Professional Documents
Culture Documents
ON
HARE RIVER
JUNE 2010
ARBA MINCH
DESIGN OF MINI HYDROPOWER PROJECT ON HARE RIVER
A REPORT BY:
1. FASIL TESHOME
2. HENOCK TEFERA
3. HANAN TADELE
4. MELKAMU TESHOME
5. NEWAY G/TSADIK
6. SEIFU SISAY
IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE AWARD OF DEGREE
OF:
IN
AT
AND
JUNE 2010
ARBA MINCH
CERTIFICATE
1. FASIL TESHOME
2. HENOCK TEFERA
3. HANAN TADELE
4. MELKAMU TESHOME
5. NEWAY G/TSADIK
6. SEIFU SISAY
IN
AT
AND
ADANECH YARED (BSc)…………………………..
JUNE 2010
ARBA MINCH
ACKNOWLEDGEMENT
In advance, our indebted gratitude goes to the Almighty God, for His mercy, love and
care, which enable us to be alive and stay in the campus during the course of our study.
It is our pleasure to express our deepest gratitude to our advisors, Ato Melkamu
Alebachew and Wrt Adanech Yared for their consistent guidance and supervision.
Moreover, we would like to thank them for providing us the necessary reference
material for this project. And it was also impressing that they were working with the
group in harmony as a friend.
Last but not least, our sincere gratitude goes to our parents, sisters, brothers and
friends for their relevant moral and material support until we get reached this day.
The group
ABSTRACT
This report presents planning and design of mini hydropower project on Hare River
which is located in the Southern Nations, Nationalities and Peoples Regional state,
Gamo Gofa zone near Arba Minch (the capital of Gamo Gofa zone).
The power demand assessment is done for the town Kola Shara and Chano under the
topic.
For hydrological analysis, 22 years of stream flow data recorded at a gauging station,
which is around 1km downstream of the planned dam site, is used. For design flood
estimation Log-Pearson type III distribution is the nearest fit for the given data. So, by
using this distribution a100years of flood is taken as a design flood.
The reservoir is planned by the method of mass curve technique. And the sediment
volume is approximated by empirical formulas which relate the live storage with the
sediment due to due to non availability of sediment data.
Due to the availability of ample rock material and other reasonable factors, a concrete
faced rock fill dam is selected. The dam has a height of 56m with crest width and length
of 7m and 175m respectively.
The availability of a flank at the right side of the dam favors for the choice of chute type
of spillway. The spillway is designed to have an effective length of 12m and discharge of
about 32.545m3/sec.
The conveyance system consists of tower intake, concrete lined head race, forebay,
penstock and concrete lined tail race canal. The design constitutes 805m long and 0.8m
trapezoidal concrete lined headrace canal leading to 10m wide, 25mlength and 4.5m
depth forebay and 193m long and 0.7m diameter inclined pressure shaft. After passing
through the turbine the water is discharged to the main course via the coarse stone
lined tailrace which is 1.37m wide and 65m long. The diversion of the river flow during
construction, a cofferdam of height 5.5m and a diversion tunnel with a diameter of 3m
and length of 370m have been designed.
Surface powerhouse is adopted. The powerhouse has a dimension of 19m length and
13.3m width. The installed capacity of the plant is 1.22Mw and 1units of 0.62m diameter
Francis turbines are used for power generation.
Environmental impacts due to the implementation of the project are quoted and
mitigation measures are suggested under the topic.
The cost analysis is roughly done, since there is no enough data obtained for the total
economic analysis of the project.
ACKNOWLEDGEMENT ...................................................................................................................... I
ABSTRACT .....................................................................................................................................II
List of Figures. .............................................................................................................................VII
List of Abbreviations ................................................................................................................. VIII
List of Annex ............................................................................................................................. VIII
1. INTRODUCTION ................................................................................................................... 1
1.1 General background of the project.................................................................................. 1
1.2 Description of project Area ............................................................................................... 1
1.3. Objective and Designing approach ................................................................................ 3
2. POWER DEMAND ASSESSMENT ................................................................................... 5
2.1 General ................................................................................................................................ 5
2.2. Population Forecasting .................................................................................................... 5
2.3. Power demand of Kola Shara and Chano .................................................................... 7
3. HYDROLOGICAL DATA ANALYSIS ................................................................................. 8
3.1 General ................................................................................................................................ 8
3.2 Data availability .................................................................................................................. 8
3.3 Filling missing data and Transposing data to dam site................................................ 8
3.4 Return Period and Design life ........................................................................................ 10
3.5 Risk, Reliability and Safety factor.................................................................................. 11
3.6 Flood Estimation .............................................................................................................. 12
3.7 Flow Duration Curve........................................................................................................ 19
3.8 Water Law and Design Flow .......................................................................................... 21
4. RESERVOIR PLANNING AND LAYOUT OF THE PLANT.......................................... 22
4.1 General .............................................................................................................................. 22
4.2 Site Assessment .............................................................................................................. 22
4.3 Alternative Layout for Hydropower Development on Hare River ............................. 23
4.4 Types and Storage zone of Reservoir .......................................................................... 26
4.5 Physical Characteristics of Reservoir ........................................................................... 28
4.6 Reservoir Storage Capacity ........................................................................................... 30
4.7 Life of Reservoir ............................................................................................................... 35
5. FLOOD ROUTING.............................................................................................................. 36
8.5 Penstock............................................................................................................................ 82
8.6 Tail Race Channel ........................................................................................................... 85
8.7 Valves ................................................................................................................................ 85
8.8 Hydraulic Losses.............................................................................................................. 86
8.9 Diversion Work ................................................................................................................. 88
9 POWER HOUSE PLANNING ........................................................................................... 91
9.1 General .............................................................................................................................. 91
9.2 Preliminary Power Assessment and Hydraulic Design.............................................. 91
9.3 Determination of Plant Capacity .................................................................................... 91
9.4 Hydraulic Turbines and Electromechanical Equipments ........................................... 92
9.5 Turbine Scroll Case ......................................................................................................... 97
9.6 Draft Tube ......................................................................................................................... 98
9.7 Turbine Alignment............................................................................................................ 99
9.8 Cavitations and Turbine Setting .................................................................................. 100
9.9 Turbine Governor........................................................................................................... 101
9.10 Electrical and Mechanical Equipment ...................................................................... 101
9.11 Power House Planning ............................................................................................... 102
10. ENVIRONMENTAL IMPACT ASSESSMENT (EIA) ................................................ 106
10.1 General.......................................................................................................................... 106
10.2 Physical impact ............................................................................................................ 106
10.3 Impact on hydrology .................................................................................................... 107
10.4 Impacts on biological environment ........................................................................... 107
10.5 Impact on socio-economic environment .................................................................. 108
10.6 Potential positive impacts........................................................................................... 108
10.7 Mitigation measures .................................................................................................... 109
11. COST EVALUATION AND ECONOMIC ANALYSIS............................................... 110
11.1 General.......................................................................................................................... 110
11.2 Bill of Quantities and Cost estimation....................................................................... 110
11.3 Annual cost and cost recovery factor ....................................................................... 112
11.4 Benefit of the project ................................................................................................... 113
11.5 Benefit cost ratio .......................................................................................................... 113
List of Figures.
Fig 3.1 L-moment chart
List of Annex
Annex 1. Summary of Mean Monthly Discharge
Annex.6 Selection of frequency analysis method that is best suited for our site
List of Abbreviations
1 INTRODUCTION
According to Ministry of Mines and Energy, in 1990 the total energy requirement in
Ethiopia was estimated to be 177.6Twh per year. Out of which 76.1% from wood, 16.1%
from agricultural by product, 5.3% from fuel oil, 1.1% from electricity 0.8% from charcoal
and 0.6% from other energy sources.
Ethiopia has got substantial hydropower potential estimated as 30,000MW. Out of this,
less than 3% has been utilized and the remaining should be developed at small to large
scale so that the source of energy for various uses can be replaced by this more
environmentally friendly, highly efficient and perpetual alternative energy source.
When the hydropower plant that is developed on Hare River is implemented, it will play
its own role in solving the electric scarcity problem in rural areas of Chano and
KolaShara
The Hare River catchment situates in Southern Region of Ethiopia, near Arba Minch
town. It is about 491kms away from Addis Ababa and about 14km from the capital of
Gamo Gofa zone.
1.2.2 Topography
The topographical feature of the project area is surrounded by steep mountains
extending from northeast to west, lake Abaya extending from east to southeast and flat
terrain located at the boarder of lake Abaya. The lake is situated at an elevation of
1200m amsl.
The relative humidity of the region varies from 86% in January to 84% may.The
maximum sunshine hours observed is 9.5hrs in January and November. The minimum
sunshine hours observed is 4.5hrs in July. The average monthly evaporation is 125mm.
Due to its great difference in altitude the climate of the project area remains tropical in
which the temperature decreases only to 29ºc in March and falls to 15.7ºc in December
with mean annual temperature of 24.1ºc
1.3.1. Objective
The objective of this project is to summarize our overall courses for partial fulfillment of
Bachelor of Science in hydraulic engineering. These courses helped us to get enough
knowledge on how to design and construct different water resource projects
theoretically and practically. Therefore, when we do this project our main objective is to
combine our theoretical and practical knowledge for designing and constructing an
efficient hydropower project and any other construction works related to our subject.
Additionally, when this project is implemented it will solve the electric scarcity in the
project area and improves the living standard of Chano Chalba people.
It is essential to establish accurately how much energy is required, for what purpose it is
used and to assess the organizational capability of the users of the scheme. This
scheme is planned for communities where most of them do not use latest electrical
household machines. Therefore, the major demand of electricity is for lightening.
Hydrology study and site survey establishes the hydropower potential of the site. It
shows how the water flow varies and the amount of stream flow (discharge) available in
the river for generation of power throughout the year.
C/Pre-feasibility study
This is a quick cost study of a range of design options and rural energy sources. The
pre-feasibility study compares different alternatives to satisfy the consumer demand and
presents their main features. It should make it clear how will supply and demand are
matched.
D/Feasibility study
It is comprehensive analysis and detail study of the contemplated project. The feasibility
is study carried out in order to determine the technical, economical and environmental
feasibility of the project. This study will provide necessary information from which the
owners can decide whether to go for the implementation of the project and it serves as
application documentation for the development license.
2.1 General
This project is mainly designed for lighting purpose at the rural area of Kola Shara and
Chano. During power demand, assessment the following thing should considered
However, mini hydropower project are designed for specific purpose. Similarly, Hare
River mini hydropower project is designed for lighting purpose. Therefore, we have
considered only power demand required by population of the area.
The annual growth rate of rural area around Arba Minch is 2% and that of Semen Omo
zone is 4%.Therefore, for this project an annual population growth rate of 3% is adopted
to assess the power demand the area.
In this method, the assumption is made that all towns and rural areas irrespective of
size tend to grow according to the following equation
N=Number of years
K=Growth rate
From table it is clearly seen that the total number of population of Kola Shara and
Chano in 1994 is 8783.So,by using method used by CSA the present population of the
area is calculated as follows:-
= (8783) (. ∗ )
= 14,194
By adopting the same procedure the population of the area at different year up to end of
design life is calculated and represented in table shown below.
= (120W) ( )
= (120W)( )
=340.7KW
Total Power demand at the end of design life is computed by assuming constant
increase in power demand throughout the design life. Therefore,
.
=( )( )
=620.77KW
To be conservative a higher value is adopted. Therefore, total power demand at the end
of design life for lighting purpose is taken as 700KW
3.1 General
Hydrology is a branch of science dealing the occurrence, circulation and distribution of
water in the earth and earth atmosphere.
Some of hydrological data needed for a design of different water resource projects are:
1) precipitation and climatic data 2) stream flow data 3) ground water and water quality
data 4) evaporation, transpiration and infiltration data 5) water availability and utilization
studies.
It has its own aspect in different water resource works especially in hydropower project.
