Professional Documents
Culture Documents
net/publication/280133395
CITATIONS READS
3 422
2 authors:
Some of the authors of this publication are also working on these related projects:
A NUMERICAL AND ANALYTICAL STUDY ON OPTIMIZATION AND EFFICIENCY OF STRUCTURAL FORMS BY TWO-OUTRIGGER IN TALL BUILDINGS View project
All content following this page was uploaded by Saeed Reza Mohandes on 26 August 2015.
!"
"
!
-
.
!
"-
(
%
.
%
% % % $
$$ -
-
- -
iii
ACKNOWLEDGEMENT
iv
ABSTRACT
One of the most the most vital aspects of construction industry which needs
to be taken into account is sustainability development. This issue has been
categorized into different subdivisions such as thermal properties, sound insulation,
environmental impacts and flexibility. One critical element of the buildings playing a
pivotal factor in order to meet the rHVLGHQW¶VQHHGVRQWKHLQWHULRUVSDFHLVSDUWLWLRQ
wall. Although some research has been carried out on the subject of sustainability in
different aspects of partition walls such as embodied energy or thermal properties,
there has not been any research carried out exploiting BIM (building information
modeling) as a tool in order to simulate work process, calculate time and take-off
quantities pertaining to this crucial element on the interior space of the buildings.
Gaining innumerable benefits regarding the usage of BIM have been overlooked over
the past researches conducted on the field of partition walls. As a result, this research
has presented a new framework of exploiting BIM software in doing so. The main
goal of this research is to propose a new type of partition wall and its fasteners with
the aim of shortening the installation process, materials needed and enhancing the
functionality on the interior space of the buildings. The objectives of this study are:
1) To calculate time and quantity take-off pertaining to the existing partition walls
and their fasteners, 2) To propose a new partition wall with its fasteners and 3) To
examine the effectiveness of new partition wall in terms of time, material saving and
functionality. The scope of presented work is limited to the connections between the
partition walls to the exterior walls and to the columns. To achieve the mentioned
objectives, a case study has been chosen. The used methodology has comprised the
simulation of work process regarding each partition wall using Revit Architecture
and Autodesk Inventor and calculation the quantity and time required to install each
employing Naviswork Manage 2014. The results have shown that the proposed
v
partition wall would be by far more effective to be used on the interior space of the
buildings in comparison with the other results.
vi
ABSTRAK
Salah satu yang paling aspek yang paling penting dalam industri pembinaan
yang perlu diambil kira adalah pembangunan kemampanan. Isu ini telah
dikategorikan ke dalam subdivisi yang berbeza seperti sifat haba , penebatan bunyi,
kesan alam sekitar dan fleksibiliti. Salah satu unsur kritikal bangunan memainkan
faktor penting dalam usaha untuk memenuhi keperluan pemastautin itu pada ruang
dalaman adalah partition dinding. Walaupun beberapa kajian telah dijalankan ke atas
subjek kemampanan dalam aspek dinding partition seperti tenaga termaktub atau
sifat haba , tidak ada apa-apa penyelidikan yang dijalankan mengeksploitasi BIM
(bangunan pemodelan maklumat) sebagai alat untuk mensimulasikan proses kerja ,
mengira masa dan berlepas kuantiti yang berkaitan dengan elemen penting ini di
ruang dalaman bangunan. Mendapat manfaat yang begitu banyak mengenai
penggunaan BIM telah diabaikan sejak kajian lepas yang dijalankan ke atas bidang
dinding partition. Hasilnya, kertas ini telah dibentangkan satu rangka kerja baru
mengeksploitasi perisian BIM dalam berbuat demikian. Matlamat utama kertas ini
adalah untuk mencadangkan satu jenis baru partition dinding dan pengikat dengan
tujuan untuk memendekkan proses pemasangan , bahan yang diperlukan dan
meningkatkan fungsi pada ruang dalaman bangunan. Objektif kajian ini ialah: 1 )
Untuk mengira masa dan kuantiti berlepas berkaitan dengan dinding partition yang
sedia ada dan pengikat mereka, 2) Untuk mencadangkan partition dinding baru
dengan pengikat dan 3) Untuk mengkaji keberkesanan partition dinding baru dalam
dari segi masa , penjimatan bahan dan fungsi. Skop kerja yang dibentangkan adalah
terhad kepada sambungan antara dinding partition untuk dinding luar dan kepada
tiang. Bagi mencapai objektif tersebut, satu kajian kes telah dipilih . Kaedah yang
digunakan telah terdiri simulasi proses kerja mengenai setiap dinding partition
menggunakan Revit Architecture dan Autodesk Pencipta dan pengiraan kuantiti dan
masa yang diperlukan untuk memasang setiap Naviswork menggunakan Mengurus
2014. Keputusan telah menunjukkan bahawa partition dinding yang dicadangkan
vii
akan dengan jauh lebih berkesan untuk digunakan pada ruang dalaman bangunan di
perbandingan dengan orang lain.
