
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum 276.750 276.750 276.750 564.724 156287.328 156287.328 156287.328 M-041
cum per 10 sqm
* Any one of the alternative may be adopted as per approved
design
Type - A
d) Overhead charges @ 8% on @ 10% on @ 12% on 88494.363 111565.545 135883.572
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 119467.390 122722.099 126824.667
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10250 Sqm = a+b+c+d+e 1314141.293 1349943.091 1395071.340
Rate per Sqm = (a+b+c+d+e)/10250 128.209 131.702 136.105
Say, 128.21 131.70 136.10
Type - B
d) Overhead charges @ 8% on @ 10% on @ 12% on 80004.300 100952.966 123148.478
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 108005.806 111048.263 114938.580
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10250 Sqm = a+b+c+d+e 1188063.862 1221530.893 1264324.375
Rate per Sqm = (a+b+c+d+e)/10250 115.909 119.174 123.349
Say, 115.91 119.17 123.35
5.9 511 Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A and B seal coats
(i) Case - I : Type A
Unit = sqm
Taking output = 10250 sqm 92.25 cum
a) Labour
Mate day 0.240 0.240 0.240 622.000 149.280 149.280 149.280 L-12
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.051 3.051 3.051 951.000 2901.116 2901.116 2901.116 P&M-23001
Air compressor 250 cfm hour 3.051 3.051 3.051 550.000 1677.827 1677.827 1677.827 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 2.847 2.847 2.847 1550.000 4413.194 4413.194 4413.194 P&M-24001
Hydraulic self propelled chip spreader hour 8.429 8.429 8.429 1989.000 16765.831 16765.831 16765.831 P&M-32001
Front end loader
(i) 3.1 Cum Capacity hour 0.563 3907.000 2197.688 P&M-5001
(ii) 2.1 Cum Capacity hour 0.831 2393.000 1988.777 P&M-5002
(iii) 1 Cum Capacity hour 1.741 1633.000 2842.344 P&M-5003
Tipper
For loading time
(i) 18 cum capacity hour 0.563 2621.000 1474.313 P&M-6001
(ii) 14 cum capacity hour 0.831 2331.000 1937.250 P&M-6002
(iii) 10 cum capacity hour 1.741 2077.000 3615.156 P&M-6003
For Transportation
(i) 18 cum capacity t.km 202.95 x L1 6.830 2772.297 P&M-72002
(ii) 14 cum capacity t.km 202.95 x L1 7.770 3153.843 P&M-73002
(iii) 10 cum capacity t.km 202.95 x L1 9.620 3904.758 P&M-74002
For unloading time
(i) 18 cum capacity hour 8.429 2621.000 22093.133 P&M-6001
(ii) 14 cum capacity hour 8.429 2331.000 19648.643 P&M-6002
(iii) 10 cum capacity hour 8.429 2077.000 17507.607 P&M-6003
Smooth steel wheeled tandem roller for static and hour 4.082 4.082 4.082 1864.000 7608.163 7608.163 7608.163 P&M-8001
vibratory passaes
c) Material
Bitumen@ 9.80 kg per 10 sqm tonne 10.045 10.045 10.045 34512.450 346677.560 346677.560 346677.560 M-074
Crushed stone chipping of 6.7 mm size defined as 100 cum 92.250 92.250 92.250 860.758 79404.906 79404.906 79404.906 M-049
per cent passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.09 cum per 10 sqm
Unit = sqm
Taking output = 35 sqm 2.0125 tonnes
a) Labour
Mate day 0.440 0.440 0.440 622.000 273.680 273.680 273.680 L-12
Mazdoor day 10.000 10.000 10.000 560.000 5600.000 5600.000 5600.000 L-13
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Amount
Quantity
(Rs.)
Reference to Rate Remarks/ Input
Sr No Description Unit For Large For Medium For Small Medium
MORT&H Specification (Rs.) Large Project Small Project ref.
Project Project Project Project
Mazdoor skilled day 1.000 1.000 1.000 592.000 592.000 592.000 592.000 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 0.010 0.010 0.010 951.000 9.906 9.906 9.906 P&M-23001
Air compressor 250 cfm hour 0.010 0.010 0.010 550.000 5.729 5.729 5.729 P&M-15001
Mastic cooker 1 tonne capacity hour 3.000 3.000 3.000 600.000 1800.000 1800.000 1800.000 P&M-27001
Bitumen boiler 1500 litres capacity hour 3.000 3.000 3.000 664.000 1992.000 1992.000 1992.000 P&M-26001
Tractor for towing and positioning of mastic cooker and hour 1.000 1.000 1.000 820.000 820.000 820.000 820.000 P&M-12001
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
iii) Lime stone dust filler with calcium content not less tonne 0.361 0.361 0.361 6500.000 2344.160 2344.160 2344.160 M-190
than 80 per cent by weight @ 17.92 per cent by weight
of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cent cum 0.553 0.553 0.553 860.758 475.900 475.900 475.900 M-042
by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 =
0.55
v) Pre-coated stone chips of 13.2 mm nominal size for cum 0.018 0.018 0.018 2250.000 39.375 39.375 39.375 M-141
skid resistance = 35 x 0.005/10 = 0.018
vi) Bitumen for coating of chips @ 2 per cent by weight = kg 0.510 0.510 0.510 34512.450 17587.545 17587.545 17587.545 M-074
0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg
(i) 5 mm thickness
Unit = sqm
Taking output = 16000 sqm 80 cum 176.000
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 0.240 0.240 622.000 149.280 149.280 149.280 L-12
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 4.762 4.762 4.762 951.000 4528.571 4528.571 4528.571 P&M-23001
Air compressor 250 cfm hour 4.762 4.762 4.762 550.000 2619.048 2619.048 2619.048 P&M-15001
Mobile slurry seal equipment hour 4.386 4.386 4.386 3674.000 16114.035 16114.035 16114.035 P&M-41001
Front end loader
(i) 3.1 Cum Capacity hour 0.488 3907.000 1905.854 P&M-5001
(ii) 2.1 Cum Capacity hour 0.721 2393.000 1724.685 P&M-5002
(iii) 1 Cum Capacity hour 1.509 1633.000 2464.906 P&M-5003
Tipper
Tipper for loading time
(i) 18 cum capacity hour 0.488 2621.000 1278.537 P&M-6001
(ii) 14 cum capacity hour 0.721 2331.000 1680.000 P&M-6002
(iii) 10 cum capacity hour 1.509 2077.000 3135.094 P&M-6003
For Transportation
(i) 18 cum capacity t.km 176 x L1 6.830 2404.160 P&M-72002
(ii) 14 cum capacity t.km 176 x L1 7.770 2735.040 P&M-73002
(iii) 10 cum capacity t.km 176 x L1 9.620 3386.240 P&M-74002
Tipper for unloading time
(i) 18 cum capacity hour 4.386 2621.000 11495.614 P&M-6001
(ii) 14 cum capacity hour 4.386 2331.000 10223.684 P&M-6002
(iii) 10 cum capacity hour 4.386 2077.000 9109.649 P&M-6003
Water tanker (speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 3 km/hr )
(i) 16 KL capacity hour 2.300 1357.000 3121.100 P&M-11001
(ii) 12 KL capacity hour 3.067 1187.000 3640.133 P&M-11002
(iii) 6 KL capacity hour 6.133 904.000 5544.533 P&M-11003
Pneumatic tyred roller with individual wheel load not hour 3.509 3.509 3.509 2333.000 8185.965 8185.965 8185.965 P&M-10001
exceeding 1.5 tonnes
c) Material
Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11 tonne 19.360 19.360 19.360 35012.450 677841.032 677841.032 677841.032 M-077
Fine aggregate 4.75 mm and below 87 per cent of total cum 102.080 102.080 102.080 302.410 30870.006 30870.006 30870.006 M-029
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5, =
153.12/1.5 = 102.08 cum
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02 tonne 3.520 3.520 3.520 6500.000 22880.000 22880.000 22880.000 M-190
Cost of water KL 12.000 12.000 12.000 74.540 894.480 894.480 894.480 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 63011.814 78744.596 94929.941
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 85065.950 86619.055 88601.278
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 16000 Sqm = a+b+c+d+e 935725.445 952809.610 974614.058
Rate per Sqm = (a+b+c+d+e)/16000 58.483 59.551 60.913
Say, 58.48 59.55 60.91
5.12 (ii) 3 mm thickness
Unit = sqm 132.000 tonne
Taking output = 20000 sqm 60 cum
a) Labour
Mate day 0.200 0.200 0.200 622.000 124.400 124.400 124.400 L-12
Mazdoor day 5.000 5.000 5.000 560.000 2800.000 2800.000 2800.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 5.952 5.952 5.952 951.000 5660.714 5660.714 5660.714 P&M-23001
Air compressor 250 cfm hour 5.952 5.952 5.952 550.000 3273.810 3273.810 3273.810 P&M-15001
Mobile slurry seal equipment hour 5.482 5.482 5.482 3674.000 20142.544 20142.544 20142.544 P&M-41001
Front end loader
(i) 3.1 Cum Capacity hour 0.366 3907.000 1429.390 P&M-5001
(ii) 2.1 Cum Capacity hour 0.541 2393.000 1293.514 P&M-5002
(iii) 1 Cum Capacity hour 1.132 1633.000 1848.679 P&M-5003
Tipper
Tipper for loading time
(i) 18 cum capacity hour 0.366 2621.000 958.902 P&M-6001
(ii) 14 cum capacity hour 0.541 2331.000 1260.000 P&M-6002
(iii) 10 cum capacity hour 1.132 2077.000 2351.321 P&M-6003
For Transportation
(i) 18 cum capacity t.km 132 x L1 6.830 1803.120 P&M-72002
(ii) 14 cum capacity t.km 132 x L1 7.770 2051.280 P&M-73002
(iii) 10 cum capacity t.km 132 x L1 9.620 2539.680 P&M-74002
Tipper for unloading time
(i) 18 cum capacity hour 5.482 2621.000 14369.518 P&M-6001
(ii) 14 cum capacity hour 5.482 2331.000 12779.605 P&M-6002
(iii) 10 cum capacity hour 5.482 2077.000 11387.061 P&M-6003
Water tanker (speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 3 km/hr )
(i) 16 KL capacity hour 2.833 1357.000 3844.833 P&M-11001
(ii) 12 KL capacity hour 3.778 1187.000 4484.222 P&M-11002
(iii) 6 KL capacity hour 7.556 904.000 6830.222 P&M-11003
Pneumatic tyred roller with individual wheel load not hour 4.386 4.386 4.386 2333.000 10232.456 10232.456 10232.456 P&M-10001
exceeding 1.5 tonnes
c) Material
Residual Binder @ 13 per cent of mix = 60 x 2.2 x 0.13 tonne 17.160 17.160 17.160 35012.450 600813.642 600813.642 600813.642 M-077
Fine aggregate 3 mm and below 85 per cent of total cum 74.800 74.800 74.800 302.410 22620.263 22620.263 22620.263 M-029
mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 per cent of total mix = 60x 2.2 x 0.02 tonne 2.640 2.640 2.640 6500.000 17160.000 17160.000 17160.000 M-190
Cost of water KL 12.000 12.000 12.000 74.540 894.480 894.480 894.480 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 56490.246 70559.093 85041.513
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 76261.832 77615.002 79372.078
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 20000 Sqm = a+b+c+d+e 838880.150 853765.025 873092.863
Rate per Sqm = (a+b+c+d+e)/20000 41.944 42.688 43.655
Say, 41.94 42.69 43.65
5.12 (iii) 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm 36 cum 79.200
a) Labour
Mate day 0.200 0.200 0.200 622.000 124.400 124.400 124.400 L-12
Mazdoor day 5.000 5.000 5.000 560.000 2800.000 2800.000 2800.000 L-13
b) Machinery
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Amount
Quantity
(Rs.)
Reference to Rate Remarks/ Input
Sr No Description Unit For Large For Medium For Small Medium
MORT&H Specification (Rs.) Large Project Small Project ref.
Project Project Project Project
Mechanical broom (2.1m sweeping width) hour 7.143 7.143 7.143 951.000 6792.857 6792.857 6792.857 P&M-23001
Air compressor 250 cfm hour 7.143 7.143 7.143 550.000 3928.571 3928.571 3928.571 P&M-15001
Mobile slurry seal equipment hour 6.579 6.579 6.579 3674.000 24171.053 24171.053 24171.053 P&M-41001
Front end loader
(i) 3.1 Cum Capacity hour 0.220 3907.000 857.634 P&M-5001
(ii) 2.1 Cum Capacity hour 0.324 2393.000 776.108 P&M-5002
(iii) 1 Cum Capacity hour 0.679 1633.000 1109.208 P&M-5003
Tipper
Tipper for loading time
(i) 18 cum capacity hour 0.220 2621.000 575.341 P&M-6001
(ii) 14 cum capacity hour 0.324 2331.000 756.000 P&M-6002
(iii) 10 cum capacity hour 0.679 2077.000 1410.792 P&M-6003
For Transportation
(i) 18 cum capacity t.km 79.2 x L1 6.830 1081.872 P&M-72002
(ii) 14 cum capacity t.km 79.2 x L1 7.770 1230.768 P&M-73002
(iii) 10 cum capacity t.km 79.2 x L1 9.620 1523.808 P&M-74002
Tipper for unloading time
(i) 18 cum capacity hour 6.579 2621.000 17243.421 P&M-6001
(ii) 14 cum capacity hour 6.579 2331.000 15335.526 P&M-6002
(iii) 10 cum capacity hour 6.579 2077.000 13664.474 P&M-6003
Water tanker (speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 3 km/hr )
(i) 16 KL capacity hour 3.367 1357.000 4568.567 P&M-11001
(ii) 12 KL capacity hour 4.489 1187.000 5328.311 P&M-11002
(iii) 6 KL capacity hour 8.978 904.000 8115.911 P&M-11003
Pneumatic tyred roller with individual wheel load not hour 5.263 5.263 5.263 2333.000 12278.947 12278.947 12278.947 P&M-10001
exceeding 1.5 tonnes
c) Material
Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16 tonne 12.670 12.670 12.670 35012.450 443607.742 443607.742 443607.742 M-077
Fine aggregate 2.36 mm and below,82 per cent of total cum 43.300 43.300 43.300 302.410 13094.350 13094.350 13094.350 M-029
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5
Filler @ 2 per cent of total mix = 36x 2.2 x 0.02 tonne 1.580 1.580 1.580 6500.000 10270.000 10270.000 10270.000 M-190
Cost of water KL 12.000 12.000 12.000 74.540 894.480 894.480 894.480 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 43383.139 54138.911 65254.391
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 58567.237 59552.802 60904.098
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 24000 Sqm = a+b+c+d+e 644239.612 655080.827 669945.082
Rate per Sqm = (a+b+c+d+e)/24000 26.843 27.295 27.914
Say, 26.84 27.30 27.91
Note 1.Tack coat, if required to be provided, before laying slurry
seal may be measured and paid separately
5.13 519 Recycling of Bituminous Pavement with Central Recycling
Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stock piling the reclaimed
material near the central recycling plant after carrying out
necessary checks and evaluation, adding fresh material
including rejuvenators as required, mixing in a hot mix plant,
transporting and laying at site and compacting to the
required grade, level and thickness, all as specified in clause
519.
Unit = cum
Taking output = 120 Cum 276 tonnes
a) Labour
Mate day 0.280 0.280 0.280 622.000 174.160 174.160 174.160 L-12
Mazdoor day 4.000 4.000 4.000 560.000 2240.000 2240.000 2240.000 L-13
Mazdoor skilled day 3.000 3.000 3.000 592.000 1776.000 1776.000 1776.000 L-15
b) Machinery
Cold milling machine @ 80 cum per hour hour 1.500 1.500 1.500 28922.000 43383.000 43383.000 43383.000 P&M-48001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1550.000 1033.333 1033.333 1033.333 P&M-24001
0.667 0.667 0.667
Unit = sqm
Taking output = 10500 Sqm
(i) a) Labour
Mate day 0.120 0.120 0.120 622.000 74.640 74.640 74.640 L-12
Mazdoor day 3.000 3.000 3.000 560.000 1680.000 1680.000 1680.000 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 3.125 3.125 3.125 951.000 2971.875 2971.875 2971.875 P&M-23001
Air compressor 250 cfm hour 3.125 3.125 3.125 550.000 1718.750 1718.750 1718.750 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) tonne 1550.000 4520.833 4520.833 4520.833 P&M-24001
2.917 2.917 2.917
c) Material
Bitumen emulsion @ 0.75 kg per sqm tonne 7.880 7.880 7.880 35012.450 275898.106 275898.106 275898.106 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on 22949.136 28686.420 34423.705
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 30981.334 31555.062 32128.791
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 340794.675 347105.687 353416.700
Rate per Sqm = (a+b+c+d+e)/10500 32.457 33.058 33.659
Say, 32.46 33.06 33.66
(ii) 1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160 0.160 0.160 622.000 99.520 99.520 99.520 L-12
Mazdoor for precoating of grit day 4.000 4.000 4.000 560.000 2240.000 2240.000 2240.000 L-13
b) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 26.250 26.250 302.410 7938.261 7938.261 7938.261 M-023
Bitumen emulsion for precoating grit @ 2 per cent of tonne 0.790 0.790 0.790 35012.450 27659.836 27659.836 27659.836 M-077
grit,39.38 x 0.02
37937.616 37937.616 37937.616
3.613 3.613 3.613
Say, 3.61 3.61 3.61
5.15 518 Bituminous Cold Mix ( Including Gravel Emulsion)
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Amount
Quantity
(Rs.)
Reference to Rate Remarks/ Input
Sr No Description Unit For Large For Medium For Small Medium
MORT&H Specification (Rs.) Large Project Small Project ref.
Project Project Project Project
Unit = cum
Taking output = 205 Cum 450 tonnes
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm size
aggregate
Composition of mix (450 tonne) is assumed to be as under:-
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 90.000 90.000 906.193 81557.402 81557.402 81557.402 M-046
Aggregates size 6 to 0.075 mm - 450 x 0.35 x 1/1.5 cum 105.000 105.000 105.000 285.550 29982.743 29982.743 29982.743 M-029
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 90.000 90.000 906.193 81557.402 81557.402 81557.402 M-046
Aggregates size 6 to 0.075 mm - 450 x0.38 x 1/1.5 cum 114.000 114.000 114.000 699.312 79721.592 79721.592 79721.592 M-030
Unit = cum
Taking output = 205 Cum 450 tonnes
a) Labour
Mate day 0.480 0.480 0.480 622.000 298.560 298.560 298.560 L-12
Mazdoor day 7.000 7.000 7.000 560.000 3920.000 3920.000 3920.000 L-13
Mazdoor skilled day 5.000 5.000 5.000 592.000 2960.000 2960.000 2960.000 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 13298.000 39894.000 P&M-18001
(ii) HMP 160 TPH hour 3.750 9323.000 34961.250 P&M-18002
(iii) HMP 120 TPH hour 5.000 7568.000 37840.000 P&M-18003
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 8638.000 25914.000 P&M-29001
(ii) Paver (240HP) hour 3.750 8638.000 32392.500 P&M-29001
(iii) Paver (174HP) hour 5.000 6848.000 34240.000 P&M-29002
Electric generator
(i) 500 KVA hour 3.000 6985.000 20955.000 P&M-22002
(ii) 400 KVA hour 3.750 5635.000 21131.250 P&M-22003
(iii) 250 KVA hour 5.000 3970.000 19850.000 P&M-22004
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.044 3907.000 19708.497 P&M-5001
(ii) 2.1 Cum Capacity hour 7.441 2393.000 17805.117 P&M-5002
(iii) 1 Cum Capacity hour 15.664 1633.000 25579.656 P&M-5003
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 6.830 6147.000 P&M-72002
(ii) 14 cum capacity t.km 450 x L1 7.770 6993.000 P&M-73002
(iii) 10 cum capacity t.km 450 x L1 9.620 8658.000 P&M-74002
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2621.000 15726.000 P&M-6001
(ii) 14 cum capacity hour 7.500 2331.000 17482.500 P&M-6002
(iii) 10 cum capacity hour 10.000 2077.000 20770.000 P&M-6003
Smooth steel wheeled tandem roller for static and hour 1864.000 33814.059 33814.059 33814.059 P&M-8001
vibratory passaes 18.141 18.141 18.141
c) Material
Composition of mix (450 tonne) is assumed to be as
under:-
Density 2.20 tonne per cum
Weight450 tonne
Bitumen5 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 93 per cent
Bitumen@ 5 per cent tonne 22.500 22.500 22.500 34512.450 776530.125 776530.125 776530.125 M-074
Filler (lime)@ 2 per cent tonne 9.000 9.000 9.000 6500.000 58500.000 58500.000 58500.000 M-190
Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5 cum 288.620 288.620 288.620 955.775 275855.781 275855.781 275855.781 M-004
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Amount
Quantity
(Rs.)
Reference to Rate Remarks/ Input
Sr No Description Unit For Large For Medium For Small Medium
MORT&H Specification (Rs.) Large Project Small Project ref.
Project Project Project Project
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.160 0.160 0.160 622.000 99.520 99.520 99.520 L-12
Mazdoor day 4.000 4.000 4.000 560.000 2240.000 2240.000 2240.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.125 3.125 3.125 951.000 2971.875 2971.875 2971.875 P&M-23001
Air compressor 250 cfm hour 3.125 3.125 3.125 550.000 1718.750 1718.750 1718.750 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1550.000 4520.833 4520.833 4520.833 P&M-24001
2.917 2.917 2.917
Hydraulic Chip spreader hour 5.397 5.397 5.397 1989.000 10734.221 10734.221 10734.221 P&M-32001
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 1864.000 10059.622 10059.622 10059.622 P&M-8001
c) Material
Modified binder tonne 9.450 9.450 9.450 35012.450 330867.653 330867.653 330867.653 M-078
Crushed stone aggregates 5.6 mm size cum 105.000 105.000 105.000 860.758 90379.568 90379.568 90379.568 M-049
d) Overhead charges @ 8% on @ 10% on @ 12% on 36287.363 45359.204 54431.045
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 48987.940 49895.125 50802.309
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 538867.345 548846.370 558825.395
Rate per Sqm = (a+b+c+d+e)/10500 51.321 52.271 53.221
Say, 51.32 52.27 53.22
5.17 (ii) Stress absorbing membrane (SAM) with crack width 6 mm to
9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with IRC:SP: 53, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.160 0.160 0.160 622.000 99.520 99.520 99.520 L-12
Mazdoor day 4.000 4.000 4.000 560.000 2240.000 2240.000 2240.000 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.125 3.125 3.125 951.000 2971.875 2971.875 2971.875 P&M-23001
Air compressor 250 cfm hour 3.125 3.125 3.125 550.000 1718.750 1718.750 1718.750 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1550.000 4520.833 4520.833 4520.833 P&M-24001
2.917 2.917 2.917
Hydraulic Chip spreader hour 5.397 5.397 5.397 1989.000 10734.221 10734.221 10734.221 P&M-32001
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 1864.000 10059.622 10059.622 10059.622 P&M-8001
c) Material
Modified binder tonne 11.550 11.550 11.550 35012.450 404393.798 404393.798 404393.798 M-078
Crushed stone chipping 11.2 mm size cum 105.000 105.000 105.000 860.758 90379.568 90379.568 90379.568 M-050
d) Overhead charges @ 8% on @ 10% on @ 12% on 42169.455 52711.819 63254.182
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 56928.764 57983.000 59037.237
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 626216.405 637813.005 649409.605
Rate per Sqm = (a+b+c+d+e)/10500 59.640 60.744 61.849
Say, 59.64 60.74 61.85
5.17 (iii) Stress absorbing membrane (SAM) crack width above 9 mm
and cracked area above 50 per cent
Providing and laying a single coat of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 per cent after
cleaning with a mechanical broom, using modified binder
complying with IRC:SP: 53, sprayed at the rate of 15 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 0.240 0.240 622.000 149.280 149.280 149.280 L-12
Mazdoor day 4.000 4.000 4.000 560.000 2240.000 2240.000 2240.000 L-13
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.125 3.125 3.125 951.000 2971.875 2971.875 2971.875 P&M-23001
Air compressor 250 cfm hour 3.125 3.125 3.125 550.000 1718.750 1718.750 1718.750 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1550.000 4520.833 4520.833 4520.833 P&M-24001
2.917 2.917 2.917
Hydraulic Chip spreader hour 5.397 5.397 5.397 1989.000 10734.221 10734.221 10734.221 P&M-32001
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 1864.000 10059.622 10059.622 10059.622 P&M-8001
c) Material
Modified binder tonne 15.750 15.750 15.750 35012.450 551446.088 551446.088 551446.088 M-078
Crushed stone aggregates 11.2 mm size cum 126.000 126.000 126.000 860.758 108455.481 108455.481 108455.481 M-050
d) Overhead charges @ 8% on @ 10% on @ 12% on 55478.412 69348.015 83217.618
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 74895.856 76282.816 77669.777
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 823854.418 839110.981 854367.544
Rate per Sqm = (a+b+c+d+e)/10500 78.462 79.915 81.368
Say, 78.46 79.92 81.37
Note In case 2nd coat is also required to be provided, material
provided for the 2nd coat shall be as per Table 500-43.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.280 0.280 0.280 622.000 174.160 174.160 174.160 L-12
Mazdoor day 5.000 5.000 5.000 560.000 2800.000 2800.000 2800.000 L-13
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 1.042 1.042 1.042 951.000 990.625 990.625 990.625 P&M-23001
Air compressor 250 cfm hour 1.042 1.042 1.042 550.000 572.917 572.917 572.917 P&M-15001
Bitumen pressure distributor (Spraying width 4.5 m) hour 1550.000 1506.944 1506.944 1506.944 P&M-24001
0.972 0.972 0.972
Pneumatic roller hour 2.000 2.000 2.000 2333.000 4666.000 4666.000 4666.000 P&M-10001
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 kg tonne
per sqm 3.680 3.680 3.680 35012.450 128845.816 128845.816 128845.816 M-075
Geotextile including 10 per cent for overlaps sqm 3850.000 3850.000 3850.000 145.000 558250.000 558250.000 558250.000 M-107
d) Overhead charges @ 8% on @ 10% on @ 12% on 55919.237 69899.046 83878.855
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 75490.970 76888.951 78286.932
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 3500 Sqm = a+b+c+d+e 830400.669 845778.459 861156.249
Rate per Sqm = (a+b+c+d+e)/3500 237.257 241.651 246.045
Say, 237.26 241.65 246.04
NOTE As bitumen overlay construction shall follow closely the fabric
placement on the same day, an output of 3500 sqm only has
been considered for the analysis which will cover a length of
500 m, of 7 m wide carriagway. This can be conveniently
overlaid by a bitumenious course in a day
Unit = cum
Taking output 205 Cum 450 tonnes
(i) 75 mm thickness
a) Labour
Mate day 0.480 0.480 0.480 622.000 298.560 298.560 298.560 L-12
Mazdoor day 7.000 7.000 7.000 560.000 3920.000 3920.000 3920.000 L-13
Mazdoor skilled day 5.000 5.000 5.000 592.000 2960.000 2960.000 2960.000 L-15
b) Machinery
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Amount
Quantity
(Rs.)
Reference to Rate Remarks/ Input
Sr No Description Unit For Large For Medium For Small Medium
MORT&H Specification (Rs.) Large Project Small Project ref.
Project Project Project Project
Unit = cum
Taking output 450 cum
990 tonne
a) Labour
Mate day 0.360 0.360 0.360 622.000 223.920 223.920 223.920 L-12
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
Mazdoor day 7.000 7.000 7.000 560.000 3920.000 3920.000 3920.000 L-13
b) Machinery
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 2.045 26584.000 54376.364 P&M-30001
(ii) Paver Finisher Concrete with 241 HP Motor 3.000 17178.000 51534.000 P&M-30002
(iii) Paver Finisher Concrete with 118 HP Motor 5.625 4204.000 23647.500 P&M-30003
Vibratory roller 8-10 t capacity hour 2.045 3.000 5.625 2335.000 4776.136 7005.000 13134.375 P&M-7001
Tipper
For Transportation
(i) 18 cum capacity t.km 990 x L1 6.830 13523.400 P&M-72002
(ii) 14 cum capacity t.km 990 x L1 7.770 15384.600 P&M-73002
(iii) 10 cum capacity t.km 990 x L1 9.620 19047.600 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 4.545 2621.000 11913.636 P&M-6001
(ii) 14 cum capacity hour 5.500 2331.000 12820.500 P&M-6002
(iii) 10 cum capacity hour 10.625 2077.000 22068.125 P&M-6003
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 3.019 1357.000 4096.444 P&M-11001
(ii) 12 KL capacity hour 4.025 1187.000 4777.675 P&M-11002
(iii) 6 KL capacity hour 8.050 904.000 7277.200 P&M-11003
c) Material
Concrete from sub-analysis of concrete Rate
(i) Using Batching Plant 240 Cum Capacity
Sub-Analysis of
cum 450.000 2379.83 1070923.319
Concrete - 19.18 A
Cost of water (Curing) KL 217.350 217.350 217.350 74.54 16201.269 16201.269 16201.269 M-191
Unit = cum
Taking output = 900 Cum 2070 Tonne
a) Labour
Mate day 0.440 0.440 0.440 622.000 273.680 273.680 273.680 L-12
Mazdoor skilled day 5.000 5.000 5.000 592.000 2960.000 2960.000 2960.000 L-15
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.893 0.893 0.893 951.000 849.107 849.107 849.107 P&M-23001
Air compressor 250 cfm hour 0.893 0.893 0.893 550.000 491.071 491.071 491.071 P&M-15001
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 4.091 26584.000 108752.727 P&M-30001
(ii) Paver Finisher Concrete with 241 HP Motor 6.000 17178.000 103068.000 P&M-30002
(iii) Paver Finisher Concrete with 118 HP Motor 11.250 4204.000 47295.000 P&M-30003
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km 2070 x L1 2070 x L1 2070 x L1 12.220 50590.800 50590.800 50590.800 P&M-76001
For unloding time hour 4.091 4.091 11.250 2198.000 8991.818 8991.818 24727.500 P&M-34001
Concrete joint cutting machine hour 101.587 101.587 101.587 452.000 45917.460 45917.460 45917.460 P&M-42001
Texturing machine
Texturing machine (TCM) - upto 18 m hour 4.091 4543.000 18585.000 P&M-31001
Texturing machine (TCM) - upto 18 m 6.000 4543.000 27258.000 P&M-31001
Texturing machine (TCM) - upto 9 m 11.250 3570.000 40162.500 P&M-31002
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 22.313 1357.000 30278.063 P&M-11001
(ii) 12 KL capacity hour 29.750 1187.000 35313.250 P&M-11002
(iii) 6 KL capacity hour 59.500 904.000 53788.000 P&M-11003
c) Material
Concrete from sub-analysis of concrete Rate
Sub-Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 900.000 4160.57 3744511.470
Concrete - 19.19 A
Sub-Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 900.000 4160.57 3744511.470
Concrete - 19.19 A
Sub-Analysis of
(iii) Using Batching Plant 120 Cum Capacity cum 900.000 4216.95 3795256.470
Concrete - 19.19 C
36 mm mild steel dowel bars of grade S 240 tonne 9.170 9.170 9.170 58000.00 531860.000 531860.000 531860.000 M-125
12 mm deformed steel tie bars of grade S 415 tonne 1.051 1.051 1.051 62000.00 65162.000 65162.000 65162.000 M-083
Separation Membrane of impermeable plastic sheeting 125 sqm 3150.000 3150.000 3150.000 15.00 47250.000 47250.000 47250.000 M-165
micron thick (including 5% Overlap)
Joint sealant kg 609.524 609.524 609.524 55.00 33523.810 33523.810 33523.810 M-119
Sealant primer kg 100.003 100.003 100.003 155.00 15500.443 15500.443 15500.443 M-097
Plastic sheath,1.25 mm thick for dowel bars sqm 155.735 155.735 155.735 50.00 7786.752 7786.752 7786.752 M-137
Curing compound Liter 600.000 600.000 600.000 60.00 36000.000 36000.000 36000.000 M-091
Cost of water (Curing) KL 472.500 472.500 472.500 74.54 35220.150 35220.150 35220.150 M-191
Add 1 per cent of material for cost of miscellaneous materials
like tarpauline, Hessian cloth, metal cap, cotton / compressible
sponge and cradle for dowel bars, work bridges for men to
approach concrete surface without walking over it, cutting
47878.64 47958.88 48379.75
blades and bites, minor equipments like scabbling machine,
threads, ropes, guide wires and any other unforeseen items.
Unit = cum
Taking output 450 cum
990 tonne
a) Labour
Mate day 0.360 0.360 0.360 622.000 223.920 223.920 223.920 L-12
Mazdoor skilled day 2.000 2.000 2.000 592.000 1184.000 1184.000 1184.000 L-15
Mazdoor day 7.000 7.000 7.000 560.000 3920.000 3920.000 3920.000 L-13
b) Machinery
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 2.045 26584.000 54376.364 P&M-30001
(ii) Paver Finisher Concrete with 241 HP Motor 3.000 17178.000 51534.000 P&M-30002
(iii) Paver Finisher Concrete with 118 HP Motor 5.625 4204.000 23647.500 P&M-30003
Vibratory roller 8-10 t capacity hour 2.045 3.000 5.625 2335.000 4776.136 7005.000 13134.375 P&M-7001
Tipper
For Transportation
(i) 18 cum capacity t.km 990 x L1 6.830 13523.400 P&M-72002
(ii) 14 cum capacity t.km 990 x L1 7.770 15384.600 P&M-73002
(iii) 10 cum capacity t.km 990 x L1 9.620 19047.600 P&M-74002
For loading & unloading Time
(i) 18 cum capacity hour 4.545 2621.000 11913.636 P&M-6001
(ii) 14 cum capacity hour 5.500 2331.000 12820.500 P&M-6002
(iii) 10 cum capacity hour 10.625 2077.000 22068.125 P&M-6003
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 3.019 1357.000 4096.444 P&M-11001
(ii) 12 KL capacity hour 4.025 1187.000 4777.675 P&M-11002
(iii) 6 KL capacity hour 8.050 904.000 7277.200 P&M-11003
c) Material
Concrete from sub-analysis of concrete Rate
Sub-Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 450.000 2243.23 1009453.463
Concrete - 19.18 B
Sub-Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 450.000 2243.23 1009453.463
Concrete - 19.18 B
Sub-Analysis of
(iii) Using Batching Plant 120 Cum Capacity cum 450.000 2275.19 1023835.963
Concrete - 19.18 D
Cost of water (Curing) KL 217.350 217.350 217.350 74.54 16201.269 16201.269 16201.269 M-191
Unit = cum
Taking output = 900 Cum 2070 Tonne
a) Labour
Mate day 0.440 0.440 0.440 622.000 273.680 273.680 273.680 L-12
Mazdoor skilled day 5.000 5.000 5.000 592.000 2960.000 2960.000 2960.000 L-15
Mazdoor day 6.000 6.000 6.000 560.000 3360.000 3360.000 3360.000 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.893 0.893 0.893 951.000 849.107 849.107 849.107 P&M-23001
Air compressor 250 cfm hour 0.893 0.893 0.893 550.000 491.071 491.071 491.071 P&M-15001
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 4.091 26584.000 108752.727 P&M-30001
(ii) Paver Finisher Concrete with 241 HP Motor 6.000 17178.000 103068.000 P&M-30002
(iii) Paver Finisher Concrete with 118 HP Motor 11.250 4204.000 47295.000 P&M-30003
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km 2070 x L1 2071 x L1 2072 x L1 12.220 50590.800 50590.800 50590.800 P&M-76001
For Unloding time hour 4.091 6.000 11.250 2198.000 8991.818 13188.000 24727.500 P&M-34001
Concrete joint cutting machine . hour 101.587 101.587 101.587 452.000 45917.460 45917.460 45917.460 P&M-42001
Texturing machine . hour 4.091 6.000 11.250 4543.000 18585.000 27258.000 51108.750 P&M-31001
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 22.313 1357.000 30278.063 P&M-11001
(ii) 12 KL capacity hour 29.750 1187.000 35313.250 P&M-11002
(iii) 6 KL capacity hour 59.500 904.000 53788.000 P&M-11003
c) Material
Concrete from sub-analysis of concrete Rate
Sub-Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 900.000 3816.97 3435275.938
Concrete - 19.19 B
Sub-Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 900.000 3816.97 3435275.938
Concrete - 19.19 B
36 mm mild steel dowel bars of grade S 240 tonne 9.170 9.170 9.170 58000.00 531860.000 531860.000 531860.000 M-125
12 mm deformed steel tie bars of grade S 415 tonne 1.051 1.051 1.051 62000.00 65162.000 65162.000 65162.000 M-083
Separation Membrane of impermeable plastic sheeting 125 sqm 3150.000 3150.000 3150.000 15.00 47250.000 47250.000 47250.000 M-165
micron thick (including 5% Overlap)
Joint sealant kg 609.524 609.524 609.524 55.00 33523.810 33523.810 33523.810 M-119
Sealant primer kg 100.003 100.003 100.003 155.00 15500.443 15500.443 15500.443 M-097
Plastic sheath,1.25 mm thick for dowel bars sqm 155.735 155.735 155.735 50.00 7786.752 7786.752 7786.752 M-137
Curing compound Liter 600.000 600.000 600.000 60.00 36000.000 36000.000 36000.000 M-091
Cost of water (Curing) KL 472.500 472.500 472.500 74.54 35220.150 35220.150 35220.150 M-191
CHAPTER-6
CEMENT CONCRETE PAVEMENTS
Amount
Quantity
(Rs.)
