DEFINE / INITIATION

Objective/Goal:

Cycle time/Lead time of Plant to be reduced from 24


days to NMT 15 days by Feb

Scope:

All commercial product-From Dispensing of product till


final release of the product. Trial batches are excluded.

Expected outcome/result:

 Reduce cycle time and waiting time


 Faster release of products
 Reduced cost of inventory
Project Team:

Production Head: Jeff D’souza


SME: Mac Cafe
Project Lead: Peter England

Time Line:
Stage START DATE END DATE
DEFINE/Initiation Month-1 Month-2
MEASURE/Planning Month-3 Month-4
ANALYZE/Execution Month-5 Month-7
IMPROVE/Execution Month-8 Month-11
CONTROL/Closure Month-12 Month-14