Professional Documents
Culture Documents
Professor C F Leung
Ph D, C Eng, P Eng (Geo)
e-mail: cvelcf@nus.edu.sg; ceelcf@nus.edu.sg
1
2.1 Slope stability
Method of analysis
• Limit equilibrium analysis
• Factor of safety against slope failure for a
given trial slip surface F
= restoring moment/disturbing moment
where restoring moment is contributed by
the soil resistance (strength) along the slip
surface and disturbing moment is mainly
contributed by weight of soil within the slip
2
Limit Equilibrium Analysis
• φu = 0 (saturated clay undrained condition,
i.e. for temporary slope only)
• Factor of safety of a particular slip
F = restoring moment/disturbing moment
= cuLaR/Wd (see next slide for definition)
• Slip is assumed to be circular
Disturbing moment
(due to weight of soil
W inside slip circle)
= Wd
Resisting moment
(due to shear
strength cu along slip
arc) = cu La R
= cu R2 θ
3
Effect of tension cracks
Depth of
tension
crack Zo
4
Craig Example 9.1
What happen
if there are
tension
cracks (with
or without
water in the
cracks)?
Discuss on
Zo
5
Taylor’s chart
• Applicable to quick and approximate
estimation for temporary slope excavation
(i.e. total stress analysis involving cu and φu)
• Factor of safety (of all possible slip
surfaces) F = cu/(Ns γ H)
where Ns is obtained from the Taylor’s
chart, γ is the unit weight of soil and H is
height of slope (see next slide)
Taylor’s chart
6
Example on Taylor’s chart
Sewerage pipes will be placed in a vertical trench. Estimate
the maximum temporary excavation height for the pipe
installation by adopting a minimum F of 1.3. (Given γ =
17 kN/m3, φu = 0 and cu = 30 kPa, i.e. firm clay).
(1) Vertical trench implies slope angle β = 90o
(2) No information on bedrock so take D as infinity
(3) Ns = 0.26 from Taylor’s chart
(4) F = 1.3 = 30/(0.26 x 17 x H)
Hence maximum excavation depth H = 5.22 m
[Note: H will decrease significantly with time when negative
excess pore pressure (i.e. suction) has time to dissipate.]
7
Bishop’s simplified method
To handle a more general analysis involving
different soils, total or effective stress analysis
etc., Bishop simplified method is the most
commonly used. Assumptions:
– Circular slip analysis
– Limit equilibrium analysis
– Slip surface is divided into a number of slides
– An iteration approach by assuming an initial F until the
left hand and right hand F coincides
8
Equations
• In terms of total stress (temporary excavation)
Factor of safety of a trial slip surface F
= ∑{(cub + W tan φu) sec α/(1 + tan α tan
φu/F)}/(∑W sin α)
Symbols
• b = width of individual slice,
• W = weight soil within each slice,
• α = angle of inclination of base of each slice with
respect to horizontal
• u = pore pressure at mid-base of each slice
• Use the shear strength parameters of the soil that
is in contact with the base of the given slice
[Note: water greatly affects slope stability as it
increases W and u and reduces soil strength.]
9
Example on Bishop method, see earlier figure for slide configuration
From C R Scott
10
Factor of safety
• The above example only gives a factor of safety
against slope failure for a given trial slip surface.
Many trials need to be carried out to obtain F of
all possible trial slices and the factor of safety of a
slope is the absolute minimum F of all F values
determined.
• Hence computer program is required to handle the
analysis.
• Use effective soil parameters c’, φ’ and water
pressure u (long term is more critical) except for
temporary cuts.
Infinite slopes
11
(1) End effect ignored
for a sufficiently long
slope.
(2) Failure plane
(depth z) and water
table (at mz above
failure plane) are
assumed parallel to
the slope surface.
(3) Water flows
parallel to the slope
surface with a simple
flow net.
(4) Taking an inclined
slope length of 1 m
as shown, the pore
pressure u (anywhere
on the failure plane)
and weight of soil can
be determined by
geometry (see left).
