Professional Documents
Culture Documents
Rural Road
A rural road may be defined as a motorable road or track owned, regulated and maintained by the local
governing institutions. These roads may have either earthen or graveled or paved surface and are
operational either during a part of or throughout the year.
Primary information was taken from concerned community people, VDC officials, and schoolteachers
about real accessibility situation of settlements in special format developed for this purpose.
Secondary data such as DTMP, transport infrastructure inventory (strategic roads, rural roads, and main
trails), demographic and socio economic data of district, settlement pattern, development potential areas
(agriculture, industries, livestock, tourism etc.), market centers and service centers (hospitals, healthpost,
schools etc.) of the district, various maps(administr.ative map, district road map, topographic maps etc),
will be collected from various district level offices as well as National level offices.
Different roads will have a different impact in people's life. It is essential to assess the future
benefits of a road before making decision about constructing new road or upgrading existing
road. Priority should be given to those roads that generate substantial benefits to local people.
Proper rural road selection criteria must give consideration to: ·
• Economic development such ·increase agriculture production, access to market and a raise in
income
• Improvement in Quality of life such as higher, education levels and an improved health status of
the population served 2
• Equity like improve the existing road density of the area (population/km or land area per km etc.)
and make it more equal with other areas
Once individual road has been selected for construction or up gradation, the detailed information on the.se
roads should be compiled for carrying out feasibility study. For this a walkover survey of the road (and
th~ corridor) needs to be undertaken so that technical, socio-economic, environmental and social
inforlnation pertaining to the road and the corridor is collected. At the same time an assessment of the
required civil works should also be undertaken so that a tentative cost estimate for the sub-project is
made.
The feasibility study report should be reviewed thoroughly by DDCs before approving and/or making
decision as to budgetary allocation. Under review process there may be various issues including
information on technical, socio-economic, environmental and social aspects of the proposed road. Result
ofthis process may be approval or acceptance of the project, refinement and approval and rejection.
Once the feasibility study report is accepted and investment decision is made, the detailed project report
need to be prepared. For this purpose, number of activities will have to be undertaken such as a) detail
topographical survey; b) socio-economic assessment; c) social and environmental impact assessment; d)
detail cost estimates and preparation of bid documents; e) preparation of implementation plan and
procurement plan.
This involves reviewing of the appraisal report and selection of the most appropriate project. This also
forms part of project negotiation. At this level, the implementing and financing agencies draw up a formal
implementation or operation plan. Once all these are done and are acceptable to both parties then, the
project is approved and funds and other resources are c<!inmitted for the implementation of the project.
Once approved, roads will be rehabilitated or constructed by the local departments, private contractors or
communities.
1.1.9 Evaluation
An impact assessment aims at appraising to what extent improved road links have led to changes life and
livelihoods in local communities. Impact studies often require sophisticated surveys to collect qualitative
and quantitative data necessary to measure changes.
Rural roads are part of total Transport Network which consists of highways, feeder road, district roads
and village roads including trail bridges for pedestrian mobility. Rural roads which include District Roads
and Village Roads are tertiary system for providing accessibility in rural areas.
'
· A road network, therefore, needs to be developed in such a way that the travel needs of the people in an
area are met to the maximum extent at the lowest cost of development. In rural areas major part of travel
needs comprises of travel to market place, education and health centers. Roads have to be planned and
programmed in such a way that all villages/habitations are connected in an optimal way to achieve
efficient flow of traffic and accessibility. Some of the concepts for preparing rural road network are:
Concept of zone of influence area: Concept of zone of influence area is defined as an area on either side
of the road that is within 4 hours walk from the road. The areas that are beyond the Zol are inaccessible
area. The planning team proposes the road network for the inaccessible area as identified by the Zol
analysis.
Accessibility Criteria: The accessibility may be classified as (i) access to fulfill social needs and (ii) to
provide access to market centers to increase economic activities of the area. Accessibility based network
planning shall be required to address the sparsely populated areas (like hill and Himalayas) with dispersed
settlements.
Fixed point system model: In a fixed point system model, junctions are confined to a finite set of
locations such as markets, historical/archeological locations, These junctions are connected by rural roads
to improve accessibility of the people to markets and services.
Rural road is one of the components. to improve the access through the increase on the mobility of
services and fapilities to the settlements/communities where the linkage with the market centers,
agricultural production pocket areas and other potentialities of the district. Preliminary road network plan
for inaccessible area is prepared based on the nodal points/market centers and national transport policy.
Local level workshops/meetings is conducted and the proposed preliminary network plan for inaccessible
area is presented and discussed to verify and preliminary approval of the proposed road networks. All
suggestions and feedbacks were collected and incorporated in preliminary proposed road network plan.
On long term perspective, District Transport Master Plan (DTMP) prepared for the planned development
of the rural roads in the district. It contains inventory of existing rural transport infrastructures, list of all
the rural transport infrastructures to be developed in future and prioritized list of rural roads to be
developed within next five years. DoLIDAR has recommended a set of particular steps while preparing
district transport master plan as given below (DoLIDAR Approach Manual)
Step 1: Prepare and finalize Indicative Development Potential Map of the District
Step 2: Prepare District Inventory Map of Rural Road Network
Step 3: Collection of Demands for New Transport Linkages from VDCs
Step 4: Prepare Draft Perspective Plan of District Rural Road Network
Step 5: Synchronizing the Draft Perspective Plans of adjoining districts
Step 6: Acceptance of the Perspective Plan of District Rural Road Network
Step 7: Preparation ofFive Year Rural Road Master Plan ofDistrict
Step 8: Updating year-wise list of prioritized road links and approval
The survey for the route selection is normally carried out in four stages: reconnaissance survey,
preliminary survey, and location survey. The final centerline is determined from the preliminary records.
Three different stages of route location survey are described below.
a. Reconnaissance Survey: Based on available information and maps (Topographical map of district,
meteorological, geological,' aerial photographs, etc. The reconnaissance is normally done by walking
along the tentative route. During the survey, assessment is made of various factors affecting the
alignment, ~uch as topography, soil conditions, availability of construction materials including
sources of water, climatic conditions, means of communication, construction feasibility, bridging
requirements, population centers, costs etc.
b. Preliminary Survey: After the reconnaissance survey, a preliminary survey is carried out in order to
study the most feasible alignment in detail. In this survey, use of survey instrument (compass,
leveling equipment) may be required. Based on the information and data collected, the calculation
and plotting work should be done in the design office.
c. Final locf}tion survey: After the alignment has been selected on paper, final location survey ·is
conducted to locate alignment on the ground. The centerline may be staked at 50 m intervals in
straight reac)les and 25 m in curves. In hilly and mountainous reaches, the interval may be reduced to
20 and 10 m respectively.
A number of considerations need to be taken into account before finalizing the alignment. It would be rare
that a single alignment satisfies all the factors involved. In most cases, an engineer exercises his judgment
and decides on the best alignment keeping in view the technical and other considerations. Some of the
factors to be considered are listed out below:
2. Cost
• Alignment that is most economical for construction, serving maximum number of
j:10useholds and as direct as possible
• A void costlier spots such as river crossings, hard rock cuttings and large gullies as far as
possible
• Minimal land acquisition and avoid costly lands, agriculture lands etc
4. Topographic Condition
• Steep terrain should be avoided
• Unstable hilly features (rock dips, fissured strata, Slides etc.) can lead to maintenance
problems on long-term basis
• As far as possible, mountain ridges should be crossed at their lower elevation.
• In hilly country, a location subject to sunlight should get preference over a location in the
shade.
• Areas liable to snow drift should be avoided.
5. Availability of Materials:
• Availability of materials for embankment and pavement construction should be kept in
view while finalizing the alignment
8. Environmentally sound:
• Avoid destruction of forests, national parks, conservation areas as far as possible
• Avoid passing through active landslides and vulnerable zones as far as possible
• Avoid any damage to the livelihood assets ofthe local communities e. g. water resources,
fertile lands, community forests, local trails
• It should also be kept in view of minimizing dust and vehicle exhaust .fumes
Nepal Rural Road Standard 2055 has classified rural roads as district road and village road.
District Road (Core network) - An important road joining a VDC HQ's office or nearest economic
centre to the district headquarters, via either a neighboring district headquarters or the Strategic Road
Network.
Village Road - Smaller roads not falling under District Road (Core Network) category are Village
Roads, including other Agriculture Road. ·
There are five classes of the rural roads including roads, trails and ropeways which are as follows:
Rural Road Class 'A' (RRA) - District Road: All rural roads which connect one or more major
Growth Centers (market, tourism centre, industry, etc.) or several VDCs with the headquarters of the
same/neighboring district directly or through the National Strategic Road Network
Rural Road Class 'B' (RRB) - Village Road: All rural roads which connect a Village Development
Committee Centre (VDC) with another VDC Centre or National Strategic Road Network or district
road or a major Growth Centre of the same/neighboring district.
Rural Road Class 'C' (RRC) -Main Trail: All major non-motorable foot/mule trails which connect
a VDC Centre with the district headquarters of the same/neighboring district, National Strategic Road
Network, district road, village road , another VDC Centre, A major Growth Centre of the
same/neighboring VDC.
Rural Road Class 'D' (RRD) - Village Trail: All minor non-motorable foot/mule trails which
connect a place of a village with VDC Centre of the village, another place within the VDC, a place of
the neighboring VDC, National Strategic Road ..Network, district road, village road, main trail, or
another village trail.
Rural Road Class 'E' (RRE)- Rope Way: In the high mountainous region where construction of
trails (with sufficient width) is impossible, rope ways shall be considered. One of the main purposes
of such rope ways would be the transportation of to and from the pocket areas where high value crops
are being produced.
The rural roads may also be classified according to the following criteria:
i. Serviceability condition
- All-weather roads (passable throughout the year)
-Fair-weather roads (passable only a part of the year)
2.2.1 Traffic I
It is necessary to design and construct new road or upgrade the existing ones using an anticipated
future traffic volume for design year. Rural road is designed for a capacity sufficient to cope with the
estimated traffic volume 10 years after the date of completion of the works.
b) Equivalency Factors
The design of road needs to meet different types of vehicles with different speed and capacity.
Equivalency factor is unit to convert different types of vehicles into equivalent passenger car unit so
that the capacity of a road can be expressed into a common unit. Tentative equivalency factors for
conversion of different types of vehicles into equivalent passenger cars units are given in the Table
below.
T a ble 1- E~mva
' Ien~ F actor
SN IVehicle Type l£quivalency Factor
1 Car, Light Van, jeeps and Pick Up 1.0
2 Light Truck up to 2.5 tonnes gross 1.5
3 !Heavy Truck 3.0- 4.0
4 !Bus, Minibus 3.0-4,0
5 . Motorcycle, scooter, bicycle 0.5
6 Rickshaw and Tricycle carrying goods 1.0
7 Hand Cart ~.0
8 Bullock Cart 6.0-8.0
9 !Pedestrian 0.2
10 !Porter 0.40
(Source: Nepal Rural Road Standard, 2055)
c) . Design Capacity
Design capacity is a given traffic volume that keep road at the Level of Service B. Level of service B
is defined as a stable flow zone which affords reasonable freedom to drivers in terms of speed
selection and maneuvers within the traffic strea~.
