Professional Documents
Culture Documents
net/publication/272182158
CITATIONS READS
14 962
1 author:
Kiyoshi Yamashita
Takenaka Research & Development Institute
45 PUBLICATIONS 401 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Kiyoshi Yamashita on 10 April 2015.
Keywords: piled raft, settlement, load sharing, measurement, case history, seismic loading
ABSTRACT: This paper offers field measurements on the settlement and the load sharing of piled rafts in
Japan. In the first part of this paper, the measurement results obtained from the selected structures on piled
rafts, completed in 1984 to 2009, are overviewed and general aspects of the foundation settlements and the
load sharing between raft and piles are discussed. In the second part of this paper, the two buildings on piled
rafts subjected to the seismic loading during the 2011 Tohoku Pacific Earthquake are presented and the
effects of the strong seismic motion on the behavior of the piled rafts are discussed.
piles and the load sharing between the raft and the
piles, field measurements on the foundation
settlement and the axial loads of the piles, the
contact pressures beneath the raft were carried out.
In the 1980s and 1990s, piled rafts were applied to
several structures, mainly small-scale structures
(Kakurai, 2002). These foundations may be called
‘piled rafts of the first generation in Japan’.
Figure 3. Schematic view of the four-story building with soil Figure 4. Foundation plan with locations of monitoring
profile. devices.
3 CASE HISTORIES IN 2000S ・It has to be proved that the factor of safety
against the ultimate bearing capacity of a piled
3.1 Introduction raft foundation is larger than 3.0. The ultimate
In the early 2000s, a basic framework of design bearing capacity of the piled raft foundation can
method, including seismic design method, for piled be replaced with the ultimate bearing capacity of
rafts has been established in Japan (AIJ, 2001). To the raft foundation alone (ignoring the effect of
confirm the validity of the design method, field the piles).
measurements on the settlements and the load ・It has to be proved that the maximum settlement
sharing between the raft and the piles have been and the maximum differential settlement are less
carried out for the selected structures. Table 1 shows than the allowable values. The maximum
the case histories of the piled rafts completed in the differential settlement can be replaced with the
2000s (Yamashita et al., 2011a; Yamashita et al., maximum angular rotation.
2011b).
Typical values for the limited allowable angular
