From: m.aboshabanah@pillararabian.com
Sent: Sunday, April 3, 2022 7:25 AM
To: H.Alzahrani@pillararabian.com; Hishamadel415@gmail.com; a.refaai@pillararabian.com;
a.alhakeem@pillararabian.com
Cc: h.elgendy@pillararabian.com; hatem@pillararabian.com
Subject: RE: RFI For shuttering of blinding for manholes
3
<hatem@pillararabian.com>
Subject: RE: RFI For MANHOLES
Installation of Manholes
1-f6-18
2-f6-19
3-ps2-40-5-7
4-f6-17
5-ps2-40-5-2
4
first , second and third Coat Damp proofing for back drop of manholes
1-ps2-7-18
2-ps2-7-17
3-ps2-7-16
Grouting for manholes
1-f4-19A
2-F4-19
First ,second and third Damp proofing external
1-from f5-6-1 to f5-6-3
2-from PS2-15-18 to ps2-15-25
Dear Gents,
1- Please find below requests for installation of Manholes
1-F5-10-1A
2-F4-17
2-shuttering for blinding
1-MH-PS2-25
2-MH-PS2-24
3-MH-PS2-23
4-MH-PS2-22
3—Grouting for manholes
1-MH-F5-6-3
2-MH-F5-6-2
3-F4-1-3-1
4-F4-1-3-2
4-coating for benching
1-MH-F4-1-3-1
2-MH-F4-1-3-2
7
5-External coating for manholes 3 layers
From f5-5-2 to f5-5-8
6-Back drop for manholes
1-ps2-7-18
2-ps2-7-17
3- ps2-7-16
Dear Gent,
Please find below requests for installation of Manholes
1-MH-F5-5
2-MH-F4-1-11
3-MH-F4-1-10
4-MH-F4-1-9
5-MH-F4-1-1-2A
ENG.Mohamed Shabana