T a ble 2 D es1gn
' C apac1'ty 0 fR uraIRoad
District Road Core network) Village Road
Design Parameters
Hill Terai Hill Terai
Design Capacity - in both directions
200 (400) 400 (800) 100 (200) 200 (400)
Vehicle per day/PCU per day)
(Source: Nepal Rural Road Standard, 2055)
d) Design Speed:
Design speed is a selected speed used to determine geometric design features. The choice of design
speeds depends on terrain and road function. Minimum design speed may, however, be adopted where
the site condition and cost does not permit a design based on Ruling Design Sp~ed.
Table 3 Design Speed of Rural Road
Hills Terai
Road Categories
Ruling Minimum Ruling Minimum
District Road (Core Network) 25 20 50 40
Village Road 15 30
(Source: Nepal Rural Road Standard, 2055)
Carriage way width ofDistrict Road is 3.75 m but can be reduced to 3 m where traffic volume is less
than 100 motorized veh/day. For district roads (core network) with a volume of traffic greater than
400 vpd, carriage way width should be at least 5.5 m. The carriageway width of village road will be
3.75 m if traffic volume is more than 100 motorized vpd. The recommended carriageway width at
culverts and bridges are 4.25 m for single lane and 6 m for intermediate_ lane.
b) Shoulder Width
Shoulder width is measured from the edge of the carriageway to the edge of the usable formation.
Wide shoulders have following advantages; '
• Space is available for vehicles to stand clear of the pavement
• Non-motorized traffic/pedestrian can travel with minimum encroachment on carriageway and
greater safety. ·
• Provides additional maneuvering SP,ace
• The capacity of the road can be increased by providing paved shoulder up to 15%
• Sealing of shoulder reduces maintenance costs and improves moisture condition under
pavement
Since Non-motorized vehicles in hills are smaller than Terai, shoulder width in hills are relatively
smaller. Shoulder widths of each type of road are presented in Table 4 below.
6.25
5.25
3.75
:I
.10.75~
ct.
6.25
·I
I
1
1.5o m I
1
j
'"0
b I
~I
.JIJ1• $l)
~
I
n
:td 0
0
.s
Cl)
i I~
~
I=Q
-
Cl) I >-'•
~ Is: 0
...... '"0 ~ ~ I >-'•
l::l
~ ~ td
......gf
I(Jq
on ~ 0
:r~r
~
......
-::s
'"0
......
'"0
(lj
~
-
'"0
......
::s
I=Q I~
§
~
$l)
I
:(p
I
I=Q I
I I
I
0 !
Figure: Carnageway, Shoulder, Roadway width, RoW.
Shoulders having the same surface as the carriageway should have the same cross slope. Unpaved
shoulders on paved carriageway should be at least 0.5 per cent steeper than the cross fall of the
carriageway. However, 1 per cent more slope than the carriageway is desirable.
a) Lat~ral clearance
Lateral clearance between roadside objects and the edge of the shoulder should be:
• Hill road- normally 1.0 m (minimum 0.5 min steep and difficult areas)
• J'erai road- normally 1.5 m (minimum of 1.0 m)
b) Vertical Clearance
• 5m over the full width of roadway at all underpasses, and similarly at overhanging cliffs
• 7 m for overhead wires, poles etc
a) Super elevation
Super elevation is provided to maintain the design traffic speed at a given radius. Maximum Super
Elevation Value should not be more than 7% in terai and 10% in. hill.
Where,
v Vehicle Design Speed, km/hr
R= Radius, m
e Super elevation ratio, meter per meter.
f = Coefficient of side (lateral) friction between the vehicle tyres and pavement.
d) Widening of Curve
At sharp horizontal curves, it is necessary to widen the carriageway to provide safe passage of
vehicles. Widening is dependent on curve radius, width of carriageway and type of vehicle (length
and width).Widening has two components: (1) mechanical widening to compensate for the extra
width occupied by the vehicle on the curve due to tracing of the rear wheels, and (ii) psychological
widening vehicles in a lane tend to wander more on a curve than on a straight reach.
In single lane roads the outer wheels of vehicles use the shoulders whether on the straight or on a
. curve. Therefore use of the mechanical component of widening should be sufficient on its own. For
single lane roads, only mechanical widening is required for low traffic speed.
Lz
W=2R
Where,
W = Widening, m, L = length of wheel base of longest vehicle (m), R = Radius of horizontal curve, m
e) Hairpin Bend
Hairpin bend is a bend in a road with a very acute inner angle, making· it necessary for a vehicle to
turn almost 180° to continue on the road~ The designer should locate the hairpin bends at suitable and
flatter hill slopes, so that there is sufficient space for the layout of the hairpin bend. Proper water
management needs to be designed so that a disposal of water from the hairpin bend does not cause
erosion problems on the slope.
A hair pin bend may be designed as a circular curve ·with transition at each end. Alternatively,
compound circular curves may be provided. The desirable spacing of hair pin bend is 100 m for both
district road and village. However, it may be less as per site condition. The following design criteria
should be followed normally for the design of hairpin bends.
Table 7: Hairpin Bend Design Criteria
District Road 1 (Core
SNo. Design standard
.. Network)
Hill
Village Road
Hill
1 fhlinimum spacing between
100 100
Hairpin Bends (m)
2 Minimum radius of curve (m) 12.5 10
3 Minimum Roadway width a 5.5 for 4.5m roadway width 5 for a 4m roadway
apex (m) 6.25 for 5.25m roadway width width
4 !Maximum gradient (%) 4 4
5 Minimum gradient (%) 0.5 (max 1) 0.5 (max 1)
6 Maximum superelevation (o/o) 10 10
7 Minimum transition curve length
15 15
m)
pavement must have sufficient camber to drain storm water laterally. Recommended gradient for
different terrain condition are given in Table 8. Exceptional gradients should be adopted only in very
difficult places and unstable locations in short length in hill.
Table 8: Recomq~ended gradients
District Road Village Road
Design Standard
SNo Hill Terai Hill Terai
1 Ruling gradient (%) 7 5 7 5
2 !Limiting gradient (%) 10 6 10 6
3 Exceptional gradient (%) 12 7 12 7
!Limitation of maximum gradient length (m)
4 300 300
above average gradient of 7% - -
Maximum recovery gradient (%) to be
5 applied after gradient in excess of 7% for· a 4 4
minimum recovery length of 150 m - -
6 Maximum gradient at bridge approach (%) 6 57 6 5
Minimum gradient on hill roads (for better
7
drainage) (%)
0.5 (max 1%) - 0.5 (max 1%) -
c) Vertical curve
Vertical curves are introduced for. smooth transition at grade changes. Both summit curve and valley
curire are designed as parabolas. The length of vertical curves is controlled by sight distance
requirements, but curves with greater lengths are aesthetically better. Curves should be provided at all
grade changes exceeding those given in Table 12.2 and the minimum length as given in the same table
9.
2.2. 7 Others
a) Co-ordination ofHorizontal and Vertical Alignments
The plan and profile of the road should be designed in proper coordination to ensure safety and utility
of the road.
• Sharp horizontal curves should be avoided at or near the apex of the summit, on vertical
curves or the lowest point of valley curves.
• Horizontal and vertical alignment should coincide with each other as far as possible
and their length should be more or less equal. If this is difficult for any reason, the horizontal
curve should be somewhat longer than the vertical curve.
• The degree of curvature should· be in proper balance with the gradients
b) Passing Zone
·Passing place should be located every 300 m for Hill and 500 m for Terai. The location of passing
place depends on the sight distance and should be provided at or near blind and sharp summit
curves; where the likelihood of vehicles meeting between passing places is high; and where
reversing would be difficult. The passing places should be constructed at the most economic location
as determined by the terrain and ground condition, such as at transitions from cut to fill, rather than at
precise intervals.
The increased width at passing zones should allow two trucks (2 axles) to pass. The passing zones
should be tapered gradually towards the carriageway so that vehicles can leave or join the traffic
stream safely. The width of carriage way should be 5.5 m and length about 12m along the outside
edge and 30m along inside.
c) Lay-bys
Lay-bys may be provided for parking or for bus stops to allow vehicles to stop safely without
impeding passing traffic. The minimum bus lay-by width shall be 3 m (i.e minimum 6 m carriageway
widths). The lay bys should be tapered gradually towards the carriageway so that vehicles can leave
or join the traffic stream safely. The length should be 12m along the outside edge and 30m along the
inside edge. · ·
d) Traffic Signs
• Different regulatory and warning signs for narrow road widths; sharp and blind curves; .stop
signs at junctions should be provided for rural roads .
• All-weather roads should have kilometre posts. The shape and size of kilometre posts is as in
DoR Standard Design
• Delineator posts or other low cost delineating devices such as earth filled bitumen drum etc.
or low cost safety barrier such as gabion hairier should be provided along the sharp curves
and blind curves that have large (> 3 m) drops on the yalley side.
3.1 Definition
The term low cost road stands for roads that can be constructed and maintained at comparatively low cost
by using locally available resources. The DDC have to strike a balance between construction of roads of
comparatively higher specifications in which case the DDC has to curtail the length of such roads or to
cover larger area of district by comparatively lower specifications which may be termed as 'Low cost
roads.'
Low cost roads are characterized by:
• Design year traffic of less than 20 vehicles per day
• Constructed generally close to the ruling grade of the natural ground
• Constructed mainly from the in situ soils
• Constructed on the basis of minimal designs.
3.4.1. Definition
Environmental impact assessment (EIA) is a formalized procedure for investigating, analyzing and
presenting the environmental implications of a proposed development and identifYing mitigation
measures required to reduce environmental impact to acceptable levels. .
The advantage of such a procedure is that environmental impacts and potential benefits are brought to
light prior to implementation in an objective way, for discussion between concerned organizations such as
the funding agency, the client, natural resource experts, community representatives and the engineering
design management.
3.4.3. Procedure
a) Project description
An overview ofthe proposed (or existing) scheme is required, in terms of its location, size, technical
design and construction method, construction time-frame, estimated cost, labor force requirements and
operational procedures.
c) Impact prediction
Various types of impact on the baseline environment due to the project are to be identified early. Impact
prediction and assessment should be undertaken for all relevant environmental topics. Also, these impacts
are to be assessed during construction of road and after construction of roads. The following parameters
are assessed such as:
• Types of impact positive or negative, direct or indirect etc.
d) Evaluation of Alternatives
Avoidance of the impact is the preferred approach through selecting an alternative option or design.
