Professional Documents
Culture Documents
© Wiley 2010 3
An Overview of MRP
© Wiley 2010 4
Input/Output - MRP Process
© Wiley 2010 5
Types of Demand
© Wiley 2010 6
Objectives of MRP
© Wiley 2010 8
MRP Inputs - Authorized MPS
• System checks the inventory record for each BOM item to see if
inventory is available or if a replenishment order is needed to
build the cabinets.
Table 14-3 First Inventory Record for CD Cabinet
Item: CD Cabinet
Lot size rule: L4L
Lead time: 1 week
1 2 3 4 5 6 7 8 9 10 11 12
Gross Requirements: 0 0 0 100 0 0 100 0 0 100 0 0
Scheduled Receipts:
Projected Available: 0 0 0 0 -100
Planned Orders
© Wiley 2010 12
The MRP Explosion Process
Using this table and the product structure tree, we will work
through an example of how the MRP explosion process
calculates the requirements for building a CD cabinet. Next we
start with the cabinet top to show how MRP calculates the gross
requirements for this component.
© Wiley 2010 13
Inventory Records - Components
• It was noted on the previous slide that the parent item (CD Cabinet) has
planned orders in periods 3, 6, and 9.
• Its children (top, bottom, door, left & right side, shelves, and supports) have
gross requirements in periods 3, 6, and 9.
© Wiley 2010 14
Inventory Records - Components
© Wiley 2010 15
Inventory Records– Components con’t
© Wiley 2010 16
Inventory Records– Components con’t
© Wiley 2010 17
Inventory Records – Remaining Components
© Wiley 2010 18
Inv. Records – Remaining Components con’t
© Wiley 2010 19
Inv. Records – Remaining Components con’t
© Wiley 2010 20
MRP Action Notices
• Action Notices:
– Indicate items that need a production planner’s
attention
– Are created when a planned order needs to be
released, due dates need to be adjusted, or when
there is insufficient lead time for normal
replenishment
– Often require planners to rush or expedite orders
© Wiley 2010 21
MRP Action Notices
• Action Bucket:
– Is the current period where we take actions such as
releasing, rescheduling, or canceling orders
– A positive quantity in current period’s planned order
row means that an order must be released
© Wiley 2010 22
Example Comparing Lot Size Rules: Three lot sizing rules used within MRP
Systems are: fixed order quantity (FOQ), lot for lot (L4L), and period order quantity
(POQ). Cost comparison is based on Inventory holding costs ($0.10/period) and
ordering cost ($25/order). In this example POQ is best at $133.50.
© Wiley 2010 23
Rough Cut Capacity Example: The CRP module uses data from MRP. Calculate
workloads for critical work centers based on open shop orders and planned shop
orders. These shop orders are translated into hours of work by work center and
by time period.
Table 14-11 show items scheduled for work Center 101.
© Wiley 2010 25
Resource Planning within OM: How it
all fits together
• Enterprise resource planning provides a common database for use by an
organization, its suppliers, and its customers.
• MRP reports are used by the production and inventory planners to (1)
generate purchasing requisitions and (2) develop schedules of different
activities to be done on the manufacturing floor.
• Techniques for sequencing activities are discussed in Chapter 15.
• The authorized MPS, the bill of material (BOM) file, and the inventory
records are inputs to the MRP system. It is critical that the MPS be feasible
and that the BOM file and the inventory records be accurate. This implies
that the time standards (Chapter 11) are valid and that cycle counting
(Chapter 12) be used to maintain inventory record accuracy. If not,
material is not ordered at the appropriate time in the right quantity.
© Wiley 2010 26
Resource Planning Across the
Organization
© Wiley 2010 27
Example 2 - of MRP
• Next, it is going to be exposed the practical
case of the operating MRP, we will see again
the making up of the scissors; remember the
bill of materials (BOM) is the following:
Bill of materials
• To a better understanding of the MRP, imagine
you need 2 screws to make the scissor ,
therefore the bill of materials will be the
following
The initial dates are the following:
• For the article S, the emission of the planned orders, indicates that
we have to launch the fabrication order or the sell of 825 units of
screws during the first week. If we acquire them by a supplier, the
EPO shows that in this week we have to realise the order in order of
be given the product by the supplier the second week. If we do this,
we can cover the Net Requirements, the information let us
generating automate reports to our suppliers, and therefore they
can work avoiding the delays or the mistakes as well as having a
minimum stock.
Report of Exceptions and Actions
Many times we can find that when exploring the MRP, some
EOP in past , for example: