Professional Documents
Culture Documents
Table Of Content
TABLE OF CONTENT
(b)
Determining the film thickness ............................................................................. 19
(c)
Cantabro abrasion test........................................................................................... 19
(d)
Determination of in situ water permeability of bituminous road surfacing or
roadbase layers by using the falling head (MARVIL) apparatus.......................... 21
(e) Test site, and apparatus preparation and positioning ............................................ 21
10110 Tests Relating To Chemical Stabilization................................................................... 25
(a) Test for cementitious binder content..................................................................... 25
(b) Canvas-patch test for the spreading rate of cementitious binder .......................... 25
10111 Tests On Pavements .................................................................................................... 25
(a) Determining the texture depth............................................................................... 25
(b) Straightedge test for surface irregularities on surfaces with a coarse surface texture
............................................................................................................................... 25
(c) Using the rolling straight-edge for measuring surface irregularities .................... 26
10112 Structural Tests ........................................................................................................... 26
(a) Tests on elastomeric bearings ............................................................................... 26
(b) Prestressed concrete: Testing prestressing steel, anchorage assemblies, couplings
and grout ............................................................................................................... 26
(c) Load test on foundation piles ................................................................................ 28
10113 Tests on Silicone Sealants........................................................................................... 29
(a) Bond to cement mortar.......................................................................................... 29
10114 Tests on Geotextiles and Geotextile-Soil Compatibility Tests ................................... 29
(a) Puncture resistance tests on geotextiles ................................................................ 29
(b) Permeability reduction (flow test)......................................................................... 32
10115 Classifying the Tests ................................................................................................... 34
10116 Testing of Construction Water.................................................................................... 35
(a) Compressive strength test ..................................................................................... 35
(b) Inorganic impurities criteria.................................................................................. 35
10117 Measurement And Payment ........................................................................................ 36
Item 101.01 Special tests on elastomeric bearings........................................................ 36
Item 101.02 Other special tests requested by the engineer ........................................... 36
Item 101.03 Providing testing equipment ..................................................................... 36
Table 10100/1 Schedule Showing Quantities And Times For Submitting The Materials For
Approval And Mix Designs .................................................................................... 9
Table 10100/2 Recommended Mark....................................................................................... 24
Table 10100/3 Criteria for Inorganic Impurities in Water Used To Manufacture Concrete .. 35
Figure 10100/1 Weathering Apparatus ................................................................................... 37
Figure 10100/2 Visual Classification...................................................................................... 38
Figure 10100/3 Marvil Apparatus........................................................................................... 39
Figure 10100/4 Grease Ring ................................................................................................... 39
Figure 10100/5 Placing Of Prestik.......................................................................................... 40
Figure 10100/6 Placing Of Plaster Of Paris............................................................................ 40
Figure 10100/7 Flow Cone ..................................................................................................... 41
Figure 10100/8 Metal Or Glass Container.............................................................................. 42
Figure 10100/9 Cone Assembly And Measuring Device ....................................................... 43
Figure 10100/10 Permeameter for Permeability Production Tests (Flow Tests).................... 44
Figure 10100/11 Permeability Reduction Criteria .................................................................. 45
Table 10200/1 Critical Values (Except Roadbase and Asphalt Mixes).................................. 50
2
Table 10200/2 Values Of x0.99 Distribution .......................................................................... 51
Table 10200/3 Outlier Test for Roadbase: Critical Values..................................................... 52
Table 10200/4 Outlier Test for Asphalt: Critical Values C .................................................... 52
Table 10200/5 Values of F Distribution (Σ = 0.05) ................................................................ 54
Table 10200/6 Values for T-Distribution (Σ = 0.05) .............................................................. 55
Table 10200/7 Characteristic Properties: Judgement Plan B.................................................. 56
Table 10200/8 Minimum Sample Sizes For Concrete (Structural)......................................... 57
Formula 10200/1 ..................................................................................................................... 57
Table 10200/9 Values Of Constants N, Ls, L's And φ .......................................................... 59
Table 10200/10 Values Of Ka (Single Limits)........................................................................ 60
Table 10200/11 Values Of Kad (Double Limits).................................................................... 61
Table 10200/12 Properties In Respect Of Which Conditional Acceptance May Be Applied 62
Table 10200/13 Rejection Limits (Lr And L'r) For Sample Mean ( x )................................ 63
n
Table 10200/14 Values Of Kr (Single-Limit Specification)................................................... 65
Table 10300/1 Critical Values ................................................................................................ 71
Table 10300/2 Outlier Test For Roadbase: Critical Values C ................................................ 72
Table 10300/3 Outlier Test For Asphalt: Critical Values C ................................................... 72
Table 10300/4 Acceptance Limits In Respect Of Compaction............................................... 75
Table 10300/5 Acceptance Limits For Bituminous Binder Content....................................... 76
Table 10300/6 Acceptance Factors for Strength Concrete ..................................................... 77
Table 10300/7 Minimum Sample Sizes for Strength Concrete (Structural)........................... 77
Table 10300/8 Properties To Which Conditional Acceptance May Apply ........................... 78
Table 10300/9 Rejection Limits (Lr And L'r) For The Sample Mean ( xn )........................... 79
Table 10300/10 Payment Reduction Factors for Conditionally Accepted Bituminous Binder
Application Rates.................................................................................................. 80
10101 SCOPE
During the progress of the work tests shall be conducted on materials and workmanship to
ensure compliance with the requirements of the specifications
Certain sampling and testing procedures not covered in the other sections of the specifications
by reference to the standard methods mentioned in clause 10102 are given in this section
(a) General
The contractor as part of his process control shall regularly test aggregates, as they are being
manufactured or brought onto the site and used or taken to stockpile.
(e) Determining the effect of sand on the water demand of a concrete mix
Water demand is defined as the quantity of water per cubic metre of concrete required to give
a slump of 75 mm in a concrete with an optimum quantity of stone with a nominal size of 19
mm.
The following materials are required:
• Ordinary Portland cement
• Crushed stone with a nominal size of 19 mm
• Sand or a sand mix to be tested.
Method:
1) Determine the relative density (Rsa) in accordance with SABS 844 and the fineness
modules (FM) of the sand or sand mix.
2) Determine the compacted bulk density (CBD) of the 19 mm aggregate in accordance
with SABS 845. Also determine the relative density of the stone (Rst)
3) Determine the required quantity of stone (S) per cubic metre of mix (in kg/m3) in
accordance with formula:
S = CBD (0.975 - 0.1 FM).
4) Estimate the water demand (W) of the mix (in l/ m3). (220 l/m3 may be used as a
starting point.)
5) Determine the required cement content (C) for the mix (in kg/m3) by using the water
content (W) as obtained from (4) and a water-cement ratio of 0.59.
6) Determine the desired sand content (SC) of the mix (in kg/m3) in accordance with
the formula:
SC = 1 - (C/3140 + W/1000 + S/Rst)
7) Decide on the mix size, which will apply to the available equipment and calculate
the mix quantities in relation to the calculated quantities per cubic metre. Do not produce a
mix of less than 10 l.
8) Prepare the mix and determine the slump in accordance with SABS 862. Repeat the
test with adjusted quantities of cement, water and sand until a slump of 75 mm is achieved.
(As a rule, a change of 10 l/m3 in the water content either halves or doubles the slump.)
9) The water content giving a slump of 75 mm will then be the water demand for the
mix.
10) In order to facilitate the repeatability of results the following parameters should be
kept constant:
• Material temperature
• Mixing time
• Source of cement
• Source of stone.
Table 10100/1 Schedule Showing Quantities And Times For Submitting The Materials
For Approval And Mix Designs
Material Proposed use Submission for quality Submission for quality approval
submitted approval only and mix design
Minimum Minimum Minimum time Minimum
time to be quantity to be to be allowed for quantity
allowed for submitted testing, approval to be submitted
testing and and mix design
approval
Crushed stone 150 kg of each
Coarse 8 weeks for
50 kg of each size of stone for
aggregate for 2 weeks structures and
size of stone each class of
concrete concrete roads
concrete
Bituminous 50 kg of each 50 kg of each size
2 weeks 2 weeks
seals size of stone of stone
50 kg of each 100 kg of each
Asphalt mixes 2 weeks 8 weeks
size of stone size of stone
Crushed-stone
8 weeks
base or 3 weeks 50 kg 200 kg
(stabilization)
subbase
Crusher dust 150 kg of each
50 kg of each
and/or sand Fine aggregate type proposed for
2weeks size of 10 weeks
for concrete use for each class
aggregate
of concrete
15 kg of each 150 kg of each
Asphalt mixes 2weeks size of 8 weeks type proposed for
aggregate use
15 kg of each 50 kg of each type
Slurry or sand
2 weeks type proposed 6 weeks proposed for
seal
for use use
Gravel Subbase 200 kg of each 8 weeks
4weeks 200 kg
and/or base sample (stabilization)
Other materials
e.g. paint,
As specified As prescribed by the engineer
cement, addi-
tives, etc
(f) Accelerated-test method for determining the potential alkali reactivity of aggregates
container, which is large enough for the prisms to be completely immersed. (Glass and metal
containers are unsuitable as they are susceptible to attack by the caustic solution.) The prisms
are measured every working day for a period of 14 days at a room temperature of 23 OC, and
their linear expansion is calculated. The average expansion of the three prisms for each day is
then calculated. Where none of the values deviate by more than 15% from the average, the
repeatability is regarded as being satisfactory. The average expansion after 10 or 12 days is
taken to be the reference value for determining the potential alkali reactivity.
(ii) Criteria
The criteria proposed provisionally for the accelerated mortar-prism testing method shall be
as follows:
1) Percentage of linear expansion after 10 days.
< 0.08 the alkali reactivity of the aggregate is not harmful
> =0.08 but < 0.20 the alkali reactivity of the aggregate is harmful and the aggregate is
expanding slowly
>=0.20 the alkali reactivity of the aggregate is harmful and the aggregate is expanding
rapidly
2) Percentage of linear expansion after 12 days:
< 0.10 the alkali reactivity of the aggregate is not harmful
>=0.10 but < 0.25 The alkali reactivity of the aggregate is harmful and the aggregate is
expanding slowly
>=0.25 The alkali reactivity of the aggregate is harmful and the aggregate is expanding
rapidly.
3) Interpretation
For aggregates falling in the slowly expanding group, the alkalinity per m3 of concrete shall
not exceed 2.80 kg of a Na2O equivalent.
For aggregates falling in the rapidly expanding group, the alkalinity per m3 of concrete shall
not exceed a value of 2.10 kg of a Na2O equivalent per m3, depending on the reactivity.
The dilution and palliative effect of extenders in the cementitious binders, such as slagment
(where permitted in structural concrete) and fly ash, shall be taken into account in the
interpretation of the results.
(b) Consistency
The test method described in TMH1 method D3 shall apply in regard to the slump test, and
the method described in BS 881 (Part 104) in regard to the VEBE test.
(f) Curing concrete cubes to attain accelerated strength development (55 °C /20 hours)
(i) Scope
A method is described for curing concrete cubes at 55 OC for 20 hours with a view to
predicting the 28-day compressive strength for purposes of quality control. The accelerated
tests are additional tests and do not replace the 28-day tests.
(ii) Apparatus
The following equipment is required:
• Apparatus for preparing the concrete cubes in accordance with method Dl of
TMH1
• Plastic sheets of 180 mm x 180 mm
• Hessian sheets for covering the samples
• A suitable water bath with a circulation system of adequate capacity and a
thermostat to maintain the temperature constantly at 55 OC +/- 1 OC.
(iii) Method
Prepare the required number of concrete cubes in accordance with method Dl in TMH1 and
completely cover the exposed surface within the cube mould with small plastic sheets and
then with wet hessian. Keep it covered for 3 hours +/- 15 minutes.
Place the concrete cubes in their moulds in the hot-water bath at a rate which will not cause
the water temperature to drop below 54 OC. Record the exact time when each cube is placed
into the water and leave it in the water at a temperature of 55 OC +/- 1 OC for 20 hours +/- 15
minutes.
Remove the moulds containing the cubes from the water and then carefully remove the cubes
from their moulds. Cool the cubes for 2 hours +/- 15 minutes in water at 20 OC +/- 5 OC.
Test the compressive strength of the cubes in accordance with method Dl of TMHl.
10107 TESTING THE SOILS, GRAVELS AND CRUSHED STONE MATERIALS FOR
EARTHWORKS AND PAVEMENT LAYERS
Specimens of soils, gravels and crushed-stone materials in earthworks and pavement layers
shall be taken in accordance with the methods described in TMH5 (unless SABS 827 is
specified), and any tests thereon shall be conducted in accordance with the methods described
in TMHl (A series), all subject to the following additional provisions:
(i) Apparatus
o 37.5 mm and 26.5 mm, 300mm diameter sieves, complying with SABS 197.
o Stainless steel weathering basins, 150 mm (L) x 100 mm (W) x 50 mm (H) with
perforated base (see figure 10101/1 (a))
o Stainless steel reaction troughs, 500 mm (L) x 160 mm (W) to hold three (3)
weathering basins (see figure 10101/1(b)).
o Stainless steel drip tray, 500 mm (L) x 450 mm (W) x 25 mm (H), to hold nine (9)
weathering basins for oven drying (see figure 10101/1(c)).
o Force draught oven, capable of maintaining a temperature between 105 OC and 110 OC
o Tank with distilled water supply.
Place the weathering basins with aggregate particles in the reaction trough and add clean
water until the particles are covered by at least 15 mm of water.
Keep the aggregate particles immersed in the water at room temperature for 8 hours +/- 30
minutes.
Lift the weathering basins containing the aggregate particles out of the water and, by tilting it
through 90 degrees, allow the weathering basins to rest on the inner shoulders of the trough
for drip drying. This completes the first cycle.
Visually inspect each particle and record the condition of each particle noting cracks, flaws,
extent of fissures etc before starting the following cycle.
Repeat until five cycles are completed and finally inspect each aggregate particle.
(iv) Evaluation
The disintegration pattern of the aggregate fragments shall be visually classified in
accordance with the five classes specified in (v) and illustrated in figure 10100/2.
The terms to be used to describe the shape of the fragments are as follows:
o Plates - plates of fairly uniform thickness.
o Flakes - fragments of non-uniform thickness, concave, convex, or wedge-shaped.
o Chunks - roughly equi-dimensional fragments (> 3 mm).
o Grains - fragments from about sand size to 3 mm diameter.
o Silt, mud or clay
(v) Classification
The five classes for rating the aggregate are as follows:
Class I: Nil to minimal disintegration with only minor closed cracks and difficult separation
along these fractures planes
Class II: Disintegration into hard fragments with some open cracks.
Class III: Moderate disintegration with a high percentage of open cracks into less hard
fragments.
Class IV:Extensive disintegration into soft fragments with total separation along fracture
planes.
Class V: Slaking into very soft fragments, silt, mud or clay
10108 DETERMINING THE TOTAL APPROXIMATE DRY BULK RELATIVE DENSITY AND
THE APPARENT RELATIVE DENSITY
(i) Definitions
The definitions in methods B14 and B15 of TMH1 are applicable.
(ii) Apparatus
1. +4.75 mm fraction
The same apparatus as that required by method B14,
2. -4.75 mm fraction
• A 2 liter pycnometer.
• A balance with a capacity of at least 5 kg and accurate to 0.5g.
• A vacuum pump capable of maintaining a reduced pressure of 100 mm
mercury.
• A water bath capable of maintaining a temperature of 25 C +/-1 OC.
• A drying oven, thermostatically controlled and capable of maintaining a
temperature of 105 OC to 110 OC.
• A 25 ml pipette.
• A 0.075 mm sieve.
(iii) Method
1. +4.75 mm fraction
The method is the same as method B14.
2. -4.75 mm fraction
After riffling, the volume of the sample shall be 40% =/- 5% of that of the
pycnometer.
Wash the sample thoroughly to remove the -0.075 mm fraction and soak the sample
for 24 hours +/- 4 hours
After the sample has been soaked transfer it to a clean pycnometer.
Add distilled water to the sample in the pycnometer until the pycnometer is
approximately three-quarters full. Remove any entrapped air by subjecting the
sample to partial vacuum (air pressure approximately 100 mm mercury) for a few
(iv) Calculations
1. +4.75 mm fraction
Calculate the dry bulk relative density to the nearest 0.001 g/c m3 from the following
formula:
Dry bulk relative density (25 OC) : Gbc = a/(b-c)
where :
a = mass of oven-dry sample in air
b = mass of saturated surface-dry sample in air
c = mass of saturated surface-dry sample in water at 25 OC.
The test shall be repeated if the duplicate results do not agree within +/- 0.005.
Report the result to the nearest 0.001 g/cm3.
Calculate the percentage of water absorbed from the following formula:
Percentage of water absorption (mass): Pwa = 100 (b – a)/a
Report the result to the nearest 0.1%.
2. -4.75 mm fraction
Calculate the apparent relative density to the nearest 0 001 g/cm3 from the following
formula:
Apparent relative density (25 OC): Gaf = (A – E)/[(D - E) - (C - A)]
where:
A= mass of oven-dry sample and pycnometer
C= mass of saturated sample and pycnometer filled with water at 25 OC
D= mass of pycnometer filled with water only. At 25 OC
E= mass of clean, dry pycnometer.
The test shall be repeated if the duplicate results do not agree within + 0.005.
Report the result to the nearest 0.001 g/cm3.
Calculate the dry bulk relative density of the -4.75 mm fraction from the following
formula:
Dry bulk relative density - fines (25 OC): Gbf = Gaf/(Pwa.Gaf/100 + 1)
Calculate the dry bulk relative density of the total sample less the -0.075 mm
fraction, from the following formula:
Dry bulk relative density - total (25 OC): Gbf = 100/(P1/Gbf + P2/Gbs) where :
P1 = percentage passing through the 4.75 mm sieve
P2 = percentage retained on the 4.75 mm sieve.
(i) Apparatus
• A balance to weigh 5 kg accurately to within 0.5 g
• A pycnometer, eg a preservative jar with a smooth flat rim.
• A thermostatically controlled bath capable of maintaining a temperature of 25 OC +/-
1OC.
• A drying oven capable of maintaining the temperature between 105 OC and 110 OC.
• A thermometer marked from 0 – 100 OC.