viii
TABLE OF CONTENTS
DEDICATION iii
ACKNOWLEDGEMENT iv
ABSTRACT v
ABSTRAK vi
TABLE OF CONTENTS vii
LIST OF TABLES x
LIST OF FIGURES xi
1 INTRODUCTION 1
1.1 Introduction 1
1.2 Problem Statement 2
1.3 Aim and Objectives 2
1.4 Scope of Study 3
1.5 Expected Findings 3
2 LITERATURE REVIEW 4
2.1 Introduction 4
2.2 Industrial Building System 4
2.2.1 Definition of Industrialised Building
System (IBS) 6
2.2.2 Types of Industrial Buildings Systems 9
2.2.3 The advantages of using industrialized
building system 10
ix
2.3 Building Information Modelling 12
2.3.1 Definition 14
2.3.2 Advantages of using BIM 15
2.3.3 BIM Tools 17
2.3.4 BIM on the Planning and Preconstruction
Phase 18
2.3.5 BIM for Development of the 3D Model 18
2.3.6 BIM for Constructability Analysis and
value engineering 19
2.3.7 BIM for 4D Schedule 20
2.3.8 BIM for 5D 21
2.3.9 BIM for Preconstruction and Construction
Phases 22
2.3.10 BIM for Project Team Management 23
2.3.11 BIM in Construction Process Management 24
2.3.12 The Nature of Information 24
2.4 Joints for construction 25
2.4.1 Structural joining 25
2.4.2 Structural joints of Screws, bolts and nuts 27
2.4.3 Failure modes of mechanical joints 28
2.4.4 Effect Shear forces on joints 28
2.4.5 Loosening behavior of screw fasteners 30
2.4.6 Tensile behavior of fasteners 30
2.5 Partition and divider of buildings 31
3 METHODOLOGY 34
3.1 Introduction 34
3.2 Determination of problem statement, objectives and scope
34
3.3 Exploration of Literature 35
3.4 BIM Data Collections 35
3.5 Specific Research Methodology 39
x
4 RESULTS AND DISCUSSION 40
4.1 Introduction 40
4.2 Case Study: 40
4.3 Assessment of Existing Partition Study 47
4.3.1 Work Process of construction and
assembly 47
4.3.2 Doors and windows 63
4.3.3 The extraction of data from the work
processes 80
5 CONCLUSION 92
REFERENCES 94
xi
LIST OF TABLES
xii
LIST OF FIGURES
xiii
4.23 Installing horizontal track to the floor 55
4.24 Installing horizontal track to the ceiling 56
4.25 Installing vertical stud to the flanking wall 57
4.26 Installing the remaining vertical studs 58
4.27 Installing the gypsum wallboard to the installed vertical studs 58
4.28 &RPSOHWLRQRIGU\ZDOO¶VLQVWDOODWLRQ 59
4.29 Details of connection between gypsum wallboard and vertical
studs simulated in Autodesk Inventor (Plan and front View) 59
4.30 Front view of Drywall Screw TB 60
4.31 Perspective view of Drywall Screw TB 60
4.32 Square Tube 61
4.33 Attaching gypsum wallboard to the square tube 61
4.34 Detail of connection between square tube and horizontal
track simulated in Autodesk Inventor 62
4.35 Front view 62
4.36 Perspective view of Pan Head Screw LB 62
4.37 'RRU¶VLQVWDOODWLRQ 63
4.38 :LQGRZ¶VLQVWDOODWLRQ 63
4.39 Horizontal track 65
4.40 Installed flanking vertical stud 67
4.41 Screwed angular plate to the horizontal track and flanking
vertical stud 68
4.42 Detail of screwed angular plate using galvanized screw with
nailable plug (front and perspective view) 68
4.43 Screwing the angular plate to the installed track on the ceiling 69
4.44 False column 69
4.45 Installing the rest of false columns 70
4.46 Installing wood veneer 70
4.47 Installing the rest of wood veneers 70
4.48 Installing Square tube 71
4.49 Installing wood veneers on the square tube 71
4.50 Exterior wall 73
xiv
4.51 A component of IBS partition wall 73
4.52 A complete IBS partition wall 74
4.53 Two types of blocks used in IBS partition wall as fasteners 74
4.54 Placing the blocks inside the embedded holes of Exterior wall 74
4.55 Installed the first component of IBS partition wall 75
4.56 Installed the second component of IBS partition wall 75
4.57 A completed IBS partition wall 76
4.58 A component of IBS partition wall for corners 76
4.59 Installing the first component in the corner 77
4.60 Installed the second component in the corner 77
4.61 A completed IBS partition wall in the corner 78
4.62 Installing two interior IBS partition walls (hidden line) 78
4.63 IBS column 79
4.64 Installing IBS partition wall to IBS column 79
4.65 Specifying different identifications in Naviswork Manage for
Brick Wall 81
4.66 Specifying different identifications in Naviswork Manage for
Drywall 84
xv
CHAPTER 1
1 INTRODUCTION
1.1 Introduction
Partition walls are important building elements and have a great importance in
the overall life-cycle impacts of a building. A partition wall is a thin element built to
divide the indoor space into rooms or other compartments. Additionally, it is used to
enable more effective space organization and to improve comfort and safety.
