Professional Documents
Culture Documents
Acknowledgment
We would like to express our gratitude to all those who help us for the success and
accomplishment of the final project, whose support was either direct or indirect during our
project progress.
We would like to give special thanks to our advisor Efrem Yitbarek, who gave us a complete
and series comments, suggestion and give the direction how to we do the project. We would like
also give tanks for Ahmed Muhamud and Tediross Tafese who gave the data and directions for
the completeness of the project.
Above all, we owe much attribute to the almighty God who gave us a life worth living and the
strength to accomplish this work.
Our thanks will still be incomplete if we did not mention the effort of our friends and classmates
for giving us encouragement, valuable discussions throughout the work of this Project.
ACRONYM
AMC=Anticipated moisture condition
BM=Bench mark
TR=Retention time
Tc= Time concentration
ARF=Areal rain fall
TP= Peak time
MASL=Mean sea level
CN=curve number
D/S = Down stream
D/S HFL= Downstream high flood level
D/S LSL=Downstream lowest score level
D/S TEL =Downstream total energy level
JHC=Jump height curve
SCS-CN = The United States Soil Conservation Service curve number
TWRC =Tail water rating curve
U/S =upstream
U/S HFL= upstream high flood level
U/S LSL=upstream lowest score level
U/S TEL= Upstream total energy level
UTM =universal transfer Mercator
1 TABLE OF CONTENTS
ACKNOWLEDGMENT ........................................................................................................... I
ACRONYM ............................................................................................................................. II
LIST OF FIGURE .................................................................................................................... V
LIST OF TABLE ..................................................................................................................... V
2 INTRODUCTION ........................................................................................................ 1
2.1 Objective of the project .......................................................................................................... 2
2.2 Methodology .......................................................................................................................... 2
2.3 site description ....................................................................................................................... 2
3 HYDROLOGY ANALYSIS ......................................................................................... 4
3.1 Data Availability .................................................................................................................... 4
3.2 Data Consistency Test ............................................................................................................ 4
3.2.1 Rough screening of the data……………………………………………………………………6
3.2.2 Plotting the data………………………………………………………………………………...7
3.2.3 Testing for Outlier………………………………………………………………………………7
3.3 Base Flow Estimation............................................................................................................. 9
3.4 Design Rain fall Computation ................................................................................................ 9
3.5 Design Flood Analysis ......................................................................................................... 15
3.6 Design Storm Analysis ......................................................................................................... 15
3.6.1 Rainfall profile………………………………………………………………………………...16
3.6.2 Run off synthesis………………………………………………………………………………17
3.7 Peak flood analysis ............................................................................................................... 17
3.7.1 SCS unit hydrograph method………………………………………………………………….17
3.7.2 Flood Mark Method…………………………………………………………………………...21
3.7.3 Rational method……………………………………………………………………………….22
4 HEAD WORK DESIGN ............................................................................................ 25
4.1 Head Work Site Selection..................................................................................................... 25
4.1.1 Geology of the area……………………………………………………………………………25
4.1.2 Upstream and downstream of the headwork site……………………………………………...25
4.1.3 Availability of construction materials…………………………………………………………25
LIST OF FIGURE
Figure 1: location of project area ............................................................................................... 3
LIST OF TABLE
Table 1: daily heaviest rain fall data consistency test ................................................................. 4
Table 11: Average Rainfall Intensity in mm per hour Duration, Return period......................... 23
Table 13: The design flood level at river cross section of the weir ........................................... 26
Abstract
Engulie irrigation project is located in Amhara National Regional State,West Gojam Zone, Mech
woreda, Abiyot Fana kebele at 77km from the Regional town Bahir Dar. The GPS location of the
proposed headwork site of the project is about at UTM coordinate of Easting 295269m and
Northing 1251001m.
The project mainly contains hydrological analysis of the project from the metrological data of
Merawi town station. On this part it mainly contains highest rain fall data, Geological data,
Hydrological analysis, Consistency test ,Estimation of peak discharge head work structure and
canal.
Hydrology analysis includes the occurrence of 49 years rainfall data. The peak discharge is
designed by using SCS-CN method which is 146.8559m3/s.
The headwork structure include the weir, under sluice, head regulator, stilling basin and retaining
wall are designed based on peak discharge. The weir type, we should have to consider the
availability of construction materials, peak discharge and the river bed material as well as weir
height. The weir type is ogee weir and the weir height is 1.5m.
The crop water requirement also include in the design part of the project to determine the
maximum water requirement of different types of crop. The Engulie diversion irrigation project
has been proposed to help the society living around the project to be able to produce crops
throughout the year. The command area is located nearby the boundary of the river. The project
is planned to irrigate 52.69ha of land. The maximum quantity of water that the crop requires with
50% efficiency and 18hr irrigated 2.81l/s/ha.
Next to these, main canal profile and dimensions are designed based on the base flow of the
river. Canal dimensions are 0.6m depth and 1m width with trapezoidal cross_ section.
2 INTRODUCTION
General
Irrigation and drainage development is an important sector for agricultural sustainability of a
country. The whole process of the work requires systematic and integrated management to
achieve the ultimate desired goal of agricultural development. Irrigation development process
begins with the preliminary resource assessment of a certain area and then proceeds to the next
more detail processes. From start to the end irrigation development in general requires higher
investment, appropriate technology (traditional and/or modern), skilled manpower and
conducive environment. Apart from such behaviours of irrigation, its roles in agricultural
sustainability are unquestionable and must be practiced at each level of different sectors.
The source of water for irrigation is obtained through abstractions from rivers, springs and
water harvesting schemes. Abstraction of irrigation water from such sources requires also
appropriate study and design for sustainability of its future for the intended purpose. One and
the main irrigation water abstraction method is the use of diversion weirs to raise the level of
water in such a way that the intended command area is incorporated in future irrigation.
Such diversion weirs are sluice gate, canal head regulator retaining wall and other part of
structure may be designed by well qualified engineers at regional and zoned level and also by
woreda levels and even by users traditionally.
However irrigation weir designers working at various levels require adequate data and general
procedure to proceed to the designing. The main purposes of this design guideline is to enable
engulie kebele so that they are able to design smaller weirs usually broad crested weirs either in
local materials or in masonry/concrete following the most acceptable procedures of design. As
indicated above irrigation structures are capital intensive and we must be sure to minimize the
risk of failure and that is following accepted engineering rules/ways.
For the indicated reasons this simple guideline includes all necessary data requirements, steps,
important equations, examples and reasons of selection. However the guideline must be
transferred to the users through a brief training.