• Towels.
• Teepol (10%) solution.
(ii) Method
Take 3 kg to 4 k g of the material as obtained from a density hole in the road. All the material
obtained from the hole should preferably be used. If it is too much for one pycnometer, more
than one pycnometer shall be used.
(iii) Calculation
The apparent relative density of the material is calculated as follows:
• Mass of pycnometer + glass sheet = a
• Mass of pycnometer + glass sheet + material = b
• Mass of material only = (b - a)
• Mass of pycnometer + material + water + glass sheet =c
• Mass of pycnometer + water + glass sheet = d
• Apparent relative density of material = 1000[(b-a)/{(d-a) – (c-b)}]
Notes:
1) No chemicals other than the Teepol solution may be added to the water.
2) No suction may be applied to the water to remove air.
3) The temperature of the water shall be 25 OC +/- 1 OC and no other temperature may be
used.
4) Where two pycnometers are used, the apparent relative density shall be calculated from the
weighted average of the two results.
5) Where the water absorption of the aggregate exceeds 1.0%, the engineer will determine the
soaking period.
(a) Tests described in the standard specifications for tars, bitumens and bituminous
emulsions
The engineer shall be entitled to order the contractor to have materials tested by an approved
laboratory for compliance with all or any of the requirements specified, and the results of such
tests shall be submitted directly to the engineer by the testing laboratory with copies, if
requested, to the contractor.
The cost of such tests shall be borne as specified in Clause 10103.
(i) Apparatus
The apparatus shall be a Los Angeles Testing Machine as described in ASTM Method C131.
The machine shall consist of a hollow steel cylinder, closed at both ends, having an inside
diameter of 710 mm +/- 5 mm and an inside length of 510 mm +/-5 mm.
The cylinder shall be mounted with stub shafts attached to the end of the cylinder, but not
entering it, and shall be mounted in such a manner that it may be rotated with the axis in a
horizontal position with a tolerance in slope of 1 in 100.
An opening in the cylinder shall be provided for introduction of the test sample.
The opening shall be provided with a suitable, dust-tight cover secured in place by bolts.
The cover shall be designed to maintain the cylindrical contour of the interior surface unless
the shelf is so located that the charge and/or test sample will not fall on the cover, or come in
contact with it during the test.
A removable steel shelf extending the full length of the cylinder and projecting 90 mm +/- 2
mm inward shall be mounted on the interior cylindrical surface of the cylinder. in such a way
that a plane centred between the large faces coincides with an axial plane.
The shelf shall be 25 mm +- 1 mm thick and mounted by bolts or other suitable means so that
it is firm and rigid.
The position of the shelf shall be such that the distance from the shelf to the opening,
measured along the outside circumference of the cylinder in the direction of rotation, shall not
be less than 1 270 mm.
The machine shall be driven and counterbalanced to maintain uniform peripheral speed of 30
- 33 rpm for 300 revolutions.
If an angle is used as the shelf, the direction of rotation shall be such that the charge is caught
on the outside surface of the angle.
(iii) Calculations
The percentage abrasion loss for each specimen shall be calculated as follows:
P = 100(P1 - P2)/P1 where:
P1 = mass of specimen before testing.
P2 = mass of specimen after testing.
The mean of the three specimens shall be determined at the various binder contents.
(iv) Notes:
The determination of the optimum binder content is based on the following considerations:
1/ a minimum binder content limit to ensure resistance against aggregate loss due to traffic
and to enhance durability
2/ a maximum binder content limit to avoid binder run-off and to ensure good drainage in the
mix as a layer on the road.
The minimum binder content to ensure adequate coating thickness shall not be less than 4%.
The density of the specimen can also be determined by calculating the volume of the
specimen.
The voids in the specimen can also be calculated if the maximum theoretical voidless density
(Rice) is determined:
% Voids in specimen = 100 (Rice density - Specimen density)/Rice Density.
(i) Scope
This method describes the determination of the in situ water permeability of asphalt surfacing
and/or roadbase layers and is based on the principle of the falling head permeameter. The
permeability of a layer is an indication of the intensity of interconnected voids in the layer
that may be detrimental to the material due to oxidation of the binder and/or ingress of water
to the lower layers.
(ii) Apparatus
The apparatus consists of the falling head permeability (MARVIL) apparatus with a circular
weight and an acrylic tube with volume markings from 0 ml to 300 ml in 50 ml increments
(see figure 10100/3).
Other items required are:
• Adhesive putty (Prestik or similar approved)
• Water resistant grease (BP LS 3 or wheel bearing grease)
• Plaster of Paris (commercial grade) optional for granular layers
• Stop watch, accurate to 1 second
• Plastic tanks with sufficient drinking water (40 l or more)
• Plastic beakers or aluminium kettles of 5 l capacity
• Mechanical power saw with a corundum blade (optional for cutting through
thick asphalt layers)
(iii) Sundries
• Chisels (25 mm and 100 mm width)
• Hammers (1 kg - 2 kg mass)
• Paint brushes (25 mm and 100 mm width)
• Putty knives (50 mm width)
• Spatula (20 mm width)
• Hand cleaning cream, paper towels
• Toluol (at least 5 l)
bottom of the base of all grease using Toluol (or similar approved organic solvent) and dry
with paper towels.
Place a Prestik thread of 5 mm diameter around the inner and outer rims of the base edge and
press firmly so that it adheres to the base. The function of the inner thread is to prevent grease
from being expelled into the test area.
As the test is started under a head of 380 mm of water, the two threads must not be so thick as
to prevent the base of the apparatus from coming in close contact with the surface of the test
area. Fill the space between the threads of Prestik with grease. The grease shall be applied so
that it protrudes below the Prestik (see figure 10100/4). Place the apparatus lightly on the pre-
marked surface of the road. Lift the apparatus off the surface and apply extra grease over the
grease band left on the road and work it into the surface with a spatula or finger.
Place the apparatus with the undisturbed adhesive threads, and with additional grease added
between the threads, exactly on the pre-marked area. Press firmly until the grease is expelled
from underneath the base. Place the circular weight on the upper side of the base. This is to
keep the apparatus stable and to prevent the water from lifting it.
The expelled grease from underneath the base is worked into the surface to form a band of
grease about 20 mm wide around the base of the apparatus to achieve a watertight seal. The
apparatus is then ready for filling with water.
After testing, carefully lift the apparatus with the aid of a screwdriver from the surface.
Inspect the condition of the threads and if they are loose, press down again or replace and fill
with grease again.
(v) Notes
Table 10100/2 indicates the recommended mark to be taken for a reading as indicated by the
time for the water level to reach the graduation mark and the number of repetitions (refills) at
a test point.
When there is a possibility of the wafer level not reaching the 50 ml mark in 10 minutes,
estimate the volume to the nearest 10 ml at 10 minutes, stop the test and calculate the
permeability.
The times (or flows) may remain fairly constant when taken three times or more, but a
decrease in flow indicates that the material is becoming saturated. An increase in flow
indicates that the water opens up paths to flow into and if water appears on the surface in the
vicinity of the apparatus there has been horizontal flow through the material and this may also
give rise to an increase in the flow rate.
If it is required to test the bond between the surfacing and the base layer, ten repetitions or
more may be required.
If the bond is not sufficient, an increase in the water flow may be encountered and the surface
layer will eventually lift up from the roadbase.
If this does not happen, it is not necessarily an indication of a good bond between the
surfacing and the base. In this case the granular base material may be sufficiently permeable
for the water to penetrate into the base or even lower layers, rather than follow a horizontal
path.
The testing for bond strength between the surface and the base, especially in the case of
granular materials, should be considered carefully as the unnecessary over saturation of the
layer with water may be detrimental to the road. This procedure is more applicable to research
projects.
The permeability of a layer will depend on many factors such as:
• the degree of saturation of the layer, e.g. after a spell of rain, or due to built-in
moisture content.
• the degree of density of the layer.
• the grading, shape and texture of the material, and
• the degree of saturation of the underlying layer under a thin upper layer.
Testing of the surface where it shows signs of intensive cracking should be considered.
The plaster of Paris should be mixed to obtain approximately 900 ml of slurry which should
be sufficient if the hole is not more than 300 mm in diameter. The procedure is as follows:
Add approximately 1100 g of plaster of Paris to approximately 900 ml of water in a mixing
bowl or small plastic bucket. Let the powder form a small heap in the middle of the water.
Let it stand for a minute or two before mixing. Mix it slowly with the fingers to a watery
consistency. Add more water if necessary until a creamy consistency is obtained so that when
the slurry is poured around the base of the apparatus it will fill all the crevices. The slurry
must cover the base to a depth of 5 mm to 10 mm. The process must be completed before
hardening starts. Air and water temperature may influence the setting of the slurry,
When the surface layer is thinner than the base of the apparatus, the circular weight shall be
used to hold the apparatus in the starting position. Less slurry of plaster of Paris will be
required.
(b) Straightedge test for surface irregularities on surfaces with a coarse surface texture
Where surface irregularities are measured on surfaces with a coarse surface texture such as
grooved concrete pavements, crushed-stone pavement layers, natural gravel roadbase, asphalt
with rolled-in chippings, surface treatments, seals and other like surfaces, the following
procedure shall be followed:
A metal wedge of 100 mm in length and 50 mm in width shall be constructed with a taper of
7.5 horizontal to 1.0 vertical and tapering to a feather edge (50 mm wide). Parallel lines
spaced at 7.5 mm intervals shall be engraved on the sloping face and numbered to indicate the
positions where the wedge is 1.0 mm. 2.0 mm, etc, thick.
Where surface irregularities are measured, the 3.0 m straight-edge, which shall have sharp
right-angled corners at the bottom, shall be placed on the road and the thin edge of the wedge
inserted below the straight-edge from the front at the position where a surface irregularity is to
be measured. The size of the irregularity shall be determined in accordance with the mark to
which the wedge can be inserted without lifting the straight-edge. The width of the contact
plane of the straight edge shall be 18 mm +/- 2 mm and its height shall be 80 mm +/- 10 mm.
(i) General
Tests on elastomeric bearings shall be conducted in accordance with BS 5400 part 9.2, and the
bearings shall comply with the test requirements specified in the said specification.
(i) General
Where so directed by the engineer, the contractor shall make arrangements for samples of the
materials he intends to use in the works to be tested by an independent testing authority. The
cost of testing prestressing steel, anchorage assemblies and couplings will be paid for as
specified in sub-clause 10103. Control tests on the viscosity and bleeding of grout will be
regarded as part of the contractor's obligations under clause 36 of the General Conditions of
Contract and 10209 for process control and will not be paid for separately.
Materials represented by samples, which do not comply with the specified requirements, shall
be removed and replaced with suitable material.
(iv) Grout
The fluidity of grout shall be measured with a flow cone, immersion apparatus or viscometer.
The instrument shall be accurately calibrated in a laboratory so that the specified viscosity of
the grout can be controlled satisfactorily
The procedure for conducting the flow-cone test for measuring the fluidity of grout shall be as
follows.
Unless otherwise approved, the flow cone shall be as shown in figure 10100/7.
Immediately after the grout has been mixed the pre-wetted flow cone, which is held firmly
with its top rim in a level position, shall be filled with grout to the level indicated by the pre-
set pointer, whilst the bottom orifice is held closed with a finger.
As soon as the required volume of grout (+/- 1,750 ml) is reached, the finger shall be released
to allow the grout to flow out freely through the bottom orifice. A stopwatch shall be used to
determine the flow time for emptying the cone, to the nearest second
The readings obtained during grouting shall be compared with the times determined in the
laboratory for grouts of the specified viscosities.
The bleeding of grout shall be measured in a metal or glass container with an internal
diameter of approximately 100 mm and a height of approximately 120 mm. The grout and
water levels in the container shall be controlled with a metal bridge into which two adjustable
studs A and B are secured. See figure 10100/8 for details of the apparatus.
The procedure for determining the bleeding of grout shall be as follows:
Studs A and B in the metal bridge shall be adjusted and locked so that the distance from the
lower tips of the studs to the bottom of the container will be approximately 100 mm and 107
mm respectively. The volumes VA and VB for the container at the respective levels of the stud
settings shall then be determined to the nearest millilitre.
The container shall be filled with freshly mixed grout to a level where the grout will just touch
the tip of stud A, which points downwards. The bridge shall then be removed and the
container tightly sealed to prevent evaporation. The container shall then be stored at 20 OC
and kept free from vibrations for the entire duration of the test.
Three hours after the grout has been mixed, the container shall be opened and the free (bleed)
water poured off. The bridge shall be placed over the container with the tip of stud B pointing
downwards and water poured onto the grout with a measuring apparatus until the water level
touches the tip of stud B. The volume of water added shall be determined to the nearest
millilitre and designated as ∆V.
The percentage of bleeding shall be calculated from the formula:
{1-(VB – ∆V)/ VA } x 100
(ii) Specimens
1. Dimensions of specimens
Specimens shall be either 250 mm x 250 mm square. or circular with a diameter of
282 mm.
2. Number of specimens
At least 10 specimens shall be tested.
3. Preparation of specimens
The position of the holes on the specimen shall be marked through the stencil with
the felt-tipped pen. The specimens shall be cut by means of the metal stencil. With
the aid of the stencil, mark on the conditioned sample the positions of the required
specimens, together with the positions of the holes for bolts and locating pins. The
specimens shall be set out in two rows equally spaced across the width of the sample.
The spacing of the specimens shall be as specified, except that the distance between
the two rows shall be 150 mm. Where the width of the sample does not allow all the
specimens to be set out in two rows, the number of rows shall be increased.
Carefully cut each specimen from the sample as specified. Centre the punch over the
marked positions and punch out the holes.
Maintain the conditioned specimens in the specified atmosphere. Test the specimens
in the testing atmosphere.
(iii) Procedure
1. Assembly
Place the lower clamping ring with bolts in position on the mounting device and
carefully position the specimen over the bolts and pins so as to ensure that the
specimen is free from stress and is lying flat on the mounting device. Position the
upper clamping ring over the bolts and pins, and carefully lower the ring onto the
specimen. Secure the ring in position by tightening the nuts to a torque of 30 Nm.
2. Testing
Ensure that the mounting-platen supporting-sleeve assembly is central with the line
of the fall of the cone.
Place the clamping-ring assembly on the supporting cylinder.
Operate the cone-release system.
Carefully remove the cone from the specimen and measure the diameter of the hole
formed in the specimen with the measuring device. The device shall be gently
lowered vertically, by hand, into the hole formed in the specimen until penetration
under its own mass stops. The diameter of the hole is taken as the graduation nearest
to the line of contact between the device and the geotextile.
Note:
It is advisable to pack the inside of the supporting cylinder with a resilient material of
sufficient thickness to prevent damage to the cone in the event of complete
penetration of the specimen.
(i) Apparatus
1. Water supply
A supply of water from an overhead tank with a constant head of 1,000 mm +/- 25
mm above the geotextile sample.
Permeameter with a suitable means of mounting to ensure that the permeameter
remains in a vertical position throughout the test. The permeameter shall consist of
the following:
Two 90 mm internal diameter Perspex cylinders: the bottom cylinder with a recess
for the support mesh and a breather hole.
Two Perspex end caps with inlet/outlet nozzles: machined as shown in figure
10100/10 to fit over the cylinders and to allow air bubbles to escape through the inlet
nozzle; the upper cap provided with a bleeding hole.
Three brass rods and nuts (wing nuts).
Brass or stainless steel mesh with 2.67 mm openings (standard soil sieve).
2. Cutting device
A means of cutting out a circular specimen with a diameter of at least 110 mm.
3. Miscellaneous equipment
• Containers with capacity of at least 5 litres.
• A riffler with 25.0 mm openings.
• A soil-test sieve with 13.2 mm openings.
• A balance to weigh up to 1 kg, to an accuracy of 1 g.
• Stopwatch.
• Silicone grease.
• Pans.
(ii) Specimens
1. Number of specimens
Conduct one test for each soil/geotextile combination,
2. Geotextile specimens
Mark and cut the required number of specimens and maintain them in the standard
atmosphere until they are tested.
3. Soil samples
Sieve the oven-dried soil through a 13.2 mm sieve and discard the material larger
than 13.2 mm. Riffle the remaining soil to obtain specimens of 1,000 g +/- 5 g. Place
the specimens in sample bags and label them.
(iii) Procedure
Place the geotextile specimen between the two cylinders on top of the mesh. Apply silicone
grease to ensure that water does not leak out between the two cylinders.
Mix the amount of water required to bring the soil sample to modified AASHTO optimum
moisture content (OMC). With dispersive soils, friable mudstones and heavy clays
remoulding often gives an impermeable soil mass. In such cases this step shall be omitted and
the soil sample shall be placed dry.
Place the soil sample on top of the geotextile Smooth the surface without compacting the soil.
Place the Perspex end caps in position and fasten the rods and nuts. Place the assembled
permeameter in its mounting.
Close the outlet and the breather hole in the lower cylinder and slowly fill the entire cylinder
with water from the top. Care must be taken not to disturb the surface of the soil sample. This
can be done by using a small-diameter pipe with a spray nozzle, which is inserted through the
top inlet to a height just above the soil surface. Fill the permeameter to the top of the inlet
nozzle, remove the small-diameter pipe, and connect the hose from the constant-head tank.
Remove any entrapped air bubbles through the inlet nozzle and the bleeding hole.
Open the outlet nozzle and breather hole in the lower cylinder and record the time at the
beginning of the test.
The first outflow measurement shall be taken between 1 minute and 5 minutes after the
beginning of the test. Outflow is measured by way of a container and stopwatch. The
container shall be placed under the outflow and the time to fill the 5 litre container, or the
amount of flow that occurs in 30 minutes recorded, whichever occurs first. It is not important
that exactly 5 litres or 30 minutes be used, but the time and volume shall be recorded
accurately. Record the following with each outflow measurement:
• Date and time (hours and minutes)
• Flow volume (1,000 mm = 1 ml) - Calculate flow in m3/s
• Flow time (minutes and seconds)
• Height of the sample (soil + geotextile) in mm
• Height of the water head above the bottom of the geotextile in mm (ensure that this
height remains at 1,000 mm +/- 25 mm)
• The discoloration or otherwise of the water at the outlet.