Generally, partition walls are non-load bearing. For a loadbearing wall, strength to
vertical loads is an important factor of design, since it influences the overall structural
behavior of the building. In a partition wall, the main structural requirement is to
have the necessary strength to support a suitable surface for decoration and the
accidental impacts resulting from the occupation of the building.
1
1.2 Problem Statement
Partition walls are crucial components of the buildings as they separate and
provide distinction between internal spaces, enhance comfort, health and safety, and
provide more effective space utilization. Although some research has been carried out
on the subject of sustainability in different aspects of partition walls such as
embodied energy or thermal properties, there has not been any research carried out
exploiting BIM (building information modeling) as a tool in order to simulate work
process, calculate time and take-off quantities pertaining to this crucial element on
the interior space of the buildings. Gaining innumerable benefits regarding the usage
of BIM have been overlooked over the past researches conducted on the field of
partition walls. As a result, this paper has presented a new framework exploiting BIM
software in doing so.
2
1.4 Scope of Study
The scope of this study in order to achieve the mentioned objectives is to focus
on the connections between partition walls to exterior walls and to the columns. To
fulfill the scope of this research following works need to be carried out:
Simulating the work process of installation steps with the aim of computing
the time and materials needed more precisely regarding the existing and
proposed partition walls exploiting BIM
Relate utilization of space; in terms of flexibility to modify the interior
space, to sustainability through employing BIM tools
Assumption: Building is divided into zones of ceilings, roofs, interior and
exterior wall and the study is focused on interior walls
The chosen case study of this research is M46 which is an office building
locating at the University Technology Malaysia (Johor Bahru).This office building
has been chosen because it has numerous types of partition walls and consists of
offices and public educational spaces.
The use of existing partition walls and their fasteners are evaluated
The new type of IBS partition wall and its fasteners are discussed and
evaluated by using BIM tools in terms of time, saving of material.
3
CHAPTER 2
2 LITERATURE REVIEW
2.1 Introduction
4
can be provided to the workers since the site is clean from the mess of
construction tools, prevent the congested environment that full with too
many workers and prevent social problems among the workers [1-4].
5
2.2.1 Definition of Industrialized Building System (IBS)
6
then will be delivered to the site. As Construction Industry Development
Board (CIDB) described Industrialized Building System (IBS) as
building systems where the components are manufactured in a factory,
on or off site or can be called as prefabricated components. Then the
materials will be transported, positioned and assembled on site with less
of additional site works.
7
System (IBS). With this regard, the term building system is defined by
Warszawski [3] as a set of inter connected elements that joint together to
enable the designated performance of building. It is also characterized as
a set of interrelated elements that act together to enable designated
performance of building. In wider sense, it may include several
procedures (managerial and technological) for the production and
installation of these elements for this purpose [10].
8
organized using machine, formworks and other forms of mechanical
equipment. The components are manufactured in the factory and once
completed will be delivered to construction sites for assembly and
erection. Activities and results supported by the used of highly
developed components. The term is also defined as a new construction
method that can improve the quality and productivity of work through
the use of better construction machineries, equipment, materials, and
extensive project planning [18, 19].
9
2.2.3 The advantages of using industrialized building system
2- Cost
10
Exemption of the Construction Levy for housing developers
who utilize IBS components exceeding than 70 % [3].
No need to do rectification works because of closely checking
and controlling in factory and this will save a lot of money [3].
3- Time
4- Safety
11
Reduction of construction material at site [20].
Reduction of waste materials at site duo to casting in factory
[21].
Minimizing the use of formworks and props at site because of
casting in factory [3].
6- Social benefits:
12
to maintain its consistency with the design. Because this manual process
was time consuming, the specialist consultants could not respond to the
timeframe of design decision-making. Assessments within the design
process were intuitively made from experience and most computational
analyses were done near the end of design to validate already made
decisions [20].
13
the current model, or to restart a new one. Generally it will take a
fraction of the time that it took to get to the same point of development
because all the thinking and planning has now been done and the
modeling has been well planned and can be executed efficiently. The
result will be a new model that will no longer slow down progress or be
inaccurate in the way it represents the project [23].
2.3.1 Definition
14
only provides predictable information with regard to quantity, cost,
schedules, and materials but also makes it possible to perform data
analysis depending on structure and environment [24].
15
project requirements, and to assist in describing the project in an
efficient manner [24].
16
7. The best routing for ductwork, pipes, wires, lights,
sprinklers, and cables can be reviewed.
8. Logistics of the site with the location of cranes and hoists
can be analyzed.
9. Lift schedules for the placement of steel, concrete, and large
mechanical and electrical equipment can be determined.
10.The development of schedules and the associated logic will
be enhanced.
11.Potential safety problems can be assessed.