3.2 Design method rotation are 1/1000 to 1/500 radian in Japan. The
settlements of the foundations, as well as the load
The design method for the piled rafts listed in Table sharing between raft and piles, were computed by
1 was based on the following common design the simplified method of analysis developed by
criteria. The design criteria under working load Yamashita et al. (1998). The deformation parameters
conditions are as follows: of the soil were determined based on the shear
81
Table 1. Case histories of piled rafts in 2000s.
㻯㼍㼟㼠㻙㼕㼚㻙㼜㼘㼍㼏㼑
㻝㻝㻙㼟㼠㼛㼞㼥㻌㼛㼒㼒㼕㼏㼑㻌㼎㼡㼕㼘㼐㼕㼚㼓 㻭㼕㼏㼔㼕 㻞㻜㻜㻠㻙㻜㻡 㻢㻜㻚㻤 㻝㻤㻝 㻟㻚㻜,㻟㻚㻢 㻝㻣㻚㻜 㻠㻜 㻞㻣㻚㻡,㻞㻢㻚㻥 㻝㻚㻝㻛㻝㻚㻠 *㻙㻝㻚㻡㻛㻝㻚㻤 *
㼏㼛㼚㼏㼞㼑㼠㼑㻌㼜㼕㼘㼑
㻮㼛㼞㼑㼐㻌㻌㼜㼞㼑㼏㼍㼟㼠
㻝㻟㻙㼟㼠㼛㼞㼥㻌㼔㼛㼟㼜㼕㼠㼍㼘 㻻㼟㼍㼗㼍 㻞㻜㻜㻠㻙㻜㻡 㻡㻝㻚㻟 㻝㻢㻥 㻢㻚㻠 㻞㻚㻡 㻝㻣 㻝㻥㻚㻜 㻜㻚㻤㻙㻝㻚㻜
㼏㼛㼚㼏㼞㼑㼠㼑㻌㼜㼕㼘㼑
㻮㼛㼞㼑㼐㻌㻌㼜㼞㼑㼏㼍㼟㼠
㻴㼍㼐㼞㼛㼚㻌㼑㼤㼜㼑㼞㼕㼙㼑㼚㼠㼍㼘㻌㼔㼍㼘㼘 㻵㼎㼍㼞㼍㼗㼕 㻞㻜㻜㻡㻙㻜㻣 㻝㻥㻚㻜 㻞㻡㻥-㻠㻠㻞 㻤㻚㻜-㻝㻟㻚㻠 㻠㻚㻜 㻟㻣㻝 㻞㻞㻚㻜-㻞㻡㻚㻣 㻜㻚㻢㻙㻜㻚㻤
㼏㼛㼚㼏㼞㼑㼠㼑㻌㼜㼕㼘㼑
㻯㼍㼟㼠㻙㼕㼚㻙㼜㼘㼍㼏㼑
㻠㻣㻙㼟㼠㼛㼞㼥㻌r㼑㼟㼕㼐㼑㼚㼠㼕㼍㼘㻌㼠㼛㼣㼑㼞 㻭㼕㼏㼔㼕 㻞㻜㻜㻢㻙㻜㻥 㻝㻢㻝㻚㻥 㻢㻜㻜 㻠㻚㻟 㻞㻚㻡 㻟㻢 㻡㻜㻚㻞 㻝㻚㻡㻙㻝㻚㻥㻛㻞㻚㻥*
㼏㼛㼚㼏㼞㼑㼠㼑㻌㼜㼕㼘㼑
㻮㼛㼞㼑㼐㻌㻌㼜㼞㼑㼏㼍㼟㼠
㻣㻙㼟㼠㼛㼞㼥㻌㼛㼒㼒㼕㼏㼑㻌㼎㼡㼕㼘㼐㼕㼚㼓 㼀㼛㼗㼥㼛 㻞㻜㻜㻟㻙㻜㻠 㻞㻥㻚㻠 㻝㻜㻜 㻝㻚㻢,㻞㻚㻞 㻝㻚㻡 㻣㻜 㻞㻥㻚㻤,㻟㻜㻚㻠 㻜㻚㻢㻙㻜㻚㻥
㼏㼛㼚㼏㼞㼑㼠㼑㻌㼜㼕㼘㼑
㻯㼍㼟㼠㻙㼕㼚㻙㼜㼘㼍㼏㼑
㻝㻥㻙㼟㼠㼛㼞㼥㻌㼞㼑㼟㼕㼐㼑㼚㼠㼕㼍㼘㻌㼎㼡㼕㼘㼐㼕㼚㼓 㻷㼍㼓㼛㼟㼔㼕㼙㼍 㻞㻜㻜㻡㻙㻜㻢 㻣㻡㻚㻤 㻞㻡㻣 㻟㻚㻞 㻟㻚㻜 㻞㻤 㻢㻞㻚㻤 㻝㻚㻞㻛㻝㻚㻤 *,㻝㻚㻟㻛㻞㻚㻞 *
㼏㼛㼚㼏㼞㼑㼠㼑㻌㼜㼕㼘㼑
㻮㼛㼞㼑㼐㻌㻌㼜㼞㼑㼏㼍㼟㼠
㻝㻞㻙㼟㼠㼛㼞㼥㻌㼞㼑㼟㼕㼐㼑㼚㼠㼕㼍㼘㻌㼎㼡㼕㼘㼐㼕㼚㼓 㼀㼛㼗㼥㼛 㻞㻜㻜㻣㻙㻜㻤 㻟㻤㻚㻣 㻝㻥㻥 㻠㻚㻤 㻝㻚㻤 㻝㻢 㻠㻡㻚㻜 㻜㻚㻥㻙㻝㻚㻞
㼏㼛㼚㼏㼞㼑㼠㼑㻌㼜㼕㼘㼑
㻼㼕㼘㼑㼐㻌㼞㼍㼒㼠 㼣㼕㼠㼔㻌㼓㼞㼛㼡㼚㼐㻌㼕㼙㼜㼞㼛㼢㼑㼙㼑㼚㼠
* 㻰㼕㼍㼙㼑㼠㼑㼞㻌㼛㼒㻌㼑㼚㼘㼍㼞㼓㼑㼐㻌㼎㼍㼟㼑
modulus at very small strains. The secant shear 169 kPa in the high-rise section and 114 kPa in the
modulus was set to 0.30 times the shear modulus at low-rise section. In the low-rise section, a raft
very small strains in the analysis. foundation was proposed because the consolidation
The design criteria under seismic loading yield stresses of the soft sandy silt and the silty clay
conditions are as follows: below the raft were slightly larger than the average
・It has to be proved that the factor of safety against contact pressure. In the high-rise section, to reduce
the ultimate bearing capacity of the piled raft is consolidation and differential settlement, a piled raft
larger than 1.5 under vertical loading together foundation consisting of seventeen 19-m long PHC
with lateral loading. (pretensioned spun high-strength concrete) piles in
・It generally has to be proved that the factor of the inside and 198 steel-H piles built in the
safety against the ultimate bearing capacity of the soil-cement diaphragm walls in the perimeter was
piles is larger than 1.5 against the maximum axial proposed. The piles were constructed by inserting
load assumed in the design load sharing. the PHC piles into a pre-augered borehole filled with
mixed-in-place soil cement.