Outflow measurements shall be taken at the beginning of the test (1 minute to 5 minutes after
the outlet has been opened) and thereafter at least once a day. The test shall be continued for
at least 400 hours (17 days).
(iv) Calculations
Permeability coefficient. K
Calculate the permeability coefficient for each outflow measurement, as follows:
k = Q/iA (mm/s), where
• Q = outflow (mm3/s)
• i = hydraulic gradient = water head above geotextile (mm) / sample height (mm)
Payment will be made under the pay items of clause 10117 only in regard to special tests.
Payment for ordinary tests shall be included in the rates tendered by the contractor for the
items of work to which the ordinary tests relate.
Sugar Negative
Item 101.01 Special tests on elastomeric bearings (150% vertical load and 150% shear
distortion) as described in sub-clause 10112(a):.......................... number (No)
The unit of measurement shall be the number of elastomeric bearings tested as described.
The tendered rate shall include full compensation for having the test conducted by an
approved laboratory, also for replacing the bearings that may possibly have been damaged
during testing.
Item 101.02 Other special tests requested by the engineer......................... provisional sum
The provisional sum provided to cover the cost of special tests as requested by the engineer in
terms of clause 10115 shall be expended in accordance with the provisions of the general
conditions of contract. Payment will not be made for any special test should the test indicate
that the specifications have not been complied with.
10201 SCOPE
This section describes one scheme for determining compliance with certain requirements of
the specifications in regard to the properties of materials and workmanship, by means of
measurements and tests and by applying statistical judgement plans.
It also covers the requirements in regard to the control to be exercised by the contractor to
monitor the quality of his work and materials, and the routine tests and inspection to be
carried out by the engineer.
10203 DEFINITIONS
For the purposes of this section the following words and symbols shall have the following
meanings:
Lot
A lot is a sizeable portion of work or quantity of material, which is assessed as a unit for the
purposes of quality control, and which is selected to represent material or work produced by
essentially the same process and from essentially the same materials.
Random sample
A random sample is a group of "n" test measurements at "n" separate test positions or on "n"
sample portions obtained from the lot in an unbiased manner.
Random sampling shall mean stratified random sampling, unless inconsistent with the
context.
Sample mean ( x )
n
x is the arithmetic mean of a set of "n" test results constituting the sample.
n
S n
= (¦ x − n x )÷ (n−1 ) , where:
2 2
(ii) Concrete
The lot size shall be determined by the engineer, with due regard to the size and the type of
structure in which the concrete is placed, the specific portion of the structure and the total
quantity of concrete placed in a day. The lot sizes in concrete structures could therefore vary
considerably, and, particularly in the case of small structures, it could be necessary to combine
samples of the same grade of concrete from different structures, provided that the concrete is
obtained from the same concrete plant and is cast in the same period.
(iii) Other
In other cases, as for example in material stockpiles where the definition of a lot in
accordance with sub-clause 10203 (a) does not apply directly the engineer will determine lot
sizes in each case according to the circumstances.
(d) Outliers
Test results shall be scanned for possible outliers. Where a test result deviates greatly from the
remainder in a lot, it shall, if possible, be re-examined by further testing and, if there is
reasonable evidence to suggest that the test result is erroneous, it shall be regarded as an
outlier, rejected, and replaced with a fresh test result.
Where repeating a test or re-examining a test result is impossible, Method 1 shall be used for
identifying outliers for all work, except roadbase and bituminous pavement and surfacing
layers. Method 2 shall be used for identifying outliers for roadbase and bituminous pavement
and surfacing layers.
(i) Method 1
Calculate the value of To from: To = (x − x )÷ S
o n n
Where:
x n
and S n
are respectively the sample arithmetic mean and standard deviation, and
x o
is the value of the test result differing most from the mean.
Compare the value of To with the value of T for the applicable value of "n", from table
10200/1.
If the absolute value of To is greater than T, then xo is an outlier.
Where S n
is very small, it may be the cause for a value being wrongly classified as an
outlier. For this purpose a minimum value S n
(min) shall be determined for S n
as follows:
2
S n
(min) = ( x0.99 : n - 1) / (n - 1) , where:
2 2
x 0.99
: n -1 = x 0.99
for (n - 1) degrees of freedom as obtained from table 10200/2; and
2
Table 10200/2 Values Of x 0.99
Distribution
2 2 2
(n - 1) x 0.99
(n - 1) x 0.99
(n - 1) x 0.99
(ii) Method 2
In the case of roadbase and asphalt work the following procedure shall be used for identifying
outliers where it is impossible to repeat a test or to reinvestigate a test result:
Calculate the absolute value Co from: Co = / xo - x /
n
Where x o
represents the possible outlier.
Compare Co with the critical value C = C0.01; nσ
Where σ is the standard deviation of the population derived from historical data.
If the absolute value Co > C, the test result x o
shall be regarded as an outlier and shall be
excluded from the sample.
The critical values for different values of "n" are given in tables 10200/3 and 10200/4 for the
different product properties.
CRITICAL VALUES C
For For sieve size (mm)
n percentage 26.5 19.0 13.2 4.75 2.00 0.425 0.075 For PI
compaction
4 4.1 6.1 8.5 8.5 7.3 5.6 3.6 3.2 2.4
5 4.4 6.4 9.0 9.0 7.7 5.9 3.9 3.3 2.6
6 4.6 6.7 9.4 9.4 8.0 6.2 4.0 3.5 2.7
7 4.7 6.9 9.7 9.7 8.3 6.3 4.1 3.6 2.8
8 4.8 7.1 9.9 9.9 8.5 6.5 4.2 3.7 2.8
8 4.9 7.2 10.1 10.1 8.6 6.6 4.3 3.7 2.9
10 4.9 7.3 10.2 10.2 8.7 6.7 4.4 3.8 2.9
CRITICAL VALUES C
n For density For bitumen For voids in mix
content
4 3.2 0.4 2.3
5 3.3 0.5 2.4
6 3.5 0.5 2.5
7 3.6 0.5 2.6
Every outlier shall be discarded and replaced by another random test value. The sample mean
x and the sample standard deviation S n shall then be recalculated. If an outlier cannot be
n
replaced, the sample mean and standard deviation shall be calculated on the basis of the
remaining test results. The final number of test results used in the assessment after the
elimination of an outlier shall never be less than four.
(e) Resubmission
Where a lot has been accepted conditionally or has been rejected, the engineer may agree to
its resubmission for approval if:
it has been reworked and the engineer is satisfied that a proper attempt was made to improve
the properties which were unacceptable;
or
where, in his opinion, there are valid technical reasons therefor.
In both cases a fresh sample shall be taken, and a fresh (second) set of test values determined.
The first and second sets of test values shall then be compared with each other to determine
whether their properties differ significantly.
Where in the opinion of the engineer a significant difference does occur, the submission of the
lot shall be regarded as a first submission and be assessed as such, and only the second set of
test values shall then be used for this purpose.
Where in the opinion of the engineer no significant difference occurs, the submission of the
lot shall be regarded and assessed as a resubmission, which will mean, inter alia, that the first
and second sets of test values shall be combined for purposes of assessment.
In order to be able to determine theoretically whether there is a significant difference between
the two sets of test values (suffixes a and b), the Fisher F-test shall be conducted, and, if
necessary, also the t-test, all as described below.
The Fisher F-test is conducted as follows:
2 2
Calculate the value of F = S g ÷ S k , where:
S g
= the greater value of S a
and S b
S k
= smaller value of S a
and S b
U g
= sample size minus one, from the sample with the larger standard deviation.
U k
= sample size minus one, from the sample with the smaller standard deviation.
Then calculate t = x − x ÷ S (1 / n
a b a
+ 1 / nb )
Where x −x
a b
is the absolute value of the difference between x a
and x b
and is always
positive.