BIAs address at least two alternatives (with and without the project); they can include multiple
alternatives (usually limited to three to five alternatives). Alternatives for projects may involve: I) site
selection (alignment alternative); 2) design alternatives for a given site; 3) construction, operation, and
decommissioning alternatives for a design; 4) project scale; 5) phasing alternatives; and 6) timing
alternatives etc. Alternatives are compared as per total impacts associated with each alternative. Different
approaches such as weighting scheme, ranking, scaling scheme helps to clarify the total impact associated
with each alternative.
g) Environmental Monitoring
Environmental monitoring is the process of measuring changes in landscape, land use or cultural activity
that arise as a result of the implementation of a development project. Monitoring measures for the project
may take a variety of forms such as:
• Compliance monitoring to enforce the implementation of agreed mitigation
• Effects monitoring/evaluation to consider the accuracy of the EIA predictions
Environmental Monitoring also helps to identifY, evaluate and mitigate any undesirable effect which was
not predicted during project feasibility and design stage.
a) Rock blasting
Uncontrolled rock blasting is a typical feature of road construction in Nepal and other developing
countries. Labour-intensive methods of excavation rely on a totally fragmented rock mass for easy
removal. However, bulk blasting usually results in s~nificant over break and the creation of a highly
fractured rock mass. Cushion blasting remove smaller quantities of rock along predetermined planes of
weakness so that over break is minimized and the remaining rock mass is left intact, and hence is more
stable. However, these methods require a greater design expertise and a large number of closely-spaced
drill holes to be accurately orientated.
e) Rate of construction
Actual rates of construction vary widely according to the relative proportion of labour and machine-
intensive activities, volumes of earthworks, frequency and size of culverts and retaining walls, and the
ability to construct pilot tracks (see below). In a labour-based approach, the rate of construction will
depend upon the size of the labour force, although factors such as availability of materials, spoil disposal
and the contractor's working method are also relevant. Dry season labour-intensive construction rates
might be of the order of 1km/month. In the case of predominantly machine-intensive construction, the
rate of progress of advancing or fronts might be between 2 and 3km/month, depending on formation
width, access and contractor's working method. 0.5km/ month is probably the maximum progress likely to
be achieved in the wet season. 3.Construct pilot !.Clear and remove 2.Strip topsoil as
:•cldf poo•ihle Thn' & Vog<tWon re\ire~ ~:b/ '
f) Construction sequence
The recommended sequence of
cross-section construction is shown 4.Bench Slope, \ _ ,,--
in Figure 4.2. excavate road, construe}-''
10. Trim slope & \ embankment _,-'
1) Clear and remove turf and plant vegetation
vegetation
2) Strip topsoil as required, grub
out roots
3) Construct pilot track if -·-·-
practicable
4) Bench slope, excavate road, ·-·-· 5.Construct cross
construct embankment drainage if any
5) Construct cross drainage if any ~- 6.Construct retaining
6) Construct retaining wall if any wall if any
Figure 4.2 Typical sequence of cross-section construction
In mountains the possibilities for upgrading through widening or improvement to geometric standard are
limited, as it is impracticable to make minor modifications to the geometry without having to undertake
significant earthworks and retaining wall construction, involving high costs and the risk of reactivating
slope instability and erosion.
i) Maintenance practice
Timely maintenance is necessary to avoid unstable situation. Proper design of retaining wall, drainage
works and good construction supervision during maintenance work are as important as during the initial
construction period. Neglected and ill advised maintenance practice should be avoided. Some of the more
common maintenance practices that create instability problems are listed below:
• Uncontrolled tipping of spoil materials arising from cut slope failures. This causes erosion and
siltation below the road .,....
\ ...___ /
• Diversion of road drainage water around slip material on the carriageway causes uncontrolled
runoff over the road edge
• Failure to repair eroded side drain inverts leads to erosion of adjacent materials
• Failure to clear drains of debris leads to overtopping of the drain and erosion of adjacent slopes
• Quarrying into cut slopes for road maintenance materials, and inadequate quarry restoration, can
create slope instability problems
• Often, where the slope below the road is eroding, a hillside is progressively cut back in order to
maintain passage. This de-stabilises the hillside.
• Removal of construction materials and disturbance to road drainage systems are problems that
require rectification and monitoring.
Government of Nepal
• Department of Road (DoR)
• Department of Local Infrastructure Development and Agricultural Roads (DoLIDAR)- it
co-ordinates and monitors all programme activities in close consultation with the RAP TA
consultants.
• Other line departments of HMG such as Ministry of Agriculture and Co-operatives, Department
ofForestry, Department of Irrigation, Nepal Electricity Authority, Department ofHousing and
Building Construction
• Local government bodies ofNepal Government such as
o District Development Committee (DDC)
o Village Development Committee (VDC)/Municipalities
4.1. Culvert
A closed conduit placed under the embankment to carry water from the uphill side of the road to the
lower side where it can be safely discharged. The water may be from natural streams or run-off surface
water from the road structure or areas close to the road. More than 75% cross drainage structures are
culvert. Culvert are preferred because: '
• Culvert are laid beneath embankment
• Culvert does not change driving condition as 50 em back fill embankment above it
• Hydraulically efficient
• Identical discharge through culver is higher than bridge
• Arch Culvert
- • Slab culvert: slab culvert is one where a
simply supported reinforced slab is
placed over abutments
(2) Apron: Aprons are constructed at the inlets and outlets to protect the culvert bed and the
connecting ditches from erosion and scouring. At the ·outer end of the aprons, it is common
practice to construct a toe wall to prevent water from eroding the soils underneath the apron.
Aprons and toe walls can be made of stone, brick, concrete or gabions.
(3) Headwall: Head wall protects backfill and side slope of the road embankment from water.
Headwall built parallel to centre line of road and is made of dry stone, masonry or concrete.
(4) Wing wall: The wing walls prevent scour, soil erosion, retain the embankment adjacent to the
culvert, and direct water flow. They are constructed at an angle of 30° or 45° to the culvert centre
line. Wing wall also can be built using hand packed stone, mortar bound masonry or concrete.
(5) Drop inlet: Drop inlet is constructed if headwall and wingwall at inlet side is not provided. In
populated areas, the inlet can be fitted with a grill to avoid people and debris falling into it.
(6) Bedding: The pipes are htid on stable bedding, properly aligned and at correct levels. Depending
on soil foundation, bedding may be sand bedding or PCC or RCC. Sand bedding is for pipe
culvert.
Pavement
Backfill embankment Inlet Headwall
Outlet - Headwall (Compac din layers of 15 em)
.. . ... ..
Apron Subgrade
(Concrete+Stones)
"'*
/
• If the culvert is required for a stream, it should / \, I
follow the alignment of the existing channel - 'v<_ .
a
skewed if required. If it is relief culvert, it ~' \ ,~~\-
should be set out perpendicular to the road
centre line. __ _R~ . _
• Culvert skew should not generally exceed 45
degrees measured from a line perpendicular to
,.__
\
"-'1
the roadway centerline. . ------ l,__ ~'
(2) Slope of Culvert (gradient of culvert): Gradient of culvert is as close as natural gradient of bed
slope of water way. Recommended gradient of culvert is 1 in 100 in hill roads (max. 1 in 30) and
1 in 1000 in plain roads.
(3) Culvert size: The minimum size of the culvert is fixed on the basis of ease in maintenance,
movement of fish, debris etc. Nepal rural road standard recommended minimum 60 em diameter
of pipe for circular culvert. Minimum 1.2 m diameter has been recommended by IRC SP 13: 2004
for Hume Pipe culvert for easy cleaning and maintenance.
(4) Height of Culvert: Minimum height of the formation level of the road from bed level is 1.75 m
for 1 m diameter pipe and 2.15 m for 1.2 m diameter pipe. Minimum height of slab culvert is
1.775m which include height of abutment (1.5m), thickness of slab (0.2m) and wearing coarse
(0.075m)
(5) Length oflleadwall: Length of headwall is four times diameter of pipe. Headwall is raised upto
top ofthe pipe and 0.5 m parapet wall is provided above it
(6) Invert level and height of fill: Invert level for· culvert is 150 mm below the average bed level.
Minimum height of fill above pipe is 1 IIi.
(7) Jointing: Flush joint or collar joint is provided to join two pipes with space 13mm for filling
cement. Width of collar is 150 to 200 mm
The hydrological design of a culvert is governed by the hydrological response of a catchment to the
design rainfall over it. Various factors which affect the peak run-off from a drainage basin are
Characteristics of catchment areas such as size, shape, slope. Cover conditions, permeability,
antecedent moisture condition etc.
Rainfall- .its magnitude, inter;tsity, duration and frequency (or return period) .
• Time of concentration i.e. the time of overland flow and flow through channel from the
hydrologically most distant point in the catchment (Ic)
• Determination of storm duration to be consi~red depending upon concentration time
Movement of storm towards or away from the outfall point
Since the catchment area of culverts is small, peak flood for culvert is usually calculated by using
Rational formula:
=
Q 0.028 PfAle
Where,
Q= Maximum run off (peak flood discharge) in m 3 /sec,
f = speed factor depend on catchment area
P = mean run-off coefficient of the catchment area contributing flow to the culvert. 'P' value
can be found by the relation given by equation (2)
p = L~lAiPi
Ef=lAi
Io =F( 1
1
+2 /r)
F = the of rainfall in em dropped by severest storm over a period ofT hours
tc = time of concentration in hours
. = (0.87L3)0.385
tc H
Where, 'L' is the distance from the critical point to the culvert in km, and 'H' is the fall in level from the
critical point to culvert in m
Q = A X 4.43 ( 1 +
. Ke
H + Kr :Y
Entry & friction Circular pipes Rectangular Charts
co-efficient Square entry Bevelled entry Square entry Bevelled entry
i.)
-
Dead Load: Dead load is the total weight of all superstructure elements (elements above the
bearing) such as the deck, wearing coat, railings, parapet, stiffeners and other utilities. ·
ii.) · Live Load (Vehicle Load): Live load includes standard wheeled or tracked vehicles or trains of
vehicles that moves along the length of the span. By definition a man walking on the bridge is
also a live load. Small bridge or culvert shall be designed to withstand IRC class A for all
permanent bridges and culverts. For temporary bridge such as bridge with timber span and for
bridges in specified area, IRC class B loading shall be adopted..
iii.) Impact Load: Impact or dynamic load is considered by an increment of the live load by a
fraction of the applied live load.
iv.) Wind Load: All structures shall be designed for lateral wind forces. The wind forces depend. on
wind pressures and wind velocities.
v.) Water Current Force: Any part of a road bridge which may be submerged in running water
shall be designed to sustain safely the horizontal pressure due to the force of the water current.
The force of water current depends on water velocity and shape of pier
vi.) Longitudinal forces: Longitudinal forces arises due to tractive effort cause through acceleration
of the driving wheels, braking effects results from the application of the brakes, frictional
resistance offered to the movement of free bearings due to change oftemperature.
vii.) Centrifugal forces: Where a road bridge is situated on a curve, all portions of the structure
·affected by the centrifugal action of moving vehicles are to be considered.
viii.) Buoyancy: In the design of abutments, especially those of submersible bridges, the effects of
buoyancy shall be considered ·
ix.) Earth pressure: Structures designed to retain earth fill shall be designed to withstand pressure
due to soil behind.
x.) Temperature: Change in the overall temperature of bridge result in load effects due to restraint
to the expansion/contraction of structures, temperature differences between top and bottom
layers, frictions on bearings etc.
xi.) Deformation stress: A deformation stress due to the bending stress caused by vertical deflection
of the girder. All steel bridges shall be designed such that deformation stresses are minimum
xii.) ErectiQn Stress and construction loads: Erection stresses during construction shall be
considered. Construction .loads are those which are incident upon a structure during the
· construction of structures.
xiii.) Seismic Force: Both horizontal and vertical seismic forces may be taken into account
xiv.) Snow load: Snow load to be considered where accumulation of snow is considerable.
both through the culverts and over the road. Deck level is so fixed that it does not get submerged except
during high flood
Points to be considered:
• Period of interruption of traffic 3 days or 15 days per year in total
• It should be designed for flood over 10 year as design,flood
3m
_,.,__~I• 31"d_15% 1•
.. 4 - 24 m .. I•
-~-'··~-Concrete or Cement
masonry Retaining wall
4.10. Scupper
It is most economical type of cross drainage structure. .. . . • . 1)('\,. .. • . • . .