The influence of the lateral loading on the piled Figure 7 shows the foundation plan with a layout
raft has to be considered, i.e., the maximum bending of the piles and the locations of the monitoring
moment and the shear force on the cross-sections of devices. The two piles at locations of 3C and 4C
the pile evaluated by the analytical method were installed with a couple of LVDT-type strain
developed by Hamada et al. (2009) should be less gauges at the pile head. Four earth pressure cells and
than the design structural strength of the piles. one piezometer were installed beneath the raft. The
vertical ground displacement below the raft was
3.3 Thirteen-story hospital on soft clay measured near the center of the high-rise section by
differential settlement gauges. The settlements of the
The hospital building is located in Osaka (Yamashita foundation were measured at the monitoring points
et al., 2011a). Figure 6 shows a schematic view of of the selected columns by an optical level.
the building and the foundation with a soil profile. Figure 8 shows the vertical ground displacement
The building consists of a thirteen-story high-rise measured at the depth of 7.5 m, which is
section and a four-story low-rise section. The approximately equal to the foundation settlement,
high-rise part is a steel-framed structure, while the with the settlement of the raft measured at column
low-rise section and the basement are a reinforced 3C by an optical level. The ground displacement
concrete construction. The soil profile down to a reached 20.6 mm at the end of observation, 52
depth of 8 m is made of loose sand and silty sand. months after the end of construction. The maximum
From the depth of 8 to 21 m, there lie soft sandy silt angular rotation was 1/1440 radian at the edge of the
and silty clay layers. high-rise section.
The average contact pressure over the raft was
82
㻿㼠㼑㼑㼘㻙㻴㻌㼜㼕㼘㼑㼟㻌㼕㼚㻌
㼟㼛㼕㼘㻙㼏㼑㼙㼑㼚㼠㻌
㼐㼕㼍㼜㼔㼞㼍㼓㼙㻌㼣㼍㼘㼘㼟㻌
Figure 6. Schematic view of the building and foundation Figure 7. Layout of piles with locations of monitoring devices.
with soil profile.
Figure 8. Measured settlement of ground and raft. Figure 9. Measured axial loads of piles 3C and 4C.
Load (kN)
㻟㻜㻜㻜㻜
㻞㻜㻜㻜㻜
㻝㻜㻜㻜㻜
㻜
㼀㼛㼠㼍㼘㻌㼘㼛㼍㼐
㻜㻞㻜
㻾㼍㼒㼠㻌㼘㼛㼍㼐
㻠㻜㻢㻜㻤㻜
㻝㻜㻝㻞
㻝㻠㻝㻢㻝㻤
㻞㻜㻞㻞
Time (day)
㻮㼡㼛㼥㼍㼚㼏㼥
㻜㻜 㻜 㻜㻜㻜㻜㻜
㻜㻜㻜㻜㻜㻜
㻜㻜㻜㻜
系列1
系列5
系列6
㻼㼕㼘㼑㻌㼘㼛㼍㼐㻌
㻝㻜㻜
㻡㻜
㻜
㻜 㻞㻜㻜 㻠㻜㻜 㻢㻜㻜 㻤㻜㻜 㻝㻜㻜㻜 㻝㻞㻜㻜 㻝㻠㻜㻜 㻝㻢㻜㻜 㻝㻤㻜㻜 㻞㻜㻜㻜 㻱㼒㼒㼑㼏㼠㼕㼢㼑㻌
㼘㼛㼍㼐㻌
㻱㻝 㻱㻞 㻱㻟 㻱㻠 㼃 系列5
Figure 10. Measured contact pressures and pore-water pressure. Figure 11. Load sharing between raft and piles in
tributary area.
Figure 9 shows the measured axial loads of the load, is 23.8 MN. The sum of the measured
two piles. Figure 10 shows the development of the pile-head loads and the raft load in the tributary area
measured contact pressures of the raft and the is generally consistent with the sum of the design
pore-water pressure beneath the raft. Figure 11 load of the two columns. The ratios of the load
shows the time-dependent load sharing among the carried by the piles to the effective load were
piles, the soil and the buoyancy in the tributary area estimated to be 0.60 to 0.62 and those to the total
of two columns, 3C and 4C. The sum of the load were estimated to be 0.45 to 0.46, respectively,
measured pile-head loads and the raft load in the 25 to 52 months after the end of construction.