Some of engineering aspects of hydrology are estimation of water resource, study of
flood, study of rainfall and ways of combating flooding problems. Water resource project
designed without careful analysis of hydrological data will fail or have limited life.
There are different methods used for filling missing stream flow record of a given river.
= ( + …+ )
= ( + +. . . + )
Where m-number of year with full data above the year with missing data
In this project, normal ratio method is used to obtain missing value of run-off depth.
= +
A & B-Coefficients
In this project, linear regression is used to obtain missing mean flow, maximum flow and
minimum flow value. We have selected this method due to the following reasons:-
= ×
No Structure Return
period(yrs)
1 Spill ways for projects with storage of more than 1000
60million cum
2 Barrage and miner dams with storage less than 60 100
million cum
3 Spill ways of small reservoir dams in the country side, 10-20
not endangering urban residences
4 As above but located so as endanger other structures or 50-100
urban residences in case of failure
5 Diversion weirs 50-100
6 Small bridges on main high ways 50-100
(Source: Rozgar Baban, Design of Diversion Weirs)
Depending on the above table, the return period for this project is hundred years.
=100years
The selection of design life for diversion works depends on the risk that one is prepared
to take. In some cases use cost-benefit analysis and economic evaluation as
complementary measure.
= 1 − (1 − )N
R-risk
The designer of hydraulic structures always faces an engineering doubt about the risk of
failure of his /her structure. This is because the estimation of hydrologic design values
(such as-the design flood discharge and river stage during the design flood) involve a
natural or inbuilt uncertainty and as such a hydrological risk of failure.
It can be seen that the return period for which a structure should be designed depends
up on acceptable level of risk. In practice, the acceptable level of risk is governed by
economic and policy consideration.
For this project, the risk of failure of the structure can be computed as:-
20
= 1− 1−
= 18.2%
= 1−
= (1 − )N
Safety factor, Sf
An outlier is an observation that deviates significantly from the bulk of the data, which
may be due to errors in data collection, or recording, or due to natural causes. The
presence of outliers in the data causes difficulties when fitting a distribution to the data.
Low & high outliers are both possible and have different effect on the analysis. The
Grubbs & Beck (1972) test (G-B) May be used to defect outliers. In this test the
quantities x H & x L are calculated by using equations shown below:-
=exp ( + )
=exp ( − )
Where and S are the mean and standard deviation of the natural logarithms of the
sample respectively. is the G-B statistic tabulated for various sample size and
significance levels by Grubbs and Beck (1972). At5 the 10% significance level, the
following approximation proposed by Pilon at al. (1985) is used, where N is the sample
size
1 1 3
= −3.62201 + 6.2844N -2.49835N +0.491436N -0.037911N
4 2 4
Substituting N=23 the K value becomes 2.448 and therefore for this project the high and
low outliers are calculated to be = 34.254 m3/sec and = 1.667 m3/sec
respectively according to equations shown above.
=( )
B/Rational Method
One of the most commonly used method for the calculation of peak flow from small
areas(i.e less than 0.8km2) .It is based on the application of the formula:-
A-catchment area
It is applicable for small and medium basin (A<5000km 2) since according to the theory
storm distribution over the area is assumed to be fairly even.
There are different methods of flood frequency analysis. But, the most commonly known
methods are:-
Several general approaches are available for estimating the parameters of a distribution.
Some of these methods are the following:-
Method of moments
Method of maximum likelihood
Method of probability weighted moments etc
Method of moments
Sample estimator of L-moment are linear combinations of the ranked observation and
thus do not involve squaring or cubing the observations. That is why it said L-moments.
In a wide range of hydrological applications, L-moments provide simple and reasonably
efficient estimator of the characteristics of hydrologic data and distribution parameters.
1 n j 0.35) r
*
br x( j ) {1 ( )}
n j n n
j 0.35
Where, 1-( ) are estimators of F(x).
n
br Is suggested function use when estimating quantiles and fitting distribution of a single
site; though it is biased, it generally yields smaller mean square error quantile estimator
that the unbiased estimators.
( )
∑ ( )
( )(( ) )
∑
( )( )
( ) ( ) (( ) )
∑
( )( )( )
6.096138
4.747202
3.932203
For any distribution, L-moment are easily calculated in terms of PWMs from
= = 9.06013
=2 − = 3.132146
=6 −6 + =0.96651
=20 − 30 + 12 − =0.321534
= =0.345707
= =0.308578
= =0.102656
Measure of skewness
Measure of kurtosis
To select the type of distribution, which fit to the given data, is using the following
equations:
A/Uniform distribution
=0 =0
B/Exponential Distribution
=1/3, =1/6
C/Normal distribution
= 0, = 0.1226
D/Gumbel distribution
=0.1699, =0.1504
E/ Log-normal distribution
2 4 6 8
=0.12282 + 0.77518 +0.12279 -0.1368 +0.11368
F/ Log-PearsonIII distribution
=0.1224+0.30115 2+0.95812 4
-0.57488 6
+0.19383 8
L-moment chart
1.2
1
General Extreme Value
0.8 Gamma & Pearsonlll
Kurtosis
Log normal
0.6 Weir Site
Uniform
0.4
Gumbel
Logistic
0.2
Exponential
0 Normal
0 0.5 1 1.5
Skewness
From the skewness versus kurtosis plot, the distribution that best fit to our dam site is
Log Pearson type III.
∑( )
=
( )( )
∑( )
= standard deviation, = ( )
4. Obtain the frequency factor, K from table (Rozgar Baban, Design of diversion head
works)
log Q = +
Q =antilog (log Q )
The test uses the correlation r between the ordered observations X (i) and the
corresponding fitted quantities Wi = G -1 (1-qi), determined by plotting position qi for each
X(i). Values of r near 1 suggested that the observation could have drawn from the fitted
distribution. Essentially, r measures the linearity of the probability plot, providing a
quantitative assessment of fit. If x denotes the average value of the fitted quantiles.
Then,
X i
X W W i
X X * W W
r=
2 2 0 .5
i i
r=0.9046
Different plotting position attempt to achieve almost quantile unbiasedeness for different
distribution; many can be written as-
( )
=( )
( )
For Log Pearson type III distribution =3 8, then =( )
100
80
Discharge
60
Qactual
40 Qcomputed
20
0
1975 1980 1985 1990 1995 2000 2005
Year
Due to total year method incorporates all the flow records; it gives more accurate result
than the calendar year method. Thus, it is used to plot flow duration curve for this project
using Weibull formula.
i.e. =( ∗ 100…………………………………………..
)
From the flow duration curve the conventional discharges that are obtained for some
percentage of excedence are , , .
Where,
– Minimum flow available for 100% of time, which is used for the computation of
minimum potential power (firm power)
– Small potential power computed from the flow available for 95% of time
– Median potential power is computed from the flow available for 50% of time
- Mean potential power is computed from the average of mean yearly flow for period
10 – 30 year.
Depending on the Flow Duration Curve analysis, the conventional discharge values are
tabulated as follows:-
0.095
0.350
1.421
4
Discharge in cumecs
0
0 20 40 60 80 100 120
Percentage of exceedence
The Hare River mostly uses for irrigation, home use and for drinking cattle’s in the area.
As a solution for this case, the Hare River Hydropower Project is reserved some amount
of water for aquatic biota in the river and water which returns to stream through tail race
will be used for other purpose like irrigation ,home uses etc.
Design flow for hydropower project is a flow that hits the turbine for generation of power.
When someone aims to fix design flow, he/she should have to fulfill water law.
Design flow chosen for a hydropower scheme is depending on the type of power
generated. This means whether it is firm or peak power etc
4.1 General
River flow rate may vary considerable during different periods of a year. It may carry
little or no water during in a drought year and carry a large amount of water after heavy
rains. This heavy rain may cause flood hazard along the riverbanks or outside. During
extremely low flows, it may not possible to meet the demand of different consumers of
water by directly drawing from a river.
To alleviate this problem reservoir or artificial lake are created by constructing a dam
across the river which can retain the excess water during period of high flows for use in
the period of low flows on the drought season. In addition, for conserving water for latter
use, the storage of floodwater may also reduce flood damage in the downstream of the
reservoir.
Geological study
Geological investigation of water power structure site selected for detailed evaluation is
directed to determination of geological structure, faulting jointing and to establishing
ground and ground water condition adjacent to selected site.
Topography
During topographic study, suitable land escape for different components of hydropower
plant should be studied. The suitable land escape for different structures varies. For
example weir or dams requires narrow valley with sound at the abutment and
foundation.
Based on our field visit and topographic map of the area we have selected two possible
alternative sites for locating the main components of Hare River mini hydropower plant
such as dam, conveyance systems and powerhouse.
Alternative I
The main criteria comparing this alternative are:
Based on the above criteria’s the possible alternative sites are discussed as follow.
Alternative II
Alternative I
It is located at 6o05’ latitude and
This site is located at 37o34’ longitude
37o35’longitude.
and 6o07’ latitude.
The proposed power plant components
The proposed power plant components
for this site are-
for this site are
Diversion weir
Rock fill dam for storage
Canal for water conveyance
Canal for conveyance system
Underground powerhouse
Surface powerhouse
4.4.1General
Availability of water in Equator area like Ethiopia is highly uneven both in space and in
time. To meet the demand of water at the location of water resource project arising out
of the variability of the resource, storage reservoir provide the only viable alternative.
The variation of discharge in the river is common during different period of the year. In
rainy season there is excess flow down the valley in the river .When a barrier is
constructed across some river in the form of a dam water gets stored on the upstream
on side of the barrier forming a pool of water generally called a dam reservoir .The
stored water meets the demand in dry periods
A rock fill dam is built across a Hare river to reserve sufficient water behind it so that
water can supplement the various demands (power generation) during lean seasons.
A city water supply, irrigation water supply or a hydroelectric project drawing water
directly from river or stream may fail to satisfy the consumer demand during extremely
low flows, while during high flows it may become difficult to carry out their operations
due to devastating floods. Storage or a conservation reservoir can retains such excess
supplies during period of peak flows and can release gradually during low flows.
A flood control reservoir, generally called a flood mitigation reservoir stores a portion of
flood flows in such away to minimize the flood peaks at the areas to be protected
downstream. To accomplish this entire inflow entering the reservoir is discharged until
the out flow reaches safe capacity and the channel downstream. The inflow in excess of
this rate is stored in the reservoir, which is then gradually released, to recover the
storage capacity for the next flood.
3. Multipurpose reservoir
A reservoir planned and constructed to serve not only one purpose but also various
purposes together is called a multipurpose reservoir. This type of reservoir can be
designed to protect the downstream areas from floods and to conserve water for water
supply, irrigation, industrial needs, hydroelectric purposes etc.
4. Distribution reservoir
A distribution reservoir is a small storage reservoir constructed within a city water supply
system. Such a reservoir can be filled by pumping water at certain rate and can be used
to supply water even at rates higher than the inflow rate during periods of maximum
demand(critical period of demand).
It is the maximum elevation, to which the reservoir water surface will rise during normal
operating condition.
The lowest water surface elevation, which has to be kept under normal operating
condition in a reservoir
c. Surcharge storage:
This is the storage between full reservoir level and maximum water level.
It is the minimum reservoir level below which, water is not allowed to be drawn for
conservation purposes. This also represents a level below which the silt carried by the
river is expected to be deposited. Dead storage is generally taken as 10 to 25 % of the
gross storage.
e. Live storage:
f. Bank storage:
HYDRAULIC AND WATER RESOURCE ENGINEERING DEPT. JUNE, 2010 27
DESIGN OF MINI HYDROPOWER PROJECT ON HARE RIVER
It is the level of spillway crest (for un gated spillway) or the top of spillway gate (for
gatedspillway) to which the reservoir is usually filled.
It is the new elevation to which, water in the reservoir rises when design flood impinges
at full reservoir level.
