Initiation phase Task:

1. Prepare a primary high level Tender Schedule. (1 page)

a. Should contain up to Level 3

b. Manpower S-Curve

c. Plants S-Curve

d. S-curve (Early and Late)

Ans:

 List Down the Scope

 Plan WBS

 Create Activity

WBS Activity Qty. Productivity Duration


Engineering
Construction Pipe laying 500m 10m/d 50
T&C
 Quantity analysis for the activity

1. Create Project in P6

2. Upload resources Manpower and Material and Plant

3. Generate S-Curves