Reference to Rate
Sr No Description Unit Remarks/ Input ref.
MORT&H Specification For Large For Medium For Small (Rs.)
Large Project Medium Project Small Project
Project Project Project
Unit = sqm
Taking output = 2800 sqm
a) Labour
Mate day 0.800 0.800 0.800 622.00 497.60 497.60 497.60 L-12
Mazdoor day 20.000 20.000 20.000 560.00 11200.00 11200.00 11200.00 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 0.833 2.240 2.240 951.00 792.50 2130.24 2130.24 P&M-23001
Pneumatic roller 14 tonnes 2000 sqm per hour hour 1.400 1.400 1.400 2333.00 3266.20 3266.20 3266.20 P&M-10001
Bitumen pressure distributor (Spraying width 4.5 hour 0.778 0.778 0.778 1550.00 1205.56 1205.56 1205.56 P&M-24001
m)
c) Material
Paving Fabric sqm 2940.0 2940.0 2940.0 125.00 367500.00 367500.00 367500.00 M-132
Paving Bitumen 80-100 tonne 2.800 2.800 2.800 35012.45 98034.86 98034.86 98034.86 M-075
c) Overhead charges @ 8% on @ 10% on @ 12% on 38599.74 48383.45 58060.13
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 52109.65 53221.79 54189.46
(a+b+c) (a+b+c) (a+b+c)
Cost for 2800 sqm = a+b+c+d+e 573206.10 585439.69 596084.05
Rate per sqm =(a+b+c+d+e)/2800 204.72 209.09 212.89
say 205.00 209.00 213.00
7.3 703 Laying Boulder Apron in Crates of Synthetic Geogrids
Unit = cum
Taking output = 3 cum
a) Labour
Mate day 0.060 0.060 0.060 622.00 37.32 37.32 37.32 L-12
Mazdoor skilled day 0.500 0.500 0.500 592.00 296.00 296.00 296.00 L-15
Mazdoor day 1.500 1.500 1.500 560.00 840.00 840.00 840.00 L-13
b) Material
Geo grids sqm 21.000 21.000 21.000 190.00 3990.00 3990.00 3990.00 M-104
Connectors/ Staples each 50.000 50.000 50.000 55.00 2750.00 2750.00 2750.00 M-086
Polymer braids metre 20.000 20.000 20.000 150.00 3000.00 3000.00 3000.00 M-139
Stones with minimum size of 200 mm cum 3.450 3.450 3.450 420.14 1449.47 1449.47 1449.47 M-003
Stones spall for filling voids cum 0.450 0.450 0.450 302.41 136.08 136.08 136.08 M-008
c) Overhead charges @ 8% on @ 10% on @ 12% on 999.91 1249.89 1499.86
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1349.88 1374.88 1399.87
(a+b+c) (a+b+c) (a+b+c)
Cost for 3 cum = a+b+c+d 14848.66 15123.63 15398.61
Rate per cum = (a+b+c+d)/ 3 1142.20 1163.36 1184.51
say 1142.00 1163.00 1185.00
7.4 3100 Reinforced Earth Structures
Reinforced earth Structures have four main
components as under:
a) Excavation for foundation, foundation concrete
and cement concrete grooved seating in the
foundation for facing elements (facia material).
Page 1 of 253
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Amount
Quantity
Reference to (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
Mazdoor skilled day 2.000 2.000 2.000 592.00 1184.00 1184.00 1184.00 L-15
b) Material
@ Reinforcement strips 60 mm wide 5 mm thick as
per clause 3103. including 5% wastage
1.Galvanised carbon steel strips metre 472.500 472.500 472.500 180.00 85050.00 85050.00 85050.00 M-155
Add 5 per cent of the cost of reinforcing elements 8505.00 8505.00 8505.00
strip towards accessories like tie-strips, nuts and
bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps heat
bonding or extension
or
2.Copper Strips metre 472.500 472.500 472.500 185.00 87412.50 87412.50 87412.50 M-154
Add 5 per cent of the cost of reinforcing elements 8741.25 8741.25 8741.25
strip towards accessories like tie-strips, nuts and
bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps heat
bonding or extension
or
3.Aluminium Strips metre 472.500 472.500 472.500 190.00 89775.00 89775.00 89775.00 M-158
Add 5 per cent of the cost of reinforcing elements 8977.50 8977.50 8977.50
strip towards accessories like tie-strips, nuts and
bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps heat
bonding or extension
or
4.Stainless steel strips metre 472.500 472.500 472.500 180.00 85050.00 85050.00 85050.00 M-157
Add 5 per cent of the cost of reinforcing elements 8505.00 8505.00 8505.00
strip towards accessories like tie-strips, nuts and
bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps heat
bonding or extension
or
5.Glass reinforced polymer/fibre reinforced metre 472.500 472.500 472.500 150.00 74250.00 74250.00 74250.00 M-156
polymer/polymeric strips
Add 5 per cent of the cost of reinforcing elements 7425.00 7425.00 7425.00
strip towards accessories like tie-strips, nuts and
bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps heat
bonding or extension
Unit = sqm
Taking output 300 sqm
a) Labour
Mate day 0.200 0.200 0.200 622.00 124.40 124.40 124.40 L-12
Mazdoor day 3.000 3.000 3.000 560.00 1680.00 1680.00 1680.00 L-13
Mazdoor skilled day 2.000 2.000 2.000 592.00 1184.00 1184.00 1184.00 L-15
b) Material
Synthetic Geogrids as per clause 3100 and sqm 315.000 315.000 315.000 150.00 47250.00 47250.00 47250.00 M-183
approved design and specifications including 5%
wastage.
Add 5 per cent of the cost of reinforcing elements 2362.50 2362.50 2362.50
(synthetic geogrids) for accessories like tie-strips,
nuts and bolts and loops/lugs for joining
reinforcing elements with the facia pannels,
overlaps and other protective elements for
synthetic geogrids.
Page 2 of 253
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Amount
Quantity
Reference to (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
Non-Woven geotextile behind the fascia element Sqm 80.000 80.000 80.000 145.00 11600.00 11600.00 11600.00 M-107
to avoid leaching out of backfill material
HYSD steel @ 7 kg / sqm (Refer Item 12.6 ,Basic tonnes 1.400 1.400 1.400 67548.00 94567.20 94567.20 94567.20 67548.00
Cost of Labour, Material & Machinery )
Add 2 per cent of cost of facia pannels, for all 6272.79 6272.79 6272.79
necessary temporary form work, scaffolding and
provision of loops/lugs for lifting of pannels and
joining the reinforcing elements.
d) Overhead charges @ 8% on @ 10% on @ 12% on 608.42 760.53 912.63
(a+b) (a+b) (a+b)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 821.37 836.58 851.79
(a+b+d) (a+b+d) (a+b+d)
Cost for 200 sqm = a+b+c+d+e 321341.96 321509.28 321676.60
Rate per sqm = (a+b+c+d+e)/200 1606.71 1607.55 1608.38
say 1607.00 1608.00 1608.00
Note 1.The specification and construction details to be
adopted shall be as per section 3100 of MoRTH
Specification.
2.Drainage arrangement shall be made as per
approved design and drawings.
3.The quantity of filler media shall be calculated as
per approved design and specifications and shall be
priced separately.The rate for same to be adopted
from chapter 9.
4.Excavation for foundation including foundation
concrete and groove in the foundation for seating of
bottom most facia panel and capping beam to be
calculated as per design and priced separately. The
rates for excavation and foundation concrete shall be
taken from the chapter 9 culvert chapter
7.5 703 (i) Supplying & laying of bi-axial extruded high modulus
polypropylene geogrid conforming to MORT&H
specification for base/sub-base reinforcement having
minimum tensile strength 15kN/m in the longitudinal
and transverse direction, with 5kN/m and 7kN/m
tensile strength at 2% and 5% strain respectively in
the longitudinal and transverse direction, junction
efficiency not less than 95% and with 38mm X 38mm
mesh opening.
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 622.00 124.40 124.40 124.40 L-12
Mazdoor day 3.000 3.000 3.000 560.00 1680.00 1680.00 1680.00 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 592.00 1184.00 1184.00 1184.00 L-15
b) Material
Bi-Axial Extruded GeoGrids of Minimum Tensile sqm 300.00 300.00 300.00 95.00 28500.00 28500.00 28500.00 M-286
Strength 15 kN/m in the longitudinal and
transverse direction
Add 10 % of the cost of reinforcing elements 2850.00 2850.00 2850.00
(synthetic geogrids) for wastage and accessories
like tie-strips, nuts and bolts and loops/lugs for
joining reinforcing elements with the facia
pannels, overlaps and other protective elements
for synthetic geogrids and all other activities
required to complete the item in all respect
including taxes and transportation.
Page 3 of 253
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Amount
Quantity
Reference to (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
7.5 703 (ii) Supplying & laying of bi-axial extruded high modulus
polypropylene geogrid conforming to MORT&H
specification for base/sub-base reinforcement having
minimum tensile strength 20kN/m in the longitudinal
and transverse direction, with 7kN/m and 14kN/m
tensile strength at 2% and 5% strain respectively in
the longitudinal and transverse direction, junction
efficiency not less than 95% and with 38mm X 38mm
mesh opening.
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 622.00 124.40 124.40 124.40 L-12
Mazdoor day 3.000 3.000 3.000 560.00 1680.00 1680.00 1680.00 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 592.00 1184.00 1184.00 1184.00 L-15
b) Material
Bi-Axial Extruded GeoGrids of Minimum Tensile sqm 300.00 300.00 300.00 109.00 32700.00 32700.00 32700.00 M-287
Strength 20 kN/m in the longitudinal and
transverse direction
Add 10 % of the cost of reinforcing elements 3270.00 3270.00 3270.00
(synthetic geogrids) for wastage and accessories
like tie-strips, nuts and bolts and loops/lugs for
joining reinforcing elements with the facia
pannels, overlaps and other protective elements
for synthetic geogrids and all other activities
required to complete the item in all respect
including taxes and transportation.
7.5 703 (iii) Supplying & laying of bi-axial extruded high modulus
polypropylene geogrid conforming to MORT&H
specification for base/sub-base reinforcement having
minimum tensile strength 30kN/m in the longitudinal
and transverse direction, with 10.5kN/m and 21kN/m
tensile strength at 2% and 5% strain respectively in
the longitudinal and transverse direction, junction
efficiency not less than 95% and with 38mm X 38mm
mesh opening.
7.5 703 (iv) Supplying & laying of bi-axial extruded high modulus
polypropylene geogrid coforming to MORT&H
specification for base/sub-base reinforcement having
minimum tensile strength 40kN/m in the longitudinal
and transverse direction, with 14kN/m and 28kN/m
tensile strength at 2% and 5% strain respectively in
the longitudinal and transverse direction, junction
efficiency not less than 95% and with 38mm X 38mm
mesh opening.
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 622.00 124.40 124.40 124.40 L-12
Mazdoor day 3.000 3.000 3.000 560.00 1680.00 1680.00 1680.00 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 592.00 1184.00 1184.00 1184.00 L-15
b) Material
Bi-Axial Extruded GeoGrids of Minimum Tensile sqm 300.00 300.00 300.00 260.00 78000.00 78000.00 78000.00 M-289
Strength 40 kN/m in the longitudinal and
transverse direction
Add 10 % of the cost of reinforcing elements 7800.00 7800.00 7800.00
(synthetic geogrids) for wastage and accessories
like tie-strips, nuts and bolts and loops/lugs for
joining reinforcing elements with the facia
pannels, overlaps and other protective elements
for synthetic geogrids and all other activities
required to complete the item in all respect
including taxes and transportation.
Page 4 of 253
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Amount
Quantity
Reference to (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
Skilled Beldar day 2.000 2.000 2.000 592.00 1184.00 1184.00 1184.00 L-15
a) Material
(i) Synthetic Geogrid Ultimate tensile strength- 100 sqm 300*1.1 300*1.1 300*1.1 200.00 66000.00 66000.00 66000.00 M-200
kN/m
(ii) Synthetic Geogrid Ultimate tensile strength- 150 sqm 300*1.1 300*1.1 300*1.1 220.00 72600.00 72600.00 72600.00 M-201
kN/m
(iii) Synthetic Geogrid Ultimate tensile strength- 200 sqm 300*1.1 300*1.1 300*1.1 300.00 99000.00 99000.00 99000.00 M-202
kN/m
(iv) Synthetic Geogrid Ultimate tensile strength- 250 sqm 300*1.1 300*1.1 300*1.1 330.00 108900.00 108900.00 108900.00 M-203
kN/m
(v) Synthetic Geogrid Ultimate tensile strength- 300 sqm 300*1.1 300*1.1 300*1.1 350.00 115500.00 115500.00 115500.00 M-204
kN/m
(vi) Synthetic Geogrid Ultimate tensile strength- 350 sqm 300*1.1 300*1.1 300*1.1 390.00 128700.00 128700.00 128700.00 M-205
kN/m
(vii) Synthetic Geogrid Ultimate tensile strength- 400 sqm 300*1.1 300*1.1 300*1.1 420.00 138600.00 138600.00 138600.00 M-206
kN/m
(viii) Synthetic Geogrid Ultimate tensile strength- 500 sqm 300*1.1 300*1.1 300*1.1 500.00 165000.00 165000.00 165000.00 M-207
kN/m
(ix) Synthetic Geogrid Ultimate tensile strength- 600 sqm 300*1.1 300*1.1 300*1.1 550.00 181500.00 181500.00 181500.00 M-208
kN/m
(x) Synthetic Geogrid Ultimate tensile strength- 800 sqm 300*1.1 300*1.1 300*1.1 708.00 233640.00 233640.00 233640.00 M-209
kN/m
(xi) Synthetic Geogrid Ultimate tensile strength- 900 sqm 300*1.1 300*1.1 300*1.1 841.00 277530.00 277530.00 277530.00 M-210
kN/m
(xii) Synthetic Geogrid Ultimate tensile strength- 1000 sqm 300*1.1 300*1.1 300*1.1 950.00 313500.00 313500.00 313500.00 M-211
kN/m
(xiii) Synthetic Geogrid Ultimate tensile strength- 1100 sqm 300*1.1 300*1.1 300*1.1 1000.00 330000.00 330000.00 330000.00 M-212
kN/m
(xiv) Synthetic Geogrid Ultimate tensile strength- 1200 sqm 300*1.1 300*1.1 300*1.1 1088.00 359040.00 359040.00 359040.00 M-213
kN/m
@ Any one of the above alternative may be
adopted as per approved design.
Add 10 per cent of the cost of reinforcing
elements (synthetic geogrids) for wastage and
accessories like tie-strips, nuts and bolts and
loops/lugs for joining reinforcing elements with the
facia pannels, overlaps and other protective
elements for synthetic geogrids and all other
activities required to complete the item in all
respect including taxes and transportation.
Page 5 of 253
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Amount
Quantity
Reference to (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 622.00 124.40 124.40 124.40 L-12
Mazdoor day 3.000 3.000 3.000 560.00 1680.00 1680.00 1680.00 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 592.00 1184.00 1184.00 1184.00 L-15
b) Material
Geosynthetic Drainage Composite sqm 300.00 300.00 300.00 504.00 151200.00 151200.00 151200.00 M-290
Add 10 per cent of the cost of synthetic Composits 15120.00 15120.00 15120.00
for wastage and accessories for joining sheets
with the facia pannels, overlaps and other
protective elements for synthetic Composits and
other miscelleneus activities required to complete
the item in all respect including transpotarion &
takes.
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 622.00 124.40 124.40 124.40 L-12
Mazdoor day 3.000 3.000 3.000 560.00 1680.00 1680.00 1680.00 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 592.00 1184.00 1184.00 1184.00 L-15
b) Material
Geosynthetic Drainage Composite sqm 300.00 300.00 300.00 600.00 180000.00 180000.00 180000.00 M-291
Add 10 per cent of the cost of synthetic Composits 18000.00 18000.00 18000.00
for wastage and accessories for joining sheets
with the facia pannels, overlaps and other
protective elements for synthetic Composits and
other miscelleneus activities required to complete
the item in all respect including transpotarion &
takes.
Page 6 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Page 1 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Unit = Each
Taking output = one traffic sign
Item No. - 9.01 A -
i) Excavation for foundation cum 0.122 0.122 0.122 204.71 24.87 24.87 24.87
(I)
3900.00 Item No. - 9.14 A,
ii) Cement concrete M15 grade cum 0.122 0.122 0.122 473.85 473.85 473.85
case - II
iii) Painting angle iron post two coats sqm 1.414 1.414 1.414 65.92 93.20 93.20 93.20 Item No. - 8.9
a) Labour (For fixing at site)
Mate day 0.010 0.010 0.010 955.78 9.56 9.56 9.56 M-004
Mazdoor day 0.250 0.250 0.250 955.78 238.94 238.94 238.94 M-005
b) Material
Mild Steel 'L' Angle Back Support Frame 25 x 25 x
kg 2.200 2.200 2.200 65.00 143.00 143.00 143.00 M-181/1000
3mm
Page 2 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
c) Machinery
Tractor-trolley hour 0.010 0.010 0.010 820.00 8.20 8.20 8.20 P&M-12001
( ii ) 90 cm equilateral triangle
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 320.66 400.83 481.00
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 432.90 440.91 448.93
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4761.87 4850.05 4938.24
say 4762.00 4850.00 4938.00
( v ) 120 cm circular
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 619.74 774.67 929.61
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 836.65 852.14 867.63
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 9203.13 9373.56 9543.98
say 9203.00 9374.00 9544.00
(vi) 90 cm circular
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 430.07 537.59 645.11
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 580.60 591.35 602.10
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6386.61 6504.88 6623.15
say 6387.00 6505.00 6623.00
(viii) 60 cm circular
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 294.60 368.25 441.90
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 397.71 405.08 412.44
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4374.82 4455.83 4536.85
say 4375.00 4456.00 4537.00
( ix ) 90 cm x 75 cm rectangular
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 444.96 556.20 667.44
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 600.69 611.82 622.94
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6607.63 6729.99 6852.35
say 6608.00 6730.00 6852.00
Page 3 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
( x ) 80 mm x 60 mm rectangular
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 370.21 462.76 555.32
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 499.79 509.04 518.30
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5497.65 5599.45 5701.26
say 5498.00 5599.00 5701.00
(xi) 60 cm x 50 cm rectangular
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 301.22 376.52 451.82
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 406.64 414.17 421.70
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4473.05 4555.88 4638.71
say 4473.00 4556.00 4639.00
(xii) 60 cm x 45 cm rectangular
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 289.72 362.14 434.57
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 391.12 398.36 405.60
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4302.28 4381.95 4461.62
say 4302.00 4382.00 4462.00
(xiii ) 60 cm x 60 cm square
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 324.21 405.27 486.32
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 437.69 445.79 453.90
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4814.58 4903.74 4992.90
say 4815.00 4904.00 4993.00
Unit = sqm
Taking output = 0.9 sqm
Item No. - 9.01 A -
i) Excavation for foundation cum 0.122 0.122 0.122 204.71 24.87 24.87 24.87
(I)
Item No. - 9.14 A,
ii) Cement concrete M15 grade cum 0.122 0.122 0.122 3906.00 474.58 474.58 474.58
case - I
iii) Painting angle iron post two coats sqm 1.414 1.414 1.414 65.92 93.20 93.20 93.20 Item No. - 8.9 A,
a) Labour (For fixing at site)
Mate day 0.010 0.010 0.010 622.00 6.22 6.22 6.22 L-12
Mazdoor day 0.200 0.200 0.200 560.00 112.00 112.00 112.00 L-13
b) Material
Mild Steel 'L' Angle Back Support Frame 35 x 35 x
kg 6.080 6.080 6.080 65.000 395.20 395.20 395.20 M-181/1000
3mm
Page 4 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Unit = sqm
Taking output = 1.5 sqm
Item No. - 9.01 A -
i) Excavation for foundation cum 0.243 0.243 0.243 204.71 49.74 49.74 49.74
(I)
Item No. - 9.14 A,
ii) Cement concrete M15 grade cum 0.243 0.243 0.243 3906.00 949.16 949.16 949.16
case - I
iii) Painting angle iron post two coats sqm 2.827 2.827 2.827 65.92 186.40 186.40 186.40 Item No. - 8.9
a) Labour (For fixing at site)
Mate day 0.010 0.010 0.010 622.00 6.22 6.22 6.22 L-12
Mazdoor day 0.300 0.300 0.300 560.00 168.00 168.00 168.00 L-13
b) Material
Mild Steel 'L' Angle Back Support Frame 40 x 40 x 5
kg 14.400 14.400 14.400 65.000 936.00 936.00 936.00 M-181/1000
mm
Page 5 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Add @ 5 per cent cost of labour and materials to 31.30 31.30 31.30
prepare the surface by filling minuts roughness on
the surface and priming the surface before laying 2
coats of painting.
Per Sqm Basic Cost of Labour & Material (a+b) 65.92 65.92 65.92
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 52.74 65.92 79.11
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 56.96 72.52 88.60
Cost for 10 sqm = a+b+c+d 768.94 797.68 826.95
Rate per sqm= (a+b+c+d)/10 76.89 79.77 82.69
say 77.00 80.00 83.00
8.10 803 Painting on Wood Surfaces
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 0.030 0.030 622.00 18.66 18.66 18.66 L-12
Painter day 0.500 0.500 0.500 622.00 311.00 311.00 311.00 L-18
Mazdoor day 0.200 0.200 0.200 560.00 112.00 112.00 112.00 L-13
b) Material
Paint ready mixed of approved brand. Litre 1.500 1.500 1.500 150.00 225.00 225.00 225.00 M-130
Add @ 1 per cent on cost of material for scaffolding 2.25 2.25 2.25
Add @ 5 per cent cost of labour and materials to 33.33 33.33 33.33
prepare the surface by filling minuts roughness on
the surface and priming the surface before laying 2
coats of painting.
Per Sqm Basic Cost of Labour & Material (a+b) 70.22 70.22 70.22
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 56.18 70.22 84.27
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 75.84 77.25 78.65
Cost for 10 sqm = a+b+c+d 834.26 849.71 865.16
Rate per sqm = (a+b+c+d)/10 83.43 84.97 86.52
say 83.00 85.00 87.00
Painting Lines, Dashes, Arrows etc on Roads in Two
8.11 803
Coats on New Work
Page 6 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Page 7 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i 29903.45 30097.38 30291.31
Add 10 per cent cost of material for installation 630.00 630.00 630.00
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 601.19 751.49 901.79
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 811.61 826.64 841.67
Cost for 30 Nos. delineators = (a+b+ c+d) 8927.68 9093.00 9258.33
Rate per delineators = (a+b+c+d) /30 297.59 303.10 308.61
say 298.00 303.00 309.00
In case of soft ground, a proper foundation may be
provided as per approved design. In case foundation is
Note required to be provided, the items of excavation and
foundation concrete are required to be measured and
paid separately.
8.16 806 Boundary pillar
Unit = Each
Taking output = 57 Nos.
Page 8 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57 711.38 717.90 724.41
say 711.00 718.00 724.00
In case of soft ground, a proper foundation may be
provided as per approved design. In case foundation is
Note required to be provided, the items of excavation and
foundation concrete are required to be measured and
paid separately.
8.17 808 G.I Barbed Wire Fencing 1.2 Metre High
Page 9 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 0.6 3900.00 2527.20 2527.20 2527.20 Item No. - 9.14 A,
cum 0.648 0.648 0.648 Case II
x 0.3
iii) Painting of pipe sqm 4.710 4.710 4.710 65.92 310.50 310.50 310.50 Item No. - 8.9
iv) Painting of channel section 6 nos,1.8 metres each 65.92 142.40 142.40 142.40 Item No. - 8.9
sqm 2.160 2.160 2.160
0.2 x 1.8 x 6 = 2.16
a) Labour (For fixing at site)
Mate day 0.010 0.010 0.010 622.00 6.22 6.22 6.22 L-12
Mazdoor day 0.250 0.250 0.250 560.00 140.00 140.00 140.00 L-13
Plumber day 0.010 0.010 0.010 622.00 6.22 6.22 6.22 L-02
b) Material
Steel pipe 50 mm external dia as per IS:1239 metre 30.000 30.000 30.000 220.00 6600.00 6600.00 6600.00 M-176
65.00 6458.40 6458.40 6458.40 M-181/1000
Medium weight steel channel (ISMC series) 100 mm
kg 99.360 99.360 99.360
x 50 mm,10.8 metres length @ 9.2 kg per metre
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x 5661.55 3668.68 3668.68 3668.68 Item No. - 9.14 A,
cum 0.648 0.648 0.648 Case II
0.6 x 0.3
iii) RCC M - 20 for pre cast posts 6 nos of 1.8 metres 6409.00 30186.39 30186.39 30186.39 Item No. - 9.14 C,
cum 4.710 4.710 4.710 Case II
each
iv) Painting of pipe sqm 2.160 2.160 2.160 76.89 166.09 166.09 166.09 Item No. - 8.9
a) Labour
Mate day 0.010 0.010 0.010 622.00 6.22 6.22 6.22 L-12
Mazdoor day 0.250 0.250 0.250 560.00 140.00 140.00 140.00 L-13
Plumber day 0.010 0.010 0.010 622.00 6.22 6.22 6.22 L-02
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 30.000 30.000 220.00 6600.00 6600.00 6600.00 M-176
c) Machinery
Tractor-trolley hour 0.040 0.040 0.040 820.00 32.80 32.80 32.80 P&M-12001
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 542.82 678.52 814.23
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 732.81 746.38 759.95
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 42347.33 42496.61 42645.88
Page 10 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Page 11 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Suggest
8.25 Flexible Crash Barrier, Wire Rope Safety Barrier
ive
c) Painting
77.00 1270.50 1270.50 1270.50 Item No. - 8.9
Applying 2 coats of painting on exposed surface sqm 16.500 16.500 16.500
d) Machinery
Tractor-trolley hour 0.250 0.250 0.250 820.00 205.00 205.00 205.00 P&M-12001
e) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+d) (a+b+d) (a+b+d) 1932.96 2416.19 4455.53
f) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+d+e) (a+b+d+e) (a+b+d+e) 2609.49 2657.81 4158.50
Cost for 15 m = a+b+c+d+e+f 29974.88 30506.45 47013.97
Rate per m = (a+b+c+d+e+f)/15 1998.33 2033.76 3134.26
say 1998.00 2034.00 3134.00
The items of excavations and cement concrete works will
Note be measured and included separately as per the
approved designs and drawings.
Suggest
8.26 Anti-Glare Devices in Median
ive
A Plantation
Page 12 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 0.030 0.030 622.00 18.66 18.66 18.66 L-12
Mazdoor day 0.500 0.500 0.500 560.00 280.00 280.00 280.00 L-13
Electrician day 0.250 0.250 0.250 622.00 155.50 155.50 155.50 L-02
b) Material
i) Steel circular hollow pole of standard specification
for street lighting to mount light at 10 m height above each 1.000 1.000 1.000 62500.00 62500.00 62500.00 62500.00 M-172
road level
ii) Sodium vapour lamp each 1.000 1.000 1.000 7800.00 7800.00 7800.00 7800.00 M-169
Add 5 per cent of cost of material for holder, electric
3515.00
cable, insulation, ladder, scaffolding etc .
c) Painting
For Fixing in Median
77.00 442.75 442.75 442.75 Item No. - 8.9
Providing two coats of alluminium paint over steel
sqm 5.750 5.750 5.750
circular hollow pipe with overhang on both sides
Suggest
8.28 Lighting on Bridges
ive
Unit = Each
Taking output = one light
a) Labour
Mate day 0.020 0.020 0.020 622.00 12.44 12.44 12.44 L-12
Mazdoor day 0.400 0.400 0.400 560.00 224.00 224.00 224.00 L-13
Electrician day 0.200 0.200 0.200 622.00 124.40 124.40 124.40 L-02
b) Material
i) Steel circular hollow pole of standard specification 35000.00 35000.00 35000.00 35000.00 M-171
for street lighting to mount light at 5 m above deck each 1.000 1.000 1.000
level
ii) Sodium vapour lamp 70 watt each 1.000 1.000 1.000 7800.00 7800.00 7800.00 7800.00 M-169
Page 13 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Suggest
8.29 Cable Duct Across the Road
ive
Page 14 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Suggest
8.30 Highway Patrolling and Traffic Aid Post
ive
It is proposed to locate one Traffic Aid Post every 50-60
km of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .
Suggest Items Related to Underpass/ Subway/ Overhead Bridge/
8.31
ive Overhead Foot Bridge
Suggest
8.32 Traffic Control System and Communication System
ive
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.080 0.080 0.080 622.00 49.76 49.76 49.76 L-12
Mazdoor day 1.500 1.500 1.500 560.00 840.00 840.00 840.00 L-13
Blacksmith day 0.250 0.250 0.250 622.00 155.50 155.50 155.50 L-02
b) Material
Scrap tyres of size 900 x 20 each 80.000 80.000 80.000 60.00 4800.00 4800.00 4800.00 M-162
20 mm steel wire rope kg 150.000 150.000 150.000 55.00 8250.00 8250.00 8250.00 M-178
Add 1 per cent of cost of wire rope for clamps etc. 82.50 82.50 82.50
c) Machinery
Tractor-trolley hour 3.000 3.000 3.000 820.00 2460.00 2460.00 2460.00 P&M-12001
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 1331.02 1663.78 1996.53
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 1796.88 1830.15 1863.43
Cost for 20 sqm = a+b+c+d+e 19765.66 20131.69 20497.72
Rate per sqm = (a+b+c+d+e)/20 988.28 1006.58 1024.89
say 988.00 1007.00 1025.00
8.34 B Using Plastic/Steel Barrel, Filled with Sand
Page 15 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.130 0.130 0.130 622.00 80.86 80.86 80.86 L-12
Mazdoor day 3.000 3.000 3.000 560.00 1680.00 1680.00 1680.00 L-13
Blacksmith day 0.250 0.250 0.250 622.00 155.50 155.50 155.50 L-02
b) Material
Plastic barrels each 50.000 50.000 50.000
or
Steel barrels each 50.000 50.000 50.000 110.00 5500.00 5500.00 5500.00 M-173
Sand cum 8.000 8.000 8.000 955.78 7646.20 7646.20 7646.20 M-004
20 mm steel wire rope kg 15.000 15.000 15.000 55.00 825.00 825.00 825.00 M-178
Add 1 per cent of cost of wire rope for clamps etc. 8.25
c) Machinery
Tractor-trolley hour 2.000 2.000 2.000 820.00 1640.00 1640.00 1640.00 P&M-12001
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 1402.20 1752.76 2104.30
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 1892.98 1928.03 1964.01
Cost for 20 sqm = a+b+c+d+e 20822.74 21208.35 21604.12
Rate per sqm = (a+b+c+d+e)/20 1041.14 1060.42 1080.21
say 1041.00 1060.00 1080.00
8.34 C With HI - DRO cell Sandwich (Patented)
(In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a pre-
determined time, thus absorbing the energy)
Providing and installing a patentend HI - DRO cell system
as a traffic impact attenuators, using plastic tubes 50 cm
dia, 1.2 m in height, 25 mm opening at the top, placed in
three rows, filled with water and tied with a 20 mm steel
wire rope
Unit = sqm
Taking output = 10sqm
a) Labour
Mate day 0.100 0.100 0.100 622.00 62.20 62.20 62.20 L-12
Mazdoor day 2.500 2.500 2.500 560.00 1400.00 1400.00 1400.00 L-13
b) Material
Plastic tubes 50 cm dia,1.2 m high each 40.000 40.000 40.000 40.00 1600.00 1600.00 1600.00 M-138
Cost of water KL 12.000 12.000 12.000 74.54 894.48 894.48 894.48 M-191
20 mm steel wire rope kg 100.000 100.000 100.000 55.00 5500.00 5500.00 5500.00 M-178
Add 1 per cent of cost of wire rope for clamps etc. 55.00
c) Machinery
Tractor-trolley hour 2.000 2.000 2.000 820.00 1640.00 1640.00 1640.00 P&M-12001
Water tanker6 KL capacity hour 2.000 2.000 2.000 904.00 1808.00 1808.00 1808.00 P&M-11003
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 1032.37 1290.47 1555.16
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 1393.71 1419.51 1451.48
Cost for 10 sqm = a+b+c+d+e 15330.76 15614.66 15966.33
Rate per sqm = (a+b+c+d+e)/10 1533.08 1561.47 1596.63
say 1533.00 1561.00 1597.00
Suggest
8.35 Solar Powered Road Marker ( Solar Stud)
ive
Supplying of Solar Raised Pavement Markers made of
polycarbonate molded body with circular shape, solar
powered,LED self illumination in active mode, 360
degree illumination and reflective panels with micro
prismatic lens capable of providing total internal reflection
of the light entering the lens face in passive mode. The
marker shall support a load of 20000 kg tested in
accordance to ASTM D 4280. The marker should be
resistant to dust and water ingress according to IP 65
standards and should withstand temperatures in the
range of 0 C to 70 C. Color of lighting could be provided
in red or yellow (amber) as per requirement and typical
frequency of blinking is 1 Hz. There should be current
losses of less than 20 microamperes at 2.4 V in
sleepcharging mode to enhance the life of the marker
and a full charge should provide for a minimum autonomy
of 50 hours. The height, width and length of the marker
shall not be less than 10 mm x 100 mm x 100 mm. Also,
the surface diameter of the marker shall not be less than
100 mm respectively. The weight of the marker shall not
exceed 0.5 Kilograms. Fixing will be by drilling holes on
the road for the shanks to go inside, without nails and
using epoxy resin based adhesive and complete as
directed by the engineer.
Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 0.040 0.040 622.00 24.88 24.88 24.88 L-12
Mazdoor day 1.000 1.000 1.000 560.00 560.00 560.00 560.00 L-13
b) Material
11500.00 11500.00 11500.00
Poly carbonate or ABS body and shall support a load
of 13.635 Kg tested in accordance to ASTM D 4280
each 50.000 50.000 50.000 230.00 M-062
with height not exceeding 20mm and width/length not
exceeding 130mm
Page 16 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
C Lawn
Providing a lawn planted with grass and its maintenance
The rate per sqm of premix carpet and road marking may
be adopted from chapter 5 & 8 respectively for the
quantities calculated from approved drawings
Suggest
8.39 Policeman Umbrella
ive
Unit = each
Taking output = one number
Earthwork cum
Cement Concrete cum
brick masonry or cum
stone masonry cum
Painting sqm 2.500 2.500 2.500 65.92 164.81 164.81 164.81 Item No. - 8.9
a) Labour
Mate day 0.090 0.090 0.090 622.00 55.98 55.98 55.98 L-12
Mazdoor day 1.000 1.000 1.000 560.00 560.00 560.00 560.00 L-13
Blacksmith (Ist class) day 1.000 1.000 1.000 622.00 622.00 622.00 622.00 L-02
Welder day 0.250 0.250 0.250 622.00 155.50 155.50 155.50 L-02
b) Material
Steel pipe 100 mm dia metre 3.500 3.500 3.500 380.00 1330.00 1330.00 1330.00 M-177
Steel pipe 25 mm dia metre 10.000 10.000 10.000 130.00 1300.00 1300.00 1300.00 M-175
CGI sheets (0.8 mm) kg 8.000 8.000 8.000 60.00 480.00 480.00 480.00 M-082
Add 25 per cent of cost of material for fabrication 1167.07 1167.07 1167.07
Add 2 per cent of cost of material for welding
93.37 93.37 93.37
consumables, J-hooks, washers etc.
c) Machinery
Tractor-trolley hour 0.500 0.500 0.500 820.00 410.00 410.00 410.00 P&M-12001
d) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b+c) (a+b+c) (a+b+c) 507.10 633.87 760.65
e) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c+d) (a+b+c+d) (a+b+c+d) 684.58 697.26 709.94
Rate per policeman umbrella = a+b+c+d+e Say 4642.12 4781.57 4921.02
suggesti
8.40 High Mast Pole Lighting at Interchanges and Flyovers
ve
Page 17 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b) Traffic sign ahead
c) Road ahead closed
d) Men at work
e) Road narrow
f) Single file traffic
g) Right lane diverted
h) Left lane diverted
i) Right lane closed
j) Left lane closed
k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z) Overtaking prohibited
aa) Speed limit
bb) Weight limit
cc) Height and length limit
dd) No stopping or standing
ee) Any other warning or regulatory safety sign as per
site requirement and consistent with IRC:SP:55 and
IRC:67
The rate for traffic signs are already worked out and
given elsewhere in this chapter. The same may be
adopted.
suggesti
8.43 Portable Barricade in Construction Zone
ve
Unit = each
Taking output = one steel portable barricade
a) Labour
Mate day 0.020 0.020 0.020 622.00 12.44 12.44 12.44 L-12
Page 18 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Mazdoor day 0.250 0.250 0.250 560.00 140.00 140.00 140.00 L-13
Painter day 0.500 0.500 0.500 622.00 311.00 311.00 311.00 L-18
Welder day 0.250 0.250 0.250 622.00 155.50 155.50 155.50 L-02
b) Material
Angle iron 45 x 45 x 5 mm kg 25.000 25.000 25.000 65.00 1625.00 1625.00 1625.00 M-181 /1000
65.00 975.00 975.00 975.00 M-181 /1000
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg 15.000 15.000 15.000
Paint litre 0.500 0.500 0.500 150.00 75.00 75.00 75.00 M-130
Add 2 per cent of cost of steel for welding consumables,
52.00 52.00 52.00
nuts & bolts and drilling holes
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 267.68 334.59 401.51
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 289.09 368.05 449.69
Rate per barricade = a+b+c+d 3902.70 4048.59 4197.15
say 3903.00 4049.00 4197.00
suggesti
8.44 Permanent Type Barricade in Construction Zone
ve
A With steel components
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 0.050 0.050 622.00 31.10 31.10 31.10 L-12
Mazdoor day 0.300 0.300 0.300 560.00 168.00 168.00 168.00 L-13
Painter day 0.600 0.600 0.600 622.00 373.20 373.20 373.20 L-18
Welder day 0.300 0.300 0.300 622.00 186.60 186.60 186.60 L-02
b) Material
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos. kg 15.000 15.000 15.000 65.00 975.00 975.00 975.00 M-181 /1000
MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m 65.00 3250.00 3250.00 3250.00 M-181 /1000
kg 50.000 50.000 50.000
length
Paint litre 1.000 1.000 1.000 150.00 150.00 150.00 150.00 M-130
Add 1 per cent of cost of steel for welding consumables,
84.50 84.50 84.50
nuts & bolts and drilling holes
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 417.47 521.84 626.21
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 563.59 574.02 584.46
Rate per barricade = a+b+c+d 6199.46 6314.26 6429.07
say 6199.00 6314.00 6429.00
8.44 B With wooden components
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 0.050 0.050 622.00 31.10 31.10 31.10 L-12
Mazdoor day 0.300 0.300 0.300 560.00 168.00 168.00 168.00 L-13
Painter day 0.600 0.600 0.600 622.00 373.20 373.20 373.20 L-18
Carpenter day 0.600 0.600 0.600 622.00 373.20 373.20 373.20 L-04
b) Material
Timber cum 0.180 0.180 0.180 650.00 117.00 117.00 117.00 M-187
Add 1 per cent of cost of timber for nuts & bolts, nails,
1.17 1.17 1.17
etc.
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 85.09 106.37 127.64
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 114.88 117.00 119.13
Rate per barricade = a+b+c+d 1263.64 1287.04 1310.44
say 1264.00 1287.00 1310.00
8.44 C With bricks
Construction of a permanent type barricade made with
brick work in mud mortar, 1.5 m high, 4 m long, 600 mm
thick, plastered with cement mortar 1:6, painted with
yellow and white strips
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.240 0.240 0.240 622.00 149.28 149.28 149.28 L-12
Mazdoor day 3.000 3.000 3.000 560.00 1680.00 1680.00 1680.00 L-13
Painter day 1.000 1.000 1.000 622.00 622.00 622.00 622.00 L-18
Mason day 2.000 2.000 2.000 622.00 1244.00 1244.00 1244.00 L-11
b) Material
Brick each 1800.000 1800.000 1800.000 5.00 9000.00 9000.00 9000.00 M-079
Cement kg 22.000 22.000 22.000 6.50 143.00 143.00 143.00 M-081 /1000
Sand cum 0.090 0.090 0.090 955.78 86.02 86.02 86.02 M-005
Paint litre 1.250 1.250 1.250 150.00 187.50 187.50 187.50 M-130
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1048.94 1311.18 1573.42
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 1416.07 1442.30 1468.52
Rate per barricade = a+b+c+d 15576.82 15865.28 16153.74
say 15577.00 15865.00 16154.00
suggesti
8.45 Drum Delineator in Construction Zone
ve
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.020 0.020 0.020 622.00 12.44 12.44 12.44 L-12
Mazdoor day 0.250 0.250 0.250 560.00 140.00 140.00 140.00 L-13
Painter day 0.250 0.250 0.250 622.00 155.50 155.50 155.50 L-18
b) Material
Steel drum 300 mm dia 1.2 m high/empty bitumen 110.00 110.00 110.00 110.00 M-173
each 1.000 1.000 1.000
drum
Page 19 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Paint litre 0.500 0.500 0.500 150.00 75.00 75.00 75.00 M-130
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 39.44 49.29 59.15
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 53.24 54.22 55.21
Rate per drum delineator = a+b+c+d 585.61 596.46 607.30
say 586.00 596.00 607.00
suggesti
8.46 Water Filled Barricades Work zone sheeting
ve
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.020 0.020 0.020 622.00 12.44 12.44 12.44 L-12
Mazdoor day 0.250 0.250 0.250 560.00 140.00 140.00 140.00 L-13
b) Material
Water Filled Barricades Work zone sheeting each 1.000 1.000 1.000 3200.00 3200.00 3200.00 3200.00 M-238
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 268.20 335.24 402.29
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 362.06 368.77 375.47
Rate per drum delineator = a+b+c+d 3982.70 4056.45 4130.21
say 3983.00 4056.00 4130.00
suggesti
8.47 Tubular Marker/ Spring post 450 mm
ve
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.020 0.020 0.020 622.00 12.44 12.44 12.44 L-12
Mazdoor day 0.250 0.250 0.250 560.00 140.00 140.00 140.00 L-13
b) Material
Tubular Marker/ Spring post 450 mm each 1.000 1.000 1.000 490.00 490.00 490.00 490.00 M-237
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 51.40 64.24 77.09
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 69.38 70.67 71.95
Rate per drum delineator = a+b+c+d 763.22 777.35 791.49
say 763.00 777.00 791.00
suggesti
8.48 Tubular Marker/ Spring post 700 mm
ve
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.020 0.020 0.020 622.00 12.44 12.44 12.44 L-12
Mazdoor day 0.250 0.250 0.250 560.00 140.00 140.00 140.00 L-13
b) Material
Tubular Marker/ Spring post 700 mm each 1.000 1.000 1.000 610.00 610.00 610.00 610.00 M-236
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 61.00 76.24 91.49
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 82.34 83.87 85.39
Rate per drum delineator = a+b+c+d 905.78 922.55 939.33
say 906.00 923.00 939.00
suggesti
8.49 Flagman
ve
Unit = each
Taking output = one flagman
a) Labour
Mate day 0.040 0.040 0.040 622.00 24.88 24.88 24.88 L-12
Mazdoor day 1.000 1.000 1.000 560.00 560.00 560.00 560.00 L-13
b) Material
Flag of red color cloth 600 x 600 mm each 1.000 1.000 1.000 30.00 30.00 30.00 30.00 M-099
Wooden staff for fastening of flag 25 mm dia, one m 12.00 12.00 12.00 12.00 M-198
each 1.000 1.000 1.000
long
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 50.15 62.69 75.23
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 67.70 68.96 70.21
Rate per flagman = a+b+c+d 744.73 758.52 772.32
say 745.00 759.00 772.00
Page 20 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Video Management Software with atleast 150 VMS Lic. Nos. 1.000 1.000 1.00 780000.00 780000.00 780000.00 780000 M-260
Facility Monitoring System Controller Software Nos. 1.000 1.000 1.00 440000.00 440000.00 440000.00 440000 M-261
Server & Database license Nos. 1.000 1.000 1.00 800000.00 800000.00 800000.00 800000 M-262
Antivirus license Nos. 1.000 1.000 1.00 160000.00 160000.00 160000.00 160000 M-263
PTZ Camera (including CCTV Controller) Set 1.000 1.000 1.00 96000.00 96000.00 96000.00 96000 M-264
Solar System with UPS, battery & 12m Pole & Cabinet Set 1.000 1.000 1.00 68000.00 68000.00 68000.00 68000 M-265
D1 VIDS Camera (including Image Processing unit) Set 1.000 1.000 1.00 132000.00 132000.00 132000.00 132000 M-266
D3 Cabinet Nos. 1.000 1.000 1.00 22800.00 22800.00 22800.00 22800 M-268
D4 12 m Pole (including manufacturing and galvanizing) Nos. 1.000 1.000 1.00 20160.00 20160.00 20160.00 20160 M-269
D5 Solar System with UPS & batteries Set 1.000 1.000 1.00 18000.00 18000.00 18000.00 18000 M-270
E3 Solar System with UPS, batteries Set 1.000 1.000 1.00 74880.00 74880.00 74880.00 74880 M-272
VMS (Variable Message Sign - M type) Nos. 1.000 1.000 1.00 920000.00 920000.00 920000.00 920000 M-273
Gantry (including manufacturing and galvanizing) Nos. 1.000 1.000 1.00 760000.00 760000.00 760000.00 760000 M-274
Uninterruptible Power Supply (UPS) For TMC (30 KVA) Set 1.000 1.000 1.00 1160000.00 1160000.00 1160000.00 1160000 M-277
Power Distribution Board (Essential & Critical Supply) Set 1.000 1.000 1.00 44000.00 44000.00 44000.00 44000 M-278
MOS sensor Equipment (including MOS Controller) Set 1.000 1.000 1.00 848000.00 848000.00 848000.00 848000.00 M-279
Cabinet Nos. 1.000 1.000 1.00 22800.00 22800.00 22800.00 22800.00 M-280
Pole Nos. 1.000 1.000 1.00 25600.00 25600.00 25600.00 25600.00 M-281
Steel fence for protection Set 1.000 1.000 1.00 60000.00 60000.00 60000.00 60000.00 M-282
Page 21 of 253
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
24 Core Armoured OFC + all accessories Km 1.000 1.000 1.00 384.00 384.00 384.00 384.00 M-283
Page 22 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
9.01 304 Excavation for Structures
Earth work in excavation of foundation of structures as
per drawing and technical specification, including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with
approved material.
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 0.14 0.14 622.00 87.08 87.08 87.08 L-12
Mazdoor day 3.50 3.50 3.50 560.00 1960.00 1960.00 1960.00 L-13
Per Cum Basic Cost of Labour, Material & Machinery 204.71 204.71 204.71
(a+b+c)
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 409.42 409.42 409.42
Page 1 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Cost for 300 cum = a+b+c+d 25053.47 27893.52 49306.46
Rate per cum = (a+b+c+d)/300 83.51 92.98 164.35
say 84.00 93.00 164.00
9.1 B (iii) Mechanical Means (Depth above 6 m)
Unit = cum
Taking output = 270 cum
a) Labour
Mate day 0.320 0.320 0.320 622.00 199.04 199.04 199.04 L-12
Mazdoor day 8.000 8.000 8.000 560.00 4480.00 4480.00 4480.00 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.732 1748.00 8271.79 P&M-3003
(ii) 1.1 cum bucket capacity hour 5.450 1748.00 9526.24 P&M-3004
(iii) 0.9 cum bucket capacity hour 7.619 2570.00 19580.95 P&M-3005
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.839 1748.00 4963.07 P&M-3003
(ii) 1.1 cum bucket capacity hour 3.270 1748.00 5715.74 P&M-3004
(iii) 0.9 cum bucket capacity hour 4.571 2570.00 11748.57 P&M-3005
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 162.000 6.83 1106.46 P&M-72002
(ii) 14 cum capacity t-km 162.000 7.77 1258.74 P&M-73002
(iii) 10 cum capacity t-km 162.000 9.62 1558.44 P&M-74002
c) Overhead charges @ 20% on @ 20% on @ 20% on 3804.07 4235.95 7513.40
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 2282.44 2541.57 4508.04
(a+b+c) (a+b+c) (a+b+c)
Cost for 270 cum = a+b+c+d 25106.87 27957.29 49588.45
Rate per cum = (a+b+c+d)/270 92.99 103.55 183.66
say 93.00 104.00 184.00
9.1 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 0.20 0.20 622.00 124.40 124.40 124.40 L-12
Mazdoor day 5.00 5.00 5.00 560.00 2800.00 2800.00 2800.00 L-13
b) Overhead charges @ 8% on (a) 584.88 584.88 584.88
c) Contractor's profit @ 10% on (a+b) 350.93 350.93 350.93
Cost for 10 cum = a+b+c 3860.21 3860.21 3860.21
Rate per cum = (a+b+c)/10 386.02 386.02 386.02
say 386.00 386.00 386.00
Note Cost of dewatering upto 10 per cent of labour cost
may be added, where required. Assessment for
dewatering shall be made as per site conditions..
B Mechanical Means
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 0.210 0.210 0.210 622.00 130.62 130.62 130.62 L-12
Mazdoor day 3.000 3.000 3.000 560.00 1680.00 1680.00 1680.00 L-13
Driller day 2.000 2.000 2.000 592.00 1184.00 1184.00 1184.00 L-06
Page 2 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Blaster day 0.250 0.250 0.250 560.00 140.00 140.00 140.00 L-03
b) Machinery
Air compressor hour 6.000 6.000 6.000 550.00 3300.00 3300.00 3300.00 P&M-15001
Jack Hammer for drilling holes (@ 4.5 m per hour) hour 24.000 24.000 24.000 11.00 264.00 264.00 264.00 P&M-45001
Jack Hammer (consider 5% of the volume for hour 1.024 1.024 1.024 206.00 210.94 210.94 210.94 P&M-4001
dressing)
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 1.024 1748.00 1789.95 P&M-3003
(ii) 1.1 cum bucket capacity hour 1.024 1748.00 1789.95 P&M-3004
(iii) 0.9 cum bucket capacity hour 1.024 2570.00 2631.68 P&M-3005
For loading
(i) 1.2 cum bucket capacity hour 2.094 1748.00 3660.01 P&M-3003
(ii) 1.1 cum bucket capacity hour 2.411 1748.00 4215.07 P&M-3004
(iii) 0.9 cum bucket capacity hour 3.371 2570.00 8663.97 P&M-3005
Tipper
For transportation considering lead @ 1 km
(i) 18 cum capacity t-km 180.000 6.83 1229.40 P&M-72002
(ii) 14 cum capacity t-km 180.000 7.77 1398.60 P&M-73002
(iii) 10 cum capacity t-km 180.000 9.62 1731.60 P&M-74002
For loading & unloading time
(i) 18 cum capacity hour 2.094 2621.00 5487.92 P&M-6001
(ii) 14 cum capacity hour 2.411 2331.00 5620.89 P&M-6002
(iii) 10 cum capacity hour 3.371 2077.00 7001.97 P&M-6003
c) Materials
Small dia.Explosive at 0.40 kg / cum for 120 cum kg 48.000 48.000 48.000 55.00 2640.00 2640.00 2640.00 M-215
( 120 x 0.40 )
Explosive at 0.20 kg / cum for secondary blast @
5%of the total volume ( 120 x 0.2x5% )
Electric detonators at 1 per hole for main blast no 69.000 69.000 69.000 12.00 828.00 828.00 828.00 M-217
holes (21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 7.000 7.000 7.000 55.00 385.00 385.00 385.00 M-216
holes( required for 5% of the total quantity @ 0.6 m
per hole for I cum )
Detonating fuse coil m 213.000 213.000 213.000 105.00 22365.00 22365.00 22365.00 M-218
d) Overhead charges @ 20% on @ 20% on @ 20% on 9058.97 9230.42 10631.36
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 5435.38 5538.25 6378.81
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 cum = a+b+c+d+e 59789.20 60920.74 70166.95
Rate per cum = (a+b+c+d+e)/120 498.24 507.67 584.72
say 498.00 508.00 585.00
Page 3 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
(iii) 10 cum capacity t-km 390.000 9.62 3751.80 P&M-74002
For loading & unloading time
(i) 18 cum capacity hour 8.506 2621.00 22294.68 P&M-6001
(ii) 14 cum capacity hour 9.796 2331.00 22834.88 P&M-6002
(iii) 10 cum capacity hour 13.695 2077.00 28445.50 P&M-6003
c) Material
Selected earth for refilling cum 156.000 156.000 156.000 75.00 11700.00 11700.00 11700.00 M-164
d) Overhead charges @ 20% on @ 20% on @ 20% on 10422.41 11054.75 15935.91
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 6253.45 6632.85 9561.55
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 260 cum = a+b+c+d 68787.90 72961.38 105177.00
Rate per cum = (a+b+c+d)/260 264.57 280.62 404.53
say 265.00 281.00 405.00
9.1 VI Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.12 0.12 0.12 622.00 74.64 74.64 74.64 L-12
Mazdoor for dressing sides, bottom and backfilling day 3.00 3.00 3.00 560.00 1680.00 1680.00 1680.00 L-13
b) Machinery
Tractor-trolley for transportation hour 2.00 2.00 2.00 820.00 1640.00 1640.00 1640.00 P&M-12001
c) Overhead charges @ 20% on @ 20% on @ 20% on 678.93 678.93 678.93
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 407.36 407.36 407.36
(a+b+c) (a+b+c) (a+b+c)
Cost for 6 cum = a+b+c+d 4480.92 4480.92 4480.92
Rate per cum = (a+b+c+d)/6 746.82 746.82 746.82
say 747.00 747.00 747.00
9.2 304 Filling Annular Space Around Footing in Rock
Unit = cum
Taking out put = 1 cum
PCC-15 nominal mix. Rate may be taken as per item
9.14.
9.3 304 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mazdoor day 1.00 1.00 1.00 560.00 560.00 560.00 560.00 L-13
b) Machinery
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading @ 30 mins per trip )
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.32 0.32 0.32 622.00 199.04 199.04 199.04 L-12
Mason day 1.00 1.00 1.00 622.00 622.00 622.00 622.00 L-11
Mazdoor day 7.00 7.00 7.00 560.00 3920.00 3920.00 3920.00 L-13
b) Material
Plain cement concrete 1:3:6 nominal mix using cum 15.00 15.00 15.00 3260.10 48901.46 48901.46 48901.46 Sub-Analysis of
batching plant (Rate as sub-analysis) Concrete - 19.02
Water KL 3.24 3.24 3.24 74.54 241.51 241.51 241.51 M-191
c) Machinery
Plate Compactor hour 1.00 1.00 1.00 528.00 528.00 528.00 528.00 P&M-46001
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading @ 30 mins per trip )
Page 4 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
9.6 Sub- (A) Cement Mortar 1:3 (1 cement : 3 sand)
analysis
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 0.51 0.51 6500.00 3315.00 3315.00 3315.00 M-081
Sand cum 1.05 1.05 1.05 955.78 1003.56 1003.56 1003.56 M-005
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mazdoor day 0.90 0.90 0.90 560.00 504.00 504.00 504.00 L-13
Total Material and Labour = (a+b) say 4847.00 4847.00 4847.00
Sub- (B) Cement Mortar1:2 (1cement :2 sand)
analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.67 0.67 0.67 6500.00 4368.00 4368.00 4368.00 M-081
Sand cum 0.93 0.93 0.93 955.78 888.87 888.87 888.87 M-005
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mazdoor day 0.90 0.90 0.90 560.00 504.00 504.00 504.00 L-13
Total Material and Labour = (a+b) say 5786.00 5786.00 5786.00
Sub- (C) Cement Mortar1:4 (1cement :4 sand)
analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 0.40 0.40 6500.00 2620.80 2620.80 2620.80 M-081
Sand cum 1.12 1.12 1.12 955.78 1070.47 1070.47 1070.47 M-005
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mazdoor day 0.90 0.90 0.90 560.00 504.00 504.00 504.00 L-13
Total Material and Labour = (a+b) say 4220.00 4220.00 4220.00
Sub- (D) Cement Mortar1:6 (1cement :6 sand)
analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.29 0.29 0.29 6500.00 1872.00 1872.00 1872.00 M-081
Sand cum 1.34 1.34 1.34 955.78 1278.01 1278.01 1278.01 M-005
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mazdoor day 0.90 0.90 0.90 560.00 504.00 504.00 504.00 L-13
Total Material and Labour = (a+b) say 3679.00 3679.00 3679.00
9.7 1400 Stone Masonry Work in Cement Mortar 1:3 in
Foundation complete as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
1405.4 (A) Square Rubble Coursed Rubble Masonry (first sort)
a) Material
Stone cum 5.50 5.50 5.50 470.14 2585.74 2585.74 2585.74 M-170
Through and bond stone each 35.00 35.00 35.00 25.00 875.00 875.00 875.00 M-184
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as sub-analysis) cum 1.50 1.50 1.50 4888.87 7333.31 7333.31 7333.31 Sub-Analysis of
Concrete - 19.01
(A)
b) Labour
Mate day 0.66 0.66 0.66 622.00 410.52 410.52 410.52 L-12
Mason day 7.50 7.50 7.50 622.00 4665.00 4665.00 4665.00 L-11
Mazdoor day 9.00 9.00 9.00 560.00 5040.00 5040.00 5040.00 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on 4181.91 4181.91 4181.91
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 2509.15 2509.15 2509.15
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 27600.63 27600.63 27600.63
Rate per cum (a+b+c+d)/5 5520.13 5520.13 5520.13
say 5520.00 5520.00 5520.00
1405.3 (B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 5.50 5.50 470.14 2585.74 2585.74 2585.74 M-147
Through and bond stone each 35.00 35.00 35.00 25.00 875.00 875.00 875.00 M-184
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in sub-analysis) cum 1.55 1.55 1.55 4888.87 7577.75 7577.75 7577.75 Sub-Analysis of
Concrete - 19.01
(A)
b) Labour
Mate day 0.62 0.62 0.62 622.00 385.64 385.64 385.64 L-12
Mason day 6.00 6.00 6.00 622.00 3732.00 3732.00 3732.00 L-11
Mazdoor day 9.00 9.00 9.00 560.00 5040.00 5040.00 5040.00 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on 4039.23 4039.23 4039.23
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 2423.54 2423.54 2423.54
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 26658.90 26658.90 26658.90
Rate per cum (a+b+c+d)/5 5331.78 5331.78 5331.78
say 5332.00 5332.00 5332.00
Note The labour already considered in cement mortar has
been taken into account while proposing labour for
masonry works.
9.8 1300 & Brick masonry work in 1:3 in sub-structure complete
2200 excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 500.00 500.00 5.00 2500.00 2500.00 2500.00 M-079
Cement mortar 1:3 (Rate as from sub-analysis) cum 0.24 0.24 0.24 4888.87 1173.33 1173.33 1173.33 Sub-Analysis of
Concrete - 19.01
(A)
Water for curing KL 0.48 0.48 0.48 74.54 36.00 36.00 36.00 M-191
b) Labour
Mate day 0.06 0.06 0.06 622.00 37.32 37.32 37.32 L-12
Mason day 0.80 0.80 0.80 622.00 497.60 497.60 497.60 L-11
Mazdoor day 0.80 0.80 0.80 560.00 448.00 448.00 448.00 L-13
Add for scaffolding @ 5 per cent of cost of material 234.61 234.61 234.61
and labour
c) Machinery
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading @ 30 mins per trip )
Page 5 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on 592.32 592.50 593.16
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum (a+b+c+d+e) 6515.48 6517.48 6524.81
say 6515.00 6517.00 6525.00
9.9 1300 & Pointing with cement mortar (1:3 ) on brick work in
2200 substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as from sub-analysis) cum 0.03 0.03 0.03 4888.87 146.67 146.67 146.67 Sub-Analysis of
Concrete - 19.01
(A)
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mason day 0.50 0.50 0.50 622.00 311.00 311.00 311.00 L-11
Mazdoor day 0.50 0.50 0.50 560.00 280.00 280.00 280.00 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on 152.51 152.51 152.51
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 91.51 91.51 91.51
(a+b+c) (a+b+c) (a+b+c)
Rate per 10 sqm (a+b+c+d) 1006.56 1006.56 1006.56
say 1007.00 1007.00 1007.00
Note Scaffolding is already included in item 13.1
9.10 1300 & Plastering with cement mortar (1:3 ) on brick work in
2200 sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as from sub-analysis) cum 0.144 0.144 0.144 4888.87 704.00 704.00 704.00 Sub-Analysis of
Concrete - 19.01
(A)
Water for curing KL 0.14 0.14 0.14 74.54 10.37 10.37 10.37 M-191
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mason day 0.50 0.50 0.50 622.00 311.00 311.00 311.00 L-11
Mazdoor day 0.50 0.50 0.50 560.00 280.00 280.00 280.00 L-13
c) Machinery
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading @ 30 mins per trip )
Page 6 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 1.11 1.11 470.14 521.85 521.85 521.85 M-170
Through and bond stone each 7.00 7.00 7.00 25.00 175.00 175.00 175.00 M-184
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 0.33 0.33 4888.87 1613.33 1613.33 1613.33 Sub-Analysis of
Concrete - 19.01
(A)
Water for curing KL 0.97 0.97 0.97 74.54 72.01 72.01 72.01 M-191
b) Labour for masonry work
Mate day 0.20 0.20 0.20 622.00 124.40 124.40 124.40 L-12
Mason day 2.50 2.50 2.50 622.00 1555.00 1555.00 1555.00 L-11
Mazdoor day 2.50 2.50 2.50 560.00 1400.00 1400.00 1400.00 L-13
Add for scaffolding @ 5 per cent of cost of a) 273.08 273.08 273.08
Material and b) Labour
c) Machinery
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading @ 30 mins per trip )
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
A 1000 mm dia
a) Labour
Mate day 0.100 0.100 0.100 622.00 62.20 62.20 62.20 L-12
Mason day 0.500 0.500 0.500 622.00 311.00 311.00 311.00 L-11
Mazdoor day 2.000 2.000 2.000 560.00 1120.00 1120.00 1120.00 L-13
b) Material
Sand at site cum 0.070 0.070 0.070 955.78 66.90 66.90 66.90 M-005
Cement at site tonne 0.050 0.050 0.050 6500.00 325.00 325.00 325.00 M-081
RCC pipe NP-4 /prestressed concrete pipe metre 12.500 12.500 12.500 7500.00 93750.00 93750.00 93750.00 M-148
including collar at site
Granular material passing 5.6 mm sieve for cum 4.500 4.500 4.500 725.78 3265.99 3265.99 3265.99 M-009
bedding
c) Machinery
Light Crane 3 tonnes capacity for placing of Hume hour 2.08 2.08 2.08 966.00 2012.50 2012.50 2012.50 P&M-63001
pipe
d) Overhead charges @ 20% on @ 20% on @ 20% on 20182.72 20182.72 20182.72
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 12109.63 12109.63 12109.63
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 12.5 metres = a+b+c+d 133205.94 133205.94 133205.94
Rate per metre = (a+b+c+d)/12.5 10656.48 10656.48 10656.48
say 10656.00 10656.00 10656.00
Note 1. In case of cement craddle bedding, quantity of PCC
M15 is to be calculated as per design and priced
separately and added .
2. The rate analysis does not include excavation,
cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to
be calculated as per approved design and drawings
and priced separately on rates available under
respective sections
Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length
each in two rows.)
A 1000 mm dia
a) Labour
Page 7 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Mate day 0.200 0.200 0.200 622.00 124.40 124.40 124.40 L-12
Mason day 1.000 1.000 1.000 622.00 622.00 622.00 622.00 L-11
Mazdoor day 4.000 4.000 4.000 560.00 2240.00 2240.00 2240.00 L-13
b) Material
Sand at site cum 0.140 0.140 0.140 955.78 133.81 133.81 133.81 M-005
Cement at site tonne 0.100 0.100 0.100 6500.00 650.00 650.00 650.00 M-081
RCC pipe NP-4/prestressed concrete pipe metre 25.000 25.000 25.000 7500.00 187500.00 187500.00 187500.00 M-148
including collar at site
Granular material passing 5.6 mm sieve for cum 12.500 12.500 12.500 725.78 9072.19 9072.19 9072.19 M-009
bedding
c) Machinery
Light Crane 3 tonnes capacity for handling Hume hour 4.17 4.17 4.17 966.00 4025.00 4025.00 4025.00 P&M-63001
pipe
d) Overhead charges @ 20% on @ 20% on @ 20% on 40873.48 40873.48 40873.48
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 24524.09 24524.09 24524.09
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 12.5 metres = a+b+c+d 269764.96 269764.96 269764.96
Rate per metre = (a+b+c+d)/12.5 21581.20 21581.20 21581.20
Note 1. In case of cement craddle bedding, quantity of PCC say 21581.00 21581.00 21581.00
M15 is to be calculated as per design and priced
separately and added .
2. The rate analysis does not include excavation,
cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to
be calculated as per approved design and drawings
and priced separately on rates available under
respective sections
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) cum 15.00 15.00 15.00 3260.59 48908.86 48908.86 48908.86 Sub-Analysis of
Concrete - 19.03
Water for curing Kl 7.88 7.88 7.88 74.54 587.00 587.00 587.00 M-191
b) Labour
For pouring and placing
Mate day 0.38 0.38 0.38 622.00 236.36 236.36 236.36 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 8.00 8.00 8.00 560.00 4480.00 4480.00 4480.00 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 12.22 916.50 916.50 916.50 P&M-76001
For unloading hour 0.83 0.83 0.83 2198.00 1831.67 1831.67 1831.67 P&M-34001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 8 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
(ii) 12 KL capacity hour 0.58 1187.00 692.42 P&M-11002
(iii) 6 KL capacity hour 1.17 904.00 1054.67 P&M-11003
Per Cum Basic Cost of Labour, Material & Machinery 3900.00 3906.00 3930.00
(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. 5848.71 5858.58 5894.81
cost of material, labour and machinery
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.83 0.83 0.83 2198.00 1831.67 1831.67 1831.67 P&M-34001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 9 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
d) Formwork @ 10 per cent on cost of concrete i.e. 12297.52 12317.26 12389.71
cost of material, labour and machinery
For unloading hour 0.83 0.83 0.83 2198.00 1831.67 1831.67 1831.67 P&M-34001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.83 0.83 0.83 2198.00 1831.67 1831.67 1831.67 P&M-34001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 10 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
f) Contractor's profit @ 10% on @ 10% on @ 10% on 9333.93 9346.96 9394.78
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.83 0.83 0.83 2198.00 1831.67 1831.67 1831.67 P&M-34001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 11 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
say 6496.00 6506.00 6541.00
Case II PCC Grade M30 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) cum 15.00 15.00 15.00 4110.93 61663.90 61663.90 61663.90 Sub-Analysis of
Concrete - 19.08
Water for curing Kl 7.88 7.88 7.88 74.54 587.00 587.00 587.00 M-191
b) Labour
For pouring and placing
Mate day 0.38 0.38 0.38 622.00 236.36 236.36 236.36 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 8.00 8.00 8.00 560.00 4480.00 4480.00 4480.00 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 12.22 916.50 916.50 916.50 P&M-76001
For unloading hour 0.83 0.83 0.83 2198.00 1831.67 1831.67 1831.67 P&M-34001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.83 0.83 0.83 2198.00 1831.67 1831.67 1831.67 P&M-34001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 12 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.00 30.00 30.00 4267.05 128011.61 128011.61 128011.61 Sub-Analysis of
Concrete - 19.11
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.83 0.83 0.83 2198.00 1831.67 1831.67 1831.67 P&M-34001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 13 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 9.00 9.00 9.00 560.00 5040.00 5040.00 5040.00 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L 37.5 x L 37.5 x L 12.22 916.50 916.50 916.50 P&M-76001
For unloading hour 0.83 0.83 0.83 2198.00 1831.67 1831.67 1831.67 P&M-34001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 14 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L 75 x L 75 x L 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and tonne 8.40 8.40 8.40 62000.00 520800.00 520800.00 520800.00 M-083
wastage
Binding wire Kg 48.00 48.00 48.00 67.00 3216.00 3216.00 3216.00 M-072
b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate day 0.16 0.16 0.16 622.00 99.52 99.52 99.52 L-12
Blacksmith day 1.00 1.00 1.00 622.00 622.00 622.00 622.00 L-02
Mazdoor day 3.00 3.00 3.00 560.00 1680.00 1680.00 1680.00 L-13
Page 15 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
c) Machinery
Cutting Machine hour 5.33 5.33 5.33 468.00 2496.00 2496.00 2496.00 P&M-43001
Bending Machine hour 5.33 5.33 5.33 468.00 2496.00 2496.00 2496.00 P&M-43001
Electric generator 15 KVA hour 5.33 5.33 5.33 374.00 1994.67 1994.67 1994.67 P&M-22009
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8xL 6.83 109.28 P&M-72002
(ii) 14 cum capacity t.km 8xL 7.77 124.32 P&M-73002
(iii) 10 cum capacity t.km 8xL 9.62 153.92 P&M-74002
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.00 2621.00 2621.00 P&M-6001
(ii) 14 cum capacity hour 1.28 2331.00 2983.68 P&M-6002
(iii) 10 cum capacity hour 1.78 2077.00 3692.44 P&M-6003
Light weight Crane
At cutting bending yard hour 2.00 2.00 2.00 966.00 1932.00 1932.00 1932.00 P&M-63001
At site hour 2.00 2.00 2.00 966.00 1932.00 1932.00 1932.00 P&M-63001
Per MT Basic Cost of Labour, Material & Machinery 67500.00 67548.00 67640.00
(a+b+c)
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per metre 31.50 31.50 31.50 350.00 11025.00 11025.00 11025.00 M-056
cent )
Average length of weep hole is taken as one metre for
the purpose of estimating.
MS clamp each. 30.00 30.00 30.00 65.00 1950.00 1950.00 1950.00 M-122
collar for AC pipe (average) taking 10% of above each. 10.00 10.00 10.00 35.00 350.00 350.00 350.00 M-056/10
pipe rate
Cement mortar 1:3 (Rate as from sub-analysis) cum 0.05 0.05 0.05 4888.87 244.44 244.44 244.44 Sub-Analysis of
Concrete - 19.01
(A)
b) Labour
Mate day 0.03 0.03 0.03 622.00 18.66 18.66 18.66 L-12
Mason day 0.50 0.50 0.50 622.00 311.00 311.00 311.00 L-11
Mazdoor day 0.25 0.25 0.25 560.00 140.00 140.00 140.00 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on 2779.82 2779.82 2779.82
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1681.89 1681.89 1681.89
(a+b+c) (a+b+c) (a+b+c)
Cost for 30 m = a+b+c+d 18500.82 18500.82 18500.82
Rate per m (a+b+c+d)/30 616.69 616.69 616.69
say 617.00 617.00 617.00
Note 1. In case of stone masonry, the size of the weep hole
shall be 150 mm x 80 mm or circular with 150 mm
diameter.
2. For structure in stone masonry, the weep holes shall
be deemed to be included in the item of stone masonry
work and shall not be paid separately.
9.18 2700 PCC M15 Grade leveling course below approach slab
complete as per drawing and Technical specification
Unit = 1 cum
Taking output = 1 cum
a) Material
Case I PCC Grade M15 using batching plant & Concrete
pump
a) Material
Concrete, Rate as per item No. 9.14 (A) excluding cum 1.00 3624.00 3624.00 Item No - 9.14 (A),
formworks Case-I
Concrete, Rate as per item No. 9.14 (A) excluding 1.00 3631.00 3631.00 Item No - 9.14 (A),
formworks Case-I
Concrete, Rate as per item No. 9.14 (A) excluding 1.00 3655.00 3655.00 Item No - 9.14 (A),
formworks Case-I
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 724.80 726.20 731.00
b) Material
Case II PCC Grade M15 using batching plant & manual placing
Concrete, Rate as per item No. 9.14 (A) excluding cum 1.00 3900.00 3900.00 Item No - 9.14 (A),
formworks Case-II
Concrete, Rate as per item No. 9.14 (A) excluding 1.00 3906.00 3906.00 Item No - 9.14 (A),
formworks Case-II
Concrete, Rate as per item No. 9.14 (A) excluding 1.00 3930.00 3930.00 Item No - 9.14 (A),
formworks Case-II
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 780.00 781.20 786.00
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of cum 1.00 1.00 1.00 4505.00 4505.00 4505.00 4505.00
concrete in item 9.15 (B)by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)
Added at the rate of 2 per cent of cost 90.10 90.10 90.10
HYSD bar reinforcement Rate as per item No 9.16 tonne 0.05 0.05 0.05 67500.00 3375.00 3375.00 3375.00
(Excluding OH & CP)
c) Overhead charges @ 20% on @ 20% on @ 20% on 1594.02 1594.02 1594.02
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 956.41 956.41 956.41
(a+b+c) (a+b+c) (a+b+c)
Rate per cum (a+b+c) 10520.53 10520.53 10520.53
Page 16 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
say 10521.00 10521.00 10521.00
Note The grade of reinforced cement concrete may be
adopted as M30 for severe conditions and M25 for
moderate conditions.