Factor of safety F
• F = available shear strength τf/ mobilized shear
strength τ
Mohr-Coulomb concept
• In terms of total stress (short term/end of
construction) τf = cu + σ tan φu
• In terms of effective stress (long term)
τf = c’ + (σ - u) tan φ’
• By geometry (previous slide) [β is slope angle]
– σ = W cos β
– τ = W sin β
12
Example
Discussions
13
Embankment (short term is critical)
uo = original pore
Embankment pressure (before
construction)
Δu = excess pore
pressure built up due to
embankment
construction
tc = time at end of
construction
Factor of safety of slope F increases with time, use total stress analysis!
Slope excavation
After Craig
Factor of safety of slope F
14
Tell-tale signs of slope failure
• Development of cracks especially near the
edges
• Abrupt changes in a short period of time
– soil settlement
– lateral soil movement
– pore water pressure
[Note: quickly stabilise slope base area if
there are danger signs]
15
Slope
failed &
house had
moved
down
Drainage channels
Shotcrete
on slope
protection
on slope
Contiguous bored pile
to stabilise slope
Cut back
of slope Piles
crest
16
2A Derbyshire Road
1.
6
1.555
1.6
Description: Fill
Unit Weight: 17.5
103 Cohesion: 25
101
Description: Peaty clay
99 Unit Weight: 14
97 Cohesion: 20
95
93 Description: Marine clay
91 Unit Weight: 15
89 Cohesion: 20
87
85
83
0 5 10 15 20 25 30 35 40 45 50 55 60
Fig. 11
2.2 Embankment
• Slope stability concern at both edges under
embankment loading
17
Preloading using an embankment
18
19
2.3 Earth pressures
Permanent Retaining structures:
use effective stress soil parameters drained
cohesion c’ and friction angle φ’ plus water
pressure
20
Earth pressure at rest
• Earth pressure at rest situation:
Wall is fixed and therefore soil cannot move
Fixed
wall
• Lateral pressure = po = Ko γz
where Ko is the coefficient of earth pressure at rest
= OCR0.5 (1 - sin φ)
where OCR = overconsolidation ratio
[=1 for normally consolidated (soft) clay; >1 for
overconsolidated (stiff) clay.]
21
Active earth pressure
Soil pushes wall (soil behind a retaining wall situation)
22
Passive earth pressure
23
What you have learned so far is the “Rankine earth pressure theory”
At
rest
24
Earth pressure thrust
• Passive earth pressure thrust PP
= 0.5 Kp γH2 + 2c sqrt(Kp)H (unit kN/m run)
• Soil parameters --
– For permanent wall, use effective stress soil parameters
c’ and φ’
– For temporary wall (e.g. temporary sheet pile wall for
excavation), use total stress soil parameters cu and φu
25
Critical effect of water pressure
From the previous slide, you may note that water has
no Ka (i.e. its K = 1 because it is a liquid). Thus
water pressure can be a major component of the
pressure thrust on a wall especially for sandy
backfill (with Ka << 1). Thus it is good to let the
water behind a retaining wall to drain away as
quickly as possible. That is
– Place sand between wall and impermeable
cohesive backfill
– Provide weep holes at the wall and maintain
them properly during service life of wall
26
Craig Example 6.2
27
Comments:
(1) For retaining wall, backfill is used. Thus soil profile is simple and
earth pressure calculations are easier.
(2) For sheet pile wall, insitu soils are involved. The soil profile can
be complex and earth pressure calculations are very tedious.
28
2.4 Rigid retaining walls
• Stability of wall relies on the weight of wall
and soil above the wall.
Soil above wall base
increases wall stability
soil
Gravity Soil
Wall (active
pressure) soil Cantilever
Soil
wall
(passive
pressure)
29
Weep hole
Old fashion rigid to drain away Reinforced earth
retaining wall water wall (AYE Ayer
Rajah Crescent)
Design checks
• Reinforcement of cantilever wall by
structural engineers
– (Caution: wrong re-bar design and placement
had caused many wall failures)
30
Design check against sliding
Wall may fail by sliding laterally
Factor of safety against sliding failure
F = (ΣHorizontal resistance)/(Σ Horizontal force)
where horizontal resistance = W.tanδ,
W is total weight of wall and soil above wall base
and δ is the angle of friction between wall base
and soil (typically about 0.5 to 0.67φ)
and horizontal force is the active pressure thrust on
the wall.
