Work Procedure List

Denso Mexico Silao Plant Phase 3 Project Date: 3-Mar-2022

No. Description Document exposition/sending Approval Start of activity Remark Machinery and main tools
Expected Actual Status Status Date Expected Actual
WAREHOUSE
1 Steel structure erection 1-Nov-2022 18-Nov-2022 Y 25-Nov-2021 15-Nov-2022 25-Nov-2022 Crane, sling, elavation platform,
drill.
2 Roof lamination 17-Jan-2022 19-Jan-2022 Y 9-Feb-2022 31-Jan-2022 10-Feb-2022 Crane, sling, elavation platform,
sheet forming machine, grimper
machine, drill, shackle

3 Wall lamination 31-Jan-2022 4-Feb-2022 Y 25-Feb-2022 14-Feb-2022 25-Feb-2022 Elavation platform, locking
clamp, drill, bending machine,
rope, metal scissors.

4 HVAC equipment on roof 30-march-2022 29-Apr-2022 Crane, sling, drill.


EXPANSION FACTORY
1 Steel structure erection 31-Jan-2022 1-Feb-2022 Y 14-Feb-2022 14-Feb-2022 14-Feb-2022 Crane, elavation platform, drill.

2 Interconection of axis 3 21-Feb-2022 23-Feb-2022 Y 2-Mar-2022 7-Mar-2022 Looking for dates according to Crane, elavation platform,
the inside bldg. users. welding machine.
3 Roof lamination 21-Mar-2022 21-march 21-march 4-Apr-2022 Crane, sling, elavation platform,
sheet forming machine, grimper
machine, drill, shackle

4 Wall lamination 11-Apr-2022 25-Apr-2022 Elavation platform, locking


clamp, drill, bending machine,
rope, metal scissors.

5 Reinforcement of axis 3 16-May-2022 30-May-2022 Crane, elavation platform,


welding machine.
6 Electrical Works 04-april-2022 11-april-2022 elevation platform,drill
7 HVAC equipment on roof 16-May-2022 30-May-2022 Crane, sling, drill.