12.Can evaluate alternatives in more realistic terms.
13.Can coordinate trades prior to performing the actual work.
1. Autodesk Revit
2. ArchiCAD from Graphicisoft
3. Bently Architecture
4. Digital Project from Gehry Technologies LLC(book)
5. Autodesk Nawiswork(Manage,Simulate and Freedom)
17
2.3.4 BIM on the Planning and Preconstruction Phase
18
improved 3D enabled visualization is also very helpful for the designers
with respect to progress in their own work. Almost all ideas for the
project will be reflected in the model in one way or another. At this stage
the project is still fairly schematic, and therefore it is generally not
difficult to represent the ideas of the project team members in the model
[24].
19
2.3.7 BIM for 4D Schedule
20
schedule, which shows that conventional methods cannot be avoided. In
the meantime [27] implemented a 4D simulation system that
automatically connects geometry information based on data stored in a
building model with time schedules to plan a construction sequence.
However, the system could not break from the existing frame, which is
merely a simple connection between geometry information and the
schedule [28] implemented the functions necessary for managing 3D
geometry models, schedules, and dynamic resources on the 4D
information system platform called Graphics for Construction and Site
Utilization. However, this platform did not suggest results for developing
an actual system or applications; it simply provided conceptual
definitions for important factors to be included in the 4D simulation.
21
and an external database that contains the actual cost information. The
quantities in the model are combined with the linked cost data so that a
project cost estimate is generated. The database is editable and can be
FXVWRPL]HG WR WKH XVHUV¶ FKRLFH 0DQ\ FRPSDQLHV ZLOO EDVH WKHLU FRVW
estimates on historical data and can use already familiar data from a
proprietary database. It is also possible to use commercially available
cost data [24].
22
2.3.10 BIM for Project Team Management
23
2.3.11 BIM in Construction Process Management
This pertains to all information that is part of, or connected to, the
components as well as the physical information inherent in the model
itself (i.e., size, location, etc.). It is important that all information
required making an actual analysis be available from the BIM. The basic
informational questions are as follows:
24
x Will the information simply be available (linked to) or also
require a certain amount of processing (i.e., scheduling
information, productivity rates, etc.)?
x What is the required format for the information?
x Will the information need to be exported (quantity takeoff,
cost estimates, etc.)?
x Is the information imported (database link) or created in the
model components (parametric objects)?
x What information will be required by the team to perform all
its tasks in a timely manner? [24].
25
area of study for phenomenological understanding, design and analysis
[29].
26
2.4.2 Structural joints of Screws, bolts and nuts
27
be analyzed, the behavior of each of the involved component must be
known. This analysis should be performed with material properties that
are obtained at a strain-rate level that is representative for the impact
situation [31].
28
loosening. This paper studies failure of threaded fasteners by vibration
induced loosening caused due to dynamic shear loads. Such failures can
be avoided by proper joint design using guidelines based on the
understanding of loosening caused by dynamic loads. The work
presented in this paper is a step towards development of such design
guidelines [32].
29
2.4.5 Loosening behavior of screw fasteners
30
distribution, and the developed theory has gained general acceptance and
shown good agreement with experiments.
Tensile stress increases with increase in test velocity, and that bolt
thread stripping leads to a completely different nominal stress-elongation
curve than what is found for bolt breaking. The most striking difference
is the reduction of the ductility of the threaded assembly. Several
parameters have an influence on the failure mode, such as the length of
the thread engagement, the grip length and the strain-rate. The threaded
assembly tests showed that the number of threads in the grip length
changed the failure mode. A short grip length reduced the thread shear
area because diffuse necking occurred in the thread engagement length.
31
hollow or solid; they may extend from floor to ceiling or only partway;
and they may serve additionally as cabinets or closets or as a
concealment for piping and electrical conduit.
32
gypsum board. Hollow masonry unit partitions can be internally
reinforced to provide the required lateral support in lieu of cross walls or
projecting pilasters. A continuous vertical core at the required interval is
reinforced with deformed steel bars and then grouted solid to form an in-
wall column. Cavity walls can be similarly reinforced and also facilitate
the placement of conduit and piping for utility distribution within a
building. The continuous cavity easily accommodates horizontal runs.
33
CHAPTER 3
3 METHODOLOGY
3.1 Introduction
34
After the preliminary review, some specific scopes of the study
has been determined by considering various aspects such as achievability
of the study, the time constraints, availability of the research materials
and the specific scopes that have been discussed previously in the first
chapter.
Study and explore all the fasteners and partition walls which
can be used in construction
Study and examine BIM(building information modeling) and
its relevant tools such as Revit Architecture 2011, Nawiswork
Manage 2014 and Autodesk Inventor 2011
Study related books, journals and thesis and etc for gathering
information regarding work process of partition walls
Data collection is the most critical part of the study since the
accuracy of the data will determine the success or failure of the research.
35
The purpose of data preparation is to present the data, to have a feel of
the data, and to get the data correct and ready for analysis. In this step of
this research work process of existing fasteners in different partition
walls will be discussed in details.