2.2 M ETHODOLOGY
In the designing of this final year project on diversion weir we will use the following
procedures:
Data collecting from different sources and we get:
A 49 year highest rain fall data
Geological data
Hydrological analysis
Consistency test
Estimation of peak discharge from the given rainfall data
Flood mark method
Weir designing
Selection of site and weir type
Weir height determination
Stability analysis
under sluice, head regulator and stilling basin
Design retaining wall, pipe culvert, main canal and secondary canal.
Using these methods we analysis and design our proposed wire on engulie River.
(BM-1) of the diversion weir is geographically located at 295269m (UTM) Easting and
1251001(UTM) Northing. The command area extends from 294346.86m to 1253787.88m
(UTM) Easting and from 294346.86m to 1253787.88m (UTM) Northing. The location of the
project area is described here.
3 HYDROLOGY ANALYSIS
3.1 DATA AVAILABILITY
Mostly for the proposed projects has not metrological data so have taken the nearly metrological
stations. Our project Motet Abay diversion headwork or Engulie irrigation project the
metrological data was taken Merawi and Bahir Dar.
heaviest
no. Year rn(x) y=log(x) (y-y ̅)^2 (y-y ̅)^3
1 1960 116.3 2.06558 0.081552 0.023289
2 1961 114.1 2.057286 0.076884 0.021318
3 1962 110 2.041393 0.068323 0.017859
4 1963 108.7 2.03623 0.065651 0.016821
5 1964 105.5 2.023252 0.059169 0.014393
6 1965 102 2.0086 0.052255 0.011945
7 1966 90.5 1.956649 0.031203 0.005512
8 1967 86.9 1.93902 0.025285 0.004021
9 1968 85.7 1.932981 0.023401 0.00358
10 1969 83.3 1.920645 0.019779 0.002782
11 1970 80 1.90309 0.01515 0.001865
12 1971 79.9 1.902547 0.015016 0.00184
Mean = 𝑛𝑖=1 𝑦𝑖 /N
Checking data reliability
Number of data (N) =49
𝑛 (𝑦𝑖−𝑦)²
standard devation=[ 𝑖=1
𝑛−1
]^½
Standard deviation, n1 23.4375315
Mean ( 𝑥) =64.34081633
n1 23.4375315
Standard error of mean, n = =3.348218785
n 7
The basic procedure begins with an initial, rough screening of the data. For rainfall totals, we
advise tabulating daily observations by observations from several collection stations should be
available. This will allow visual detection of whether the observations have been consistently or
accidentally credited to the wrong day, whether they show gross errors or whether they contain
misplaced decimal points. An analysis of the frequency distribution of one-day rainfall might
also be useful. Other observations have their specific sources of error. One should be aware of
these and the methods of detecting them. Verifying the completeness of the data and checking of
the observer. The missing of the observation is clearly recorded. In most cases, it is convenient -
and perfectly acceptable - to use yearly totals as long as by ‘year’ one means ‘water year’
(hydrological year). This definition removes any risk of the seasons’ being split over two years.
So our data is completeness in this testing method of data; since the observation no specific
removing data.
After doing the rough of data test, one plot the graph by using time verses heaviest rainfall to
check the continuity of a given data.
rainfall(mm)
1963 108.7 1980 64.3 1996 47.4 80
1964 105.5 1981 64.3 1997 39
1965 102 1982 62 1998 38.7 60
1966 90.5 1983 61.1 1999 38
1967 86.9 1984 61.1 2000 37.4 40
1968 85.7 1985 58.8 2001 37.3
1969 83.3 1986 58.3 2002 37.3 20
1970 80 1987 58.3 2003 36.6
0
1971 79.9 1988 57.3 2004 36.6
1972 77.6 1989 57.1 2005 35.9 1940 1960 1980 2000 2020
1973 77.4 1990 57.1 2006 35.9 time(year)
1974 75.8 1991 56.2 2007 34.5
1975 73.4 1992 53.8 2008 27.5
1976 72
Figure 2: Rough Screening of the data
on arithmetic graph paper
The fugire shows a time series of yearly rain fall total at the Bahir Dar Metrological Department
from 1960 to 2008.It does not show any obvious trends discontinuity. So none of the data is
remove in this test method of checking or verifying.
From the Water Resources Council method recommends that adjustments be made for outliers
are data points that depart significantly from the trend of the remaining data. The retention or
deletion of these outliers can significantly affect the magnitude of statistical parameters
computed from the data, especially for small samples. Procedures for testing outliers require
judgment involving both mathematical and hydrologic considerations. According to the Water
Resources Council (1981), if the station skew is greater than +.0.4, tests for high outliers are
considered first; if the station skew is less than -0.4, tests for low outliers are considered first.
Where the station skew is between a0.4, tests for both high and low outlier should be applied
before eliminating any outliers from the data set. For our skewers value is-0.09044 this value is
less than -0.4, so we required to check the Lower outlier.
Yh Y K n S y
Higher outlier
Where: Y = mean of data in log unity
loweroutlier=10𝑌𝐿 =21.74mm
The Lowest recorded value is (27.5mm) which is greater than lower outlier (21.74mm). Hence
lower recorded data will not eliminate. From the test result it is conclude that the daily lowest
rainfall data recorded from E.C year 1960 t0 2008 depart significantly from the trend of the data
series, and hence the data could be said from 1960 t0 2008 E.C consistent for flood frequency
analysis.