V = (A1+ A2)
2. Simpson’s rule
3. Cone formula
∆V1 = (A1+A2+ A1 * A2 )
V=Σ∆v
4.Integration technique
Integratining area elevation curvve yilds capasity elevation curve. The surveyed area at
large contour interval may be plotted on a simple graph paper and smooth curve i.e area-
elevation curve is drawn. The equation of this curve is now obtained by statistical
method, which can be integrated to obtain the equation of the capasity-elevation curve.
The equation of the area elevation curve, will generally of the form
A=a+bh+ch2+dh3+....................+mh n-1
a,b,c,d............m – constants
n – number of contours
For this project integration technique is selected.Becouse,this method gives better result
with minimum error for contous at large contour interval when compared to other
methods.
2.5 0
2 50
1.5 100
1 150
0.5 200
0 250
1250 1300 1350 1400 1450 1500
-0.5 300
Area-Elevation Capacity-Elevation
The demand for this project is determined from the total power demand, which is
calculated in chapter two. Out flow includes: water released for downstream
requirement, loss as evaporation, seepage and water required to generate the required
power. The demand for power generation is a flow corresponding to 75%exceedence
Different methods are available to determine the live storage for a given demand and in
flow. The two most widely methods are:-
1. Mass curve
The flow mass curve is a plot of the commutative discharge volume against time plotted
in chronological order. It is also known as ripple’s mass curve. The abscissa of mass
curve is chronological time in days, weeks, or months depending on the data being
analyzed. Whereas,the ordinate is in units of volume in Mm 3, m3/s*day (cumec* day),
ha*m and ha*cm over a catchments area.
1. The reservoir is full at the beginning of the critical draw down period.
2. As the analysis utilizes historical stream flow data, it is implicit that future sequence
of inflow will not contain a more severe draught than the historical sequence.
Steps to find the storage capacity of a reservoir from the mass curve
i) For the proposed dam site, construct a mass curve of cumulative curve of the
historical stream flows by taking three consecutive dry years.
ii) Superimposed on the mass curve the cumulative draft line for the reservoir such
that it is tangential to each lump of the mass inflow curve.
iii) Measure the largest intercept between the mass inflow curve and the cumulative
draft line. This gives the storage capacity desired.
The live storage for this project from mass curve analysis is 5.3088031Mm3
35
30
25
20
Cumulative Inflow
15
Cumulative Demand
10
0
0 2 4 6 8 10 12 14
4.6.3.1 General
Sediment is the fragmental earth materials eroded, transported and deposited
elsewhere naturally by agent like air and water. Sediment transport is a natural process
and therefore, it can not be stopped completely.
condition is developed. This water reaches the dam and then rises vertically along the
wall of the dam. In the process, mixing also take place between the reservoir and river
water and part of turbid water spills over the dam. With time the sediment usually settles
at the bottom of the reservoir
Sedimentation of a reservoir reduces the storage capacity and it was the primary
problems to be dealt with in the 21st century. The final destiny of a reservoir as to be
filled with sediment, if the sediment inflow is large compared with the reservoir capacity;
the useful life of the reservoir may be varying short.
Rate of silting
Relation between stream flow and suspended sediment load
Total sediment transport in the catchment
Bed load or suspended sediment load volume etc
However, for the case of Hare River none of the above data is recorded. Therefore, we
are going to take assumptions depending on different literatures and our field visit.
a) Selection of dam site: - The silting depends upon the amount of erosion from the
catchments. If the catchment is less eroding able, the silting will less. Then the silting
can be reduced by choosing the reservoir site in such away as to exclude the runoff
from the easily erodible catchments.
c) Construction of under sluice in the dam:-The dam is provided with openings in its
bed, so as to remove the more silted water on downstream side.
Among the above equations, penman’s equation is applied to compute the potential
evapotranspiration from the water surface of Hare hydropower plant reservoir. This
equation is based on sound theoretical reasoning and is obtained by combination of the
energy balance and mass transfer approach.
Ea =0.35(1+ ) (ew-ea)
Since the volume and the surface area of water in the reservoir is not constant, two-third
of maximum, area is assumed as a mean and net evaporation volume is estimated.
2
A mean== (0.307499) = 0.2049993km
Total storage=7.03874135Mm3
Elevation=1320.1217m (NPL)
5. FLOOD ROUTING
5.1 General
Flood routing is the method of determining the flood hydrograph at a section of a river by
utilizing the data of flood flow at one or more upstream sections.
The hydrologic analysis of problems such as flood forecasting, flood protection, reservoir
design and spillway design invariably include flood routing. In these applications two
broad categories of routing can be recognized.
This are-
1. Reservoir routing
2. Channel routing
The equation of continuity used in all hydrologic routing is the primary equation. This
states that the difference between inflow & out flow rate is equal to the rate of change of
storage
i.e.
Q=outflow
∆S=change in storage
∆t =change in time
To develop inflow hydrograph to a catchment, detail information about the rainfall and the
resulting flood hydrograph are needed. However, mostly seen information would not be
available, therefore to construct unit hydrograph for some area, empirical equation of
regional validity that relate the hydrograph characteristics are available. Unit hydrographs
derived from such relationship is known as synthetic unit hydrograph.
In order to develop synthetic unit hydrograph the equation which was first developed by
Synder and modified by Linsley et al. is used for computing the lag time(tp) to peak of the
inflow hydrograph.
= ( )n
√
Where; L =is the basin length measured along the water course from basin dived
gauging station in mile.
Lc=distance along the main water course from gauging station to a point
opposite to the water shed centroid in mile
S=basin slope
n =basin constant
=10.706hr
=2hr
HYDRAULIC AND WATER RESOURCE ENGINEERING DEPT. JUNE, 2010 37
DESIGN OF MINI HYDROPOWER PROJECT ON HARE RIVER
= + = 10.72 + =11.72hr
Say = 12hr
There are several methods to develop synthetic unit hydrograph. Among the methods,
Dimension less unit hydrograph method approach is the most widely used one.
0 0.1 0.2 0.3 0.4 0.5 0. 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4
6
0 0.01 0.07 0.1 0.2 0.4 0. 0.7 0.8 0.9 1 0.9 0.9 0.8 0.7
5 5 6 8 3 6 7 9 7 8 2 4 5
0.6 0.5 0.4 0.3 0.2 0.1 0.1 0.09 0.07 0.03 0.01 0.00 0.0
6 6 2 2 4 8 3 8 5 6 8 9 4
INFLOW HYDROGRAPH
40
35
FLOW (m3/sec)
30
25
20
15
10
5
0
0 10 20 30 40 50 60
TIME(hr)
Therefore, the outflow discharge is computed by considering the over fall spill out of
water. That means
Q = C*L*H 1.5
In the determination of the spillway length 10m, 12m, and 15m are taken for the
comparison. When the length of the spillway decreases the height of the outflow above
the spillway, will increases. It results in increasing the dam height, which in turn
increases the dam cost. On the other hand, when the length of the spillway increases it
will make the design of the spillway more costly.
Taking in to account all the above advantage and disadvantage, 10m effective length of
the spillway is taken.
From these equations, the trial and error method is adopted as it is widely used with the
help of spreadsheet.
The equation of continuity used in all the hydrograph routing methods, as the primary
equation, states that the difference between the inflow equation and outflow rate is
equal to the rate of change of storage.
I –Q= ∆S/∆t
But,
Q1 Q2 I1 I 2
Qavg , I avg and S S2 S1
2 2
I I2 Q Q2
t 1 t 1 S 2 S1
2 2
I I 2 S1 Q1 S 2 Q2
1
2 t 2 t 2
Therefore, S=A.H
The routing process is done with the help of spreadsheet application by using goal seek
and the whole calculation is shown at annex.
INFLOW-OUTFLOW HYDROGRAPH
40
35
30
25
FLOE(m3/sec)
20
INFLOW
15
OUTFLOW
10
5
0
-5 0 10 20 30 40 50 60
TIME(hr)
From the inflow-outflow hydrograph the maximum discharge over spillway corresponds
to the point on a curve at which the inflow hydrograph crosses the peak of outflow
hydrograph. Hence, the maximum discharge over the spillway Qmax =32.515m3/s and
the corresponding height is 1.15m. Therefore, for the design of spillway
Qmax=32.515m3/s at an elevation of (1.15+1320.1217)=1321.2717m a.s.l
6. DAM CONSTRUCTION
6.1 General
Dam is a solid barrier generally impervious in nature constructed at the narrow out let of
a catchment area or in a valley. They can be constructed of earth, steel, timber rock or
from solid masonry concrete. It holds up the flow of water to raise the water level to a
fixed level to form a reservoir on the upstream side.
It passes the water over or through it when it is required or when the water is surplus
Storage dam
Diversion and detention dam
Therefore, a thorough deal about the site for bearing capacity should be made and you
have to check whether fault fissured materials or permeable rock present or not.
If the solid rock foundation is granite or gneiss, we can construct any type of dam.
Otherwise, for the foundation such as gravel, which is unable to carry the weight of high
concrete gravity dam and silt or fine sand foundation, which have high seepage problem
the construction should precede after an appropriate treatment is made.
Therefore the type of dam to be selected is the one for which the required construction
material is in the vicinity of the project site as it reduces the total cost of project by
reducing transportation expense ,human labor and time.
Therefore, spill way is much more important on streams with large flood potential than
the type of dam to be considered.
In addition to this adoption to the purpose of the dam supposed to serve, economy and
safety the best dam for the given site will be selected.
In addition to this since the materials required for the construction of the dam is at the
reasonable distance from the dam site it will reduce the transportation cost. In other
ways while using those naturally existing materials (rocks), the cost of concrete will
decrease which gives rise to our economy. The area is affected by seismic wave; an
embankment type of dam is the most suitable for the site.
In general, considering the above reasons and others like safety, suitable site for
locating the spillway, rock fill type of dam with suitable cut off to reduce seepage loss is
selected.
i. Central core
ii. Sloping core
iii. Upstream membrane or decked
In the central core, the dam is provided with a central impervious core covered by
comparatively pervious transition zone, which is finally surrounded by much more
pervious outer zone. The central core checks the seepage, the transition zone prevent
piping though the cracks which develop in the core while the outer core gives stability
to the central impervious and distribute a load over a large area of foundation .this type
of dam is widely constructed if the pervious central core is sufficiently available. Clay
soil is impervious but do not make the best core because it shrinks and swell too much.
Therefore, it has to be mixed with a fine sand or fine gravel for the best impervious
central core.
In sloping core, the type of core of the dam will remain with the same criteria as a
central core but if the core will be rearranged at an angle for the better stability of core
material. In other words, the central and sloping core is internal membranes used to
increase the maximum contact pressure with the foundation.
For Hare River, an upstream membrane with reinforced concrete facing is selected,
because, the membrane has the following advantage
A. Free board:-it is a vertical distance between the maximum reservoir level of the
top of the dam the free board has several components.
Rise in reservoir level due to flood routing
Seiche effect
Wind set up of the water
Wave action
Run up of waves on the dam
The last four components are of the considered as the free board
Wind set up-this height of water filled up due to the blowing wind. It can be calculated by
Zuider Zee equation.
= /
Where U-wind speed 40km/hr(assumed)
K-constant=62000
∗ .
= = 0.000655
∗ .
/
= 0.032√ + 0.763 − 0.271( ) , for F≤32km =0.032√40 ∗ 1.30208 + 0.763 −
/
0.271(1.30208) = 0.664
Wave run up:-the maximum height attained by a wave running up a dam face referred
to steady level without wind action. It primarily depends up on the wave height, depth in
front of the dam geometry and material of the upstream face of the dam approach
condition in the reservoir.
. . ∗ .
Wave run up=0.75 ∗ +( )
= 0.75 ∗ 0.664 + ( )
= 0.9056
∗ .
= −
Dam height includes the heights up to NPL, routed height, free board and allowance for
settlement.
I. Settlement calculation
Rock fill settlement is associated with particle crashing and is greatly increased by
saturation it can therefore be calculated design construction operation. The construction
settlement at crest level is given by
( )
Where α-constant between (0.2-0.5)
Take α=0.2 for small dam series settlement in an embankment dam is low
-time of construction=2yr
. ( ) .