36
employing Revit Architecture including all plan, elevation and section
views and components such as exterior and interior walls, floors,
ceilings, columns, roofs, windows, doors and so forth. Revit software has
the ability to categorize different components of the buildings into sub-
categories in accordance with their identifications. Therefore, it has
divided all the interior partition walls into smaller parts with regards to
their lengths, widths and thicknesses. Then, in order to compute
quantities and time needed, the modeled cast study has been exported to
Naviswork Manage 2014. Autodesk Navisworks is a powerful tool for
construction managers using BIM. Navisworks is collaboration software
that allows a design team to share, combine, review and correct a BIM
model and 3D files using a 3D viewer. The series of Navisworks
software including manage, simulate and freedom are quite beneficial to
be used for running a schedule animation, sequencing animation, and
clash detection. When it comes to computing the duration of activities
involved in a project, time liner is very useful in providing a simulation
of the construction sequence. By either importing a construction
schedule from an outside software or building a new schedule in Time
Liner, the 3D model components can be linked to a schedule task, and
thus can be seen appearing or disappearing in timed sequence. On top of
all those aforementioned advantages of exploiting Navisworks, a new
feature has been added to the version 2014 of these series software
named as quantity take-off. The new methods for generating quantities
from and alongside a model provide the opportunity to go from highly
detailed models to virtually no details and still enable proper quantity
take-off. This flexibility provides powerful quantification tools to benefit
37
the pre-construction process when using Building Information Models. It
is done in 3 different ways as below:
38
CHAPTER 4
4.1 Introduction
40
Table 4.1: Different Levels in the chosen case study
%DVH/HYHO¶V+HLJKW)URP 7RS/HYHO¶V+HLJKW)URP
Levels
GURXQG¶V6XUIDFHPP *URXQG¶V6XUIDFHPP
Level 1 -2500 +2500
Level 1-1 *URXQG¶V6XUIDFH +5000
Level 2 +2500 +7500
Level 2-1 +5000 +1000
Level 3 +7500 +12500
Level 3-1 +1000 +15000
Level 4 +12500 +17500
41
Figure 4.2 Perspective View
42
Figure 4.4 Level 1 Plan
43
Figure 4.6 Level 2 Plan
44
Figure 4.8 Level 3 Plan
45
Figure 4.10 Level 4 Plan
46
Figure 4.13 West Elevation
The first type of wall partition is constructed from clay bricks with
dimensions 215mm (length) by 102.5mm (height) by 65mm (depth),
with 6 voids in two rows and finally coated with a 25 mm thick Portland
cement plaster on both sides. As a result, the total thickness of wall
would be 150 mm. Both surfaces are finished with latex or water based
47
paint layer as the final coating. Every third horizontal course and
intersection points of two interior walls are reinforced with one steel bar.
The bricks are held together using cement lime mortar (1part cement: 1
part lime: 6 parts sand). Lime mortars exhibit greater elasticity than pure
cement mortars, allowing the take up of moisture movement in the
bricks. The different steps of constructing the interior brick wall have
been explained and shown (using Revit Architecture) as follows:
Step 1: Locate face of the walls on the floor. Snap a chalk line.
Step 2: The two ends of wall are built first using a spirit level for
checking the balance measure from the outer edge of the brick at
one end to the outer edge of the brick at the other end to get the
length of your wall as can be seen in Figure 4.14.
Step 3: Spread mortar bed on the surface and shaped to accept the
bricks.
Step 4: Laying the bricks one after another on the spread mortar
using taut string line as a guide to line and level .The level needs
to be put against the face of the bricks to make sure that they are
straight. The end of the brick to be laid is buttered with mortar and
then shoved against the preceding brick, squeezing the mortar to a
width of 20mm. The brick is tapped down to level with the heel of
the trowel, any surplus mortar extruded from the bed or the
perpend (vertical joint) is scraped off with the trowel, and then the
process needs to be repeated until the end of wall (Fig 4.15). At
the completion of each course, the guide line is moved up to the
next course.
48
Step 5: In the second course half bricks first need to be laid on the
mortar at both ends, followed by the other complete bricks as
illustrated in Figure 4.16. As a result, the vertical joints of brick
wall are not along the same path leading strong bond between
different brick layers.
49
Figure 4.16 Laying the second course
50
Figure 4.17 Plan view of embedded rebars in the brick layers
51
Figure 4.19 Position of rebars after precasting the column concrete
52
Step8: Ultimately, the surface of brick wall is painted with the
desired colors.
53
4.3.1.2 Dry Wall
54
Figure 4.23 Installing horizontal track to the floor
Step 4: To plumb upper and lower track, you can use either
a laser level, a plumb bob, or two water levels:
55
levels are plumb. Mark off your plump line on the
floor or ceiling.