2.7(𝑚 ^3⁄𝑠)
Max irrigable area = =320.8ha
3∗2.81(𝑙⁄(𝑠⁄_𝑎 ))
Distribution, cow (1953) derived the expression, the empirical for this distribution is:
xT=X +σ n −1 ∗K t
Where 𝑋𝑇 =the data of random hydrologic series with a return period T
𝑋= the mean value of the data
𝜎𝑛−1 = the standard deviation of the data
Where 𝑋𝑇 =the data of random hydrologic series with a return period T
𝑋= the mean value of the data
𝜎𝑛−1 = the standard deviation of the data
(𝑥−𝑥 )^2
Kt = frequency factor 𝜎𝑛−1 = 𝑁 −1
𝑇
kt= - 6/𝜋 0.5772 + 𝑙𝑛 𝑙𝑛 𝑇−1
Xt=64.34081633+(2.5922*23.4375315)=125.096mm
The frequency factor can be expressed and has the value of corresponding to an exceeding
probability of p (p = 1/T).and can be calculated by finding the value of an intermediate variable
1 1
w= ln(𝑝 2 ) 2 (0≤P≤ 0.5 ) ……………………1
1
w=ln (1−𝑝 ) ^0.5 (p≥ 0.5)……………………………2
Then the frequency factor will calculated using the approximation equation:
2.515517 + 0.802853 ∗ 𝑊 + 0.010328 ∗ 𝑊^2
𝐾𝑇 = 𝑊 −
1 + 1.432788 ∗ 𝑤 + 0.189269 ∗ 𝑤 2 + 0.001308 ∗ 𝑊^3
Where w is the intermediate variable
KT is the frequency factor
𝑋𝑇 = 𝑚𝑒𝑎𝑛 + 𝑓𝑟𝑒𝑞𝑢𝑒𝑛𝑐𝑦 𝑓𝑎𝑐𝑡𝑜𝑟 ∗ 𝑆𝑇𝐷𝐸𝑉
1
[ 2 ]0.5 where W is intermediate variable
W=ln
𝑝
1
W = (ln
( ))0.5 For T=50 years, p=1/T=1/50=0.02 by using case 1
0.02 2
W =2.7971
2.515517 + 0.802853 ∗ w + 0.010328 ∗ w^2
KT = W −
1 + 1.432788 ∗ w + 0.189269 ∗ w 2 + 0.001308 ∗ w^3
K T =2.227
OR 𝐾𝑇 = 2.227 Table 12.3.1 (for T=50 ventichow page 179)
Xt=64.34081633+(2.227*23.4375315)=116.536mm
3) log person type III
Xt=64.34081633+(2*23.4375315)=111.222mm
xT=X +σn −1 ∗K t
Where 𝑋𝑇 =the data of random hydrologic series with a return period T
𝑋= the mean value of the data
𝜎𝑛−1 = the standard deviation of the data
(𝑥 −𝑥 )^2
𝜎𝑛−1 = 𝑁 −1
Kt = frequency factor
𝑌𝑇 −𝑌 𝑛
𝑘𝑡 = (Using modified Gumbell frequency analysis equation 𝑋𝑇 is calculated.
𝑆𝑛
𝑇 𝑇
𝑦𝑇 =-[ln (ln𝑇−1 )] or 𝑦𝑝 = − 0.834 + 2.303 ∗ log 𝑙𝑜𝑔 𝑇−1 = 3.902
T=return period, for weir and small dam the return period (T) = 50 year.
𝑌𝑛 =The reduced mean as a function of sample size N
𝑆𝑛 = the reduced standard deviation as a function of sample size N
𝑆𝑛 =1.1601 and 𝑌𝑛 =0.5462 for N=49 respectively by interpolate (source: hydrology principle
analyisis and design ranguth, relation between Gumbell’s reduced standard deviation & sample
size, table 15.1, page 368)
Reduced mean=64.34081633
Reduced stdev=23.4375315
3.902 −0.5462
𝐾𝑡 = = 2.8926
1.1601
𝑋𝑇 = 64.34081633+(2.89334*23.4375315)=130.888mm
The D-Index test is supposed to be the better goodness to select the best distribution for the given
data. Hence, in this study it was used to
4
108.7 11.42196 28.64602 -38.1308 7.711373 61.51163
5
105.5 11.11868 29.73967 -29.702 7.429138 55.52254
6
102 10.118 30.16729 -23.9114 6.459976 49.78756
7
90.5 0.838444 22.37779 -27.6944 -2.77937 36.42985
8
86.9 -0.74756 22.37082 -24.7048 -4.31743 31.24495
9
85.7 -0.09228 24.72182 -20.16 -3.60699 28.66615
10
83.3 -0.76244 25.89482 -17.4704 -4.21501 25.04832
11
80 -2.43386 26.25032 -16.2025 -5.81738 20.6595
12
79.9 -0.9883 29.95115 -12.1592 -4.29576 19.57629
13
77.6 -1.81162 31.66821 -10.6673 -5.03584 16.38105
14
77.4 -0.5926 35.78704 -7.37069 -3.7261 15.36014
15
75.8 -0.82209 38.91691 -5.7252 -3.85703 13.00284
16
73.4 -1.89255 41.80439 -5.0955 -4.82064 9.90054
17
72 -1.9976 46.45538 -3.65289 -4.81 7.846253
18
71.3 -1.43177 52.87312 -1.67371 -4.119 6.534216
19
70.4 -1.09028 60.62812 -0.03826 -3.64217 5.059627
20
65.4 -4.86892 66.59721 -2.62989 -7.27441 -0.48155
21
64.3 -4.76389 80.16753 -1.43442 -7.01099 -2.09276
22
64.3 -3.57171 101.2905 0.760336 -5.6473 -2.57692
23
62 -4.68914 132.9192 0.564985 -6.57885 -5.33659
24
61.1 -4.41315 197.4932 1.688803 -6.10112 -6.67395
25
61.1 -3.2408 384.6293 3.639994 -4.70949 -7.09093
26
58.8 -4.36922 8006.537 3.225868 -5.59914 -9.78922
27
58.3 -3.69559 -415.301 4.553003 -4.66493 -10.6703
28
58.3 -2.51702 -198.118 6.327368 -3.20133 -11.0355
29
57.3 -2.33058 -127.972 7.054435 -2.70224 -12.386
30
57.1 -1.33317 -92.1158 8.539277 -1.36082 -12.9229
31
57.1 -0.12153 -69.8451 10.18665 0.23066 -13.2471
32
56.2 0.207883 -55.2717 10.90106 0.981111 -14.4595
33
53.8 -0.94107 -46.0215 10.08687 0.300956 -17.1608
34
52 -1.46406 -38.509 9.848348 0.302552 -19.2517
35
52 -0.15621 -30.7037 11.38974 2.200781 -19.5329
36
50.7 -0.1119 -25.1989 11.61537 2.913855 -21.105
37
47.4 -2.02456 -22.3606 9.829775 1.764442 -24.6684
38
39 -8.98637 -25.052 2.937765 -4.3187 -33.3238
39
38.7 -7.78787 -19.8905 4.144645 -2.09832 -33.8714
40
38 -6.91734 -15.2211 4.956417 -0.02499 -34.8119
41
37.4 -5.85998 -10.3967 5.880109 2.468789 -35.6454
42
37.3 -4.19655 -4.85903 7.324251 5.87826 -35.9724
43
37.3 -2.30123 1.184639 8.899633 9.943508 -36.1932
44
36.6 -0.93806 7.199377 9.82056 14.08142 -37.1082
45
36.6 1.345649 14.99405 11.50711 20.05112 -37.3175
46
35.9 3.232443 23.8817 12.58955 27.10408 -38.2215
47
35.9 6.264518 36.70951 14.5183 37.99016 -38.4204
48
34.5 8.626693 55.06024 15.29111 54.07669 -40.0144
49
27.5 6.878459 89.26537 10.96002 84.82102 -47.2037
Sum(absolute) 14.466 8613.826 262.643 181.0571 26.0352
when we check D_ Index Test the normal distrubition is selected for our analysis to minimize
the risk or minimum ratio of sum/mean. So the point design rain fall is 110.747mm.