tributary area varied from 28 to 29 MN 25 to 52
months after the end of construction. The sum of the 3.4 Forty-seven-story residential tower on medium
design vertical load of the two columns, which sand
corresponds to the sum of the dead load and the live
83
㻡㻰㻌 㻣㻰㻌
㻡㻰㻌 㻣㻰㻌
㼀㼞㼕㼎㼡㼠㼍㼞㼥㻌 㼍㼞㼑㼍㻌
㻝㻢㻝㻚㻥㼙㻌
㼀㼞㼕㼎㼡㼠㼍㼞㼥㻌 㼍㼞㼑㼍㻌
㻿㻼㼀㻌 㻿㻙㼣㼍㼢㼑㻌
㻺㻙㼂㼍㼘㼡㼑㻌 㼂㼟㻔㼙㻛㼟㻕㻌
㻳㻸±㻌㻜
㻜 㻢㻜 㻜
㻜㻌 㻌 㻌 㻡㻜㻌 㻜㻌 㻌 㻌 㻌㻡㻜㻜
㻡㻜㻜㻌 㻸㼍㼙㼕㼚㼍㼠㼑㼐㻌㼞㼡㼎㼎㼑㼞㻌㼎㼑㼍㼞㼕㼚㼓㼟㻌 Figure 13. Layout of piles with locations of monitoring devices.
㻿㼕㼘㼠
㻿㼍㼚㼐㻌㼍㼚㼐㻌㼓㼞㼍㼢㼑㼘 㻡㻚㻟㼙㻌 㻡㻚㻤㼙㻌 㻠㻚㻟㼙㻌
㻝㻜
㻿㼍㼚㼐
㻝㻤㼙㻌
㻞㻜
㻿㼕㼘㼠
㻰㼑㼜㼠㼔㻌㻔㼙㻕
㻟㻜 㻿㼍㼚㼐
㻿㼍㼚㼐㻌㼍㼚㼐㻌㼓㼞㼍㼢㼑㼘
㻟㻞㼙㻌
㻠㻜 㻿㼍㼚㼐
㻠㻝㼙㻌
㻿㼕㼘㼠
㻡㻜 㻡㻞㻚㻠㼙㻌
㻿㼍㼚㼐㻌㼍㼚㼐㻌㼓㼞㼍㼢㼑㼘 㻡㻠㻚㻡㼙㻌
㻢㻜
㻣㻜㼙㻌 㻿㼑㼠㼠㼘㼑㼙㼑㼚㼠㻌㼓㼍㼡㼓㼑㼟㻌
84
■
Figure 15. Measured axial loads of the piles 7D. Figure 16. Measured contact pressures and pore-water pressure.
㻠㻜
㻟㻜
㻞㻜
㻝㻜
㼀㼛㼠㼍㼘㻌㼘㼛㼍㼐
㻜
㻾㼍㼒㼠㻌㼘㼛㼍㼐
㻜 㻞㻜 㻠㻜 㻢㻜 㻤㻜 㻝㻜 㻝㻞
㻮㼡㼛㼥㼍㼚㼏㼥
㻜 㻜 㻜 㻜 㻜㻜 㻜㻜
系列3
㻰㼑㼟㼕㼓㼚㻌㼘㼛㼍㼐㻌㻞㻢㻚㻟㻹㻺
㻼㼕㼘㼑㻌㼘㼛㼍㼐㻌
㻱㼒㼒㼑㼏㼠㼕㼢㼑㻌
㼘㼛㼍㼐㻌
(a)Load sharing between raft and pile (b)Ratio of load carried by pile
Figure 17. Load sharing between raft and piles in tributary area of column 7D.
load versus time together with that to the total load construction and at the end of observation.
versus time. The sum of the measured pile-head load
and raft load on the tributary area was 29.6 MN on 3.5 Piled raft with ground improvement
columns 7D at the end of observation. The design The seven-story office building is located in
vertical load of columns 7D, which correspond to Tokyo (Yamashita et al., 2011b). Figure 18 shows a
the sum of the dead load and the live load, was 35.6 schematic view of the building and the foundation
MN. Therefore, the sum of the measured pile-head with a soil profile. The building is a steel-framed
load and the raft load on the tributary area was structure. The soil profile down to a depth of 11 m
consistent with the design load. The ratios of the from the ground surface is made of soft silt and
load carried by the piles to the effective load on the loose sand. Between depths of 11 m to 42 m, there
tributary area of columns 5D and 7D were estimated lies a thick soft to medium silt stratum, underlain by
to be 0.93 and 0.87, respectively, both at the end of a diluvial very dense sandy layer.
Figure 18. Schematic view of the building and foundation with soil profile.