Determine the degrees of liberty U = na + nb − 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 22 24 26 28 30
Ug
Uk
1 161.44 200.00 216.00 225.00 230.00 234.00 237.00 239.00 241.00 242.00 243.00 244.00 245.00 245.00 246.00 246.00 247.00 247.00 248.00 248.00 249.00 249.00 249.00 250.00 250.00
2 18.51 19.00 19.20 19.20 19.30 19.30 19.40 19.40 19.40 19.40 19.40 19.40 19.40 19.40 19.40 19.40 19.40 19.40 19.40 19.40 19.50 19.50 19.50 19.50 19.50
3 10.13 9.55 9.28 9.12 9.01 8.94 8.89 8.85 8.81 8.79 8.76 8.74 8.73 8.71 8.70 8.69 8.68 8.67 8.67 8.66 8.65 8.64 8.63 8.62 8.62
4 7.71 6.94 6.59 6.39 6.26 6.16 6.09 6.04 6.00 5.96 5.94 5.91 5.98 5.87 5.86 5.84 5.83 5.82 5.81 5.80 5.79 5.77 5.76 5.75 5.75
5 6.61 5.79 5.41 5.19 5.05 4.95 4.88 4.82 4.77 4.74 4.70 4.68 4.66 4.64 4.62 4.60 4.59 4.58 4.57 4.56 4.54 4.53 4.52 4.50 4.50
6 5.99 5.14 4.76 4.53 4.39 4.28 4.21 4.15 4.10 4.06 4.03 4.00 3.98 3.96 3.94 3.92 3.91 3.90 3.88 3.87 3.86 3.84 3.83 3.82 3.81
7 5.59 4.74 4.35 4.12 3.97 3.87 3.79 3.73 3.68 3.64 3.60 3.57 3.55 3.53 3.51 3.49 3.48 3.47 3.46 3.44 3.43 3.41 3.40 3.39 3.38
8 5.32 4.46 4.07 3.84 3.69 3.58 3.50 3.44 3.39 3.35 3.31 3.28 3.26 3.24 3.22 3.20 3.19 3.17 3.16 3.15 3.13 3.12 3.10 3.09 3.08
9 5.12 4.26 3.86 3.63 3.48 3.37 3.29 3.23 3.18 3.14 3.10 3.07 3.05 3.03 3.01 2.99 2.97 2.96 2.95 2.94 2.92 2.90 2.89 2.87 2.86
10 4.96 4.10 3.71 3.48 3.33 3.22 3.14 3.07 3.02 2.98 2.94 2.91 2.89 2.86 2.85 2.83 2.81 2.80 2.78 2.77 2.75 2.74 2.72 2.71 2.70
11 4.84 3.98 3.59 3.36 3.20 3.09 3.01 2.95 2.90 2.85 2.82 2.79 2.76 2.74 2.72 2.70 2.69 2.67 2.66 2.65 2.63 2.61 2.59 2.58 2.57
12 4.75 3.89 3.49 3.26 3.11 3.00 2.91 2.85 2.80 2.75 2.72 2.69 2.66 2.64 2.62 2.60 2.58 2.57 2.56 2.54 2.52 2.51 2.49 2.48 2.47
13 4.67 3.81 3.41 3.18 3.03 2.92 2.83 2.77 2.71 2.67 2.63 2.60 2.58 2.55 2.53 2.51 2.50 2.48 2.47 2.46 2.44 2.42 2.41 2.39 2.38
14 4.60 3.74 3.34 3.11 2.96 2.85 2.76 2.70 2.65 2.60 2.57 2.53 2.51 2.48 2.46 2.44 2.43 2.41 2.40 2.39 2.37 2.35 2.33 2.32 2.31
15 4.54 3.68 3.29 3.06 2.90 2.79 2.71 2.64 2.59 2.54 2.51 2.48 2.45 2.42 2.40 2.38 2.37 2.35 2.34 2.33 2.31 2.29 2.27 2.26 2.25
16 4.49 3.63 3.24 3.01 2.85 2.74 2.66 2.59 2.54 2.49 2.46 2.42 2.40 2.37 2.35 2.33 2.32 2.30 2.29 2.28 2.25 2.24 2.22 2.21 2.19
17 4.45 3.59 3.20 2.96 2.81 2.70 2.61 2.55 2.49 2.45 2.41 2.38 2.35 2.33 2.31 2.29 2.27 2.26 2.24 2.23 2.21 2.19 2.17 2.16 2.15
18 4.41 3.55 3.16 2.93 2.77 2.66 2.58 2.51 2.46 2.41 2.37 2.34 2.31 2.29 2.27 2.25 2.23 2.22 2.20 2.19 2.17 2.15 2.13 2.12 2.11
19 4.38 3.52 3.13 2.90 2.74 2.63 2.54 2.48 2.42 2.38 2.34 2.31 2.28 2.26 2.23 2.21 2.20 2.18 2.17 2.16 2.13 2.11 2.10 2.08 2.07
20 4.35 3.49 3.10 2.87 2.71 2.60 2.51 2.45 2.39 2.35 2.31 2.28 2.25 2.22 2.20 2.18 2.17 2.15 2.14 2.12 2.10 2.08 2.07 2.05 2.04
21 4.32 3.47 3.07 2.84 2.68 2.57 2.49 2.42 2.37 2.32 2.28 2.25 2.22 2.20 2.18 2.16 2.14 2.12 2.11 2.10 2.07 2.05 2.04 2.02 2.01
22 4.30 3.44 3.05 2.82 2.66 2.55 2.46 2.40 2.34 2.30 2.26 2.23 2.20 2.17 2.15 2.13 2.11 2.10 2.08 2.07 2.05 2.03 2.01 2.00 1.98
23 4.28 3.42 3.03 2.80 2.64 2.53 2.44 2.37 2.32 2.27 2.23 2.20 2.18 2.15 2.13 2.11 2.09 2.07 2.06 2.05 2.02 2.00 1.99 1.97 1.96
24 4.26 3.40 3.01 2.78 2.62 2.51 2.42 2.36 2.30 2.25 2.21 2.18 2.15 2.13 2.11 2.09 2.07 2.05 2.04 2.03 2.00 1.98 1.97 1.95 1.94
25 4.24 3.39 2.99 2.76 2.60 2.49 2.40 2.34 2.28 2.24 2.20 2.16 2.14 2.11 2.09 2.07 2.05 2.04 2.02 2.01 1.98 1.96 1.95 1.93 1.92
26 4.23 3.37 2.98 2.74 2.59 2.47 2.39 2.32 2.27 2.22 2.18 2.15 2.12 2.09 2.07 2.05 2.03 2.02 2.00 1.99 1.97 1.95 1.93 1.91 1.90
27 4.21 3.35 2.96 2.73 2.57 2.46 2.37 2.31 2.25 2.20 2.17 2.13 2.10 2.08 2.06 2.04 2.02 2.00 1.99 1.97 1.95 1.93 1.91 1.90 1.88
28 4.20 3.34 2.95 2.71 2.56 2.45 2.36 2.29 2.24 2.19 2.15 2.12 2.09 2.06 2.04 2.02 2.00 1.99 1.97 1.96 1.93 1.91 1.90 1.88 1.87
29 4.18 3.33 2.93 2.70 2.55 2.43 2.35 2.28 2.22 2.18 2.14 2.10 2.08 2.05 2.03 2.01 1.99 1.97 1.96 1.94 1.92 1.90 1.88 1.87 1.85
30 4.17 3.32 2.92 2.69 2.53 2.42 2.33 2.27 2.21 2.16 2.13 2.09 2.06 2.04 2.01 1.99 1.98 1.96 1.95 1.93 1.91 1.89 1.87 1.85 1.8
4
U t U t U t
1 6.3138 11 1.7959 21 1.7207
2 2.9200 12 1.7823 22 1.7171
3 2.3534 13 1.7709 23 1.7139
4 2.1318 14 1.7613 24 1.7109
5 2.0150 15 1.7530 25 1.7081
6 1.9432 16 1.7459 26 1.7056
7 1.8946 17 1.7396 27 1.7033
8 1.8595 18 1.7341 28 1.7011
9 1.8331 19 1.7291 29 1.6991
10 1.8125 20 1.7247 30 1.6973
Structure Characteristic
Gravel pavement layers Relative compaction
The procedure to be followed when assessing the above properties shall be as follows:
Formula 10200/1
n ab
= na + nb
x ab
= (n x + n x )÷ (n + n )
a a b b a b
S ab
= ª«®(na − 1) S a + (nb − 1) S b + na
¬¯
2 2
(x ab − x a) + n (x ab − xb) ½¾¿ ÷ (n + n − 1)º»¼
2
b
2
a b
where:
subscript “a” refers to the first set of test values,
subscript “b” refers to the second set of test values
subscript “ab” refers to the combined properties.
Accept the lot if the sample mean x is equal to or greater than the acceptance limit
n
La, otherwise reject the lot.
• For an upper-limit specification
L'a = L's - Sn.ka
Accept the lot if the sample mean x is equal to or less than the acceptance limit L'a,
n
otherwise reject the lot.
• For a double-limit specification calculate
La = LS + Sn.kad
L'a = L's - Sn.kad
Accept the lot if the sample mean falls between the lower acceptance limit La
x n
and the upper acceptance limit L'a or is equal to either one, otherwise reject the lot.
Where a lot has been rejected, it may nevertheless be considered for conditional
acceptance in terms of clause 10208.
2. Resubmission
Where a lot is resubmitted for approval in terms of sub-clause 10204(e) the
acceptance limits are determined as follows:
• For a single-limit specification
La = LS + Sab.ka
L'a = L's – Sab.ka
Accept the lot if xab ≥ La in the case of a lower-limit specification and if xab ≤ L'a in
the case of an upper limit specification, otherwise reject the lot.
• For a double-limit specification
La = LS + Sab.kad
L'a = L's – Sab.kad
Accept the lot if La ≤ xab ≤ L'a. If not, reject the lot.
The values of ka and kad used in the above cases shall agree with the sample size
nab.
Where a resubmitted lot is rejected, it may nevertheless be considered for conditional
acceptance in terms of clause 10208.
The evaluation of a resubmitted lot shall be final and binding on both employer and
contractor. The provisions of this section shall be strictly complied with.
Where a resubmitted lot is rejected, the contractor shall be obliged to bear the costs
of the additional tests conducted on the resubmitted lot.
• Voids
Ls = specified values - 1.5 percentage points
L's = specified values + 1.5 percentage points
(2) Specification limits for cementitious-binder content
Ls = 70% of the specified cementitious-binder content or as ordered by the engineer.
(3) Specification limits for compressive strength of concrete
Ls = the specified 28-day cube characteristic strength (see clause 8404, e g. for class 25/38
concrete, Ls = 25 MPa.)