As we have described earlier 49 years daily or monthly heaviest Rainfall data obtained from
mehrawi Meteorological station is used for determination of maximum probable flood. Based on
the available data, the following methods are used to estimate the design flood from rain fall
data.
From the observed data point rain fall was calculated using different statistical distributions. As
we see from the above calculation Gumbell (Extreme value Type I) distribution has higher rain
fall depth value of 130.888mm but when we check D Index Test the normal distrubition is
selected for our analysis to minimize the risk. So the point design rain fall is 110.747mm.
L=13873.69m=13.87369km
H=H1-H2=2309.70-2027.48=282.22
Area=52.89km2
ARF =1-0.044A^0.275=0.868967
BAHIR DAR INSTITUTE OF TECHNOLOGY WREED Page 16
Final year project on Engulie SSI Project 2014
where A=52.89km2
Areal rainfall=0.868967*110.747=96.2355mm
3.6.2 RUN OFF SYNTHESIS
The runoff in mm is determined from the catchment input data and design rainfall. To conclude
the runoff, the rainfall profile is used to determine the actual areal rainfall depth for each time
interval. The incremental rainfall depth is determined by subtracting the required time interval
rainfall depth from the proceeding time interval depth. These incremental are tabulated 1, 2, 3, 4,
5 and 6 in descending orders and arranged as 6, 4, 3, 1, 2, and 5. Based on the rearranged on the
rearranged order incremental rainfall was calculated. The rearranged incremental rainfall depth is
shown in the table below.
the assumption that the ratio of actual retention to a potential maximum retention is equal to the
ratio of actual run off to potential maximum run off the later being rain fall minus initial
abstraction.
F Q
= P−I And F=P-Ia -Q
S a
a (P−I )2
Then Q=(P−0.8s)
the soil profile is the topography the area of The river transports small sized gravel, soils, and
deposits based on thoese information the the group of the soil profile is expresed bellow.
Table 5: General Soil profile
Land use Area Area % Hydrology Group CN(Value)
Coverage condtion from vent
(Km2) chow
Forest Land 1.67 Poor A 45
3.157497
Cultivated Land 46.17 87.29438 Good B 71
Grazing land 5.04 Poor A 68
9.529212
52.89
𝑛
CN(II)= 𝑘=0
area% ∗ CN(value)/100 =69.87969
Curve number (CN) is achieved based on USSCS method by watershed characterization in terms
of land cover, treatment, hydrologic condition and soil group. From the watershed analysis curve
number at condition II =69.8796
Peak rainfall is found at an antecedent moisture condition III state, this value has to be changed
to antecedent moisture condition III.
23 ∗CN (II )
CN(III)= 10+0.13∗CN (II )) =84.21728
Q =
p 0.8S P+0.8∗47.60081
160
146.8559646
140
120 H1
100 H2
Q m3/s
H3
80
H4
60
H5
40
H6
20
SUM
0
1 3 5 7 9 11 13 15 17 19 21 23
time hr
Note that our calculation allows you to use a variety of units. The Rational method runoff
coefficient (c) is a function of the soil type and drainage basin slope. A simplified table is shown
below. See the references at the bottom of the page for more complete tables including impact of
slope.
The Rainfall intensity (i) is typically found from Intensity/Duration/Frequency curves for rainfall
events in the geographical region of interest. The duration is usually equivalent to the time of
concentration the drainage area. The storm frequency is typically stated by local authorities
depending on the impact of the development. 1 year, 2 year, 5 year, 10 year, 25 year, 50 year,
100 year storm frequency may be specified.University of kansas June 1997 the Table Contains
Average Rainfall Intensity in in mm per hour Dration,Return period.
Table 11: Average Rainfall Intensity in mm per hour Duration, Return period
Hr:Mn 1 year 2 year 5 year 10 year 25 year 50 year 100 year
from the above table, the rainfall intensity of 50 year returned period for duration period of
2.25hr is 1.76inch/hr which is equivalent to 44.704mm/hr.
Table 12: weighted coefficient
land coverage C A (km) C*A
cultivated land 0.245 46.17 11.31165
grazing land 0.37 5.04 1.8648
Forest 0.15 1.67 0.2505
Total 52.89 13.42695
weighted coeffitiont,Cw =C1A1+C2A2+C3A3/A1+A2+A3 =0.253866
Intensity=44.704mm/hr
Table 13: The design flood level at river cross section of the weir
Sr.no Elevation Water Area Wetted Hydraulic Velocity Discharge
(m) Depth (m2) Perimeter radius(R) (m/s) (m3/s)
(m) (m)
1 2037.5 0 0 0 0 0 0
2 2038 0.5 2.83 6.9 0.410145 1.425327 4.033675
3 2038.5 1 10.98 18.8 0.584043 1.804067 19.80865
4 2039 1.5 21.45 22.35 0.959732 2.512211 53.88692
5 2039.5 2 32.34 30.1 1.074419 2.708561 87.59486
6 2039.9 2.425 49.0578 40.451 1.238 2.9766 146.86
7 2040 2.5 52 41.01 1.267983 3.024814 157.2903
8 2029.55 3 71.15 68.1 1.044787 2.658529 189.1544
3.5
3
t.water depth(mm)
2.5
2
1.5
1
0.5
0
0 50 100 150 200 250
discharge(m3/s
The weir height is determined based on the maximum command area elevation which is required
to irrigate the maximum possible irrigable area and consists of head losses: (1) across the head
regulator, (2) due to slope of main canal (3) required to drive the full supply level in the main
canal. The analysis is shown as follow: Length of the weir depends on the physical feature of the
river at the site of the weir and taking into account the area of submergence on upstream side of
weir axis. Actual river crest length is equal to bank to bank width of the over flow section of the
river from the given top map is 15m.The maximum Elevation of flood is 2039m.a.s.l. That
means the HFL before construction and the velocity head is 2039.9masl. 0.467318m.