9.20 2705 Drainage Spouts complete as per drawing and
Technical specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per Kg 4.00 4.00 4.00 75.00 300.00 300.00 300.00 M-088/1000
cent wastage
GI pipe 100mm dia metre 6.00 6.00 6.00 350.00 2100.00 2100.00 2100.00 M-056
GI bolt 10 mm Dia each 6.00 6.00 6.00 25.00 150.00 150.00 150.00 M-109
Galvanised MS flat clamp each 2.00 2.00 2.00 10.00 20.00 20.00 20.00 M-101
b) Labour
For fabrication
Mate day 0.02 0.02 0.02 622.00 12.44 12.44 12.44 L-12
Skilled (Blacksmith, welder etc.) day 0.02 0.02 0.02 622.00 12.44 12.44 12.44 L-02
Mazdoor day 0.02 0.02 0.02 560.00 11.20 11.20 11.20 L-13
For fixing in position
Mate day 0.01 0.01 0.01 622.00 6.22 6.22 6.22 L-12
Mason day 0.01 0.01 0.01 622.00 6.22 6.22 6.22 L-11
Mazdoor day 0.20 0.20 0.20 560.00 112.00 112.00 112.00 L-13
Add @ 5 per cent of cost of material and labour for 136.53 136.53 136.53
electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc.
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of cum 1.00 1.00 1.00 4545.00 4545.00 4545.00 4545.00 Item No - 9.15 (C)
concrete in Item 9.15 (C ) excluding formwork
HYSD bar reinforcement Rate as per item No 9.16 tonne 0.075 0.075 0.075 67500.00 5062.50 5062.50 5062.50 Item No - 9.16
(Excluding OH & CP)
b) Labour
Mazdoor for cleaning deck slab concrete surface. day 0.15 0.15 0.15 560.00 84.00 84.00 84.00 L-13
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.49 0.49 0.49 622.00 304.78 304.78 304.78 L-12
Mazdoor day 11.00 11.00 11.00 560.00 6160.00 6160.00 6160.00 L-13
Mazdoor (Skilled) day 1.25 1.25 1.25 592.00 740.00 740.00 740.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 0.06 0.06 951.00 57.06 57.06 57.06 P&M-23001
Air compressor 250 cfm hour 0.06 0.06 0.06 550.00 33.00 33.00 33.00 P&M-15001
Mastic cooker 1 tonne capacity hour 6.00 6.00 6.00 600.00 3600.00 3600.00 3600.00 P&M-27001
Bitumen boiler 1500 litres capacity hour 6.00 6.00 6.00 664.00 3984.00 3984.00 3984.00 P&M-26001
Tractor for towing and positioning of mastic cooker hour 1.00 1.00 1.00 820.00 820.00 820.00 820.00 P&M-12001
and bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
ii) Crusher stone dust @ 31.9 per cent by weight of cum 0.39 0.39 0.39 302.41 117.94 117.94 117.94 M-020
mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 =
0.39
iii) Lime stone dust filler with calcium carbonate tonne 0.36 0.36 0.36 6500.00 2340.00 2340.00 2340.00 M-190
content not less than 80 per cent by weight @
17.92 per cent by weight of mix = 2 x 17.92/100 =
0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ cum 0.55 0.55 0.55 860.76 473.42 473.42 473.42 M-050
40 per cent by weight of mix = 2 x 40/100 = 0.8 MT
= 0.8/1.456 = 0.55
v) Pre-coated stone chips of 9.5 mm nominal size cum 0.036 0.036 0.036 2250.00 81.00 81.00 81.00 M-141
for skid resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by kg 1.05 1.05 1.05 34.51 36.24 36.24 36.24 M-074/1000
weight = 0.036 x 1.456 x 2/100 = 0.001048MT =
1.05kg
d) Overhead charges @ 20% on @ 20% on @ 20% on 5157.59 5157.59 5157.59
(a+b+c) (a+b+c) (a+b+c)
Page 17 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on 3094.56 3094.56 3094.56
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 72.46 sqm = a+b+c+d+e 34040.13 34040.13 34040.13
Rate per sqm = (a+b+c+d+e)/72.46 469.78 469.78 469.78
say 470.00 470.00 470.00
Note 1.The rates for 6 mm or any other thickness may be
worked out on pro-rata basis.
2. Where tack coat is required to be provided before
laying mastic asphalt, the same is required to be
measured and paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per
mix design.
4.This rate analysis is based on design made by CRRI
for a specific case and is meant for estimating
purposes only. Actual design is required to be done for
each case.
5.The quantity of bitumen works out 17 per cent of the
mastic asphalt blocks without aggregates and falls
within the standards laid down by MoRTH
Specifications.
9.23 800 Crash Barriers
The rate analysis for rigid crash barrier in reinforced
cement concrete, semi-rigid crash barrier with metal
beam and flexible crash barrier with wire ropes have
been made and included in chapter-8 on Traffic and
Transportation.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 0.01 0.01 622.00 6.22 6.22 6.22 L-12
Painter day 0.25 0.25 0.25 622.00 155.50 155.50 155.50 L-18
Mazdoor (Skilled) day 0.25 0.25 0.25 592.00 148.00 148.00 148.00 L-15
b) Material
Water based paint of approved quality for cement Litres 5.00 5.00 5.00 120.00 600.00 600.00 600.00 M-192
concrete surface
c) Overhead charges @ 20% on @ 20% on @ 20% on 181.94 181.94 181.94
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 109.17 109.17 109.17
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm (a+b+c+d) 1200.83 1200.83 1200.83
Rate per sqm (a+b+c+d)/10 120.08 120.08 120.08
say 120.00 120.00 120.00
9.25 2605 Filler joint
(i) Providing & fixing 2 mm thick corrugated copper plate
in expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mazdoor day 0.50 0.50 0.50 560.00 280.00 280.00 280.00 L-13
Mazdoor (Skilled) day 0.50 0.50 0.50 592.00 296.00 296.00 296.00 L-15
b) Material
Copper plate - 12m long x 250 mm wide kg 55.00 55.00 55.00 620.00 34100.00 34100.00 34100.00 M-087
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55
kg.
c) Overhead charges @ 20% on @ 20% on @ 20% on 6940.18 6940.18 6940.18
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 4164.11 4164.11 4164.11
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 45805.16 45805.16 45805.16
Rate per m = (a+b+c+d)/12 3817.10 3817.10 3817.10
say 3817.00 3817.00 3817.00
9.25 (ii) Providing & fixing 20 mm thick compressible fibre
board in expansion joint complete as per drawing &
Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 0.008 0.008 622.00 4.98 4.98 4.98 L-12
Mazdoor day 0.10 0.10 0.10 560.00 56.00 56.00 56.00 L-13
Mazdoor (Skilled) day 0.10 0.10 0.10 592.00 59.20 59.20 59.20 L-15
b) Material
20 mm thick compressible fibre board 12 m long x sqm 3.00 3.00 3.00 115.00 345.00 345.00 345.00 M-085
25 cm deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 20% on @ 20% on @ 20% on 93.04 93.04 93.04
(a+b) (a+b) (a+b)
Page 18 of 253
CHAPTER-9
CULVERTS & BOX CELL
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
d) Contractor's profit @ 10% on @ 10% on @ 10% on 55.82 55.82 55.82
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 614.03 614.03 614.03
Rate per m = (a+b+c+d)/12 51.17 51.17 51.17
say 51.00 51.00 51.00
9.25 (iii) Providing and fixing in position 20 mm thick
premoulded joint filler in expansion joint for fixed ends
of simply supported spans not exceeding 10 m to cater
for a horizontal movement upto 20 mm, covered with
sealant complete as per drawing and technical
specifications.
the rates at Sl. No. i), ii), iii) & iv) shall be added
9.26 710.1.4.of Back filling behind abutment, wing wall and return wall
IRC:78 & complete as per drawing and Technical Specification
2200
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 0.28 0.28 622.00 174.16 174.16 174.16 L-12
Mazdoor day 7.00 7.00 7.00 560.00 3920.00 3920.00 3920.00 L-13
b) Material
Granular material cum 12.00 12.00 12.00 725.78 8709.30 8709.30 8709.30 M-009
c) Machinery
Plate compactor/power rammer hour 2.50 2.50 2.50 528.00 1320.00 1320.00 1320.00 P&M-46001
Water Tanker hour 0.05 0.05 0.05 904.00 45.20 45.20 45.20 P&M-11003
d) Overhead charges @ 20% on @ 20% on @ 20% on 2833.73 2833.73 2833.73
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 1700.24 1700.24 1700.24
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum of granular backfill = a+b+c+d+e 18702.63 18702.63 18702.63
Rate per cum = (a+b+c+d+e)/10 1870.26 1870.26 1870.26
say 1870.00 1870.00 1870.00
9.26 B Sandy material
a) Labour
Mate day 0.28 0.28 0.28 622.00 174.16 174.16 174.16 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 7.00 7.00 560.00 3920.00 3920.00 3920.00 L-13
b) Material
Sand cum 12.00 12.00 12.00 805.78 9669.30 9669.30 9669.30 M-006
c) Machinery
Plate compactor/power rammer hour 2.50 2.50 2.50 528.00 1320.00 1320.00 1320.00 P&M-46001
Water Tanker hour 0.06 0.06 0.06 904.00 54.24 54.24 54.24 P&M-11003
d) Overhead charges @ 20% on @ 20% on @ 20% on 3027.54 3027.54 3027.54
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 1816.52 1816.52 1816.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum of sandy backfill = a+b+c+d+e 19981.76 19981.76 19981.76
Rate per cum = (a+b+c+d+e)/10 1998.18 1998.18 1998.18
say 1998.00 1998.00 1998.00
9.27 710.1.4.of Providing and laying of Filter media with granular
IRC:78 materials/stone crushed aggregates satisfying the
and requirements laid down in clause 2504.2.2. of MoRTH
2504.2 specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger size
towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full
height compacted to a firm condition complete as per
drawing and Technical Specification.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 0.32 0.32 622.00 199.04 199.04 199.04 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 7.00 7.00 560.00 3920.00 3920.00 3920.00 L-13
Mazdoor (Skilled) day 1.00 1.00 1.00 592.00 592.00 592.00 592.00 L-15
b) Material
Filter media of stone aggregate conforming to cum 12.00 12.00 12.00 716.17 8594.07 8594.07 8594.07 M-011
clause 2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 0.06 0.06 904.00 54.24 54.24 54.24 P&M-11003
d) Overhead charges @ 20% on @ 20% on @ 20% on 2671.87 2671.87 2671.87
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 1603.12 1603.12 1603.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
cost for 10 cum of Fiter Media = a+b+c+d+e 17634.34 17634.34 17634.34
Rate per cum = (a+b+c+d+e)/10 1763.43 1763.43 1763.43
say 1763.00 1763.00 1763.00
Page 19 of 253
CHAPTER- 10
MAINTENANCE OF ROADS
Amount
Reference to Quantity
Rate (Rs.) Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
10.1 3002 Restoration of Rain Cuts
Restoration of rain cuts with soil, moorum, gravel
or a mixture of these, clearing the loose soil,
benching for 300 mm width, laying fresh material in
layers not exceeding 250 mm and compacting with
plate compactor or power rammers to restore the
original alignment, levels and slopes
Unit = cum
Taking output = 10 cum 10 Cum 12 tonne
a) Labour
Mate day 0.080 0.080 0.080 622.00 49.76 49.76 49.76 L-12
Mazdoor day 2.000 2.000 2.000 560.00 1120.00 1120.00 1120.00 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.007 1748.000 12.553 P&M-3003
(ii) 1.1 cum bucket capacity hour 0.008 1748.000 14.457 P&M-3004
(iii) 0.9 cum bucket capacity hour 0.012 2570.000 29.716 P&M-3005
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 12 x L2 6.830 163.920 P&M-72002
(ii) 14 cum capacity t.km 12 x L2 7.770 186.480 P&M-73002
(iii) 10 cum capacity t.km 12 x L2 9.620 230.880 P&M-74002
For loading & unloading
(i) 18 cum capacity hour 0.007 2621.000 18.823 P&M-6001
(ii) 14 cum capacity hour 0.008 2331.000 19.279 P&M-6002
(iii) 10 cum capacity hour 0.012 2077.000 24.016 P&M-6003
Plate compactor hour 0.500 0.500 0.500 528.00 264.00 264.00 264.00 P&M-46001
d) Overhead charges @ 20% on @ 20% on @ 20% on 130.32 165.40 206.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 175.94 181.94 192.46
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum = a+b+c+d 1935.32 2001.31 2117.03
Rate per cum = (a+b+c+d)/10 193.53 200.13 211.70
say 194.00 200.00 212.00
Note Only 75 per cent of fresh material has been
provided as 25 per cent can be retrieved at site
from earth that is flown down the slope in the form
of slurry and deposited at the foot of there in cuts
Page 1 of 253
CHAPTER- 10
MAINTENANCE OF ROADS
Amount
Reference to Quantity
Rate (Rs.) Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Removal of all failed material, trimming of
completed excavation to provide firm vertical faces,
cleaning of surface, painting of tack coat on the
sides and base of excavation as per clause 503,
back filling the pot holes with hot bituminous
material as per clause 510, compacting, trimming
and finishing the surface to form a smooth
continuous surface, all as per clause 3004.2
Page 2 of 253
CHAPTER- 10
MAINTENANCE OF ROADS
Amount
Reference to Quantity
Rate (Rs.) Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
10-5 mm 25 per cent cum 71.250 71.250 71.250 843.90 60127.72 60127.72 60127.72 M-024
5 mm and Below43 per cent cum 122.550 122.550 122.550 286.00 35049.30 35049.30 35049.30 M-020,M-021
and M-023
Filler 2 per cent tonne 9.000 9.000 9.000 6500.00 58500.00 58500.00 58500.00 M-190
Add 5 per cent for wastage 11291.95 11291.95 11291.95
Any one of the above alternatives of aggregate i.e.
19mm or 13mm nominal size may be adopted as
per approved design.
10.5 (i) for grading I Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 93898.35 116794.99 140645.69
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 126762.77 128474.49 131269.31
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 4900 cum = a+b+c+d+e 1394390.52 1413219.37 1443962.39
Rate per cum = (a+b+c+d+e)/4900 284.57 288.41 294.69
say 285.00 288.00 295.00
10.5 (ii) for grading II Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 97892.05 121787.11 146636.23
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 132154.27 133965.82 136860.48
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 4900 cum = a+b+c+d+e 1453696.93 1473624.05 1505465.33
Rate per cum = (a+b+c+d+e)/4900 296.67 300.74 307.24
say 297.00 301.00 307.00
Note For detailed working of quantities of aggregates,
refer item 5.8 of chapter 5
10.6 3004.3. Crack Filling
3
Filling of crack using slow - curing bitumen
emulsion and applying crusher dust in case crack
are wider than 3mm.
Unit = Running Meter
Taking out put = 500m
a) Labour
Mate day 0.040 0.040 0.040 622.00 24.88 24.88 24.88 L-12
Mazdoor day 1.000 1.000 1.000 560.00 560.00 560.00 560.00 L-13
b) Material
Slow-curing bitumen emulsion Kg 33.000 33.000 33.000 35.01 1155.41 1155.41 1155.41 M-077/1000
Stone crusher dust cum 0.020 0.020 0.020 302.41 6.05 6.05 6.05 M-020
c) Overhead charges @ 8% on @ 10% on @ 12% on 139.71 174.63 209.56
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 188.60 192.10 195.59
(a+b+c) (a+b+c) (a+b+c)
Cost for 500sqm = a+b+c+d 2074.65 2113.07 2151.49
Rate per meter = (a+b+c+d+e)/500 4.15 4.23 4.30
say 4.00 4.00 4.00
10.7 3004.4 Dusting
Applying crusher dust to areas of road where
bleeding of excess bitumen has occurred.
Unit = Sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 0.080 0.080 622.00 49.76 49.76 49.76 L-12
Mazdoor day 2.000 2.000 2.000 560.00 1120.00 1120.00 1120.00 L-13
b) Material
Stone crusher dust finer than 3mm with not cum 6.250 6.250 6.250 302.41 1890.06 1890.06 1890.06 M-020
more than 10 per cent passing 0.075 sieve.
Page 3 of 253
CHAPTER- 10
MAINTENANCE OF ROADS
Amount
Reference to Quantity
Rate (Rs.) Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
10.10 3005.2 Repair of old Joints Sealant
Removal of existing sealant and re sealing of
contraction, longitudinal or expansion joints in
concrete pavement with fresh sealant material
c) Materials
Explosives kg 17.500 17.500 17.500 55.00 962.50 962.50 962.50 M-215
Electric Detonators @ 1 Detonator for 2 each 70.000 70.000 70.000 12.00 840.00 840.00 840.00 M-217
Gelatine sticks of 125 gms each
c) Overhead charges @ 8% on @ 10% on @ 12% on 644.96 806.20 967.44
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 870.70 886.82 902.95
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 cum = a+b+c+d+e 9577.67 9755.03 9932.40
Rate per cum = (a+b+c+d+e)/100 95.78 97.55 99.32
say 96.00 98.00 99.00
Note Credit for the rock if found acceptable as
construction material shall be afforded
10.14 3000 Snow Clearance on Roads with Dozer
Snow clearance from road surface by a bull- dozer
165 Hp and disposing it on the valley side
Unit = cum
Taking output = 5000 cum
a) Labour
Mate day 0.080 0.080 0.080 622.00 49.76 49.76 49.76 L-12
Mazdoor day 2.000 2.000 2.000 560.00 1120.00 1120.00 1120.00 L-13
b) Machinery
Dozer 175 HP hour 5.880 5.880 5.880 2099.00 12342.12 12342.12 12342.12 P&M-1002
c) Overhead charges @ 8% on @ 10% on @ 12% on 1080.95 1351.19 1621.43
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1459.28 1486.31 1513.33
(a+b+c) (a+b+c) (a+b+c)
Cost for 5000 cum = a+b+c+d 16052.11 16349.37 16646.64
Rate per cum = (a+b+c+d)/5000 3.21 3.27 3.33
say 3.00 3.00 3.00
Page 4 of 253
CHAPTER- 10
MAINTENANCE OF ROADS
Amount
Reference to Quantity
Rate (Rs.) Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Note i) Labour provided will not be cutting the snow.
They will be guiding the dozer operator on the
alignment of the road as entire surface gets
covered with snow and the edges of the road are
not visible and for changing the blade angle. Also
they will keep a watch on the hill side for any
eventuality of avalanches, slide etc
Page 5 of 253
CHAPTER-11
HORTICULTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
11.1 307 Spreading of Sludge Farm Yard Manure or/and
good Earth
Spreading of sludge farm yard manure or/ and
good earth in required thickness (cost of sludge,
farm yard manure or/and good earth to be paid for
separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.040 0.040 0.040 622.00 24.88 24.88 24.88 L-12
Mazdoor day 1.000 1.000 1.000 560.00 560.00 560.00 560.00 L-13
b) Overhead charges @ 8% on (a) @ 10% on (a) @ 12% on (a) 46.79 58.49 70.19
Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate day 0.170 0.170 0.170 622.00 105.74 105.74 105.74 L-12
Mazdoor for grassing day 0.750 0.750 0.750 560.00 420.00 420.00 420.00 L-13
Mazdoor for maintenance for 30 days day 1.000 1.000 1.000 560.00 560.00 560.00 560.00 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 904.00 452.00 452.00 452.00 P&M-11003
c) Material
Doob grass kg 100.000 100.000 100.000 3.50 350.00 350.00 350.00 M-111
d) Overhead charges @ 8% on @ 10% on @ 12% on 151.02 188.77 226.53
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 203.88 207.65 211.43
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 2242.64 2284.17 2325.70
Rate per sqm= (a+b+c+d+e)/100 22.43 22.84 23.26
say 22.00 23.00 23.00
11.2 (ii) In rows 7.5 cm apart in either direction
a) Labour
Mate day 0.220 0.220 0.220 622.00 136.84 136.84 136.84 L-12
Mazdoor for grassing. day 1.250 1.250 1.250 560.00 700.00 700.00 700.00 L-13
for maintenance for 30 days day 1.000 1.000 1.000 560.00 560.00 560.00 560.00 L-13
b) Machinery
Water tanker6 KL capacity hour 0.750 0.750 0.750 904.00 678.00 678.00 678.00 P&M-11003
c) Material
Doob grass kg 200.000 200.000 200.000 3.50 700.00 700.00 700.00 M-111
d) Overhead charges @ 8% on @ 10% on @ 12% on 221.99 277.48 332.98
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 299.68 305.23 310.78
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 3296.51 3357.56 3418.60
Rate per sqm = (a+b+c+d+e)/100 32.97 33.58 34.19
say 33.00 34.00 34.00
Note In the case of horticulture one mate has been
provided for every 10 mazdoors as maintenance of
grass and plants require more care.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.150 0.150 0.150 622.00 93.30 93.30 93.30 L-12
Mazdoor for preparation of ground day 0.500 0.500 0.500 560.00 280.00 280.00 280.00 L-13
Mali for fetching doobs grass roots and day 1.000 1.000 1.000 592.00 592.00 592.00 592.00 L-09
grassing at 15 cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 904.00 452.00 452.00 452.00 P&M-11003
Tractor with tipper hour 0.010 0.010 0.010 820.00 8.20 8.20 8.20 P&M-12001
c) Material
Supply of farm yard manure at site of work cum 0.180 0.180 0.180 150.00 27.00 27.00 27.00 M-168
Fine grass kg 100.000 100.000 100.000 21.00 2100.00 2100.00 2100.00 M-112
d) Overhead charges @ 8% on @ 10% on @ 12% on 284.20 355.25 426.30
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 383.67 390.78 397.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 4220.37 4298.53 4376.68
Rate per sqm = (a+b+c+d+e)/100 42.20 42.99 43.77
say 42.00 43.00 44.00
11.4 307 Maintenance of Lawns or Turfing of Slopes
Maintenance of lawns or Turfing of slopes (rough
grassing) for a period of one year including
watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 10.000 10.000 592.00 5920.00 5920.00 5920.00 L-09
b) Machinery
Water tanker6 KL capacity hour 15.000 15.000 15.000 904.00 13560.00 13560.00 13560.00 P&M-11003
c) Material
Cost of water KL 90.000 90.000 90.000 74.54 6708.60 6708.60 6708.60 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 2095.09 2618.86 3142.63
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 2828.37 2880.75 2933.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 31112.06 31688.21 32264.36
Rate per sqm = (a+b+c+d+e)/100 311.12 316.88 322.64
say 311.00 317.00 323.00
11.5 307 Turfing Lawns with Fine Grassing including
Ploughing, Dressing
Page 1 of 253
CHAPTER-11
HORTICULTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Turfing lawns with fine grassing including
ploughing, dressing including breaking of clods,
removal of rubbish, dressing and supplying doobs
grass roots at 10 cm apart, including supplying and
spreading of farm yard manure at rate of0.6 cum
per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.250 0.250 0.250 622.00 155.50 155.50 155.50 L-12
Mazdoor for preparation of ground day 1.000 1.000 1.000 560.00 560.00 560.00 560.00 L-13
Mali for fetching doobs grass roots hedges and day 1.500 1.500 1.500 592.00 888.00 888.00 888.00 L-09
grassing at 10 cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 904.00 452.00 452.00 452.00 P&M-11003
Tractor with tiller hour 0.010 0.010 0.010 820.00 8.20 8.20 8.20 P&M-12001
c) Material
Supply of farm yard manure at site of work @ cum 0.600 0.600 0.600 150.00 90.00 90.00 90.00 M-168
0.6 cum per 100 sqm
Fine grass kg 100.000 100.000 100.000 21.00 2100.00 2100.00 2100.00 M-112
d) Overhead charges @ 8% on @ 10% on @ 12% on 340.30 425.37 510.44
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 459.40 467.91 476.41
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 5053.40 5146.98 5240.56
Rate per sqm = (a+b+c+d+e)/100 50.53 51.47 52.41
say 51.00 51.00 52.00
11.6 307 Maintenance of Lawns with Fine Grassing for the
First Year
Maintenance of lawns with fine grassing for the first
year including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 10.000 10.000 592.00 5920.00 5920.00 5920.00 L-09
b) Machinery
Water tanker6 KL capacity hour 20.000 20.000 20.000 904.00 18080.00 18080.00 18080.00 P&M-11003
c) Material
Cost of water KL 60.000 60.000 60.000 74.54 4472.40 4472.40 4472.40 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 2277.79 2847.24 3416.69
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 3075.02 3131.96 3188.91
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 33825.21 34451.60 35078.00
Rate per sqm = (a+b+c+d+e)/100 338.25 344.52 350.78
say 338.00 345.00 351.00
11.7 307 Planting and Maintaining of Permanent Hedges
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 904.00 452.00 452.00 452.00 P&M-11003
c) Material
Cost of hedge plants 2 rows at 30 cm apart each 2x340 2x340 2x340 5.00 3400.00 3400.00 3400.00 M-115
Supply of farm yard manure at site of work cum 4.670 4.670 4.670 150.00 700.50 700.50 700.50 M-168
Page 2 of 253
CHAPTER-11
HORTICULTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
b) Machinery
Water tanker6 KL capacity hour 6.000 6.000 6.000 904.00 5424.00 5424.00 5424.00 P&M-11003
c) Material
Plants each 200.000 200.000 200.000 30.00 6000.00 6000.00 6000.00 M-100
Shrubs each 800.000 800.000 800.000 22.00 17600.00 17600.00 17600.00 M-167
Manure sludge/Farm yard manure cum 63.640 63.640 63.640 150.00 9546.00 9546.00 9546.00 M-168
Pesticide kg 0.500 0.500 0.500 200.00 100.00 100.00 100.00 M-135
Cost of water KL 36.000 36.000 36.000 74.54 2683.44 2683.44 2683.44 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 3905.59 4881.98 5858.38
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 5272.54 5370.18 5467.82
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per Km = (a+b+c+d+e) 57997.97 59072.01 60146.04
say 57998.00 59072.00 60146.00
11.8 (b) Maintenance of flowering plants and shrubs in
central verge for one year
Unit = km
Taking output = one km
a) Labour
Mate day 36.000 36.000 36.000 622.00 22392.00 22392.00 22392.00 L-12
Mazdoor day 365.000 365.000 365.000 560.00 204400.00 204400.00 204400.00 L-13
b) Machinery
Water tanker6 KL capacity hour 90.000 90.000 90.000 904.00 81360.00 81360.00 81360.00 P&M-11003
c) Material
Manure Sludge / farm yard manure at site cum 10.000 10.000 10.000 150.00 1500.00 1500.00 1500.00 M-168
Cost of water KL 180.000 180.000 180.000 74.54 13417.20 13417.20 13417.20 M-191
Replacement of casualties @ 10 per cent
Plants each 20.000 20.000 20.000 30.00 600.00 600.00 600.00 M-100
Shrubs each 80.000 80.000 80.000 22.00 1760.00 1760.00 1760.00 M-167
Pesticides kg 1.500 1.500 1.500 200.00 300.00 300.00 300.00 M-135
d) Overhead charges @ 8% on @ 10% on @ 12% on 26058.34 32572.92 39087.50
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 35178.75 35830.21 36481.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per Km for one year = (a+b+c+d+e) 386966.29 394132.33 401298.37
say 386966.00 394132.00 401298.00
11.9 307 Planting of Trees and their Maintenance for one
Year
Planting of trees by the road side (Avenue trees) in
0.60 m dia holes, 1 m deep dug in the ground,
mixing the soil with decayed farm yard/sludge
manure, planting the saplings, backfilling the
trench, watering, fixing the tree guard and
maintaining the plants for one year
Unit = Each
Taking output = 10 trees
a) Labour
Mate day 1.700 1.700 1.700 622.00 1057.40 1057.40 1057.40 L-12
Mazdoor for planting day 2.000 2.000 2.000 560.00 1120.00 1120.00 1120.00 L-13
Mazdoor for maintenance for one year day 15.000 15.000 15.000 560.00 8400.00 8400.00 8400.00 L-13
b) Machinery
Water tanker6 KL capacity hour 2.000 2.000 2.000 904.00 1808.00 1808.00 1808.00 P&M-11003
c) Material
Sapling 2 m high 25 mm dia each 10.000 10.000 10.000 55.00 550.00 550.00 550.00 M-161
Farm yard manure cum 0.940 0.940 0.940 150.00 141.00 141.00 141.00 M-168
Pesticide kg 0.500 0.500 0.500 200.00 100.00 100.00 100.00 M-135
Cost of water KL 12.000 12.000 12.000 74.54 894.48 894.48 894.48 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 1125.67 1407.09 1688.51
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 1519.66 1547.80 1575.94
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 trees = a+b+c+d+e 16716.21 17025.76 17335.32
Rate per trees = (a+b+c+d+e)/10 1671.62 1702.58 1733.53
say 1672.00 1703.00 1734.00
11.10 308 Renovation Lawns including, Weeding, Forking the
Ground, Top Dressing with Forked Soil
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 622.00 74.64 74.64 74.64 L-12
Mazdoor day 3.000 3.000 3.000 560.00 1680.00 1680.00 1680.00 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 904.00 452.00 452.00 452.00 P&M-11003
c) Material
Cost of water KL 3.000 3.000 3.000 74.54 223.62 223.62 223.62 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 194.42 243.03 291.63
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 262.47 267.33 272.19
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 2887.15 2940.61 2994.08
Rate per sqm = (a+b+c+d+e) 28.87 29.41 29.94
say 29.00 29.00 30.00
11.11 308.2 Supply at Site Well Decayed Farm Yard Manure
Page 3 of 253
CHAPTER-11
HORTICULTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
a) Cost, carriage, loading, unloading and quintal 1.000 1.000 1.000 25.00 25.00 25.00 25.00 M-242
stacking in store/site
b) Overhead charges @ 8% on (a) @ 10% on (a) @ 12% on (a) 2.00 2.50 3.00
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 0.050 0.050 622.00 31.10 31.10 31.10 L-12
Mason day 0.250 0.250 0.250 622.00 155.50 155.50 155.50 L-11
Mazdoor day 0.250 0.250 0.250 560.00 140.00 140.00 140.00 L-13
b) Material
Brick 2nd class including carriage each 230.000 230.000 230.000 5.00 1150.00 1150.00 1150.00 M-079
Cement mortar 1:6 cum 0.025 0.025 0.025 3702.28 92.56 92.56 92.56 Sub-Analysis of
Concrete - 19.01
D
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 125.53 156.92 188.30
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 169.47 172.61 175.75
(a+b+c) (a+b+c) (a+b+c)
Rate per tree Guard = a+b+c+d 1864.16 1898.68 1933.20
say 1864.00 1899.00 1933.00
11.15 New Edging with 2nd Class Bricks, Laid Dry Lengthwise
Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.002 0.002 0.002 622.00 1.24 1.24 1.24 L-12
Mason day 0.050 0.050 0.050 622.00 31.10 31.10 31.10 L-11
Mazdoor day 0.050 0.050 0.050 560.00 28.00 28.00 28.00 L-13
b) Material
Brick 2nd class including carriage each 50.000 50.000 50.000 5.00 250.00 250.00 250.00 M-079
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 24.83 31.03 37.24
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 33.52 34.14 34.76
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 metre = a+b+c+d 368.69 375.52 382.34
Rate per metre = (a+b+c+d)/10 36.87 37.55 38.23
say 37.00 38.00 38.00
11.16 New Making Tree Guard 53 cm dia and 1.3 m High as
per Design from Empty Bitumen Drums
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 0.020 0.020 622.00 12.44 12.44 12.44 L-12
Blacksmith day 0.150 0.150 0.150 622.00 93.30 93.30 93.30 L-02
Mazdoor day 0.070 0.070 0.070 560.00 39.20 39.20 39.20 L-13
b) Material
Empty bitumen drum each 1.000 1.000 1.000 110.00 110.00 110.00 110.00 M-173
MS sheet 50 x 0.5 mm kg 0.650 0.650 0.650 65.00 42.25 42.25 42.25 M-181 / 1000
Rivets 6 mm dia and 10 mm in length each 22.000 22.000 22.000 1.50 33.00 33.00 33.00 M-159
d) Overhead charges @ 8% on @ 10% on @ 12% on 26.42 33.02 39.62
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 35.66 36.32 36.98
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate for each tree guard = a+b+c+d 392.27 399.53 406.79
say 392.00 400.00 407.00
11.17 New Making Tree Guard 53 cm dia and 2 Metre High as
per Design from Empty Bitumen Drums
Unit = Each
Taking output = one tree guard
a) Labour
Mate 0.040 0.040 0.040 622.00 24.88 24.88 24.88 L-12
Blacksmith day 0.200 0.200 0.200 622.00 124.40 124.40 124.40 L-02
Mazdoor 0.200 0.200 0.200 560.00 112.00 112.00 112.00 L-13
b) Material
Empty bitumen drum each 1.500 1.500 1.500 110.00 165.00 165.00 165.00 M-173
Page 4 of 253
CHAPTER-11
HORTICULTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
MS sheet50 x 0.5 mm kg 0.650 0.650 0.650 65.00 42.25 42.25 42.25 M-181 / 1000
Rivets 6 mm dia and 10 mm in length each 50.000 50.000 50.000 1.50 75.00 75.00 75.00 M-159
MSplate30 x 3 mm kg 1.300 1.300 1.300 65.00 84.50 84.50 84.50 M-181 / 1000
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 50.24 62.80 75.36
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 67.83 69.08 70.34
(a+b+c) (a+b+c) (a+b+c)
Rate for each tree guard = a+b+c+d 746.10 759.92 773.73
say 746.00 760.00 774.00
11.18 New Wrought Iron and Mild Steel Welded Work
Wrought iron and mild steel welded work (using
angles, square bars, tees and channel grills,
grating frames, gates and tree guards of any size
and design etc. including cost of screens and
welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and
concrete for fixing which will be paid separately
Unit = quintal
Taking output = one quintal
a) Labour
Mate day 0.450 0.450 0.450 622.00 279.90 279.90 279.90 L-12
Blacksmith/ welder for cutting to design and day 2.000 2.000 2.000 622.00 1244.00 1244.00 1244.00 L-02
shape and jointing
Mazdoor for fixing and helper for day 2.500 2.500 2.500 560.00 1400.00 1400.00 1400.00 L-13
Blacksmith/welder
b) Material
Angle, tees, channels etc quintal 1.050 1.050 1.050 6500.00 6825.00 6825.00 6825.00 M-181 / 10
Deduct the cost of scrap quintal 0.050 0.050 0.050 (2166.67) (108.33) (108.33) (108.33) M-181 / 10/3
Add 5 per cent of cost of material for welding rods 335.83 335.83 335.83
and other welding accessories
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on 798.11 997.64 1197.17
(a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1077.45 1097.40 1117.36
(a+b+c) (a+b+c) (a+b+c)
Rate per quintal = a+b+c+d 11851.96 12071.44 12290.92
say 11852.00 12071.00 12291.00
11.19 New Tree Guard with MS Iron
Providing and fixing MS iron tree guard 60 cm dia
and 2 metre high above ground level formed of 4
Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical
MS riveted to 3 Nos (25 x 6 mm) iron rings in two
halves, bolted together with 8 mm dia and 30 mm
long bolts including painting two coats with paint of
approved brand over a coat of priming, complete in
all respects.