. . .
Top width;-the top width of an embankment dam should be sufficient to keep the
phreatic line with in the dam when the reservoir is full. It should also be sufficient to with
stand earthquake shock and wave action.
The top width (T) of the embankment the dam can be selected as per the following
recommendation.
Take T=7m
6.7.1Embankment section
The upstream and downstream slopes of the dam will depend on the type of impervious
membrane and its location. Rock fills dams in which the membrane is placed on the
upstream face, the dam usually have upstream slope ranging from 1.3 to 1.7:1 with
downstream slopes approximating the natural slope of the rock.
Thus it is recommended where seismic activity is expected decked rock fill dam
containing large dam stream slope of the decked fill be flattened to a slope of 1.7 to1 in
all case.
For Hare River considering the fact that, the African Great Rift Valley passes through
the area and there is active seismic wave an upstream slope of 1.3:1 and the
downstream slope of 1.7:1is adopted.
The interior section of the decked rock fill dam can be divided in to three zones and
described as
Zone A -Well graded, smaller sized rock and gravel; used to provide bedding for the
upstream membrane and to retard extreme water losses should the membrane crack
Zone B-rock of lesser quality than zone C, such as excavated material from the spillway
used to minimize to total dam costs.
Zone C- The larger downstream zone of the dam, consisting of the best quality, larger
size, compacted rock, and this zone provides high stability to the section.
In addition, the settlement of rock material has been correlated with the application of
water. Rock fill material dry and subsequently cured may settle appreciably than others.
Sluicing has long been advocated as a method, which assures that point-to-point
bearing occurs between the larger rock and the finer ones that the finer materials
washed in to the void.
When rock fill materials are placed in thin lifts and compacted there appears to be no
definite proof that shining operations provided a significant reduction in the total
settlement.
Dirty rock will require a greater amount of water to wash away the fine material.
Therefore, case should be taken that an accommodation of mud does not form at the
bottom of the lift due to sluicing sufficient sluicing equipment should be available to add
the maximum rock placing rates. Since its absence may affect the quantity of rock fill
placed.
In a concrete faced rock fill dam the zone a material has been eliminated and only a
leveling course is applied to the face zone B. compaction of the leveling coarse is
performed by drawing a smooth drum vibration roller up the face. The final upstream
surface of zone B may also be finished by pulling the vibratory roller up its face. The
advice of an experienced dam design should be obtained before zone A is eliminated.
Low permeability
Sufficient strength to bridge subside area of face
High resistance to weathering action
Sufficient flexibility to tolerate small embankment settlement
The recommended slab thickness for facing varies from 20 to 90cm, the concrete to be
used should be dense, durable, weather resistant and of low permeability. For the case
of possibility of settlement by earthquake the slab thickness for the membrane may be
increased
= 0.3 + 0.003
Say t=0.5
H-reservoir depth
= = × = 314 = 3.14 × 10
0.18825
= = 599.522
3.14 × 10
= 600
.
= ×
= 15.302
∅
=
The force tending to cause sliding of the dam is the horizontal component of water head
pressure.
1
2.89 × 9810 × 2 × [ + ] tan ∅
2.89 × 9810 ×
1
2.89 × 9810 × 2 × [7 + 175]56 tan 35
= = 6.531 > 2
0.5 × 9810 × 56
Shear safety
The shear safety of a horizontal dam section is tan
Z
z = H/2
r = 20 KN/m3
h = reservoir depth
×
= = 20 × 56 × 0.5 = 560 /
. /
= = 0.1318 ≤ tan 35 = 0.7
/
Sliding Safety
The sliding safety of the entire dam body subjected to deadweight and water pressure
must be checked.
N= vertical forces = water weight above + weight of the u/s slope fill material
= = /2
ℎ = 51.3217
= 16.795 /
. .
∑ = + = 118.715 /
= = 0.1088 ≤ tan 35
. /
The foundation of the dam must be strong enough and capable of withstanding the
foundation pressure exerts on it under varies conditions of loading.
I. Foundation grouting
II. Provision of cut off
Foundation grouting is a process in which a grout in liquid form is injected in to the soil
or fissured rocky foundation according to foundation served, foundation grouting is
divided in to
a. construction grouting
b. curtain grouting
c. blanket or area grouting
For concrete facing rock dam type of grouting adopted mostly is a curtain type of
grouting because it depends on the treatment to be given to the foundation.
1. Minimum leakage
2. Prevention of piping
3. Limited settlement
4. Sufficient friction development between abutment and foundation to ensure
sliding stability
A minimum width and depth of 3 feet is recommended for cutoff walls in sound rock,
deeper walls should be in unsound, broken or closely jointed rock.
Provide access for grouting when it cannot be done from the face of dam
7.1 General
Spillway is structure constructed at or near the dam site for effective disposal of surplus
water from upstream to downstream of it .A spillway capable of discharging the probable
maximum flood, which cannot contain in the allotted storage, and at diversion dam to
bypass flows exceeding those, which turn to the diversion system.
The spillway must have adequate discharge capacity to pass the maximum flood
downstream without causing any damage to the dam and its appurtenant structures and
it must be hydraulically and structurally safe.
A spillway can be located either within the body of the dam or at one end of it or entirely
away from it as an independent structure.
Service (or main) spillways design for frequent use in conveying flood release
from the reservoir to a watercourse downstream from a dam. It designed to pass
the entire flood.
Auxiliary spillways designed for in frequent use and many sustain limited
damages when used. Some damages of the structure from passage of infrequent
flood are possible. It is provided in conjunction with the main spillway is designed
are expected .the total capacity of the spillway is then equal to the sum of the
capacity of the main and auxiliary spillways.
Emergency spillways designed to provide a reserve protection against over toping
of a dam intend for use under extreme conditions, such as disoperation or,
malfunction of a service spillway.
Controlled or gated spillway a controlled spillway is one, which provide with the
gates over the crest to control the out flow from the reservoir. In the controlled
spillway, the full reservoir usually keeps at the top level of the gates. The out flow
from the reservoir can be released the reservoir even when the water levels below
the full reservoir level.
Uncontrolled (ungated) spillway it can control spillway, the gates are not provided
our not provided over the crest to control the over flow from the reservoir .The full
reservoir level is at crest level of the spillway. The water escapes automatically
when the water level rises above the crest level. Thus, the main advantage of
uncontrolled spillway is that it does not require the gates and the operator and
lifting power to operate the gates besides there is no problem related to the
maintenance and repair of gat
o type of dam,
o quantity of floodwater to discharge,
o amount of excavation and possibility for is use as construction material or
embankment material,
o stability of foundation and excavation,
o hydraulic condition,
o geological conditions,
o topography of the site and
o Overall economy of the scheme
For this particular project, chute type of spillway is well suited. Because;
Chute spillway essentially requires enough slope to maintain super critical flow, it avoid
unstable flow conditions. Actually, Hare River Hydropower project site is located in high
mountainous zone, which make easy to give slope to maintain supercritical flow .
Since the chute spillway is provided in a flank or a saddle, the height of the spillway or
ogee weir required to be constructed in that flank will be small. Sometimes flat low weir
shall be required depending on the natural level of the bottom of the flank.
If the flank bottom is lower than the natural pool level, an ogee weir shall have to be
constructed up to that level and if flank bottom is at a higher level than the normal pool
level, excavation will have to be done up to that level. In such a case the weir crest is
normally left flat as it shall seldom be economical to excavate the rock just for the
sake of constructing an ogee shape for obtaining high coefficient of discharge.
b. Chute slope
The water spilling over the control structure (ogee weir) and then flow through the chute
channel. The maximum slope of the chute is governed by the condition that supercritical
flow must be maintained.
The side walls of the chute should such a height that water does not spill over them. A
sufficient freeboard must be provided above the top of the water nape, for obtaining the
top level of the sidewalls .The freeboard is generally given by equation:
d. Approach channel
e. Discharge carrier
It is part of the spillway, which leads the water from the control structures to the
downstream rivers. It is generally straight in plan .However, if any curvature is required
to be provided ,its floor should be supper elevated to guide the high velocity flow
around the bend ,thus avoiding filing up of flow towards the outside of the chute.
Assume the coefficient of discharge as 2.2 and taking Le as the clear width which equal
to 12m and assuming He is equal with H we get
32.515=2.2*12*H3/2
H3/2=1.23163
H=1.15m
Water depth = Upstream water level –Bed level in the flank = 1321.272-
1316.3=4.972m= Y
A= (18+4.972)*4.972=114.22m2
Velocity head. Ha =
.
Ha= =0.00413m
.
P=18+2√2(4.972)=32.063m
.
R= =3.562m
.
Assuming the length of the channel to be 30m;the head loss due to friction upto spillway
crest is given by Manning’s formula as:
o ℎ =
. ∗ . ∗
ℎ = = 0.000162
.
Level of upstream TEL= upstream water level + velocity head- head loss due to friction
Effective length, = − 2[ + ]
Therefore, the design shall be done for a design head equal of 1.17m
Hence, lies between 0 and 0.08 and ≥ 1.0, it is possible to use the equation
recommended by WES for downstream profile
. .
= 1.852 But, =1.174m
.
= 2.099y
.
y= .
II. Position of downstream apron of spillway
The apron or toe of spillway should be at such an elevation that it does not affect the
coefficient of discharge.
ℎ + ≥ 1.7
ℎ + ≥ 1.996
.
If d is the width, then the velocity, V== =
.
( )
Specific energy = + = + = − . = 1.996
.
The remaining coordinates of downstream profile between X=0 and X=1.4m are worked
out as
X in meters Y=
.
in meters
.
0 0
0.3 0.056
0.6 0.192
0.9 0.395
1.1 0.565
1.3 0.760
1.377 0.842
The coordinates of the upstream profile are calculated as shown in the table below
X Y
0.000 0.00 0 0
0.020 0.0004 0.0235 0.0005
0.060 0.0036 0.0704 0.00422
0.100 0.0103 0.1174 0.0121
0.120 0.015 0.141 0.0176
0.140 0.0207 0.164 0.0243
0.150 0.0239 0.176 0.0281
0.160 0.0275 0.1878 0.0323
0.175 0.0333 0.2054 0.0391
0.190 0.0399 0.223 0.0468
0.195 0.0424 0.2289 0.0498
0.200 0.045 0.2348 0.0528
The depth at the top of spillway (d) was calculated to be 0.341m,which is less than .
Hence, the flow at the top of spillway is supercritical.
The chute channel should now be given a milder slope for little distance from toe, but in
no case less than the critical slope.
.
Critical velocity, = = = 2.606 /
.
But, V= ⁄ ⁄
A rectangular channel with bottom width 18m should be provided as the chute channel
for the chute spillway.
P= + 2 = 18 + 2 × 0.693 = 19.386
.
R= = = 0.643
.
2.60 6= × 0.643 ⁄ ⁄
.
S = 0.0044 =
A slope of say is provided in 35m distance from the top of the spillway.
The reverse curve at the toe may have the radius equal to 2 = 2 × 1.174 = 2.438
From this point on wards i.e RL =1318.93m up to RL=1270.3m the slope of discharge
carrier is steeped at a slope of 7:1. The entire design is now like a rectangular channel.
The depth, velocity etc at the end point of 1 in 100 slope may be taken to be the same
as they were at the toe of the spillway, because the small length of 25m shall not
produce much difference.
The calculations of water depth, velocity, etc can now be carried out for the entire reach
(RL =1318.93masl to RL =1270.3masl) of the discharge carrier by dividing the channel
length in to small reaches.The depth (d) at the point is assumed in col (6). Specific
energy is calculated in col (9).The TEL at the end is calculated in col (10). The drop in
energy line (hf) in the interval is calculated in col (17). The drop h f at the end of the
interval is subtracted from the final calculated TEL at the beginning of the interval in col
(18). The col (18), is then compared with col (10). They should be almost equal. If the
difference is large, the assumed depth is changed till equivalence is obtained.
Calculation of water depth on the chute is done in the annex
Design of curve (at the junction of 100:1 and 6:1 slopes, a convex curve shall be
provided)
= − tan − . [ ( ) ]
.
( )
The specific energy at junction point ( + ℎ )=0.3144+0.3144 + .
= 1.996
.
The curve meet downstream slope where = − (-ve sign shows that as x increases y
decreases)
Other coordinates of this curve for values of x between x=0 and x=0.94m determined
from equation = + .
= 0.61 + 0.04
.
= 0.215 + + (0.61 + 0.04 × 7.0645 × 0.265 = 1.434
.
.
= 0.226 + + (0.61 + 0.04 × 7.833 × 0.23 = 1.43
.
.
= 0.228 + + (0.61 + 0.04 × 7.88 × 0.223 = 1.43
.
Therefore, reinforcement is provided using ∅16 bars at 27cm c/c in both directions.
Chute spillway generally discharges water at a point far away from the dam. Hence,
protection is required only for the spillway as the danger for the main dam is not there.
For this reason, a hydraulic stilling basin is sufficient, and provide at the discharging point
of the spillway. Stilling basins are not simple concrete apron, but are provided with
auxiliary devices, such as, chute blocks, sills, baffle blocks, etc. they are devices which
help in dissipating the incoming energy by offering resistance to flow and may stabilize
flow in a shorter length of the basin, thus reducing the cost. In general, stilling basin may
be defined as, a structure where energy dissipation action is confined.
y1
y2 1 8 F1 1
2
2
From the table given at annex, the following parameters are known: Froude number =
5.272, the depth y1 = 0.229m and velocity = 7.897m/s. y2=1.597m
Since our Froude number Fr=5.272 is greater than 4.5 and velocity V=7.897m/s is less
than 15m/s U.S.B.R stilling basin type can be provided. This type of stilling basin is
provided with, chute blocks, baffle blocks and end sills.
8.1General
Intake, head race tunnel, penstocks, outlets, conduits etc drawing water from reservoir,
river or canal have to be provided with suitable arrangement to draw in required supply
in a satisfactory manner for the production of power. Structures for this purpose are
known as water conveyance structures.
The effectiveness of the intake in preventing sediment entry increase with the
sharpness of the bend
Intakes from the straight reaches can be made favorable by artificially forcing
the water to follow a curved path.
Best position of intake is with the screen at right angles to the spillway so that
in flood seasons the flow carries the debris over its crest.
In order to attain the required discharge capacity the intake must be placed
sufficiently below reservoir level and high enough to prevent entry of
sediment.
.
= = 1.1282
.
= 1.1282 ⇒ = 1.2
4
= 2 ℎ ℎ .
= = 0.18
The gate operates at 0.18m above the centerline of conduit. Entrance to the gate
should be shaped such that the entrance loss is minimum. A bell mouth entry
provides such condition. The shape of bell mouth is elliptical, as suggested by the
equation:
−( =1
( . ) . )
Location of intake
ℎ = + 2 = 1.2 + 2 × 0.18 = 1.56
D=Diameter of conduit
Gates
The form of a reservoir outlet works will vary considerably with the type of dam and
the purpose of the reservoir. Each installation consists of a conduit through which or
under the dam or the abutment with suitable control valves or regulate to the flow.
i. The outlet should be hydraulically smooth pipe when full open in order to pass the
maximum discharge.
ii. When opened partially sufficient air should be admitted to present vibration and
cavitations.
iii. The whole arrangement should be simple, rigid, and economical and facilitate
easy inspection and maintenance.
Bulk head gate is usually located at the upstream end of outlet conduits in order to
shutoff flow and is subject to relatively high heads .bulk head gates are kept fully
opened or fully closed.
Regulating gates are used for regulating flow water .This is operated under unbalanced
head condition and is designed to be operated at any opening.
A/ General Arrangement
Girders form vertical divisions of trash rack. These divisions are known as panels. The
dimensions of panels are determined by the possible of transport and handling. Each
panel consists of the following.
A system of rigid frame for small grills and the fixing plates for the big areas
A system of vertical bars generally of rectangular section
A series of horizontal pieces, the functions of which is of prime importance
These are intermediate supports for the vertical bars besides distributing the load
It gives protection to the bars against vibration. These are keeping 400mm - 500mm
apart.
Adoption of higher value of design head will make the structure uneconomical, while its
lower value might make it unsafe.
V 0.075√2
For this project, the trash rack is designed so that the approach velocity (Va) is in
between 0.6 to1.5 m/s. we take the average of this equals to 1.0 m/s.
E/ Racks
I. Bar thickness
Thickness of bars is usually from 6mm to 25mm.For Hare river hydro project take the bar
thickness 25mm.
6 50 42 32 29 24
10 75 60 47 40 35
12 100 80 63 55 45
20 150 115 100 82 65
25 175 145 125 112 88
For thickness, 25mm and velocity 1.0 m/s calculated above, the length of bars from
above table would be 145cm.
III. Spacing
Trash rack have usual inter spacing of 100 to 500 mm. The experimental
recommendation is:
t= thickness of bar
≤ 10, ≤
10
100
≤ , 10 ≤ 25 !
10
The functions are 1) to nullify vacuum effect, this creates when the penstock drain after
control gate closed and 2) intake gates operate under condition of balanced pressure on
both sides of the gate. Thus, the conduit is required to be filling with water through a by-
pass line.
= 400 .
Where =discharge of air in m3/s,
C=7
USBR’S design guide: capacity of air vent 25% of conduit discharge and
allowable air velocity in air vent is between (40-90) m/s, so take 40m/s.
= 25%
. ⁄
Area of air vent = = = =
.
= 11.6 = 12 Therefore, the size of an air vent is
12cm.
8.3.1Power Canal
Power canal can be lined or unlined. The line canals usually lined with impervious
material such as concrete, masonry or clay. In the proposed project, concrete lined
canal selected since canal lining carried out to reduce seepage losses, reduce canal
surface roughness, prevent the growth of weeds, reduce damage caused by erosion,
rodents & livestock, and reduce the required volume of excavations.
Canal Design
Canal power design involves determination of velocity of water, roughness coefficient,
slope and cross-sectional of the canal.
I Velocity
The flow velocities in the canal or other water conduits in general are determined
according to economic point of views (investments, head loss, wear & tear of the
material, danger of erosion and silting).The velocity must be high enough to prevent bed
erosion for unlined and wear by abrasion for lined canals.
For this particular, the flow velocity takes 1.2 in concrete lined power canal.
II Roughness coefficient
The rougher the material, the more frictional loss and the greater the head drop or slope
needed for the given velocity. The roughness coefficient (n) for concrete lining ranges
from 0.010 to 0.020, take 0.015.
. .
= ⁄
= . ⁄
⇒ = 0.0012
The slope found from the above equation should nearly coincide with the available
natural topography.
IV Cross-Sectional Profile
The material in which the canals construct generally dictates its cross-sectional profile.
The common cross-sections canals are semi-circular (most efficient profile but
impractical to excavate), trapezoidal section (most widely used profile for both lined and
unlined canals excavated in earth) and rectangular section (most appropriate when
excavation is undertaken in firm rock).In this project, trapezoidal section is selected.
( )= + 2√2
= , = 0.5
( + )
0.5 = ⇒ = 0.8282
+ 2 √2
.
= = 1.414 =( + ) ⇒ = 0.8795 & b=0.73m
.
The parameter of power canal cross-section giving some freeboard allowance (0.15-
0.7m) is 0.8 × 1.5 .
8.4 Forebay
A forebay is a basin located at the end of power canal just before the entrance to the
penstock or pressure shaft. It is called ahead pond. It acts as a transition between
power canal and the penstock. It is formed by simply widening the power canal at the
end.
805
= = = 670.833 ≈ 671 .
1.2
A rule of thumb is to submerge the penstock mouth by a distance below water the level
of more than 4 times the penstock diameter. This is to prevent air being drawn in to the
pipe because of a vortex, which can be formed, on the surface if the penstock is closer
to the surface.
1136
= = = 25
× 10 × 4.5
1.6923
= = = 0.0376 ⁄
10 × 4.5
ℎ 25
= = = 664.89 = 665
ℎ ℎ 0.0376 ⁄
2
=
− 1
2
.
Lt= ×2= × 2 = 9.2
× ×
=
× −( − )∗
10 × 0.8 × 9.2 73.6
= =
9.2 × 10 − (10 − 0.8) × 92 − 9.2
X(m) 0 2 4 6 8 9.2
Bx(m) 0.8 1 1.33 2 4 10
8.5 Penstock
The penstock carries water from the headrace tunnel to the turbines within the least
possible loss of head consistent with the overall economy of the project. There may be
pressure conduit or shaft. The penstock used for the project is made of steel because of
the available high head.
Factors that must consider for choice of material for pressure tunnel are head,
topography and discharge. Various material used are steel, R.C, asbestos, cement, PVC,
etc. but the following have to also be considered when deciding to use for. These are
required pressure, design life etc. steel penstock become the most common type of
installation in hydropower development due to simplicity in fabrication, strength, and has
long life etc. hence considering the above steel penstock selected for this particular
project.
investment will get higher, therefore a size, which gives least cost selected. The
permissible velocity for ranges from 3 5 ⁄ .we adopts 4.0 ⁄ velocity.
.
792.217
= 0.62 × .
= 1.082
35.1217
Where H= − . = 35.1217
× . × .
P=0.62 = 792.217
2- USBR
V=0.125 2 ℎ
Q D2
A= = *
V 4
D =0.656m
3) P.J.BIER’S
.
D=0.176( ) = 0.75185
penstock and the operating pressure it will experience during its use i.e. the head of
water above the penstock and water hammer pressure during sudden opening and
closure of turbine.
=
2
ℎ =
t- Thickness of penstock
2.18 × 10 4
ℎ = × = 602
1000 9.81
= 680.1217 KN/m2
If > 20
. × .
≥ ≥ = 1.6 ⇔ = = 438 >>> 20 !
× × . .
= 1.2 ⁄
= 0.04( ℎ )
Hydraulic radius(R) =
.
From continuity = = = 1.41
.
.
= = 0.903 ; ℎ( ) = 0.75 × 0.903 = 0.677
.
.
= = = 0.513
⁄ × ⁄ . ⁄ ×
To determine bed slope use Manning’s equation = = 1.2 = ⁄
.
Slope =0.0058 =
Therefore adopt a tailrace channel width (b) =1.37m, depth(y) =1.027m length (l) =65m.
8.7 Valves
Valves are controlling structure installed at different points where the flow is to be
regulated and controlled. For the particular system a valve is needed at the entry of the
penstock prevent the back flow of water from the turbine in times when the units are not
functional.
A butter fly valve is recommended to be provided just upstream of the turbine as its
primary use is as service or guard gate in the power penstock.
1. Entrance loss
∆ℎ = × Where: Kt = 0.3 for bell mouth entry.
V= 1m/s
1
∆ℎ = 0.3 × = 0.015
2 × 9.81
1
∆ℎ = 2.4 × ( ) × sin 65° = 0.017
2 × 9.81
.
= = 0.2 × = 0.023m where = 0.2
× .
4. Transition loss
. . .
= + = 0.16 × + = 0.053
× . × .
= Velocity in canal
= . 16 (Expansion coeffient)
. .
= = 0.16 = 0.012
× .
= = 0.03 × = 0.025
× .
V=velocity of penstock
7 Penstock loss
0.011 × 218 × 4
ℎ = = = 2.8
2 2 × 9.81 × 0.7
ℎ = ⁄
, = 0.018(
Diversion tunnel
A 10 years return period flood is taken as a design flood for designing the cofferdam
from the upstream irregular channel the rating curve river channel corresponding water
surface elevation with certain freeboard is height of coffer dam
The maximum flood flow for a return period of 10 years calculated by using log Pearson
type III
log = log +
= 16.766 /
Diversion tunnel can be design for the design discharge by using the recommended
velocity of flow of water through the tunnel. The velocity depends on whether the tunnel
is lined or not. For unlined tunnel 2 to 2.5 m/s and for concrete line tunnel 4 to 5 m/s are
often recommended.