River bed level=2037.5m.a.s.l.
Maximum command area elevation=2037.6m.a.s.l
Maximum flood elevation=2039.9m.a.s.l
Distance from the head work site=1768m
Free board=0.2
Slope of the canal=0.001
Head losses the turn out =0.02m
Accordingly the weir height was fixed to be 1.5m and the corresponding crest level was fixed to
be 2038.77masl
Velocity head, a
𝒗𝟐
ha=𝟐𝒈=0.276m
4.2.2.4 A FFLUX
The rise of the maximum flood level in the river upstream of the weir after construction is known
as afflux. The amount of afflux will determine the top levels of guide banks and marginal banks.
By providing a higher afflux, the waterway, the length of the weir can be reduced, but it will
increase the cost of training works and the risk of failure by outflanking. At the same time, the
BAHIR DAR INSTITUTE OF TECHNOLOGY WREED Page 29
Final year project on Engulie SSI Project 2014
discharge intensity and the consequent scour shall go up, and hence, the sections of loose
protections upstream and downstream as well as the depths of pile lines at either ends shall have
to be increased, thereby making it costly. It is, therefore, always desirable to limit the afflux to a
safe value of 1.0 to 1.2 meters, however, in steep reaches with rocky bed, a higher value of afflux
may be permitted.
1.2<1.7., however, in steep reaches with rocky bed; a higher value of afflux may be permitted.
We have taken afflux 1m
The ogee weir with the vertical face on the u/s and ogee shaped crest on the d/s. Based on
experiments approval to avoid negative pressure including consideration of practicability,
hydraulic efficiency, stability and economy, the eqn. is derived. The portion of the dawn stream
is defined as:
𝑋 1 𝑦
𝑋 𝑛 = 𝐾 ∗ 𝐻𝑑 𝑛−1 ∗ 𝑦 , i.e (𝐻 )^𝑛 = 𝑘 ∗ 𝐻 ., the ogee is has the vertical u/s face. Hence from the
𝑑 𝑑
construction point of view and stability, it is better to provide the u/s slope 1:1and d/s slope 0.7:1
Therefore n=1.85, K=2. So, the value of a, b, r 1 & r2, as shown in the figure and table below
Relation b/n Hd, a, b, R1 & r2
Parameter Hd A B r1 r2
Relation 2.42 0.175*Hd 0.282*Hd 0.5*Hd 0.2*Hd
Value 2.42 0.424 0.98 1.21 0.48
𝑥 1.85 𝑥 1.85 𝑥 1.85
From d/s equation y = substituting the valves, Y= =
2∗𝐻𝑑 0.85 2∗2.42^0.85 4.24
x= 3.936
For x= 3.936, y= 3.12
Based on this value, the coordinate of y=0 to y=1.5m is tabulated as follow as:
Downstream profile
X 0 0.915 1.330 1.765 1.995 2.583 2.809 3.18 3.318
Upstream profile
The u/s profile from the axis is computed using the following eqn.
y=0.724*(x+0.27*He) ^1.85/He^0.85+0.126*He-0.4315*He^0.375*(x+0.27He)^0.625.
The upstream profile extended up to x=-0.27*Hd=0.27*2.42=0.65 where the depth of flow at the
design discharge above the weir crest.
y=0.724*(x+0.27*1.51) ^1.85)/1.51^0.85+0.126*1.51-0.4315*1.52^0.375(x+0.27*1.51)^0.627, The
upstream profile at an interval of 0.05m in the x direction and the corresponding y is presented in
the following table.
Upstream profile
X 0 -0.1 -0.2 -0.3 -0.4 -0.5 -0.6 -0.65
Y
0.0045 0.007 0.017 0.0349 0.059 0.09 0.2127 0.248583
Therefore the upstream profile extends up to the point of coordinates (-0.65., 0.258m)
Bottom width of weir (B) determined the sum of The length is the sum of b, length at the
toe for 60° curve (Li) and X
Q 146 .86
Intensity of discharge (q) = L = = 9.790667m^3/s/m
15
Silt factor f = 1.76 md where md the particle size = 1 for 50%finer (see appendix 5)
(9.79 2
Scour depth= 1.35(q^2/f) ^ (1/3) =1.35* 1,76 )^1/3 =4.061574189
v1 7.04
Fr1= (𝑔𝑌1)^0.5= =1.9 supercritical flow
(9.81∗1.39)^0.5
2
Q(m3/s) q(m /s) He(m) Y1(m) V(m/s) Fr Y2(m)
0 0 0 0 0 0 0
20 1.33 0.72 0.21 6.34 4.42 1.9
40 2.66 1.14 0.4 6.67 3.36 3.3
60 4 1.49 0.59 6.77 2.81 4.3
80 5.33 1.76 0.75 7.11 2.62 5.4
9
8
jump hiht curve depth(m)
7
tail water and
6
5
4
jhc
3
twrc
2
1
0
0 2 4 6 8 10 12
q(m2/s)
It is the jump characteristic for Y2>Y2' thought the range of q. As the TWRC is lower than HJC
the hydraulic jump forms at a certain section down steam of the toe. For the formation of the
jump, the horizontal apron may be depressed by excavation the river bed downstream of the toe
of the spillway to increase the toe water depth. The depth of depression can be taken as the
difference b/n the tail water depth and post jump depth.
d2 =2037.5m-2032.8m =4.69m
Creep length
The creep length, L=C*Hs, where C is the creep coefficient, (c=12 for coarse grained sand) from
Garg.
L =12*1.5=18m
1.5 1.5
D/s apron length (Ld) =2.21*c =2.21*12 = 9𝑚
13 13
𝑊𝑒𝑖𝑔𝑡(𝑊) = 𝛾𝑐 ∗ 𝐴𝑐
The external water pressure on the upstream face of the weir is calculated for sever case i.e for
the design discharge level. It has the four components P w1, Pw2, Pw3 and P w4 as shown in fig
below. The water pressure that could be exerted on the weir body due to a change in momentum
as the water flows over the curved toe surface was also calculated and incorporated in the
analysis. This is calculated based on the following formula
12
Pw1= γw acting at h1/3 in KN/m where h1 is the weir height.
2
And for the pressure at u/s curved surface (Z), (P w2) = γW*Z*b in KN/m.
22
Tail water pressure (Pw3) = γw
2
3. Dynamic
PU1= γw*h2*B acts at B/2 from the toe
PU 2 =0.5*B* γw*(h1-h2)
Where h1 is the water depth in u/s and h2 is the tail water depth=3.1m.