. '.a.· ... ........ .. . ..
Water is collected through side drain: It is 0.9 to 1 m
wide made of random rubble dry masonry abutment. The
abutments are constructed with the coursed dry rubble
masonry and to reduce the width at the top, they are
corbelled from both the side till a gap of 500mm t~
600mm remains; the gap is then covered up by stone or
concrete slab. · · ""
a) Material:
• CBR not less than 5% measured after a 4-day soak on a laboratory mix compacted to 95% MDD
(heavy compaction),
• Expansion less than 1%
• Plasticity index less than 40%
• Organic matter content less than 3%.
b) Desirable properties of Sub grade soil
• Stability
<.J • Incompressibility
• Permanency in strength
• Minimum variation in expansion
• Good drainage
• Ease in compaction
5.2 Embankment
Embankments will be required to obtain a satisfactory alignment. The road embankments will be needed (i) to
raise the road above flood water levels, (ii) in side long ground, (iii) across gullies and (iv) at the approaches
to water crossings.
It is important to identify all potential problems during the survey and recommendations made for more
detailed investigations where necessary. Following points are to be considered for constructing embankment.
• Look for evidence of water flow across the line ofthe road, either on the surface or at shallow depth.
• Drains must be installed to intercept ground water, and culverts of suitable size must be provided to
allow water to cross the road alignment where necessary.
• It is also important to identify any areas of potential ground instability which might affect
embankments. • ·
\_J
• The slope below the road should be examined to ensure that it is not being undercut by the stream at
the base.
a) Materials: Almost all types of soil (sandy clays, broken rock etc.) Material of low plasticity is preferred.
a) Selection of Materials : Earth available could be used but preferable to have soil properties as given
below·
Base Course Wearing Course
Liquid Limit <35% <35%
Plastic Limit <6% 4 to 10%
b) Construction Procedure
• Soil survey is done to find borrow pit material which are free from organic matter, trees, shrubs, grass
roots and top soils
• Centerline with wooden pegs and referenc.e pegs are fixed
• Sub grade is prepared by clearing site, grading cut or fill to the desired grade,· shaping of sub grade
and compaction before placing the material
• The borrowed soil are dumped on prepared sub grade and pulverized. The field moisture content is
once checked and additional water mixed if necessary to bring it up to OMC.
• . Soil mixed with water spread and rolled in layers up to compacted thickness 10 em.
• Camber of final compacted pavement is 1 in 20 to 1 in 25 to keep the pavement surface free from
standing water.
• After few days, road is opened to traffic after setting of compacted earth
a) Material Selection: The material shall be of crushed stone, free from clay, organic matter with Los
Angels Abrasion (LAA) Max. 35% (base), 40% (sub-base); Aggregate Impact Value (AIV) Max. 20%
(Base) 30% (Sub-base); Sodium Sulphate Soundness (SSS) Max. 12% (base & Sub-base), Flakiness
Index (FI) 25% (base) 30% (Sub-base), CBR Min. 80% (base) 60% (Sub-base), California R-Value (CR)
Min. 80% (base) 30% (Sub-base), PI Max. NP (base) 6(Sub-base)
b) Equipment: Static roller (normally10"12t) and vibratory roller, dozer/digger/loader and grader, Haulage
by truck, tractor trailer or cart, watering equipment, pump etc.
c) Construction Procedure:
• The preparation ofthe existing surface includes clearing and reconditioning infnecessary
• The aggregate are spread uniformly upon the prepared surface to achieve final compacted thickness of
150 mm.
• Aggr~gate is first rolled dry with a vibratory roller. The rolling shall begin from edges with roller
running forward and backward, parallel to the centre line ofthe road until the layer has been firmly
compacted.
• The rolled surface is checked transversely and longitudinally with templates to see any irregularities
• After the dry rolling, the surface is sprinkled with water, swept and rolled with the a vibratory roller
• The sprinkling, sweeping, and rolling operations is continued until the coarse aggregate has been
thoroughly keyed, well bonded and firmly set in its full depth
• After final compaction of the road base, the road shaii be aiiowed to dry overnight
• Open traffic after 24 hours
a) Materials Selection: Hard, durable and strong varieties of gravel of specified gradation are used. In
practice, softer varieties are also used. Rounded stone or river stone are not preferable as they have poor
interlocking properties. Proper gradation is chosen to have a maximum density.
b) Equipment: Static roiier (normaiiyi0-12t) and vibratory roiier, dozer/digger/loader and grader, Haulage
by truck, tractor trailer or cart, watering equipment, pump and bowser).
c) Construction procedure
• Clearing and preparing the surface on which gravel material is to be placed
• The gravel course materials are placed on prepared surface
• Spreading of gravel material is done either by hand or by graders in a uniform layer or layers not
exceeding 150mm compacted thickness.
• The moisture content of the gravel material is adjusted by watering with sprinkler trucks or by
manually
• The gravel materials are compacted by means of compaction equipment progressing gradually from
the outside towards the centre of the road with each succeeding pass uniformly overlapping half of
roiier width of the previous pass. ·
• Rolling is continued until the entire thickness of each layer is uniformly compacted to the specified
density
• The gravel course shall be compacted to 98% MDD(Road base) or 95% MOD (Sub-base & Shoulder)
• ·Open the traffic after 24 hours
a) Materials
• Shape of broken stones should be angular and cubical to behave adequate interlocking. Gravel with
rounded shape is undesirable when superior wearing is not provided. ·
• Hand or machine crushed stone durable single size coarse aggregate (nominal 35-50mm) with a Los
Abrasion value of less than 40% and flakiness index less than I 5%.
• Screemng matena . Is
Grading Size range Screening
1 90 to 40 12.5mm
2 63 to 40 IOmm
3 5 to 25
• Filler materials (binding material) : Plastic Limit of fiiier materials shall be up to 9
b) Equipment: Manually or water tanker, grader and compaction equipment (static roller 10- 12 ton)
c) Construction Procedure
i) material required with 20% extra broken stones shall be' stocked along the roads
ii) preparation of sub grade for receiving the WBM course
iii) pavement construction
a. Lateral confinement may be done by compacting the shoulder in advance to a thickness equal
to that of the compacted WBM layer and by trimming the ihner side vertically.
b. Spreading of coarse aggregate- Compacted thickness< 7.5cm
c. Dry rolling- roller 6 to 10 tonnes
d. dry screening is applied gradually over the surface to fill the voids.
e. The surface is sprinkled with water a and wet rolling to fill about 50% or total voids
f. Application of binding material at a uniform and slow rate at two and more thin layers
iv) Making of shoulders
v) Opening of traffic after few days of construction
a) Equipments: Laboratory facilities to determine ff'ie proportion of the modified material, motor grader
or rotavator for mixing, compaction equipment such as 3 tone vibrating roller, Hand tools and
equipments for labor based construction
b) Material Selection: Density 95% maximum, Plasticity Index 6 for base course and 5 to 10 for
surface course
c) Construction Procedure:
• Preparation of sub grade or sub base
• Pulverization of soil
• Application of required proportion of material and mixing
• Spreading and grading ·
• Compaction by smooth wheeled roller
a) Material: Consistent quality cement (normally Ordinary Portland Cement), fresh water for
compaction moisture control and curing, material grade (passing 4.75 mm > 50%, passing 0.075 mm
> 50%, Liquit limit >40%, Plastic limit > 18%)
b) Equipment: Mixing plant- manually or a small agricultural tractor (rotovator) for mix in place or
mixing plant for plant mix, light vibrating roller (1-3 t) for compaction
c) Construction procedure:
• Preparation of sub grade or sub base
• Pulverization of soil
• Application of cement and dry mixing
• Addition or spraying water and reaming
• Spreading and grading
• Compaction by smooth wheeled roller
a) Equipment: Mixing plant- manually or a small agricultural tractor (rotovator) for mix in place or
mixing plant for plant mix, light vibrating roller (1-3 t) for compaction
b) Material Selection: Local soil compatible with lime modification. Source of consistent quality slaked
or hydrated lime, calcium hydroxide- Ca(OH)2, Fresh water for compaction moisture control and·
curing.
c) Construction Steps:
• Preparation of Sub grade
• Pulverization of the soil to be stabili.zed
• Addition of part of lime as dry powder or as. slurry with water and mixing
• Allowing mixture to age for a day and remixing when pulverization becomes easy
• Addition rest of the lime and water if necessary and remixed
• Spreading to desired grade, shape and compaction
• Curing - soil lime is protected from drying out and allowed moist curing for .14 days
• Check moisture content at the time of compaction and checking of dry density soon after
compaction
5.4 Shoulders
Shoulders provide lateral support for the pavement layers, as well as providing the space for vehicles to pass.
The shoulders are constructed of the same material to the full width of the road. Thus the shoulders will have
the same permeability as the pavement However, it will generally be too expensive to construct them to' the
full width using wholly crushed materials. Therefore, shoulder is also constructed with different material.
5.5.1.1 Bitumen Chip Seals (Seal coat) (Surface Dressing or Surface treatment)
Chip Seals (Surface dressing) comprise the application of a seal of bituminous emulsion binder material over
the previously prepared road base. The. seal is immediately covered with single sized stone aggregate
chippings that are lightly rolled into the seal to form an interlocking mosaic.
When one application of bituminous material and aggregate is placed it .is termed as Single Bituminous
Surface Treatment (SBST), with two applications it is termed as Double Bituminous Surface Dressing
(DBST). When a tougher, more resistant surface is desired than that obtained with a single surface treatment,
-
multiple surface treatment is used. In DBST the first layer chippings (typically 14-19mm) are larger than the
second (typically 6-lOmm).
a) Equipment: Manual watering cans or a towed/self-propelled distributor for spraying binder, a manual
.
''--...c/
chip spreader or from a truck with or without a tailgate chip spreader, 5- to 8-ton roller (pneumatic tire
roller), mechanical brooms etc.
b) Material Selection: Aggregate with a Flakiness Index less than 20%, the nominal size of chippings
normally used for SD are 6, 10, 14, 20, and bitumen of 80/1 00 penetration grade
c) Construction Procedure: Single Bituminous Surface Treatment (SBST)
• The surface is thoroughly cleaned by sweeping with mechanical brooms. All loose and foreign
material are removed
• The edgesofroad surface shall be marked out and prime/tack coat is sprayed on to it at the
specified rate
. • The primed surface is allowed to cure for at least 24 hours, during which period no traffic is
ill~~ .
• An asphalt emulsion is applied from a spray truck to the surface of the existing pavement
• A thin aggregate cover of uniform gradation is spread over the asphalt material before it has set.
· • A pneumatic tire roller is used to push the aggregate into the asphalt material.