After completion of the construction work of the project, the diversion tunnel may be filled
with soil or covered. Therefore, for hare hydropower project, unlined tunnel with maximum
allowable velocity of 2.5m/s is assumed 2.5m /s .Therefore,
= ×
Therefore, one diversion tunnel having 3m is provided for diversion tunnel upstream of
the dam.
Cofferdam
A cofferdam is a temporary dam or barrier used to divert the stream or to enclose an
area during construction. The design of an adequate cofferdam involves the problem of
construction economics. The cofferdam must be designed that it is not only safe, but
also of the optimum height.
For the design of the cofferdam, the height of the coffer dam is taken as sum of the
diameter of the tunnel and some allowance for free board.
For Hare, the upstream cofferdam has 5.5m height and slope may be taken as 2H: 1V. It
is constructed partly by using tunnel rock spoil from the excavation of the diversion tunnel
and impermeable material from the overburden excavation.
9.1 General
The powerhouse is the conspicuous and vital part of hydroelectric development. The
basic objective of the powerhouse planning is to house all the equipment suitably in
structural complex, which call as the powerhouse. The basic requirement of the
powerhouse is its functional efficiency coupled with aesthetic beauty therefore,
harmonization with the surrounding is very necessary. The option of setting a power
house whether it was surface or underground power house is dictated by the relative
merits of the possibilities have to be weighed before the choice is made. In addition, the
choice largely dictates by economic and geologic considerations.
B/ The net head it is the gross head minus the sum of all the losses arising from trash
racks, pipe friction, bends and valves. The net head is the available head to drive
turbines.
Hydraulically available power to the turbine (P) is the product of available head,
discharge and unit weight of water.
H= available head
o Reaction turbine
o Impulse turbine
o Reaction turbines: In this type of turbine, the water enters the turbine in a
circumferential direction in to the scroll case and moves in to the runner through a
series of guide vanes, called wicket gates. The available energy partly converted to
kinetic energy and substantial magnitude remains in the form of pressure energy.
Some examples of reaction turbines are Francis, Kaplan, Propeller, Bulb, etc.
o Impulse turbine: All the available potential energy converts in to kinetic energy with
the help of contracting nozzles. The water after impinging on the curved vanes or
bucket is discharged freely to downstream channel. Example for this type of turbine
is pelton wheel.
I Specific speed
The specific speed, Ns, of a turbine is the most important characteristic, & is part of
paramount importance in design. It is defined as the speed at which geometrically
similar runner would rotate if it were so proportioned that it would develop 1 KW when
operating under a head of 1 meter, and is given by
N P
Ns=
H 5/ 4
Where: NS = specific speed
N = rotational speed (rpm)
P = power developed (kW)
H = effective head (m)
Low specific speed turbine 11-43rpm
= = = 192.4
√ √ .
= = 185.5
√
o Moody formula
= + 83.6 = 161.6
.
= = 174.2
√
= . = 190.9
×
= = = 750
×
=
√
. × . ⁄
=( ) =( ) = 3.16
.
Number of unit= = = 0.4 ≅ 1
.
I Head maximum net head acting on turbines are an important consideration in the
selection of type of turbine for a power plant.
II Specific speed it is defined as the speed at which a geometrically similar runner would
rotate if it were so proportional that it would develop 1 KW when operating under
a head of 1m.
⁄
= 0.036 = 0.57
The table below shows various values of , , and efficiency ( ) for the three main
types of turbines.
Q = discharge = 1.6923
o According to Desiervo and Deleva (1976), the following equation for Francis
turbine runner is used.
78.1217
= (26.2 + 0.211 )√ = (26.2 + 0.211 × 121) √ = 0.592
750
Therefore by taking the average of the above values as the outer diameter
. . .
= = 0.586 ≅ 0.6
Entrance diameter
√
= 84.6 = 0.62
According to F.de Sierico and F.de Leva (1976) (water power July 1975)
. .
= (1.2 − ) = 0.62 = (0.89 + ) = 1.04
. .
= (1.1 + ) = 0.95 = (0.79 + ) = 0.9
.
= (1.32 + ) = 1.09
= (0.1 + 0.00065 ) = 0.11
.
= (1.5 + ) = 1.2
= (0.88 + 0.00049 ) = 0.56
.
= (0.98 + ) = 0.95 = (0.6 + 0.00015 ) = 0.37
.
= (1 + ) = 1.3
o To recover as much as possible of the velocity energy of the water leaving the
runner, thus increasing the dynamic draft head.
o To utilize the vertical distance between the turbine exit and the tail water level,
called static draft head.
The dimension of the draft tube is calculated according to F.de.siervo & F. de. Leva
(1976) formula used for design of draft tube.
= 8.74 + = 10.92
.
1) = (1.54 + )=2 6) = = 3.66
. .
. .
4) = 0.58 + = 0.47 9) = (1.1 + ) = 0.94
. .
5) = (1.6 − ) = 0.96 10) = (2.63 + ) = 1.76
o It is more compact and needs less floor area for power house
o The design of hydraulic passages is simpler in vertical arrangement.
o Above heads of 25m, a vertical arrangement gives cheaper solutions.
= =atmospheric pressure
= vapor pressure
H= effective head
=Thomas’s factor (sigma)
=Turbine centerline from the TWL
− = =barometric pressure (which is usually taken to be about 10m)
. = − ---------------Thomas’s formula
Determination of sigma ( )
I). E. Mosonyi’s formula
( ) = 0.0432( ) = 0.056
a) = ≥ 180
.
b) = = 0.043 < 180
Electrical equipments
- Generator
- Exciter and voltage
- Regulator Transformer
- Control room equipment including switch
Mechanical equipments
- Shaft, bearings, coup lings, etc for the generator
- The oil circuits and pumps
- Compressors and pumps
- Cranes and other lifting equipments
Besides the above, auxiliary equipments for the powerhouse lighting, water supply and
drainage needed.
9.10.1 Generator
The generator is an electrical machine coupled to the turbine shaft. The mechanical
energy produced by the turbine is changed in to electrical energy by the generator. The
sizes of the generator vary depending on their rating & on their shaft arrangements
(either vertical or horizontal).
J.H walker has given elaborate curves and relations to determine the dimensions of the
generators. The relations will be as follows.
32.5
= ( + ) = 2.38 ≅ 2.5 ( )
62
= +2 =2+2=4
- Arrangement of shaft
- Overhead erection crane and its minimum requirement
- The dimensions of individual units
- Dimension of erection bay
- The number of units
The three essential constituents of powerhouse are
o Unit bays housing the main turbine and generator.
o Control bays housing the main control and their equipments.
o Service and erection bays provided for handling erection and maintains of
main machines.
A/Unit Spacing
i. E.Mosony’s Formu
= (5.5 − ) = 3.98 ≅ 4
100
ii. J.J.Donald’s Formula
= (3.5 6) = 4.75 × 0.6 = 2.85
iii. N.Venkata Rows Formula
= (3.8 5) = 2.64
Therefore, take the largest value with some allowable clearance of 2.25m. The unit
spacing is 6.25.
B/Length
The length of the machine hall depends on the number of units and the size of the
machine. The preliminary dimensions between center to center of one unit is L = 6.25m
Hence, the total length: LT = 1 unit + 1 unit for erection bay + 1unit for control room
= 3 units
LT = 3 × 6.25 = 18.75 ≅ 19
C/Width
The width of the machine hall is determined by the size and clearance spacing between
the wall needed as a gantry way.
i. According to U.S.B.R, the width of the power house can be calculated as;
131
.4
W =F+C+2+1.85D Where: F = D (1+ ) =7.77m
NS
.
C = D (1.32+ ) =2.35m
= 4.25m
D/ Height
The height of the machine hall is fixed by the headroom requirement. The hall must
have a height, which will enable the crane to lift the rotor of the generator or the runner
of the turbine clear of the floor without any abstraction. To this clearance, space is to be
added the depth of crane girder, and the headroom for the operating cabin.
H=6.25+4+2+4.5 = 15m
Therefore, the size of the powerhouse will be, L= 19 m, W= 13.3 & H=15m
10.1 General
EIA is the process of predicting the consequence and ways of human development by
planning appropriate measures to eliminate or reduce the adverse effect of any project.
It also identifies the potential problems and outlines the ways to improve the project
suitability for the proposed site.
The development of any water resource project is to improve the quality human life and
the conservation of the natural environment, which is indicator of the level of one
countries’ development.
The strategy for small hydropower development relies on clean recycling and use of
renewable resources with the minimum cost to protect the existing impact.
Generally, EIA predicts problem, find the ways to avoid them or reduce it and enhance
the positive effects of the project by providing a unique opportunity to demonstrate ways
in which the environment may be improved on apart of development process.
Water quality
The quality of natural water varies considerably and this contribute to the diversity of
species in to habitat found in fresh water when human activity modify the chemical
environment to the extent that strays out to the side the natural range for the river
damage to a fresh water community is most likely to occur.
Ground water
The change and the variation of the water level by the reservoir operation will change
the ground water in the surrounding area. The change in flow on dam stream
watercourse may also lead to ground water changes. The change in ground water may
influence the supply of drinking water.
During power generation, the river is diverted to somewhere required. As a result, the
amount of water in the river will decrease. The water required for irrigating the
surrounding farmland specially banana that requires too much water would be affected.
As the water joins Lake Abaya, the lives in the river such as hippopotamus and
crocodile are affected.
i) Terrestrial ecology
Hare hydropower cause loss of natural vegetation available in those sites due to
construction of the dam, access roads, powerhouse, access tunnels etc. In addition,
operation of quarries for selected materials, construction equipment and disposal of
wastes generated from tunneling and dam foundation will affect certain areas of natural
vegetation.
The area to be taken for strong water, which will be cleared before reservoir filling will be
an important loss of wild life habitat.
During the construction of dam, lots of activities such as undesirable noises, air
pollution due to the vehicle and machineries and some others should be properly
considered and adequately responded by the design and construction engineers. In
addition, it affects the flora and fauna, causes soil and water pollution and health
problem.
11.1 General
Economic analysis of hydropower project concern measuring the benefit from the
development and the cost expended. In the context of hydropower planning, benefits
are the service produced by the development and costs are the goods used in
constructing and maintaining the development. An economic analysis is necessary to
determine whether the project is worth building or to determine the economic size of the
development or the components of the development.
The total cost of the project is been estimated as follows depending on the bill of
quantities and their corresponding unit rates. This tabular description of cost should be
analyzed from each structure parametrically.
2 Spillway
i. Top excavation M3 7358 8 58864
ii. Chute spillway section m 292 2280 665760
3 Intake structure
i. Trash rack Kg 270 8 2160
ii. Air vent M3 18 88 1584
iii. Volume of concrete M3 284 150 42600
iv. Valves 3 2260 6780
v. Reinforcement Kg 11187 8 89496
vi. Foundation masonry work M3 32 200 6400
vii. Other hydraulic steel work 20000
4 Conveyance structure
i. Power canal excavation M3 2777 8 22216
ii. Concrete for canal lining M3 438 250 109500
iii. Fore bay excavation M3 1125 8 9000
iv. Concrete for fore bay M3 69 250 17250
v. Penstock m 193 1700 328100
5 Diversion structures
Excavation for coffer dam M3 2700 8 21600
Diversion tunnel work m 370 470 173900
6 Power house
i. Excavation M3 980 250 245000
TOTAL 12374624
i(1 i) n
CRF=P n Where i= annual interest rate =10% (assumed)
(1 i) 1
0.1(1 0.1) 20
CRF= = 0.1175
(1 0.1) 1
20
= 0.1175 × 12374624
= 1454018.32
= 0.02*1454018.32
= 29080.3664
= 1.05 *29080.3664
=30534.3847
= 4274880 Birr
= = 2.824
. . .