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 0.050 0.050 622.00 31.10 31.10 31.10 L-12
Blacksmith day 0.250 0.250 0.250 622.00 155.50 155.50 155.50 L-02
Mazdoor day 0.250 0.250 0.250 560.00 140.00 140.00 140.00 L-13
b) Material
MS iron 25 x 6 mm kg 19.200 19.200 19.200 65.00 1248.00 1248.00 1248.00 M-181 /1000
MS iron 25 x 3 mm kg 9.600 9.600 9.600 65.00 624.00 624.00 624.00 M-181 / 1000
Add 5 per cent of cost of material for riveting,
bolting and welding accessories
c) Machinery
Tractor-trolley hour 0.040 0.040 0.040 820.00 32.80 32.80 32.80 P&M-12001
d) Painting
Painting two coats including priming sqm 1.770 1.770 1.770 77.00 136.29 136.29 136.29 Item No. - 8.9
Unit = Each
Taking output = one
a) Labour
Mate day 0.050 0.050 0.050 622.00 31.10 31.10 31.10 L-12
Blacksmith day 0.250 0.250 0.250 622.00 155.50 155.50 155.50 L-02
Welder day 0.250 0.250 0.250 622.00 155.50 155.50 155.50 L-02
Mazdoor day 0.250 0.250 0.250 560.00 140.00 140.00 140.00 L-13
b) Material
MS angle 30 x 30 x 3 mm kg 13.500 13.500 13.500 65.00 877.50 877.50 877.50 M-181 / 1000
MS iron 25 x 3 mm kg 18.000 18.000 18.000 65.00 1170.00 1170.00 1170.00 M-181 / 1000
Steel wire 3 mm dia kg 6.000 6.000 6.000 75.00 450.00 450.00 450.00 M-194
Add 5 per cent of cost of material for riveting, 124.88 124.88 124.88
bolting and welding accessories
c) Machinery
Tractor-trolley hour 0.040 0.040 0.040 820.00 32.80 32.80 32.80 P&M-12001
d) Painting
Painting two coats including priming sqm 1.500 1.500 1.500 77.00 115.50 115.50 115.50 Item No. - 8.9
e) Overhead charges @ 8% on @ 10% on @ 12% on 250.98 313.73 376.47
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on 338.83 345.10 351.37
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Rate per tree guard = a+b+c+d+e+f 3842.58 3911.60 3980.62
say 3843.00 3912.00 3981.00
11.21 New Compensatory Afforestation
Planting trees as compensatory afforestation at the
rate of 290 trees per hectare at a spacing of 6 m by
grubbing and leveling the ground upto a depth of
150 mm, digging holes 0.9 m dia, 1 m deep, mixing
farm yard/sludge manure with soil, planting of
sapling 2 m high with 25 cm dia stem, backfilling
the hole and watering
Unit = Hectare
Taking output = one hectare
Page 5 of 253
CHAPTER-11
HORTICULTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
a) Labour
i) Planting
Mate day 2.500 2.500 2.500 622.00 1555.00 1555.00 1555.00 L-12
Mazdoor day 25.000 25.000 25.000 560.00 14000.00 14000.00 14000.00 L-13
ii) For Maintenance for one year
Mate day 5.000 5.000 5.000 622.00 3110.00 3110.00 3110.00 L-12
Mazdoor day 50.000 50.000 50.000 560.00 28000.00 28000.00 28000.00 L-13
b) Machinery
Dozer 80 HP @ 1000 sqm/hour hour 10.000 10.000 10.000 1267.00 12670.00 12670.00 12670.00 P&M-1003
Water tanker6 KL capacity (for planting) hour 3.000 3.000 3.000 904.00 2712.00 2712.00 2712.00 P&M-11003
Water tanker6 KL capacity (for maintenance) hour 25.000 25.000 25.000 904.00 22600.00 22600.00 22600.00 P&M-11003
c) Material
Sapling 1 to 1.5 m high 2 cm dia stem each 290.000 290.000 290.000 44.00 12760.00 12760.00 12760.00 M-161 x 0.8
Add 10 per cent of sapling each 29.000 29.000 29.000 44.00 1276.00 1276.00 1276.00 M-161 x 0.8
Decayed farm yard/sludge manure (planting) cum 60.900 60.900 60.900 150.00 9135.00 9135.00 9135.00 M-168
Decayed farm yard/sludge manure cum 4.000 4.000 4.000 150.00 600.00 600.00 600.00 M-168
(maintenance)
Pesticides for planting kg 0.500 0.500 0.500 200.00 100.00 100.00 100.00 M-135
Pesticides for maintenance kg 1.500 1.500 1.500 200.00 300.00 300.00 300.00 M-135
Cost of water KL 18.000 18.000 18.000 74.54 1341.72 1341.72 1341.72 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 8812.78 11015.97 13219.17
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 11897.25 12117.57 12337.89
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per hectare = a+b+c+d+e 130869.75 133293.26 135716.78
say 130870.00 133293.00 135717.00
Note Cost of fencing to be provided as per size of plot
and approved design, measured and paid
separately
Page 6 of 253
CHAPTER-12
FOUNDATIONS
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
say 6895.77 6904.80 6937.96
12.12 Section Sinking of 6 m external diameter well (other than
1200 pneumatic method of sinking) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.
Page 1 of 253
CHAPTER-12
FOUNDATIONS
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
a Add 5 per cent for every additional meter depth of For dewatering For dewatering For dewatering @
sinking over the rate of sinking for the previous meter @ 5% of cost, @ 5% of cost, if 5% of cost, if
if required required required
b Add 20 per cent of cost for Kentledge including 20% for 20% for 20% for Kentledge
supports, loading arrangement and Labour. Kentledge Kentledge
b Add 20 per cent of cost for Kentledge including 20% for 20% for 20% for
supports, loading arrangement and Labour. Kentledge Kentledge Kentledge
Air compressor with pneumatic chisel attachment hour 2.00 2.00 2.00 561.00 1122.00 1122.00 1122.00 P&M-15001 +P&M-
for cutting hard clay. 45001
Consumables in sinking @ 10 per cent of (b) 700.20 700.20 700.20
Page 3 of 253
CHAPTER-12
FOUNDATIONS
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
b Add for dewatering @ 5 per cent of cost, if required. For dewatering For dewatering For dewatering @
@ 5% of cost, @ 5% of cost, if 5% of cost, if
if required required required
c Add 20 per cent of cost for Kentledge including 20% for 20% for 20% for Kentledge 5% for dewatering,
supports, loading arrangement and Labour). Kentledge Kentledge if required
Page 4 of 253
CHAPTER-12
FOUNDATIONS
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
31st m 10% 60096.00 60096.00 60096.00 12019.00 12019.00 12019.00 3005.00
32nd 10% 66106.00 66106.00 66106.00 13221.00 13221.00 13221.00 3305.00
33rd m 10% 72717.00 72717.00 72717.00 14543.00 14543.00 14543.00 3636.00
34th m 10% 79989.00 79989.00 79989.00 15998.00 15998.00 15998.00 3999.00
35th m 10% 87988.00 87988.00 87988.00 17598.00 17598.00 17598.00 4399.00
36th m 10% 96787.00 96787.00 96787.00 19357.00 19357.00 19357.00 4839.00
37th m 10% 106466.00 106466.00 106466.00 21293.00 21293.00 21293.00 5323.00
38th m 10% 117113.00 117113.00 117113.00 23423.00 23423.00 23423.00 5856.00
39th m 10% 128824.00 128824.00 128824.00 25765.00 25765.00 25765.00 6441.00
40th m 10% 141706.00 141706.00 141706.00 28341.00 28341.00 28341.00 7085.00
Total Cost from 30m upto 40m 957792.00 957792.00 957792.00 191558.00 191558.00 191558.00 47888.00
Avg Rate per metre 95779.20 95779.20 95779.20 19156.00 19155.80 19155.80 4788.80
12.12 C Extra over item no. 12.12 (A) & (B) irrespective of
depth for sinking in Soft Rock (6m dia well )
Page 5 of 253
CHAPTER-12
FOUNDATIONS
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Diver day 0.50 0.50 0.50 622.00 311.00 311.00 311.00 L-07
Driller day 2.00 2.00 2.00 592.00 1184.00 1184.00 1184.00 L-06
Page 6 of 253
CHAPTER-12
FOUNDATIONS
Amount
Reference to Quantity
Rate (Rs.)
Sr No MORT&H Description Unit For Large For Medium For Small Remarks/ Input ref.
(Rs.) Large Project Medium Project Small Project
Specification Project Project Project
Blaster day 0.25 0.25 0.25 560.00 140.00 140.00 140.00 L-03
Mazdoor day 6.00 6.00 6.00 560.00 3360.00 3360.00 3360.00 L-13
c) Machinery
Air Compressor 250 cfm hour 23.355 23.355 23.355 550.00 12844.994 12844.994 12844.994 P&M-15001
Pneumatic breaker hour 22.619 22.619 22.619 11.00 248.814 248.814 248.814 P&M-45001
Pneumatic breaker for drilling holes (@ 4.5 m hour 8.090 8.090 8.090 11.00 88.986 88.986 88.986
per hour) P&M-45001
Consumables in protected blasting @ 10 per 1318.28 1318.28 1318.28
cent of (c)
Add for dewatering @ of 15 per cent of (a+b+c), 4624.21 4624.21 4624.21
if required
d) Overhead charges @ 20% on @ 20% on @ 20% on 5330.26 5330.26 5330.26
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 3198.15 3198.15 3198.15
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per metre = (a+b+c+d+e) 35179.70 35179.70 35179.70
say 35179.70 35179.70 35179.70
12.12 E Extra over item no. 12.12 (A) & (B) irrespective of
depth for sinking in rock bouldery strata (6m dia
well )
Unit = Running Meter.
Taking output = 1 m
a) Labour
Mate day 0.41 0.41 0.41 622.00 255.02 255.02 255.02 L-12
Sinker ( skilled ) day 1.50 1.50 1.50 592.00 888.00 888.00 888.00 L-15
Sinking helper ( semi-skilled ) day 2.25 2.25 2.25 592.00 1332.00 1332.00 1332.00 L-14
Diver day 0.50 0.50 0.50 622.00 311.00 311.00 311.00 L-07
Mazdoor day 6.00 6.00 6.00 560.00 3360.00 3360.00 3360.00 L-13
b) Machinery
Air Compressor 250 cfm hour 18.850 18.850 18.850 550.00 10367.256 10367.256 10367.256 P&M-15001
Pneumatic breaker hour 37.699 37.699 37.699 11.00 414.690 414.690 414.690 P&M-45001
Consumables in sinking @ 5 per cent of (b) 539.10 539.10 539.10
Page 7 of 253
CHAPTER-13
SUB-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium ref.
Specification Large Project Small Project
Project Project Project Project
13.1 1300 & Brick masonry work in 1:3 in sub-structure
2200 complete excluding pointing and plastering, as per
drawing and Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 500.00 500.00 5.00 2500.00 2500.00 2500.00 M-079
Cement mortar 1:3 (Rate as sub-analysis) cum 0.24 0.24 0.24 4888.87 1173.33 1173.33 1173.33 Sub-Analysis of
Concrete - 19.01
(A)
Water for curing KL 0.48 0.48 0.48 74.54 36.00 36.00 36.00 M-191
b) Labour
Mate day 0.06 0.06 0.06 622.00 37.32 37.32 37.32 L-12
Mason day 0.80 0.80 0.80 622.00 497.60 497.60 497.60 L-11
Mazdoor day 0.80 0.80 0.80 560.00 448.00 448.00 448.00 L-13
Add for scaffolding @ 5 per cent of cost of 234.61 234.61 234.61
material and labour
c) Machinery
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading @ 30 mins
per trip )
(i) 16 KL capacity hour 0.007 1357.00 9.10 P&M-11001
(ii) 12 KL capacity hour 0.009 1187.00 10.62 P&M-11002
(iii) 6 KL capacity hour 0.018 904.00 16.17 P&M-11003
d) Overhead charges @ 20% on (a+b+c) 987.19 987.50 988.61
e) Contractor's profit @ 10% on (a+b+c+d) 592.32 592.50 593.16
Unit = sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as sub-analysis) cum 0.03 0.03 0.03 4888.87 146.67 146.67 146.67 Sub-Analysis of
Concrete - 19.01
(A)
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mason day 0.50 0.50 0.50 622.00 311.00 311.00 311.00 L-11
Mazdoor day 0.50 0.50 0.50 560.00 280.00 280.00 280.00 L-13
c) Overhead charges @ 20% on (a+b) 152.51 152.51 152.51
d) Contractor's profit @ 10% on (a+b+c) 91.51 91.51 91.51
Rate per 10 sqm (a+b+c+d) 100.66 100.66 100.66
say 100.66 100.66 100.66
Note Scaffolding is already included in item 13.1
13.3 1300 & Plastering with cement mortar (1:3 ) on brick work
2200 in sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as sub-analysis) cum 0.144 0.144 0.144 4888.87 704.00 704.00 704.00 Sub-Analysis of
Concrete - 19.01
(A)
Water for curing KL 0.14 0.14 0.14 74.54 10.37 10.37 10.37 M-191
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mason day 0.50 0.50 0.50 622.00 311.00 311.00 311.00 L-11
Mazdoor day 0.50 0.50 0.50 560.00 280.00 280.00 280.00 L-13
c) Machinery
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading @ 30 mins
per trip )
(i) 16 KL capacity hour 0.002 1357.00 2.62 P&M-11001
(ii) 12 KL capacity hour 0.003 1187.00 3.06 P&M-11002
(iii) 6 KL capacity hour 0.005 904.00 4.66 P&M-11003
13.4 1400 & Stone masonry work in cement mortar 1:3 for
2200 substructure complete as per drawing and
Technical Specifications
A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 1.00 1.00 470.14 470.14 470.14 470.14 M-147
Through and bond stone No 7.00 7.00 7.00 25.00 175.00 175.00 175.00 M-184
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as sub-analysis) cum 0.33 0.33 0.33 4888.87 1613.33 1613.33 1613.33 Sub-Analysis of
Concrete - 19.01
(A)
Water for curing KL 0.97 0.97 0.97 74.54 72.01 72.01 72.01 M-191
b) Labour
Mate day 0.10 0.10 0.10 622.00 62.20 62.20 62.20 L-12
Mason day 1.20 1.20 1.20 622.00 746.40 746.40 746.40 L-11
Mazdoor day 1.20 1.20 1.20 560.00 672.00 672.00 672.00 L-13
Add for scaffolding @ 5 per cent of cost of a) 190.55
Material and b) Labour
c) Machinery
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading @ 30 mins
per trip )
(i) 16 KL capacity hour 0.013 1357.00 18.21 P&M-11001
(ii) 12 KL capacity hour 0.018 1187.00 21.23 P&M-11002
(iii) 6 KL capacity hour 0.036 904.00 32.34 P&M-11003
c) Overhead charges @ 10% on (a+b) 382.93 383.23 403.40
d) Contractor's profit @ 30% on (a+b+c) 1263.66 1264.66 1331.21
Rate per cum (a+b+c+d) 5475.86 5480.19 5768.57
say 5476.00 5480.00 5769.00
13.4 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.10 1.10 1.10 470.14 517.15 517.15 517.15 M-147
Through and bond stone each 7.00 7.00 7.00 25.00 175.00 175.00 175.00 M-184
(7 no.x 0.24 m x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar 1:3 (Rate as sub-analysis) cum 0.30 0.30 0.30 4888.87 1466.66 1466.66 1466.66 Sub-Analysis of
Concrete - 19.01
(A)
Water for curing KL 0.97 0.97 0.97 74.54 72.01 72.01 72.01 M-191
b) Labour
Mate day 0.12 0.12 0.12 622.00 74.64 74.64 74.64 L-12
Page 1 of 253
CHAPTER-13
SUB-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium ref.
Specification Large Project Small Project
Project Project Project Project
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 1.50 1.50 1.50 560.00 840.00 840.00 840.00 L-13
Add for scaffolding @ 5 per cent of cost of 203.92 203.92 203.92
material and labour
c) Machinery
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading @ 30 mins
per trip )
(i) 16 KL capacity hour 0.013 1357.00 18.21 P&M-11001
(ii) 12 KL capacity hour 0.018 1187.00 21.23 P&M-11002
(iii) 6 KL capacity hour 0.036 904.00 32.34 P&M-11003
c) Overhead charges @ 10% on (a+b) 430.06 430.36 431.47
d) Contractor's profit @ 30% on (a+b+c) 1419.19 1420.19 1423.86
Rate per cum (a+b+c+d) 6149.84 6154.17 6170.05
say 6150.00 6154.00 6170.00
13.4 C Ashlar masonry ( first sort )
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 1.11 1.11 470.14 521.85 521.85 521.85 M-170
Through and bond stone each 7.00 7.00 7.00 25.00 175.00 175.00 175.00 M-184
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as sub-analysis) cum 0.33 0.33 0.33 4888.87 1613.33 1613.33 1613.33 Sub-Analysis of
Concrete - 19.01
(A)
Water for curing KL 0.97 0.97 0.97 74.54 72.01 72.01 72.01 M-191
b) Labour for masonry work
Mate day 0.20 0.20 0.20 622.00 124.40 124.40 124.40 L-12
Mason day 2.50 2.50 2.50 622.00 1555.00 1555.00 1555.00 L-11
Mazdoor day 2.50 2.50 2.50 560.00 1400.00 1400.00 1400.00 L-13
Add for scaffolding @ 5 per cent of cost of a) 273.08 273.08 273.08
Material and b) Labour
c) Machinery
Water tanker (speed @ 20km/hr and return
speed @ 30 km/hr and spreading @ 30 mins
per trip )
(i) 16 KL capacity hour 0.013 1357.00 18.21 P&M-11001
(ii) 12 KL capacity hour 0.018 1187.00 21.23 P&M-11002
(iii) 6 KL capacity hour 0.036 904.00 32.34 P&M-11003
c) Overhead charges @ 10% on (a+b) 575.29 575.59 576.70
d) Contractor's profit @ 30% on (a+b+c) 1898.45 1899.45 1903.11
Rate per cum (a+b+c+d) 8226.60 8230.93 8246.82
say 8227.00 8231.00 8247.00
Note The labour already considered in the cement
mortar have been taken into account while
providing these categories in the stone masonry
works.
13.5 1500, Plain/Reinforced cement concrete in sub-structure
1700 & complete as per drawing and Technical
2200 Specifications
13.5 S PCC Grade M15
(p) Height upto 5m
PCC Grade M15 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 3260.59 97817.72 97817.72 97817.72 Sub-Analysis of
Concrete - 19.03
Water for curing Kl 15.750 15.750 15.750 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.156 0.156 0.156 622.00 96.76 96.76 96.76 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 2.389 2.389 2.389 560.00 1337.78 1337.78 1337.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.16 0.16 0.16 622.00 96.76 96.76 96.76 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 2.39 2.39 2.39 560.00 1337.78 1337.78 1337.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Page 2 of 253
CHAPTER-13
SUB-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium ref.
Specification Large Project Small Project
Project Project Project Project
f) Contractor's profit @ 10% on @ 10% on @ 10% on 14802.74 14828.80 14924.43
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.16 0.16 0.16 622.00 96.76 96.76 96.76 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 2.39 2.39 2.39 560.00 1337.78 1337.78 1337.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.16 0.16 0.16 622.00 96.76 96.76 96.76 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 2.39 2.39 2.39 560.00 1337.78 1337.78 1337.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Add 2 per cent of cost of material, Labour and 2.00 2663.11 2667.06 2681.55
machinery excluding formwork to cater for extra lift
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.16 0.16 0.16 622.00 96.76 96.76 96.76 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 2.39 2.39 2.39 560.00 1337.78 1337.78 1337.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Add 4 per cent of cost of material, Labour and 4.00 5326.23 5334.13 5363.11
machinery excluding formwork to cater for extra lift
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.16 0.16 0.16 622.00 96.76 96.76 96.76 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 2.39 2.39 2.39 560.00 1337.78 1337.78 1337.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.16 0.16 0.16 622.00 96.76 96.76 96.76 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 2.39 2.39 2.39 560.00 1337.78 1337.78 1337.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Add 2 per cent of cost of material, Labour and 2.00 2684.34 2688.29 2702.78
machinery excluding formwork to cater for extra lift
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.16 0.16 0.16 622.00 96.76 96.76 96.76 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 2.39 2.39 2.39 560.00 1337.78 1337.78 1337.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Add 4 per cent of cost of material, Labour and 4.00 5368.67 5376.57 5405.55
machinery excluding formwork to cater for extra lift
Page 4 of 253
CHAPTER-13
SUB-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium ref.
Specification Large Project Small Project
Project Project Project Project
Same as Item 12.8 (C) upto 5 m height, except for
formwork which shall be 10 per cent instead of 4
per cent of cost of material, labour and machinery.
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.16 0.16 0.16 622.00 96.76 96.76 96.76 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 2.39 2.39 2.39 560.00 1337.78 1337.78 1337.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.16 0.16 0.16 622.00 96.76 96.76 96.76 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 2.39 2.39 2.39 560.00 1337.78 1337.78 1337.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Add 2 per cent of cost of material, Labour and 2.00 192.36 196.31 210.80
machinery excluding formwork to cater for extra lift
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.16 0.16 0.16 622.00 96.76 96.76 96.76 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 2.39 2.39 2.39 560.00 1337.78 1337.78 1337.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Page 5 of 253
CHAPTER-13
SUB-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium ref.
Specification Large Project Small Project
Project Project Project Project
Add 4 per cent of cost of material, Labour and 4.00 4919.01 4926.91 4955.89
machinery excluding formwork to cater for extra lift
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
Page 8 of 253
CHAPTER-13
SUB-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium ref.
Specification Large Project Small Project
Project Project Project Project
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Page 11 of 253
CHAPTER-13
SUB-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium ref.
Specification Large Project Small Project
Project Project Project Project
f) Contractor's profit @ 10% on @ 10% on @ 10% on 20942.36 20969.00 21066.72
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Water for curing Kl 15.75 15.75 15.75 74.54 1174.01 1174.01 1174.01 M-191
b) Labour
For pouring and placing
Mate day 0.20 0.20 0.20 622.00 121.64 121.64 121.64 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 3.39 3.39 3.39 560.00 1897.78 1897.78 1897.78 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 12.22 1833.00 1833.00 1833.00 P&M-76001
For unloading hour 0.69 0.69 0.69 2198.00 1526.39 1526.39 1526.39 P&M-34001
Hydraulic Boom placer pump hour 0.69 0.69 0.69 4033.00 2800.69 2800.69 2800.69 P&M-36001
Water tanker ( speed @ 20km/hr and return
speed @ 30 km/hr and 30 mins for unloading )
Mate day 0.16 0.16 0.16 622.00 99.52 99.52 99.52 L-12
Blacksmith day 1.00 1.00 1.00 622.00 622.00 622.00 622.00 L-02
Mazdoor day 3.00 3.00 3.00 560.00 1680.00 1680.00 1680.00 L-13
c) Machinery
Cutting Machine hour 6.67 6.67 6.67 468.00 3120.00 3120.00 3120.00 P&M-43001
Bending Machine hour 6.67 6.67 6.67 468.00 3120.00 3120.00 3120.00 P&M-43001
Electric generator 15 KVA hour 6.67 6.67 6.67 374.00 2493.33 2493.33 2493.33 P&M-22009
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.83 109.28 P&M-72002
(ii) 14 cum capacity t.km 8 x L1 7.77 124.32 P&M-73002
(iii) 10 cum capacity t.km 8 x L1 9.62 153.92 P&M-74002
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.00 2621.00 2621.00 P&M-6001
(ii) 14 cum capacity hour 1.28 2331.00 2983.68 P&M-6002
(iii) 10 cum capacity hour 1.78 2077.00 3692.44 P&M-6003
Light weight Crane
At cutting bending yard hour 2.00 2.00 2.00 966.00 1932.00 1932.00 1932.00 P&M-63001
At site hour 2.00 2.00 2.00 966.00 1932.00 1932.00 1932.00 P&M-63001
Mate day 0.16 0.16 0.16 622.00 99.52 99.52 99.52 L-12
Blacksmith day 1.00 1.00 1.00 622.00 622.00 622.00 622.00 L-02
Mazdoor day 3.00 3.00 3.00 560.00 1680.00 1680.00 1680.00 L-13
c) Machinery
Cutting Machine hour 6.67 6.67 6.67 468.00 3120.00 3120.00 3120.00 P&M-43001
Page 12 of 253
CHAPTER-13
SUB-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium ref.
Specification Large Project Small Project
Project Project Project Project
Bending Machine hour 6.67 6.67 6.67 468.00 3120.00 3120.00 3120.00 P&M-43001
Electric generator 15 KVA hour 6.67 6.67 6.67 374.00 2493.33 2493.33 2493.33 P&M-22009
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.83 109.28 P&M-72002
(ii) 14 cum capacity t.km 8 x L1 7.77 124.32 P&M-73002
(iii) 10 cum capacity t.km 8 x L1 9.62 153.92 P&M-74002
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.00 2621.00 2621.00 P&M-6001
(ii) 14 cum capacity hour 1.28 2331.00 2983.68 P&M-6002
(iii) 10 cum capacity hour 1.78 2077.00 3692.44 P&M-6003
Light weight Crane
At cutting bending yard hour 2.00 2.00 2.00 966.00 1932.00 1932.00 1932.00 P&M-63001
At site hour 2.00 2.00 2.00 966.00 1932.00 1932.00 1932.00 P&M-63001
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 metre 31.50 31.50 31.50 150.00 4725.00 4725.00 4725.00 M-114
per cent )
Average length of weep hole is taken as one metre
for the purpose of estimating.
MS clamp each. 30.00 30.00 30.00 65.00 1950.00 1950.00 1950.00 M-122
collar for AC pipe (average) taking 10% of each. 10.00 10.00 10.00 35.00 350.00 350.00 350.00 M-056/10
above pipe rate
Cement mortar 1:3 (Rate as sub-analysis) cum 0.05 0.05 0.05 4888.87 244.44 244.44 244.44 Sub-Analysis of
Concrete - 19.01
(A)
b) Labour
Mate day 0.03 0.03 0.03 622.00 18.66 18.66 18.66 L-12
Mason day 0.50 0.50 0.50 622.00 311.00 311.00 311.00 L-11
Mazdoor day 0.25 0.25 0.25 560.00 140.00 140.00 140.00 L-13
c) Overhead charges @ 20% on (a+b) 1547.82 1547.82 1547.82
d) Contractor's profit @ 10% on (a+b+c) 928.69 928.69 928.69
Cost for 30 m = a+b+c+d 10215.62 10215.62 10215.62
Rate per m (a+b+c+d)/30 340.52 340.52 340.52
say 341.00 341.00 341.00
Note 1. In case of stone masonry, the size of the weep
hole shall be 150 mm x 80 mm or circular with 150
mm diameter.
2. For structure in stone masonry, the weep holes
shall be deemed to be included in the item of stone
masonry work and shall not be paid separately.
13.9 710.1.4. Back filling behind abutment, wing wall and return
of wall complete as per drawing and Technical
IRC:78 Specification
& 2200
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 0.28 0.28 622.00 174.16 174.16 174.16 L-12
Mazdoor day 7.00 7.00 7.00 560.00 3920.00 3920.00 3920.00 L-13
b) Material
Granular material cum 12.00 12.00 12.00 725.78 8709.30 8709.30 8709.30 M-009
c) Machinery
Plate compactor/power rammer hour 2.50 2.50 2.50 528.00 1320.00 1320.00 1320.00 P&M-46001
Water Tanker hour 0.05 0.05 0.05 904.00 45.20 45.20 45.20 P&M-11003
d) Overhead charges @ 20% on @ 20% on @ 20% on 2833.73 2833.73 2833.73
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 1700.24 1700.24 1700.24
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum of granular backfill = a+b+c+d+e 18702.63 18702.63 18702.63
b) Material
Sand cum 12.00 12.00 12.00 805.78 9669.30 9669.30 9669.30 M-006
c) Machinery
Plate compactor/power rammer hour 2.50 2.50 2.50 528.00 1320.00 1320.00 1320.00 P&M-46001
Water Tanker hour 0.06 0.06 0.06 904.00 54.24 54.24 54.24 P&M-11003
d) Overhead charges @ 20% on @ 20% on @ 20% on 3027.54 3027.54 3027.54
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 1816.52 1816.52 1816.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum of sandy backfill = a+b+c+d+e 19981.76 19981.76 19981.76
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 0.32 0.32 622.00 199.04 199.04 199.04 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 7.00 7.00 560.00 3920.00 3920.00 3920.00 L-13
Mazdoor (Skilled) day 1.00 1.00 1.00 592.00 592.00 592.00 592.00 L-15
b) Material
Filter media of stone aggregate conforming to cum 12.00 12.00 12.00 716.17 8594.07 8594.07 8594.07 M-011
clause 2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 0.06 0.06 904.00 54.24 54.24 54.24 P&M-11003
d) Overhead charges @ 20% on @ 20% on @ 20% on 2671.87 2671.87 2671.87
(a+b+c) (a+b+c) (a+b+c)
Page 13 of 253
CHAPTER-13
SUB-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium ref.
Specification Large Project Small Project
Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on 1603.12 1603.12 1603.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
cost for 10 cum of Fiter Media = a+b+c+d+e 17634.34 17634.34 17634.34
Rate per cum = (a+b+c+d+e)/10 1763.43 1763.43 1763.43
say 1763.43 1763.43 1763.43
13.11 704 Supplying & laying of drainage composite for use
behind walls, between two different fills, alongside
drains of road, below concrete lining of canals etc.
Geocomposite for planar drainage, realized by
thermobonding a draining core in extruded
monofilaments with two filtering nonwoven
geotextiles that may also be working as separation
or protecting layers. The draining three
dimensional core will have a “W” configuration as
longitudinal parallel channels. Minimum thickness
to be 7.2mm, with two filtering UV stabilized
polypropylene nonwoven geotextile of minimum
thickness of 0.75 mm having pores of 150 micron
and tensile strength of 8.0 kN/m that will be
working as separation or protecting layer,
geocomposite having in plane flow capacity of 2.1
L / (m.s) at hydraulic gradient of 1.0 & 20 kpa
pressure and tensile strength of 18 kN/m , with
mass per unit area of 740 gsm, supplied in the
form of roll for easy transportation to site of work as
per detailed specification all complete as per
directions of Engineer in charge.
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 622.000 124.40 124.40 124.40 L-12
Mazdoor day 3.000 3.000 3.000 560.000 1680.00 1680.00 1680.00 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 592.000 1184.00 1184.00 1184.00 L-15
b) Material
Geosynthetic Drainage Composite sqm 300.00 300.00 300.00 504.00 151200.00 151200.00 151200.00 M-290
Add 10 per cent of the cost of synthetic 15120.00 15120.00 15120.00
Composits for wastage and accessories for
joining sheets with the facia pannels, overlaps
and other protective elements for synthetic
Composits and other miscelleneus activities
required to complete the item in all respect
including transpotarion & takes.
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 622.000 124.40 124.40 124.40 L-12
Mazdoor day 3.000 3.000 3.000 560.000 1680.00 1680.00 1680.00 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 592.000 1184.00 1184.00 1184.00 L-15
b) Material
Geosynthetic Drainage Composite sqm 300.00 300.00 300.00 600.00 180000.00 180000.00 180000.00 M-291
Add 10 per cent of the cost of synthetic 18000.00 18000.00 18000.00
Composits for wastage and accessories for
joining sheets with the facia pannels, overlaps
and other protective elements for synthetic
Composits and other miscelleneus activities
required to complete the item in all respect
including transpotarion & takes.
Page 14 of 253
CHAPTER-13
SUB-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium ref.
Specification Large Project Small Project
Project Project Project Project
cost for 250 tonnes capacity bearing = a+b+c+d 107835.18 107835.18 107835.18
Add 1 per cent of cost of bearing assembly for 1318.50 1318.50 1318.50
foundation anchorage bolts, lifting
arrangements, grease and other consumables.
Add 1 per cent for foundation anchorage bolts 170.40 170.40 170.40
and consumables.
c) Overhead charges @ 20% on @ 20% on @ 20% on 3620.74 3620.74 3620.74
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 2172.45 2172.45 2172.45
(a+b+c) (a+b+c) (a+b+c)
cost for 80 tonnes capacity bearing = a+b+c+d 23896.91 23896.91 23896.91
a) Labour
Mate day 0.06 0.06 0.06 622.00 37.32 37.32 37.32 L-12
Mazdoor day 1.00 1.00 1.00 560.00 560.00 560.00 560.00 L-13
Mazdoor (Skilled) day 0.50 0.50 0.50 592.00 296.00 296.00 296.00 L-15
b) Material
Elastomeric bearing assembly consisting of 7 each. 1.00 1.00 1.00 16900.00 16900.00 16900.00 16900.00 M-066
layers of elastomer bonded to 6 nos. internal
reinforcing steel laminates by the process of
vulcanisation, complete with all components as
per drawing and Technical Specifications.
Add 1 per cent of cost of bearing assembly for 169.00 169.00 169.00
foundation anchorage bolts and consumables.
Page 15 of 253
CHAPTER-13
SUB-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium ref.