The stability analysis is done for expected sever different load combinations. This is the
condition when the weir body is subjected to design flood water and pond levels with all intakes
and sluice gates are closed, tail water depth at the downstream level and silt pressure equivalent
to the silt height is acting on the upstream face of the overflow section.
Water pressure and Uplift pressure for two cases
Pond level case
Weir height (h) =1.5m, height of u/s curved surface (Z) =0.25m and tail water depth=1.3m
Table 16: Stability analysis of weir design
Type of load vertical load horizontal load moment Moments point O
(pressure) arm
+ve -ve +ve -ve +ve -ve
Factor of Safety
i. Factor of safety against overturning (FO): the factor of safety against overturning should
not be less than 1.5.
Fo =
M
=
264.593
=1.54> 1.5 it is safe
M
171.968
36.62
=0.65* 5.62 = 4.23 > 1.5 safe!
B
Eccentricity, e=-0.1m < = 1.5/6=0.25m (no tension)
6
Enables the canal to flow silt free water from surface as much as possible.
The Scour of the silt deposited in front of the canal off take (regulator) Preserve a clear
In addition to the supply of water to the intake and the removal of silt, this acts to remove the
boulder that comes to wards it.
Design consideration
To ensure the proper scouring its capacity should be at least double the canal discharge.
Considering this, the opening size of the gate is 1.5 m*1m. The discharge passing is computed
using the following formula.
Q=Cd*L*H*(2*g*h) ^0.5
=0.62*1*1.5* 2 ∗ 9.81 ∗ 0.276 =1.73m3 /sec
The under sluice can discharge 1.82𝑚 3 /sec which is more than two times of the head regulator.
Hence, during non-rainy time, it is possible to flush the silt easily when required.
Water depth=1.5 m
The critical case in the case of under sluice is during non-flow condition. The high flood
condition is expected during summer. In this condition, water is not required for irrigation. If
water is not required for irrigation, the under sluice should be fully opened.
Q=cd*(2*9.81*h) ^0.5*A
Where h= water depth=0.6m
Cd=0.62
Q=L*H*0.62*(2*9.81*h) ^0.5
Q =0.4*0.6*0.62*(2*9.81) ^0.5=0.5m3/s
The capacity of the discharge has at least the base flow and the gate dimensions are determined
as water depth H=0.6m and width 0.4m
The transition from super critical to subcritical flow takes place in the form of hydraulic jump.
The stilling basin is designed to insure that the jump occurs always at such location that the flow
velocity entering the erodible d/s channels are incapable causing harmful scour.
The design of a particular stilling basin is depend on the magnitude of Froude number and other
characteristics of flow to be handled.
𝑣1 𝑞
Fr1= =
(𝑔𝑦 1) (𝑔𝑦 1^3)
7.04
Fr1= =1.9
(9.81∗1.39)^0.5
𝛾𝑠𝑎𝑡 =12𝐾𝑁 ⁄𝑚 3
𝛾𝑤 =10𝐾𝑁 ⁄𝑚 3
𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝑔𝑟𝑎𝑣𝑖𝑡𝑦 𝑜𝑓 𝑚𝑎𝑠𝑛𝑜𝑟𝑦 = 2.3
U/s wall height = U/s HFL – river bed level + free board, Adapt 0.5m free board
W1=T*H*𝛾𝑚𝑎𝑠 = 0.5*4.57*23=52.56𝐾𝑁/𝑚
W2=1/2*(B-T)*H*𝛾𝑚𝑎𝑠 = W2*(B-0.5) =52.56(B-0.5)
W3=1/2*(B-T)*H*𝛾𝑑𝑟𝑦 = 43.41*(B-T)
Earth pressure load (P)
1 1
1 = 3 ∗ 𝐻 = 3 ∗ 4.57 =1.52𝑚
2 2
2 = ∗ 𝐻 = ∗ 4.57 =3.05𝑚
3 3
1 2 2
𝑃1 = 2 ∗ 𝐾𝑎 ∗ 1 ∗ 𝛾𝑑𝑟𝑦 = 0.5 ∗ 0.33 ∗ 1.52 ∗ 19=7.24KN/m
1 2 2 2 2
𝑃4 = 2 ∗ 𝛾𝑤 ∗ ∗𝐻 = 0.5 ∗ 10 ∗ ∗ 4.57 =46.41KN/m
3 3
𝐵−𝑇 𝐵 − 0.5
𝑀3 = 𝑃3 ∗ 𝑇 + = 18.36 𝐵 − 0.5 ∗ (0.5 + 2 ∗ ( )
3 3
Total (Ms) = 𝑀1 + 𝑀2 + 𝑀3
Over turning moment (Mo)
1 1
𝑀1 = 𝑃1 ∗ 2 + 3 1 = 7.24 ∗ (3.05 + 3 ∗ 1.52) =25.75KNm/m
2 3.05
𝑀2 = 𝑃2 ∗ = 18.36 ∗ =27.99KNm/m
2 2
2 3.05
𝑀3 = 𝑃3 ∗ = 18.36 ∗ =27.99KNm/m
2 2
2 3.05
𝑀4 = 𝑃4 ∗ = 46.41 ∗ =70.77KNm/m
2 2
Use this as left and right retaining wall for u/s of weir.
h =2039.9-2037.5+0.5=2.9m
But the downstream depth Y2 of hydraulic jump is 3.1m so the downstream wall height is
greater than 3.1m+free board.3.1m+0.5m=3.6m.Therefore we have taken 3.6m
𝐻 3.6
h1= 3 = = 1.2𝑚
3
𝐻 2∗3.6
2 = 2 ∗ 3 = =2.4m
3
1
𝑃4 = ∗ 𝛾𝑤 ∗ 2 2 = 0.5 ∗ 10 ∗ 2.22 =24.2KN/m
2
𝐵 2
Now compare e and = 6 = 𝑒 𝑖𝑠 𝑙𝑒𝑠𝑠 0.333 safe! Use as for left and right d/s retaining wall.