Since B/c ratio is greater than one the project is economically feasible.
12.1 Conclusion
The design of Hare Hydropower Project based on the utilization of Hare River flow.
12.2 Recommendations
In this project, since there is no any sediment data, we make rough estimation.
But, since it has great effect on the design of the hall hydraulic structures, directly
or indirectly, there should be detail and accurate sediment data.
Since the reservoir created by the implementation of the project may facilitate the
spread of the diseases in the area, appropriate heath care services and creation
of awareness for controlling the diseases has to be established with the
implementation of the project. And also appropriate protection measures should
be taken for other impacts of the project as much as possible
The estimated cost is obtained by rough analysis, which need further detail
quantity surveying
To have efficient use of water and to keep the structure in good condition, the
owner of the project should have to manage it appropriately
Afforastation should be seriously done for protection of erosion to protect
sedimentation of the reservoir easily.
Facilitation of fish husbandry and recreational centers should be carried out
Some parts of the lands near the site are rain fed lands due to its topography, but
from this structure, it is easy to irrigate that land, if the government or any other
concerned sectors think about it
REFERENCES:
1. Chow, V.T (1988), Applied Hydrology.Mc Graw-Hill Book Company, Singapore.
2. Garg, S.K (1979), Irrigation Engineering and Hydraulic Structures.Khanan
publishers, New Delhi.
3. Sharma, K.N (1999), Water Power Engineering. Vikas Publishers.House
PVT.LTD, NewDelhi.
4. Subramanya,K(1984), Engineering Hydrology.Mc Graw-Hill
Publishers.Company Ltd, New Delhi.
5. Adam Harvey (1993),Micro-Hydro Design Manual, Sontramgton row, London
4CIBHH,UK.
6. P.Novak, A.I.B.Moffat, C.Nelluri & R.Nayayan ;( 1996), Hydraulic Structures
(4 ) E& FN Spon, London.
7. M.M Pandeker and K.N.Sharma; 1979 Water Power Engineering, Vikas Publish
house P VT New Delhi.
8. Rozgar Baban; 1995, Design of Diversion Weirs, J ohnwiley and sons,
Newyork
9. Abbet R.W(1963), Engineering Cotracts and Specifications, Johnwilley and
Sons, Newyork
10. John Giasson ,Riki Therivel, Andrew Chadwick(1994),Introduction to
Environmental Impact Assessement .UCL Press, L ondon.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1980 0.652 0.573 0.549 2.02 3.096 1.66 1.533 1.527 1.611 1.305 0.984 0.752
1981 0.62 0.627 1.106 1.99 2.006 1.171 1.857 2.017 2.602 2.124 1.347 0.926
1982 0.803 0.751 0.715 1.338 2.226* 1.209* 1.463* 2.035 2.157 3.333 2.04 1.551
1983 1.042 0.937 0.8 2.044 3.938 2.765 2.777 3.429 3.417 3.885 3.002 2.333
1984 0.272 0.166 0.169 0.235 2.399 3.254 1.051 1.666 2.725 2.084 1.19 0.746
1985 0.431 0.348 0.493 1.048* 1.936* 2.103 3.081 2.246 1.805 1.755 0.994 0.557
1986 0.409 0.642 0.917 1.855 3.691 5.582 2.587 2.233 5.874 2.902 1.526 3.227
1987 1.194 0.97 1.702 4.097 4.774 3.028 1.843 2.482 1.959 2.745 1.833 1.262
1988 1.189 1.258 0.963 2.074 3.103 2.461 4.607 4.261 3.695 3.937 1.761 1.185
1989 1.013 1.635 1.459 2.778 3.181 2.134 3.004 2.405 3.407 3.688 1.333 1.988
1990 1.229 1.882 2.042 2.199 1.323 0.871 0.912 1.817 1.017 0.944 0.557 0.34
1991 0.428 0.234 0.54 0.494 2.066 1.284 1.733 0.95 1.657 0.865 0.529 0.371
1992 0.273 0.288 0.207 0.992 1.033 1.517 1.378 1.408 2.341 4.103 2.142 1.128
1993 2.229 3.228 1.282 2.009 4.37 2.585 0.507 0.097 5.053 4.504 3.216 2.479
1994 0.366 0.309 0.338 0.599 2.442 1.801 2.358 3.327 1.779 1.733 1.545 1.023
1995 0.81 0.777 0.946 2.009 2.071 1.922 1.957 2.199 1.835* 1.843* 1.454 0.975
1996 0.705 0.614 0.873 1.894 5.601 3.688 2.435 2.945 2.986 1.948 1.357 1.135
1997 1.025 0.843 0.832 1.603 1.878 1.636 3.22 2.641 1.679 4.197 2.854 1.476
1998 1.48 0.847 0.776 0.632 1.066 0.878 1.272 1.421 1.187 2.299 1.309 0.752
1999 0.541 0.443 0.533 0.641 0.729 0.781 1.073 1.428 1.361 2.55 1.203 0.811
2000 0.599 0.506 0.413 0.918 2.147 1.245 1.772 2.284 1.933 2.632 1.86 1.034
2001 0.689 0.641 0.797 1.122 1.213 1.131 0.874 1.293 1.049 1.494 1.394 1.11
2002 1.051 0.995 1.089 1.331 1.294 1.194 1.242 1.439 1.246 1.278 1.17 1.192
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1980 0.787 0.685 0.685 5.134 4.319 2.472 2.126 2.371 2.371 1.662 1.32 0.893
1981 0.685 1.042 2.574 3.325 4.815 1.574 3.782 3.214 3.899 2.996 2.174 1.042
1982 0.893 1.445 1.889 2.996 3.536* 2.191* 2.828* 2.835 3.551 4.752 4.137 2.322
1983 1.119 1.042 1.08 21.152 5.994 6.337 4.38 6.756 5.069 5.927 4.878 3.214
1984 0.382 0.25 0.279 0.462 14.869 13.379 1.886 3.719 5.542 4.047 1.886 1.412
1985 0.552 0.506 1.327 2.494* 7.349* 2.576 22.367 4.757 5.14 2.974 2.452 0.707
1986 0.421 1.021 3.408 4.047 9.78 10.691 3.719 4.946 18.156 5.14 2.214 14.112
1987 1.639 1.398 7.945 7.768 8.48 5.889 2.481 5.317 2.755 5.479 2.964 1.578
1988 2.213 2.413 1.109 3.614 6.813 3.912 10.414 9.298 10.039 5.236 2.548 1.398
1989 1.701 4.838 5.806 4.292 6.221 2.617 5.398 3.394 6.643 13.727 2.481 4.68
1990 3.178 4.759 3.837 4.369 2.686 1.517 1.28 3.467 1.578 1.578 0.889 0.889
1991 1.826 0.784 0.998 0.682 5.156 2.964 3.25 2.018 2.617 1.165 0.836 0.442
1992 0.311 0.442 0.442 4.838 2.617 3.25 2.617 2.018 3.322 7.856 5.642 2.617
1993 5.806 6.985 2.279 5.317 12.534 5.889 0.784 0.23 8.211 6.643 4.063 2.686
1994 0.39 0.346 0.669 1.935 4.898 5.2 3.761 5.139 3.87 2.743 2.37 1.169
1995 0.906 1.42 1.65 3.035 5.139 3.135 2.936 3.548 3.124* 3.140* 1.852 1.135
1996 0.814 0.726 1.893 7.015 11.481 5.824 3.391 4.839 3.87 2.236 1.572 1.169
1997 1.068 0.969 1.77 3.761 3.495 2.28 4.202 4.545 2.192 9.564 6.277 2.062
1998 1.852 1.239 1.383 0.726 1.935 1.458 1.852 2.192 1.935 3.339 3.548 0.969
1999 0.614 0.46 1.002 1.458 1.101 1.347 1.496 1.77 1.73 4.09 1.69 0.937
2000 0.669 0.561 0.46 3.979 8.215 2.648 2.507 3.87 2.936 4.146 2.936 1.275
2001 0.731 0.688 1.897 1.997 1.782 1.67 1.024 2.037 1.284 4.833 2.058 1.179
2002 1.15 1.051 1.495 1.8 1.616 1.347 2.142 1.581 1.379 1.478 1.363 1.937
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1980 0.588 0.526 0.466 0.496 2.174 1.198 1.198 1.158 1.279 1.08 0.857 0.652
1981 0.557 0.526 0.526 1.32 1.445 1.042 1.042 1.445 1.707 1.488 1.042 0.857
1982 0.718 0.652 0.62 0.787 1.395* 0.917* 1.037* 1.488 1.488 1.707 1.445 1.158
1983 0.967 0.822 0.718 0.718 2.223 1.889 1.843 2.174 2.272 2.472 2.03 1.752
1984 0.222 0.113 0.151 0.151 0.131 1.167 0.823 1.021 1.093 1.021 0.886 0.506
1985 0.345 0.279 0.345 0.665* 1.122* 1.686 1.686 1.021 1.021 0.886 0.652 0.462
1986 0.382 0.382 0.707 0.707 1.327 1.886 2.101 0.823 1.5 1.886 1.167 1.093
1987 0.998 0.889 0.889 2.481 2.082 1.953 1.578 1.398 1.578 1.889 1.398 1.109
1988 0.998 0.998 0.836 0.836 1.953 1.701 2.213 1.889 1.889 2.686 1.398 0.998
1989 0.889 0.836 0.889 2.082 1.889 1.701 1.953 1.889 2.213 1.578 0.889 0.998
1990 0.682 0.632 0.998 0.998 0.682 0.733 0.682 1.165 0.733 0.583 0.353 0.192
1991 0.155 0.155 0.192 0.353 0.998 0.583 0.442 0.682 1.109 0.682 0.397 0.27
1992 0.23 0.23 0.12 0.27 0.583 0.583 0.682 0.889 1.109 2.279 1.053 0.784
1993 0.682 1.517 0.889 0.784 2.148 0.682 0.23 0 0 3.394 2.755 2.279
1994 0.324 0.263 0.283 0.283 1.101 1.383 1.611 2.062 1.347 1.383 1.169 0.906
1995 0.726 0.697 0.784 0.814 1.169 1.496 1.42 1.811 1.259* 1.263* 1.169 0.814
1996 0.641 0.561 0.535 1.034 2.887 2.601 1.977 2.062 2.28 1.572 1.169 1.068
1997 0.969 0.754 0.726 0.844 1.002 1.347 1.852 1.852 1.347 2.105 1.496 1.239
1998 1.239 0.697 0.561 0.587 0.587 0.726 0.875 1.034 0.906 1.611 0.969 0.561
1999 0.485 0.413 0.436 0.485 0.587 0.561 0.561 0.697 0.969 1.69 0.937 0.726
2000 0.561 0.46 0.368 0.413 0.969 0.844 1.239 1.383 1.534 1.811 1.239 0.814
2001 0.657 0.617 0.607 0.895 0.945 0.87 0.811 1.038 0.945 1.121 1.193 1.051
2002 1.011 0.971 0.984 1.051 1.193 1.15 1.15 1.3 1.15 1.193 1.079 1.024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1980 8.233 6.778 6.933 24.702 39.119 20.299 19.362 19.289 19.696 16.49 12.036 9.505
1981 7.833 7.16 13.977 24.331 25.347 14.312 23.459 25.483 31.818 26.833 16.468 11.694