56
Figure 4.25 Installing vertical stud to the flanking wall
57
Figure 4.26 Installing the remaining vertical studs
Figure 4.27 Installing the gypsum wallboard to the installed vertical studs
58
Figure 4.31 Perspective view of
Screw TB
60
Figure 4.32 Square Tube
61
Figure 4.34 Detail of connection between square tube and horizontal track
simulated in Autodesk Inventor
62
4.3.2 Doors and windows
In order to install door and window in dry wall, additional vertical and
horizontal studs need to be installed as illustrated in Figure 4.37 and 4.38.
63
4.3.2.1 Wood Partition Wall
There are slight differences between drywall and wood partition wall in terms
of installations process and components. For instance, flanking vertical stud and false
columns are used instead of simple vertical stud; however, there solely need to be
used for installing interior doors and windows as well as in drywall. In this type of
wall partition, angular plate is used to join tightly the flanking vertical stud to
flanking walls and track to ceiling or floor. This type of wall as well as drywall is
installed in two ways:
Step 1: Using a chalk line in order to outline where the track needs to be
installed.
Step 3: Screwing the track to the floor (see Figure 4.39 and 4.40).
Step 4: Using either laser level or a plumb bob or two water levels in
order to plumb the track on the ceiling.
64
Step 6: Screwing the flanking vertical stud to its intersection points with
installed tracks on the floor and ceiling using angular plate and
galvanized screw with nailable plug as shown in Fig 4.42-4.46.
Step 8: Attach the false column to the installed track on the floor and
ceiling using angular plates with the same fasteners used for joining the
vertical studs to the flanking walls or columns (see Figure 4.47 and
4.48). Generally, the distance between false columns is approximately
1000mm from center to center.
Step 9: Joining the wood veneer to the false column less 50mm gap the
WRSDQGWKHERWWRPRIWKHSDUWLWLRQLQWHUPVRIDHVWKHWLFV¶SRLQWRIYLHZ
using drywall screw TB as shown in Figure 4.49 and 4.50.
65
Figure 4.40 Installed horizontal track on the floor
66
Figure 4.42 Flanking vertical stud
67
Figure 4.41 Screwed angular plate to the horizontal track and flanking vertical stud
Figure 4.42 Detail of screwed angular plate using galvanized screw with nailable plug (front and
perspective view)
68
Figure 4.43 Screwing the angular plate to the installed track on the ceiling
69
Figure 4.45 Installing the rest of false columns
70
ii. $V ZHOO DV LQ WKH VHFRQG PHWKRG RI GU\ZDOO¶V LQVWDOODWLRQ 6TXDUH WXEH LV
used in places where the possibility of installing interior walls up to the
main ceiling is impracticable, Figure 4.46 and 4-49. For instance, one
condition would be innumerable existence of different mechanical
installations under the main ceiling. In other words, the walls are installed
up to the false ceiling. The other process of installations is as same as
mentioned in the method of this part.
71
4.3.2.2 IBS Wall Partition
In this section a new type of wall partition with its fasteners has been proposed.
These types of wall partitions are well-suited to be used in the projects constructed
with the technology of Industrialized Building System (IBS). In order to join the
interior wall to any components of IBS tightly, some holes inside them (with the
exact size of mentioned fasteners) need to be designed while prefabricating exterior
walls or columns as can be seen in Figure 4.50. Each type of this proposed wall
partition consists of three precast concrete panels including precast concrete blocks
considered as fasteners (see Figure 4.51 and 4.52 ).Required numbers of mentioned
panels are quite variable with regards to the length and height of interior space of
which needs to be divided. For instance, type A of wall partitions in this case study
have 1600mm length by 3500 height, so that three panels with the size of 1600mm by
1165 are required, whereas type H need twelve to be installed. It is recommended
that each 5 meters of interior space would be divided by three panels placing on top
of one another. Furthermore, two blocks with the size of 200*100*50 and
400*100*50 are required to join the interior wall to exterior wall or column (see
Figure 4.53).There is no necessity to use mortar to join the interior wall to other
components. The different steps of installing this type of wall partition have been
mentioned as follow [36]:
Step 1: Locating face of the walls on the surface using chalk line with
considering the places of the embedded holes inside the exterior wall or
column.
72
Step 3: Lift precast concrete panel and place it on the located face of
wall using crane, followed by other panels in order to make a complete
partition wall. The above-mentioned steps (from 1 to 3) have been
shown in Figure 4.55-4.62 including the corner connection between two
interior walls. The connection between interior wall and precast concrete
column has been illustrated in Figure 4.63 and 4.64.
Step 4: Using a spirit level for checking the balance of installed panels.
73
Figure 4.52 A complete IBS partition wall
Figure 4.53 Two types of blocks used in IBS partition wall as fasteners
Figure 4.54 Placing the blocks inside the embedded holes of Exterior wall
74
Figure 4.55 Installed the first component of IBS partition wall
75
Figure 4.57 A completed IBS partition wall
76
Figure 4.59 Installing the first component in the corner
77
Figure 4.61 A completed IBS partition wall in the corner
Figure 4.62 Installing two interior IBS partition walls (hidden line)
78
Figure 4.63 IBS column
79
4.3.3 The extraction of data from the work processes
As regards the different plans drawn in Revit Architecture 2011, eight types of
interior walls have been categorized in accordance with their lengths, heights,
thicknesses and numbers for exporting to Nawiswork Manage 2014 as can be seen in
Table 4.2.