85
An assessment of a potential of liquefaction displacements below the raft were measured by
during earthquakes was carried out using the differential settlement gauges. The settlements of the
simplified method (Tokimatsu and Yoshimi, 1983). foundation were measured by an optical level.
It indicated that the loose sand had a potential of Figure 21 shows the measured vertical ground
liquefaction during earthquakes with the peak displacements below the raft at three depths relative
horizontal ground acceleration of 2.0 m/s2. to a reference point at a depth of 46 m. The ground
Therefore, to cope with the liquefiable sand and displacement at a depth of 3.0 m reached 21.9 mm at
ensure bearing capacity of a raft, grid-form deep the end of observation, 72 months after the end of
cement mixing walls (TOFT method) shown in Fig. construction. The settlements of the foundation
19 were employed below the raft. As to the TOFT measured by the optical level were 17 to 31 mm and
method, typical compressive strength of the soil the maximum angular rotation of the raft was 1/1200
cement is 2 N/mm2 and the high-modulus radian four years after the end of construction.
soil-cement walls confine loose sand so as not to Figure 22 shows the time-dependent load sharing
cause excessive shear deformation to the loose sand among the piles, the soil, the soil-cement walls and
during earthquakes. The effectiveness of the TOFT the buoyancy in the tributary area, where the total
method was confirmed during the 1995
Hyogoken-Nambu earthquake (Tokimatsu et al.,
1996).
The average contact pressure over the raft was
100 kPa. In order to reduce overall and differential
settlement due to consolidation of the soft cohesive
soil, a piled raft consisting of seventy 30-m long
PHC piles with grid-form deep cement mixing walls
was employed. Figure 20 shows a layout of the piles
and the grid-form soil-cement wall with the
locations of the monitoring devices. Two piles were
installed with a couple of LVDT-type strain gauges.
Two earth pressure cells and a piezometer were
installed beneath the raft. The vertical ground Figure 19. Grid-form deep cement mixing walls (TOFT
method).
■
○ ◎ d=0.9m ○ d=0.8m
○○
㻯 ○ ● ○ ○ ○ ○ ○ ○ ○ ● ● ○
○
Tributary area d=0.7m d=0.6m
㻟㻞㻚㻠㼙
㻝㻜㻚㻤㼙
○ ●
☆
○
○○
㻮 ○ ○ ○
● ● ○ ○ ○ ○
E1
○ ○ ● ●
E2
○ Monitoring devices
㻝㻜㻚㻤㼙
W ● ○
○ ○ Instrumented pile
○
○ ● ● ○ ○ ● ● ○ ○ ● ● ○ ○ ◎ ◎
㻭
● ● ●
□ Earth pressure cell
△ Piezometer ■
㻝㻜㻚㻤㼙 㻝㻜㻚㻤㼙 㻝㻜㻚㻤㼙 㻝㻜㻚㻤㼙 㻝㻜㻚㻤㼙 㻝㻜㻚㻤㼙 㻝㻜㻚㻤㼙 㻝㻜㻚㻤㼙 㻝㻜㻚㻤㼙 㻝㻜㻚㻤㼙 㻝㻜㻚㻤㼙
☆ Settlement gauges
㻺
㻝㻝㻤㻚㻤㼙
① ② ③ ④ ⑤ ⑥ ⑦ ⑧ ⑨ ⑩ ⑪ ⑫
Figure 20. Layout of piles and grid-form deep cement mixing walls with locations of monitoring devices.
Figure 21. Measured vertical ground displacement. Figure 22. Time-dependent load sharing between raft and
piles in tributary area.
86
■
load is assumed to be equal to the sum of the design 㻜㻌
㼀㼕㼙㼑㻌(㼐㼍㼥㼟)
㻞㻜㻜㻌 㻠㻜㻜㻌 㻢㻜㻜㻌 㻤㻜㻜㻌 㻝㻜㻜㻜㻌㻝㻞㻜㻜㻌㻝㻠㻜㻜㻌㻝㻢㻜㻜㻌㻝㻤㻜㻜㻌㻞㻜㻜㻜㻌㻞㻞㻜㻜㻌㻞㻠㻜㻜㻌㻞㻢㻜㻜㻌
column load. The ratio of the load carried by the 㻜㻌
㻿㼑㼠㼠㼘㼑㼙㼑㼚㼠㻌㻔㼙㼙㻕
end of observation. This was supposed to be caused
by a decrease in raft resistance due to the 㻞㻜㻌
㻝㻚㻟㻜㻌
4 DISCUSSIONS ON MEASUREMENTS
㻝㻚㻞㻜㻌
㻿㼠㻛㻿㼑㼛㼏㻌
4.1 Settlement
The vertical ground displacements just below the 㻝㻚㻝㻜㻌
㻝㻥㼙㻌
the others, possibly, because a decrease in raft 㻿㻼㼀㻌 㻿㻙㼣㼍㼢㼑㻌
㻺㻙㼂㼍㼘㼡㼑㻌 㼂㼟㻔㼙㻛㼟㻕㻌
㻰㼑㼜㼠㼔㻌 㻔㼙㻕㻌
㻿㼍㼚㼐㼥㻌㼟㼕㼘㼠㻌
㻹㼡㼐㼟㼠㼛㼚㼑㻌 㻠㻝㼙㻌
㻿㼑㼠㼠㼘㼑㼙㼑㼚㼠㻌㼓㼍㼡㼓㼑㼟㻌 㻤㻜㼙㻌
5 SEISMIC BEHAVIOUR OF PILED RAFTS Figure 26. Schematic view of the building and foundation with
soil profile.