1982 10.149 8.57 9.038 16.354 18.3** 17.32** 22.11** 25.714 26.376 42.106 24.945 19.593
1983 13.171 10.691 10.105 24.989 49.754 33.802 35.089 43.323 41.777 49.083 36.7 29.479
1984 3.435 1.962 2.14 2.872 30.315 39.779 13.275 21.044 33.312 26.331 14.548 9.427
1985 5.443 3.968 6.227 5.44** 5.34** 25.706 38.931 28.381 22.072 22.172 12.156 7.031
1986 5.173 7.328 11.585 22.677 46.629 68.252 32.679 28.214 71.812 36.669 18.657 40.768
1987 15.091 11.071 21.501 50.097 60.321 37.021 23.279 31.355 23.948 34.686 22.416 15.938
1988 15.026 14.873 12.165 25.353 39.197 30.094 58.206 53.833 45.174 49.741 21.529 14.97
1989 12.797 18.656 18.438 33.962 40.187 26.094 37.953 30.38 41.657 46.597 16.301 25.115
1990 15.528 21.472 25.797 26.892 16.71 10.651 11.52 22.951 12.434 11.932 6.812 4.298
1991 5.409 2.669 6.825 6.039 26.107 15.701 21.892 12.002 20.262 10.935 6.473 4.688
1992 3.443 3.399 2.617 12.134 13.051 18.545 17.41 17.782 28.622 51.842 26.193 14.251
1993 28.156 36.838 16.194 24.562 55.205 31.603 6.403 1.229 61.784 56.9 39.324 31.319
1994 4.628 3.523 4.266 7.318 30.847 22.018 29.794 42.03 21.755 21.9 18.884 12.922
1995 10.232 8.862 11.951 24.566 26.168 23.498 24.722 27.784 23.12** 22.08** 17.772 12.319
1996 8.904 7.253 11.034 23.161 70.768 45.087 30.77 37.208 36.51 22.08 16.593 14.343
1997 12.949 9.62 10.517 19.602 23.726 20.002 40.684 33.366 20.526 22.08 34.896 18.653
1998 18.695 9.665 9.803 7.722 13.468 10.729 16.075 17.948 14.51 22.08 16.002 9.503
1999 6.838 5.059 6.732 7.842 9.209 9.55 13.561 18.039 16.641 22.08 14.71 10.247
2000 7.573 5.986 5.212 11.22 27.125 15.225 22.384 28.854 23.632 22.08 22.736 13.061
2001 8.699 7.314 10.065 13.72 15.326 13.825 11.042 16.332 12.823 22.08 17.044 14.028
2002 13.284 11.349 13.759 16.277 16.345 14.597 15.688 18.175 15.235 22.08 14.305 15.063
2.632 1 46 17.29323308
2.602 1 47 17.66917293
2.587 1 48 18.04511278
2.585 1 49 18.42105263
2.55 1 50 18.79699248
2.482 1 51 19.17293233
2.479 1 52 19.54887218
2.461 1 53 19.92481203
2.442 1 54 20.30075188
2.435 1 55 20.67669173
2.405 1 56 21.05263158
2.399 1 57 21.42857143
2.358 1 58 21.80451128
2.341 1 59 22.18045113
2.333 1 60 22.55639098
2.299 1 61 22.93233083
2.284 1 62 23.30827068
2.246 1 63 23.68421053
2.233 1 64 24.06015038
2.229 1 65 24.43609023
2.226 1 66 24.81203008
2.199 2 67 25.18796992
2.157 1 68 25.56390977
2.147 1 69 25.93984962
2.142 1 70 26.31578947
2.134 1 71 26.69172932
2.124 1 72 27.06766917
2.103 1 73 27.44360902
2.084 1 74 27.81954887
2.074 1 75 28.19548872
2.071 1 76 28.57142857
2.066 1 77 28.94736842
2.044 1 78 29.32330827
2.042 1 79 29.69924812
2.04 1 80 30.07518797
2.035 1 81 30.45112782
2.02 1 82 30.82706767
2.017 1 83 31.20300752
2.009 2 84 31.57894737
2.006 1 85 31.95488722
1.99 1 86 32.33082707
1.988 1 87 32.70676692
1.959 1 88 33.08270677
1.957 1 89 33.45864662
1.948 1 90 33.83458647
1.936 1 91 34.21052632
1.933 1 92 34.58646617
1.922 1 93 34.96240602
1.894 1 94 35.33834586
1.882 1 95 35.71428571
1.878 1 96 36.09022556
1.86 1 97 36.46616541
1.857 1 98 36.84210526
1.855 1 99 37.21804511
1.843 2 100 37.59398496
1.835 1 101 37.96992481
1.833 1 102 38.34586466
1.817 1 103 38.72180451
1.805 1 104 39.09774436
1.801 1 105 39.47368421
1.779 1 106 39.84962406
1.772 1 107 40.22556391
1.761 1 108 40.60150376
1.755 1 109 40.97744361
1.733 2 110 41.35338346
1.702 1 111 41.72932331
1.679 1 112 42.10526316
1.666 1 113 42.48120301
1.66 1 114 42.85714286
1.657 1 115 43.23308271
1.636 1 116 43.60902256
1.635 1 117 43.98496241
1.611 1 118 44.36090226
1.603 1 119 44.73684211
1.551 1 120 45.11278195
1.545 1 121 45.4887218
1.533 1 122 45.86466165
1.527 1 123 46.2406015
1.526 1 124 46.61654135
1.517 1 125 46.9924812
1.494 1 126 47.36842105
1.48 1 127 47.7443609
1.476 1 128 48.12030075
1.463 1 129 48.4962406
1.459 1 130 48.87218045
1.454 1 131 49.2481203
1.439 1 132 49.62406015
1.428 1 133 50
1.421 1 134 50.37593985
1.408 1 135 50.7518797
1.394 1 136 51.12781955
1.378 1 137 51.5037594
1.361 1 138 51.87969925
1.357 1 139 52.2556391
1.347 1 140 52.63157895
Annex.6 Selection of frequency analysis method that is best suited for our site
Year
Qpeak=X Qp in descending Rank,i
q=(i3/8)/(N+.25) G=P^(i1)*(1-P) W=(1-q)/G Qcomputed
Qpeak
Qpeak in descending order Z=Log(Qpeak)
(Z-Zmean)^2 (Z-Zmean)^3
Month Inflow Inflow Vol Cum.Inflow Demand Dem. volum Cum dem. vol. Difference
Jan 0.428 1.12416768 1.12416768 0.9293 2.440862208 2.440862208 -1.31669453
Feb 0.234 0.61461504 1.73878272 0.9293 2.440862208 4.881724416 -3.1429417
Mar 0.54 1.4183424 3.15712512 0.9293 2.440862208 7.322586624 -4.1654615
Apr 0.494 1.29752064 4.45464576 0.9293 2.440862208 9.763448832 -5.30880307
May 2.066 5.42647296 9.88111872 0.9293 2.440862208 12.20431104 -2.32319232
Jun 1.284 3.37250304 13.25362176 0.9293 2.440862208 14.64517325 -1.39155149
Jul 1.733 4.55182848 17.80545024 0.9293 2.440862208 17.08603546 0.719414784
Aug 0.95 2.495232 20.30068224 0.9293 2.440862208 19.52689766 0.773784576
Sep 1.657 4.35220992 24.65289216 0.9293 2.440862208 21.96775987 2.685132288
Oct 0.865 2.2719744 26.92486656 0.9293 2.440862208 24.40862208 2.51624448
Nov 0.529 1.38945024 28.3143168 0.9293 2.440862208 26.84948429 1.464832512
Dec 0.371 0.97445376 29.28877056 0.9293 2.440862208 29.2903465 -0.00157594
Mo Number Temp. Relative Sun Wind Rainfall PET PET Net PET
nth of days (CO) humidity shine velocity (mm) (mm/day)
(%) (Hr/day) (km/hr)
(mm) (mm)
Jan 1.33 22.4 13.5 11.8 0.682 14.75 297 15.635 5.91 3.25 5.196
Feb 1.36 22.9 13.5 11.9 0.757 13.803 297.4 15.728 6.6 4.15 5.948
Mar 1.52 26 14.3 12.1 0.71 15.148 299.5 16.173 6.9 5.15 6.491
Apr 1.37 23.2 15 12.3 0.598 16.586 297.6 15.766 6.68 3.16 5.754
May 1.30 21.8 15.1 12.4 0.693 16.172 296.5 15.539 6.84 2.54 5.665
Jun 1.29 21.6 14.6 12.5 0.545 14.063 296.4 15.513 5.77 3.53 5.153
Jul 1.26 21 14.3 12.4 0.397 14.343 295.9 15.409 5.22 3.05 4.617
Aug 1.29 21.6 14.7 12.3 0.42 14.37 296.4 15.511 5.5 3.35 4.91
Sep 1.42 21.6 14.9 12.6 0.588 13.916 298.3 15.911 6.23 10.5 7.317
Oct 1.30 21.8 14.5 12 0.555 16.65 296.5 15.534 6.2 2.18 5.099
Nov 1.25 20.7 13.7 11.9 0.658 14.82 295.7 15.367 6 2.31 4.96
Dec 1.26 20.9 13.1 11.7 0.673 13.569 295.9 15.405 5.6 3.06 4.842
t/tp Q/Qp T(hr) DELTA T Inflow (I1+I2)/2 OUT STO. S1/∆t- Q2/2+S2/∆t H
t FLOW Q1/2
0.2 0.075 2.4 2 4 2.604 4.025 0.214739 13115. 1.71428 5.73965 0.04045
0.3 0.16 3.6 2 6 5.447 7.454 1.041555 37581.8 4.69891 12.1529 0.11589
0.4 0.28 4.8 2 8 9.461 11.97 3.030328 76591.7 9.12258 21.0923 0.23619
0.5 0.43 6 2 10 14.48 17.32 6.564638 128232 14.5277 31.8494 0.39543
0.6 0.6 7.2 2 12 20.17 23.01 11.60906 187523 20.2403 43.2485 0.57827
0.7 0.77 8.4 2 14 25.85 28.03 17.64321 247879 25.6061 53.6318 0.76439
0.8 0.9 9.6 2 16 30.2 31.37 23.62154 301112 30.0103 61.381 0.92854
0.9 0.97 10.8 2 18 32.54 33.04 28.33463 339939 33.0464 66.0896 1.04828
1 1 12 2 20 33.55 33.21 31.29155 363195 34.798 68.0085 1.11999
1.1 0.98 13.2 2 22 32.88 31.87 32.51545 372605 35.493 67.3655 1.14901
1.2 0.92 14.4 2 24 30.87 29.53 32.10409 369456 35.2613 64.7923 1.1393
1.3 0.84 15.6 2 26 28.19 26.69 30.47009 356811 34.322 61.0098 1.10031
1.4 0.75 16.8 2 28 25.18 23.68 28.10428 338094 32.9053 56.5826 1.04259
1.5 0.66 18 2 30 22.17 20.5 25.39256 315980 31.1899 51.6894 0.97439
1.6 0.56 19.2 2 32 18.83 16.49 22.47211 291263 29.2171 45.7026 0.89817
1.8 0.42 21.6 2 34 14.14 12.47 19.01785 260593 26.6846 39.1561 0.8036
2 0.32 24 2 36 10.8 9.461 15.40644 226459 23.7495 33.2105 0.69834
2.2 0.24 26.4 2 38 8.123 7.12 12.29598 194849 20.9143 28.0338 0.60086
2.4 0.18 28.8 2 40 6.116 5.28 9.737758 166787 18.2959 23.5757 0.51432
2.6 0.13 31.2 2 42 4.444 3.908 7.662614 142159 15.913 19.8213 0.43838
2.8 0.098 33.6 2 44 3.373 2.988 6.020166 121040 13.801 16.7894 0.37325
3 0.075 36 2 46 2.604 1.951 4.773838 103697 12.0155 13.967 0.31977
3.5 0.036 42 2 48 1.299 0.998 3.686842 87288.8 10.28 11.2782 0.26917
4 0.018 48 2 50 0.697 0.547 2.7267 71386.1 8.55139 9.09796 0.22013
4.5 0.009 54 2 52 0.396 0.312 2.010678 58266.3 7.0872 7.39962 0.17968
5 0.004 60 2 54 0.229 0.114 1.497992 47884.5 5.90163 6.01603 0.14766