31
Design check against overturning
Wall may fail by overturning and design is by
examining moment about the wall toe.
F = (Σ resisting moment about toe)
/(Σ overturning moment about toe)
wall
PA
W
Moment arm
toe
Moment
arm
Desired F > 2
PA
Pmax = (W/B)(1+6e/B) e Pmin = (W/B)(1-6e/B)
O.5B
should be < allowable & should be > 0
bearing capacity pmin I.e. e < B/6
pmax [middle third rule]
Base pressure distribution
32
Example on rigid wall (from Craig)
33
34
BCA on slope protection structure
35
2.5
Sheet pile
wall
36
Sheet pile cofferdam
Waler
Close-up view
of ground
anchor
37
Cantilever Sheet pile wall
Steel
sheet
pile
38
Anchored sheet pile wall
Net of water
pressure for
both sides
39
Choose pile section that can resist the bending moment
40
41
2.6 Deep excavation
Retaining wall type Support type
Soldier pile & lagging Lateral strut
Sheet pile wall Raker (inclined strut)
Contiguous bored piles Berm
Diaphragm wall Ground anchors
42
Nil support or single support walls. Applicable for stiff soils and/or
shallow excavation. Previous sheet pile wall analysis is valid.
Refer to
case studies
later
43
2
5
4 (strut)
3 (King post)
44
Deep excavation construction sequence
Placing of strut on
king post and waler
Proceed to second stage excavation
Weak
rock:
Only lean
concrete
required
for such a
deep
excavation
45
Typical modes of failures
46
Design against base heave
47
Earth pressure on supports
Peck’s apparent
pressure diagram
48
Settlement behind wall
• Zone I: Sand and soft to hard clay average
workmanship
• Zone II: a) Very soft to soft clay
– 1) Limited depth of clay below bottom of
excavation
– 2) Significant depth of clay below bottom of
excavation but N < 5.14
b) Settlements affected by construction difficulties
• Zone III: Very soft to soft clay to a significant depth
below bottom of excavation and with N > 5.14
[Stability number N = γH/cb]
Ground settlement
Excessive ground movements when
• excavation is allowed to proceed too deep
before uppermost strut is placed
• layer of stiff clay for sheet pile embedment
is located at great depth
• strength of sheet piles and struts inadequate
49
Example on temporary deep excavation
Base heave check:
F = Nbc/(γH + q)
where Nb = 5.5 for a strip
excavation with H/B = 7/20 =
0.35,
c = cu = 15 kPa,
Average
Cu = 15 kPa H=7m
γ = 16 kN/m3
Thus F = 0.67
grossly inadequate as
expected for excavation in
soft clay. The retaining wall
needs to penetrate deeper into
Width of excavation B = 20 m
sound formation to prevent
base heave.
Earth
pressure
50
Settlement behind wall: Stability number N = γH/cb
= 16 x 7/15 = 7.5 > 5.14. Worst scenario – Zone III soil.
Settlement is expected to be very large.
51
Practical considerations to minimise
ground movement
• good monitoring program
• reduce storage of materials adjacent to
excavation
• excavation of soft soil in small and alternate
stages
• cross-strutting and attachment to king post must
be done as soon as possible
• wedging or jacking to maintain tight contact for
all bracing members
• preloading of struts to remove Preloading
slackness of support system jack
‘Chicken feet’ to
spread load at
waler and corner
52
Basement slab
(usually very thick
and heavily reinforced
to resist uplift)
Excessive settlement
results in the
neighbourhood
(due to rapid
drawdown of water
behind wall)
53
Important points
• Water is a major culprit in retaining
structures and water behind retaining walls
should be drained away quickly
• Deep excavation analysis: base heave,
pressure acting on strut and ground
settlement
• Ground settlement is a major concern for
deep excavation in soft soil and needs to be
monitored frequently.
54