Table 4.2: Types of Interior Walls for taking-off and computing time
Thickness
Type of Wall Length (mm) Height (mm) Numbers
(mm)
A 1600 3500 150 40
B 2750 3500 150 24
C 3500 3500 150 146
D 4500 3500 150 66
E 5250 3500 150 55
F 7000 3500 150 17
G 10000 3500 150 9
H 20000 3500 150 2
80
Brick Wall
After exporting the Revit file to Naviswork Manage, three different materials
used in constructing interior brick walls including brick, rebar and mortar have been
specified pertaining to their lengths in details for each type of wall. For instance,
different specifications identified in Naviswork Manage for three different walls
(Type A) in terms of mortar volume have been mentioned as follow (Figure 4.65):
Figure 4.65 Specifying different identifications in Naviswork Manage for Brick Wall
81
The summary of the materials quantity take-off for the total interior brick walls
in the Naviswork Manage 2014 have been shown on the following:
In order to take-off materials used very precisely, areas of windows and doors
should be deducted from the total numbers of brick, mortar and painting, table 4.4
and 4.5. Consequently, new quantity take-off has been shown in table 4.6.
82
Table 4.5: Quantity Take-Off from Interior Doors
Drywall
As well as quantity take-off for brick wall, Naviswork Manage 2014 has
calculated total amount of used components for installing drywall according to what
have been identified for different types of walls. For instance, specifications of
drywall screw TB regarding the three different interior walls (type A) have been
shown in Figure 4.66. Quantity take-off of drywall also can be seen in table 4.7.
Additionally, the take-off pertaining to interior windows and doors have been shown
in table 4.8 and 4.9. On the one hand, numbers of track, vertical stud and drywall
screw used in both interior windows and doors should be added to the first calculated
quantity take-off. On the other hand, the numbers of wallboard used and area of
83
interior doors and windows installed in drywall should be deducted. As a result, total
quantity take-off of dry wall can be observed in table 4.10.
84
Table 4.8: Quantity Take-Off from Interior Windows
85
Table 4.10: Total Quantity Take-Off
86
Table 4.11: Total Quantity Take-Off
87
Table 4.12: Total Quantity Take-Off
Table 4.13: Categories of Interior Walls in each Level for Time Calculation
88
Activity duration is computed by dividing the quantity of work involved with
the number of resources used and with the corresponding production rate of that
activity. It is assumed that three skilled labors working 8 hours daily have been
involved in order to construct or install different partition wall in this case study. The
start date for constructing each type of partition wall is assumed to be on the first of
January 2014. One day has been considered as day-off in doing so (every
Saturdays).As well as for quantity take-off, Revit file has been exported to
Naviswork Manage 2014 in order to compute the time pertaining to each type of wall
partition. The duration for installing each type of wall partition in each level has been
specified separately with regards to different steps of installation productivity rate
and quantity of work pertaining to each one. Table 4.14 has shown the duration of all
partition walls in each level and in total:
89
Table 4.14: Time Computation in each Level and In Total for Different Partition Walls
In this research, the assessment of the effectiveness of partition walls will come
from their comparisons with one another in terms of quantity and time needed to
install each and sustainability.
According to the different materials used in the all mentioned partition walls, it
is practicable to conclude that the proposed partition wall in this research is by far
more effective to be employed in comparison with others (compare Table 4.12 with
Tables 4.6, 4.10 and 4.11).
As regards the time required for installing or constructing each type of partition
wall, it can clearly be observed that the proposed partition wall needs less time in
doing so (see Table 4.14).
90
any desired directions without considering the mandatory functional needs for the
existing partition wall.
91
CHAPTER 5
5 CONCLUSION
92
brick wall would be contemplated as by far the worst one in terms of
both materials and time needed to be built in comparison with others.
93
REFERENCES
94
the 6th Asia-Pacific Structural Engineering and Construction Conference
(APSEC 2006): Kuala Lumpur Malaysia, 2006.
9. CIB report. New perspective in industrialization in construction a state of the
art report. CIB Publication 329, 2010.
10. Sarja. A. Open and industrialized building. International Council for Building
Research: E & FN Spoon, London, 1998.
11. Abdullah. MR and Egbu. C. IBS in Malaysia: Issues for research in a
changing financial and property market. BuHu 9th International Postgraduate
Research Conference (IPGRC): Salford, United Kingdom, 15-25, 2009.
12. Hassim. S, Jaafar. MS and Sazali. AH. The contractor perception towers
industrialized building system risk in construction projects in Malaysia.
American Journal of Applied Sciences, 6(5): 937-942, 2009.
13. Chung. LP. Implementation strategy for Industrialized Building System (IBS)
[dissertation]. Universiti Teknologi Malaysia: Johor Bharu, Malaysia, 1-126,
2006.