• Excess chipp"ing should be removed within 24 - 48 hours
d) Construction Procedure: Double Bituminous Surface Treatment(DBST)
• Lay the first layer the same as a single surface treatment. Sweep away loose aggregate so that
subsequent layers will bond together. ·
• Apply binder (bituminous) material about one-third or one-half of the first layer
• Apply the aggregate which is about one-half the diameter of that used in the first application.
• A roller (usually a pneumatic tire roller) is used to push the aggregate into the asphalt material.
• Excess chipping should be removed within 24 - 48 hours
a) Equipment: light static roller (preferably rubber tyred), watering cans or hand lance or motorized
hand sprayer for applying bitumen, manual tools or distributor for spreading Sand, hauling trucks or
wheel borrows, shovel etc.
Percentage passing
Sieve (mm)
b) Materials Selection: Medium curing cut-back MC-800 or bv wei!!ht
MC-3000 or Kl-60 cationic emulsion, fine aggregate 10.00 100
(sand, or fine screenings) free from organic matter, clay 4.75 70-90
and other deleterious materials. The fines (passing a 0.425 2.36 45-75
mm sieve) shall be non-plastic. The grading has shown in 0.60 IS-35
Table. 0.15 0-2
c) Construction Procedure:
• The surface to be covered is cleaned of all loose materials and foreign matter with mechanical
brooms and defects shall be corrected, if any
• The edges of road surface shall be marked out
• Medium cured cut back or asphalt emulsion is applied from a spray truck to the surface of the
existing pavement. Bitumen is applied at the rate of 1.2- 1.4 liter/m 2 for cut back bitumen and 1.4
- 1.6 liter/m 2 for emulsions.
... • Sand is uniformly spread over the asphalt material before it has set. this the sand is applied at a
rate between 100 and 200 m2/m 3 ·
·1B!nder
2 Grade<! aggregate
DOUBlE OHA
SEAL
!No Prime
!Binder
2Grnde<l
aggregate
a) Eqtlipment: Hot bitumen spray equipment; 10-12 Tonne pneumatic tyred roller or suitably loaded ."---./.
trucks. Hand tools such as shovels, wheelbarrows, and hard brooms etc.
b) Material Selection: Graded Soft bitumen (MC3000 cut-back or 150/200 penetration grade).
Aggregate of plasticity index 10 (maximum) and Flakiness index 30 (maximum). Graded natural. or
processed fime aggregate
· w1t· h the grad.mg as £0 11ows:
Sieve Sizes (mm) %passing
19 100
16 80- 100
13.2 52-100
9.5 36-98
6.7 20-80
4.75 .10-70
2.00 0-48
1.18 0-38
0.425 0-25
0.075 0-10
Construction procedure
''---'/
• Base formation is broomed to make it dust free •
• The aggregate is transported and placed along the both side of road section to be sealed
• The bitumen distributor is checked to ensure right temperature and uniform spreading. One half width
of the road section of about 300m is sprayed
• The chip spreading team cover each section sprayed with aggregate as fast as possible and within
about 20 minutes.
• Compaction of the uniformly laid chippings is done with pneumatic-tyred rollers of a minimum
weight of 12 tonnes or more. A minimum of 15 passes is required,
• After the initial rolling, it may be an advantage to apply one pass with a static tandem steel roller to
improve the embedment of the larger aggregate
• Commercial traffic is allowed on the surfaced area immediately following completion of the initial
rollirtg with the pneumatic roller(s) ·
• Minimum of 15 passes with the pneumatic tyred roller should be applied daily for first two days in
order to ensure that all particles are embedded in the binder.
• Second layer is applied 8- 12 weeks after first layer completion
a) Material required:
• Bitumen- 80/100; 60/70; 30/40 (5-6.7 kg/m 2 for first application for 5 and 7.5 em thick, second
application 2-3 per m2)
• Aggregate used for this construction should be hard strong, durable clean etc. with LAA value 40%
(max), Aggregate Impact value - 35%(max), Flakiness ind~x - 25%(max). Stripping Value - 25%
max. Grad' 'h
atton o f aggregate Is c osen depending upon thickness of laver:
Fine
Coarse Aggregate Key Aggregate
aggregates
Layer
Approx. Qt. Approx. Qt. Max. size
Max. size Max. size
required required
3
7.5 em thick 63 mmdown 0.90 m3/10m 2 25mmdown 0.18 m /l0m 2 10mm
5 em thick 50mmdown 0.60 m3/10m? m
19mmdown 0.15 3/10m 2 IOmm
b) Equipment: Bitumen Heating device, Bitumen distributor, Aggregate Spreader, Pneumatic Roller
c) Construction Procedure
• Preparation of existing surface and recondition it as necessary
• Spreading of Coarse aggregates
; • Rolling- 10 tonnes
• Apply the first layer of bituminous material- 5-6.7 kg/m2
• Spreading of key aggregates
~
• Rolling- I 0 tonnes
• Apply the second layer of bituminous material.
• Apply stone chippings .
• Drag-broom, roll, and hand-broom the surface
• Opening of traffic - After 24 hours
__./
\,
a) Material
• Bitumen- 80/100 grade 313 kg per 100m2 for 40 mm thick and 176 kg per 100m2 for 20 mm thick
• Coarse aggregare- should be angular, clean, hard, tough, durable with 16 mm downsize aggregate for
40 mm thick and 10 mm downsize aggregate for 20 mm thick with LAA value 40% (max),
Aggregate Impact value- 35%(max), Flakiness index- 30%(max)
• Sand should be of clean, hard, durable
b) Plants and Equipments: Bitumen heating device, Bitumen Distributor, Mechanical pavers, grader,
Pneumatic Roller
c) Construction Procedure:
• Preparation of the existing surface- cleaned of dust, loose material and foreign material
• Application of tack coat or prime coat- Bitumen is heated I 77°-188° and spread uniformly at the rate
of 1 kg/m2
• Preparation and placing of premix- coarse aggregate and bitumen are thoroghly mixed by mechanical
mixtures or hand mixing drums
• Transportation and spreading- Premix is emptied on the wheel barrows and carried to work site.
Immediately after applying tack coat, the premix is spread with rakes to the required thickness and
distributed evenly by means of a drag spreader
• Rolling and finishing by 8 to 10 Pneumatic roller. Rolling should commence from edges and proceed
towards center longitudinally
• A liquid seal coat, having following specifications should be applied immediately after laying the
carpet and rolled to achieve maximum compaction
• Opening to traffic after 24 hours
Asphalt concrete means a thoroughly controlled, hot-mixed, hot-laid, plant mixture of well graded dried
aggregate and penetration grade bitumen, which, when compacted, forms a dense material. Mix should have
following properties:
Wearing course Binder course
Stability 50 blows (N) Min 8000 Min 6000
Flow Value 2-3mm 2-3mm
Voids in mix % 2-4 3-7
Com~J>ression/Immersion Ratio > 0.75 >0.75
a) Material :
• Maximum sizes of aggregates are 20 mm down or 12.5 mm down. Properties of aggregate are Los
Angles Abrasion Value (40% max), Aggregate Impact Value (30% max), Flakiness Index (25% max),
Stripping Value (25% max)
• Filler consist of finely ground particles of limestone, hydrated lime, ordinary Portland cement or other
non-plastic mineral material.
• Bitumen of grade 30/40, 60170, 80/100 and quantity is determined by Marshall stability test (about 5
to 7.5% by weight of aggregate).
b) Plants and Equipments: Bitumen sprayer, Bitumen Distributor, Hot mix Plant, Mechanical pavers,
grader, Pneumatic Roller
c) Construction Procedure
• Preparation of existing base course layer
• Production of mix from hot mix plant
• Laying of the mix to the required grade and shape. The minimum thickness of the compacted layer in
· wearing course shall be 25 mm and 40 mm in binder course
• Rolling first two passes by either 8 tonnes smooth wheel roller, 4 tones vibro roller and then with 8 to
12 tonnes pneumatic roller
a) Materials: Portland cement, coarse aggregates with Crushing Value - 30% max., Aggregate Impact
Value- 30% max., L:AA - 16% max., Soundness Value- 12% in Na2S04 and 16% in MgS04 and fine
aggregate
b) Plant and equipment: Concrete mixture, hatching device, wheel barrow, needle vibrators, brus.h,
finishing tools etc.
c) Construction Procedures
• Preparation of Sub Grade and sub base: cleaned of dust, loose material and foreign material
• Placing of forms: All form work are placed and well secured to resist the tamping forces. The top edge
ofthe formwork shall be within± 2mm of the required finished rmid levels
• Batching of material and mixing: Coarse aggregate, fine aggregate, cement and required amount of
water are either mixed on site in batch mixer or transported from mixing plant.
• Transporting and placing of concrete : Concrete is transported to the site and deposited on the sub
base to the required depth
• Compaction and finishing: Once the concrete had been placed uniformly within the forms,
compaction is carried out using a mechanical poker (needle) vibrator.
• Texturing: Just before the concrete becomes non plastic, the surface shall be textured with an
approved long handled steel or fiber brush. Texturing is perpendicular to the center line of the
pavement and about l.Smm deep
• Curing of cement Concrete: After finishing, the pavement surface shall be entirely covered with wet
hessian cloth, burlap or jute mats for 24 hours. Upon the removal of wet covers, the slabs shall be
thoroughly wetted and then cured by ponding.
Construction Procedure:
• Construction of cement/lime stabilized base
• Construction of bituminous surfacing
Chapter 6
Flexible and Rigid Pavement Construction
• Flexible pavements: Those pavements which are surfaced with bituminous materials. These types of
pavements are called "flexible" since the total pavement structure "bends" or "deflects" due to traffic
loads. A flexible pavement structure is generally composed of several layers (surface, base, subbase) of
materials.
• Rigid pavements. Those which are surfaced with portland cement concrete (PCC). These types of
pavements are called "rigid" because they are substantially stiffer thim flexible pavements due to PCC's
high stiffuess ..
,,
Flexible Pavement Rigid Pavement
i. Deformation in the sub grade is transferred to the i. Deformation in the subgrade is not transferred to
. upper layers
ii. Design is based on load distributing
subsequent layers
ii. Design is based on flexural strength or slab
characteristics ofthe component layers action
iii. Have low flexural strength iii. Have high flexural strength
iv. Load is transferred by grain to grain contact iv. No such phenomenon of grain to grain load
transfer exists
v. Have low completion cost but repairing cost is
high
vi. Have low life span (High Maintenance Cost)
- v. Have low repairing cost but completion cost is
high
vi. Life span is more as compare to flexible (Low
Maintenance Cost)
vii. Surfacing cannot be laid directly on the sub vii. Surfacing can be directly laid on the sub grade
grade but a sub base is needed
viii. No thermal stresses are induced as the pavement viii. Thermal stresses are more vulnerable to be
have the ability to contract Md expand freely induced as the ability to contract and expand is
very less in concrete
ix. Thats why expansion joints are not needed ix. Thats why expansion joints are needed
X. Strength of the road is highly- dependent on the X. Strength of the road is less dependent on the
strength of the sub grade strength of the sub grade
xi. Rolling of the surfacing is needed XI. Rolling of the surfacing in not needed
xii. Road can be used for traffic within 24 hours xii. Road cannot be used until 14 days of curing
xiii. Force of friction is less Deformation in the sub xiii. Force of friction is high
grade is not transferred to the upper layers.
xiv. Damaged by Oils and Certain Chemicals xiv. No Damage by Oils and Greases
-
"'
The road construction may be done manually or by means of equipment. If the road construction is done
manually, it takes lot oftime to complete the road project. Usually for small projects labor intensive works can
be adopted. But for big projects without construction equipment, it is almost impossible. However in developing
countries like Nepal most of contractor prefers to use more labor than to utilize construction equipment because
of cheap labor and expensive equipment. The equipment has to be imported from other countries and need more
investment for the purchasing and there is no guarantee of getting continuous work for the purchased equipment
and most of the time equipment will be idle.