6
The ETO represents the potential evaporation of well watered gross crop. To determine ETO by
using, the pen man-Montith Method from climate data on:
Temperature
Humidity
Sunshine
Wind speed
Rain fall data Climate data collection
Temperature data
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Avg
max 28.7 29.5 30.6 30.3 29.2 26.3 23.9 24 25.1 26.2 27.5 27.9 27.43333
min 7.2 8.4 11.1 12.1 12.9 13.1 12.9 12.8 12.1 11.1 9 6.8 10.79167
Min Max
Month Temp Temp Humidity Wind Sun Rad ETo
°C °C % km/day Hours MJ/m²/day mm/day
January 7.2 28.7 7 53 9.6 21.1 3.39
February 8.4 29.5 7 59 9.6 22.5 3.87
Rank Rain Fa
Year 1338.7 fall(descending) Ra.no
1961 1291.4 32 2036 1 2.380952
1962 1512.2 15 1945.8 2 4.761905
1963 1777 4 1844.7 3 7.142857
1964 1068.7 42 1777 4 9.52381
1965 1557.7 12 1682.9 5 11.90476
1966 1485.2 19 1671.4 6 14.28571
1967 1609.9 9 1627.7 7 16.66667
1968 1627.7 7 1614.6 8 19.04762
1969 1682.9 5 1609.9 9 21.42857
1970 1844.7 3 1564.3 10 23.80952
1971 1453.9 23 1557.7 11 26.19048
1972 2036 1 1557.7 12 28.57143
1973 1945.8 2 1545.2 13 30.95238
1974 1671.4 6 1540 14 33.33333
1975 1467.8 22 1512.2 15 35.71429
1976 1545.2 13 1500.5 16 38.09524
1977 1297.3 31 1495.5 17 40.47619
1978 1280 33 1494.6 18 42.85714
1979 1118.2 40 1485.2 19 45.2381
1980 1396.9 26 1481.7 20 47.61905
1981 1309.9 29 1468.6 21 50
1982 1257.2 34 1467.8 22 52.38095
1983 1216.7 35 1453.9 23 54.7619
1984 1494.6 18 1422.5 24 57.14286
1985 1214.3 36 1413.7 25 59.52381
1986 1152.7 39 1396.9 26 61.90476
1987 1305.5 30 1364.9 27 64.28571
1988 1614.6 8 1338.7 28 66.66667
1989 1422.5 24 1309.9 29 69.04762
1990 1557.7 11 1305.5 30 71.42857
1991 1413.7 25 1297.3 31 73.80952
1992 1564.3 10 1291.4 32 76.19048
1993 1085.3 41 1280 33 78.57143
1994 1185.2 38 1257.2 34 80.95238
1995 1364.9 27 1216.7 35 83.33333
1996 1207.4 37 1214.3 36 85.71429
1997 1500.5 16 1207.4 37 88.09524
Total
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct nov dec
RF(mm) 2.6 1.6 6.8 21.2 75.6 166.9 371.2 344.9 173.8 81.6 17.1 2.8 1266.1
EF.Rf(mm) 2.6 1.6 6.7 20.7 66.5 122.3 162.1 159.5 125.5 70.9 16.6 2.8 757.6
Crop Water:-Crop water requirements, schemes water supply and irrigation schedules
Essential information collected from the field should include
1. Crop and crop variety
2. First and last planting date
3. Indicative yield level
4. Indicative irrigation practices:
5. Crop characteristics’
Therefore our soil data is known as sandy Clay Soils; we selected Black clay soil in the above
category.
The Soil module is essentially data input, requiring the following general soil data:
Total Available Water (TAW)
Maximum infiltration rate
Maximum rooting depth
Initial soil moisture depletion
7 M AIN CANAL
The main canal conveys water from the source to the secondary canals. The main canal runs
almost along the contour line for a total length of 1768m from a capacity of 0.5m3/sec. It is
unlined canal depending up on geological condition. And also a trapezoidal unlined canal to
avoid risks that comes from the river edge and to minimize seepage loss, this increases efficiency
of canal.
Design canal
The main canal is designed starting from the diversion head work to supply the secondary and
tertiary canal. Hence to avoid scarcity of water especially during supplement condition, it is
designed for max expected base flow including loss through the canal.
2 1
𝐴∗𝑅 3 ∗𝑆 2
𝑄= 𝑛
The full supply discharge of the canal =maximum demand water requirement *command area *
8 working hours per day.
Secondary canal 1
Q1=2.81L/s/ha*15.7ha*3= 132.351L/S=0.132m3s
Side slope of the canal (m) = 1
Bed slope of canal (S) = 0.0005
Roughness coefficient (n) =0.035
2 1
𝐴 ∗ 𝑅3 ∗ 𝑆 2
𝑄=
𝑛
Q2=2.81L/s/ha*19.5ha*3= 164.385L/S=0.163m3s
Side slope of the canal (m) = 1
Bed slope of canal (S) = 0.001
Roughness coefficient (n) =0.035
2 1
𝐴 ∗ 𝑅3 ∗ 𝑆 2
=
𝑛
(0.163*0.035)/ (0.0005) ^0.5= (b+Y)*Y*((b+Y)*Y/ (b+2.828Y)) ^ (2/3))
Q3=2.81L/s/ha*18.69ha*3= 157.5567L/S=0.16m3s
Side slope of the canal (m) = 1
Bed slope of canal (S) = 0.0005
Roughness coefficient (n) =0.035
2 1
A ∗ R3 ∗ S 2
Q=
n
(0.157*0.035)/ (0.0005) ^0.5= (b+Y)*Y*((b+Y)*Y/ (b+2.82Y)) ^ (2/3
0.26m3/s= (b+1.5Y)*Y*((b+1.5Y)*Y/ (b+2.828Y)) ^ (2/3))
Assume the bottom width of the canal is 0.4m
b=0.4m, by trial and error, Y= 0.42m=0.5m and freeboard, d=0.5m+0.3m=0.8m
d=0.8m
b= 0.4m
Q=µ*A*(2*g*h) ^0.5
Where Q, discharge rate (m³/s)
A, wet cross section (m²)
G, gravitational acceleration (g=9.81m/s
H, head loss (m)
µ, Coefficient
Q and having set a value for h, the wet cross section (a) can be calculated. The permitted head
loss depends upon the total available head in the canal section in which structure is located.
When this load is limited culverts and bridge is usually designed for small discharge of 0.5m3s, e
head loss is 5cm (From irrigation and drainage book).
