These are the pending points to be able to carry out the HO on January 30,2024.
Civil
Closing of pending Channel in SIG/COM.
MEP
Installation of grounding rods.
Temporary air fans at doors
Temporary room panels with GFCI outlets.
The above activities as well as those being performed inside the rooms should be completed by Monday, January 29,
2024 and deep cleaning performed.
I look forward to hearing from you if these activities will be completed before the partial HO for RFTR SIG/COM or if you
have any comments regarding the points, please let me know.
Best Regards
Dear All;
As requested, a pre-inspection with NSC will be carried out on Wednesday 24 at 10 am to the technical rooms of station
13(San Bernardino), in preparation for the HO(Partial RFTR).