Specification Large Project Small Project
Project Project Project Project
cost for 80 tonnes of capacity bearing = a+b+c+d 15259.31 15259.31 15259.31
Add 1 per cent of cost of bearing assembly for 497.80 497.80 497.80
foundation anchorage bolts and consumables.
c) Machinery
2133.00 4266.00 4266.00 4266.00 P&M-63006
Crane 35 tonne capacity (For Fabrication) Hrs 2.000 2.000 2.000
Truck 10 T Capacity (For Fabrication) Hrs 2.000 2.000 2.000 1590.00 3180.00 3180.00 3180.00 P&M-6004
Erection charges @ 15% of the above 15591.76 15591.76 15591.76
Basic Cost of Labour, Material & Machinery
119537.00 119537.00 119537.00
(a+b+c) for 1 MT
Page 16 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
14.1 1500 Furnishing and Placing Reinforced/ Prestressed
&1600 cement concrete in super-structure as per drawing and
1700 Technical Specification
A RCC Grade M20
14.1A Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.00 120.00 120.00 3736.21 448344.68 448344.68 448344.68 Sub-Analysis of
Concrete - 19.05
Water for curing Kl 63.00 63.00 63.00 74.54 4696.02 4696.02 4696.02 M-191
b) Labour
For pouring and placing
Mate day 0.36 0.36 0.36 622.00 225.30 225.30 225.30 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 7.56 7.56 7.56 560.00 4231.11 4231.11 4231.11 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-km 300 x L 300 x L 300 x L 12.22 7332.00 7332.00 7332.00 P&M-76001
Kilometer
For unloading hour 2.78 2.78 2.78 2198.00 6105.56 6105.56 6105.56 P&M-34001
Hydraulic Boom placer pump hour 2.78 2.78 2.78 4033.00 11202.78 11202.78 11202.78 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 1 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
d) Formwork and staging 30 per cent of (a+b+c) 30.00 146346.00 146583.00 147452.40
Basic Cost of Labour, Material & Machinery (a+b+c) 487820.00 488610.00 491508.00
for 120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 170737.00 171013.50 172027.80
Water for curing Kl 63.00 63.00 63.00 74.54 4696.02 4696.02 4696.02 M-191
b) Labour
For pouring and placing
Mate day 0.36 0.36 0.36 622.00 225.30 225.30 225.30 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 7.56 7.56 7.56 560.00 4231.11 4231.11 4231.11 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-km 300 x L 300 x L 301 x L 12.22 7332.00 7332.00 7332.00 P&M-76001
Kilometer
For unloading hour 2.78 2.78 2.78 2198.00 6105.56 6105.56 6105.56 P&M-34001
Hydraulic Boom placer pump hour 2.78 2.78 2.78 4033.00 11202.78 11202.78 11202.78 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Basic Cost of Labour, Material & Machinery (a+b+c) 534120.00 534910.00 537808.00
for 120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 133530.00 133727.50 134452.00
Basic Cost of Labour, Material & Machinery (a+b+c) 534120.00 534910.00 537808.00
for 120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 160236.00 160473.00 161342.40
Page 2 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
f) Contractor's profit @ 10% on @ 10% on @ 10% on 83322.72 83445.96 83898.05
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 916549.92 917905.56 922878.53
Rate per cum = (a+b+c+d+e+f)/120 7637.92 7649.21 7690.65
say 7638.00 7649.00 7691.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 534120.00 534910.00 537808.00
for 120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 133530.00 133727.50 134452.00
Basic Cost of Labour, Material & Machinery (a+b+c) 534120.00 534910.00 537808.00
for 120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 160236.00 160473.00 161342.40
Basic Cost of Labour, Material & Machinery (a+b+c) 534120.00 534910.00 537808.00
for 120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 186942.00 187218.50 188232.80
Water for curing Kl 63.00 63.00 63.00 74.54 4696.02 4696.02 4696.02 M-191
b) Labour
For pouring and placing
Mate day 0.36 0.36 0.36 622.00 225.30 225.30 225.30 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 7.56 7.56 7.56 560.00 4231.11 4231.11 4231.11 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-km 300 x L 300 x L 301 x L 12.22 7332.00 7332.00 7332.00 P&M-76001
Kilometer
For unloading hour 2.78 2.78 2.78 2198.00 6105.56 6105.56 6105.56 P&M-34001
Hydraulic Boom placer pump hour 2.78 2.78 2.78 4033.00 11202.78 11202.78 11202.78 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 3 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Rate per cum = (a+b+c+d+e+f)/120 59.20 59.28 59.60
say 59.00 59.00 60.00
14.1C (i) (q) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) 538200.00 538920.00 541800.00
for 120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 134550.00 134730.00 135450.00
Basic Cost of Labour, Material & Machinery (a+b+c) 538200.00 538920.00 541800.00
for 120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 161460.00 161676.00 162540.00
Basic Cost of Labour, Material & Machinery (a+b+c) 538200.00 538920.00 541800.00
for 120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 188370.00 188622.00 189630.00
Water for curing Kl 63.00 63.00 63.00 74.54 4696.02 4696.02 4696.02 M-191
b) Labour
For pouring and placing
Mate day 0.36 0.36 0.36 622.00 225.30 225.30 225.30 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 7.56 7.56 7.56 560.00 4231.11 4231.11 4231.11 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-km 300 x L 300 x L 300 x L 12.22 7332.00 7332.00 7332.00 P&M-76001
Kilometer
For unloading hour 2.78 2.78 2.78 2198.00 6105.56 6105.56 6105.56 P&M-34001
Hydraulic Boom placer pump hour 2.78 2.78 2.78 4033.00 11202.78 11202.78 11202.78 P&M-36001
Page 4 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Basic Cost of Labour, Material & Machinery (a+b+c) 551522.00 552312.00 555210.00
for 120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 126850.06 127031.76 127698.30
Basic Cost of Labour, Material & Machinery (a+b+c) 551522.00 552312.00 555210.00
for 120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 154426.16 154647.36 155458.80
Basic Cost of Labour, Material & Machinery (a+b+c) 551522.00 552312.00 555210.00
for 120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 154426.16 154647.36 155458.80
Basic Cost of Labour, Material & Machinery (a+b+c) 551522.00 552312.00 555210.00
for 120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 182002.26 182262.96 183219.30
Page 5 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent
of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 551522.00 552312.00 555210.00
for 120 cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 209578.36 209878.56 210979.80
Water for curing Kl 63.00 63.00 63.00 74.54 4696.02 4696.02 4696.02 M-191
b) Labour
For pouring and placing
Mate day 0.36 0.36 0.36 622.00 225.30 225.30 225.30 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 7.56 7.56 7.56 560.00 4231.11 4231.11 4231.11 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-km 300 x L 300 x L 300 x L 12.22 7332.00 7332.00 7332.00 P&M-76001
Kilometer
For unloading hour 2.78 2.78 2.78 2198.00 6105.56 6105.56 6105.56 P&M-34001
Hydraulic Boom placer pump hour 2.78 2.78 2.78 4033.00 11202.78 11202.78 11202.78 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Basic Cost of Labour, Material & Machinery (a+b+c) 563047.00 563837.00 566735.00
for 120 cum
Page 6 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
d) Formwork and staging 23 per cent of (a+b+c) 23.00 129500.81 129682.51 130349.05
Basic Cost of Labour, Material & Machinery (a+b+c) 563047.00 563837.00 566735.00
for 120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 157653.16 157874.36 158685.80
Basic Cost of Labour, Material & Machinery (a+b+c) 563047.00 563837.00 566735.00
for 120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 157653.16 157874.36 158685.80
Basic Cost of Labour, Material & Machinery (a+b+c) 563047.00 563837.00 566735.00
for 120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 185805.51 186066.21 187022.55
Page 7 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
say 9166.00 9179.00 9226.00
14.1E (r) Height above 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) 563047.00 563837.00 566735.00
for 120 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 326567.26 327025.46 328706.30
Water for curing Kl 63.00 63.00 63.00 74.54 4696.02 4696.02 4696.02 M-191
b) Labour
For pouring and placing
Mate day 0.36 0.36 0.36 622.00 225.30 225.30 225.30 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 7.56 7.56 7.56 560.00 4231.11 4231.11 4231.11 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-km 300 x L 300 x L 300 x L 12.22 7332.00 7332.00 7332.00 P&M-76001
Kilometer
For unloading hour 2.78 2.78 2.78 2198.00 6105.56 6105.56 6105.56 P&M-34001
Hydraulic Boom placer pump hour 2.78 2.78 2.78 4033.00 11202.78 11202.78 11202.78 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Basic Cost of Labour, Material & Machinery (a+b+c) 565627.00 566417.00 569315.00
for 120 cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 118781.67 118947.57 119556.15
Basic Cost of Labour, Material & Machinery (a+b+c) 565627.00 566417.00 569315.00
for 120 cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 147063.02 147268.42 148021.90
Page 8 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
d) Formwork and staging 21 per cent of (a+b+c) 21.00 118781.67 118947.57 119556.15
Basic Cost of Labour, Material & Machinery (a+b+c) 565627.00 566417.00 569315.00
for 120 cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 147063.02 147268.42 148021.90
Basic Cost of Labour, Material & Machinery (a+b+c) 565627.00 566417.00 569315.00
for 120 cum
d) Formwork and staging 31 per cent of (a+b+c) 31.00 175344.37 175589.27 176487.65
Water for curing Kl 63.00 63.00 63.00 74.54 4696.02 4696.02 4696.02 M-191
b) Labour
For pouring and placing
Mate day 0.36 0.36 0.36 622.00 225.30 225.30 225.30 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Page 9 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Mazdoor day 7.56 7.56 7.56 560.00 4231.11 4231.11 4231.11 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-km 300 x L 300 x L 300 x L 12.22 7332.00 7332.00 7332.00 P&M-76001
Kilometer
For unloading hour 2.78 2.78 2.78 2198.00 6105.56 6105.56 6105.56 P&M-34001
Hydraulic Boom placer pump hour 2.78 2.78 2.78 4033.00 11202.78 11202.78 11202.78 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Basic Cost of Labour, Material & Machinery (a+b+c) 614647.00 615437.00 618335.00
for 120 cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 276591.15 276946.65 278250.75
Basic Cost of Labour, Material & Machinery (a+b+c) 614647.00 615437.00 618335.00
for 120 cum
d) Formwork and staging 55 per cent of (a+b+c) 55.00 338055.85 338490.35 340084.25
Water for curing Kl 63.00 63.00 63.00 74.54 4696.02 4696.02 4696.02 M-191
b) Labour
For pouring and placing
Mate day 0.36 0.36 0.36 622.00 225.30 225.30 225.30 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 7.56 7.56 7.56 560.00 4231.11 4231.11 4231.11 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-km 300 x L 300 x L 300 x L 12.22 7332.00 7332.00 7332.00 P&M-76001
Kilometer
For unloading hour 2.78 2.78 2.78 2198.00 6105.56 6105.56 6105.56 P&M-34001
Hydraulic Boom placer pump hour 2.78 2.78 2.78 4033.00 11202.78 11202.78 11202.78 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 10 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 623923.00 624712.00 627610.00
for 120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 218373.05 218649.20 219663.50
Basic Cost of Labour, Material & Machinery (a+b+c) 623923.00 624712.00 627610.00
for 120 cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 280765.35 281120.40 282424.50
Basic Cost of Labour, Material & Machinery (a+b+c) 623923.00 624712.00 627610.00
for 120 cum
d) Formwork and staging 55 per cent of (a+b+c) 55.00 343157.65 343591.60 345185.50
Water for curing Kl 63.00 63.00 63.00 74.54 4696.02 4696.02 4696.02 M-191
b) Labour
For pouring and placing
Mate day 0.36 0.36 0.36 622.00 225.30 225.30 225.30 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 7.56 7.56 7.56 560.00 4231.11 4231.11 4231.11 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-km 300 x L 300 x L 300 x L 12.22 7332.00 7332.00 7332.00 P&M-76001
Kilometer
For unloading hour 2.78 2.78 2.78 2198.00 6105.56 6105.56 6105.56 P&M-34001
Hydraulic Boom placer pump hour 2.78 2.78 2.78 4033.00 11202.78 11202.78 11202.78 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 11 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Basic Cost of Labour, Material & Machinery (a+b+c) 623923.00 624712.00 627610.00
for 120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 218373.05 218649.20 219663.50
Basic Cost of Labour, Material & Machinery (a+b+c) 623923.00 624712.00 627610.00
for 120 cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 280765.35 281120.40 282424.50
Basic Cost of Labour, Material & Machinery (a+b+c) 623923.00 624712.00 627610.00
for 120 cum
d) Formwork and staging 55 per cent of (a+b+c) 55.00 343157.65 343591.60 345185.50
Water for curing Kl 63.00 63.00 63.00 74.54 4696.02 4696.02 4696.02 M-191
b) Labour
For pouring and placing
Mate day 0.36 0.36 0.36 622.00 225.30 225.30 225.30 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 7.56 7.56 7.56 560.00 4231.11 4231.11 4231.11 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-km 300 x L 300 x L 300 x L 12.22 7332.00 7332.00 7332.00 P&M-76001
Kilometer
For unloading hour 2.78 2.78 2.78 2198.00 6105.56 6105.56 6105.56 P&M-34001
Hydraulic Boom placer pump hour 2.78 2.78 2.78 4033.00 11202.78 11202.78 11202.78 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Basic Cost of Labour, Material & Machinery (a+b+c) 623923.00 624712.00 627610.00
for 120 cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 280765.35 281120.40 282424.50
Page 12 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
f) Contractor's profit @ 10% on @ 10% on @ 10% on 108562.60 108699.89 109204.14
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1194188.62 1195698.77 1201245.54
Rate per cum = (a+b+c+d+e+f)/120 9951.57 9964.16 10010.38
say 9952.00 9964.00 10010.00
14.1H (i) (r) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c) 623923.00 624712.00 627610.00
for 120 cum
d) Formwork and staging 55 per cent of (a+b+c) 55.00 343157.65 343591.60 345185.50
Binding wire Kg 48.00 48.00 48.00 67.00 3216.00 3216.00 3216.00 M-072
b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate day 0.16 0.16 0.16 622.00 99.52 99.52 99.52 L-12
Blacksmith day 1.00 1.00 1.00 622.00 622.00 622.00 622.00 L-02
Mazdoor day 3.00 3.00 3.00 560.00 1680.00 1680.00 1680.00 L-13
c) Machinery
Cutting Machine hour 8.00 8.00 8.00 468.00 3744.00 3744.00 3744.00 P&M-43001
Bending Machine hour 8.00 8.00 8.00 468.00 3744.00 3744.00 3744.00 P&M-43001
Electric generator 15 KVA hour 8.00 8.00 8.00 374.00 2992.00 2992.00 2992.00 P&M-22009
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8xL 6.83 109.28 P&M-72002
(ii) 14 cum capacity t.km 8xL 7.77 124.32 P&M-73002
(iii) 10 cum capacity t.km 8xL 9.62 153.92 P&M-74002
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.00 2621.00 2621.00 P&M-6001
(ii) 14 cum capacity hour 1.28 2331.00 2983.68 P&M-6002
(iii) 10 cum capacity hour 1.78 2077.00 3692.44 P&M-6003
Light weight Crane
At cutting bending yard hour 2.00 2.00 2.00 966.00 1932.00 1932.00 1932.00 P&M-63001
At site hour 2.00 2.00 2.00 966.00 1932.00 1932.00 1932.00 P&M-63001
Basic Cost of Labour, Material & Machinery (a+b) for 1 67937.00 67984.00 68076.00
MT
Page 13 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Sheathing duct ID 66 mm along with 5 per cent metre 42.00 42.00 42.00 60.00 2520.00 2520.00 2520.00 M-166
extra length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate, each 2.00 2.00 2.00 27.00 54.00 54.00 54.00 M-189
permanent wedges etc
Cement for grouting including 3 per cent wastage tonne 0.125 0.125 0.125 6500.00 812.50 812.50 812.50 M-081
@ 3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, =
125 kg)
Add 0.50 per cent cost of material for Spacers, 1680.94 1680.94 1680.94
Insulation tape and miscellaneous items
b) Labour
i) For making and fixing cables, anchorages
Mate day 0.16 0.16 0.16 622.00 99.52 99.52 99.52 L-12
Blacksmith day 1.00 1.00 1.00 622.00 622.00 622.00 622.00 L-02
Mazdoor day 3.00 3.00 3.00 560.00 1680.00 1680.00 1680.00 L-13
ii) For prestressing
Mate/Supervisor day 0.05 0.05 0.05 622.00 31.10 31.10 31.10 L-12
Prestressing operator / Fitter day 0.25 0.25 0.25 622.00 155.50 155.50 155.50 L-08
Mazdoor day 1.00 1.00 1.00 560.00 560.00 560.00 560.00 L-13
iii) For grouting
Mate/Supervisor day 0.05 0.05 0.05 622.00 31.10 31.10 31.10 L-12
Mason day 0.25 0.25 0.25 622.00 155.50 155.50 155.50 L-11
Mazdoor day 1.00 1.00 1.00 560.00 560.00 560.00 560.00 L-13
c) Machinery
Stressing jack with pump hour 2.50 2.50 2.50 513.00 1282.50 1282.50 1282.50 P&M-65001
Grouting pump with agitator hour 1.00 1.00 1.00 300.00 300.00 300.00 300.00 M-110
Generator 33 KVA. hour 3.50 3.50 3.50 659.00 2306.50 2306.50 2306.50 P&M-22008
d) Overhead charges @ 20% on @ 20% on @ 20% on 8616.68 8616.68 8616.68
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 5170.01 5170.01 5170.01
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 0.377 MT (a+b+c+d+e) 56870.07 56870.07 56870.07
Rate per MT = (a+b+c+d+e)/0.377 150848.99 150848.99 150848.99
say 150849.00 150849.00 150849.00
Note Cost of HT steel has been taken for delivery at site.
Hence carriage has not been considered.
14.4 2702 Providing and laying Cement concrete wearing coat M-
30 grade including reinforcement complete as per
drawing and Technical Specifications
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of cum 1.00 1.00 1.00 4485.00 4485.00 4485.00 4485.00 Item No. - 14.1
concrete in Item 14.1 excluding formwork C
HYSD bar reinforcement Rate as per item No tonne 0.075 0.075 0.075 67937.00 5095.28 5095.28 5095.28 Item No. - 14.2
14.2(Excluding OH & CP)
b) Labour
Mazdoor for cleaning deck slab concrete surface. day 0.15 0.15 0.15 560.00 84.00 84.00 84.00 L-13
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.49 0.49 0.49 622.00 304.78 304.78 304.78 L-12
Mazdoor day 11.00 11.00 11.00 560.00 6160.00 6160.00 6160.00 L-13
Mazdoor (Skilled) day 1.25 1.25 1.25 592.00 740.00 740.00 740.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 0.06 0.06 951.00 57.06 57.06 57.06 P&M-23001
Air compressor 250 cfm hour 0.06 0.06 0.06 550.00 33.00 33.00 33.00 P&M-15001
Mastic cooker 1 tonne capacity hour 6.00 6.00 6.00 600.00 3600.00 3600.00 3600.00 P&M-27001
Bitumen boiler 1500 litres capacity hour 6.00 6.00 6.00 664.00 3984.00 3984.00 3984.00 P&M-26001
Page 14 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Tractor for towing and positioning of mastic cooker hour 1.00 1.00 1.00 820.00 820.00 820.00 820.00 P&M-12001
and bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
ii) Crusher stone dust @ 31.9 per cent by weight of cum 0.39 0.39 0.39 302.41 117.94 117.94 117.94 M-020
mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 =
0.39
iii) Lime stone dust filler with calcium carbonate tonne 0.36 0.36 0.36 6500.00 2340.00 2340.00 2340.00 M-190
content not less than 80 per cent by weight @
17.92 per cent by weight of mix = 2 x 17.92/100 =
0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ cum 0.55 0.55 0.55 860.76 473.42 473.42 473.42 M-050
40 per cent by weight of mix = 2 x 40/100 = 0.8 MT
= 0.8/1.456 = 0.55
v) Pre-coated stone chips of 9.5 mm nominal size cum 0.036 0.036 0.036 2250.00 81.00 81.00 81.00 M-141
for skid resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by kg 1.05 1.05 1.05 34.51 36.24 36.24 36.24 M-074/1000
weight = 0.036 x 1.456 x 2/100 = 0.001048MT =
1.05kg
d) Overhead charges @ 20% on @ 20% on @ 20% on 5157.59 5157.59 5157.59
(a+b) (a+b) (a+b)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 3094.56 3094.56 3094.56
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 72.46 sqm = a+b+c+d+e 34040.13 34040.13 34040.13
Rate per sqm = (a+b+c+d+e)/72.46 469.78 469.78 469.78
say 470.00 470.00 470.00
Note 1.The rates for 6 mm or any other thickness may be
worked out on pro-rata basis.
2. Where tack coat is required to be provided before
laying mastic asphalt, the same is required to be
measured and paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI
for a specific case and is meant for estimating purposes
only. Actual design is required to be done for each
case.
5.The quantity of bitumen works out 17 per cent of the
mastic asphalt blocks without aggregates and falls
within the standards laid down by MoRTH
Specifications.
14.6 2703, Construction of precast RCC railing of M30 Grade,
1500, aggregate size not exceeding 12 mm, true to line and
1600 & grade, tolerance of vertical RCC post not to exceed 1 in
1700 500, centre to centre spacing between vertical post not
to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.09 4.09 4.09 4485.00 18352.62 18352.62 18352.62 Item No. - 14.1
concrete in Item 14.1(C) by using batching plant, C
excluding formwork i.e. per cum basic cost (a+b+c)
Add 5 per cent of above cost for form work for 917.63 917.63 917.63
casting in casting yard.
HYSD bar reinforcement Rate as per item No tonne 0.87 0.87 0.87 67937.00 58765.51 58765.51 58765.51 Item No. - 14.2
14.2(Excluding OH & CP)
Refer MoRTH SD / 202.
Add 5 per cent of (a) for handling and fixing of 3901.79 3901.79 3901.79
precast panels in position
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 16387.51 16387.51 16387.51
Page 15 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Rate per metre (a+b+c)/48 2253.28 2253.28 2253.28
say 2253.00 2253.00 2253.00
Note 1.Quantities of material have been adopted from
standard plans of MoRTH vide drawing no. SD/202.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.092 4.092 4.092 4485.00 18352.62 18352.62 18352.62 Item No. - 14.1
concrete in Item 14.1(C) by using batching plant, C
excluding formwork i.e. per cum basic cost (a+b+c)
Add 12 per cent of above cost for form work. 2202.31 2202.31 2202.31
HYSD bar reinforcement Rate as per item No tonne 0.87 0.87 0.87 67937.00 58765.51 58765.51 58765.51 Item No. - 14.2
14.2(Excluding OH & CP)
refer MoRTH SD / 202.
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 15864.09 15864.09 15864.09
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.95 2.95 2.95 65000.00 191490.00 191490.00 191490.00 M-181
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.01 1.01 1.01 65000.00 65780.00 65780.00 65780.00 M-181
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.18 0.18 0.18 65000.00 11700.00 11700.00 11700.00 M-181
4) MS bolts, nuts and washers tonne 0.15 0.15 0.15 50000.00 7500.00 7500.00 7500.00 M-129 x 1000
Add @ 5 per cent of cost of material for painting 13823.50 13823.50 13823.50
one shop coat with red oxide primer and three
coats of synthetic enamel paint and consumables to
safeguard against weathering and corrosion.
Add for cost of concrete for fixing vertical posts in 2764.70 2764.70 2764.70
the performed recess @ 1 per cent of cost of
material.
Add for electricity charges, welding and drilling 2764.70 2764.70 2764.70
equipment, electrodes and other consumables @ 1
per cent of cost of material.
b) Labour
Mate day 2.80 2.80 2.80 622.00 1741.60 1741.60 1741.60 L-12
Mazdoor (Skilled) day 30.00 30.00 30.00 592.00 17760.00 17760.00 17760.00 L-15
Mazdoor day 40.00 40.00 40.00 560.00 22400.00 22400.00 22400.00 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on 67544.90 67544.90 67544.90
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 40526.94 40526.94 40526.94
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 m steel railing = a+b+c+d 445796.34 445796.34 445796.34
Rate per metre (a+b+c+d)/100 4457.96 4457.96 4457.96
say 4458.00 4458.00 4458.00
14.9 2705 Drainage Spouts complete as per drawing and
Technical specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per Kg 4.00 4.00 4.00 75.00 300.00 300.00 300.00 M-088/1000
cent wastage
GI pipe 100mm dia metre 6.00 6.00 6.00 350.00 2100.00 2100.00 2100.00 M-056
GI bolt 10 mm Dia each 6.00 6.00 6.00 25.00 150.00 150.00 150.00 M-109
Page 16 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Galvanised MS flat clamp each 2.00 2.00 2.00 10.00 20.00 20.00 20.00 M-101
b) Labour
For fabrication
Mate day 0.02 0.02 0.02 622.00 12.44 12.44 12.44 L-12
Skilled (Blacksmith, welder etc.) day 0.02 0.02 0.02 622.00 12.44 12.44 12.44 L-02
Mazdoor day 0.02 0.02 0.02 560.00 11.20 11.20 11.20 L-13
For fixing in position
Mate day 0.01 0.01 0.01 622.00 6.22 6.22 6.22 L-12
Mason day 0.01 0.01 0.01 622.00 6.22 6.22 6.22 L-11
Mazdoor day 0.20 0.20 0.20 560.00 112.00 112.00 112.00 L-13
Add @ 5 per cent of cost of material and labour for 136.53 136.53 136.53
electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc.
14.10 2700 PCC M15 Grade leveling course below approach slab
complete as per drawing and Technical specification
Unit = 1 cum
Taking output = 1 cum
Material
Case I PCC Grade M15 using batching plant & Concrete pump
Concrete, Rate as per item No. 12.8 (A) excluding cum 1.00 4974.42 4974.42 Item No. - 12.8
formworks A
Concrete, Rate as per item No. 12.8 (A) excluding 1.00 4983.45 4983.45 Item No. - 12.8
formworks A
Concrete, Rate as per item No. 12.8 (A) excluding 1.00 5016.61 5016.61 Item No. - 12.8
formworks A
Concrete, Rate as per item No. 12.8 (A) excluding cum 1.00 5352.74 5352.74 Item No. - 12.8
formworks A
Concrete, Rate as per item No. 12.8 (A) excluding 1.00 5361.77 5361.77 Item No. - 12.8
formworks A
Concrete, Rate as per item No. 12.8 (A) excluding 1.00 5394.93 5394.93 Item No. - 12.8
formworks A
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant item of cum 1.00 1.00 1.00 4840.00 4840.00 4840.00 4840.00 Item No. - 12.8
concrete in item 12.8(G)by using batching plant, G
excluding formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)
( Refer relevant item of concrete in item No. 13.8 96.80 96.80 96.80
(G) except that form work may be added at the rate
of 2 per cent of cost against 3.5 per cent provided
in the foundation concrete.
HYSD bar reinforcement Rate as per item No tonne 0.05 0.05 0.05 8492.13 424.61 424.61 424.61 Item No. - 14.2
14.2(Excluding OH & CP)
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 1072.28 1072.28 1072.28
Page 17 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
To be taken as per the prevailing market rates.
Note Contractors generally do not have expertise for this
item . The job is therefore, got done from specialised
firms who have the expertise in the field of construction
chemicals. The prevailing rate in the market is required
to be ascertained from the market and added in the
cost estimate. Detailed guidelines in this regard have
been issued by MoRTH vide their circular no. RW/NH-
34041/44/91-S&R dated 21.3.2000.
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) cum 1.00 1.00 1.00 6500.00 6500.00 6500.00 6500.00 M-081
Water for curing Kl 0.53 0.53 0.53 955.78 501.78 501.78 501.78 M-004
HYSD steel . tonne 0.10 0.10 0.10 62000.00 6200.00 6200.00 6200.00 M-083
HT strand with 5 per cent as wastage and extra tonne 0.06 0.06 0.06 78525.27 4711.52 4711.52 4711.52 M-118
length for anchoring
LDO for steam curing Litre 37.00 37.00 37.00 30.00 1110.00 1110.00 1110.00 M-121
Add consumables such as binding wire, foam, 120.22 120.22 120.22
packing tape, shuttering oil, HDPE pipe for
unbonding of strand, bolt & nuts etc @ 1 per cent
of material cost
b) Labour
(i) Cutting, bending, making reinforcement cage,
placing in position, binding etc. complete
Mate day 0.12 0.12 0.12 622.00 74.64 74.64 74.64 L-12
Mazdoor (Skilled) day 1.00 1.00 1.00 592.00 592.00 592.00 592.00 L-15
Mazdoor day 2.00 2.00 2.00 560.00 1120.00 1120.00 1120.00 L-13
(iv) Concreting by Batching plant and stationary
concrete pump
Mate day 0.03 0.03 0.03 622.00 18.66 18.66 18.66 L-12
Mazdoor (Skilled) day 0.05 0.05 0.05 592.00 29.60 29.60 29.60 L-15
Mazdoor day 0.60 0.60 0.60 560.00 336.00 336.00 336.00 L-13
(v) Steam curing and manual curing
Mate day 0.01 0.01 0.01 622.00 6.22 6.22 6.22 L-12
Mazdoor day 0.35 0.35 0.35 560.00 196.00 196.00 196.00 L-13
(vi) Handling of precast girder, stacking in stockyard
and again loading in trailor
Mate day 0.01 0.01 0.01 622.00 6.22 6.22 6.22 L-12
Mazdoor day 0.25 0.25 0.25 560.00 140.00 140.00 140.00 L-13
(vii) Placement of girders in position over pier caps
including placement of sand jacks, channel, levelling
etc.
Mate day 0.01 0.01 0.01 622.00 6.22 6.22 6.22 L-12
Mazdoor (Skilled) day 0.06 0.06 0.06 592.00 35.52 35.52 35.52 L-15
Mazdoor day 0.24 0.24 0.24 560.00 134.40 134.40 134.40 L-13
c) Machinery
i) At casting yard
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-km 2.5 x L 2.5 x L 2.5 x L 12.22 61.10 61.10 61.10 P&M-76001
Kilometer
For unloading hour 0.02 0.02 0.02 2198.00 50.88 50.88 50.88 P&M-34001
Hydraulic Boom placer pump hour 0.02 0.02 0.02 4033.00 93.36 93.36 93.36 P&M-36001
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Page 18 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Crane 35 tonne capacity hour 0.15 1.15 2.15 2133.00 319.95 2452.95 4585.95 P&M-63006
Trailer 30 tonne capacity for transporting to site. tonne.km 2.5xL 2.5xL 2.5xL 6.83 34.15 34.15 34.15 P&M-72002
(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement. hour 0.15 1.15 2.15 2331.00 349.65 2680.65 5011.65 P&M-6002
Cost of formwork, steam curing arrangement, 1231.89 1455.42 1679.83
pretensioning arrangement etc @ 5 per cent of
cost material, labour and machinery
d) Overhead charges @ 20% on @ 20% on @ 20% on 3773.60 4712.42 5654.94
(a+b) (a+b) (a+b)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 2264.16 2827.45 3392.96
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 24905.78 31102.00 37322.58
say 24906.00 31102.00 37323.00
14.14 1700 & Providing and fixing Helical pipes in voided concrete
1800 slabs
Unit = 1 RM
Taking output = 1 RM
a) Material
Helical pipes 600mm diameter metre 1.00 1.00 1.00 140.00 140.00 140.00 140.00 M-116
Tie rods 20mm diameter each 1.00 1.00 1.00 65.00 65.00 65.00 65.00 M-185
Consumables for sealing joints etc.@ 5 per cent of 10.25 10.25 10.25
cost of material
b) Labour
Mate day 0.01 0.01 0.01 622.00 6.22 6.22 6.22 L-12
Fitter day 0.05 0.05 0.05 622.00 31.10 31.10 31.10 L-08
Mazdoor day 0.20 0.20 0.20 560.00 112.00 112.00 112.00 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on 72.91 72.91 72.91
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 43.75 43.75 43.75
(a+b+c) (a+b+c) (a+b+c)
Rate per cum (a+b+c+d) 481.23 481.23 481.23
say 481.00 481.00 481.00
14.15 800 Crash Barriers
The rate analysis for rigid crash barrier in reinforced
cement concrete, semi-rigid crash barrier with metal
beam and flexible crash barrier with wire ropes have
been made and included in chapter-8 on Traffic and
Transportation.
14.16 800 Painting on concrete surface
Providing and applying 2 coats of water based cement
paint to unplastered concrete surface after cleaning the
surface of dirt, dust, oil, grease, efflorescence and
applying paint @ of 1 litre for 2 sqm.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 0.01 0.01 622.00 6.22 6.22 6.22 L-12
Painter day 0.25 0.25 0.25 622.00 155.50 155.50 155.50 L-18
Mazdoor (Skilled) day 0.25 0.25 0.25 592.00 148.00 148.00 148.00 L-15
b) Material
Water based paint of approved quality for cement Litres 5.00 5.00 5.00 120.00 600.00 600.00 600.00 M-192
concrete surface
c) Overhead charges @ 20% on @ 20% on @ 20% on 181.94 181.94 181.94
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 109.17 109.17 109.17
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm (a+b+c+d) 1200.83 1200.83 1200.83
Rate per sqm (a+b+c+d)/10 120.08 120.08 120.08
say 120.00 120.00 120.00
14.17 2605 Filler joint
(i) Providing & fixing 2 mm thick corrugated copper plate
in expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mazdoor day 0.50 0.50 0.50 560.00 280.00 280.00 280.00 L-13
Mazdoor (Skilled) day 0.50 0.50 0.50 592.00 296.00 296.00 296.00 L-15
b) Material
Copper plate - 12m long x 250 mm wide kg 55.00 55.00 55.00 620.00 34100.00 34100.00 34100.00 M-087
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55
kg.
c) Overhead charges @ 20% on @ 20% on @ 20% on 6940.18 6940.18 6940.18
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 4164.11 4164.11 4164.11
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 45805.16 45805.16 45805.16
Rate per m = (a+b+c+d)/12 3817.10 3817.10 3817.10
say 3817.00 3817.00 3817.00
14.17 (ii) Providing & fixing 20 mm thick compressible fibre board
in expansion joint complete as per drawing & Technical
Specification.
Page 19 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 0.008 0.008 622.00 4.98 4.98 4.98 L-12
Mazdoor day 0.10 0.10 0.10 560.00 56.00 56.00 56.00 L-13
Mazdoor (Skilled) day 0.10 0.10 0.10 592.00 59.20 59.20 59.20 L-15
b) Material
20 mm thick compressible fibre board 12 m long x sqm 3.00 3.00 3.00 115.00 345.00 345.00 345.00 M-085
25 cm deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 20% on @ 20% on @ 20% on 93.04 93.04 93.04
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 55.82 55.82 55.82
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 614.03 614.03 614.03
Rate per m = (a+b+c+d)/12 51.17 51.17 51.17
say 51.00 51.00 51.00
14.17 (iii) Providing and fixing in position 20 mm thick
premoulded joint filler in expansion joint for fixed ends
of simply supported spans not exceeding 10 m to cater
for a horizontal movement upto 20 mm, covered with
sealant complete as per drawing and technical
specifications.
the rates at Sl. No. i), ii), iii) & iv) shall be added
14.18 2600 Asphaltic Plug joint
Providing and laying of asphaltic plug joint to provide
for horizontal movement of 25 mm and vertical
movement of 2 mm, depth of joint varying from 75 mm
to 100 mm, width varying from 500 mm to 750 mm (in
traffic direction), covered with a closure plate of 200mm
x 6mm of weldable structural steel conforming to IS:
2062, asphaltic plug to consist of polymer modified
bitumen binder, carefully selected single size aggregate
of 12.5 mm nominal size and a heat resistant foam
caulking/backer rod, all as per approved drawings and
specifications.
Page 20 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Mazdoor (Skilled) day 0.30 0.30 0.30 592.00 177.60 177.60 177.60 L-15
b) Material
Crushed stone aggregate 12.5 mm nominal size cum 0.75 0.75 0.75 860.76 645.57 645.57 645.57 M-051
Polymer modified bitumen kg 77.50 77.50 77.50 35.01 2713.46 2713.46 2713.46 M-078 / 1000
2.4 Galvanised structural steel plate 200 mm wide,6 kg 113.00 113.00 113.00 95.00 10735.00 10735.00 10735.00 M-103
mm thick, 12 m long (2.4 sqm) @ 47.10 kg/sqm
including 5 per cent wastage
Add 1 per cent for welding and foam 148.64 148.64 148.64
caulking/backer rod and other incidentals.
c) Machinery
Mastic cooker 1 tonne capacity hour 1.00 1.00 1.00 600.00 600.00 600.00 600.00 P&M-27001
Smooth 3-wheeled steel roller 8-10 capacity hour 0.50 0.50 0.50 1864.00 932.00 932.00 932.00 P&M-8001
c) Overhead charges @ 20% on @ 20% on @ 20% on 3308.92 3308.92 3308.92
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1985.35 1985.35 1985.35
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m asphalt plug joint = (a+b+c+d+e) 21838.89 21838.89 21838.89
Rate per m = (a+b+c+d+e)/12 1819.91 1819.91 1819.91
say 1820.00 1820.00 1820.00
Note The nominal size of aggregates shall be 12.5 mm for
depth of joint upto 75 mm and 20 mm for joints of depth
more than 75 mm.
14.19 2605 Elastomeric Slab Steel Expansion Joint
Providing and laying of an elastomeric slab steel
expansion joint, catering to right or skew (less than 20
deg., moderately curved with maximum horizontal
movement upto 50 mm, complete as per approved
drawings and standard specifications to be installed by
the manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation and clause
2605 of MoRTH specifications for road & bridge works.
Add 5 per cent of cost of material for anchorage 9900.00 9900.00 9900.00
reinforcement, welding and other incidentals.
Add 5 per cent of cost of above for structural steel 2145.30 2145.30 2145.30
for anchorage, welding and other incidentals.
Page 21 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Preformed continuous chloroprene elastomer or metre 12.00 12.00 12.00 35.00 420.00 420.00 420.00 M-142
closed cell foam sealing element with high tear
strength, vulcanised in a single operation for the full
length of a joint to ensure water tightness.
Add 1 per cent of cost of sealing element for 4.20 4.20 4.20
lubricant-cum-adhesive and other consumables.
Page 22 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
c) Overhead charges @ 20% on @ 20% on @ 20% on 39046.33 39046.33 39046.33
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 23427.80 23427.80 23427.80
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m Modular strip/box seal joint = (a+b+c+d) 257705.75 257705.75 257705.75
Page 23 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Supply of a modular box/box seal joint assembly metre 12.00 12.00 12.00 15600.00 187200.00 187200.00 187200.00 M-127
containing 3 modules/cells and comprising of edge
beams, two central beams, chloroprene seal,
anchorage elements, support and control system,
all steel sections protected against corrosion and
installed by the manufacturer or his authorised
representative.
Unit = Nos.
Taking output = 1 Nos.
a) Labour
Mate day 0.006 0.006 0.006 622.00 3.73 3.73 3.73 L-12
Painter day 0.100 0.100 0.100 622.00 62.20 62.20 62.20 L-18
Mazdoor day 0.050 0.050 0.050 560.00 28.00 28.00 28.00 L-13
b) Material
230.00 69.00 69.00 69.00 M-131
Paint conforming to requirement of clause 803.3. Litre 0.300 0.300 0.300
c) Machinery
Crane 35 tonne capacity (For Fabrication) Hrs 2.000 2.000 2.000 2133.00 4266.00 4266.00 4266.00 P&M-63006
Truck 10 T Capacity (For Fabrication) Hrs 2.000 2.000 2.000 1590.00 3180.00 3180.00 3180.00 P&M-6004
Erection charges @ 25% of the above 25986.26 25986.26 25986.26
Basic Cost of Labour, Material & Machinery (a+b+c) for
129932.00 129932.00 129932.00
1 MT
Page 24 of 253
CHAPTER-14
SUPER-STRUCTURE
Amount
Reference to Quantity
Rate (Rs.) Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
say 171509.00 171509.00 171509.00
Page 25 of 253
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
15.1 2503 Providing and laying boulders apron on river bed for
protection against scour with stone boulders weighing
not less than 40 kg each complete as per drawing and
Technical specification.
Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63 cum
a) Material
4mm GI wire crates woven in mesh size of 100 sqm 22.00 22.00 22.00 210.00 4620.00 4620.00 4620.00 M-102
mm x 100 mm.
Stone cum 5.63 5.63 5.63 420.14 2365.36 2365.36 2365.36 M-003
Stone Spalls cum 1.13 1.13 1.13 302.41 341.72 341.72 341.72 M-008
b) Labour
Mate day 0.18 0.18 0.18 622.00 111.96 111.96 111.96 L-12
Mazdoor (Skilled) day 1.50 1.50 1.50 592.00 888.00 888.00 888.00 L-15
Mazdoor day *3.00 *3.00 *3.00 560.00 1680.0 1680.0 1680.0 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on 2001.4 2001.4 2001.4
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1200.85 1200.85 1200.85
(a+b+c) (a+b+c) (a+b+c)
Cost for 5.63 cum = a+b+c+d 13209.30 13209.30 13209.30
Rate per cum = (a+b+c+d)/5.63 2346.23 2346.23 2346.23
say 2346.00 2346.00 2346.00
* Including excavation for trimming for preparation of
bed.
Note Readymade woven wire crate rolls have been
considered in the rate analysis. In case readymade
rolls are not available, GI wire 4mm dia. @ 32 kg per
10 sqm may be provided. In that case 2 per cent of
the cost of GI wire may be added for weaving the wire
crates.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 cum 1.00 1.00 1.00 3631.00 3631.00 3631.00 3631.00 Item No. - 12.8 A
(A) including OH & CP
Add 2 per cent of cost to account for excavation 72.62 72.62 72.62
for preparation of bed, nominal surface
reinforcement and filling of granular material in
recesses between blocks.
Rate per cum 3703.62 3703.62 3703.62
say 3704.00 3704.00 3704.00
15.4 2504 Providing and laying Pitching on slopes laid over
prepared filter media including boulder apron laid dry
in front of toe of embankment complete as per
drawing and Technical specifications
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 1.00 1.00 420.14 420.14 420.14 420.14 M-003
Stone spalls of minimum 25 mm size cum 0.20 0.20 0.20 302.41 60.48 60.48 60.48 M-008
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mason day 0.35 0.35 0.35 622.00 217.70 217.70 217.70 L-11
Mazdoor day 0.75 0.75 0.75 560.00 420.00 420.00 420.00 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on 228.64 228.64 228.64
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 137.18 137.18 137.18
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = (a+b+c+d) 1509.02 1509.02 1509.02
say 1509.00 1509.00 1509.00
15.4 B Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast
in cement concrete of Grade M15
Unit = cum
Taking output = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 cum 1.00 1.00 1.00 3631.00 3631.00 3631.00 3631.00 Item No. - 12.8 A
(A)
Add 2 per cent of cost to account for nominal 72.62 72.62 72.62
surface reinforcement and filling of granular
material in recesses between blocks.
Page 1 of 253
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate day 0.02 0.02 0.02 622.00 12.44 12.44 12.44 L-12
Mazdoor day 0.30 0.30 0.30 560.00 168.00 168.00 168.00 L-13
Mazdoor (Skilled) day 0.10 0.10 0.10 592.00 59.20 59.20 59.20 L-15
b) Material
Permeable synthetic geotextile including 5 per sqm 11.00 11.00 11.00 150.00 1650.00 1650.00 1650.00 M-183
cent for overlap and wastage
c) Overhead charges @ 20% on @ 20% on @ 20% on 377.93 377.93 377.93
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 226.76 226.76 226.76
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 2494.32 2494.32 2494.32
Rate per sqm = (a+b+c+d)/10 249.43 249.43 249.43
say 249.00 249.00 249.00
15.7 2504.4 Toe protection
A toe wall for toe protection can either be in dry rubble
masonry in case of dry rubble pitching or pitching with
stones in wire crates or it can be in PCC M15 nominal
mix if cement concert block have been used for
pitching . Rates for toe wall can be adopted from
respective clauses depending upon approved design.
The rate for excavation for foundation, dry rubble
masonry and PCC M15 have been analysed and
given in respective chapters.
b) Add for cement concrete bedding (M15 Nominal cum 0.33 0.33 0.33 3631.00 1210.33 1210.33 1210.33 Item No. - 12.8 A
mix) vide Item 12.8 (A) excluding OH & CP . Quantity
shall be adopted as per design ( Assume Rubble
stone Flooring thickness 300mm and cement concrete
bedding thickness 100mm)
Add 1 per cent of cost to account for excavation 18.62 18.62 18.62
for preparation of bed.
c) Material
Stone cum 1.00 1.00 1.00 420.14 420.14 420.14 420.14 M-003
Stone Spalls cum 0.20 0.20 0.20 302.41 60.48 60.48 60.48 M-008
d) Labour
Mate day 0.08 0.08 0.08 622.00 49.76 49.76 49.76 L-12
Mason day 0.50 0.50 0.50 622.00 311.00 311.00 311.00 L-11
Mazdoor (for laying stones, filling of quarry spalls) day 1.50 1.50 1.50 560.00 840.00 840.00 840.00 L-13
Add 1 per cent of cost to account for excavation 48.29 48.29 48.29
for preparation of bed.
Rate per cum 4877.52 4877.52 4877.52
say 4878.00 4878.00 4878.00
15.9 2506 Dry Rubble Flooring
Construction of dry rubble flooring at cross drainage
works for relatively less important works.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 1.00 1.00 420.14 420.14 420.14 420.14 M-003
Stone Spalls cum 0.20 0.20 0.20 302.41 60.48 60.48 60.48 M-008
b) Labour
Mate day 0.10 0.10 0.10 622.00 62.20 62.20 62.20 L-12
Mason day 0.50 0.50 0.50 622.00 311.00 311.00 311.00 L-11
mazdoor day 1.50 1.50 1.50 560.00 840.00 840.00 840.00 L-13
Add 1 per cent of (b) for trimming and 12.13 12.13 12.13
preparation of base.
c) Overhead charges @ 20% on @ 20% on @ 20% on 341.19 341.19 341.19
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 204.71 204.71 204.71
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = (a+b+c+d) 2251.85 2251.85 2251.85
say 2252.00 2252.00 2252.00
15.10 2507.2 Curtain wall complete as per drawing and Technical
specification
A Stone masonry in cement mortar (1:3)
Coursed rubble masonry (1st sort) cum 1.00 1.00 1.00 5520.13 5520.13 5520.13 5520.13 Item No. - 12.7 A
Rate same as per item No. 12.7 (A) including OH &
CP
Rate per cum say 5520.00 5520.00 5520.00
or
15.10 B Cement concrete Grade M15
Concrete Grade M15 Rate as per item No. 12.8 cum 1.00 1.00 1.00 4974.42 4974.42 4974.42 4974.42 Item No. - 12.8 A
(A) including OH & CP
Page 2 of 253
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.00 1.00 1.00 420.14 420.14 420.14 420.14 M-003
Stone Spalls cum 0.20 0.20 0.20 302.41 60.48 60.48 60.48 M-008
b) Labour
Mate day 0.05 0.05 0.05 622.00 31.10 31.10 31.10 L-12
Mason day 0.25 0.25 0.25 622.00 155.50 155.50 155.50 L-11
Mazdoor day 1.00 1.00 1.00 560.00 560.00 560.00 560.00 L-13
Add 1 per cent of cost of (a+b) for trimming and 12.27 12.27 12.27
preparation of bed.
c) Overhead charges @ 20% on @ 20% on @ 20% on 247.90 247.90 247.90
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 148.74 148.74 148.74
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = (a+b+c+d) 1636.13 1636.13 1636.13
say 1636.00 1636.00 1636.00
15.12 2503.3 Gabian Structure for Retaining Earth
Providing and construction of a gabian structure for
retaining earth with segments of wire crates of size 7
m x 3 m x 0.6 m each divided into 1.5 m
compartments by cross netting, made from 4 mm
galvanised steel wire @ 32 kg per 10 sqm having
minimum tensile strength of 300 Mpa conforming to
IS:280 and galvanizing coating conforming to IS:4826,
woven into mesh with double twist, mesh size not
exceeding 100 x 100 mm, filled with boulders with
least dimension of 200 mm, all loose ends to be tied
with 4 mm galvanised steel wire
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate day 0.28 0.28 0.28 622.00 174.16 174.16 174.16 L-12
Mazdoor day 5.00 5.00 5.00 560.00 2800.00 2800.00 2800.00 L-13
Mazdoor (Skilled) day 2.00 2.00 2.00 592.00 1184.00 1184.00 1184.00 L-15
b) Material
Galvanised steel wire crates of mesh size 100 mm sqm 61.00 61.00 61.00 210.00 12810.00 12810.00 12810.00 M-102
x 100 mm woven with 4mm dia. GI wire in rolls of
required size.
Stone boulders with least dimension of 200 mm cum 12.60 12.60 12.60 420.14 5293.70 5293.70 5293.70 M-003
Stone spalls of minimum size 25 mm cum 2.52 2.52 2.52 302.41 762.07 762.07 762.07 M-008
c) Overhead charges @ 20% on @ 20% on @ 20% on 4604.79 4604.79 4604.79
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 2762.87 2762.87 2762.87
(a+b+c) (a+b+c) (a+b+c)
Cost for 12.60 cum (a+b+c+d) 30391.59 30391.59 30391.59
Rate per cum (a+b+c+d)/12.60 2412.03 2412.03 2412.03
say 2412.00 2412.00 2412.00
Note Readymade woven wire crate rolls have been
considered in the rate analysis. In case readymade
rolls are not available, GI wire 4mm dia. @ 32 kg per
10 sqm may be provided. In that case 2 per cent of
the cost of GI wire may be added for weaving the wire
crates.
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a) Labour
Mate day 0.14 0.14 0.14 622.00 87.08 87.08 87.08 L-12
Mazdoor day 2.50 2.50 2.50 560.00 1400.00 1400.00 1400.00 L-13
Mazdoor (Skilled) day 1.00 1.00 1.00 592.00 592.00 592.00 592.00 L-15
b) Material
Galvanised steel wire crates of mesh size 100 mm sqm 65.00 65.00 65.00 210.00 13650.00 13650.00 13650.00 M-102
x 100 mm woven with 4mm dia. GI wire in rolls of
required size to cover 6.00 cum.
Stone boulders with least dimension of 200 mm cum 6.00 6.00 6.00 420.14 2520.81 2520.81 2520.81 M-003
Stone spalls of minimum size 25 mm cum 1.20 1.20 1.20 302.41 362.89 362.89 362.89 M-008
c) Overhead charges @ 20% on @ 20% on @ 20% on 3722.56 3722.56 3722.56
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 2233.53 2233.53 2233.53
(a+b+c) (a+b+c) (a+b+c)
Cost for 6.00 cum (a+b+c+d) 24568.87 24568.87 24568.87
Rate per cum (a+b+c+d)/6.00 4094.81 4094.81 4094.81
say 4095.00 4095.00 4095.00
Note Readymade woven wire crate rolls have been
considered in the rate analysis. In case readymade
rolls are not available, GI wire 4mm dia. @ 32 kg per
10 sqm may be provided. In that case 2 per cent of
the cost of GI wire may be added for weaving the wire
crates.
Page 3 of 253
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Unit = cum
Taking output = 2 x 1 x 1 m = 2 cum
a) Material
Crates made of Mesh type 10x12 (D=100 mm) Zn sqm 11.00 11.00 11.00 75.00 825.00 825.00 825.00 M-194
coated. (Mesh wire diameter 3.00 mm).
Unit = Sqm
Taking output = 60 Sqm
a) Labour
Mate day 0.120 0.120 0.120 622.000 74.640 74.640 74.640 L-12
Mazdoor day 1.800 1.800 1.800 560.000 1008.000 1008.000 1008.000 L-13
Mazdoor (skilled) day 0.600 0.600 0.600 592.000 355.200 355.200 355.200 L-15
b) Machinery
Transit truck agitator
For Transportation Transit truck agitator 6 cum t.km 13.800 x L 13.800 x L 13.800 x L 12.220 337.272 337.272 337.272 P&M-76001
capacity
Unloding time hour 0.139 0.139 0.139 2198.000 305.278 305.278 305.278 P&M-34001
Concrete Pump hour 0.139 0.139 0.139 4033.000 560.139 560.139 560.139 P&M-36001
c) Materials
PCC M30 Grade Refer relevant item of concrete in cum 6.000 6.000 6.000 4474.000 26844.000 26844.000 26844.000 Item No. - 12.8 F
Item 12.8 (F) by using batching plant, excluding
formwork i.e. per cum basic cost (a+b+c)
Fabric Form mattress with 30% shrinkage sqm 78.000 78.000 78.000 2300.00 179400.000 179400.000 179400.000 2300.00
Non-Woven Geotextile to be placed under 20700.000 20700.000 20700.000
concrete filled fabric form including 15 per cent for sqm 9.000 9.000 9.000 2300.00 2300.00
overlap and shrinkage
d) Overhead charges @ 20% on @ 20% on @ 20% on 18366.762 18366.762 27550.143
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 24795.129 24795.129 25713.467
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 60 sqm = a+b+c+d+e 272746.420 272746.420 282848.139
Rate per sqm = (a+b+c+d+e)/60 4545.774 4545.774 4714.136
Say, 4545.80 4545.80 4714.10
Page 4 of 253
CHAPTER-16
REPAIR AND REHABILITATION
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Tractor-trolley. hour 0.50 0.50 0.50 820.00 410.00 410.00 410.00 P&M-12001
c) Overhead charges @ 30% on @ 30% on @ 30% on 467.20 467.20 467.20
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 202.45 202.45 202.45
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = (a+d+c+d) 2226.97 2226.97 2226.97
Rate per sqm = (a+b+c+d)/10 222.70 222.70 222.70
say 223.00 223.00 223.00
16.2 2811 Removal of existing asphaltic wearing coat
comprising of 50 mm thick asphaltic concert laid
over 12 mm thick mastic asphalt including disposal
with all lift and lead upto 1000 m.
Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate day 0.03 0.03 0.03 622.00 18.66 18.66 18.66 L-12
Mazdoor day 0.75 0.75 0.75 560.00 420.00 420.00 420.00 L-13
b) Machinery
Air Compressor 250 cfm with pneumatic hour 0.75 0.75 0.75 550.00 412.50 412.50 412.50 P&M-15001
breaker.
Tractor-trolley. hour 0.40 0.40 0.40 820.00 328.00 328.00 328.00 P&M-12001
c) Overhead charges @ 30% on @ 30% on @ 30% on 353.75 353.75 353.75
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 153.29 153.29 153.29
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = (a+d+c+d) 1686.20 1686.20 1686.20
Rate per sqm = (a+b+c+d)/10 168.62 168.62 168.62
say 169.00 169.00 169.00
16.3 2807 Guniting concrete surface with cement mortar
applied with compressor after cleaning surface and
spraying with epoxy complete as per Technical
Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement kg 16.00 16.00 16.00 6.50 104.00 104.00 104.00 M-081/1000
Graded sand cum 0.04 0.04 0.04 955.78 38.23 38.23 38.23 M-005
Wire mesh 50mm x 50mm size of 3mm wire kg 2.00 2.00 2.00 75.00 150.00 150.00 150.00 M-194
Unit = Number
Taking output = 1 No.
a) Material
Nipples each 1.00 1.00 1.00 28.00 28.00 28.00 28.00 M-128
Cement, fixing compound and consumables @ 4.20 4.20 4.20
15 per cent of cost of nipple
b) Labour
Mate day 0.01 0.01 0.01 622.00 6.22 6.22 6.22 L-12
Mazdoor (Skilled) labour for drilling day 0.08 0.08 0.08 592.00 47.36 47.36 47.36 L-15
Mazdoor (Skilled) labour for fixing nipple and day 0.08 0.08 0.08 592.00 47.36 47.36 47.36 L-15
sealing inlets
Mazdoor for cutting and removing of nipples day 0.04 0.04 0.04 560.00 22.40 22.40 22.40 L-13
Add 10 per cent of labour cost for drilling holes 12.33 12.33 12.33
etc
c) Overhead charges @ 30% on @ 30% on @ 30% on 50.36 50.36 50.36
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 21.82 21.82 21.82
(a+b+c) (a+b+c) (a+b+c)
Rate per No. = (a+b+c+d) 240.06 240.06 240.06
say 240.00 240.00 240.00
16.5 2806 Sealing of cracks/porous concrete by injection
process through nipples/Grouting complete as per
Technical Specification.
A Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 1.10 1.10 1.10 6.50 7.15 7.15 7.15 M-081/1000
Admixtures (anti shrinkage compound) @ 1.43 1.43 1.43
20 per cent of cost of cement
Page 1 of 253
CHAPTER-16
REPAIR AND REHABILITATION
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
b) Labour
Mate day 0.08 0.08 0.08 622.00 49.76 49.76 49.76 L-12
Mazdoor (Skilled) day 0.10 0.10 0.10 592.00 59.20 59.20 59.20 L-15
Mazdoor day 0.10 0.10 0.10 560.00 56.00 56.00 56.00 L-13
c) Machinery
Grout pump with agitator and accessories hour 0.10 0.10 0.10 300.00 30.00 30.00 30.00 M-110
d) Overhead charges @ 30% on @ 30% on @ 30% on 61.06 61.06 61.06
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 26.46 26.46 26.46
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per kg = (a+b+c+d+e) 117.52 117.52 117.52
say 118.00 118.00 118.00
B Cement Mortar (1:1) Grouting
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 0.55 0.55 0.55 6.50 3.58 3.58 3.58 M-081/1000
Sand including 10 per cent wastage kg 0.55 0.55 0.55 0.64 0.35 0.35 0.35 M-005/1500
Admixtures (anti shrinkage compound) @ 0.72 0.72 0.72
20 per cent of cost of cement
b) Labour
Mate day 0.08 0.08 0.08 622.00 49.76 49.76 49.76 L-12
Mazdoor (Skilled) day 0.10 0.10 0.10 592.00 59.20 59.20 59.20 L-15
Mazdoor day 0.10 0.10 0.10 560.00 56.00 56.00 56.00 L-13
c) Machinery
Grout pump with agitator and accessories hour 0.10 0.10 0.10 300.00 30.00 30.00 30.00 M-110
d) Overhead charges @ 30% on @ 30% on @ 30% on 59.88 59.88 59.88
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 25.95 25.95 25.95
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per kg = (a+b+c+d+e) 285.43 285.43 285.43
say 285.00 285.00 285.00
16.6 2800 Patching of damaged concrete surface with
polymer concrete and curing compounds, initiator
and promoter, available in present formulations, to
be applied as per instructions of manufacturer and
as approved by the Engineer.
Unit = sqm
Taking output = 10 sqm for an average thickness of
25mm.
a) Labour
Mate day 0.06 0.06 0.06 622.00 37.32 37.32 37.32 L-12
Mazdoor (Skilled) day 0.75 0.75 0.75 592.00 444.00 444.00 444.00 L-15
Mazdoor day 0.75 0.75 0.75 560.00 420.00 420.00 420.00 L-13
b) Material
Pre-packed polymer concrete based on epoxy kg 315.00 315.00 315.00 400.00 126000.00 126000.00 126000.00 M-144
system complete with curing compound,
intiator and promoter including 5 per cent
wastage.
c) Machinery
Grout pump with agitator and accessories hour 2.00 2.00 2.00 300.00 600.00 600.00 600.00 M-110
d) Overhead charges @ 30% on @ 30% on @ 30% on 38250.40 38250.40 38250.40
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 16575.17 16575.17 16575.17
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 sqm = a+b+c+d+e 182326.89 182326.89 182326.89
Rate per sqm = (a+b+c+d+e)/10 18232.69 18232.69 18232.69
say 18233.00 18233.00 18233.00
Note This item is a proprietory item available in market
as pre-packed polymer concrete and is required to
be applied as per instructions of the manufacturer.
a) Material
Epoxy resin-hardener mix for prime coat kg 2.50 2.50 2.50 250.00 625.00 625.00 625.00 M-098
Epoxy mortar kg 2.20 2.20 2.20 400.00 880.00 880.00 880.00 M-096
Epoxy resin -hardener mix for seal coat. kg 2.00 2.00 2.00 250.00 500.00 500.00 500.00 M-098
Add 3 per cent cost of material for other 60.15 60.15 60.15
consumables like acetone etc and to cover
wastage.
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mazdoor (Skilled) day 0.50 0.50 0.50 592.00 296.00 296.00 296.00 L-15
Mazdoor day 0.50 0.50 0.50 560.00 280.00 280.00 280.00 L-13
c) Overhead charges @ 30% on @ 30% on @ 30% on 799.81 799.81 799.81
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 346.58 346.58 346.58
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 3812.42 3812.42 3812.42
Rate per sqm = (a+b+c+d)/10 381.24 381.24 381.24
say 381.00 381.00 381.00
Page 2 of 253
CHAPTER-16
REPAIR AND REHABILITATION
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
unit: sqm
Taking output = 10 sqm, 40 mm average thickness.
a) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mazdoor day 0.50 0.50 0.50 560.00 280.00 280.00 280.00 L-13
Mazdoor (Skilled) day 0.50 0.50 0.50 592.00 296.00 296.00 296.00 L-15
b) Machinery
Air compressor 250 cfm hour 1.00 1.00 1.00 550.00 550.00 550.00 550.00 P&M-15001
Shotcreteing equipment hour 1.00 1.00 1.00 1535.00 1535.00 1535.00 1535.00 P&M-59001
water tanker 6 KL capacity hour 0.02 0.02 0.02 904.00 18.08 18.08 18.08 P&M-11003
c) Material
Cement kg 120.00 120.00 120.00 6.50 780.00 780.00 780.00 M-081/1000
Sand cum 0.15 0.15 0.15 955.78 143.37 143.37 143.37 M-005
Coarse aggregate of size 4.75mm cum 0.15 0.15 0.15 302.41 45.36 45.36 45.36 M-023
Quick setting compound kg 2.50 2.50 2.50 35.00 87.50 87.50 87.50 M-146
Water KL 0.10 0.10 0.10 74.54 7.45 7.45 7.45 M-191
d) Overhead charges @ 30% on @ 30% on @ 30% on 1130.29 1130.29 1130.29
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 489.79 489.79 489.79
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 sqm = a+b+c+d+e 5387.73 5387.73 5387.73
Rate per sqm = (a+b+c+d+e)/10 538.77 538.77 538.77
say 539.00 539.00 539.00
16.10 2800 Applying pre-packed cement based polymer mortar
of strength 45 Mpa at 28 days for replacement of
spalled concrete
Unit = sqm
Taking output = 10 sqm
Assumed thickness - 10 mm
a) Material
Acrylic polymer bonding coat Litre 1.40 1.40 1.40 45.00 63.00 63.00 63.00 M-057
pre-packed cement based polymer mortar of kg 12.00 12.00 12.00 400.00 4800.00 4800.00 4800.00 M-144
strength 45 Mpa at 28 days
Add 3 per cent of (a ) above for wastage. 145.89 145.89 145.89
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mazdoor (Skilled) day 0.50 0.50 0.50 592.00 296.00 296.00 296.00 L-15
Mazdoor day 0.50 0.50 0.50 560.00 280.00 280.00 280.00 L-13
c) Overhead charges @ 30% on @ 30% on @ 30% on 1682.93 1682.93 1682.93
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 729.27 729.27 729.27
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 8021.97 8021.97 8021.97
Rate per sqm = (a+b+c+d)/10 802.20 802.20 802.20
say 802.00 802.00 802.00
16.11 2805 Eproxy bonding of new concrete to old concrete
Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy resin with pot life not less than 60-90 kg 8.00 8.00 8.00 250.00 2000.00 2000.00 2000.00 M-098
minutes and satisfying testing as per clause
2803.9
Add 3 per cent of (a ) above for wastage. 60.00 60.00 60.00
b) Labour
Mate day 0.04 0.04 0.04 622.00 24.88 24.88 24.88 L-12
Mazdoor (Skilled) day 0.50 0.50 0.50 592.00 296.00 296.00 296.00 L-15
Mazdoor day 0.50 0.50 0.50 560.00 280.00 280.00 280.00 L-13
c) Overhead charges @ 30% on @ 30% on @ 30% on 798.26 798.26 798.26
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 345.91 345.91 345.91
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 3805.06 3805.06 3805.06
Rate per sqm = (a+b+c+d)/10 380.51 380.51 380.51
say 381.00 381.00 381.00
16.12 2812 Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system.
Weight-9.42 kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and tonne 1.05 1.05 1.05 78525.27 82451.53 82451.53 82451.53 M-118
extra length for jacking
HDPE pipes 75mm dia including 5 per cent metre 112.00 112.00 112.00 120.00 13440.00 13440.00 13440.00 M-113
wastage
Cement for grouting kg 400.00 400.00 400.00 6.50 2600.00 2600.00 2600.00 M-081/1000
Tube anchorage set complete with bearing each 8.00 8.00 8.00 27.00 216.00 216.00 216.00 M-189
plate, permanent wedges etc
Epoxy kg 6.00 6.00 6.00 600.00 3600.00 3600.00 3600.00 M-095
MS plates for deviator (where deviator blocks tonne 2.10 2.10 2.10 65000.00 136500.00 136500.00 136500.00 M-181
are not provided)
Add 20 per cent cost of material for other 47761.51 47761.51 47761.51
materials like lead sheet, sleeves, deviator
fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.24 0.24 0.24 622.00 149.28 149.28 149.28 L-12
Mazdoor Semi-skilled) day 3.00 3.00 3.00 592.00 1776.00 1776.00 1776.00 L-14
Mazdoor day 3.00 3.00 3.00 560.00 1680.00 1680.00 1680.00 L-13
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 0.44 0.44 0.44 622.00 273.68 273.68 273.68 L-12
Page 3 of 253
CHAPTER-16
REPAIR AND REHABILITATION
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Blacksmith day 3.00 3.00 3.00 622.00 1866.00 1866.00 1866.00 L-02
Mazdoor day 8.00 8.00 8.00 560.00 4480.00 4480.00 4480.00 L-13
iii) For prestressing
Mate/Supervisor day 0.13 0.13 0.13 622.00 80.86 80.86 80.86 L-12
Fitter day 0.70 0.70 0.70 622.00 435.40 435.40 435.40 L-08
Mazdoor day 2.65 2.65 2.65 560.00 1484.00 1484.00 1484.00 L-13
iv) For grouting
Mate/Supervisor day 0.13 0.13 0.13 622.00 80.86 80.86 80.86 L-12
Mason day 0.70 0.70 0.70 622.00 435.40 435.40 435.40 L-11
Mazdoor day 2.65 2.65 2.65 560.00 1484.00 1484.00 1484.00 L-13
c) Machinery
Stressing jack with pump hour 4.00 4.00 4.00 513.00 2052.00 2052.00 2052.00 P&M-65001
Grouting pump with agitator hour 1.35 1.35 1.35 300.00 405.00 405.00 405.00 M-110
d) Overhead charges @ 30% on @ 30% on @ 30% on 90975.46 90975.46 90975.46
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 39422.70 39422.70 39422.70
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per MT = (a+b+c+d+e) 433649.67 433649.67 433649.67
say 433650.00 433650.00 433650.00
16.13 2812 Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13 system.
Weight-14.73 kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and tonne 3.10 3.10 3.10 78525.27 243428.34 243428.34 243428.34 M-118
extra length for jacking
HDPE pipes 90mm dia including 5 per cent metre 224.00 224.00 224.00 150.00 33600.00 33600.00 33600.00 M-114
wastage
Cement for grouting tonne 1.01 1.01 1.01 6500.00 6565.00 6565.00 6565.00 M-081
Tube anchorage set complete with bearing each 8.00 8.00 8.00 27.00 216.00 216.00 216.00 M-189
plate, permanent wedges etc
Epoxy kg 10.00 10.00 10.00 600.00 6000.00 6000.00 6000.00 M-095
MS plates for deviator (where deviator blocks tonne 7.00 7.00 7.00 65000.00 455000.00 455000.00 455000.00 M-181
are not provided)
Add 20 per cent cost of material for other 148961.87 148961.87 148961.87
materials like lead sheet, sleeves, deviator
fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.08 0.08 0.08 622.00 49.76 49.76 49.76 L-12
Mazdoor Semi-skilled) day 8.00 8.00 8.00 592.00 4736.00 4736.00 4736.00 L-14
Mazdoor day 8.00 8.00 8.00 560.00 4480.00 4480.00 4480.00 L-13
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 1.28 1.28 1.28 622.00 796.16 796.16 796.16 L-12
Blacksmith day 7.00 7.00 7.00 622.00 4354.00 4354.00 4354.00 L-02
Mazdoor day 25.00 25.00 25.00 560.00 14000.00 14000.00 14000.00 L-13
iii) For prestressing
Mate/Supervisor day 0.20 0.20 0.20 622.00 124.40 124.40 124.40 L-12
Fitter day 1.00 1.00 1.00 622.00 622.00 622.00 622.00 L-08
Mazdoor day 4.00 4.00 4.00 560.00 2240.00 2240.00 2240.00 L-13
iv) For grouting
Mate/Supervisor day 0.26 0.26 0.26 622.00 161.72 161.72 161.72 L-12
Mason day 1.50 1.50 1.50 622.00 933.00 933.00 933.00 L-11
Mazdoor day 5.00 5.00 5.00 560.00 2800.00 2800.00 2800.00 L-13
c) Machinery
Stressing jack with pump hour 7.00 7.00 7.00 513.00 3591.00 3591.00 3591.00 P&M-65001
Grouting pump with agitator hour 3.00 3.00 3.00 300.00 900.00 900.00 900.00 M-110
d) Overhead charges @ 30% on @ 30% on @ 30% on 280067.77 280067.77 280067.77
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 121362.70 121362.70 121362.70
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 3.10 MT = a+b+c+d+e 1334989.72 1334989.72 1334989.72
Rate per MT = (a+b+c+d+e)/3.10 430641.84 430641.84 430641.84
say 430642.00 430642.00 430642.00
16.14 2812 Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Page 4 of 253
CHAPTER-16
REPAIR AND REHABILITATION
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
i) Hire charges for jack of 40 tonne lifting each 3.00 3.00 3.00 339.00 1017.00 1017.00 1017.00 P&M-70001
capacity.
ii) Mate day 0.64 0.64 0.64 622.00 398.08 398.08 398.08 L-12
iii) Mazdoor (Skilled) day 4.00 4.00 4.00 592.00 2368.00 2368.00 2368.00 L-15
iv) Mazdoor day 12.00 12.00 12.00 560.00 6720.00 6720.00 6720.00 L-13
v) Wooden packing cum 0.15 0.15 0.15 2000.00 300.00 300.00 300.00 M-197
b) Cost of parts to be replaced for 3 bearings. each 3.00 3.00 3.00 8000.00 24000.00 24000.00 24000.00 M-064
Page 5 of 253
CHAPTER-16
REPAIR AND REHABILITATION
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of
dismantled material.
Mate day 0.40 0.40 0.40 622.00 248.80 248.80 248.80 L-12
Mazdoor day 10.00 10.00 10.00 560.00 5600.00 5600.00 5600.00 L-13
b) Machinery
Tractor-trolley for disposal of dismantled hour 1.00 1.00 1.00 820.00 820.00 820.00 820.00 P&M-12001
material
c) Overhead charges @ 30% on @ 30% on @ 30% on 2000.64 2000.64 2000.64
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 866.94 866.94 866.94
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 m = a+b+c+d 9536.38 9536.38 9536.38
Rate per metre = (a+b+c+d)/10 953.64 953.64 953.64
say 954.00 954.00 954.00
Note The rate for the construction of new crash barrier
may be adopted from chapter 8 on Traffic and
Transportation.
16.20 Replacement of Damaged Mild Steel Railing
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of
dismantled material.
Mate day 0.16 0.16 0.16 622.00 99.52 99.52 99.52 L-12
Mazdoor day 4.00 4.00 4.00 560.00 2240.00 2240.00 2240.00 L-13
b) Machinery
Tractor-trolley for disposal of dismantled hour 1.00 1.00 1.00 820.00 820.00 820.00 820.00 P&M-12001
material
c) Overhead charges @ 30% on @ 30% on @ 30% on 947.86 947.86 947.86
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 410.74 410.74 410.74
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 m = a+b+c+d 4518.11 4518.11 4518.11
Rate per metre = (a+b+c+d)/10 451.81 451.81 451.81
say 452.00 452.00 452.00
16.21 Repair of Crash Barrier
Repair of concrete crash barrier with cement
concert of M-30 grade by cutting and trimming the
damaged portion to a regular shape, cleaning the
area to be repaired thoroughly, applying cement
concert after erection of proper form work.
b) Material
M-30 grade cement concrete including OH & cum 0.30 0.30 0.30 5382.00 1614.60 1614.60 1614.60 Item No. - 14.1 C (i)
CP (Rate as per items 14.1 C (i)
This may be priced based on the rate given the
chapter of superstructure.
c) Overhead charges @ 30% on @ 30% on @ 30% on 175.46 175.46 175.46
(a) (a) (a)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 76.03 76.03 76.03
(a+c) (a+c) (a+c)
Cost for 10 m = a+b+c+d 2450.98 2450.98 2450.98
Rate per m = (a+b+c+d)/10 245.10 245.10 245.10
say 245.00 245.00 245.00
16.22 Repair of RCC Railing
Carrying out repair of RCC M30 railing to bring it to
the original shape.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per
cent .
a) Material
M-30 grade cement concrete excluding OH & cum 0.10 0.10 0.10 4481.00 448.10 448.10 448.10 Item No. - 14.1 C (i)
CP (Rate as per items 14.1 C (i)
HYSD bar reinforcement Rate as per item No tonne 0.01 0.01 0.01 67984.00 883.79 883.79 883.79 Item No. - 14.2
14.2(Excluding OH & CP)
b) Labour*
Mate day 0.016 0.016 0.016 622.00 9.95 9.95 9.95 L-12
mazdoor day 0.20 0.20 0.20 560.00 112.00 112.00 112.00 L-13
* For dismantling and trimming the surface to a
regular shape and removal of damaged material.
b) Labour
Mate day 0.016 0.016 0.016 622.00 9.95 9.95 9.95 L-12
Mazdoor (Skilled) day 0.20 0.20 0.20 592.00 118.40 118.40 118.40 L-15
Mazdoor day 0.20 0.20 0.20 560.00 112.00 112.00 112.00 L-13
c) Overhead charges @ 30% on @ 30% on @ 30% on 886.38 886.38 886.38
(a) (a) (a)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 384.10 384.10 384.10
(a+c) (a+c) (a+c)
Cost of repair for10m = a+b+c+d 4225.08 4225.08 4225.08
Page 6 of 253
CHAPTER-16
REPAIR AND REHABILITATION
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
M-40 grade cement concrete including OH & Cum 250.00 250.00 250.00 4746.0 1186500.00 1186500.00 1186500.00 Item No. - 12.8 (I)
CP (Rate as per items 12.8 ( I )
HYSD steel . tonne 45.00 45.00 45.00 67500.00 3037500.00 3037500.00 3037500.00 Item No. - 12.40
Providing Steel Moulds for Precasting of arch tonne 30.00 30.00 30.00 65000 1950000.00 1950000.00 1950000.00 M-181
units
Add 10 per cent of the cost of materials for 617400.00 617400.00 617400.00
accessories like Providing High tensile lifting
anchors, lifting eyes, steel jigs, spreader
beams, slings and chains
Add consumables such as binding wire, foam, 308700.00 308700.00 308700.00
packing tape, shuttering oil, waterproofing,
galvanized steel plates etc @ 5per cent of
material cost
Page 7 of 253
CHAPTER-16
REPAIR AND REHABILITATION
Amount
Quantity
Reference to (Rs.)
Rate
Sr No MORT&H Description Unit For Large For Medium For Small Medium Remarks/ Input ref.
(Rs.) Large Project Small Project
Specification Project Project Project Project
b) Labour
Mate day 30.00 30.00 30.00 622 18660.00 18660.00 18660.00 L-12
Mason day 10.00 10.00 10.00 560 5600.00 5600.00 5600.00 L-13
Mazdoor Skilled day 80.00 80.00 80.00 592 47360.00 47360.00 47360.00 L-15
c) Machinery
Trailor hour 60.00 60.00 60.00 2621.00 157260.00 157260.00 157260.00 P&M-6001
Page 8 of 253
CHAPTER-17
Tunnel Work
Unit = cum
Taking output = 60 cum
a) Labour
Mate day 0.040 622.000 24.880 L-12
Mazdoor day 1.000 560.000 560.000 L-13
b) Machinery
Excavator 1.1 cum bucket capacity hour 8.214 1748.000 14357.904 P&M-3004
Jack Hammer hour 8.214 206.000 1692.064 P&M-4001
Loading & unloading charges for disposed of grabbed material cum
(Using by 10 cum capacity Tipper & 1 Cum capacity Loader) 72.000 117.860 8485.920 P&M-77003
Unit = cum
Taking output = 50 cum
a) Labour
Mate day 0.040 622.000 24.880 L-12
Mazdoor day 1.000 560.000 560.000 L-13
b) Machinery
Excavator 1.1 cum bucket capacity hour 10.039 1748.000 17548.549 P&M-3004
Jack Hammer hour 10.039 206.000 2068.078 P&M-4001
Loading & unloading charges for disposed of grabbed material cum 60.000 7071.600
(Using by 10 cum capacity Tipper & 1 Cum capacity Loader) 117.860 P&M-77003
Tipper 10 cum capacity for transportation to dumping yard t-km 100.000 962.000
considering lead @ 1km 9.62 P&M-74002
Credit for excavated rock found suitable for use @ 50 per
cent of excavated quantity cum 30.000 350.000 (10500.000) M-090
c) Overhead charges @ 25% on (a+b) 4433.777
d) Contractor's profit @ 10% on (a+b+c) 2216.888
Cost for 50 cum = a+b+c+d 24385.773
Rate per cum = (a+b+c+d)/50 487.72
say 487.70
17.3 Excavation in Soil using Hydraulic Excavator and Tippers with
Disposal upto 1000 metres.
