You are on page 1of 10

Ed Niño Lima

SAQ - SV /ROW-SV

Libertad_bogocity_cebu (Done)

-get list of requirements for occupancy


-submission of forms to OBO
-Bfp inspection
-obo inspection
-released occupancy permit
*requirements
-fire extinguisher
*contacts
-bfp-09171325284
-obo-09179902476
(POSTCON)

Cayang_bogo city_cebu ( Done)

-get list of requirements for occupancy


-submission of forms to OBO
-Bfp inspection
-obo inspection
-released occupancy permit
*requirements
-fire extinguisher
*contacts
-bfp-09171325284
-obo-09179902476
(POSTCON)

Luyang_san remegio_cebu (Done)

-Get brgy. Permit


-secured ALOs
-submission of letter of request to DPWH
-dpwh inspection
-secured dpwh permit
-submit letter of request to the LGU for permit
-secured LGU Permit
*REQUIREMENTS
-BRGY. PERMIT
-ALOS
-dpwh permit
*contacts
-dpwh - 09329776130
(ROW)

Lambusan_san remegio_cebu (Done)

-Get brgy. Permit


-Submission of letter of request to DPWH
-dpwh inspection
-secured dpwh permit
-submission of letter of request to lgu
-secured LGU Permit
*Requirements
-Brgy. Permit
-dpwh permit
*Contacts
-dpwh - 09329776130
(ROW)

Lutopan_Toledo_Cebu (done)

-Get brgy permit


-secured ALOs
-Submission of letter of request to LGU
-secured LGU Permit
*Requirements
-Brgy permit
*contacts
-obo 09532242984
(ROW)

MATAB-ANG_TOLEDO (DONE)

-get brgy permit


-secured ALOs
-submission of letter of request to lgu
-secured LGU Permit
*Requirements
-Brgy permit
*Contacts
Obo-09532242984
(ROW)

Tunkil_talisay (done)

-get brgy permit


-secured ALOs
-get list of requirements for foc permit installation
-submission of requirements to obo
-secured LGU Permit
*Requirements
-electronics forms
-Brgy permit
*Contacts
Obo-09359437912
(ROW)

Cansojong_Talisay (done)

-get brgy permit


-get list of requirements for foc installation permit
-submission of forms to OBO
-secured LGU Permit
*Requirements
-Brgy permit
-electronics forms
*contacts
Obo-09359437912
(ROW)

Tungkol_minglanilla (done)
-get brgy permit
-secured ALOs
-get list of requirements for foc installation permit
-submission of forms to OBO
-secured LGU Permit
*Requirements
-Brgy permit
-electronics forms
*contacts
Obo-09753807368
(ROW)

Cadulawan_minglanilla (done)

-get brgy permit


-secured ALOs
-get list of requirements for foc installation permit
-submission of forms to OBO
-secured LGU Permit
*Requirements
-Brgy. Permit
*Contacts
OBo-09753807368
(ROW)

Banilad_mandaue(done)

-get brgy permit


-submission of letter of request to lgu and to TEAM for traffic clearance
-secured LGU Permit and traffic clearance
*Requirements
-traffic clearance
*Contacts
None
(ROW)

CDU_tipolo_mandue (done)

-get brgy permit


-submission of letter of request to the LGU and TEAM for traffic clearance
-secured LGU Permit and traffic clearance
*Requirements
-traffic clearance
*contacts
None
(ROW)

Buagsong_Lapu-Lapu (ongoing)

-get brgy permit


-ALOs (ongoing)
-Submission of letter of request to lgu
-submission of letter of request to meco
-Awaiting inspection
*Requirements
-NTP
-Brgy permit
*contacts
Obo-09323050719
(ROW)s

IBABAO_LAPU-LAPU (ONGOING)

-get brgy permit


-ALOs - (ongoing)
-submission of letter of request to lgu
-submission letter of request to meco
-Awaiting inspection
*Requirements
-NTP
-Brgy permit
*contacts
Obo-09323050719
(ROW)