Sample size ka
(n) φ =5% φ =10% φ =15%
4 0.747 0.445 0.220
5 0.821 0.520 0.300
6 0.878 0.576 0.358
7 0.923 0.620 0.403
8 0.961 0.656 0.440
9 0.993 0.687 0.470
10 1.020 0.713 0.496
12 1.065 0.755 0.538
14 1.101 0.789 0.571
16 1.131 0.817 0.598
18 1.155 0.840 0.620
20 1.177 0.860 0.640
(a) General
Where a lot is rejected under statistical judgement plan B but the test results are such that the
lot complies with the requirements for conditional acceptance specified hereafter, the engineer
may accept the lot conditionally, that is, the lot may be accepted at reduced payment in lieu of
complete rejection, provided that:
1) conditional acceptance shall be in the sole discretion of the engineer and not an option
which may be exercised by the contractor or a right the contractor may claim;
2) the lot is approved in respect of all other requirements not judged by a statistical
judgement plan;
3) the contractor shall have the option to remove and reinstate at his own cost conditionally
accepted work with work which complies with the requirements for acceptance at full
payment;
4) conditional acceptance and the corresponding reduced payment shall apply only in respect
of the work and properties listed in sub-clause 10208(b) below.
Property Structure
Relative compaction (i) Asphalt base or surfacing
(ii) Chemically stabilized layers
(iii) Plant mixed paver laid layers
(See note 2)
Tar or bitumen binder content Asphalt base or surfacing
Voids in mix Asphalt base or surfacing
Cementitious binder content or Chemically stabilized layers
strength requirements
28-day-cube compressive All strength concrete (concrete
strength pavements not included. See note 1)
Notes:
1) See sub-clause 7120(f) for details regarding reduced payment in the case of inadequate
concrete strength or layer thickness in concrete pavements.
2) Crushed stone layers shall not be subject to conditional acceptance, but, where compaction
to 88% of apparent density is specified but has not been obtained, the engineer in his sole
discretion may accept the layer against payment at the rate for compaction to 86% of apparent
density, provided that the layer complies with all the requirements specified for a crushed
stone layer compacted to 86% of apparent density.
The same provisions shall apply mutatis mutandis where a specified compaction of 102% of
modified AASHTO density cannot be attained, but 100% of modified AASHTO density can
be attained.
(iii) Concrete
Items 84.01, 84.02 and 84.03.
No reduction will apply to payment items for formwork, reinforcing and prestressing tendons.
(iv) Pavement layers mixed in a central mixing plant and placed by paver
Items 71.02, 71.03, 71.12, 71.13, 71.14 and 71.15.
Table 10200/13 Rejection Limits (Lr And L'r) For Sample Mean ( x )
n
(v) General
Where payment items are introduced into the project specifications or are changed in the
schedule of quantities, the payment reduction factor shall apply to the payment items
corresponding to the payment items mentioned above.
Where a lot is conditionally accepted in regard to more than one property, the payment-
reduction factor for each property shall be computed and the factor that gives the largest
reduction shall be applied, except in the case of concrete pavement when the provisions of
sub-clause 7120(f) shall apply.
together with all transport, Instruments and equipment, to ensure adequate supervision and
positive control of the works at all times.
The contractor shall conduct tests or have them conducted continually on a regular basis, to
check the properties of natural materials and processed natural materials and of products
manufactured on the site, such as concrete and asphalt mixes. Although not a requirement for
the contractor to conduct regular tests on any commercially produced products such a.
cement, bitumen, steel and pipes, the contractor shall remain fully responsible for any
defective material or equipment provided by him. Similarly, the quality of all elements of the
works shall be checked on a regular basis so as to ensure compliance with the requirements of
the specifications.
The intensity of control and of tests to be conducted by the contractor shall be adequate to
ensure that proper control is being exercised.
Where any natural materials or products made from natural materials are supplied, and upon
completion of each element of the construction work, the contractor shall test and check such
materials, products and/or elements for compliance with the specified requirements and shall
submit his results to the engineer for approval. Such submission shall include all his
measurements and test results and shall furnish adequate proof of compliance with the
specified requirements.
No specific pay items are provided as compensation for the above obligations, including the
provision of all samples delivered to the engineer, the repair of places from which samples
were taken, and the provision of the necessary personnel and testing apparatus and facilities,
for which compensation shall be Included in the tendered rates of the contractor for the
various items of work to which these obligations apply.
The contractor’s attention is also drawn to the provisions of clauses 10209 or 10308 in regard
to instituting specific process-control systems.
For continuous concrete and asphalt-production processes. the engineer may order the
contractor to augment the above-mentioned control system by introducing a system of process
control for monitoring the various properties to be controlled. The specific system used shall
be subject to the engineer's approval, and the attention of the contractor is drawn to the
systems described in clause 4.4 of TRH5, which is normally regarded as suitable.
The contractor shall take immediate steps to rectify any deviation from the specified
requirements indicated by his process-control system, and the engineer shall have the right to
inspect and be given all details of tests and testing procedures in order to satisfy himself that
the contractor is implementing an adequate process-control system.
The lot shall be conditionally accepted where x ≥ Lr and ≤ L'r , otherwise reject the lot.
n
The values of kr and krd are given in tables 10200/14 and 10200/15.
Sample kr
size (n) φ = 5% φ = 10% φ = 15%
4 0.446 0.123 -0.148
5 0.547 0.238 -0.004
6 0.622 0.320 0.089
7 0.682 0.382 0.158
8 0.732 0.432 0.211
9 0.773 0.474 0.255
10 0.809 0.509 0.292
12 0.867 0.567 0.357
14 0.914 0.612 0.397
16 0.952 0.649 0.434
18 0.985 0.680 0.465
20 1.013 0.707 0.491
Table 10200/15
VALUES OF krd (DOUBLE-LIMIT SPECIFICATION)
Sample krd
size (n) φ = 5%φ = 10%φ = 15%φ = 20%
4 0.338 -0.007 -0.324 -0.708
5 0.451 0.132 -0.130 -0.389
6 0.534 0.226 -0.016 -0.241
7 0.600 0.296 0.065 -0.144
8 0.653 0.352 0.126 -0.073
9 0.698 0.398 0.176 -0.018
10 0.736 0.437 0.217 0.027
12 0.800 0.500 0.283 0.098
14 0.850 0.550 0.334 0.152
16 0.891 0.590 0.375 0.194
18 0.926 0.624 0.409 0.229
20 0.956 0.653 0.438 0.259
10301 SCOPE
This section describes one scheme used for determining compliance with certain requirements
of the specifications in regard to the properties of materials and workmanship, by means of
tests and measurements and by applying statistical judgement plans.
It also covers the requirements in regard to the control to be exercised by the contractor for
monitoring the quality of his work and materials, and the routine tests and inspections to be
carried out by the engineer.
10303 DEFINITIONS
For the purposes of this section the following definitions of terms and symbols shall apply:
(a) Lot
A lot is a sizeable portion of work or quantity of material which is assessed as a unit for the
purposes of quality control, and selected to represent material or work produced by essentially
the same process and from essentially the same materials.
x is the arithmetic mean of a set of "n" test results constituting the sample.
n
(h) Outliers
Where, in a sample, one or more test results differ significantly from the other values
obtained, this difference could be ascribed to an assignable cause, in which case such test
result shall be regarded as an outlier and disregarded when assessing the lot.
To determine whether or not a test result is an outlier, the method given in sub-clause
10304(d) shall be adopted.
test values which shall be regarded as a first submission in terms of sub-clause 10304(e),
because the properties of the first and the second set of test values differ significantly.
(j) Resubmission
The submission of a lot for approval for a second time shall be classified as a resubmission
should it be regarded as a resubmission in terms of sub-clause 10304(e), as the properties of
the first and second sets of test values do not differ significantly.
(ii) Concrete
The lot size shall be determined by the engineer, with due regard to the size and the type of
structure in which the concrete is placed, the specific portion of the structure, and the total
quantity of concrete placed in a day. The lot sizes in concrete structures may therefore vary
considerably, and, particularly in the case of small structures, it may be necessary to combine
samples of the same grade of concrete from different structures, provided that the concrete has
been obtained from the same concrete plant in the same period.
(iii) Other
In other cases, as for example in material stockpiles where the definition of a lot in
accordance with sub-clause 10303(a) does not apply directly, the engineer will determine lot
sizes in each case according to the circumstances.
(d) Outliers
Test results shall be scanned for possible outliers. Where a test result deviates greatly from the
remainder in a lot, it shall, if possible, be re-examined by further testing, and, if there is
reasonable evidence to suggest that the test result is erroneous, it shall be regarded as an
outlier, rejected, and replaced with a fresh test result.
Where repeating a test or re-examining a test result is impossible, method 1 described below
shall be used for identifying outliers for all work except roadbase and bituminous pavement
and surfacing layers. Method 2 shall be used for identifying outliers for roadbase and
bituminous pavement and surfacing layers.
(i) Method 1
Calculate the value of To from: To = (x − x )÷ S
o n n
, where
x n
and S n
are respectively the sample arithmetic mean and standard deviation, and
x o
is the value of the test result differing most from the mean.
Compare the value of To with the value of T for the applicable value of "n", from the table
10300/1.
If the absolute value of To is greater than T, than x o
is an outlier.