Excavation for portal in soil with hydraulic excavator including
cutting and loading in tippers, trimming bottom and side slopes, in
accordance with requirements of lines, grades and cross sections,
and and disposal of excavated materials including all lifts and
lead upto 1000m
Unit = cum
Taking output = 350 cum
a) Labour
Mate day 0.040 622.000 24.880 L-12
Mazdoor day 1.000 560.000 560.000 L-13
b) Machinery
Excavator 1.1 cum bucket capacity hour 5.024 1748.000 8781.390 P&M-3004
Loading & unloading charges for disposed of grabbed material hour 5.024 2077.000 10434.181 P&M-6003
(Using by 10 cum capacity Tipper & 1 Cum capacity Loader)
Tipper 10 cum capacity for transportation to dumping yard t-km 525.000 5050.500
considering lead @ 1km 9.62 P&M-74002
c) Overhead charges @ 25% on (a+b) 6212.738
Page 1 of 253
CHAPTER-17
Tunnel Work
Unit = cum
Taking output = 480 Cum
a) Labour
Mate day 0.320 622.000 199.040 L-12
Mazdoor day 6.000 560.000 3360.000 L-13
Mazdoor (Skilled) day 2.000 592.000 1184.000 L-15
b) Machinery
Three boom Hydraulic Drill Jumbo hour 25.067 10911.000 273502.400 P&M-56001
Excavator for Scaling hour 2.000 1748.000 3496.000 P&M-3004
Tipper 10 cum capacity for transportation tonne.km 480 x 2 x L 9.620 1920.00 P&M-74002
Loading & unloading charges(Using by 10 cum capacity cum
Tipper & 1 Cum capacity Loader) 576.000 117.860 67887.360 P&M-77003
Dozer (175 HP) hour 9.600 2099.000 20150.400 P&M-1002
c) Materials
Explosives Kg 576.000 55.000 31680.000 M-215
Delay Detonators Nos. 228.000 55.000 12540.000 M-216
Electric Detonators Nos. 35.000 12.000 420.000 M-217
Detonation fuse coil Meter 50.000 105.000 5250.000 M-218
3.7 m long extension rod Nos 1.043 350.000 365.217 M-219
Difter rod Nos 0.505 650.000 328.421 M-221
R32 shank adapter Nos 1.043 1050.000 1095.652 M-222
45 mm Button Bit Nos 3.692 150.000 553.846 M-223
17.5
Dewatering tunnel by pumping out water collected by natural
drainage inside tunnel including
Dewatering in tunnel by pumping out water collected by natural
drainage inside tunnel including providing sump wherever
necessary, cost of all materials, machinery, labour, drainage and
all other ancillary operations etc., complete.
Unit = cum
Taking output = 20000 Hour
a) Labour
Mazdoor day 2500.000 560.000 1400000.000 L-13
b) Machinery 0.000
Water Pump 10 HP hour 20000.000 289.00 5780000.000 P&M-61001
c) Materials
GI Pipe 100 mm Dia Meter 500.000 340.00 170000.000 M-239
Flange Kg. 41.667 55.00 2291.667 M-241
Nut & Bolt Kg. 133.333 50.00 6666.667 M-129
Bracket Kg. 1125.000 55.00 61875.000 M-241
Credit for salvage value of GI Pipe @ 20 per cent Meter 100.000 (340.000) (34000.000) M-239
Page 2 of 253
CHAPTER-17
Tunnel Work
Unit = cum
Taking output = 26 Tonne
a) Labour
Mate day 0.800 622.000 497.600 L-12
Mazdoor day 10.000 560.000 5600.000 L-13
Mazdoor(Semi Skilled) day 5.000 592.000 2960.000 L-14
Welder day 5.000 622.000 3110.000 L-02
b) Machinery
Rotating Telehandlers hour 37.180 1091.00 40563.380 P&M-58001
c) Materials
ISMB 350 Tonne 20.732 65000.00 1347560.500 M-181
(Including 0.25% Wastage)
MS Channel ISMC 75 Tonne 3.830 65000.00 248920.750 M-181
(Including 0.25% Wastage)
MS Plate 200 x 200 x 12 mm Tonne 1.504 65000.00 97743.750 M-181
(Including 0.25% Wastage)
Nuts and bolts (M 16X40) Kg 151.200 50.00 7560.000 M-129
Add 40 per cent of cost of a+b+c towards of Fabrication,
Erection,Temporary fixture, Handling of material, final 701806.392
matching and field welding etc.
Unit = cum
Taking output = 120 Cum
a) Labour
Mate day 0.32 622.000 199.040 L-12
Mazdoor day 8.00 560.000 4480.000 L-13
b) Machinery
Batching Plant of capacity 120 cum/hour hour 1.333 3877.000 5169.333 P&M-19002
Generator 250 KVA hour 1.333 3970.000 5293.333 P&M-22004
Loader 3.1 cum capacity hour 1.333 3907.000 5209.333 P&M-5001
Transit truck agitator
For transportation (6 cum Capacity) tonne.km 300 x L 12.220 7332.000 P&M-76001
For loading & unloading hour 11.333 2198.000 24910.667 P&M-34001
Shotcrete Machine @ 12 cum/hour hour 10.000 1535.000 15350.000 P&M-59001
Compressor 500 cfm hour 10.000 2413.000 24130.000 P&M-15002
c) Materials
Cement Tonne 49.440 6500.000 321360.000 M-081
Sand Cum 86.850 955.775 83009.059 M-004
10 mm to 4.76 mm Aggregate Cum 52.080 564.724 29410.819 M-039
Steel Fiber Tonne 6.120 58500.000 358020.000 M-225
Admixture @ 0.4 % of Cement Kg 197.760 25.000 4944.000 M-182
Microsilica @ 6 % of Cement Kg 2966.400 25.000 74160.000 M-226
Accelerator @ 4.5 % of Cement Kg 2224.800 30.000 66744.000 M-227
Page 3 of 253
CHAPTER-17
Tunnel Work
Unit = cum
Taking output = 120 Cum
a) Labour
Mate day 0.32 622.000 199.040 L-12
Mazdoor day 8.00 560.000 4480.000 L-13
b) Machinery
Batching Plant of capacity 120 cum/hour hour 1.333 3877.000 5169.333 P&M-19002
Generator 250 KVA hour 1.333 3970.000 5293.333 P&M-22004
Loader 3.1 cum capacity hour 1.333 3907.000 5209.333 P&M-5001
Transit truck agitator
For transportation (6 cum Capacity) tonne.km 300 x L 12.220 7332.000 P&M-76001
For loading & unloading hour 11.333 2198.000 24910.667 P&M-34001
Shotcrete Machine @ 12 cum/hour hour 10.000 1535.000 15350.000 P&M-59001
Compressor 500 cfm hour 10.000 2413.000 24130.000 P&M-15002
c) Materials
Cement Tonne 49.440 6500.000 321360.000 M-081
Sand Cum 86.850 955.775 83009.059 M-004
10 mm to 4.76 mm Aggregate Cum 52.080 564.724 29410.819 M-039
Wiremesh (Including 10% for lapping) Sqm 1320.00 75.000 99000.000 M-228
Admixture @ 0.4 % of Cement Kg 197.760 25.000 4944.000 M-182
Microsilica @ 6 % of Cement Kg 2966.400 25.000 74160.000 M-226
Accelerator @ 4.5 % of Cement Kg 2224.800 30.000 66744.000 M-227
17.9 Providing and fixing 25 mm diameter 3 meter long steel rock bolts
including drilling 45 mm dia holes, plate, nuts, cement grout, cost
of all materials, machinery, labour, ventilation, lighting, drainage
and all other ancillary operations etc. complete as per Drawing
and Technical Specifications.
Unit = cum
Taking output = 155 Nos.
a) Labour
Mate day 0.48 622.000 298.560 L-12
Mazdoor day 8.00 560.000 4480.000 L-13
Mason (IInd class) day 4.00 622.000 2488.000 L-10
b) Machinery
Single boom Hydraulic Drill Jumbo hour 25.833 4969.000 128365.833 P&M-54001
c) Materials
3.7 m long extension rod Nos 1.011 350.00 353.804 M-219
R32 shank adapter Nos 1.011 1050.00 1061.413 M-222
45 mm dia cross bit Nos 3.577 150.00 536.538 M-223
25 mm Tor Steel (Including 2.5% Wastage) Tonne 1.927 62000.00 119458.907 M-083
17.10 Providing and fixing 32 mm diameter 7 meter long steel rock bolts
including drilling 51 mm dia holes, plate, nuts, cement grout, cost
of all materials, machinery, labour, ventilation, lighting, drainage
and all other ancillary operations etc. complete as per Drawing
and Technical Specifications.
Page 4 of 253
CHAPTER-17
Tunnel Work
Unit = cum
Taking output = 70 Nos.
a) Labour
Mate day 0.60 622.000 373.200 L-12
Mazdoor day 10.00 560.000 5600.000 L-13
Mason (IInd class) day 5.00 622.000 3110.000 L-10
b) Machinery
Single Boom Hydraulic hour 17.500 4969.000 86957.500 P&M-54001
c) Materials
3.7 m long extension rod Nos 1.065 350.00 372.826 M-219
R32 shank adapter Nos 1.065 1050.00 1118.478 M-222
32 mm coupling sleeve Nos 1.065 950.00 1011.957 M-220
51 mm dia button bit Nos 3.769 250.00 942.308 M-224
32 mm Tor Steel (Including 2.5% Wastage) Tonne 3.237 62000.00 200700.750 M-083
Unit = cum
Taking output = 1.5 Tonne
a) Labour
Mate day 0.08 622.000 49.760 L-12
Mazdoor day 2.00 560.000 1120.000 L-13
b) Machinery
Grouting machine @ 25 Bags Per Hours hour 1.200 708.000 849.600 P&M-60001
Pump 10 HP hour 1.200 0.000
Single Boom Hydraulic hour 1.250 4969.000 6211.250 P&M-54001
c) Materials
Cement Including 1% Wastage) Tonne 1.515 6500.000 9847.500 M-081
Cost of water (Water/Cement Ratio - 0.4) KL 0.606 74.540 45.171 M-191
3.7 m long extension rod Nos 0.076 350.000 26.630 M-219
R32 shank adapter Nos 0.076 1050.000 79.891 M-222
32 mm coupling sleeve Nos 0.076 950.000 72.283 M-220
51 mm dia cross bit Nos 0.269 250.000 67.308 M-224
Add 5 per cent of cost of a+b+c towards of cutting ,making tip,
Threading, nut , plate, grouting and bit sharpening etc.. 918.470
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.00 3736.21 448344.68
Concrete - 19.05
Page 5 of 253
CHAPTER-17
Tunnel Work
Unit = cum
Taking output = 120 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.00 4155.23 498627.57 Sub-Analysis of
Concrete - 19.09
Page 6 of 253
CHAPTER-17
Tunnel Work
Page 7 of 253
CHAPTER-17
Tunnel Work
Page 8 of 253
CHAPTER-17
Tunnel Work
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 12.22 1833.00 P&M-76001
Page 9 of 253
CHAPTER-17
Tunnel Work
Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 8.40 62000.00 520800.00 M-083
Binding wire Kg 48.00 67.00 3216.00 M-072
b) Labour for straightening, cutting, bending, shifting to site,
tying and placing in position
Mate day 0.16 622.00 99.52 L-12
Blacksmith day 1.00 622.00 622.00 L-02
Mazdoor day 3.00 560.00 1680.00 L-13
c) Machinery
Cutting Machine hour 8.00 468.00 3744.00 P&M-43001
Bending Machine hour 8.00 468.00 3744.00 P&M-43001
Electric generator 15 KVA hour 8.00 374.00 2992.00 P&M-22009
Tipper
Tipper for Transportation
(i) 14 cum capacity t.km 8xL 7.77 124.32 P&M-73002
Loading & Unloading Time hour
(i) 14 cum capacity hour 2.00 2331.00 4662.00 P&M-6002
Light weight Crane
At cutting bending yard hour 2.00 966.00 1932.00 P&M-63001
At site hour 2.00 966.00 1932.00 P&M-63001
Basic Cost of Labour, Material & Machinery (a+b) for 8 MT
Page 10 of 253
CHAPTER-18
Environmental Management & Bio Engineering
Amount
Quantity
(Rs.)
Reference to MORT&H Rate Remarks/ Input
Sr No Description Unit
Specification For Large For Medium For Small (Rs.) Medium Small ref.
Large Project
Project Project Project Project Project
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 622.00 74.64 74.64 74.64 L-12
Mazdoor for preparation of ground day 3.000 3.000 3.000 560.00 1680.00 1680.00 1680.00 L-13
b) Machinery
Water tanker including watering for 3 months hour 2.000 2.000 2.000 904.00 1808.00 1808.00 1808.00 P&M-11003
Tractor-trolley hour 0.500 0.500 0.500 820.00 410.00 410.00 410.00 P&M-12001
c) Material
Live Sods (.6m Length) Nr 1000.000 1000.000 1000.000 10.00 10000.00 10000.00 10000.00 M-232
Farm yard manure @ 0.18 cum per 100 sqm at site of work cum 0.180 0.180 0.180 150.00 27.00 27.00 27.00 M-168
Cost of water KL 12.000 12.000 12.000 74.54 894.48 894.48 894.48 M-191
Grass Kg 100.000 100.000 100.000 21.00 2100.00 2100.00 2100.00 M-112
d) Overhead charges @ 8% on @ 10% on @ 12% on 1359.530 1699.412 2039.294
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 1835.365 1869.353 1903.341
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 20189.015 20562.885 20936.756
Rate per sqm = (a+b+c+d+e)/100 201.890 205.629 209.368
say 202.00 206.00 209.00
18.4 Construction of vegetative Palisades in Rills using hard wood
cutting complete as per drawing and additional Technical
specification.
Unit = Rm
Taking output = 2 Rm
a) Labour
Mate day 0.012 0.012 0.012 622.00 7.46 7.46 7.46 L-12
Mazdoor skilled day 0.100 0.100 0.100 592.00 59.20 59.20 59.20 L-15
Mazdoor day 0.200 0.200 0.200 560.00 112.00 112.00 112.00 L-13
b) Machinery
Tractor-trolley hour 0.250 0.250 0.250 820.00 205.00 205.00 205.00 P&M-12001
c) Material
Horizontal Live Sods (2M Length) Nr 2 2 2 25.00 50.00 50.00 50.00 M-233
Vertical Live Sods (2 M Length) Nr 40 40 40 25.00 1000.00 1000.00 1000.00 M-233
Cost of water KL 0.100 0.100 0.100 74.54 7.45 7.45 7.45 M-191
Binding Material Rm 5.000 5.000 5.000 5.000 25.00 25.00 25.00 M-235
Page 1 of 253
CHAPTER-18
Environmental Management & Bio Engineering
Amount
Quantity
(Rs.)
Reference to MORT&H Rate Remarks/ Input
Sr No Description Unit
Specification For Large For Medium For Small (Rs.) Medium Small ref.
Large Project
Project Project Project Project Project
Cost of water KL 12.000 12.000 12.000 74.54 894.48 894.48 894.48 M-191
Grass Kg 100.000 100.000 100.000 21.00 2100.00 2100.00 2100.00 M-112
d) Overhead charges @ 8% on @ 10% on @ 12% on 1359.530 1699.412 2039.294
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 1835.365 1869.353 1903.341
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 20189.015 20562.885 20936.756
Rate per sqm = (a+b+c+d+e)/100 201.890 205.629 209.368
say 202.00 206.00 209.00
Unit = Rm
Taking output = 1Rm
a) Labour
Mate day 0.025 0.025 0.025 622.00 15.55 15.55 15.55 L-12
Mazdoor skilled day 0.100 0.100 0.100 592.00 59.20 59.20 59.20 L-15
Mazdoor day 0.200 0.200 0.200 560.00 112.00 112.00 112.00 L-13
b) Machinery
Water tanker 6 KL capacity hour 0.008 0.008 0.008 904.00 7.53 7.53 7.53 P&M-11003
c) Materials
Bamboos ( For Horizontal Beam) Rm 4.000 4.000 4.000 25.00 100.00 100.00 100.00 M-229
Live Stake Stump / Bamboos (Vertical) Rm 1.500 1.500 1.500 25.00 37.50 37.50 37.50 M-230
Live Stake Stump / Bamboos (Horizontal) Rm 1.000 1.000 1.000 25.00 25.00 25.00 25.00 M-230
Binding Material Rm 2.000 2.000 2.000 5.00 10.00 10.00 10.00 M-235
Cost of Water KL 0.050 0.050 0.050 74.54 3.73 3.73 3.73 M-191
Grass Kg 1.500 1.500 1.500 21.00 31.50 31.50 31.50 M-112
d) Overhead charges @ 8% on @ 10% on @ 12% on 32.161 40.201 48.241
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 43.417 44.221 45.025
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 1 RM = a+b+c+d+e 477.588 486.433 495.277
Rate per cum = (a+b+c+d+e) say 478.00 486.00 495.00
Page 2 of 253
SUB-ANALYSIS OF CONCRETE / MORTAR RATE
Unit = cum
Taking output = 15 Cum
a) Labour
Mate day 0.32 622.00 199.04 L-12
Skilled Mazdoor day 1.00 592.00 592.00 L-15
Mazdoor day 7.00 560.00 3920.00 L-13
b) Material
40 mm Aggregate cum 13.50 898.08 12124.11 M-054
Coarse sand cum 6.75 955.78 6451.48 M-004
cement tonne 3.45 6500.00 22425.00 M-081
Cost of water KL 1.38 74.54 102.87 M-191
c) Machinery c
Batching Plant of capacity 120 cum/hour hour 0.17 3877.00 646.17 P&M-19002
Generator 250 KVA hour 0.17 3970.00 661.67 P&M-22004
Loader 3.1 cum capacity hour 0.36 3907.00 1412.80 P&M-5001
Transit truck agitator
For loading & Unloding time hour 0.167 2198.000 366.33 P&M-34001
Rate per cum = (a+b+c)/15 3260.10
a) Material
Cement tonne 150.84 6500.00 980460.00 M-081
Coarse sand cum 162.00 955.78 154835.55 M-004
20 mm Aggregate cum 194.40 968.49 188274.25 M-052
10 mm Aggregate cum 129.60 843.90 109369.15 M-050
Admixture @ 0.3 % of Cement Kg 452.520 25.00 11313.00 M-182
Cost of water KL 60.34 74.54 4497.45 M-191
b) Labour
Mate day 0.16 622.00 4497.45 L-12
Skilled Mazdoor day 1.00 592.00 592.00 L-15
Mazdoor day 3.00 560.00 1680.00 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour hour 4.00 3877.00 15508.00 P&M-19002
Generator 250 KVA hour 4.00 3970.00 15880.00 P&M-22004
Loader 3.1 cum capacity hour 8.68 3907.00 33907.18 P&M-5001
Transit truck agitator
For loading & Unloding time hour 4.000 2198.000 8792.00 P&M-34001
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)/360 4248.91
19.11 RCC Grade M35 Using Batching Plant
Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 151.92 6500.00 987480.00 M-081
Coarse sand cum 162.00 955.78 154835.55 M-004
20 mm Aggregate cum 194.40 968.49 188274.25 M-052
10 mm Aggregate cum 129.60 843.90 109369.15 M-050
Admixture @ 0.4 % of Cement Kg 607.680 25.00 15192.00 M-182
Cost of water KL 60.77 74.54 4529.65 M-191
b) Labour
Mate day 0.16 622.00 99.52 L-12
Skilled Mazdoor day 1.00 592.00 592.00 L-15
Mazdoor day 3.00 560.00 1680.00 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour hour 4.00 3877.00 15508.00 P&M-19002
Generator 250 KVA hour 4.00 3970.00 15880.00 P&M-22004
Loader 3.1 cum capacity hour 8.68 3907.00 33907.18 P&M-5001
Transit truck agitator
For loading & Unloding time hour 4.000 2198.000 8792.00 P&M-34001
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)/360 4267.05
c) Machinery
Batching Plant of capacity 120 cum/hour hour 4.00 3877.00 15508.00 P&M-19002
Generator 250 KVA hour 4.00 3970.00 15880.00 P&M-22004
Loader 3.1 cum capacity hour 8.68 3907.00 33907.18 P&M-5001
Transit truck agitator
For loading & Unloding time hour 4.000 2198.000 8792.00 P&M-34001
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)/360 4870.39
19.16 RCC Grade M60 Using Batching Plant
Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 160.20 6500.00 1041300.00 M-081
Coarse sand cum 162.00 955.78 154835.55 M-004
20 mm Aggregate cum 194.40 968.49 188274.25 M-052
10 mm Aggregate cum 129.60 843.90 109369.15 M-050
Admixture @ 1 % of Cement Kg 1281.600 25.00 32040.00 M-182
Silica Fume @ 6% of Cement Kg 9612.000 20.00 192240.00 M-199
Cost of water KL 64.08 74.54 4776.52 M-191
b) Labour
Mate day 0.16 622.00 99.52 L-12
Skilled Mazdoor day 1.00 592.00 592.00 L-15
Mazdoor day 3.00 560.00 1680.00 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour hour 4.00 3877.00 15508.00 P&M-19002
Generator 250 KVA hour 4.00 3970.00 15880.00 P&M-22004
Loader 3.1 cum capacity hour 8.68 3907.00 33907.18 P&M-5001
Transit truck agitator
For loading & Unloding time hour 4.000 2198.000 8792.00 P&M-34001
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)/360 4998.04
19.17 RCC Grade M65 Using Batching Plant
Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 162.00 6500.00 1053000.00 M-081
Coarse sand cum 162.00 955.78 154835.55 M-004
20 mm Aggregate cum 194.40 968.49 188274.25 M-052
10 mm Aggregate cum 129.60 843.90 109369.15 M-050
Admixture @ 1 % of Cement Kg 1296.000 25.00 32400.00 M-182
Silica Fume @ 6% of Cement Kg 9720.000 20.00 194400.00 M-199
Cost of water KL 64.80 74.54 4830.19 M-191
b) Labour
Mate day 0.16 622.00 99.52 L-12
Skilled Mazdoor day 1.00 592.00 592.00 L-15
Mazdoor day 3.00 560.00 1680.00 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour hour 4.00 3877.00 15508.00 P&M-19002
Generator 250 KVA hour 4.00 3970.00 15880.00 P&M-22004
Loader 3.1 cum capacity hour 8.68 3907.00 33907.18 P&M-5001
Transit truck agitator
For loading & Unloding time hour 4.000 2198.000 8792.00 P&M-34001
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)/360 5037.69
19.18 A DLC Using Batching Plant-240 cum capacity Plant
Unit = cum
Taking output = 450 Cum
a) Material
Cement @ 150 kg/cum of concrete tonne 67.50 6500.00 438750.00 M-081
Coarse Sand as per IS: 383 @ 0.45 cum/cum of cum 202.50 955.78 193544.44 M-004
concrete
Reference to MORT&H Rate Amount Remarks/
Sr No Description Unit Quantity
Specification (Rs.) (Rs.) Input ref.)
Crushed stone coarse aggregate of 25 mm and 12.5 cum 405.000 906.19 367008.31 M-053 +M-
mm nominal sizes graded as per table 600-1 @ 0.90 051 / 2
cum/cum of concrete conforming to clause 602.2.6.
Fly ash conforming to IS: 3812-1966 (Part-I) cum 9.640 153.28 1477.57 M-010
Cost of water (Water/Cement Ratio - 0.4) KL 23.144 74.54 1725.15 M-191
b) Labour
Mate day 0.16 622.00 99.52 L-12
Skilled Mazdoor day 1.00 592.00 592.00 L-15
Mazdoor day 3.00 560.00 1680.00 L-13
c) Machinery
Batching Plant of capacity 240 cum/hour hour 2.50 5971.00 14927.50 P&M-19001
Generator 250 KVA hour 2.50 3970.00 9925.00 P&M-22004
Loader 3.1 cum capacity hour 10.85 3907.00 42383.97 P&M-5001
Unit = cum
Taking output = 450 Cum
a) Material
Cement @ 150 kg/cum of concrete tonne 67.50 6500.00 438750.00 M-081
Coarse Sand as per IS: 383 @ 0.45 cum/cum of cum 202.50 955.78 193544.44 M-004
concrete
Reference to MORT&H Rate Amount Remarks/
Sr No Description Unit Quantity
Specification (Rs.) (Rs.) Input ref.)
Crushed stone coarse aggregate of 25 mm and 12.5 cum 405.000 906.19 367008.31 M-053 +M-
mm nominal sizes graded as per table 600-1 @ 0.90 051 / 2
cum/cum of concrete conforming to clause 602.2.6.
Fly ash conforming to IS: 3812-1966 (Part-I) cum 9.640 153.28 1477.57 M-010
Cost of water (Water/Cement Ratio - 0.4) KL 23.144 74.54 1725.15 M-191
b) Labour
Mate day 0.16 622.00 99.52 L-12
Skilled Mazdoor day 1.00 592.00 592.00 L-15
Mazdoor day 3.00 560.00 1680.00 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour hour 5.00 3877.00 19385.00 P&M-19002
Generator 250 KVA hour 5.00 3970.00 19850.00 P&M-22004
Loader 3.1 cum capacity hour 10.85 3907.00 42383.97 P&M-5001
b) Labour
Mate day 0.16 622.00 99.52 L-12
Skilled Mazdoor day 1.00 592.00 592.00 L-15
Mazdoor day 3.00 560.00 1680.00 L-13
c) Machinery
Batching Plant of capacity 240 cum/hour hour 5.00 5971.00 29855.00 P&M-19001
Generator 250 KVA hour 5.00 3970.00 19850.00 P&M-22004
Loader 3.1 cum capacity hour 20.97 3907.00 81942.35 P&M-5001
Transit truck agitator
For loading & Unloding time hour 5.000 2198.000 10990.00 P&M-34001
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)/900 4160.57
###
Fly ash Total fly ash = 40.693 + 54.26 = 94.95 tonnes.
(Say 95 tonnes)
###
Reference to MORT&H Rate Amount Remarks/
Sr No Description Unit Quantity
Specification (Rs.) (Rs.) Input ref.)
Unit ; cum
Taking output = 900 Cum ###
a) Material
Cement tonne 379.80 6500.00 2468700.00 M-081
Coarse sand cum 364.50 955.78 348379.99 M-004
20 mm Aggregate cum 486.00 968.49 470685.61 M-052
10 mm Aggregate cum 324.00 843.90 273422.88 M-050
Admixture @ 0.4 % of Cement Kg 1519.200 25.00 37980.00 M-182
Cost of water KL 151.92 74.54 11324.12 M-191
b) Labour
Mate day 0.16 622.00 99.52 L-12
Skilled Mazdoor day 1.00 592.00 592.00 L-15
Mazdoor day 3.00 560.00 1680.00 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour hour 10.00 3877.00 38770.00 P&M-19002
Generator 250 KVA hour 10.00 3970.00 39700.00 P&M-22004
Loader 3.1 cum capacity hour 20.97 3907.00 81942.35 P&M-5001
Transit truck agitator
For loading & Unloding time hour 10.000 2198.000 21980.00 P&M-34001
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)/900 4216.95
###
Sand @ 0.45 cum / cum of concrete = 900 x 0.45 = 405
x 1.6 = 648 tonnes.10 per cent to be replaced by flyash.
Balance sand = 648 x 0.9 = 583.2 tonnes = 583.02 / 1.6 =
364.5cum. Quantity of flyash = (648-583.2) x specific
gravity of fly ash/specific gravity of sand = 64.8 x 2.25 /
2.687 = 54.26 tonnes
###
Fly ash Total fly ash = 40.693 + 54.26 = 94.95 tonnes.
(Say 95 tonnes)
###
19.20 PCC Grade M15 Using Batching Plant for Kerb
Unit = cum
Taking output = 360 Cum
a) Material
Cement tonne 99.00 6500.00 643500.00 M-081
Coarse sand cum 162.000 955.78 154835.55 M-004
40 mm Aggregate cum 194.400 898.08 174587.15 M-054
20 mm Aggregate cum 97.200 968.49 94137.12 M-052
10 mm Aggregate cum 32.400 843.90 27342.29 M-050
Cost of water (Water/Cement Ratio - 0.4) KL 39.600 74.54 2951.78 M-191
b) Labour
Mate day 0.16 622.00 99.52 L-12
Skilled Mazdoor day 1.00 592.00 592.00 L-15
Mazdoor day 3.00 560.00 1680.00 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour hour 4.00 3877.00 15508.00 P&M-19002
Generator 250 KVA hour 4.00 3970.00 15880.00 P&M-22004
Loader 3.1 cum capacity hour 8.68 3907.00 33907.18 P&M-5001
Transit truck agitator
For loading & Unloding time hour 4.000 2198.000 8792.00 P&M-34001
a) Labour
Mate day 0.360 0.360 0.360 622.000 223.920 223.920 223.920
Painter day 6.000 6.000 6.000 622.000 3732.000 3732.000 3732.000
Mazdoor day 3.000 3.000 3.000 560.000 1680.000 1680.000 1680.000
b) Material
Coal Tar Epoxy coating @ 0.5 Kg per Square Meter coverage Kg.
including 5% wastage 52.500 52.500 52.500 220.00 11550.000 11550.000 11550.000
Add 1 per cent of cost of abs towards miscellaneous (water,
painting brush etc.). 171.86 171.86 171.86
c) Overhead charges @ 8% on (a+b) @ 10% on @ 12% on (a+b) 1388.622 1735.778 2082.934
(a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1874.640 1909.356 1944.071
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 Sqm. = a+b+c+d 20621.042 21002.913 21384.784
Rate per Sqm = (a+b+c+d)/100 206.210 210.029 213.848
Say, 206.20 210.00 213.80
Unit = Cum.
Taking output 100 Cum
a) Material
Corrosion Inhibiting Admixture @ 3 kg per cubic Meter Kg. 300.000 52.500 52.500 128.50 38550.000 6746.250 6746.250
Providing and applying two coats of Two component, high build, 100
% solid content, low VOC,, polycyclin aromatic hydrocarbon based,
Pot life – 2 hrs @ 72 deg. F , Tack free – 4-6 hrs , DFT per coat 80 -
120 microns (dry) coal tar epoxy coating with Sunepoxy Coal tar or
Equivalent
Unit = Sqm.
Taking output 100 Sqm
a) Labour
Mate day 0.360 0.360 0.360 622.000 223.920 223.920 223.920
Painter day 6.000 6.000 6.000 622.000 3732.000 3732.000 3732.000
Mazdoor day 3.000 3.000 3.000 560.000 1680.000 1680.000 1680.000
b) Material
Primer @ 100 gm. per Sqm. coverage Kg. 10.000 10.000 10.000 210.00 2100.000 2100.000 2100.000
Coal Tar Epoxy coating @ 450 gm. per Square Meter coverage Kg.
including 5% wastage 52.500 52.500 52.500 235.00 12337.500 12337.500 12337.500
Unit = Sqm.
Taking output 100 Sqm
a) Labour
Mate day 0.400 0.360 0.360 622.000 248.800 223.920 223.920
Mason 2nd class day 4.000 6.000 6.000 622.000 2488.000 3732.000 3732.000
Mazdoor day 6.000 3.000 3.000 560.000 3360.000 1680.000 1680.000
b) Material
PU primer @ 250 gms per Sq.mtr coverage Kg. 25.000 25.000 25.000 250.00 6250.000 6250.000 6250.000
Liquid applied polyurethane mambrane @1.5 kgs per Sq.mtr Kg.
coverage 150.000 150.000 150.000 550.00 82500.000 82500.000 82500.000
Non shrink cementitious for Grouting Kg. 13.200 13.200 13.200 150.00 1980.000 1980.000 1980.000
Unit = Nos.
Taking output 150 Nos.
a) Labour
Mate day 0.075 0.075 0.075 622.000 46.650 46.650 46.650
Mazdoor Skilled (for chemical dispensing & rebar fixing) day 0.625 0.625 0.625 592.000 370.000 370.000 370.000
Driller (Jumper) (for drilling) day 0.625 0.625 0.625 592.000 370.000 370.000 370.000
Mazdoor (for cleaning holes incl. brushing & blowing) day 0.625 0.625 0.625 560.000 350.000 350.000 350.000
b) Material
Chemical ml 1200.0 1200.0 1200.0 10.64 12770.400 12770.400 12770.400
c) Machinery
Drill Machine (2 Nos.) hour 5.000 5.000 5.000 120.00 600.000 600.000 600.000
Drill Bit - 14 mm (with wear mark & anchor mark) Nos. 1.000 1.000 1.000 1508.00 1508.000 1508.000 1508.000
Generator 20 KVA hour 2.500 2.500 2.500 374.00 935.000 935.000 935.000
Unit = Nos.
Taking output 150 Nos.
a) Labour
Mate day 0.090 0.090 0.090 622.000 55.980 55.980 55.980
Mazdoor Skilled (for chemical dispensing & rebar fixing) day 0.750 0.750 0.750 592.000 444.000 444.000 444.000
Driller (Jumper) (for drilling) day 0.750 0.750 0.750 592.000 444.000 444.000 444.000
Mazdoor (for cleaning holes incl. brushing & blowing) day 0.750 0.750 0.750 560.000 420.000 420.000 420.000
b) Material
Chemical ml 1680.0 1680.0 1680.0 10.64 17878.560 17878.560 17878.560
c) Machinery
Drill Machine (2 Nos.) hour 6.000 6.000 6.000 120.00 720.000 720.000 720.000
Drill Bit - 16 mm (with wear mark & anchor mark) Nos. 1.200 1.200 1.200 2660.00 3192.000 3192.000 3192.000
Generator 20 KVA hour 3.000 3.000 3.000 374.00 1122.000 1122.000 1122.000
Unit = Nos.
Taking output 150 Nos.
a) Labour
Mate day 0.120 0.120 0.120 622.000 74.640 74.640 74.640
Mazdoor Skilled (for chemical dispensing & rebar fixing) day 1.000 1.000 1.000 592.000 592.000 592.000 592.000
Driller (Jumper) (for drilling) day 1.000 1.000 1.000 592.000 592.000 592.000 592.000
Mazdoor (for cleaning holes incl. brushing & blowing) day 1.000 1.000 1.000 560.000 560.000 560.000 560.000
b) Material
Chemical ml 2865.0 2865.0 2865.0 10.64 30489.330 30489.330 30489.330
c) Machinery
Drill Machine (2 Nos.) hour 7.500 7.500 7.500 120.00 900.000 900.000 900.000
Drill Bit - 20 mm (with wear mark & anchor mark) Nos. 1.600 1.600 1.600 3841.00 6145.600 6145.600 6145.600
Generator 20 KVA hour 3.750 3.750 3.750 374.00 1402.500 1402.500 1402.500
Unit = Nos.
Taking output 150 Nos.
a) Labour
Mate day 0.150 0.150 0.150 622.000 93.300 93.300 93.300
Mazdoor Skilled (for chemical dispensing & rebar fixing) day 1.250 1.250 1.250 592.000 740.000 740.000 740.000
Driller (Jumper) (for drilling) day 1.250 1.250 1.250 592.000 740.000 740.000 740.000
Mazdoor (for cleaning holes incl. brushing & blowing) day 1.250 1.250 1.250 560.000 700.000 700.000 700.000
b) Material
Chemical ml 5535.0 5535.0 5535.0 10.64 58903.470 58903.470 58903.470
Drill Bit - 20 mm (with wear mark & anchor mark) Nos. 1.500 1.500 1.500 4670.00 7005.000 7005.000 7005.000
c) Machinery
Drill Machine (2 Nos.) hour 10.000 10.000 10.000 120.00 1200.000 1200.000 1200.000
Generator 20 KVA hour 5.000 5.000 5.000 374.00 1870.000 1870.000 1870.000