Daanlungsod_oslob (ongoing)

-get brgy permit


-secured ALOs
-remaining Alo(ongoing)
-get list of requirements for foc installation permit
*Requirements
-tax Dec for lessors
-Brgy permit
-electronic forms
*Contacts
Obo-09617328030
(ROW)

Baliwagan_balamban(ongoing)
-get brgy permit
-secured ALOs
-get list of requirements for foc installation
*Requirements
-Brgy permit
-electronic forms
*Contacts
None
(ROW)

TALAVERA_TOLEDO (ONGOING)

-get brgy permit


-secured ALOs
-submission of letter of request for LGU permit
*Requirements
-Brgy permit
-ALOs
*Contacts
Obo-09532242984
(ROW)

Bulongan_toledo(ongoing)

-get brgy permit


-secure ALOs (ongoing)
Submission of letter of request for LGU permit
*Requirements
-Brgy permit
-ALOs
*Contacts
-obo- 09532242984
(ROW)

AN-NIESA ASIM

PRE Con (Pasona & Canelar)

Building Permit

*Application Process:

1. Secure building permit application, requirements and checklist

2. Secure locational clearance from the city planning and development coordinator’s office

3. Submit plumbing/sanitary plan and documents to city health office for the evaluation of sanitary
and plumbing permit

4. Secure fire safety evaluation from the bureau of fire protection

5. Submit plans and documents for verification by the receiving section

6. Evaluation and assessment of line and grade, architectural, structural and mechanical

7. Payment at City treasurer’s office

8. Approval of building permit by the building official, recording and releasing

*Requirements:

1. Duly accomplished application forms

-building permit
-electrical permit
-sanitary permit
-mechanical permit

2. If the applicant is the registered lot owner:

-certified true copy of the transfer certificate title (TCT)


-tax declaration
-current real property tax receipt

3. If applicant is not registered lot owner:

-duly notarized copy of the contract of lease or


-duly notarized copy of deed absolute seal or duly notarized copy of sale
-authorization from the lot owner (duly notarized)

4. Minimum of five sets of standard plans and specifications prepared, signed and sealed
-by a duly licensed architect or civil engineer (Architectural or structural plans)
-by a duly licensed sanitary engineer or master plumber (plumbing or sanitary plans)
-by a duly licensed professional electrical engineer (electrical plans)
-by a duly licensed professional mechanical engineer (mechanical plans)
-detailed estimate of the project, signedand sealed by duly licensed architect or engineer

5. Structural analysis amd design computation for two storey and up

6. Boring and load test for three storey and up

7. Fire safety evaluation clearance, from the bureau of fire protection

8. Estimated cost of the project (prepared, signed and sealed by a duly licensed architect or
engineer)

9. Locational clearance from the city planning and development office

10. Certificate of approval from DOLE (safety management program)

Postcon:

1. Mercedes
2. Tumaga01
3. Tumaga02
4. Sinunoc

Occupancy Permit

*Application Process:

1. Submission of form and documentary requirements

2. Receipt of order of payment

3. One time payment

4. Issuance of certificate of Occupancy, FSIC, certificate of final electrical inspection and related
documents and clearances

* Requirements:

a. Forms
1. Application form for certificate of occupancy (to be submitted in 3 copies that are duly notarized)

2. Filled-up application form for tax declaration

b. Documentary requirements:

1. 3 copies of the duly notarized certificate of completion

2. 1 copy of the construction logbook

3. 1 photo copy of the valid licenses of all involved professionals


4. Photograph of the completed structures showing front, sides, and back areas

5. Yellow card issued by electrical service provider (for the issuance of the CFEI)

*Checklist of occupancy permit application requirements:

1. Copy of approved Building application forms


-building permit
-electrical permit
-mechanical permit
-sanitary permit

2. Certificate of completion (Civil, Electrical, sanitary and mechanical)

3. Copy of the approved building plans and specifications

4. Copy of building permit fees and fire fund free

5. Fire safety inspection certificate for residential, commercial, institutional and industrial
buildings.

6. Attached picture of the building

7. SPA and/or Authorization

MARIA REMEDIOS JOVEN

for cagayan sites:


OBO requirements:
*AFI plan signed and sealed
* forms for excavation and electronics signed by professional engineers
*SPA or Authorization
*MOA from Coop or RTA
*pole excavation details
*BOM
sites:carmen02
Bulua 9&10
Consolacion

Macasandig
Brgy.1
Brgy.22 capitol

For Hinaplanon site:same as stated aboved

For Tailaron site same as stated above

cagayan OBO contact no.09354608746


oroquita OBO
09516532869
Michael Angelo V. Medija
SAQ-SV/ROW-SV

Brgy. Tapilon Daanbantayan Cebu(DONE)

-get list of requirements for occupancy permit and row


-submission of forms to OBO
-BFP inspection
-OBO inspection
-DPWH inspection
-released occupancy permit
-released row permit
-released DPWH permit
*requirements
-fire extinguisher
-AFI Plan
*contacts
-OBO- 09171142978
-BFP- 4373788
(Postcon)
(ROW)

Brgy. Poblacion Daanbantayan Cebu(DONE)

-get list of requirements for occupancy permit and row


-submission of forms to OBO
-BFP inspection
-OBO inspection
-released occupancy permit
-released row permit
*requirements
-fire extinguisher
-AFI Plan
*contacts
-OBO- 09171142978
-BFP- 4373788
(Postcon)
(ROW)

Brgy. Mactan Lapulapu City Cebu(DONE)

-get list of requirements for ROW


-submission of forms to OBO
-released row permit
-released NTP
*requirements
-AFI Plan
*contacts
-OBO- 3400656
(ROW)

Brgy. Basak Lapulapu City Cebu(DONE)

-get list of requirements for ROW


-submission of forms to OBO
-released row permit
-released NTP
*requirements
-AFI Plan
*contacts
-OBO- 3400656
(ROW)

Brgy. Babag Lapulapu City Cebu(DONE)

-get list of requirements for ROW


-submission of forms to OBO
-released row permit
-released NTP
*requirements
-AFI Plan
*contacts
-OBO- 3400656
(ROW)

Brgy. Guinsay Danao City(DONE)

-get list of requirements for Occupancy


-submission of forms to OBO
-released occupancy
*requirements
-AFI Plan
-Fire Extinguisher
*contacts
-BFP-09173305646

Brgy. Pagsabungan Mandaue City Cebu(DONE)

-get list of requirements for occupancy


-submission of forms to OBO
-released occupancy permit
*requirements
-AFI Plan
-fire extinguisher
*contacts
-none
(POSTCON)

Brgy. Tunga Moalboal Cebu(DONE)

-get list of requirements for Occupancy


-submission of forms to OBO
-released occupancy permit
*requirements
-AFI Plan
*contacts
-none
(POSTCON)

Brgy. Lamacan Argao Cebu(ONGOING)

-get list of requirements for ROW


-secured Brgy. Clearance
*requirements
-AFI Plan
-LOI
*contacts
-none
(ROW)

Brgy. Poblacion Dalaguete Cebu(ONGOING)

-get list of requirements for ROW


-Brgy. Clearance not secured because Brgy. Captain is waiting for the water pump
*requirements
-AFI Plan
-LOI
*contacts
-Brgy. Captain-09330232307
(ROW)

Brgy. Dunggoan2 Danao City Cebu(DONE)

-get list of requirements for ROW


-submission of forms to OBO
-released row permit
-released NTP
*requirements
-AFI Plan
*contacts
(ROW)

CEBU SAFARI CARMEN Cebu(ONGOING)

-get list of requirements for ROW


-submission of forms to OBO
-released NTP
*requirements
-AFI Plan
*contacts
(ROW)