You are on page 1of 4

Abstract for R.C.C Hand Rail for 2 mtr.

( Between Two Post)

S.No. Description Unit Quantity Rate (Rs.) Amount

Concrete including
1 Cum 0.179 6000.00 1071
Shuttering M-30

2 Steel Kg 22.000 65.00 1430

A Total 2501

Abstract for 40nb M.S Hand Rail for 2 mtr. ( Between Two Post )

S.No. Description Unit Quantity Rate (Rs.) Amount


M.S 40 nb c-Class
1 Kg 35.200 67.00 2358
Pipe
B Total 2358

Diff. A-B 143


Concrete Quantity for Hand Rail 2 M

S.No. Description Unit Nos. Length Width Depth Quantity

1 Hand Rail Cum 3 2.000 0.170 0.175 0.179


Name of the Project : - Four - laning of Aligarh & Kanpur section from Km.140.200 (Design Chainage 149.900) to Km.186.000 (Design chainage 195.733) [Pakage -1 from
aligarh-Bhadwas] of NH- 91 in the State of Uttar Pradesh on Hybrid Annuity Mode under Bharatmala Pariyojna.

BAR BENDING SCHEDULE

Type of Structure :- HAND RAIL CONCRETE LENGTH 2000 MM

LENGTH MM Dia wise Total Length (m) Remarks

Location
Dia Opposite Dedu. Lap Total
Bar Spacing Cut Length
S.No. Description (mm Length Bar Shape @ 2d Length @ No. of Bar no. of
Mark (mm) A B C D E F (m) 8 10 12
) (mm) (mm) 50d (mm) Bars

2000 MM

1 Main Bar 3 10 EQ 4 Nos 3 2000 0 0 2 4 12 - 24.000 -

2 Stirrups 4 8 150 2000 3 50 70 75 70 75 50 112 0 0.403 14 42 16.926 - -

Dia of TMT Bars (mm) 8 10 12


Dia Wise Total Length of TMT Bars (m) 16.926 24.000 0.000
Dia Wise Unit Weight of TMT Bars (Kg) 0.395 0.617 0.889
Dia Wise Total Weight of TMT Bars (Kg) 6.686 14.808 0.000
Dia Wise Total Weight of TMT Bars (MT) 0.007 0.015 0.000
TOTAL WEIGHT : - 0.022 MT
22.000 KG
40 nb M.S STEEL PIPE BETWEEN TWO POST

S.No. Description Unit Nos Length Unit Weight KG/M Total Weight Remarks

40 nb M.S C-
1 Class pipe for Hand Kg 4 2 4.4 35.2
Rail