Design calculation for culvert
Q=µ*A*(2*g*h) ^0.5
Where Q, discharge rate (m³/s)
A, wet cross section (m²)
G, gravitational acceleration (g=9.81m/s)
H, head loss (m)
µ, Coefficient
Q=0.5m³/s discharges from the main canal
The common Coefficient value used for culverts are,µ=0.8-0.9, we have taken 0.8
A=Q/ µ *(2*(2*g*h) ^0.5g*h) ^0.5=0.5/0.8* (2*9.81*0.05) ^0.5=0.63m2
The diameter D=896mm, take D=900mm
Unit Quantity
Activity description of
head work structure
Subtotal
5.0 upstream retaining wall
for both left and right
side
5.1 earth Excavation M3 20.945
5.2 Hard rock excavation M3 26.18066
5.3 lean concrete M3 17.4
5.4 Masonry M3 80.8878
5.5 Backfill M3 28.045
Subtotal
6.0
upstream retaining wall
for both left and right
side
6.1 earth Excavation M3 23.5
6.2 Hard rock excavation M3 32
6.3 lean concrete M3 20
6.4 Masonry M3 106.8648
6.5 Backfill M3 30
subtotal
7.0 Main canal
7.1 Earth excavation M3 5728.32
7.2 masonry M3 7637.89
7.3 Back fill M3 1909.44
The ogee type weir is selected in order to dissipate the higher energy due to higher discharge and
boulders that comes from river flow. It is structurally safe but the design analysis and
construction of ogee type is difficult as compared to broad crested weir type short crested weir
tye. In the design of weir the cut-off depth on the down steam pile is very, so were commended
the length should be less than 4.57m.
Generally, the project is proposed to construct for the purpose of irrigation by considering the
local community to reduce or eliminate the scarcity of food allowance. To attain this goal local
community should participate to make the designed project perfect and real through providing
necessary information during feasibility and reconnaissance study.
9 REFERENCE
rd
1. Design and Hydrology Principle Analysis Ender son 3 edition.
7. Water Resource Development and Management Officers FAO Sub Regional Office For East
and South Africa. By Andreas P.SVVA and Karen FRENKEN.
8. Irrigation, Waterpower & Water Resource Engineering, by Dr K.R. Arora third edition
August 2001.standared publisher distributer.
10 APPENDIX
Table 22: wind speed calculation
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1992 0.6 0.7 0.8 0.9 0.9 1 0.8 0.7 0.7 0.7 0.7 0.6
1993 0.6 0.7 0.9 1 0.9 0.8 0.7 0.7 0.6 0.7 0.6 0.6
1994 0.5 0.6 0.7 0.9 0.9 1.1 0.6 0.6 0.7 0.6 0.6 0.6
1995 0.5 0.6 0.7 0.8 0.8 0.8 0.7 0.6 0.6 0.7 0.5 0.6
1996 0.5 0.6 0.7 1 0.7 0.7 0.7 0.6 0.6 0.6 0.6 0.5
1997 0.5 0.5 0.8 0.7 0.7 0.7 0.6 0.6 0.6 0.7 0.6 0.5
1998 0.4 0.5 0.6 0.6 0.6 0.8 0.6 0.6 0.6 0.6 0.5 0.4
1999 0.5 0.5 0.5 0.8 0.7 0.7 0.6 0.6 0.5 0.6 0.6 0.5
2000 0.4 0.5 0.6 0.8 0.7 0.7 0.7 0.6 0.6 0.6 0.5 0.3
2001 0.5 0.5 0.6 0.6 0.6 0.7 0.5 0.5 0.5 0.5 0.4 0.4
2002 0.3 0.4 0.5 0.7 0.5 0.6 0.5 0.5 0.3 0.3 0.3 0.3
2003 0.2 0.3 0.5 0.4 0.4 0.4 0.4 0.3 0.6 0.6 0.5 0.5
2004 0.4 0.5 0.5 0.6 0.6 0.7 0.7 0.6 0.6 0.6 0.5 0.4
2005 1.1 1.2 1.4 1.4 1.3 1.5 1.1 1 0.9 1 1.1 1
2006 1.1 1.1 1.4 1.6 1.5 1.4 1.2 1 1 1 1.1 1
2007 1 1.1 1.4 1.6 1.5 1.3 0.9 1 1 1.1 1 0.9
2008 1.1 1.1 1.3 1.4 1.4 1.2 1.1 0.9 0.9 0 0 0
2009 0.9 1.1 1.4 1.4 * 1.4 1.1 0.8 0.8 1 0.9 0.9
2010 0.9 0.8 1.3 1.5 1.3 1.1 0.9 0.8 0.8 0.8 0.8 0.7
Avg 0.63 0.7 0.8 0.9 0.89 0.92 0.7 0.68 0.6 0.6684 0.621 0.6
Km/day 53.2 59 73 83 75 78.1 63.9 57.7 57.3 56.415 52.42 48
2003 10.3 9.3 8.8 9.8 8.5 6.5 3.8 3.5 5.5 9.5 9.6 10
2004 9.7 9.8 9.9 7.9 9.7 6.2 5.4 4.6 6.2 8.7 9 9.7
2005 9.3 10 8.8 8.6 8.7 7.1 3.8 5.1 6.2 8.8 10 10
2006 9.8 10 8.8 8.8 7.7 7 4.7 3.8 5.7 8.8 9.6 9.6
2007 9.2 8.6 9.6 8.9 8.2 6.6 3.6 4.5 5.8 8.8 9.3 10
2008 9 9.8 10.2 10.7 8 8 5.1 4.2 5.8 8.5 9.7 9.4
ave(hr) 9.59 9.58 9.1 8.98 8.25 6.97 4.59 4.49 6.4 8.53 9.56 9.8
1997 0 0 19.4 29.1 238 121.7 233.5 218 180 135.5 23.4 10
1998 0 0 18.8 0.6 108 196.5 384 433 241 115.3 1.1 3
1999 9 0 0 8.1 45.7 129.9 393.6 486 196 197.3 3 0
2000 0 0 0.3 90.3 61.2 153.7 314.2 512 226 179.3 3 0
2001 0 0 1 22.7 54.8 257.3 379.6 522 143 86.7 2.5 13
2002 0 1.2 8.2 15.9 2 437.2 461.8 395 155 17.8 0.5 1
2005 0.4 2.7 52 20.4 107 214.6 445.7 285 297 109.6 22.6 0
2006 0.4 0 0.8 0.8 235 407 536.1 449 285 163.2 0.2 11
2007 7.55 1.77 26.9 25.5 99.3 455 273.5 271 280 86.9 52 0
2008 12.1 0 0 142 188 328.9 386 302 190 57.2 31.2 0
2009 1 35.5 21 47.2 158 199.4 470.3 469 117 108.1 19.9 22
2010 3 0 1.1 27.6 167 321 333.7 331 146 71.1 24.4 0
Ave 3.067 2.3973 8.91 26.7 95.6 207.31 422.68 389 201 94.12292 20.2583 3.5