1. Tools
• Hand shovel
• Spade
• Chisel
• Peak
• Hand rammer
• Brushes
• Trowel
• Wheel borrows
2. Equipment
b. Compaction equipment
c. Leveling equipment
• Grader
d. Paving Equipment
• Binder spreader
• Heating kettle for binder
•: Aggregate Spreader
• Cement Concrete mixer
• Bituminous Pavers
• Cement Concrete Pavers
- . -~-···········~9..
··~!f
1350 mm - - - - - - - - - -
e. Lifting Equipment
f. Transporting equipment
..
•
•
Dumping trucks (tipper)
Trucks (flatbody)
Mini dumper
3. Phmt
• Cement concrete plant
• Asphalt concrete plant
• Aggregate crushing plant
.Dozer: Dozer is high powered tractor having a blade fixed at end. Blade is curved in vertical section and
provided with a sharp cutting edge at the bottom. The blade is slightly longer than the width of the tractor. There
are three types of dozer:
i) Bull dozer- used for pushing earth in forward direction only
ii) · Angle dozer- a blade can be set obliquely to the direction of movement (up to 30°). This is .used to
push material sideways.
iii) Tree dozer- a special type of blade, useful for felling trees and uprooting the stumps.
Scraper: Scraper is a machine generally towed by tractor and is used for scraping, carrying and spreading of the
earth on the site. It consists of a cutting edge for scraping and bucket for loading. The cutting edge excavates
earth and the excavated earth is colle~ted in bucket by itself.
Loader: A bucket is attached to arms, capable of being raised, lowered and dumped through mechanical control.
It is used in land filling, road Maintenance etc.
E~cavator (Back Hoe): Hoe is excavating equipment of the power shovel family. Hoe is meant to excavate
below the natural surface where machine is situated. It can control depth of excavation. Hoe can exert high tooth
pressure and hence can excavate stiff material. .....
Drag line: Drag line is used to excavate soft earth and to deposite in nearby banks. It can operate on natural
ground. The bucket is thrown out from the dragline on the top of the earth to be excavated and then pulled back
toward~ the base of the machine.
Clam shell: Clam shell consists of special types of bucket of two halves. The two halves remain hinged together
at top. The open clam shell bucket is thrown on the top of the loose material to be dug. As the bucket is lifted,
the two half closes entrapping the material into bucket. It is used for soft to medium and loose materials.
Trench Digger: It is used for excavating trenches for laying pipelines, sewer, cables etc. Operation is quick
giving the required depth or width. It may be wheel type or ladder type.
Aggregate Spreader: The aggregate spreader, sometimes called the "spreader box" is used to distribute
aggregate evenly over the film of asphalt sprayed by the asphalt distributor. The specifications require aggregate
spreaders to be self-propelled and have a continuous feed feature. The spreader must distribute cover aggregate
at a uniform rate over the entire width and length of the area being sealed. Not only must it be uniformly spread,
it must also be the correct quantity of aggregate.
Cement Concrete Mixer: A concrete mixer is a device that homogeneously combines cement, aggregate such
as sand or gravel, and water to form concrete. A typical concrete mixer uses a revolving drum to mix the
components. For smaller volume works portable concrete mixers are often used so that the concrete can be made
at the construction site, giving the workers ample time to use the concrete before it hardens.
Cement Concrete Pavers: Cement concrete pavers are self-propelled machines to place cement concrete mix on
the roadway to a specific depth and to provide initial compaction of the mat. Thickness of mat is controlled by
pavers speed, material feed rate.
Pulley: A pulley is a set ofwheels and rope that allows you to move heavy objects with minimal effort.
Crane: A crane is a type of machine, generally equipped with a hoist, wire ropes or chains, and sheaves, that
can be used both to lift and lower materials and to move them horizontally. It is mainly used for lifting heavy
things and transporting them to other places. Cranes may be stationary, mobile, overhead gantry, tower
Hoist: Hoist is commonly used on large scale construction projects, such as high-rise buildings or major
hospitals. The purpose is being to carry personnel, materials, and equipment quickly between the ground and
higher floors, or between floors in the middle of a structure.
2. F. Transporting Equipments
The equipment used for transportation of material are known as Transporting (hauling) equipment or simply
haulers.
,Haul Trucks: Haul trucks are used for. transporting HMA and aggregates from the place of production to the
construction site. Haul trucks are loaded at the production plant. Before loading of truck, trucks are to be cleaned
from foreign material and lubricated to prevent sticking of HMA on truck beds.
Tipper: A truck or lorry the rear platform of whieh can be raised at the front end to enable the load to be
discharged by gravity also called tip truck.
2. B. Compaction equipment
Smooth wheeled roller: These rollers have smooth wheels especially of steels. It may be hand, animal or power
driven. Hand or animal driven may have only one drum which is 90 em is dia and 1.2 m to 1.5 m in length.
Power driven roller may have two axles or three axles. Two axles may have three wheels (two on back and one
on front axle) or two wheels (one on each axle). Smooth wheeled rollers are suitable for compacting gravel,
sand, crushed rock, where crushing action is required.
Vibrating roller: Steel wheel rollers can be equipped with vibratory drums. Drum vibration adds a dynamic
load to the .static roller weight to create a greater total compaction effort .. Vibrating roller used to compact
pavement layers and sub grade to a high degree of density. This roller vibrates while traveling. These rollers
achieve high compaction with a few passes.
Pneumatic tyred rollers: The pneumatic tire roller is a self-propelled compaction device that uses pneumatic
tires to compact the underlying layers. Pneumatic tire rollers employ a set of smooth tires on each axle; typically
four on one axle and five on the other. The tires on the front axle are aligned with the gaps between tires on the
rear axle to give complete anduniform compaction coverage over the width of the roller.
Sheep foot rollers: Sheep foot rollers consist of hollow circular drum of steel 1.2- 1.5 m long and 0.9- 1.2 m
in diameter with projecting legs on circumferential area at the rate of 12- 18 per m2• The temping feet are.
staggered in rows. As the roller is pulled over the layer ofthe soil to be compacted, the projections penetrate into
the layer and perform compaction of soil.
Rammers: Rammers are useful for compacting relatively small area and where rollers can't operate such as
compaction of trenches foundation and slopes. The output is slow then roller.
Concrete Vibrator: For compacting the concrete after its placement concrete vibrator is used. It help volume of
concrete quickly placed, give high density, reduce. air voids. Concrete vibrator may be surface vibrator, table
vibrator, needle vibrator etc.
2. C. Leveling Equipment
Grader: It is self propelled machine which has its blade within the wheel base. The blade is 3.5 m long but
effective length during spreading is 2.75 m. Blade supported on machine frame work and capable of turning,
tilting. The graders are useful for spreading heaped earth ihto layers, shaping the cross section, maintain cross
sections and gravel surfaces.
2. D. Paving Equipments
-
Bitumen Spreader (Distributor): The distributor is used to spray the asphalt over the base before placement of
HMA or Premix. An asphalt distributor is a truck mounted or trailer mounted asphalt tank with pumps, spray
bars and appropriate controls for regulating the rate at which asphalt leaves the spray barnozzles. The distributor
provided with heating system to maintain proper· application temperature. The spray bar is adjusted
perpendicular to the road surface. A hand held spray attachment is for the applying asphalt to areas inaccessible
to the spray bars.
Bituminous Pavers: Pavers are self-propelled machines designed to place hot mix asphalt concrete or premix
carpet on the roadway to a specific depth and to provide initial compaction of the mat. The tractor unit provides
moving power for the pavers. Thickness of mat is controlled by pavers speed, material feed rate .In order to
achieve the most consistent thickness and smoothest possible surface, and pavers attempt to maintain a constant
speed, and use automatic feed controls. Special concrete transport trucks (in-transit mixers) are made to
transport and mix concrete up to the construction site. They can be charged with dry materials and water, with
the mixing occurring during transport.
Mini Dumper: they are high speed pneumatic wheeled trucks of short chasis and strong bodies. Loading,
hauling and dumping are done very fast as compared to other equipment. They are suitable for short houls on
rough roads.
I
Concrete Transport Truck: Concrete transport trucks are made to transport and mix concrete up to the
construction site. They can be charged with dry materials and water, with the. mixing occurring during transport.
4. Plant
Stone Crusher: A crusher is a machine designed to reduce large rocks into smaller rocks, gravel, or rock dust.
Crushers may be used to reduce the size, or change the form, of waste materials so they can be more easily
disposed of or recycled, or to reduce the size of a solid mix of raw materials (as in rock ore), so that pieces of
different composition can be differentiate.
Asphalt Mixing Plant: Asphalt plants are used to prepare asphalt. It may be hot mix plant or cold mix plant.
Aggregate & bitumen are heated and then mixed in a unit is known Hot mix Plant. Cold mixing involves mixing
of cold or sun warmed aggregate, with hot or cold application of bitumen. Function of asphalt mixing plant
includes heating and drying aggregate, screening & measuring aggregate, the filler and bitumen and mixing the
aggregate & bitumen in proportion to produce homogenous mix.
Cement concrete plant: Cement concret mixing plant mixes different ingredients (coarse aggregate, fine
aggregate, admixture, cement and water) in required proportion. It consists of storage bins for storing materials
like cement and admixtures. Aggregate is mix in it with the help of a hopper which is fixed in plant.
::
CHAPTER 7 ROPEWAY
7.1. Definition
A ropeway is a mode of transport in which special types of carriers are suspended from, or. simply
atta.ched to, an overhead rope to facilitate the transfer of materials, goods or passengers, from one
point to another. The rope runs the entire length over which the ropeway operates, which typically
ranges from a few hundred meters to several kilometers. ·
b) Mono-cable systems: A mono-cable system uses a single rope, which serves the dual purpose of
carrying and hauling carriers. Carriages are attached to the rope by grips and move when the rope
moves.
Tower
•
Drum-type bk:able system
b) Circulating System
a
In circulating system, the hauling rope runs continuously in one direction and passes around the
sheaves at the ends. The cars move from one side of the rope to the other as the rope moves from one
station to the other and back.
• (o)
Looped hauling cable
7.2.4. According to
Vehicle type
a) Open-air ropeways
(chair lifts): chairs or
benches with up to four
seats, each suspended
on a steel rope driven
in a loop.
b) Open cabins with roof and railing and meant for 1 to 6passengers
c) Semi enclosed cabins with roof, railing and sides not fully covered and meant for 1 to 6
passengers
d) Closed cabins or gondolas are fully closed cabin with glass or transparent windows with a
capacity of 1 to 6 passengers
7.3.1. Rope
The rope or cable of a ropeway bears the suspended· load an~ hauls it along. A rope is made up of
several strands of steel wires spun together. In a rope the core may be a strand (a wire-strand core) a
second smaller rope (an independent wire-rope· core), or a fibre core. Rope with a fibre-core is
generally used as a hauling cable.