14. Hamid. ZA, Kamar. KAM, Zain. MZM, Ghani. MK and Rahim. AHA.
Industrialized Building System (IBS) in Malaysia: the current state and R&D
initiatives. Malaysian Construction Research Journal (MCRJ). 2(1): 1-11,
2008.
15. Hong. OC. Analysis of IBS [dissertation]. School Complex: Universiti
Teknologi Malaysia, Johor Bharu, Malaysia, 1-86, 2006.
16. Din, H., "Industrialised Building and Its Application in Malaysia",
Proceeding on Seminar on Prefabrication Building Construction, Kuala
Lumpur, 1984.
17. Noraini Bint Bahri, Construction Technology and Innovation Development
Sector, - Construction Industry Development Board (CIDB), Kuala Lumpur,
Malaysia, Personal communication, January 2009
18. PENG, C.S., "The scenario of industrialised building systems in Malaysia".
Proceedings of a UNESCO/FEISEAP Regional workshop, UPM, Serdang,
1986.
19. Wisam Mohamed S. Masod "Simulation of allocation activities of logistic for
semi precast concrete construction: case study", UTM, Johor, 2007
95
20. V. Bazjanac, Building energy performance simulation as part of interoperable
software environments, Build. Environ. 39 (2004) 879±883.
21. H. M. SHIN, H. M. LEE, S. J. OH and J. H. CHEN, 2011. The Twelfth East
Asia-Pacific Conference on Structural Engineering and Construction
22. S. Fox, Jiri Hietanen, Interorganizational use of building information models:
potential for automational, informational and transformational effects,
Construction Management and Economics 25 (2007) 289±296.
23. Willem Kymmell (2008).Building Information Modeling: planning and
managing construction projects with 4D CAD and simulations. New York,
Chicago, San Francisco, Lisbon, London, Madrid, Mexico City, Milan, New
Delhi, San Juan, Seoul, Singapore, Sydney, Toronto: The McGraw-Hill
Companies, Inc.
24. J. Choi, I. Kim, C. Jo, J. Choi, Application status of domestic architectural
industry of open BIM and development direction, Transactions of the Society
of CAD/CAM Engineers 14 (6) (2009) 355±363.
25. John Eschemuller and Richard Lambeck (2009).Urban Construction Project
Management. New York, Chicago, San Francisco, Lisbon, London, Madrid,
Mexico City, Milan, New Delhi, San Juan, Seoul, Singapore, Sydney,
Toronto: The McGraw-Hill Companies, Inc.
26. J. Tulke, M. Nour, K. Beucke, A dynamic framework for construction
scheduling based on BIM using IFC, in: Proceedings of the 17th IABSE
Congress, Chicago, USA, 2008.
27. J. Tulke, J. Hanff, 4D construction sequence planning ± new process and data
model, in: Proceedings of the CIBW78 24th International Conference on
Information Technology in Construction, Maribor, Slovenia, (2007), pp. 79±
84.
28. K.W. Chau, M. Anson, J.P. Zhang, 4D dynamic construction management
and visualization software: 1, Development, Automation in Construction 14
(4) (2005) 512±524.
29. M. L. Blosser, Thermal-stress-free fasteners for joining orthotropic materials.
AIAA Jnl 27, 472478 (1989).
96
30. N. Sase, K. Nishioka, H. Fujii, Analysis of screw fasteners loosening and
development of evaluation method, Trans. Jpn. Soc. Mech. Eng. 62 (596)
(1996) 1527±1532
31. H. Fransplass a,b,n, M.Langseth b, O.S.Hopperstad b. International Journal of
Mechanical Sciences 53 (2011) 946±957
32. Han L, Chen YK, Chrysanthou A, O_Sullivan JM. Self-pierce riveting ± a
new way for joining structures. ASME 2002; PVP-vol. 446(2):123±7.
33. Kasei S, Matsuoka H. Considerations of thread loosening by transverse
impacts. ASME Pressure Vessels and Piping Division (Publication) PVP
1998;367:117±23.
34. Den Hartod JP. The mechanics of plate rotors for turbo-generators, Trans
ASME, Paper no. APM 51±1, 1±10; 1929.
35. Jonathan T. Ricketts Building Design and Construction Handbook Sixth
Edition. New York, San Francisco, Washington, D.C., Auckland, Bogotá,
Caracas, Lisbon, London, Madrid, Mexico City, Milan, Montreal, New Delhi,
San Juan, Singapore, Sydney, Tokyo, Toronto: The McGraw-Hill Companies,
Inc, 2001.
36. 0DUVRQR$.%0DNKWDU$0%DQG0DVLQH%0'7$3´%XLOGLQJ
$VVHPEHO\ 6\VWHP´8QLYHUVLWL 7HNQRORJL 0DOD\VLD 6NXGDL -RKRU
Darul Tazim (MY).International Application Number: PCT/MY2011/000182.
97
View publication stats