5.1 The 2011 Tohoku Pacific Earthquake N
K
㻱㼤㼜㼑㼞㼕㼙㼑㼚㼠㼍㼘㻌㼘㼕㼚㼑
★㻼㻝 㻼㻞
The earthquake struck the sites of the two
buildings, e.g. the hadron experimental hall and the
twelve-story building listed in Table 1. The 㻮㼑㼍㼙㻌㼐㼡㼙㼜
following shows the field measurement results on 㻮㼑㼍㼙㻌㼘㼕㼚㼑
the piled rafts before and after the earthquake as well
as discussions on the effects of the seismic motion
on the foundation behaviour. 㻡㻢㼙 㻞㻜㼙
㻠㻝㻚㻜㼙㻌 㻿㼕㼘㼠㻌
㼃㼑㼍㼠㼔㼑㼞㼑㼐㻌
㼙㼡㼐㼟㼠㼛㼚㼑㻌
㻜㻌
Figure 28. Measured vertical ground displacements. Figure 29. Profiles of vertical ground displacements.
the peak ground acc elerations at a depth of 6 m occurred mostly by the compression of the silty soil
below the ground surface were recorded to be 3.24 between depths o f 23 and 41 m. The compression of
m/s2 for the horizontal direction and 2.77 m/s2 for the silty soil seemed to be caused by the vertical
the vertical direction (Hashimura et al., 2011). Photo cyclic loading due to the inertial force acting on the
1 shows the ground subsidence along the northeast building.
side of the experimental hall, which reached a Figure 30 shows the measured axial loads of the
maximum of 1.2 m after the earthquake. piles. Figure 31 shows the measured contact
Figure 28 shows the measured vertical ground pressures and pore-water pressure beneath the raft.
displacements relative to the reference point. The After the earthquake, the axial loads of pile P1
ground displacement at the depth of 12.5 m was decreased only slightly and the contact pressures
approximately equal to “foundation settlement” in near pile P1 increased slightly. On the other hand,
case that it was initialized just before the casting of the axial load of pile P2 at pile head increased 30%
the foundation mats. The foundation settlement and the contact pressures near pile P2 increased 39%,
reached 20.7 mm just before the earthquake. Figure possibly, because the frictional resistance at the
29 shows the profiles of the measured vertical interface of the outside wall of the structure and the
ground displacements before and after the back-filled sand was considerably reduced by the
earthquake. The foundation settlement increased 4.1 subsidence of the back-filled sand due to the strong
mm to 24.8 mm 28 days after the earthquake when seismic motion. The pore-water pressures were not
the monitoring system was restored. It can be seen affected by the seismic motion.
that the increments in the ground displacements
Figure 32. Load sharing between raft and piles in tributary Figure 33. Load sharing between raft and piles in tributary
area of pile P1. area of pile P2.
Figure 32 shows the time-dependent load sharing the ratios of the pile load to the effective load were
among the piles, the soil and the buoyancy on the quite stable.
tributary area of pile P1. Figure 33 shows those on
the tributary area of pile P2. The ratio of the load 5.3 Twelve-story base-isolated building in Tokyo
carried by the piles to the effective load on the The twelve-story residential building is located in
tributary area of pile P1 was estimated to be 0.85 Tokyo (Yamashita et al., 2011b). The building is a
and that of pile P2 was 0.67 just before the reinforced concrete structure with a base isolation
earthquake. The former decreased only slightly to system of laminated rubber bearings. Figure 34
0.82 and the latter decreased slightly to 0.57 28 days shows a schematic view of the building and the
after the earthquake. In one year after the earthquake,
Figure 34. Schematic view of the building and foundation with soil profile.