Types of Ropes according to the way in which the wir~s and strands· are laid
a) Equal Lay: In an 'equal lay' rope, all the- wires in a strand are wound with the same helix angle.
The wires of different layers be of different sizes and that the smaller wires be closer to the core.
b) Cross lay: In a 'cross- lay' rope the wires in all layers are the same size and a different helix
angle or length of lay must be used for each layer.
7.3.3. Towers
Towers or trestles are supporting structures. Depending upon the type ofropeway and its use, they are
made of wood, steel, or concrete~ Towers are provided with a saddle and rollers. Rollers are small
wheels used to support the hauling rope in a hi-cable system or the main rope in a mono-cable system.
Rollers are generally grouped into a battery;A saddle or shoe is used to support the track rope on the
7.3.4. Stations
Minimum two stations are necessary for a
ropeway system as one is situated at the starting
-point and one at the end of it.
Types of Stations
• Tension stations: Tension stations placed
at appropriate points along a ropeway line
are used to limit the length and maintain
the tension of the track cable.
• Drive station: A drive station contains
the drive system of a ropeway, which includes a motor drive mechanism and a driving sheave.
• Return station: This station at the end of the line contains a return sheave, from which
carriers move back towards the drive station.
• Divide stations: These intermediate stations are used in long ropeways to limit the length and
tension of the rope. They divide a ropeway into smaller segments, each of which functions as
a separate ropeway.
7.3.5. Sheaves
Sheaves are wheels of large diameter found at both ends of the line and in the stations. The hauling
rope passes around them. A driving sheave is powered either by an engine or an electric motor
connected to the sheave with a suitable drive mechanism. At the other end of the line there is a return
sheave which is not powered but is free to rotate.
7.4.1. Profile
The profile of the aerial ropeway (longitudinal side elevation) shall be, as far as practicable, parallel to
the terrain over which it passes. The maximum gradient of the rope shall not exceed 1.0 (45°) except
in the case of aerial ropeway of fixed grip type. The transport path shall be straight between
successive stations
7.4.5. Ropes -
The ratio of minimum breaking load of rope and the maximum rope tension in service shall not be
less than the following values:
• Carrying rope(bicable)- 3.0
• Hauling rope for both rnonocable and bicable - 4.5
• Tension rope for bicable and rnonocable -5.0
• Signalling and telephonic cables- 3.3
7.4.6. Vehicles
a) Maxi~um Speed
In no case shall the maximum speed exceed the values given below:
·1) System with closed gondolas having locked doors- 6rn/s
2) Chairlift and system with open gondolas with adequate protection- 5 rn/s
3) Others - 3rn/s
b) Capacity of Vehicles
The calculation of the various components shall be done, taking into account the weight of 80 kg per
passenger. The vehicles may be following types:
• chairs with one seat or more seats for passengers not exceeding four,
• open cabins with roof and railing and meant for 1 to 6passengers
• semi enclosed cabins with roof, railing and sides not fully covered, and meant for 1 - 6
• passengers, and closed cabins with small windows with a capacity of 1 to 6 passengers
c) Spacing or carriages
The minimum distance between two successive carriages shall not be less than 1.5 times the stopping
distance under the most unfavorable load conditions.
7.4.8. Crossings
• The crossing of routes, railways, waterways or other ropeways shall be avoided as far as
possible.
• When it is not possible, the clearances shall be determined and shall have protective structures
• The crossings and paralleling with railways, highways, ropeways or overhead electrical lines
shall be so done that no mutual discomfort results either in course of normal operation or
rescue operation or during installation operations.
References: [Ropeways in Nepal (Nepal Water Conservation Foundation (NWCF}, 2004); IS 5229
-1998; IS 9706-1997; and other internet resources]
Chapter 8 Bio-Engineering
8.2. Bio-engineering
Bioengineering techniques have proven to be very successful, cost effective, environmentally friendly
and sustainable in solving a range of slope instability problems, from simple to complex landslides in
Nepal. The Bio-engineering technique is an integrated engineering technique for slope stabilization.
Bio-engineering technique means is the use of living vegetation or vegetation parts, either alone
or in conjunction with civil engineering structures and non living plant materials, to reduce
shallow-seated instability and erosion on slopes. Other terms that have been used to describe this
process include: vegetation structures, bio-technical engineering, vegetative soil conservation, and
engineering biology. . ·
.I
the air through transpiration
staking, brush layers, live palisades, live contour line, fascines etc. These live materials
develop roots and sprouts foliage. The resulting vegetation becomes a major structural
component and the structure grows stronger with time.
c) Bio-Technical Techniques use living materials which are combined or integrated with
structural materials. E.g. Live crib walls, vegetated gabions etc. The structural elements provide
immediate resistance to sliding, erosion, and wash out. As vegetation becomes established, roots
invade and spread through the slope. Over time, the structural elements undergo to a progressive
loss of strength where as the vegetation increases in strength and functionality.
88 .
- n·1o-engmeerm2 T ech.
-
. t e t o N epa an d th e1r
mques A.ppro{)_na . Strue t uraI C on t ri"b u f Ion
1. Planted grass lines :
• The planting of grass slips and cuttings is intended to create a strengthened slope
surface resistant to erosion.
• These techniques most commonly used in conjunction with standard mesh jute netting
2. Grass seeding: Grass is sown direct on to the site. It allows easy vegetation coverage of
large areas This techni ue is often used in con'unction with mulching and jute netting
3. Turfing: Turf, consisting of a shallow rooting grass and the soil it is growing in, is placed
on the slope. This technique Is commonly used on gentle embankment slopes. Its only
function Is armouring.
4. Shrub and tree lanting Shrubs or trees are planted at regular intervals on the slope.
As they grow, they create a dense network of roots in the soil.
The main engineering functions are to reinforce and, later, to
anchor the slope. In the long term, large trees can also be
used for slope support.
"'" ~· ,............,
««>»>.~··A'\
Shrub (or tree) seeds are applied directly to the site. This
technique alloJVS very .steep, rocky and unstable slopes to be
revegetated where cuttings and seedlings cannot be planted.
There are two methods: (1) direct sowing end (2)
broadcasting. In the first method, seeds are placed
individually, whereas the second Involves scattering the seed
"'·~ ~,., .... ... ,..
~
««>•>l.Y·x:>
all over the site. The main engint(ering functions are to
reinforce and, later, to anchor the slo e.
6. Large bamboo planting
Two methods: (i) traditional planting method or (ii) planting rooted culm cuttings
• Reinforce and support slopes, but do not have an anchoring function;
• can add weight (surcharge) high up on the slope.
7. Brush Layering • Woody (or hardwood) cuttings are laid
3-r, following the contour
/ / .· • a strong barrier, preventing the development
/~,:<- · of rills
,~·/" .
•
10. Fascines . ·~,
Bundle of Hardwood
- g!.!!!Jlg§.~\1~§~\.K\n Nos:
X-Section Plan
• The word "fascine" means a bundle of sticks (Also called live contour wattling)
• bundles of live branches are laid in shallow trenches and buried
• - They put out roots and shoots, forming a strong line of vegetation.
• The main engineering functions are to catch deb,ris, and to armour and reinforce the slope.
11. Vegetated stone pitching • Slopes are strengthened by a combination of
dry stone walling or cobbling, and vegetation
planted in thegaps between the stones.·
• There are two distinct uses: (1) reinforced toe
walls; and (2) protected gully beds. T
• A very strong form of armouring.
C) Organizational Principle
6) Performance-based Work Management
Rather than paying workers at a fixed daily rate, they are paid on the basis of the amount of work they
accomplish. This provides a major incentive to work more so that they earn more. Small contract work
assignments are used only complex structural works that require external construction material,
equipment and professional skill.
F) Economic Principle
10) Low cost, high benefit
A high Benefit to Cost Ratio through improved road access to a large beneficiary population is achieved
with Green roads by accepting a simpler design standard. While other conventionally constructed mid-
hills rural roads cost considerably more, Green roads cost less.
a) Minimize slope cutting: Green road avoids the conventional road construction practice of
developing the road width by full cutting and throwing the excavated material. Slope. cutting is as
small as possible and box cutting is avoided as much as possible. Therefore cut slope are much more
stable.
b) Mass balancing concept: The mass balancing concept is used in the green road approach. The
excavated materials are used for fill on the valley side by constructing toe wall. Excavated stone
blocks are stockpiled and re-used for constructing stone structures such as dry stone walls in the later
phase.
c) Environment Friendly Construction methods: Green road is constructed in phases with the
objective of conserving the fragile mountain slope by minimizing the risk of landslide and soil
erosion. The phase wise construction help in assessing the local natural resources for utilization in
construction phase. Rock blasting is not allowed in Green road approach. Instead a simple method
like Chiseling and Hammering, Heating and Breaking and Drilling is done to cut the rocks. Heavy
) equipments which consumes extensive amount of the fuels are no used.
d) Proper water management: Green road approach adopts dispersed water management to avoid
concentration of water along the road surface. Natural slope is used to disperse water towards the
valley in a controlled manner. The road surface i~ generally provided with a 5% outward slope so
that the surface runoff flows out of the road surface downhill.
e) Environment appraisal: Environmental Impact Assessment (EIA) study is done to assess the
likely impact on the environment and to offer ~commendations. The EIA includes documentation
of environmental baseline information of the project influence area, analysis of positive and
negative impacts, recommendation of appropriate preventive and curative measures and
environmental and social management plan .
t) Bi<iengineering: Green road approach incorporates bioengineering as one of the important tools of
environment conservation and slope stabilization. Suitable plants are collected and assessed for the
bioengineering purpose. The local communities and farmers and landowners in the road corridors are
trained for the use of the bioengineering.
new roads, driving vehicles, and working in automobile workshops etc. These activates will help in
reducing poverty.
b) Local level capacity building: Various levels of training for skill development are provided
during the construction process and trained local people become a source of local manpower for
neighboring road projects, and for later maintenance, rehabilitation, and upgrading works. Self help
group such as saving and credit groups are formed for off farm income generating activities. These
groups are able to upgrade themselves for sustainable livelihood even after the withdrawal of the
project support.
c) Social equality and gender balance: The green road approach emphasizes on the good
participation of the indigenous, low caste and disadvantage group. Likewise Green road concept
promote the women participation in all areas. The project provides the equal opportunities for men
and women and integrates women into the decision making process.
iv.) Slope stabilization (Simple retaining structure such as dry stone wall, gabion wall etc. and
Bioengineering)
v.) Poverty alleviation and capacity building programs
Locally available instrument and equipment are during the construction. E.g. spade, pick, shovel, sickle
etc. Rock cutting is also done with the local technologies as far as possible.
A. Phased Construction
Phased construction is one of the approaches to build the road in different phases. Unlike National
highways where the tracks are constructed to full width at the first, this sort of phased construction helps
the local people and technicians to know the geology of the place better and can also forecast the
necessary preparations to be made in the future regarding construction of structures, changing the
alignment, number of labor gang required, financial resources, etc.
