EARTH WORKS
PROCEDURES
REVISION HISTORY
Pa ge |1
KAK KHONAINI & PARTNER CONTRACTING COMPANY LTD. (KAK)
Pa ge |2
KAK KHONAINI & PARTNER CONTRACTING COMPANY LTD. (KAK)
1. SCOPE
The work covered by this work procedure covers excavation, compaction and
backfilling of soil for structure RCC foundations, trenches and security fence.
2. WORK EXTENT
3. REFERENCES
ASTM D 1556 – Standard Test Method for Density and Unit Weight of Soil in Place
by Sand-Cone Method
ASTM D 2922 – Standard Test Methods for Density of Soil and Soil-Aggregate in
Place by Nuclear Methods (Shallow Depth)
ASTM D 2167 – Standard Test Method for Density and Unit Weight of Soil in Place
by the Rubber Balloon Method
ASTM D 2937 – Standard Test Method for Density of Soil in Place by the Drive-
Cylinder Method
4. WORK EQUIPMENTS
4.1 Shovels
4.2 Crowbars/Picks
4.3 Wheel Barrow
4.4 Roller/Plate Compactor
5. WORK MATERIALS
Pa ge |3
KAK KHONAINI & PARTNER CONTRACTING COMPANY LTD. (KAK)
6. WORK PROCEDURE
6.1.1 Permit shall be obtained from the relevant authority and CLIENT prior
commencement of excavation works. Documents shall be kept at site at all
times in the event of verification by any authorized personnel from the
authority.
6.1.2 Surveyor shall mount the monuments for establishing the bench mark and all
survey reference prior to excavation work to start.
6.1.3 Prepare and display of warning sign boards on the area to be excavated.
Proper barricade with blinker light shall be place during the night activities.
All workers shall be worn a visible reflector safety vest with complete PPE
required on the job site.
6.1.4 Where necessary, the surfaces of cut areas shall be sloped to prevent erosion
and the contractor shall provide shoring once the depth of excavation exceeds
one meter.
6.1.5 Access of equipment shall be clear from obstruction, abandoned concrete
structures, trees and other parking equipment, etc. Ensure that the movement
and swing of the equipment are free from workers to prevent any accident that
might happen.
6.1.6 Commencement of excavation shall start upon ensuring all safety
requirements have been displayed and permit to excavate must be approved
by the CLIENT representative before start excavation.
6.1.7 All underground facilities shall be identified; precaution and protection shall
be taken into consideration. In this regard, slit trenches shall be prepared by
hand excavation in specific locations to identify and locate existing services.
A separate method statement for slit trenches should be prepared and
approved.
6.1.8 Surveyor has to determine the actual reduce level, elevations, actual
coordinates base from the IFC drawing required. Site engineer has to ensure
and compile all the survey report witnessed by CLIENT representative for
future references.
6.1.9 Excavated areas shall be barricaded with suitable warning signs.
6.1.10 Excavated soil shall be safely removed from site and dumped at temporary
dumping area approved by CLIENT. Dumping place shall be accessible to all
dump truck for proper storage of dumping materials.
Pa ge |4
KAK KHONAINI & PARTNER CONTRACTING COMPANY LTD. (KAK)
6.2 BACKFILLING
Pa ge |5
KAK KHONAINI & PARTNER CONTRACTING COMPANY LTD. (KAK)
6.2.4.7 All observed soft spots or loose zones shall be compacted in place or
excavated to firm soil and replaced with properly compacted fill.
6.2.4.8 In-place density and moisture content of soils shall be determined by
the sand cone method per ASTM D 1556, nuclear method per ASTM
D 2922, the rubber balloon method per ASTM D 2167, or drive
cylinder method as per ASTM D 2937. Acceptance testing of in-place
density and moisture content (file density testing) on compacted fill
will be performed at the following rates;
6.2.5 Each layer of fill material shall be compacted mechanically to the required
density before filling with successive layers until the completion of fill to the
required grade or level is achieved as per IFC drawing.
6.3.1 Compaction of fill or backfill shall be used tired roller and vibratory roller
compactor or plate load compactor or any equipment suitable to the site
conditions for achieving the required compaction specification requirements.
6.3.2 After completion of compaction works, tests shall be conducted to determine
the desired density of consolidation as required in the project specifications.
All compaction tests carried out shall be inspected, checked and certified by an
approved third party testing agency.
6.3.3 All compaction test reports shall be kept and preserved as project records for
future references. All compaction tests and its due course during the progress
of work shall be properly planned in advance and programmed with third party
testing agency according to project requirements.