90
㻼㼕㼘㼑㻌㼐㼕㼍㼙㼑㼠㼑㼞 㻹㼛㼚㼕㼠㼛㼞㼕㼚㼓㻌㼐㼑㼢㼕㼏㼑㼟 ◆ 㻭㻞(㻳㻸㻙㻝㻡㼙)
㻞㻚㻡㼙 㻞㻚㻡㼙
㻝㻚㻞㼙 㻵㼚㼟㼠㼞㼡㼙㼑㼚㼠㼑㼐㻌㼜㼕㼘㼑 ◆ 㻭㻝(㻳㻸㻙㻝㻚㻡㼙)
㻝㻚㻜㼙 㻱㼍㼞㼠㼔㻌㼜㼞㼑㼟㼟㼡㼞㼑㻌㼏㼑㼘㼘 ◆ 㻭㻟(㻳㻸㻙㻡㻜㼙)
㻜㻚㻤㼙 㻼㼕㼑㼦㼛㼙㼑㼠㼑㼞
㻤㻚㻜㼙
㻿㼑㼠㼠㼘㼑㼙㼑㼚㼠㻌㼓㼍㼡㼓㼑㼟
◆ 㻭㼏㼏㼑㼘㼑㼞㼛㼙㼑㼠㼑㼞
㻜㻚㻤㼙
㻲
㻭㼏㼏㼑㼘㼑㼞㼍㼠㼕㼛㼚㻌㻔㼙㻛㼟㻞㻕㻌
㻤㻚㻤㼙
㻰
㻟㻟㻚㻞㻡㼙
㻝㻜㻚㻟㼙
㻱㻝 㻱㻟 㻱㻡 㼃
㻡㻮 㻣㻮
㻮 㻰㻝 㻰㻞
㻱㻞 㻱㻠 㻱㻢
㻝㻜㻚㻡㻡㼙
㼀㼞㼕㼎㼡㼠㼍㼞㼥㻌㼍㼞㼑㼍
① ③ ⑤ ⑦ 㼀㼕㼙㼑㻌㻔㼟㻕㻌
㻥㻚㻜㻞㻡㼙 㻤㻚㻠㼙 㻥㻚㻜㻞㻡㼙
㻟㻜㻚㻜㻡㼙 Figure 36. Time histories of EW accelerations of ground and
structure.
Figure 35. Layout of piles and grid-form deep cement mixing
walls with locations of monitoring devices.
㻹㼍㼞㻚㻌㻝㻝㻘㻌㻞㻜㻝㻝㻌
91
㻹㼍㼞㻚㻌㻝㻝㻘㻌㻞㻜㻝㻝㻌 㻹㼍㼞㻚㻌㻝㻝㻘㻌㻞㻜㻝㻝㻌
㻢㻚㻜㼙㻌
㻝㻢㻚㻜㼙㻌
(a) Pile 5B
㻹㼍㼞㻚㻌㻝㻝㻘㻌㻞㻜㻝㻝㻌
Figure 40. Contact pressures between raft and deep mixing
walls and those between raft and soil.
㻢㻚㻜㼙㻌
㻝㻢㻚㻜㼙㻌
㻠㻢㻚㻡㼙㻌
㻯㼛㼚㼠㼍㼏㼠㻌㼜㼞㼑㼟㼟㼡㼞㼑㻌 (㼗㻼㼍)㻌
㼀㼕㼙㼑㻌㻔㼟㻕㻌
㻯㼛㼚㼠㼍㼏㼠㻌㼜㼞㼑㼟㼟㼡㼞㼑㻌 (㼗㻼㼍)㻌
(b) Pile 7B
㼀㼕㼙㼑㻌㻔㼟㻕㻌
Figure 38. Measured axial loads of piles 5B and 7B.
㻼㼞㼑㼟㼟㼡㼞㼑㻌 (㼗㻼㼍)㻌
㻭㼤㼕㼍㼘㻌㼘㼛㼍㼐㻌㻔㻹㻺㻕㻌
㼀㼕㼙㼑㻌㻔㼟㻕㻌
㼀㼕㼙㼑㻌㻔㼟㻕㻌
㻹㼍㼞㻚㻌㻝㻝㻘㻌㻞㻜㻝㻝㻌
㼀㼕㼙㼑㻌㻔㼟㻕㻌
(b) Pile 7B
㻰㼑㼟㼕㼓㼚㻌㼏㼛㼘㼡㼙㼚㻌㼘㼛㼍㼐㼟㻌㻟㻢㻚㻜㻹㻺
Figure 39. Fluctuations of axial loads of at pile head.