The main objectives of the phased construction can be pointed out as follows:
• Conserve the fragile mountain slope by minimizing the risk of landslides and soil erosion
• Build a consensus on the selected road alignment among local people relevant stakeholders by
having interaction
• Identify critical sections and make necessary adjustment if required.
• Assess the natural resources available (e.g. soil, stones, plants, etc) for construction works.
The 4 phases of a new Rural road are as follows:
• Phase I: a trail along the future road alignment
• Phase II: a track created by the gradual widening of the trail
• Phase III: a road including retaining structures, water management structures and bio-engineering
• Phase IV: road surface compaction and construction of road surface draining system including
bio-engineering
Phase II: Gradual Widening of Trial to a Tractr! In this phase Ffg : Phali>~ 1 - Op.eni11g: Of A Tr;all
the 1.25m trails are widened to 2.5m tracks along the finally fixed alignment. During fair weather
condition, the tracks can be used by agricultural equipment. The approximate work input of this phase is
about 25%.
Phase III: Road construction: After the natural compaction of the track over the period of one monsoon,
Phase 3 is implemented. In this phase the tracks are widened to 4.5m width to bring the track to the
w,, .. :2J!Om=;l;;~
~lltlll¥!2i\Q~)
required rural road standards. This phase has the highest work input of about 40%, since the construction
of retaining structures and water management structures are implemented in this phase. Bio-:-engineering
tool is also applied in this phase as a preventive measure.
B. Staged Construction
The staged construction in rural road means to construct the final road i.e. a double layer bituminous road.
As the fund is available, the 4.5m seasonal road is upgraded with improvement over the road and the
structure to an all-weather road. The further construction will be carried out with the rural road principles.
The decision to upgrade the fair- weather earthen road will base on the factors like:
• Consensuses reached among local people and ail relevant stakeholders
• Relevant studies justifying the need of upgrading
• The traffic volume increases and the existing rural roads are not possible to accommodate the
increase traffic volume
• The resources needed for construction and maintenance are available and sufficient.
If the aforementioned criteria are fulfilled, then the following stages of construction are carried out which
is more or less close to DaR's concept of Staged construction.
Stage 1: Fair-weather Earthen Road: A low-cost, low volume, fair weather and single-lane earthen
rural road with necessary by passes.
Stage II: Gravel road: A road which can pass higher volume of traffic, with improved geometries. The
road is graveled, cross-sections are improved by widening and the retaining and water management
structures are also improved and updated.
Stage III: all weather Bituminous Road: The road is finally brought to all weather road with
bituminous surface with further improved curves, culverts and bridges and better provisions of retaining
and water management structures.
C. Sectorial construction
When the length of rural road is long, it may take a long time for the construction work to finish and the
vehicles to ply on it. This problem can be solved by sectorial construction. After finalizing the road
alignment, the road is divided into sectors of about 10 km. Each sector consists of sufficient labor gangs,
technicians, and supervisors for execution of work. A separate technical team is formed in each sector,
which is responsible for group formation, organization and management of works, supervision,
monitoring and training works. Construction works are carried out simultaneously in all sectors, thus
speeding up the work. For the sectorial construction to be carried out; the following factors to be fulfilled:
• Enough funds should be available for construction and disbursement of these funds should be
timely
• Sufficient labor groups should be available and they should be properly mobilized
• There should be enough technical team, so that there is no interruption in work at any point
• Imported materials like gabion, wires, etc should be available in the site before hand for
uninterrupted work
• Well experienced team providing engineering and social services should be available.
v) Construction material
Locally available natural resources are used. The re-utilization of material obtained froin the excavation is
strongly recommended. Excavated soil, rocks and top soil and vegetation are the primary construction
materials for green road, as:
• Excavated material can be utilized for back filling and widening the roads
• Stone can be used for construction of dry stone masonry walls and gabion walls, and water
management structures.
• Gravel can be used for spot surface improvement of critical (steep, moist) road sections.
• Vegetation and topsoil can be used for turfing and re-vegetation of the hill slopes.
• Government Agencies:
o Department of Local Infrastructure Development and Agricultural Roads
o Department of Roads """
o DDCs (District Development Committees)
o VDCs (Village Development Committees)
• INGOs
o GIZ (German Agency for International Coopearation) - Rural community and Infrastructure
Works (RCIW) 1996-2007
o HELVETAS
o Swiss Agency for Cooperation and Development - District Road Support Program (DRSP I, II, &
III) 1999-2002
o ICIMOD
o World Bank- Rural Access Improvement & Decentralization Program (RAIDP) 2005-10
o ADB (Asian Development Bank) - Rural Infrastructure Development Program (RIDP) 1995-2005
o DFID (Department for International Development, UK) - Rural Access Program (Phase I & II);
Decentralized Finance and Development Program (DFDP) 2000-2007
o UNCDF (United Nations Capital Development Fund) - Decentralized Finance and Development
Program (DFDP) 2000:..2007
o WFP (World Food Program)- Rural community and Infrastructure Works (RCIW) 1996-2007
• NGOs
o DEPROSC- Nepal (Development Project Service Center)- Mule Trial in Jajarkot
o RRN (Rural Reconstruction Nepal)
Table: Tools Used in Green Road Construction
Approx. Approx. Amount Approx. Amount
s. Name of tools in English/Nepali Weight per required per labor required per Site (in
No.
Piece (in kg) group (in no.) no.)
1 Aluminum water vessel20 litre (Gagro) 2.75 1 25
2 Axe (Bancharo) local made 2.50 1 25
3 Bamboo wicker baskets (Doko I Thunse with 2.0 18 450
4 Chisel (ChinnolRino pin 2.00 4 100
5 Crowbar (medium) 1 1/8" dia 4.50 1 25
6 Crowbar (large Gal) 11.00 1 25
7 Crowbar (small Gal) 1"dia 7.20 1 25
8 Crowbars (extra 118") for chisel 9.50 2 50
9 First Aid kit box with medicines and 3.00 - 5 boxes
10 Frog and Feathers 0.50 3 75
11 Hammer (Ghan) large (10 lb) 4.50 1 25
12 Hammer (Ghan) small (5 Ib) 2.27 1 25
13 Hammer (Ghan) medium (2 lb) 1.00 2 50
14 Large tarpolene sheet (Tripal) 2 - 20
15 Mason's hammer (Mairi) 1.00 4 100
16 Mason's nylon thread (3 mm dia.) 1 2 50
17 Nylon rope in coils of 40m (6mm dia.) 1.50 2 50
18 Pan (Karai) 1.70 2 50
19 Pick (Gainti Tala) 2.50 6 150
20 Pipe level (3" dia. polvthene pipe 10m lonq) 0.25 - 10
21 Plastic Muo 0.10 2 50
22 Pliers for gabion crates (Penchisl 0.8 - 5
23 Plumb bob (Ghanti) 0.25 2 50
-~
24 Shovei (steei handie indian kiwi) 2.40 6 150
25 Sickle (Ansu or Hansiya locally made) 1.50 1 25
26 Spade (prefer local made Kuto or Kodalo) 1.75 6 ISO
27 Spirit Level (Pani Level) 0.2 . - 10
28 Tape (Phitta) 30m 0.75 - 10
29 Tape (Phitta) 5 m 0.15 - 15
30 Terai Spade (Faruwa) 2.00 2 50
31 Trowel (Jyawal) 0.3 - 10
32 Wheelbarrow (Thela Gadi) pneumatic 25.00 2 50
33 Spares for wheel barrow 5.00 - -
Equipments
34 Calculator 0.5 - 5
35 Computer, printer and 10 - 1
36 Drilling Machine with accessories ·25 - 1
Chapter 10
Agencies for Rural Road Development in Nepal
1. Overview of Agencies
DoR: Department of Road (DoR) under take task of road development to link various geographical
regions and economic zones with surface transport, waterways, railways and ropeways. DoR may
provide heavy equipments for the construction and other technical assistance to local authorities for
road development.
DDCs and VDCs: These are local authorities responsible for planning, designing, construction and
maintenance of rural roads. Rural road development is carried out through user committee. User
committee is elected through the VDC connected by rural road and also from villages from which
labors are supplied. DDC chairman is chairman for the user committee. DoR may provide heavy
equipments for the construction and other technical assistance.
National Transport Policy has been introduced to provide transport facility in the remote and
backward region as soon as possible from the minimum source, make the existing transport
infrastructure organized and reliable and develop the transport system of international standard of
foreign countries.
2.1. Objective:
To develop a reliable, cost effective, safe facility oriented and sustainable transport system that
promotes and sustains the economic, social, cultural and tourism development ofNepal as a whole.
2.2. Strategies:
For the attainment of the above through and objecU,ves the following strategies will be followed:
(i) Take responsibility of transport structure to be constructed from the central level.
(ii) Strong decentralized governance system,
(iii) The development and promotion of transport system from the local level itself.
(iv) Maximum private Sector involvement
2.3. Policy:
The following policies shall be followed in order to attain the above mentioned objectives:
• The construction and development of transport infrastructure in central and local level as per
the short term, medium term and long term master plan of the transport infrastructure
• The central level government plays role as supporter of the local level government for
development of transport infrastructure
• High priority shall be given to completing the construction of roads connecting all
75 District Headquarters of the Country to the main road network.
• Development of the East-West Mid-Hills Highway by constructing artd improving the
component Feeder and District Roads
• Roads shall be constructed, to connect the northern border
• The maintenance and repair of the existing· transport infrastructure to ensure appropriate
service levels
• The local level transport infrastructure shall be constructed and maintained from the local
level itself.
• Priority shall be given to maintain 'and upgrade of transport infrastructure of the central
level on the basis of traffic density and economic consideration.
• The construction, improvement and management of the means of transport shall be done in
harmony with the traffic safety and environmental effect.
• The skill and working capacity of the concerned labour force shall be enhanced.
• The expansion of the solar and electricity powered throughout the country
• Cross border, regional and sub-regional transport and transit facilities shall be further
developed and expanded.
• Improving public transport service and to reducing harmful emissions arising from public
transport operations.
• Promote Private sector involvement in the development and expansion of service of the
transport infrastructure.
• The provide a minimum level of transport inf~astructure in the remote areas
• Foreign loans will not be utilized unless its positive economic feasibility
• To develop various mean of transportation and infrastructure in a coordinated manner.
• Private sectors shall be encouraged to construct and operate rope ways in the areas where
construction of road is dangerous in environmental and geographical view or where operating
road transport is comparatively costly.
• The construction and maintenance of main trails and tracks shall be undertaken by local
institutions with the maximum utilization of local skills, labour and materials through public
participation.
Nepal has adopted a planned approach to development of the country. Planned endeavor of
development was initiated with the inception of the First Five Year Plan in 1956. The Ninth Plan is
under implementation. The Ninth Plan has initiated a long term concept for development in the
country. The plan targeted to achieve sustainable growth by fully utilizing and investing available
resources in infrastructure and social sectors. It is targeted to a:freve 6 percent per annum growth
rate in the Ninth Plan, on average of 7.2 percent during the 20 year period.
-
• Substantial reduction in Road accident b): adopting enhanced safety