Every outlier shall be discarded, and, if possible, be replaced with a new random test value.
(ii) Method 2
In the case of roadbase and asphalt work the following procedure shall be used for identifying
outliers where it is impossible to repeat a test or to reinvestigate a test result:
Calculate the absolute value Co from Co = / xo - x / , where x o
represents the possible
n
outlier.
Compare Co with the critical value C = C0.01; nσ
Where σ is the standard deviation of the population derived from historical data.
If the absolute value Co > C, then the test result x o
shall be regarded as an outlier and shall
be excluded from the sample.
The critical values for different values of "n" are given in tables 10300/2 and 10300/3 for the
different product properties.
Every outlier shall be discarded and replaced by another random test value. The sample mean
x and the sample standard deviation S n shall then be recalculated, if an outlier cannot be
n
replaced, the sample mean and standard deviation shall be calculated on the basis of the
remaining test results. The final number of test results used in the assessment after the
elimination of an outlier shall never be less than four (4).
CRITICAL VALUES C
n
For density For bitumen content For voids in mix
4 3.2 0.4 2.3
5 3.3 0.5 2.4
6 3.5 0.5 2.5
7 3.6 0.5 2.6
(e) Resubmission
Where a lot has been accepted conditionally or has been rejected, the engineer may agree to
its resubmission for approval if:
--it has been reworked and the engineer is satisfied that a proper attempt was made to improve
the properties which were unacceptable;
or
--where, in his opinion there are valid technical reasons therefore.
In both cases a fresh sample shall be taken, and a fresh (second) set of test values determined.
The first and second sets of test values snail then be compared with each other to determine
whether their properties differ significantly.
Where in the opinion of the engineer a significant difference does occur, the submission of the
lot shall be regarded as a first submission and assessed as such, and only the second set of test
values shall then be used for this purpose.
Where in the opinion of the engineer no significant difference occurs, the submission of the
lot shall be regarded and assessed as a resubmission. Where a lot is resubmitted, it shall be
assessed on the same basis as a first submission, except that the original and the second set of
sample results shall be combined for purposes of assessment.
10305 PROCEDURES
The statistical judgement procedures described below will apply to the corresponding product
properties for purposes of acceptance control.
Note:
For rehabilitation or repair work the number of measurements, tests or samples for acceptance
control in respect of the product properties specified in sub-clauses (a) to (f) below shall be as
specified in the project specifications or prescribed by the engineer.
The sample mean x shall not less than the acceptance limit (La) for the sample mean as
n
given in table 10300/4, and no single test value shall be lower than the acceptance limit (Le)
for single values.
Required Minimum average relative compaction Minimum value for any single test for
Layer Compactio Test Method for the following sample sizes the following sample sizes
n 4 5 6 7 8 9 4 5 6 7 8 9
Selected layer 90% AASHTO T-180 density 90.1 90.4 90.6 90.7 90.9 91.0 86.4 86.2 86.0 85.9 85.8 85.7
93% AASHTO T-180 density 93.1 93.4 93.6 93.7 93.9 94.0 89.4 89.2 89.0 88.9 88.8 88.7
95% AASHTO T-180 density 95.1 95.4 95.6 95.7 95.9 96.0 91.4 91.2 91.0 90.9 90.8 90.7
100% AASHTO T-180 density 100.1 100.4 100.6 100.8 100.9 101.0 96.4 96.2 96.0 95.9 95.8 95.7
Subbase 95% AASHTO T-180 density 95.1 95.4 95.6 95.7 95.9 96.0 91.4 91.2 91.0 90.9 90.8 90.7
96% AASHTO T-180 density 96.1 96.4 96.6 96.7 96.9 97.0 92.4 92.2 92.0 91.9 91.8 91.7
97% AASHTO T-180 density 97.1 97.4 97.6 97.7 97.9 98.0 93.4 93.2 93.0 92.9 92.8 92.7
Gravel roadbase 97% AASHTO T-180 density 97.1 97.4 97.6 97.7 97.9 98.0 93.4 93.2 93.0 92.9 92.8 92.7
98% AASHTO T-180 density 98.1 98.4 98.6 98.7 98.9 99.0 94.4 94.2 94.0 93.9 93.8 93.7
100% AASHTO T-180 density 100.1 100.4 100.6 100.8 100.9 101.0 96.4 96.2 96.0 95.9 95.8 95.7
Crushed-stone roadbase
G1 88% Apparent relative density 88.1 88.4 88.5 88.7 88.8 88.9 84.7 84.6 84.4 84.3 84.2 84.1
G2 85% Bulk relative density 85.1 85.4 85.6 95.7 85.9 86.0 81.4 81.2 81.0 80.9 80.8 80.7
G3 98% AASHTO T-180 density 98.1 98.4 98.6 98.7 98.9 99.0 94.4 94.2 94.0 93.9 93.8 93.7
G4 100% AASHTO T-180 density 100.1 100.4 100.6 100.8 100.9 101.0 96.4 96.2 96.0 95.9 95.8 95.7
Asphalt base and 100% (97-% voids in mix) %
100.1 100.3 100.5 100.6 100.7 100.8 97.1 96.9 96.8 96.7 96.6 96.5
surfacing of theoretical density
Shoulders and wearing 93% AASHTO T-180 density
93.2 93.6 93.8 94.0 94.2 94.3 87.9 87.6 87.4 87.2 87.0 86.9
course
Plant mixed pavement 100% AASHTO T-180 density
100.1 100.3 100.5 100.7 100.8 100.9 96.4 96.2 96.0 95.9 95.8 95.7
layers (section 3700)
Sample Maximum deviation from the sample Maximum deviation of any single test
size mean from the sample binder content value from the specified binder
(number) (%of binder) content
(% of binder)
Gap-graded and Continuous, semi- Gap-graded and Continuous and
non-homogeneous gap-graded and semi-gap-graded open-graded mixes
modified binder open-graded mixes
mixes and slurry conventional and
seals homogeneous
modified binder
mixes
2 0.51 0.37 0.76 0.54
3 0.44 0.33 0.81 0.58
4 0.41 0.30 0.84 0.60
5 0.38 0.29 0.87 0.62
6 0.36 0.27 0.89 0.64
7 0.35 0.25 0.91 0.65
8 0.33 0.25 0.92 0.66
2) x ≥ Ls -
n ∆B, where:
(a) General
Where a lot is rejected under a statistical judgement plan described in this section but the test
results are such that the lot complies with the requirements for conditional acceptance
specified hereafter, the engineer may accept the lot conditionally, that is, the lot may be
accepted at reduced payment in lieu of complete rejection, provided that
1) conditional acceptance shall be in the sole discretion of the engineer and is not an option
which may be exercised by the contractor or a right he may claim;
2) the lot is approved in respect of all other requirements not judged by a statistical judgement
plan:
3) the contractor shall have the option, at his own cost, to remove work which has been
conditionally accepted and replace it with work which complies with the requirements for
acceptance at full payment;
4) conditional acceptance and the corresponding reduced payment shall apply only in respect
of the work and properties listed in sub-clause 10307(b) below.
Property Structure
Relative compaction (i) Asphalt base or surfacing
(ii) Chemically stabilized layers
(iii) Plant mixed paver laid layers
Bituminous-binder content Asphalt base or surfacing
Cementitious-binder content or Chemically stabilized layers
strength requirements
28-day cube compressive All structural concrete (excepting concrete
strength pavements)
(i) Case 1
The lot complies with the requirement for sample mean, but not in all cases with the
requirement for individual test values.
The lot may be accepted conditionally, subject to the following additional conditions:
(ii) Case 2
The lot complies with the requirements for individual test values but not with the
requirements for sample mean.
The lot may be accepted conditionally on condition that the sample mean x lies within the
n
rejection limits given in table 10300/9.
(i) Case 1
The lot complies with the requirements for sample mean but not in all cases with the
requirements for single values.
fr is always taken as being equal to 0.85.
(ii) Case 2
The lot complies with the requirements for single values, but not with the requirements for
sample mean ( x ).
n
(iv) Concrete
Items 84.01, 84.02 and 84.03.
No reduction shall apply to payment items for formwork, reinforcing or pre-stressing tendons.
(vi) General
Where payment items are incorporated in the project specifications or have been amended in
the bills of quantities, the payment-reduction factor shall apply to the payment items
corresponding to the payment items mentioned above.
Where a lot is conditionally accepted in regard to more than one property, the payment-
reduction factor for each property shall be calculated, and the factor giving rise to the largest
reduction shall be applied, except in the case of concrete pavements when the provisions of
clause 7120(f) shall apply.
The contractor’s attention is also drawn to the provisions of clauses 10209 or 10308 in regard
to instituting specific process-control systems.
For continuous concrete and asphalt-production processes, the engineer may order the
contractor to augment the above control system by introducing a process control system for
monitoring the various properties to be controlled. The specific system to be applied shall be
subject to the engineer's approval, and the attention of the contractor is drawn to the Systems
described In clause 4.4 of TRH5, which will normally be regarded as suitable.
The contractor shall take immediate steps to rectify any deviation from the specified
requirements indicated by his process-control system, and the engineer shall have the right to
inspect and be given all details of tests and testing procedures in order to satisfy himself that
the contractor is implementing adequate process control system.