㻼㼕㼘㼑㼟㻌
pile head were 14.7 MN and 8.3 MN on Mar. 10 and
became 14.8 MN and 8.2 MN on Mar. 15 on piles
5B and 7B, respectively, so that there was little 㻰㼑㼑㼜㻌㼙㼕㼤㼕㼚㼓㻌㻌
change in the pile-head load before and after the 㼣㼍㼘㼘㼟㻌㻌 㻾㼍㼒㼠㻌
92
contact pressures between the raft and the deep 㻹㼍㼞㻚㻌㻝㻝㻘㻌㻞㻜㻝㻝㻌
mixing walls and those between the raft and the soil
together with the pore-water pressure beneath the 㻱㼒㼒㼑㼏㼠㼕㼢㼑㻌㼘㼛㼍㼐㻌
raft. The contact pressures between the raft and the
deep mixing walls were 296 to 316 kPa and those
between the raft and the soil were 39 to 63 kPa on
Mar. 10. The contact pressures, except for the value 㼀㼛㼠㼍㼘㻌㼘㼛㼍㼐㻌
from D1, increased very slightly on Mar. 15. Figure
41 shows the fluctuations of the contact pressure
between the raft and the deep mixing walls and that
between the raft and the soil together with the
pore-water pressure. The amplitude of the contact
pressure between the raft and the deep mixing walls Figure 43. Ratios of load carried by piles to effective load and
was significantly larger than that between the raft total load in tributary area.
and the soil as in the case of the static measurements.
The excess pore-water pressure was considerably
smaller than the contact pressures between the raft
and the soil.
Figure 42 shows the time-dependent load sharing
among the piles, the deep mixing walls, the soil and
the buoyancy in the tributary area of columns 5B
and 7B. Figure 43 shows the ratio of the load carried
㻸㼛㼍㼐㻌㻔㻹㻺㻕㻌
㻼㼕㼘㼑㼟㻌
by the piles to the effective load and that to the total
load in the tributary area versus time. The ratio of
the load carried by the piles to the effective load was
0.67 on Mar. 10 and little change in the ratio could
be observed just after and 13 months after the 㻰㼑㼑㼜㻌㼙㼕㼤㼕㼚㼓㻌㼣㼍㼘㼘㼟㻌
earthquake. Figure 44 shows the time histories of the
load sharing among the piles, the deep mixing walls, 㻿㼛㼕㼘㻌
㼁㼘㼠㼕㼙㼍㼠㼑㻌
㼁㼘㼠㼕㼙㼍㼠㼑㻌
㼁㼘㼠㼕㼙㼍㼠㼑㻦㻌 㼡㼚㼕㼠㻌 㼟㼠㼞㼑㼟㼟㻌 㼍㼠㻌 㼠㼔㼑㻌 㼑㼐㼓㼑㻌 㼛㼒㻌
㼏㼛㼚㼏㼞㼑㼠㼑㻌 㼞㼑㼍㼏㼔㼑㼟㻌 㼠㼔㼑㻌
㻭㼘㼘㼛㼣㼍㼎㼘㼑㻌 㼏㼛㼙㼜㼞㼑㼟㼟㼕㼢㼑㻌㼟㼠㼞㼑㼚㼓㼠㼔㻌㻔㻝㻜㻡㻌
㻭㼘㼘㼛㼣㼍㼎㼘㼑㻌 㻺㻛㼙㼙㻞㻕㻌 㻌
㻭㼘㼘㼛㼣㼍㼎㼘㼑㻦㻌 㼡㼚㼕㼠㻌 㼟㼠㼞㼑㼟㼟㻌 㼍㼠㻌 㼠㼔㼑㻌 㼑㼐㼓㼑㻌 㼛㼒㻌
㼟㼠㼑㼑㼘㻌㼜㼕㼜㼑㻌㼞㼑㼍㼏㼔㼑㼟㻌㼠㼔㼑㻌㼥㼕㼑㼘㼐㻌
㼟㼠㼞㼑㼟㼟㻌 㼕㼚㻌 㼠㼑㼚㼟㼕㼛㼚㻌 㼍㼚㼐㻛㼛㼞㻌
㼠㼔㼍㼠㻌 㼛㼒㻌 㼏㼛㼚㼏㼞㼑㼠㼑㻌 㼞㼑㼍㼏㼔㼑㼟㻌
㻹㼑㼍㼟㼡㼞㼑㼐㻌 㻹㼑㼍㼟㼡㼞㼑㼐㻌 㻞㻛㻟㻚㻡㻌㼠㼕㼙㼑㼟㻌㼠㼔㼑㻌㼏㼛㼙㼜㼞㼑㼟㼟㼕㼢㼑㻌
㼟㼠㼞㼑㼚㼓㼠㼔㻌
94