Indent Flow chart for Indent ≤ 200 Crore R2-Date: 24 Dec 2021
Confirm item and quantity 1. Generate GeMAR&PTS report (coordinate with Stores Officer and his office)
availability from IRPU for This should be counter signed by I/o and Indent approving authority and
condition of ‘ASO-RRCAT’ as Proceed for Custom Bidding in GeM ONLY
consignee and delivery at
Indore (M.P.)
Some selected items by I/O’s Exemption for processing through GTE IRPU will process it with local tender. No
are not available for place of GTE will be issued. As per Public
delivery at Indore region. 1. Spares and consumables of procurement Policy- Preference to
equipment on nomination basis Make in India (PPP-MII) GFR 2017-
supported with Proprietary Article Amendment to Rule 161(iv) dated
“Custom Bidding”
Before sending to DAE for GTE approval : If no offer is qualified as local supplier,
1. Publication of 3/5 year “Procurement Plan” the proposal can be put for approval of
For multiple items in large quantity, on the RRCAT Website. Secretary DAE for GTE by HoDIS through
it is recommended to go for “Bill of 2. Correspondence with DPIIT Group Director and Director, RRCAT.
Quantity” (BOQ) bidding in GeM. Shri Akhilesh Kumar, Director DPIIT (Format available on Infonet under
Ph 23062343, Mo. 9432015776 Forms-> Purchase”)
Email : <akhilesh.kumar1965@gov.in>.
3. Certification as per para 3 of OM No.
F.20/45/2020-PPD dated 8 January, 2021.